Sie sind auf Seite 1von 14

Demystifying Grey Areas in the Application of Variation Clauses

Under FIDIC Based Standard Form of Contracts in the Gulf Region

by
Dr. Chandana Jayalath

‘Variations’ has become a subject of daily


'Most of the employment given to the negotiation in any typical construction
legal profession by Engineering work contracts. Usually, the clause 51 defines a
is to do with disputes about variations’ variation as any change in form, character,
(Engineering Law and ICE Contract, kind, quality, quantity, line, level, position,
Abrahamson, 1979). alignment, or dimension of existing work
or any additional work that the Engineer
1. Background finds necessary, appropriate or desirable to
complete works. Since any ‘standard’ form
Although the majority of contracts in of contract provides only a basis for
the Gulf region maintain the principle administering variations, it is important
features of the FIDIC forms of that the parties fully understand the
contract, there are many subtle changes generality of variation clauses and the
from the FIDIC forms of contract, that variety of broad interpretation that exists.
imbalance the even risk allocation
between the parties. Many contracts 2. Validity of Variations
we come across have been drafted with
one sided language biased towards the It is fundamental that the parties are only
clients after a cut and paste exercise. bound to perform what is stipulated in the
The message to Contractors entering document they sign. Unless there is an
into contracts on the basis of these express provision allowing alterations to
forms is to review them very carefully be made during the course of the contract,
before signing without being fooled the Contractor cannot be compelled, for
into thinking they are simply the example, to perform additional works and
FIDIC versions. the Employer cannot, without being in
breach of the contract, omit any works that
Although it is advised by FIDIC not to have been agreed. Variation clauses
alter the General Conditions, but use introduce much needed flexibility into the
the particular conditions, it is found somewhat rigid rules that otherwise govern
that the clients do use their own the parties’ obligations arising under
‘standards’. This paper is not however building contracts. One of intents in the
to address each and every customized clause 51 is to enable the Engineer to vary
clause but to describe salient features, the works, under the contract and not in
the purposes, limitations, and the role the contract.
expected by the parties, as far as
variations are concerned1. The reader A valid Engineer’s variation instruction
is advised not to depend on the however must meet the following
numbers assigned to clauses, such as requirements;
51.2, 51.4 etc but understand the
principles behind the clauses. • It must be in writing or orally and
subsequently confirmed in writing;
1
It is clause 51 allocated for variations in
almost all contracts amended on the footings
of the FIDIC.

i
• Be in respect of the form, quality or information and not known until work is
quantity of the works or any part of the carried out. Similarly the length of piles
works; and driven to a specified depth may not be
known precisely at each pile location.
• In the Engineer’s opinion, be
necessary or be otherwise appropriate; The most glaring anomaly in lump sum
contracts is related to quantities. The risk
A variation instruction does not of errors may be either fallen into the
automatically entitle the Contractor to Contractor or the Employer. The chances
additional payment, but once it is to alter quantities are remote even in a
validly given, the Contractor is under substantial variance. A clause is that
an obligation to perform it. The requires the Contractor to consider b/q
circumstances where the Contractor quantities as actual and correct and any
may reasonably object a variation error or omission from the b/q provides no
order is addressed later in this paper. grounds to adjust the contract price
(penalizing for someone else’s mistakes).
3. Mistakes in Bill of Quantities In contrary, another clause is that vests
(B/Q) and Apportionment of powers to the Engineer allows room for re-
Liability measurement where the Engineer can
order increase, decrease or even omit
The use of a B/Q in a contract requires works, thereby determining the amount to
the responsibility for the consequence be adjusted in the contract price.
of the following risks to be defined,
independently of the effect of Mistakes in the bill descriptions or
variations to the Contract. quantities are unlikely to be remedied as a
legal rectification of the terms of the
(a). The preparation of the B/Q may be contract to reflect the true intention of the
incorrect, with items omitted which parties. The more likely practice is that the
should have been included in the tender price prevails rather than a price
tendered Bill for the original work revised to account of the error.
described in Drawings and
Specification; Although quantities are so-called ‘actual
and correct’, Contractors claim new rates
(b). The final quantities of work for an when quantities substantially vary when
item may be different to the estimate in the B/Q quantities are wrong. Contracts
the tendered documents (theoretical vs based on firm quantities are in essence
actual). lump sum contracts, where the quantity
risk is transferred from the Employer to
The change in the final quantities of the Contractor. Although the burden of
work for an item may so upset the quantity risk lies entirely with the
balance of resources and method of Contractor in typical lump sum contracts,
working resulting in the unit price a question is why the Contractor is held
inaccurate. The actual quantity of work liable for missing items and errors in
for an item may differ from the quantities prepared by an outsider. Many
estimate at tender for a number of contracts are silent in this issue.
reasons. In the case of excavation for
instance the removal of unsuitable
material or the extent of rock or the The Consultant shall be held liable for
extent of tunneling in particular quantity errors in case the Employer
classifications of ground, may only be becomes vicariously liable. A specific
estimated from ground investigation remedy would be to cover up this scenario

2
in the insurance policy. There should 5. Methods of Valuation
be a B/Q provision for the tenderer to
adjust the quantities when he finds any The clause 51 has two tiered approach to
missing, under measured or over the valuation of variations;
measured item so that he takes the
burden before the contract is entered 1. B/Q rates
into. 2. fair rates

As a matter of business efficacy, a Which of the above "Rules" will apply


term will be implied (in the absence of depends largely upon the timing of the
express terms) that the cost of the work variation order, the location of the work,
for a Bill item which has not been the quantity involved and the
priced by the Contractor is included in circumstances in which the work is
the prices entered elsewhere in the Bill. executed. If it can be established that these
factors preclude the valuation on the basis
4. Power of Engineer to Fix Rates of bill rates then the valuation will usually
be based on fair rates. If the varied work is
We often find a clause vesting some of a similar character and executed under
powers on the Engineer to form an similar conditions to work priced in the
opinion as to suitability and B/Q, such rates and prices shall be used to
applicability of a new rate and the limit value the varied work. The factor of profit
of enhancement of an existing bill rate. or otherwise of the rate is immaterial.
The Engineer shall determine the
suitability of the new rates based on If the varied work is of a dissimilar
the nature and amount of the subject character or is executed under dissimilar
omission or addition against the nature conditions to work priced in the B/Q, then
and amount of whole of works. the rates and prices shall be used as the
Broadly speaking, the varied work basis of valuation so far as may be
shall be priced in accordance with the reasonable. This rule applies where the
rates and prices in the contract, but if work covered by the variation order is of a
those are not applicable, the Engineer different character from the work priced in
has the power to agree rates and prices the B/Q, or is executed under different
with the Contractor. If no agreement is conditions. If the differences are relatively
reached, the Engineer has the power to small, the Engineer is generally obliged to
fix what he considers suitable. use the rates set out in the B/Q as the basis
Because the valuation of varied work for his valuation, making such adjustment
can be fertile ground for argument, if a in proportion to take account of the
Contractor disagrees with the differences. If the differences are very
Engineer’s determination on rates or great, such as where excavation is to be in
prices, he can still refer the issue to the rock instead of clay, the Engineer may
Engineer once again prior to invoke take the view that it would not be
the dispute resolution procedure. This "reasonable" to base his valuation on the
can be considered as an extra rates contained in the B/Q. The sole
contractual opportunity available for function of the words "as shall in his
the parties to avoid disputes. opinion be reasonable and proper” calls
for a comparison between the work
covered by the variation order and the
work priced in the Bill of Quantities.

3
The words do not enable the Engineer Absence of contemporary records amounts
to open up or disregard the rates on the to a situation where the Engineer shall
ground that they were inserted by make his own assessment based on
mistake. “It was the use of the rates in information available to him and as he
the changed circumstances brought feels reasonable. Items covered by pricing
about by the variation order that must preamble notes or descriptions in the bill
be reasonable, not the rates item provide no entitlement.
themselves”2. Considerations arising out of
specifications, pre-contract addendums,
A fair valuation generally means a manufacturing instructions and any minor
valuation which does give the details necessary for completion of work
Contractor more than his actual costs though not specified in specification or not
reasonably and necessarily incurred shown in drawings are deemed to be
plus similar allowances for overheads included within the price.
and profit3. The Engineer should
decide the suitability of rates giving Any item duplicated in re-measure and
due regard to all the circumstances superseded or rescinded by a subsequent
involved. instruction shall be ignored. Any work,
which exceeded the scope required by the
On the matter of overheads, a variation order, is considered as overwork.
distinction had to be made between Unless otherwise stated, any discount or
different elements of overheads. Some correction factor will be applied for the
overheads such as home overheads original works as set out in the bill of
were constant and not related to basic quantities. Variations valued as per bill
costs, unless brought into an rates will also be subject to discount. This
assessment of the cost of prolongation factor is proportionately applicable for the
by reference to the basic costs. Other measured items under appropriate bills
overheads are directly related to value unless any specific mention as to contrary
of the work. Some overheads will only has been made at the tender.
be recovered if there was proof that
they were in fact incurred or increased, 6. Economic Duress
as they will have been recovered from
valuations of the work executed. A fair The parties are the masters of their own
valuation has a contribution towards contractual fate. Indeed, the courts are
fixed or running overheads. Unlike normally slow to interfere in agreements
time-related overheads, it was not reached between two parties, but they will
necessary to prove that they were interfere in agreements procured by the
actually incurred for the purpose of a exertion of economic duress by one party
fair valuation. Hence, it is advisable on the other. Variations for instance issued
that a uniform mark up component is from time to time in connection with
always determined on the tender price variations to the contract are the subject
breakup4. matter that the Engineer should take a
middle position in interpreting them.

The ingredients of actionable economic


2
duress are as follows;
Lovell White Durrent (1999) How to Value
Variations, Judicial Guidance, CSM, February
2001, RICS a) There must be pressure whose
3
Roges Button and Richard Mills (2001) The practical effect is that there is compulsion
Fair Valuation of Variations, CSM, March 2001, on, or a lack of practical choice for, the
RICS. “victim”; and
4
Be noted there are exceptions to this ruling.

4
After receiving a tender from Henry Boot
b) The pressure must be and before execution of the contract,
illegitimate and a significant cause Alstom decided to lower the cold water
which induces the “victim” to agree to pipework. Henry Boot wrote advising of
enter into the agreement. its change in price for additional and
different temporary works. The change in
So what behaviour will amount to price was £250,880. Alstom sought
“illegitimate pressure” in the context of confirmation of the extent of the price and
a construction contract? Examples Henry Boot stated that
might include a threat by a sub-
Contractor to withhold the delivery of "The sum of £250,880 was to allow for
a crucial piece of plant or equipment additional and different temporary works
until an extension of time is granted or only, required in the Turbine Hall due to
the sub-contract price is increased. the lowering of Bonna pipe-work in this
Conversely, it might include a threat area."
by a main Contractor to refuse to grant
the sub-Contractor an extension of The tender was accepted including the sum
time (and to apply LDs for delay), of £250,880. In the subsequent arbitration
unless the sub-Contractor agrees to it was found that the sum of £250,880
carry out a substantial variation at covered the cost of additional temporary
minimal cost. Another classic case is works in the Turbine Hall, but not in the
when the Engineer unilaterally fixed a HGSR area and still less in the cooling
rate for a new work without giving the towers. The former was to be corrected as
Contractor a chance to negotiate. an omission from the Bill of Quantities
under Clause 55(2) and the latter the
subject of a variation order under Clause
7. Henry Boot Vs Alstom (2000) 51(1). The issue therefore was whether the
sum of £250,880 was to be used to value
Henry Boot was the civil Engineering the variation for the temporary works in
Contractor for a combined cycle gas the cooling towers.
turbine power station being built by
Alstom at Connah's Quay in Clwyd. The Arbitrator found that Henry Boot had
The contract dated 21st March 1994, calculated the sum of £250,880 by
incorporated the ICE Standard reference to the estimated quantity of steel
Conditions of Contract, 6th Edition (let sheet piling required in the HRSG area as
us understand the principles). The well as the Turbine Hall. By mistake henry
power station consisted of four gas boot’s fax referred only to the Turbine
turbines each with its own heat Hall and the mistake was not picked up by
recovery steam generator. The gas Alstom. If the sum of £250,880 was
turbines were situated in the Turbine divided by the amount of sheet piling
Hall and the steam generators in a required in the Turbine Hall it gave a rate
separate area known as HGSR. The of £89 per square metre. When the rate
cooling towers were separated from the was applied to the sheet piling in the
HGSR by a road, and cooling water HGSR it gave a sum of £231,226 and
pipes were used to condense the steam. when applied to the area of the cooling
The condensed water came back to the towers it gave a sum of £2,284,128. These
HGSR where it was turned back into were the sums claimed by Henry Boot,
steam by the exhaust gases from the whereas Alstom argued that the sum of
gas turbines.. The system was therefore £250,880 should not be extrapolated in this
a combined cycle power plant. way since it produced a "windfall gain".

5
The second rule in Clause 52(1) work covered by the variation order and
provides that the rates and prices are to the work priced in the Bill of Quantities.
be used as the basis for valuation "so The words did not enable the Engineer to
far as may be reasonable". The open up or disregard the rates on the
Arbitrator decided that it was ground that they were inserted by mistake.
reasonable not to use a price where the It was the use of the rates in the changed
price has been reached by a mistake or circumstances brought about by the
error. He therefore declined to adopt variation order that must be reasonable,
Rule 2 in the valuation and adopted the not the rates themselves.
third rule of "fair valuation". HH
Humphrey Lloyd QC allowed an It was also held that Clause 52(2) created a
appeal against the Arbitrator’s decision limited exception to Rules 1 and 2 where
and remitted the award back to the the scale and or nature of the variation
Arbitrator with a direction to make a makes it unreasonable to use the contract
valuation under Rule 2 using the sum rates. It was an exception that proved the
of "250,880 for sheet piling work in general rule that the rates could not be
the Turbine Hall. displaced because they were inserted by
mistake or were too high or too low or
The issue then was the meaning and otherwise unreasonable. The same applied
application of the second rule in to Clause 56(2) which enabled the
Clause 52(1) in the valuation of Engineer to increase or decrease the rates
variations, where the applicable rate where the actual quantities executed for
was known to contain a mistake. The the item were greater or less than those
first instance decision was upheld by a stated in the Bill of Quantities. These
majority. exceptions underlined the basic rule that
the rates themselves were not subject to
Lord Justice Lloyd held that Rule 2 correction.
provided a half-way house between
Rule 1 and Rule 3. Like Rule 1, Rule 2 Lord Justice Beldam agreed with the judge
is mandatory. It applies where the at first instance and Lord Lloyd. He held
work covered by the variation order is that Clause 52(1)(b) contemplates cases in
of a different character from the work which it would not be reasonable to use
priced in the Bill of Quantities, or is the rates and prices in the Bill of
executed under different conditions. If Quantities. It was the reasonableness of
the differences are relatively small, the using the rates and prices and not the
Engineer is obliged to use the rates set reasonableness of the rates and prices,
out in the Bill of Quantities as the basis which has to be considered.
for his valuation, making such
adjustment as may be necessary, to 8. Tender Price Break-up as a Tool
take account of the differences. If the
differences are very great, such as To facilitate the evaluation of actual and
where excavation is to be in rock correct quantities of work, the Contractor
instead of clay, the Engineer may take is required to submit a detailed breakdown
the view that it would not be of tendered lump sums and unit rates as
"reasonable" to base his valuation on required by Instructions to Tenderers.
the rates contained in the Bill of Such breakdown, though required by the
Quantities. He then must adopt Rule 3. contract is not itself a contract document
It was held that this was the sole and will be considered as a guide only.
function of the words "so far as may be The receipt of the breakdown in no way
reasonable" in Rule 2. The words implies acceptance of figures and the
called for a comparison between the Engineer reserves the right to amend or

6
modify them as and when he deems it 10. Loss of Profit against Omissions
necessary.
Whenever variations are ordered that omit
The tender price break-up to be work under clause 51, and particularly if
submitted before or after the contract such omitted work is substantial in
has been let is not, per se, a contract quantity, Contractors often argue that they
document. It is to be used, wholly or should be entitled to claim loss of profit
partly, as a guide in pricing variations, that they would have been earned on such
and remains subservient to the works if carried out. If the variation
requirements of the contract. Errors, omitting works is invalid5 then such is a
omissions oversights within the tender breach of contract entitling the Contractor
price break-up do not prove particular to damages, and loss of profit can form
inclusion or exclusion within the part of such a claim for damages. Where
contract sum. The nature of the the works have been omitted and given to
inclusions within individual tender others to carry out, it is clearly established
rates and prices are determined by the that it is a breach of contract and not a
conditions of contract, not by valid variation order. Gallagheer v Hirsch
Contractor’s subsequent break-up. No NY App Division 467 (1899) where the
Contractor can be permitted to use his American court held that the word
lack of compliance with tender ‘omission’ meant only work not to be done
requirements to maneuver to his own at all, not work not to be taken from the
advantage. Contractor and given to another to carry
out.
9. Valuation of Changes in
Measurement It could be claimable if the Employer
himself or another Contractor carries out
Generally, the Contractor is entitled to any omitted work whilst a contract exists
assume that the B/Q has been prepared without consent of the Contractor or unless
in accordance with SMM and that the it can be proved that the Contractor is
items and quantities found in the Bill technically or financially incapable of
of Quantities are reasonably accurate carrying out such omitted work. However
descriptions and estimates of the work in contracts, we find the Employer has the
shown on the Drawings and described right to omit a part of the scope and get it
in the Specification. The B/Q may not done by another Contractor under a
have been prepared in accordance with separate contract. However the Employer
the Standard Method of Measurement is entitled to entertain the benefit a valid
(SMM). The risk of inaccuracies in omission, despite of the appointment of
bills has fallen on the parties on the another Contractor. If the nature and scope
level of estimation done by a third of omission renders the existing rates no
party. Any error or omission provides longer appropriate, the Engineer has the
no grounds for adjusting the contract power to adjust it to an appropriate extent
price under lump sum contracts. in such a way that the Contractor obtains a
reasonable compensation.
The varied work should also be
measured in accordance with the
standard method of measurement
adopted in the preparation of contract
bills to maintain the uniformity in the
total contract.
5
The Employer has absolute immunity under
clause 51.1 against any claim for loss and profit
due to omitted work.

7
11. Effect of Unrealistic Rates in substantial increase or decrease in
Changes of Quantities quantities which render the existing rate
unsuitable.
Clause 51 requires variations to be
priced as per bill rates presumably for Keating on Building Contracts Fifth
works of similar nature executed under Edition as at page 523 suggests the
similar conditions. The key question is following matters be taken into account
whether it is reasonable to use bill rates when deciding whether conditions are
to value changed quantities when the similar.
rate contains an admitted error.
a. physical site conditions such as wet
The court of appeal in ‘Henry Boot vs compared with dry
Alstom (2000)6 found in favour of the b. confined space compared to ample
Contractor and emphasised the fact working space
that bill rates, which contained an c. winter working compared to
error, should not prevent them from summer
being applied to the additional work as
well. (In this case, it was an over The following matters should be taken up
pricing – see section 7). when deciding whether work is of a
similar character.
If the Contractor put an unrealistically
high rate, he is entitled to have the rate a. functions of materials
used for valuation of subsequent b. size and shape
variation. “When the Employer c. vertical, horizontal and sloping
accepted the tender with the d. location
unrealistically high rate, it can be said
that the Employer accepted also the However in either of these operations the
risk of that being used in valuing fact that a rate or price may be too high or
additional quantities”7. The application too low is completely immaterial. A very
of the contract rates can not be avoided high rate or a very low rate is not rendered
simply because one party is dissatisfied unreasonable by a variation or a
with them. The contract rates are substantial change in quantities but is
immutable, and not subject to already unreasonable when the contract is
correction. There shall be no entered into.
rectification of any error, omission or
wrong estimate in the descriptions, Alternatively, the Contractor has included
rates and prices inserted by the an unrealistically low rate in the bill of
Contractor. The effect of this principle quantities; such rate could be applied to
is that a mistake in a rate is bound by the extent of bill quantities. Any excess in
the parties equally. The only situation quantity over and above bill quantity shall
where a contract rate may be departed be paid at a fair rate. However the
from which it is not executed under conditions provide no room for the
similar conditions or when there is a Contractor to demand an enhanced rate
even where the actual quantity is of a
6
substantial increase. 8.
John B. Molloy (2001) Henry Boot
Construction Ltd vs Alstom Combined Cycles
Ltd. A most important case, Roger Knowles,
March 2001.
7
John B. Molloy (2002) Unrealistic Rates in Bill
of quantities, Roger Knowles, July 2002.
8
Nevertheless, the Contractor may lodge an ex-
gratia claim.

8
12. Limitations in the Issuance of references, detail cost break-ups,
Variations quotations approved etc, that provide
documentary evidence. In all contracts, it
The existence of a variation clause is essential to have a clear picture of
does not entitle the Engineer to make deductions and additions compared to the
large scale or significant changes to the original scope.
nature and scope of work. A variation
order that deviates from the The Contractor should establish
fundamental scope, nature, type or entitlement and then compute the
complexity of work contemplated by additional cost and time, giving due
the parties at the tender affects the reference to the contract and taking all the
validity of the contract. The Engineer circumstances into account. The Engineer
should not introduce work outside the should highlight the works omitted as
domain of the original job, which well. The Consultants should prepare his
would cause hardship to the Contractor own calculations in absence of Contractor
in terms of finance and technical records.
capacity. The criteria to evaluate
whether a change is a variation could
be the cost of work, scope of work, 14. Pending Site Instructions
technical input required, etc. Hence,
the Engineer shall make any variation It is also seen that the Contractor delays
under the contract and not in the the start of work in connection with
contract. All variations shall be variation till he gets the rates agreed and
considered in ascertaining the contract considers the date of formal instruction in
price. As a principle, no variation to writing as the date of issue of instruction
the contract can be made by the when calculating time extensions. This
Contractor. This does not however belief is wrong. As per clause 51, the
restrict the Contractor to submit at any Engineer can give oral instructions and the
time to the Engineer value Engineering Contractor should not await till he gets it
proposals which in the Contractor’s formally in writing in order to start work,
opinion will if adopted; rather he should confirm the recognition of
such instruction in writing to the Engineer,
a. accelerate completion. and immediately proceed to carry out such
b. reduce cost to the Employer in instructions. If such confirmation is not
executing, maintaining and contradicted by the Engineer, such
operating works. instruction is deemed to be a formal
c. improve efficiency. instruction of the Engineer, albeit a
d. enhance the value of completed deadline is not specified. Hence, the
work. conditions are clear enough establishing
e. otherwise be of benefit to the the validity of the Engineer’s order to
Employer. commence work.
13. Variation Claims and their The Contractors however feel hesitant to
Backups start work without getting prior approval
on the cost because of the fear of not
Claims without backups in order are getting the full entitlement under payment
also commonplace. Backups means procedures, which are usually prolonged.
interalia the copies of site instructions,
confirmation of verbal instructions, Any instruction that the consultant thinks
copies of drawings and sketches, will take additional cost and/or time
relevant pages of specifications, BOQ should accompany with a tentative budget

9
estimate before issuing the same to the therefore constituted a separated contract.
Contractor. The date ever first the When a large number of changes are
Contractor received orally any instructed though they individually fall
instruction is the effective date of within the ambit of the variation clause,
instruction unless otherwise stated. For they can collectively have the effect of
planning purposes, it is the date the completely changing the scope of the
Contractor is actually supposed to works. This is referred to as either
commence the varied work. abandonment or cardinal change and deals
with the situation where the Employer
makes excessive changes to a project
15. What Constitutes a Separate beyond what the parties reasonably could
Contract? have anticipated at the time the contract is
entered into. Courts will look at a number
There may be circumstances which of factors in helping to decide whether the
could lead to changes introduced by changes have been excessive such as the
the Engineer falling outside the size, nature, complexity, expected duration
variations clause. Contractors who find the number of changes, how many changes
themselves with unattractive contract were anticipated when the project started,
prices would find it arguable that a the magnitude of the work involved in the
change introduced by the Engineer fell changes and the length of time in which
outside the variation clause thus the such changes were made etc.
payment for the change should be on a
quantum meruit basis. In Blue Circle A misunderstanding is that the Engineer
Industries v Holland Dredging Co can issue any number of variations for any
(1987), the works involved dredging in purpose. Even where a contract includes
Larne Lough in Ireland to enable larger the usual variation clause there may be
vessels to dock. The tender referred to circumstances which could lead to
the dredged material being deposited in additions or changes introduced by the
areas approved by the public Employer which falls outside the
authorities, the intention being to variations clause where the payment for
discharge the material excavated in the change should be on a quantum meruit
suitable areas in the Lough. Larne or fair valuation basis. It can be argued by
Harbour Board rejected this proposal the Contractor that this is not a variation to
later and as a result an alternative plan the works within the confines of the
was agreed to use the excavated contract but a separate contract in its own
material to form an artificial bird right, because the additional work were so
island. It was argued by the Contractor peculiar, so unexpected and so different
that this was not a variation to the from what was contemplated by the
works within the confines of the contract.
contract but a separate contract in its
own right. It was held that if the
Also, the Engineer is under liability in the
additional or varied work were so
issue of variation orders, particularly the
peculiar, so unexpected and so
concessions granted for the Contractor.
different from what any person
Even if the Engineer’s permission for a
reckoned to such an extent that it is not
change is fully authorized, the Engineer is
contemplated by the contract then it
not freed from his general duty to the
would constitute a separate contract.
Employer to exercise reasonable care and
Hence, the construction of the bird
skill. If the change does later cause the
island was wholly outside the scope of
Employer loss, the Engineer may face
the original dredging contract and
reciprocal claim from the Employer.

10
17. Dilemma between Tender Rules and
16. Significant Quantity Changes Variations Exceeding 20%

There is a belief that the Contractors The issue of 20% variations may also
are entitled for revised rates when the revolve around the Instructions to
contract value exceeds 20%. Tenderers where the Contractors argue that
they have the right to claim new rates once
Instructions to Tenderers in some the value of works has been exceeded by
contracts specify that the Employer has 20% of the contract sum. Generally, the
a right to vary the works upto 20% of Instructions to Tenderers are related to
the contract sum. It does not mean that tender stage carrying directions to
the Contractor has a claim when the tenderers how to submit their offers. Also,
overall scope exceeded 20%, rather it no party can impose conditions each other
gives an ‘ámberlight’ for the parties to after entering into the contract without
reconsider the rights to have variations mutual consent, for instance tender and
issued and executed. auction regulations do not govern the
contracts but the tenders. The Engineer
It should also be noted that the 20% is and Employer may of course strictly
the percentage deviated from the follow such regulations and refer the
adjusted contract sum giving the net tender committee at the defined limits of
resultant effect on the contract sum values prior to issue instructions to the
purely on variations and not on any Contractor.
individual varied item. This is possible
only at the practical completion.
Accordingly, parties must understand The impression given by some instructions
that there are two separate scenarios; is that the Employer has the right to
change in quantities in individual B/Q increase or decrease work, upto 20% of the
items, and the overall change in contract sum, but not beyond. It also does
quantities exceeding 20%. not address what will happen when the
limit exceeds. It is therefore true to have a
If the nature or amount of the work fear of not getting approval for the varied
involved differs so much from that work by the Employer who is not legally
included in the original contract that capable of going beyond this limit, from
the rates and prices are rendered the Contractor’s point of view. Further, the
inapplicable, it is the Engineer's task to Contractor may or perhaps do use this
agree appropriate rates and prices with opening to cover up their losses due to
the Contractor, or, if agreement cannot open market price increases as well as any
be reached, to fix the suitable rates and item quoted unrated in the tender, in spite
prices under clause 51. The of whether a separate mechanism is in
circumstances that rendered existing effect or not.
rates inappropriate are a matter of
interpretation. Care must be taken that the Employer’s
right to issue variations upto the limit of
Any adjustments due to overall 20% original contract sum is different
variance shall be applicable only for from the variations exceeding 20% for the
the percentage deviated (eg, only 5% is compensation of unabsorbed overhead due
subject to adjustment if overall to adjustment of quantities and varied
deviation is 25%). work. The first limit could be during the
progress of work while the second only at
the practical completion. The first explains

11
the Employer’s right while the second the ignorance when some works omitted at
deals with the Contractor’s entitlement. the last lap of the project so that the net
Parties tend to refer FIDIC in silence in resultant impact is not necessarily
some contracts. The clause 52.3 of exceeding 20% but still the Contractor
FIDIC 4th edition says if it is found that may have a case validly submitted under
the limit has been exceeded on the the grounds of some tender regulations.
issue of the Taking-Over Certificate The power to control variations gone into
for the whole of the Works, the the hands of the Contractor is not at all
contract sum to be adjusted having practicable when the Employer badly
regard to the Contractor’s Site and needs some varied work inevitable for the
general overhead costs. This Sub- completion of the works. There is no limit
Clause allows the Contractor and defined in the contract for the Contractor
Engineer to discuss and agree a lump to stop work or object compliance with the
sum addition or deduction to the instructions to variations (except the
Contract Price at the practical circumstances we noted above).
completion when the
additions/deductions as described at (a)
and (b) are more than 15% of the The issue becomes worse with the goes
"Effective Contract Price". It will be onto say that the Employer has the right to
up to the Contractor to prove the vary works upto 20% of the contract sum
changes to his Site and general at the same rates and prices applicable to
overhead costs. The burden of the the contract. This again sparks a claim as it
proof lies upon the Contractor who gives formal warranty for the Contractor
affirms, not the other who may deny. to lodge a claim for rate revision, which is
Hence, the details and calculation of against the valid reasons for rate revision
the lump sum will entirely dependant given in the clause 51. A rate revision can
on the technical reasons for the be made only on the circumstances that
increase or decrease to the Contract rendered the existing rates unreasonable or
Price. inapplicable (due to nature and amount of
any omission and addition compared with
The whole idea is to compensate the the nature and amount of whole of the
Contractor for any unabsorbed contract work or to any part thereof). A
overhead component due to rate would even be reduced perhaps in a
overwhelming decrease or increase of typical civil Engineering work where the
such work where his overhead would rates could be much more profitable owing
have been expended more and his to economies of scale whenever the
profit would have been exhausted more quantities are overwhelmingly increased,
in proportion to what he had planned although many Employers are not looking
and contracted with, and vice versa for from that angle.
the Employer.
Let me present 2 cases under lump sum
It is also not reasonably inferable that
situation.
the Contractor has the right to refuse
any variations beyond this limit,
Case 1 :
except in a circumstance where the
instructed new work fall out of the
The ducts for underground electrical
contract domain because the additional
cables at 600mm level shown in tender
work were so peculiar, so unexpected
drawing No E-00 were not mistakenly
and so different from what was
measured in the b/q. The revised
contemplated by the contract. A
construction drawing No SD-E00
glaring anomaly of this instruction is

12
superseded the scope of work signing the site instruction argued that
envisaged in the tender drawing No E- dewatering is an integral part of
00. This paved the way for adjusting excavation that cannot be separated from
the contract sum as a valid variation excavation item and hence, the contract
under the contract as per clause 55, sum can not be adjusted. He further added
which involved omission and addition that he did not receive soil report at the
of the scope shown the drawing No E- time it was priced.
00 and SD-E00 respectively. The
Contractor argued that omission from Notwithstanding the extent of availability
the bill of quantities is not possible in of information related to tidal movements,
absence of a B/Q item. However, the type of soil, water table etc or the pricing
logic is that the tender shall be strategy adopted in the tender, the entire
comprehensive enough to cover up all obligation falls on the Contractor to make
the obligations under the contract as his own interpretation as to the nature and
prescribed in the contract documents extent of work involved in both temporary
including drawings, irrespective of and permanent works. Such a technical
whether a particular item of work has judgment is a sole prerogative of the
been included or excluded in the bill of Contractor for which the Employer is not
quantities unlike in a typical measure liable under whatsoever circumstances
and pay contract. The Contractor shall except in cases where the Contractor is
also be deemed to have satisfied able to justify that the Employer is at
himself before tendering as to default, such as failure to provide accurate
correctness and sufficiency of the information timely whenever expressly
tender for the works as per clause provided for in the contract.
12(1). Accordingly, the cost on PVC
ducts shown in tender drawing is The Engineer found no such record of
deemed to be priced within the tender. request or qualification during the tender.
The Contractor has neither made any
Having subsequently altered the provision in his clause 14 program nor in
subject scope by the above revised the methods statement as to how he
drawing constituting a variation to the intends to deal with the issue of
contract as per clause 51(1), the dewatering. The section B for
Engineer ascertained by ad- preliminaries in which the tenderer has an
measurement the net resultant value of opportunity to identify the items not priced
the respective work as per clause elsewhere in the b/q also had a zero value.
51(3). All such works were valued at Nothing has been executed physically later
the rates set out in the contract in order at site with regard to control of ground
to maintain the tender pricing level. As water such as installation of standpipes
such, the deduction made for omission and other devices as specified, altogether
for which the price is already catered revealing lack of compliance/emphasis on
for was contractual. the subject issue at the time of tender.

Case 2 : Nonetheless, the Contractor shall be


deemed to have satisfied himself before
Dewatering is an existing b/q item, tendering as to correctness and adequacy
quoted as a lump sum, but not of the tender for the works as per clause
prevailed at site. Hence, the Contractor 12(1), bearing in mind that pricing risks
was invited to sign the original copy of are inherent in any typical lump sum fixed
the site instruction as a formality to price contract. As such, the tender sum
omit dewatering from the scope of shall be comprehensive enough to cover
work. The Contractor regretting up all obligations under the contract as

13
specified in drawings, b/q and firm price contracts, the Engineer
specifications etc. Without prejudice to ultimately sits in a strong position to
the primary intention of the contract, convert the whole scenario into a
the Engineer reserves the right to vary traditional form of measure and pay.
the works within the meaning of clause Variations and measurement clauses are
51 (1). The distinction is made in evident enough. Indeed, computing a
clause 55, where any error or omission realistic value for variations is often not an
from the bill of quantities shall provide easy task. The parties need a considerable
no grounds for adjusting the contract knowledge, skill and exposure in the art of
price. In contrary, omission of an judgment in order to have a sound
existing b/q item is defined as a appreciation of the methods of
variation as per clause 51(1) and construction, estimating practice,
thereby provides grounds for adjusting contractual implications, construction
the contract price. This deletion is thus programming techniques and most
contractually valid and the power to do importantly the records intact.
so has been vested in the Engineer as
per said clause. Compromise is possible on a give and take
policy without prejudice to the contract
Further, the Contractor’s price against terms, accepted standard norms and
each bill item shall truly reflect the professional ethics. A more rational
value of the item described as noted in approach will enable the parties to use
pricing preamble. Any individual b/q variations as a fast track mode of
item that is itemized and separately procurement also.
measurable or payable, apart from
other pay items operationally or
otherwise integral, incidental or
associated with it can be assessed in
full at the existing contract rate/s Chandana Jayalath, DSc, MSc, PG Dip,
according to its occurrence. The BSc(QS)Hons, MRICS, AAIQS, AIQS(SL)
dewatering in this particular instance is is a Chartered Quantity Surveyor working
an independent bill item of that on free lance basis, contactable over
category that did not prevail at site at jayalathchandana@gmail.com
all, so is apparently a subsequent
variation under the contract by a
complete omission, the benefit of (This paper has been prepared for the
which shall be retained by the Continuing Professional Development
Employer. Under circumstances, the Program at the Baan Saeng Thai
Engineer found no strong valid Auditorium on 3 April 2009 organized by
technical or contractual basis to justify the SLQS Bahrain. The foregoing opinions
why the Employer is liable for related to the subject paper belong to the
payment for dewatering. Author and do not represent the issuing
authorities of the subject conditions and
18. Conclusion not to be taken as interpretation to a given
issue).
‘Variations’ has long been recognized
as a major source of conflict in
construction projects. A one of reasons
is the decisions heavily influenced by
subjectivity that differs from one
person to another. My view is that
even under the label of strict lump sum

14

Das könnte Ihnen auch gefallen