Beruflich Dokumente
Kultur Dokumente
CONTINGENCY PLANNING
Contents Page
Introduction .................................................................................................... 2
1 CONTINGENCY PLANNING........................................................................... 2
1.1 Contingency Guidelines ....................................................................... 3
1.1.1 Workstring Integrity ............................................................................. 3
1.1.2 Stuck Workstring ................................................................................. 3
1.1.3 Mechanically Damaged Workstring ...................................................... 5
1.1.4 Pressure Control Equipment ................................................................ 5
1.1.5 Coiled Tubing Equipment ..................................................................... 6
1.2 Operational .......................................................................................... 6
1.3 Determining the Stuck Point ................................................................ 6
1.4 Cutting the Coiled Tubing at Surface .................................................... 6
1.5 Preparation for Cutting Tubing Downhole .............................................. 6
1.5.1 Explosive Cutters ................................................................................ 9
1.5.2 Chemical Cutters ................................................................................. 9
1.6 Coiled Tubing Retrieval ........................................................................ 9
1.7 Emergency Procedures ..................................................................... 10
1.7.1 BOP Emergency Operation ............................................................... 10
1.7.2 Power Pack Unit Failure ..................................................................... 10
1.7.3 Stripper Leakage ............................................................................... 10
1.7.4 Stuck Coiled Tubing ........................................................................... 11
1.7.5 Collapsed Coiled Tubing ..................................................................... 11
1.7.6 Surface Treating Line Leak ................................................................ 12
1.7.7 Injector Chain Slippage...................................................................... 12
1.7.8 Reel Swivel Leak ............................................................................... 12
1.7.9 Pinhole at Surface ............................................................................. 12
1.7.10 CT Rupture at Surface ....................................................................... 13
1.7.11 Leaking Riser and/or Crossover Between BOPs and Wellhead .......... 14
Page 1 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
Well Security
Personnel Safety
Equipment and Tools
Figure 1.
Page 2 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
personnel safety. Such responses are enacted as a result Parted Tubing at Surface
of detailed training, familiarity with equipment and ex-
ecuted with the knowledge and awareness of the wellbore There are two major concerns associated with the workstring
and operational conditions. parting on the surface:
In each of the above, consideration must be given to three • Well security and the presence of a tube extending
key areas of responsibility: through the wellhead
• Well security • The free end(s) of the tubing, which react to the workstring
internal pressure
• Personnel safety
Parted Tubing in the Wellbore
• Equipment, tools and the intended operation
A workstring which has parted in the wellbore will generally
As a supplement to any contingency plans, the source and be indicated by a sudden change in the weight indicator
availability of any special equipment or services should be (weight loss) and/or a variation in circulating pressure.
noted (e.g. chemical cutting services). Attempting to tag a known restriction may confirm that the
tubing has parted, if the apparent depth is greater than
1.1 Contingency Guidelines previously noted.
The contingency guidelines are categorized as follows. In some cases the first indication that the workstring has
parted will be the release of well fluids as the tubing stub is
• Workstring integrity pulled through the stripper. In this event, closing the blind
rams will regain control of the well.
• Stuck or damaged workstring
Plugged Tubing
• Pressure control equipment
Most CT applications require fluids to be circulated, either
• Coiled tubing equipment as part of the treatment or to maintain well conditions
suitable for continuing the operation (e.g. to prevent tubing
• Operational collapse).
Fatigue tracking and reel history recording significantly There are many ways by which a workstring can become
reduces the number of workstring failures and leaks. stuck. Selection of the appropriate action or treatment to
However, fatigue, corrosion and mechanical damage can resolve the condition depends on several factors. The
result in tubing leaks of varying severity. Regardless of the following points should be considered:
cause, workstring leaks are unacceptable, and must result
in the suspension of the operation pending repair or replace- • Wellbore geometry
ment of the workstring.
• CT toolstring geometry
Leak at Surface
• Presence of fines or small solids (circulatable) in wellbore
A leak in the tubing string indicates a significantly weak- or treatment fluids
ened area which may fail completely following further
cycling. Action taken to secure the well and recover the • Presence of junk or large solids
workstring should be made while attempting to minimize
further damage or fatigue to the string at the leak point. • Characteristics of treatment, produced or wellbore fluids
Page 3 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
Page 4 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
• Circulating a dense fluid into the annulus while displacing • Intended application and anticipated forces
the tubing string to nitrogen increases buoyancy effects.
• Availability of a substitute reel
If the string remains stuck, the well should be killed and the
tubing severed above the stuck point. 1.1.4 Pressure Control Equipment
1.1.3 Mechanically Damaged Workstring Pressure control equipment is typically regulated by local
or national authorities. Should the integrity or efficiency of
Mechanical damage to the workstring is of concern for the equipment be in doubt, the intended operation must be
several reasons: suspended and the well secured until all pressure control
equipment requirements are met.
• The pressure capacity of the workstring may be weakened
to the point of failure. The equipment configuration may allow several options to
be considered in overcoming malfunctions or failures.
• The tensile capacity of the workstring almost certainly will However, it is generally required that two barriers against
be weakened. well fluids and pressure be in place at all times. The priority
in contingency planning or emergency procedures must be
• The efficiency of pressure control equipment can be to maintain or regain the required level of protection before
compromised (e.g. stripper efficiency). proceeding with the operation.
• If severe, distorted tubing will not pass through pressure Stripper Packer Failure
control equipment bushings.
Gross leaks at the stripper packer are easily identifiable
• Even small damaged areas can lead to unpredictable and cause obvious safety and environmental hazards.
failures due to the effects of localized stress. Less severe leaks can be more difficult to detect, espe-
cially if the injector head is poorly lit or some distance from
Collapsed Tubing the control cabin. However, such leaks can still pose a
significant hazard and should be rectified as soon as
Tubing collapse typically occurs near the wellhead where possible.
the axial tensile force is greatest, or at the bottomhole end
where the applied pressure is greatest. Leak in Riser/Lubricator Above BOP
A collapsed tubing string can be indicated by an increase Leaks in the riser or lubricator section above the BOP are
in circulating pressure, severe leakage of wellbore fluids often caused by an unstable equipment rig-up which can
past the stripper, or an overpull caused by the distorted result in high bending moments being exerted on connec-
tubing being forced through the stripper bushing. tions or flanges. In the event of a leak, the stability of the
equipment rig-up must be checked and improved as neces-
Damaged Tubing at Surface sary.
Kinked or damaged tubing will typically be identified by the Leak in Riser/Lubricator Below BOP
TIM as it is being spooled from the reel. A close inspection
must then be made to determine the extent of damage Leaks in the riser or lubricator below the BOP are of special
before the tubing is run through the injector head. Appropri- concern since they cannot be controlled by the primary or
ate action can then be determined following consideration secondary well control equipment. Where fitted, shear/seal
of the following points: BOPs can be activated to regain control the well. However,
the workstring and/or toolstring below the shear/seal will be
• Extent of damage parted.
• Location of damage
Page 5 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
Only items of equipment which can directly jeopardize well 1.3 Determining the Stuck Point
security are included in this section. Additional contin-
gency plans should be prepared for special or unusual When attempting to free a stuck workstring it is necessary
equipment configurations, as required. to determine as accurately as possible the point at which
the workstring is held. The completion, or well geometry,
Loss of Power or Control data are generally good indicators of potential stuck points.
However, if possible, a stretch test/calculation should be
Before repairing or replacing the power unit, the following conducted to confirm/determine the stuck point.
steps should be taken:
The worksheets shown in Figures 2 and 3 are intended to
• Close the slip rams and the pipe rams. Close the manual help record and calculate the data required to determine the
locks on both sets of rams in case of hydraulic leakage. CT stuck point. The accuracy of this technique is greatly
dependent on the accuracy of the information input. There-
• If applicable, apply the reel brake. fore, it is essential that accurate information is gathered on
tapered string dimensions, etc., before applying the calcu-
• Maintain circulation as required (e.g. to prevent tubing lation.
collapse or the settling of wellbore solids).
1.4 Cutting the Coiled Tubing at Surface
Reel Swivel Leak
Before the CT is cut at the surface, the well must be killed.
In the event of a reel swivel leak, a rapid assessment of the If possible, this should be conducted by circulating through
conditions may be necessary. For example, when circulat- the CT. This will maintain a kill-weight column of fluid inside
ing fill material from the wellbore, interrupted or reduced and outside the CT string.
circulation may result in sticking the workstring. In addition,
the nature of the fluid inside the workstring may determine If circulation is not possible, bullhead the kill fluid down the
necessary action (it is undesirable to stop circulation with annulus. In this event, account must be taken of the
cement or acid in the workstring, but it is extremely injection pressure limits imposed by the well tubulars and
hazardous to sustain a high-pressure leak of corrosive or equipment, and the risk of collapsing the CT.
flammable fluid).
The pressure control equipment shown in Figure 4 provides
1.2 Operational a means of securing and circulating through the CT after the
string has been cut downhole.
The following list of wellbore or treatment conditions can be
considered as foreseeable in certain circumstances. 1.5 Preparation for Cutting Tubing Downhole
• Circulating Applications: When cutting a CT work string, the well must be killed and
- Lost circulation/returns flow checked. To ensure that a complete cut is made, the
- Well/formation kick cutter (explosive or chemical) should be centralized with
- Interruption to fluid supply the correct standoff from the tubing to be cut. A complete
- Insufficient fluid supply (rate or volume) tubing string/well schematic must be made available for the
- Treatment fluid out of specified limits cutting technician.
- Unable to penetrate/RIH
Page 6 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
NONTAPERED STRING
AE l
Length to Stuck Point L=
12 F
2
Cross-Sectional Area.....................(in. ) x 29,000,000 x Stretch......................(in.)
= Length to Stuck Point = .......................(ft)
12 x ( Applied Load)....................(lb)
2 2
A – Cross-Sectional Area = (OD - ID ) F – Applied Load (at the time the CT stretch was measured at surface)
4
l – Measured Stretch E – Constant for Young's Modulus of Elasticity (29,000,000)
TAPERED STRING
2. Using the calculation form overleaf, determine the taper section in which the stuck point is located. Starting with the top section,
calculate and add the stretch induced in each taper section until the sum is greater or equal to the actual measured stretch.
3. Determine the location of the stuck point in the last taper section by applying the following formula. The value for l (Stretch)
is obtained by subtracting the sum of the free taper sections calculated stretch from the measured stretch.
AE l
Length to Stuck Point L=
12 F
2
Cross-Sectional Area.....................(in. ) x 29,000,000 x Stretch......................(in.)
= Length to Stuck Point = .......................(ft)
12 x ( Applied Load)....................(lb)
2 2
A – Cross-Sectional Area = (OD - ID ) F – Applied Load (at the time the CT stretch was measured at surface)
4
l – Stretch E – Constant for Young's Modulus of Elasticity (29,000,000)
4. Add this length to the lengths of the free taper sections. Taper Section No. 1 Length .......................(ft)
Page 7 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
Weld Location.................(ft)
12 F L
Tubing Stretch in Taper Section No. 1 l=
AE
Wall Thickness................(in.)
Weld Location.................(ft)
12 F L
Tubing Stretch in Taper Section No. 2 l=
AE
Wall Thickness................(in.)
Weld Location.................(ft) 12 F L
Tubing Stretch in Taper Section No. 3 l=
AE
Wall Thickness................(in.)
2
12 x ( Applied Load)....................(lb) x Taper Section Length .............................(ft)
Cross-Sectional Area (A)...................(in. ) 2
2 2
(OD - ID ) Cross-Sectional Area.....................(in. ) x 29,000,000
A=
4
Weld Location.................(ft)
12 F L
Tubing Stretch in Taper Section No. 4 l=
AE
Wall Thickness................(in.)
Weld Location.................(ft)
12 F L
Tubing Stretch in Taper Section No. 5 l=
AE
Wall Thickness................(in.)
2
12 x ( Applied Load)....................(lb) x Taper Section Length .............................(ft)
Cross-Sectional Area (A)...................(in. ) 2
2 2
A= (OD - ID ) Cross-Sectional Area.....................(in. ) x 29,000,000
4
l – Stretch F – Applied Load (At the time the CT stretch was measured at surface.
Page 8 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
Pump-in connection
Note: Explosive and chemical cutting tools must only be The chemical cutter head should be sized to allow passage
assembled and prepared by experienced and qualified of the coiled tubing string, but with minimum standoff from
personnel. it. Factors to be considered include the presence of weld
bead (if applicable) and the possible ovality of the tubing.
1.5.1 Explosive Cutters
1.6 Coiled Tubing Retrieval
The technician or engineer running the explosive cutter is
responsible for ensuring that the correct procedures and After the CT has been cut and the cutting tool string
actions are followed. The normal wireline/explosives han- retrieved, circulation through the CT may commence. In
dling safety procedures must be applied and enforced. cases where the well was not killed by circulating through
Page 9 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
the CT, at least 1-1/2 wellbore volumes should be circulated • Close the blind rams
to ensure that a continuous column of the required kill-
weight fluid exists. • Rig up to circulate the well with kill fluid through the kill
port.
Prior to rigging down the pressure control equipment, a flow
test should be conducted to verify the well status. 1.7.2 Power Pack Unit Failure
To recover the cut tubing string, the tubing must be joined In the event of a power pack unit failure, the following
temporarily by a double roll-on connector. This will allow the actions should be taken:
tubing to be spooled onto the reel. The reel-drive hydraulic
circuit should be operated at a reduced backpressure until • Apply the brake
the tubing joint is three to four wraps on the reel.
• Close the slip and pipe rams. Manually lock both rams.
An accurate track of the tubing recovered must be kept to
avoid withdrawing the end from the injector chains. How- • Depending on well pressure, it may be necessary to
ever, in most cases, tubing cut by an explosive cutter will continue circulation, to maintain differential pressure.
not pass through the stripper.
• If performing a fill cleanout job, ensure that circulation
1.7 Emergency Procedures continues until returns are clean.
If time and circumstances permit, review options with • Stop pipe movement
company representative. Where there is immediate and
serious danger to personnel, enact the BOP emergency • Increase pressure in stripper system or activate tandem
procedure. stripper
• Close shear rams and cut pipe • Even if the increased stripper pressure stopped the leak,
it may be safer to change the stripper inserts at this time
If time permits apply tension to pipe before cutting
• Close the slip and pipe rams. Manually lock both rams
• Pull pipe above the blind rams
Page 10 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
• Bleed off pressure above the pipe rams If it is not possible to free the coiled tubing:
• Release skate tension and jack up the injector • Hang off the coiled tubing in the slip rams
• Split the stripper caps and pack the stripper hydraulically • Kill the well
to remove the inserts
• Cut the coiled tubing above the injector head and cross-
• Reassemble the stripper with new inserts over the coiled tubing with the wireline lubricator
• Hydraulically pressure up the stripper • Determine the free point using the stretch method or
wireline free point tool
• Lower the injector and apply skate pressure
• Run chemical/flash cutter through the wireline and cut the
• Pressure test the stripper pipe at the free point
• Equalize pressure across the rams • Retrieve the free coiled tubing
• Open the pipe and slip rams manually • RIH with a fishing BHA and try to free remaining CT string
• Open the pipe and slip rams hydraulically 1.7.5 Collapsed Coiled Tubing
If the coiled tubing is stuck and a pull higher than 80% of • An increase in pull (stripper bushing)
the yield strength is required to free it, the following actions
should be taken: • Injector chain slippage
• Determine the possible causes, to select correct action The actions to be taken are:
plan:
• Close the slip and pipe rams on a good section of pipe.
- Work the string up and down without exceeding 80% of Manually lock both rams
the yield strength. Be aware of low cycle fatigue.
• Kill the well
- Circulate a slick pill to reduce friction between the CT
and casing/tubing walls. • Cut the coiled tubing above the injector and remove the
injector head
- Rapidly bleed off annulus (surge) while pulling on the
pipe. • Clamp down the coiled tubing and test the clamp
Page 11 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
• Walk the injector head over the 15 ft section of coiled Do not do the following:
tubing
• Stop injector chain rotation
• Connect the injector head to the BOPs. Apply inside skate
pressure • Close the BOP rams
• Connect the coiled tubing with double roll-on connector • Apply injector brakes
• Carefully spool the coiled tubing back to the reel 1.7.8 Reel Swivel Leak
1.7.6 Surface Treating Line Leak In the event of a reel swivel leak, the following actions
should be taken:
Actions to be taken include:
• Stop any coiled tubing movement
• Stop the pumps
• Close the slip and pipe rams. Manually lock both rams.
• Stop any coiled tubing movement. Depending on well
pressure and depth, it may be advisable to manually lock • Isolate the coiled tubing using the valves on the reel
the slip and pipe rams manifold
• Isolate the coiled tubing using the valves on the reel • Bleed pressure from the reel manifold
manifold
• Monitor the differential pressure on the coiled tubing by
• Bleed pressure from lines regulating the choke if necessary. Coiled tubing collapse
is a major concern at this point
• Monitor differential pressure on the coiled tubing by
regulating the choke if necessary. Collapsing coiled • Repair the leak and resume operations
tubing is a major concern at this point
1.7.9 Pinhole at Surface
• Repair the leak and resume operations
The actions to be taken depend on whether the check
1.7.7 Injector Chain Slippage valves are holding.
Actions to be taken in the event of injector chain slippage Check Valves Holding
include:
Actions to be taken include:
• Increase the skate tension
• Stop pumping
• In the event of coiled tubing runaway:
• Stop coiled tubing movement
- Apply emergency traction
• Alert people to the potential danger
- Chase coiled tubing with the injector chains
• If possible, flag the position of the pinhole with paint
- Increase stripper pressure
Page 12 of 14
COILED TUBING SERVICES MANUAL Section 420
Schlum berger
Dow ell CONTINGENCY PLANNING Rev A - 98
• If pumping corrosive fluid, run pinhole below the stripper • Walk injector head over 15 ft section of coiled tubing and
and displace with water. Caution must be exercised due connect injector head to BOPs. Apply inside skate
to the danger of breaking the pipe when running it through pressure
the gooseneck and chains
• POOH a few feet of coiled tubing
• If the fluids are not dangerous, carefully POOH coiled
tubing string • Connect coiled tubing with double roll-on connector
• Monitor the differential pressure on the coiled tubing by • Carefully spool coiled tubing back to reel
regulating the choke or flowing the well if necessary
• Rig up standby reel and complete operations
• Depending on the wellhead pressure, continue to pump to
decrease the chances of collapsing the coiled tubing The following is an alternative procedure:
string
• RIH coiled tubing below stripper. Caution must be exer-
• Rig up standby reel and resume operations cised due to danger of breaking the pipe when running it
through the gooseneck and chains
Check Valves Not Holding
• Do one of the following:
The job must be terminated. Actions to be taken include:
- Kill the well and retrieve the coiled tubing string, or
• Stop pumping
- Depending on the depth, pressure and type of reservoir
• Stop coiled tubing movement fluids in the well, continuously pump fluids or inert gases
through the coiled tubing string while pulling the coiled
• Alert people to the potential danger tubing string out of the hole
- Close slip and pipe rams The actions to be taken depend on whether the check
valves are holding.
- Close shear rams
Check Valves Holding
- Pick up CT above blind rams
The following actions should be taken:
- Close blind rams
• Stop coiled tubing movement
- Open shear rams
• Apply reel brake
- Manually lock blind, pipe and slip rams
• Stop pumping
• Kill the well
• Close slip and pipe rams. Manually lock both rams
• Prepare to retrieve the coiled tubing using an overshot or
spear • Monitor differential pressure on coiled tubing by regulating
the choke or flowing the well as necessary. Collapsing the
• Leave 15 feet of coiled tubing above the BOPs coiled tubing is a major concern at this point
Page 13 of 14
Section 420
COILED TUBING SERVICES MANUAL
Schlum berger
Rev A - 98 CONTINGENCY PLANNING Dowell
• Carefully spool coiled tubing back to reel 1.7.11 Leaking Riser and/or Crossover Between BOPs
and Wellhead
• Once there are a couple of wraps on the reel, start pumping
to reduce chances of collapse The following actions are to be taken:
• Depending on the type of well, the complete BOP • Stop coiled tubing movement
emergency procedure may need to be initiated
• Alert people to the potential danger
Check Valves Not Holding
• Apply the BOP emergency procedure without setting the
The following actions are to be taken: pipe and slip rams
• Apply the complete BOP emergency procedure - Open the shear rams
- Close slip and pipe rams - Close the wellhead master valve
- Close shear rams • Ensure sufficient coiled tubing is off bottom, so that when
the shear rams are used, the coiled tubing drops below the
- Pick up 1 ft master valve
- Manually lock the blind, pipe and slip rams • RIH with a fishing BHA and retrieve the coiled tubing
- Open shear rams The following alternative method can also be used:
• Kill the well • If available, pump an inert fluid down the coiled tubing
annulus and coiled tubing string
• Retrieve the coiled tubing using an overshot or spear
• POOH the coiled tubing string as quickly as possible
• Leave around 15 ft of coiled tubing above the BOP
Page 14 of 14