Beruflich Dokumente
Kultur Dokumente
Basic design
August 2009
AF-Colenco Ltd
Hydropower Department
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 2/65
Table of Contents
Page
1 Introduction .......................................................................................................................8
4 Topography .....................................................................................................................11
10 Cost Estimate...................................................................................................................53
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 4/65
11 Environmental aspects.....................................................................................................56
Index of Figures
Page
Figure 14. Schema of the numerical model for transient analysis of Zoti HPP.................................36
Figure 15. Max upsurge (red line) for case-2 and max downsurge (blue line) for case-4 ................37
Figure 16. Max pressure in the steel lining (at bifurcation level) for case-2 .....................................38
Figure 17. Plan view of Kvirila HPP..................................................................................................58
Figure 18. Duration curve for Kvirila HPP ........................................................................................59
Figure 19. Longitudinal profile Kvirila HPP .....................................................................................59
Index of Tables
Page
Table 1: Summary of flow data recorded on the rivers Gubazeuli at Khidistavi station ...................12
Table 2: Precipitation data from Zoti meteorological station at Gubazeuli River .............................13
Table 3: Summary of the main parameters for all catchments...........................................................14
Table 4: Power potential study results ...............................................................................................21
Table 5: Main features of the reservoir Gubazeuli.............................................................................27
Table 6: Main features of the diversion Khinistskali .........................................................................29
Table 7: Main features of the Dam Zoti .............................................................................................30
Table 8: Estimated main volumes for Gubazeuli dam .......................................................................30
Table 9: Main features of the diversion Gubazeuli Creek .................................................................32
Table 10: Main features of the diversion Kvirila ...............................................................................33
Table 11: Headrace tunnel profile types ............................................................................................34
Table 12: Main features of the upstream surge shaft .........................................................................35
Table 13: Studied operating conditions..............................................................................................36
Table 14: Results of transient calculations for the studied cases .......................................................37
Table 15: Main features of the pressure shaft ....................................................................................38
Table 16: Main features of the Underground Powerhouse and transformer cavern ..........................39
Table 17: Work capacities for the main construction items...............................................................49
Table 18: Construction schedule ........................................................................................................50
Table 19. Assumed unitary rates ........................................................................................................53
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 6/65
Table 20. Summary of the expected costs for Zoti HPP ....................................................................54
Table 21. Main hydrological information for Kvirilas River.............................................................58
Table 22. Salient features of Kvirila HPP ..........................................................................................60
Table 23. Summary of the expected costs for Kvrila HPP.................................................................63
ANNEXES
01 General Layout
Plan View
02 General Layout
Schematic longitudinal Profile
03 Derivation “Khinistskali”
Intake, Desander Facility and Transition Tunnel to the Gubazeuli Reservoir
Plan View and Sections
04 “Gubazeuli” Reservoir
Dam and Intake Structure
Plan View and Sections
09 Headrace Tunnel
Longitudinal sections and typical cross sections
14 Tailrace Tunnel
Longitudinal Sections and typical cross Sections
1 Introduction
With the aim to secure energy and to diversify sources of power supply in the country, the
Energy Ministry of Georgia announced privatization of a number of electricity distribution
companies and hydropower plants in 2006. Following this step, several foreign companies,
including the Czech energy-generation and -trading company Energo-Pro, became active in the
Georgian energy market. Besides being involved in the power distribution market, Energo-Pro
has been expanding its activities to the power generation sector and, in this context, has
approached Colenco to assess the hydropower potential in the area near the locality of Zoti.
In December 2008, AF-Colenco has prepared a due diligence study for the said project,
proposing an alternative project arrangement harnessing the hydro potential of several
catchment areas: Khinistskali River, Gubazeuli River and Kvirila River. The actual Basic
Design, presented herein, considers one additional smaller catchment area from the Gubazeuli
Creek.
The present report summarizes the findings of the Basic Design Study. All pertinent elements
and parameters that play an important role in the development of hydropower projects have
been evaluated, leading to the formulation of the basic design of the project. Principal design
drawings of the most significant structures have been also prepared.
- a first tyrolean intake at the Khinistskali river, with a free flow diversion tunnel until de
reservoir Zoti (direct catchment area: 39.5 km2)
- A 45 m high gravity dam (Zoti) in the upstream reach of the Gubazeuli river (direct
catchment area: 30.3 km2)
- A second tyrolean intake at the Gubazeuli Creek with a diversion tunnel connected to the
headrace tunnel (direct catchment area: 6.7 km2)
- A third tyrolean intake at the Kvirilas river with a diversion tunnel connected to the
headrace tunnel (direct area catchment: 46 km2)
- A surge shaft
- A pressure shaft
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 9/65
The only new source of information is a Sowjet Geological Map 1:200,000 of the region, dated
from 1957 (sheet K-38-XIX). This map, however, is very general and does not provide any new
information so far. According to this map, the entire area is uniformly covered by middle
Eozene ( = tertiary, age approx 50 ma) volcano-sedimentary rocks, consisting of tuffaceous
sandstones and breccias (hard rocks) as well as marls, shales, siltstones and some limestone. In
the Gubazeuli River valley, andesitic lava flows were also observed during the site visit.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 10/65
Exodynamic geological processes (erosion and mass movements) were identified during the
Feasibility Study as major geological risk for the project. To evade these risks, a large portion of
the present project arrangement has been placed underground.
The characterization of rock conditions along the proposed project alignment can only be done
after field studies and investigation works in the next project stage. Such investigations will
allow for further optimization of the project locations, in particular of the surge and pressure
shaft and of the powerhouse cavern location.
The weir foundations will be located in outcrops of competent bedrock, the only matter of
concern being the permeability of tuffaceous rocks (to be checked by investigations). A
prediction of the geotechnical tunneling conditions can be made after basic field and laboratory
investigations (mapping along alignment, eventually core drillings in portal area when access
available).
No particular problems are anticipated for tunneling at this stage. However, due to the
stratigraphic heterogeneity to be expected (see above), the local tunneling conditions will
strongly depend on the relative orientation of strata (bedding) and the lithostratigraphic unit
encountered. Tuffaceous sandstones and breccias are considered as hard fractured rocks, marls
and argillitic siltstone-sandstones as rather weak rocks.
Particular attention shall be given to selecting the exact powerhouse cavern location, this being
the most sensitive structure to geological conditions. Core drillings reaching the PH level are
indispensable. The required investment of funds in proper investigation must be seen in the
perspective of reducing the geological risks to an acceptable minimum and avoiding later claims
and delays during construction.
Seismicity
Figure 2: Map of Seismic Hazard of Georgia (Georgian Geophysical Society): peak ground
acceleration PGA
4 Topography
Zoti HPP has been designed based on scanned topographical maps 1:25’000 and contour lines
every 5 m. The scale of these maps allows carrying out a basic design without precise details,
however in a next design phase, more detailed topographical maps will be mandatory, e.g.
contour lines every 1 m, at least for all surface structures.
The maps are not referenced to any specific system (no coordinate grid indicated). Therefore,
there are no coordinates assigned to any of the project elements.
5 Hydrology Data
For the hydrological study, information from two gauging stations has been obtained: Bakhmaro
(1926 m.a.s.l.) and Khidistavi (150 m.a.s.l). Data seems to be reliable compared to the general
precipitation information in the project area. In view that the elevation of the Bakhmaro station
is 1926 m.a.s.l. and the project intakes are located at around 1140 m.a.s.l., the data provided at
the station Khidistavi (in the same Gubazeuli river) has been used to determine the water
availability for the basic design. Discharge data at the Khidistavi gauging station is available
from 1929-1991.
Table 1: Summary of flow data recorded on the rivers Gubazeuli at Khidistavi station
Catchment Area [km2] 337
The above presented average runoff water height and assuming a runoff coefficient of 0.65, the
corresponding annual average precipitation is 2259 mm/year.
Figure 2 shows the monthly average discharge extracted from the available data and Figure 3
depicts the flow duration curve for Khidistavi station.
30
Khidistavi station
25
Discharge [m /s]
3
20
15
10
0
I II III IV V VI VII VIII IX X XI XII
60
Khidistavi station
50
Discharge [m /s]
40
3
30
20
Qave = 15.70 m3/s
10
0
0 10 20 30 40 50 60 70 80 90 100
A precipitation distribution map of Georgia is shown in Figure 4. The map has been produced in
2003 from data of the Hydrometeorological Institute of Georgia. As can be seen, the project
area is located in the range of 1200 to 1600 mm which is consistent with the data recorded at
Khidistavi station. Additionally, Table 2 shows that the yearly value (1754 mm) measured in the
meteorological station located at Zoti is in agreement with the hydraulic data presented for this
study, confirming the reliability of these data.
5.1 Inflow
As mentioned before, the station Khidistavi (150 m.a.s.l) on the Gubazeuli River has been used
to estimate proportionally the water availability for the different catchments.
Zoti HPP takes the water from 4 different catchments as shown in Figure 5.
Catchment 3: Diversion
Gubazeuli Creek
6.7 km2
Catchment 4:
Diversion Kvirilas
46.0 km2
Catchment 2:
Gubazeuli reservoir Catchment 1: Diversion
30.3 km2 Khinistskali
39.5 km2
A scale factor according to each catchment area was calculated in order to determine the
different average duration curves. The main parameters of these catchments can be found in
Table 3.
Talweg
level 1152.5 1100.0 1144.0 1144.0
[m.a.s.l.]
Catchment
39.5 30.3 6.7 46
Area [km2]
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 15/65
Qaverage
1.84 1.41 0.31 2.14
[m3/s]
The resulting duration curves for each catchment area and the Zoti HPP are showed in Figure 6.
21
Zoti HPP
20
Kvirilas River (third tyrolean intake)
19
Gubazeuli Creek (second tyrolean intake)
18
17 Gubazeuli River (Zoti Dam)
12
11
10
9
8
7
6
Qaverage = 5.70 m3/s
5
4
3
2
1
0
0 10 20 30 40 50 60 70 80 90 100
Exceedence probability [%]
Ecological release has been taken into account for all diversions. The corresponding discharge
is determined according to Swiss regulations, where the water inflow that reaches at least during
347 days a year (95% of dependability) is the input parameter. For Zoti HPP the total ecological
release is for all catchment areas 0.64 m3/s.
Design floods were estimated for floods up to the 1000-year event. In the project area there is
no recorded data about flood events, therefore no peak values are available. Due to this lack of
information, a standard determination of maximal flows is not possible. Considering that the
project catchment areas are small, it has been decided to correlate values from Colenco data
base from other projects in the region. The design peak values are given in Figure 7.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 16/65
Q100
Q1000
6.00
Specific Design flood in m3/s/km2
4.00
2.00
0.00
10 100 1,000
Catchment area in km2
Sediment yield refers to the amount of sediment exported by a basin over a period of time,
which is also the amount which will enter a reservoir located at the downstream limit of the
basin. Sediment estimations have been made at Khidistavi Village on Gubazeuli River where
the suspended load is estimated to 138.5 t/year and the bed load to 20% of that amount.
Consequently, the sediment yield at this station is 373 m3/km2/yr. It is possible to induce that
sediments are not a big issue for the project. However, it is suggested to carry out watershed
investigations and by mean of empirical methods the sediment yield can be calculated and
compared and then should be used to plan flushing operations at the reservoir.
Sediment samples in the upstream part of the reservoir should be taken in order to elaborate a
sediment transport capacity study and verify that there are not negative effects in the reservoir
storage volume.
6 Design Parameters
There are two options for selling the electricity in Georgia, through direct contracts with the
qualified companies (distribution Licensees or large companies consuming more than 30 GWh
per year) or sale of electricity to the Electricity System Commercial Operator (ESCO) through
the balancing market. There is no difference between the peak and base energy prices.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 17/65
Normally, the selling price of electricity is established by the Georgian National Energy
Regulatory Commission (GNERC) on the basis of the relevant tariff submission made by the
company in accordance with the established tariff methodology. However, for new Hydro
Power Plants the energy legislation envisages the possibility of concluding the long term PPA
with ESCO on guaranteed purchase of the electricity. The terms of such PPA should be
negotiated at the initial stage of the project approval in the relevant Memorandum of
Understanding with the Government of Georgia. (Later GNERC shall approve such negotiated
tariff). In case if the power plant will be constructed by JSC Energo-Pro Georgia, most likely
we shall not require a compulsory purchase of electricity by ESCO but rather more sell
electricity in accordance with the needs of our distribution business - use such electricity for
distribution purposes, sell electricity to domestic large customers or export to the neighboring
markets (pending the seasons of the year).
As the initial guidance for tariff, it might be useful to note that currently HPP Paravani, that is
to be built in Georgia, has negotiated the selling price of electricity with the Government
(through the Memorandum) at 4.7 US Cents per KWh of power.
The legislation does envisage selling of capacity (MW) by newly built power plants, however
this part of regulations is constantly changing and therefore it is advisable that the calculations
are made without envisaging the possibility of selling the capacity separately.
Local Municipalities are entitled to determine the normative selling price of the land and
currently, according to the information from the legal department, such price for Chokhatauri
Region, comprises 2.16 Gel per m2 (~0.98 Eur/m2)
20
18
16
Discharge [m /s]
14
3
12 9, 10.7
13, 9.8
10 17, 8.9
8 25, 7.5
33, 6.5
0
0 10 20 30 40 50 60 70 80 90 100
Figure 8. Zoti HPP- Flow duration curve with the exceedance – discharge values for the power
potential study
The elements and parameters that have been included in the power potential study are as
follows:
Scheme elements:
• Catchment 1: Diversion Khinistskali + diversion tunnel + channel
• Catchment 2: Dam "Gubazeuli"
• Intake structure
• Catchment 3: Diversion Gubazeuli Greek + Diversion tunnel
• Catchment 4: Diversion Kvirila + Diversion tunnel
• Headrace tunnel
• Upstream surge shaft
• Pressure shaft
• Underground powerhouse, switch gear and transformer cavern
• Tailrace channel
Economical parameters:
Others:
• Accesses (roads, bridges, tunnels)
• Various Expenses (0.8% of the total construction and equipment costs)
• Investigations (1.0 % of the total construction and equipment costs)
• Feasibility Study, Final Design and Tendering (2.0 % of the total construction and
equipment costs)
• Design, Supervision and Administration (7.0 % of the total construction and equipment
costs)
• Connection to the Electrical National Grid (10 km)
All elements have been evaluated technical and economically with the same detail level. The
results of the power potential study are showed in the Table 4.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 21/65
HPP "Zoti"
9% 13% 17% 25% 33%
Installed capacity: 59.0 54.2 49.4 41.8 36.3
Total Construction and Equipment Cost 103 € 71,670.47 69,471.97 67,152.83 63,721.65 61,063.76
Civil 103 € 45,804.03 44,887.88 43,928.95 42,617.06 41,743.32
Hydraulic Steel Structures 103 € 3,786.07 3,633.65 3,403.35 3,026.02 2,607.26
Mechanical 103 € 8,294.11 7,837.39 7,380.67 6,676.56 6,125.13
Electrical 103 € 13,786.25 13,113.05 12,439.85 11,402.00 10,588.05
Total Cost various 103 € 20,640.41 20,402.97 20,152.51 19,781.94 19,494.89
Total Investment Cost 103 € 92,310.88 89,874.94 87,305.33 83,503.58 80,558.64
Energy Production
Peak Energy GWh 234.4 231.7 227.1 216.2 205.1
Off-peak Energy GWh
Total Energy Production GWh 234.4 231.7 227.1 216.2 205.1
Energy Price Peak Energy (DSI) €/MWh 34.0
Energy Price Off-peak Energy (DSI) €/MWh
Total Equi. Peak Energy Production GWh 234.4 231.7 227.1 216.2 205.1
A tendency curve has been derived from the prime cost of energy versus installed capacity for
each scenario; consequently the calculated optimum installed capacity corresponds to a value of
48 MW. (See Figure 9)
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 22/65
49.5
49.4
Prime Rate [EUR / MWh]
49.3
49.0
48.6
48.5 48.5
8 Project Layout
Catchment 1
Catchment area 39.5 km2
Talweg elevation 1152.5 m.a.s.l.
Intake type Tyrolean weir
Design discharge 2.80 m3/s
L= 60 m; Aefective= 10.15 m2;
Outdoor desilting basin
Diversion Khinistskali Dgrain= 0.25 mm
Qecological 0.21 m3/s
Diversion tunnel L= 2.7 km; free flow
Flood design 270 m3/s
Tunnel type Concrete lined; D-shape
Tunnel section excavation 21.0 m2 (including access)
Catchment 2
Dam Gubazeuli Catchment area 30.3 km2
Talweg elevation 1100 m.a.s.l.
Dam type Concrete gravity
Crest elevation 1145 m.a.s.l.
Deepest foundation elevation 1103 m.a.s.l.
Maximum height 42 m
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 23/65
Catchment 3
Diversion Gubazeuli Catchment area 6.7 km2
Greek
Talweg elevation 1144.0 m.a.s.l.
Intake type Tyrolean weir
Design discharge 0.50 m3/s
Flood design 75 m3/s
L= 25 m; Aefective= 2.1 m2;
Outdoor desilting basin
Dgrain= 0.25 mm
Qecological 0.04 m3/s
Diversion tunnel L= 230 m; pressure flow
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 24/65
Catchment 4
Catchment area 46.0 km2
Talweg elevation 1144.0 m.a.s.l.
Intake type Tyrolean weir
Design discharge 3.2 m3/s
Flood design 275 m3/s
L= 60 m; Aefective= 12.24 m2;
Diversion Kvirila Underground desilting basin
Dgrain= 0.25 mm
Qecological 0.24 m3/s
Diversion tunnel L= 420 m; pressure flow
Tunnel type Concrete lined; D-shape
Tunnel section excavation 6.8 m2
The project has a reservoir named Gubazeuli, located on the river with the same name at an
elevation of 1110.0 m.a.s.l. The water from the Khinistskali intake is diverted through the
diversion tunnel and enters directly in the reservoir. Additionally, the water from the other two
intakes enters directly in the headrace tunnel as long as the water reservoir is at level of
1140 m.a.s.l. (max. operation level). Otherwise, when the turbines are in off mode, and the
water reservoir level is lower than the maximum operation level, the water from Gubazeuli
Creek and Kvirilas intake will feed the reservoir, which maximum level is always controlled by
means of the ungated spillways. The volume curve of the reservoir is depicted in Figure 10
below. The main features of the reservoir are given in Table 5.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 27/65
1150
1145
Max. operation level = 1140 m.a.s.l.
1140
1135
Elevation [m a.s.l.]
1130
1125
1120
1115
The reservoir has a daily storage capacity and allows producing 5 hours of peak energy during
214 day in a hydrological average year with full capacity. Therefore, the annual energy
production of 255 MW can be divided in 82.7 MW (peak energy) and 142.4 MW (base energy).
At the moment there is no a tariff difference between peak and off peak energy, however having
a reservoir in the scheme allows to generate peak energy which will be economically
advantageous.
There is no information about sediment transport at the Gubazeuli River; therefore an estimate
of sediments entering in the reservoir has not been possible. However, in order to keep the life
initial life storage, we strongly recommend to envisage periodical flushing operations, e.g. once
or twice a year after heavy rain storms.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 28/65
The design discharge of 8.60 m3/s of the Zoti HPP has been determined according to the power
potential study. The total inflow volume (diverted from the four catchments) is 179.8 x106 m3
and the harnessed volume is 146.0 x106 m3.
With the chosen design discharge and the maximum net head of 640 m, an installed capacity of
48 MW results. The foreseen underground powerhouse will be equipped with two groups
(Pelton turbines), 24 MW each.
In an average hydrological year, the average annual energy production would be 225.1 GWh.
Khinistskali tyrolean intake is the most upstream intake structure of the project and it is
designed to divert 2.8 m3/s of the Khinistskali River.
The Tyrolean or drop intakes are commonly used for small and steeply sloped mountain rivers
with competent rock foundation. This type of intake, used in the absence of a reservoir, consists
essentially of a channel built in the river bed, stretching across it and protected by a trashrack
with a sloping face oriented in the direction of the river flow (Figure 12). Particles which are
smaller than the inside width between the trashrack bars are introduced into the collection canal
together with the water and these will be later on be separated from the water by a first sediment
trap for coarse material and afterwards by a desilting basins for fine material.
The structure is also composed of an ungated spillway next to the tyrolean intake to pass by the
floods up to a return period of 1000 years.
The diversion tunnel connects the Khinistskali intake structure to the reservoir Gubazeuli,
located on the Gubazeuli River. The tunnel is located on the left side bank of the intake structure
and has a length of 2700 m. This tunnel during construction serves as a main adit for the
construction of the Khinistskali intake, later on it will become a water way and a permanent
maintenance access. The section is a D-shape type. The excavated width at the invert is 3.4 m,
the vertical banks are 1.85 m high and the top arch has a radius of 1.7 m. A concrete lined
channel will be placed on the left side of the tunnel, leaving 2.3 m on the other side as
permanent maintenance access way after construction. The invert will be lined with a 30 cm
thick concrete, while the arch and one vertical sidewall will be protected with shotcrete and wire
mesh where required by geological conditions. The tunnel invert is at an elevation of 1148.80 m
a.s.l at the inlet and 1140 m a.s.l at the outlet, resulting in a constant slope of 0.3 % until
reaching the reservoir. The construction method, whether conventional or with a tunnel boring
machine (TBM) will be decided at a later design stage. Drawings annexed to this report shall be
consulted for additional geometry details.
The Gubazeuli Dam is a concrete gravity dam type of 42 m height. The main parameters are
described in Table 6:
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 30/65
Maximum height 42 m
The form of the valley at the dam axis is favourable for a simple gravity dam. Due to the
factthat the flood design discharge is not very high (250 m3/s) and that the dam crest is long
enough, two ungated spillway structures can be easily integrated within the dam body. In
addition, the incorporation of the bottom outlet or sluice way (3.50 x 4.00 m) in the dam body
represents no major challenge.
The foundation treatment will consist of contact and consolidating grouting over the whole
foundation surface (both abutments and the central part below the river) and of a grout curtain
with a depth in the central part of ~25 m. Downstream of the grout curtain drainage holes will
be provided.
Spillway
The spillway consists of an ungated overflow spillway with a total crest length of 28.0 m. A
bridge over the spillway will be provided by dividing the overfall section into 2 openings of
14 m each, separated by a pier of 2.0 m. The pier also contributes to aeration of the flow. Sill
elevation is 10 cm above the maximum operation level at 1140 m.a.s.l.
With the peak design discharge of 250 m3/s (Q1000) the maximum reservoir level will rise up to
an elevation of 1142.8 m.a.s.l. and during probable maximum flood conditions (PMF =
375 m3/s) to 1143.6 m.a.s.l. with a free board of 1.4 m.
Bottom Outlet
One bottom outlet is integrated into the right part of the dam body. This bottom outlet has not
flood purposes but rather sediment flushing operations. The frequency of the reservoir flushing
should be determined during the operation according to the sediment inflows. At this stage we
do not have any sediment information at the dam location. The invert elevation of the bottom
outlets is at a level of 1118 m.a.s.l., i.e. ~1 m above the original ground level (talweg). It serves
also to empty the reservoir in an emergency case.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 31/65
The bottom outlet consists of: a bell-mouth inlet, a pressured conduit, a sliding gate 3.5 x 4.0 m
(w x h), a set of stoplogs and a flip bucket.
The bell-mouth inlet and pressurized conduit will be fully steel-lined. Downstream of the gates,
the invert and side walls of the free flow channel up to 1 m from the invert, will be also steel-
lined. This is to prevent damage to the concrete during emptying of the reservoir. The thickness
of the steel lining should not be less than 20 mm.
Figure 13 shows the capacity curve of the bottom outlet at different opening percentages. The
dimensions of the bottom outlet will permit to empty the reservoir with the minimum operation
level in 12 hours with a maximum discharge of 35 m3/s which represents a 5 years return period
flood. It has to be noted that the discharge release should be controlled according to flood risk
assessment downstream of the reservoir and the bottom outlet width cannot be reduced because
it is adequate for sediment flushing operations.
1140.0
1135.0
Storage level [ m a.s.l. ]
1130.0
1125.0
The power intake structure is located on the left bank of the Gubazeuli reservoir. To guarantee
the submerging criteria, the invert level is fixed at an elevation of 1128.8 m.a.s.l. The whole
structure is designed to divert a discharge of 4.9 m3/s.
The size of the trash rack opening results in an intake net velocity of about 1.0 m/s. The
minimum operation water level at an elevation of 1131.8 m.a.s.l. ensures that the water inflow
in the bell-mouth inlet is free from vortices and air entrainment.
The top level of the intake structure has an elevation of 1145 m.a.s.l., equivalent to that of the
dam crest. This also allows access during floods. Access to the top platform of the structure is
by a road coming from the dam crest.
At elevation 1143.2 m.a.s.l. the gate shaft is enlarged to a chamber for maintenance works of the
sliding gate.
In the very low probability case that the Gubazeuli Creek and Kvirilas intakes are diverting only
16% of their corresponding design discharge into the system, the intake structure will
experiment higher velocities compared to the design ones. For example, assuming than
Gubazeuli Creek and Kvirilas intake divert together only 0.6 m3/s (instead of 3.70 m3/s) the
velocity through the intake tunnel entrance will rise to ~4.6 m/s (~64 % more) and the gross
velocity through the trash rack will increase to ~1.10 m/s (~70% more) for a discharge of
8.0 m3/s. Even these values are in the upper limit, they are still acceptable for non-frequent
cases.
Gubazeuli Creek includes a tyrolean type intake and it is designed to divert 0.5 m3/s. The
description of this intake structure and of the desilting facilities corresponds to that one given in
chapter 8.2.1.1.
The structure is also composed of an ungated spillway next to the tyrolean intake to pass the
floods up to a return period of 1000 years.
valve chamber)
The diversion tunnel connects the Gubazeuli Creek intake structure to the main headrace tunnel
at 7.65 km from the surge shaft. The tunnel is located on the right side bank of the intake
structure and has a length of 230 m. The section is a D-shape type. The excavated width at the
invert is 2.6 m, the vertical walls are 1.60 m high and the top arch has a radius of 1.3 m. A
30 cm thick concrete lining will be placed in the entire perimeter. The diversion tunnel invert
has an elevation of 1140.6 m a.s.l at the inlet and 1127 m a.s.l at the downstream connection to
the main tunnel, having a slope of 5 %. The construction method, whether conventional or with
a raise drill machine will be decided in a later design stage. Drawings annexed to this report
shall be consulted for additional geometry details.
Kvirilas tyrolean intake is the last water intake of the scheme. It is designed to divert 3.20 m3/s.
The description of this intake structure corresponds to that one given in chapter 8.2.1.1. The
desilting facility has the same concept as the previous intakes but because of the narrow river
bed and steep banks, it will be built underground.
The desilting basin tunnel is 85 m long and the flushing tunnel is 30 m long. From the end of the
flushing tunnel a concrete lined channel brings the mixture water-sediment back to the river. For
more details please refer to the drawings annexed to this report.
The structure is also composed of an ungated spillway next to the tyrolean intake to pass by the
floods up to a return period of 1000 years.
facility
The diversion tunnel connects the Kvirila intake structure to the main headrace tunnel at 4 km
from the surge shaft. The tunnel is located on the right side bank of the intake structure and has
a length of 420 m. The section is a D-shape type. The excavated width at the invert is 2.6 m, the
vertical walls are 1.60 m high and the top arch has a radius of 1.3 m. A 30 cm thick concrete
lining will be provided at the entire perimeter. The diversion tunnel invert has an elevation of
1135.45 m a.s.l at the inlet and 1116.6 m a.s.l at the connection to the main tunnel, having a
slope of 8 %. The construction method, whether conventional or with a raise drill machine will
be decided in a later design stage. For more details please refer to the drawings annexed to this
report.
The headrace tunnel connects the intake structure, situated at Gubazeuli reservoir, to the
pressure shaft at its lower end. It is designed to conduct a total discharge of 8.6 m3/s with a
velocity of 1.6 m/s and the head loss due to friction is 6 m, adopting a roughness of 0.0035 m. It
is located on the left side of the Gubazeuli River and has a length of 8,560 m.
The excavation is a D-shape type for all profile types (See Table 11). The excavated width at the
invert is 3.0 m, the vertical walls are 1.90 m high and the top arch has a radius of 1.50 m. A
30 cm thick concrete lining will be provided at the entire perimeter. The internal area of the
headrace tunnel has been defined according to construction criteria and not according to an
optimization of its hydraulic parameters.
From the intake, the tunnel is aligned in northwest direction until the top of the pressure shaft.
The invert is situated at an elevation of 1128.8 m.a.s.l. at the intake structure and continues with
a slope of 0.18 % downwards to the top of pressure shaft which is situated at an elevation of
111.2 m.a.s.l.
2 Fair rock 30
3 Poor rock 35
For constructive purposes, the construction of an intermediate 850 m long adit is foreseen. This
adit entrance will be situated in the access road between Zoti and Kivirila intake at an elevation
of 1150 m.a.s.l. The dimensions are the same as for the headrace tunnel and the support works
should be decided based on geological conditions.
The upstream surge shaft is located at the end of the Headrace Tunnel on the top of the vertical
pressure shaft. Table 12 shows the main parameters. Whether a sealing with a grouted
membrane system is required due to geo-mechanical properties and groundwater conditions, can
not yet be determined.
Height 48.0 m
A road of 5.4 km is foreseen to access to the top of the surge shaft. From the same road a short
tunnel of 160 m length will serve as adit for the bottom of the surge shaft and for the headrace
tunnel construction.
For verification of pressure conditions along the power waterways, a transient analysis was
carried out applying the SIMSEN HYDRO software.1
1
SIMSEN V2.3 Simulation software for Power Networks, Electrical drives and Hydraulic Systems. Swiss Federal Institute of
Technology of Lausanne (Switzerland)
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 36/65
Figure 14. Schema of the numerical model for transient analysis of Zoti HPP
The most hazardous cases of transient operations of the power-plant have been studied as
follows:
• Case-2: Start up of both units followed by emergency stop of both units at the worst
instant, maximum reservoir level
• Case-3: Emergency stop of both units followed by start up of the units at the worst
instant (one by one), minimum reservoir level
Based on the results of transient analysis, maximum upsurge level in surge shaft is 1154.2
m.a.s.l. and max downsurge is 1116.7 m.a.s.l. Pressure in penstock at bifurcation level reaches
67 bar. Results of the analysis of all four cases are presented in Table 13.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 37/65
Figures 4 to 5 show the variation of water level in the surge shaft as well as the maximum pressure
which can be reached in the penstock for the most hazardous cases.
Figure 15. Max upsurge (red line) for case-2 and max downsurge (blue line) for case-4
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 38/65
Figure 16. Max pressure in the steel lining (at bifurcation level) for case-2
A pressure shaft connects the downstream end of the headrace tunnel to the powerhouse. Its
main features are presented in Table 15.
The vertical shaft with a total height of 612 m (408 m concrete lining and 204 m steel lining)
will be followed by a 90° bend at the bottom of the shaft where a 100 m horizontal steel lining
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 39/65
stretch (including the bifurcation) will feed the two turbines in the underground powerhouse.
The resulting head losses in the pressure shaft are 1.20 m. The lengths for the different pressure
shaft stretches have to be verified in a next phase when geological information is available,
including ground water table conditions.
The present basic design does not foreseen a valve chamber before the pressure shaft, given that
the following pressure structure is developed fully underground and therefore, the risk to human
life and goods is negligible. Whether a valve chamber will be convenient for operational and
maintenance purposes should be evaluated in the next design phase according to the power plant
operator. In this case, it should be located before the pressure shaft starts and the foreseen adit
for construction purposes, as nominated in chapter 8.2.6 becomes a permanent access for
maintenance purposes.Power Plant Equipment
The powerhouse is located in an underground cavern on the left bank of the Gubazeuli River
between the villages Kvabga and Zoti. It houses two vertical Pelton turbines of 24 MW each.
The transformer is located parallel to the powerhouse in a separate cavern for security reasons.
The distance between the caverns is 50 m. The access tunnel arrives first to the transformer
cavern and later on to the powerhouse cavern. Additionally, a second tunnel is foreseen to
interconnect both caverns and it could also serve as an emergency exit.
Table 16: Main features of the Underground Powerhouse and transformer cavern
Dimensions of the main cavern (L x W x H) 44 x 20 x 24 m
The access to the powerhouse complex is through a 1 km long multipurpose access tunnel. Its
portal has an elevation of 540.0 m.a.s.l. after crossing the first bridge over the existing road
between Kvabga and Zoti. This is an existing bridge with 55 m length but a refurbishing is
foreseen in order to support the loads of the equipments and powerhouse elements. The length
of this access tunnel is 1.3 km with a slope of 4.5 %. The section is a D-shape with an
excavated width at the invert of 3.0 m, the vertical walls are 1.90 m high and the top arch has a
radius of 1.50 m. A 10 cm shotcrete lining is foreseen for the vertical walls and the top arc, and
a 15 cm asphaltic cement layer will be placed on the invert together with a drainage system to
guarantee the traffic circulation.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 40/65
Additionally, this access tunnel will port the outgoing high voltage cables placed on cable-trays
at one of the banks. Cable-trays need a sectional area of 1.2 m height x 0.4 m width inside the
tunnel. Closed ducts for fresh and waste air from the ventilation system have to be considered.
The tailrace tunnel discharges the water from the Pelton turbines and brings them back to the
Gubazeuli River. The outlet portal is located at 490 m.a.s.l., near the village of Kvabga. It has a
D-shape profile with a length of 2.19 km and a slope of 0.25 %. The excavated width at the
invert is 2.6 m, the vertical walls are 1.80 m high and the top arch has a radius of 1.3 m. The
vertical walls and the invert will form a channel with a 20 cm thick concrete. The top arc will be
supported according to the profile type. This channel is designed for a discharge of 8.6 m3/s
with a velocity of 2.8 m/s and a water depth of 1.40 m.
If the tunnel driving will be conventional or with a tunnel boring machine will be fixed in a later
design stage.
Zoti HPP is a high head scheme with storage capacity aimed to operate mainly for peak energy
production. The plant discharge is 8.6 m3/s and the maximum net head 628.6 m. Pelton turbines
have been considered for operation in this range of head. Head and discharge lead to a rated
turbine power of 48 MW.
The installation of two units is recommended for Zoti HPP in order to achieve good availability
of turbines during maintenance/repair works and in case of one turbine is out of order. Therefore
turbine rated power is proposed with 2 x 24 MW.
The arrangement of the turbines is mainly determined by the costs of the cavern works. Vertical
Pelton units with several injectors (more than 2 injectors) allow a more compact design than
horizontal units (maximum 2 injectors).
• Vertical units with higher number of jets can provide better efficiencies at minimum
plant discharge.
• Periodic inspection of the runner, nozzles and deflectors can be achieved at a glance, as
no elements hide another (visit from below).
• Stress on Pelton runners with en even number of nozzles is cancelled as nozzles are
symmetrically distributed.
A disadvantage of the vertical arrangement will be the maintenance of generator as more work
is needed than for a horizontal arrangement.
Based on the above explanations, vertical Pelton arrangement is recommended for Zoti HPP.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 41/65
In order to reach a compact vertical design of each generating unit, only two bearings for the
complete shaft will be installed: one upper combined thrust/guide bearing on top of the
generator and a lower guide bearing on top of turbine housing. The Pelton runner is bolted
directly to the lower generator shaft.
The generator frame will support the upper combined bearing. Below the generator, a large
bracket embedded in the concrete will bear the generator. Axial forces will be transmitted
through stator frame, to the bracket then into the concrete.
For the turbine vertical arrangement two alternatives are possible: units equipped with 4
injectors (n=750 rpm) and units equipped with 6 injectors (1000 rpm).
However, the alternative with a speed rotation of n=750 rpm is recommended to avoid high
runaway speed then limiting the mechanical stresses in the rotating parts.
• Synchronous condenser mode (if foreseen by the Client): This operation is aimed to
regulate the voltage of the grid by producing / absorbing reactive power. This operation
needs the permanent operation of the auxiliaries including cooling water system without
water contribution from the waterway (injectors closed). The cooling water concept
shall take this into account if this mode of operation is foreseen.
• Spinning reserve: Pelton units are favourable for this operation mode due to capability
of fast power regulation according to the grid demand. This operation is normally
foreseen for powerplants equipped with Pelton units.
• Number of turbines: 2
• 1 Pelton runner
• 1 turbine housing
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 42/65
The Main Inlet Valve (MIV) will be installed between the steel lined feeder and the inlet pipe of
the turbine distributor. Due to the high head, the MIV is of the spherical valve type, provided
with a downstream service seal and an upstream maintenance seal. This double seal concept
allows inspection and maintenance works on the turbine, as well as removal of the service seal
of the MIV without emptying the upstream waterway.
On the upstream side, the MIV will be flanged and bolted to a conical connection pipe, which is
welded to the steel lined feeder including a make-up piece.
The opening of the MIV will be operated by means of a servomotor whereas the closing will be
performed by a counterweight. One hydraulic servomotor, supported on the concrete ground
shall be installed for opening the valve rotor. The oil pressure for opening will be supplied by
the oil pressure system of the MIV.
• Spherical valve, diameter approx. 700 mm, complete with body, rotor, maintenance and
service seal
• By-pass system
The cooling water system will provide cold water to the heat exchangers of generators and
transformers as well as cooling water for generator combined thrust/guide bearings and for the
lower guide bearings.
• Three pumps (one for each unit and one as stand-by pump) pumping water from a
common sump built at the discharge pit level.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 43/65
• Header pipes.
• Check valves installed after pump exit prevent flow back to the pumps.
Other alternatives for cooling water system can be studied in the next stage.
The system will allow the collecting of seepage, leakage, drainage and oil contaminated water
from the powerhouse cavern. The system will also allow dewatering of the turbine distributor
and waterways to perform repair works of water wet parts.
Leakage, seepage, drainage and oil contaminated water of powerhouse cavern will be collected
into an oil/water separator tank before directing the water by gravity to the tailrace channel. The
oil/water separator tank will be installed below the MIV floor level.
Dewatering of the upstream waterway and turbine distributor will be performed directly by
gravity into the tailrace channel by means of isolating valves or through injectors-deflectors at
small discharge.
• Isolating valves
The powerhouse crane will provide the facility of unloading, shifting and loading of equipments
in powerhouse during erection period. It will also provide the same facility during operation and
maintenance periods.
The heaviest component to be lifted is the generator rotor of approx. 60 tons. Therefore the
capacity of the main hook will be 70 ton whereas the capacity of the auxiliary hook will be 10
ton.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 44/65
8.2.10.1 Generators
Two vertically arranged generators directly coupled with turbines shall be provided with the
main features as follows:
- Frequency 50 Hz ± 5%
- Stator with a core made of high quality lamination and a class F insulated winding
- RTD’s in winding, metal and oil bearing with cable terminated in junction boxes.
- Vibration monitoring.
The excitation system shall provide field current to the rotor poles for producing magnetic flux.
Simultaneously, a built-in Automatic Voltage Regulator shall control the field current to induce
voltage at the stator terminals in accordance with the reference voltage.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 45/65
A static excitation system with thyristor rectifier shall be used in order to achieve a system with
a very high response to grid fluctuation and low maintenance. Each unit should have its own
static excitation equipment.
Static excitation equipment for one unit shall consist of following components:
- Excitation Transformer
- Slip ring with carbon brushes with associated cable to interconnect the static exciter with
rotor
The generator transformer shall step up the generator voltage to the level of transmission line,
110kV depending on the load supply configuration. Each generator will have an independent
three phase 2 windings transformer.
- Capacity 30 MVA
In order to provide a high level of reliability, we recommend separating each generator and the
network by means of the step-up transformer.
A direct connection as shown in the previous feasibility study shall be avoided as it could result
in major damages on the stator winding in case of earth fault.
A step-up transformer spare part has not been included in the price estimation. This can be
evaluated in the next stage.
The electrical protection will be assumed by redundant multifunction digital relays. The
electrical protection will be separate in the following area:
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 46/65
- 110kV Cables
- 110kV Switchyard
- Transmission Line
Definition of protective functions will be made at tender design phase according to the current
practice and the recommendation of standardization institute.
One metal-clad switchgear per unit shall be installed in the powerhouse cavern for
interconnecting the generator, the excitation transformer, the auxiliary transformer and the main
transformer. Off-load, de-energized type switch will be used for separate the generator in order
to be able to supply the auxiliary transformer through the main transformer when the unit is not
running. SF6 circuit breaker will provide fast isolating of the auxiliary transformer in case of
electrical fault. Manually operated disconnecting and earthing switch shall be installed for
commissioning and maintenance purpose. Each of them will be equipped with:
One outdoor switchyard shall be installed near the entrance of access gallery for interconnecting
the main transformers with the transmission lines. SF6 circuit breaker will be used for
synchronization process and protection of the units and transmission lines and also for switching
operation.
The switchyard will be designed to allow easy future extension of at least one bay for
connection to the future Hydro Power Plant Kvirila
Connection between the main transformers and the switchyard will be provided by one
kilometer length 110kV XLPE insulated cables and located in the access gallery.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 47/65
One auxiliary transformer 10/0.4kV per unit shall be used to supply the plant auxiliary power.
Each transformer shall be dimensioned to provide the complete auxiliary load of the plant.
The LV power distribution shall be constituted of one main distribution board and four sub
distribution boards. The main distribution board shall collect the power from the auxiliary
transformers or the diesel generator and shall supply the sub distribution boards. The feeders
will be equipped with withdrawable circuit breaker with over current relay. The busbar shall be
equipped with over/under frequency relays and over/under voltage relays as protection purpose.
One sub distribution board shall be installed for each unit, one for the general consumers in
main cavern and one for the consumers in transformer cavern. The feeders shall be equipped
with Circuit Breaker and over current relay, Moulded-Case Circuit Breaker (MCCB), or
Miniature Circuit Breaker (MCB) depending of their nominal power. Some feeders will be
equipped with additional relays for command.
Each of these five boards shall have two sections, one supplying the normal load which will be
not supply by the EDG and the second the essential load which required supply by the EDG.
To supply power to the essential auxiliaries and to enable black start condition, a 200 KVA,
415V Emergency Diesel Generator (EDG) shall be provided. An Automatic Transfer Switch
(ATS) shall also be provided to automatically start the EDG and switch over the source of
supply to the essential loads.
Consumers located at the Zôti dam and the various tyrolean intakes will be supply by a cable
located in the penstock pit and in the headrace tunnel or by local autonomous systems.
Two sets of battery 600Ah, 220 Volt DC along with respective battery chargers shall be
provided in the power house to supply DC power to the control, instrumentation,
communication, protection, static excitation and other essential equipment as required. The
recommended batteries shall be of Nickel-Cadmium type. If equipment required a different
voltage, DC/DC converter shall propose.
A Distributed Control System (DCS) shall be proposed for the complete control command and
acquisition of the unit, switchyard and auxiliaries. The DCS system in cavern will include at
least one operator station, the plant and backup stations, a double star or ring optical network,
and four programmable logic controllers as local control unit. Additionally, two operator
stations, the engineering station, and the communication equipment will be installed in the
administrative building situated outside close to the entrance of the multipurpose tunnel access.
Communication for DCS purpose between powerhouse cavern network, switchyard and
administration building shall be made by two independent optical network cables.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 48/65
Complete electrical metering shall be provided on the MV and HV plant. Each generator,
transformer, and line feeder shall be equipped with current, voltage and power measuring
equipment. In addition each unit and line feeder shall be equipped with energy meter.
Measuring will use separate current and voltage transformer.
Fire protection of generator in underground power house will be provided by an inert gas
mixture consisting on Argon and Nitrogen. Each oil transformer shall be equipped with it own
deluge system. For other equipment and general fire hoses and hydrants will be provided at
strategic points. A water storage tank shall provide fire fighting water through pipes and valve.
It should be erected in high elevation in order to avoid any need of power during fire event. It
will be filled by means of pumps during the normal operation of the plant.
The project area shall be equipped with telecommunication system to allow internal
communication within the vicinity as well as interface with the public exchange system. A VHF
radio system can be proposed for voice communication between maintenance and operating
teams as well as for telecommunication with the instrumentation located at Gubazeuli dam and
the various tyrolean intakes.
According to the information received during the meeting stayed the 13 August 2009 in AF-
Colenco office in Baden, the plant will be connected to the nearest 110kV Georgian Substation
located at around 16km from the plant. Single circuit transmission line will be enough to
provide complete power evacuation.
9 Implementation Schedule
The following values have been adopted in order to elaborate the construction schedule.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 49/65
Rockfill / earthfill
m3/day 1500
volume
Construction of access
m/year 16000 Average
roads
The costs for roads have been assumed with the condition that the contractor has experience on
this field; otherwise the construction times might be very extensive.
The project area of Zoti HPP does not have many transport options. Therefore, 21 km of access
roads are necessary to reach the different scheme elements. Accordingly, it is needed to start the
construction of roads at least 6 months before the start of the Adit 1.
Table 18 shows the construction program where preparation works and Zoti HPP are the main
divisions. The critical path is the construction of the headrace tunnel between Adit 1 and
Gubazeuli Dam, due to the 6.1 km of road improvement and 15.2 km of new roads construction.
It is suggested to carry out a roads optimization study, taking into account more detailed
topographical and geological conditions.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 50/65
Most of the construction materials can be found close to the project area. The excavated
material is approximately 170.000 m³, it has been estimated that only 97.000 m3 can be prepared
in crushing plants for concrete. A greater portion of excavated material cannot be used for
construction purposes. The rest has to be deposited in well defined areas, which are not affected
by flood-waves so that no erosion of the material will occur.
In case of a concrete dam and tunnels, it will be economical to install a batching plant close to
each site and adits. Whereas aggregates can be quarried close by the site, cement and all
auxiliary materials for the construction of the dam, appurtenant structures, tunnels and intakes
are bought from producers in Georgia, if prices according to local custom and usage can be
negotiated. Otherwise, for best overall cost effectiveness, imports may be necessary.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 53/65
10 Cost Estimate
103 €
Civil Hydromechanical Mechanical Eletrical Total
Works Works Equipment Equipment
Part C Part H Part M Part E
1 CATCH. 1: DIVERSION KHINISTSKALI + DIVERSION TUNNEL + CHANNEL 5,944.5 12.0 10.0 5,966.5
2 CATCH. 2: DAM "ZOTI" H= 45m 6,945.0 103.1 50.0 7,098.1
3 INTAKE STRUCTURE 64.4 37.4 50.0 151.8
4 CATCH. 3: DIVERSION GUBAZEULI CREEK + DIVERSION TUNNEL 368.1 19.9 10.0 398.0
5 CATCH. 4: DIVERSION KVIRILA 1,041.2 32.2 10.0 1,083.3
6 HEADRACE TUNNEL 11,141.1 11,141.1
7 UPSTREAM SURGE SHAFT 578.9 578.9
8 PRESSURE SHAFT 1,019.1 1,914.5 2,933.6
9 UNDERGROUND POWERHOUSE AND OUTDOOR SWITCHYARD 3,694.2 27.9 6,069.6 11,818.6 21,610.4
10 TAILRACE CHANNEL 939.1 939.1
A Total Construction and Equipment Costs 41,256.4 2,469.0 6,676.6 13,143.5 63,545.4
Rate with respect to total cost A 64.9% 3.9% 10.5% 20.7% 100.0%
B Reimbursement for Land Acquisition --- 980.0
C Reimbursement for Resettlement --- -
D Accesses (roads, bridges, tunnels) --- 10,400.0
E Various Expenses 0.8% 508.4
F Investigations 1.0% 635.5
G Feasibility Study, Final Design and Tendering 2.0% 1,270.9
H Design, Supervision and Administration 7.0% 4,448.2
I Connection to the Electrical National Grid (16 km) --- 4,000.0
54/65
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 55/65
HPP "Zoti"
3
TOTAL ANNUAL COST 10 € 10,959.10
In the above table it is considered that there is no tariff difference between Peak and Base Load
energy. However, with the proposed Gubazeuli reservoir it is possible to generate peak energy
considering 5 hours per day. Therefore the total Energy Production can be divided in peak
energy (82.7 GWh) and base energy (142.4 GWh).
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 56/65
11 Environmental aspects
The basic design of Zoti HPP was developed in respect of the ecological situation. In the study
it was very important to have as less influence on the environment as possible. Therefore it has
been possible to use the river Gubazeuli and its effluents for renewable energy without a major
negative effect on the ecological system of the river.
The long tunnels of the hydro power plants do not interfere to the normal development of the
area or with the landscape; contrarily it brings new access roads and a new economical activity.
Due to the relatively sparse population characteristic at the project area, matters like land
acquisition and resettlement that normally represent an important topic in hydroelectric projects,
are not a main issue.
The two vertical Pelton turbines have an installed capacity of 24 MW each. The average annual
energy production of Zoti HPP is estimated to be 225.1 GWh and the energy rate results 47.3
Euros/MWh (uniform selling rate)
With the foreseen daily storage capacity at Gubazeuli reservoir, it is possible to divide the total
energy production into peak and base energy. For example, when assuming that 5 hours peak
energy are generated, the peak energy will correspond to 40% of the total produced energy.
Likewise if 8 peak hours are considered, the peak energy will correspond to 55% of the total
produced energy. However, such benefit can be only evaluated when a peak and a base selling
tariff have been established in the country and if it is so, the project becomes economically more
attractive.
Environmental effects do not represent a critical issue for Zoti HPP. Nonetheless, a project of
this dimension causes changes within the affected area. Therefore, of primary concern should be
the minimization of the negative impacts of the project to the local population, or further, even
to ameliorate the current living conditions. It is a fact that the project will cause indirect benefits
to the region, i.e. social and economical development.
The scheme has only one operation organ (spherical valve) which allows a simple plant
operation and consequently a friendly maintenance.
For the next design steps the following tasks are recommended to carry out in order to elaborate
the Detail design (concession design):
• Geological Study
• Survey (Topography)
To evaluate the economical attractiveness of an additional hydro power plant, situated upstream
of the derivation structure of the Kvirila catchment area at elevation 1144.0 m a.s.l. (element of
the presented Zoti HPP scheme – Chapters 1 to 12 of the present report) a rough assessment of
its economical feasibility has been carried out. The possible scheme of such a plant with daily
storage capacity is illustrated in (Figure 17) and consists of a reservoir, a headrace channel
combined with the access road to the dam, a head pond, a penstock, an outdoor powerhouse, a
switchyard and a short tailrace duct. Also a new transmission line with a length of 6 km to
connect the plant to the electrical national grid has been taken into account. For the installed
capacity the same parameters, as adopted for the Zoti HPP have been considered, i.e. the design
discharge is that one which corresponds to an exceedence value of 18.1% on the duration curve
and the required storage capacity is determined to produce peak energy at least during 5 hours a
day over the whole year. Considering a hydraulic head of around 280 m and a design discharge
of 3.15 m3/s the resulting installed capacity is around 8 MW and the average annual energy
production amounts to 34.7 GWh.
The Kvirila HPP, as presented in this chapter, is connected to the main access road system of
the Zoti HPP. In the case this project would be realized as stand alone; i.e. independently of the
Zoti HPP, additional cost for accesses and grid connection would arise. In the case the Zoti HPP
would be realized, the final connection of the water conveyance system of the Kvirila HPP with
the Zoti one should be studied more in detail. Maybe a solution can be found to connect the two
plants without losing any head, because in the presented assessment some 20 m of head are not
harnessed.
In this chapter the principal findings of the quick assessment of the Kvirila HPP are presented.
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 58/65
Powerhouse
Penstock
Head pond
Kvirila River
Pressurized headrace
channel
Kvirila Dam
Kvirila Reservoir
The hydrology data was deducted proportionally to the watershed as explained in chapter 5.1.
The main hydrological information is summarized in Table 21 and the duration curve is
depicted in Figure 18.
Kvirilas River
Factor 0.14
8
Kvirila HPP
7
6
Discharge [m /s]
3
5
3
2
1
0
0 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 100
A longitudinal profile indicationg the main elements of the scheme is shown in Figure 19 and
Table 22 presents the main features for each of the Kvirila HPP’s components.
1470
Max. op. Level = 1440 m.a.s.l. Head pond
1450
1430 Tailrace channel
1410
1390
Elevation [m.a.s.l.]
1370
1350
1330 Penstock
L= 407 m
1310
1290
1270
1250
1230
1210
1190 Outdoor
1170 Powerhouse
1150
-100 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 1600
Length 407 m
Internal diameter 1.60 m
Average thickness 0.80 cm
Penstock
Flow velocity 1.60 m/s
Head losses 0.7
Type Outdoor
Three phases, Two Windings,
Transformer type
oil filled
Transformer Capacity 9.5 MVA
Voltage ratio 110/8 kV
Total transformers provided 1
will use the same line as used per Zoti HPP for power evacuation.
grid considers a 6 km length 110kV transmission line until Zoti switchyard and afterwards it
will rise up to ~3,4 millions of Euros. Similarly, the connection of Kvirila HPP to the National
Kvrila Dam. Contrarily, assuming that any roads are built in the area the amount of the item D
access roads until Kvirila intake. From Kvrila intake only 1.43 km of road are needed until
The expected investment costs presented in Table 23 consider that Zoti HPP will provide the
103 €
Civil Hydromechanical Mechanical Eletrical Total
Works Works Equipment Equipment
Part C Part H Part M Part E
A Total Construction and Equipment Costs 3,555.0 602.1 1,585.1 2,834.0 8,576.3
Rate with respect to total cost A 41.5% 7.0% 18.5% 33.0% 100.0%
B Reimbursement for Land Acquisition --- 1.3
C Reimbursement for Resettlement --- -
D Accesses (roads, bridges, tunnels) --- 400.0
E Various Expenses 0.8% 68.6
F Investigations 1.0% 85.8
G Feasibility Study, Final Design and Tendering 2.0% 171.5
H Design, Supervision and Administration 7.0% 600.3
I Connection to the Electrical National Grid (6 km) --- 1,500.0
63/65
ENERGO-PRO, Zoti HPP Georgia
Basic Design Report 64/65
HPP "Kvirila"
3
Total Construction and Equipment Cost 10 € 8,576.30
Civil 103 € 3,555.03
Hydraulic Steel Structures 103 € 602.13
3
Mechanical 10 € 1,585.10
3
Electrical 10 € 2,834.04
3
Total Cost various 10 € 2,827.51
3
Total Investment Cost 10 € 11,403.81
3
TOTAL ANNUAL COST 10 € 1,778.60
13.5 Conclusions
Kvirila HPP, combined with Zoti HPP presents a prime cost of energy of 51.3 Eur/MWh.
Considering the whole cascade the weighted average results in 49.0 Eur/MWh, which means
0.62 % more of the Zoti HPP alone, but with an increased average annual energy production of
15% (225.1 + 34.7 = 259.8 GWh).
AF-Colenco Ltd
Hydropower Department