Beruflich Dokumente
Kultur Dokumente
SURATHKAL
Submitted By:
Submitted To:
Prof. K. Swaminathan,
Department of Civil Engineering
NITK Surathkal
Content
5. Methods of pre-stressing
6. Applications of pre-stressed elements in civil Structures
16. References
Introduction to Pre-stressed concrete
The need for pre-stressing in concrete can be justified by the following issue:
5. The full capacity of the concrete in compression can be used over entire depth under
full loading in the case of pre-stressed concrete.
Methods of Pre-stressing
The following are the two methods that are followed for pre-stressing: -
1. Pre-tensioned concrete
2. Post-tensioned concrete
Pre-tensioned concrete
Pre-tensioned bridge girder in pre-casting
bed. Note single-strand tendons exiting
through the formwork.
Pre-tensioned concrete is a variant of pre-
stressed concrete where the tendons are
tensioned prior to the concrete being cast.
The concrete bonds to the tendons as
it cures, following which the end-
anchoring of the tendons is released, and
the tendon tension forces are transferred to
the concrete as compression by static
friction.
Pre-tensioning is a common prefabrication technique, where the resulting concrete
element is manufactured remotely from the final structure location and transported to
site once cured. It requires strong, stable end-anchorage points between which the
tendons are stretched. These anchorages form the
ends of a "casting bed" which may be many
times the length of the concrete element being
fabricated. This allows multiple elements to be
constructed end-on-end in the one pre-tensioning
operation, allowing significant productivity
benefits and economies of scale to be realized for
this method of construction.
The amount of bond (or adhesion) achievable
between the freshly set concrete and the surface
of the tendons is critical to the pre-tensioning
process, as it determines when the tendon
anchorages can be safely released. Higher bond
strength in early-age concrete allows more
economical fabrication as it speeds production.
To promote this, pre-tensioned tendons are
usually composed of isolated single wires or
strands, as this provides a greater surface area for
bond action than bundled strand tendons.
1) Bridges
Of the wide range of alternative methods and materials that are available for the
construction of bridges, concrete remains the most popular structural material, and
pre-stressed concrete, in particular, is frequently adopted. When investigated in the
1940s for use on heavy-duty bridges the advantages of this type of bridge over more
traditional designs was that it is quicker to install, more economical and longer-lasting
with the bridge being less lively. One of the first bridges built in this way is the Adam
Viaduct, constructed 1946 it is the earliest railway bridge of this type in the UK. By
the 1960s pre-stressed concrete largely superseded reinforced concrete bridges in the
UK, with box girders being the dominant form.
In short-span bridges of around 10 to 40 metres (30 to 130 ft), pre-stressing is
commonly employed in the form of precast pre-tensioned girders or planks; for
medium-length structures of around 40 to 200 metres (150 to 650 ft), precast-
segmental, in-situ balanced-cantilever and incrementally-launched designs are all
efficiently constructed using pre-stressing; while for the longest bridges, pre-stressed
concrete deck structures often form an integral part of cable-stayed designs.
2) Dams
Concrete dams have used pre-stressing to counter uplift and increase their overall
stability since the mid-1930s. Pre-stressing is also frequently retro-fitted as part of
dam remediation works, such as for structural strengthening, or when raising crest or
spillway heights.
Most commonly, dam pre-stressing takes the form of post-tensioned anchors drilled
into the dam's concrete structure and/or the underlying rock strata. Such anchors
typically comprise tendons of high-tensile bundled steel strands or individual threaded
bars. Tendons are grouted to the concrete or rock at their far (internal) end, and have a
significant "de-bonded" free-length at their external end which allows the tendon to
stretch during tensioning. Tendons may be full-length bonded to the surrounding
concrete or rock once tensioned, or (more commonly) have strands permanently
encapsulated in corrosion-inhibiting grease over the free-length to permit long-term
load monitoring and pre-stressing ability.
3) Silos and tanks
Circular storage structures such as silos and tanks can use pre-stressing forces to
directly resist the outward pressures generated by stored liquids or bulk-solids.
Horizontally curved tendons are installed within the concrete wall to form a series of
"hoops" spaced vertically up the structure. When tensioned, these tendons exert both
axial (compressive) and radial (inward) forces onto the structure, which can used to
directly oppose the subsequent storage loadings. If the magnitude of the pre-stress is
designed to always exceed the tensile stresses produced by the loadings, a permanent
residual compression will exist in the wall concrete, assisting in maintaining a
watertight, crack-free structure under all storage conditions.
The maximum moment of resistance in a pole is generally required at the base and,
consequently, the maximum cross-sectional area is required at the base section. Poles
are generally tapered with hallow core to reduce the weight, which also helps in
providing a race way for electric wires.
Typical cross-sections of transmission line poles widely employed in different
countries are shown in figure 1. For small lengths of up to 12m, the square or
rectangular sections are preferable as they are easily manufactured and occupy less
space in transportation.
However, they have a larger exposed surface with thin elements and are susceptible to
corrosion, I-sections of 10m lengths have been widely used in the British railways
while V-sections have been employed in South African railways.
Tubular sections are ideally suited for longer poles. B.B.R.V.-type pre-stressed
concrete poles are manufactured in standard lengths of 9, 12, 15, and 18m and up to a
maximum diameter of 750mm using the spinning process.
Pre-stressed concrete poles
For many years throughout the world, poles made of wood, steel, and concrete have
been used to support power transmission, telephone and telegraph lines, street
lighting, overhead power lines for railroads, and antenna masts. Concrete poles were
first used over 100 years ago and were then made of normal reinforced concrete.
Pre-stressed concrete poles should not be regarded as novel or new. They were first
designed and constructed by the French pre-stressing pioneer Eugene Freyssinet in
Algeria in the middle 1930s. It was also Freyssinet who, years ago, conducted his
classic demonstration in which a
normal reinforced concrete pole and a
pre-stressed pole, designed to the same
ultimate load, were placed in a special
testing apparatus and subjected, not
only to repetition of a load equal to,
but also to alternation of a load
amounting to 50 percent of the
designed ultimate load. The normal
reinforced concrete pole failed at a few
thousand repetitions, but the pre-
stressed pole was still going strong at 5,00,000 cycles. Since this is the type of loading
that poles are expected to carry in the field, this test was of significant interest to pole
users.
The greatest hazard associated with normal reinforced concrete poles is corrosion of
steel. This leads to spalling of the concrete and, ultimately, failure of the pole. The
corrosion may be caused by insufficient cover, substandard concrete, or excessive
tensile forces, hence cracks, in handling or service, owing to poor design or to misuse.
The pre-stressed concrete pole offers the following advantages: First; the concrete
used is of a quality sufficient to resist penetration of water, otherwise the pole could
conceivably fail during the pre-stressing operation.
Secondly, in a pre-stressed pole, the concrete is usually in compression, and cracking
is not possible except under abnormal conditions of handling or service. These
characteristics give the pre-stressed pole greater advantages over the normal
reinforced pole and are the reasons for the development and use of pre-stressed
concrete poles.
They are extensively utilized in Japan and to varying degrees in many other countries
around the world. Available data indicate that the Soviet Union has produced and used
the most poles, whereas the United States and Canada have only recently initiated
their utilization.
Demand for pre-stressed electric poles
The demand for pre-stressed (Pre-cast/Reinforced) concrete-cement (PCC) poles
directly depends on the growth of electric power sector. Because these poles are solely
meant for overhead transmission and
distribution of power to consumer units. The
growth in generation and supply of electric
energy gives rise to demands for PCC poles
& other systems by way of OEM &
replacement/renovation demands.
As the electricity generation increases, there
will be the need to expand & re-strengthen
the distribution network. This new challenge
will call for fresh supplies for transmission
towers, PCC poles & other materials.
India is a developing country where
availability of infrastructural facilities is of
paramount importance for rapid development
of national economy & general status. A
large network of electricity distribution for
rural electrifications, agricultural &
irrigational consumptions can be catered to
only by establishing an efficient generation
& distribution standards.
Electrical transmission towers, steel poles and PCC poles serve the base for overhead
power transmission & distribution. All the existing transmission grids are either in a
bad condition or inefficient. These networks require renovation. Their energy carrying
capacities can't be increased unless & until those are replaced by a new transmission
line. Then, there is the need to reach electrical light/power to all those areas where
presently this facility is missing. All these factors are essentially going to raise the
demand for not only electrical equipment but also distribution materials including
poles.
P.C.C. Poles are essentially made of concrete which are inevitably less costly and
more economically maintainable than the conventional steel poles. They are of two
types depending upon the end use of the pole-Low tensile and High Tensile Line. The
latter is primarily used for transmission of electricity. Pre-stress Cement Concrete
Poles are essentially made of concrete. High tensile wire is inserted into the pre-
designed moulds and stretched to reach a certain tension. Galvanised wire is fixed
inside the mould for earthing following which a right proportion of concrete mix is
poured. Then, the concrete is compacted through vibration to produce high strength
concrete poles. After 72 hours, the tension is released and demoulding done.
Design Loading on Pre-stressed concrete poles
Pole structures have to be designed to be reliable, serviceable, and to resist (without
permanent distortion) all anticipated maximum service loads. In the United States, the
loading conditions for electric power structures have to meet or exceed those given in
the National Electrical Safety Code (NESC). For lighting structures, the loading
conditions have to meet or exceed the NESC andlor AASHTO Standard
Specifications for Structural Support for Highway Signs, Luminaires, and Traffic
Signals. For microwave or antenna towers, the loading conditions have to meet or
exceed the Electronic Industries Association Standard RS-222-C. These loadings are
minimum requirements and the designer's study of the structure location will
determine whether these minimum requirements should be increased. Loads other
than those required by the codes or standards that affect the design of these structures
are those due to extreme weather, or to manufacturing, handling, transportation, and
erection.
Electric Power Transmission Structures
In these types of structures the design loadings are due to (1) vertical loads, (2)
transverse loads, and (3) longitudinal
loads. In addition to their own weight,
structures are subjected to vertical
loads due to dead loads of wire and
attachments, and ice. The only
variable here is the ice. A structure
should be designed for vertical loads
due to maximum vertical span, ice,
construction, and maintenance loads.
The maximum vertical span depends
on the terrain. Structures located on
hills must support more wire load, low
point to low point of wire sag, than
the adjacent structures which are
located on level ground. The
horizontal wind span is unaffected by
terrain and will always he half the true
horizontal distances between
suspension structures. Selection of the ice loads should be based on experience
records for each service area; these records can be obtained from the U.S. Weather
Bureau.
Ice build-up may not be the same on all spans, and the engineer should recognize this
effect when designing for unbalanced longitudinal loads. During the wire stringing
operation, the structure may receive vertical loads more severe than those in normal
design loadings. For maintenance loads, the structure should be designed to provide
adequate support for conductors that are being lowered during a repair operation. This
is often overlooked and could be a critical factor for a light structure.
Transverse loads are caused by (1) wind pressure on the structure and wires and (2)
the transverse component of line tension at angles. In combining these loads to give a
total transverse design loading, it is important to ensure that the appropriate conductor
tension be used with the corresponding wind load.
Extreme wind forces on transmission lines may be caused by three fundamentally
different types of meteorological systems: (1) tornadoes, (2) hurricanes, and (3) local
thunderstorms. A tornadic wind is a type of a whirlwind with rotating wind velocities
estimated at well over 200 mph (322 kmlh).
Lighting Structures
Lighting pole structures must meet or exceed the design loadings of the NESC and/or
AASHTO Standard Specifications for Structural Supports for Highway Signs,
Luminaires and Traffic Signals, and include (1) dead load, (2) live load, (3) ice load,
and (4) wind load. In addition to its own weight, the dead load includes all
permanently attached fixtures, including hoisting dePCI JOURNAL/September-
October 1984 67 vices and walkways provided for servicing of luminaires, if required.
Live load need not be applied to structural supporting members. The only member
requiring a live load design would be the walkway and ladders. The ice load of 3 psf
(0.14 kPa) is applied only to the attached fixtures, ladders, walkways, luminaires or
signs, and is based on 0.50 in. (13 mm) of ice at 60 pef (961 kg/ms).
Antenna Support Structures
Antenna support structures must meet or exceed the design loads of the Electronic
Industries Association, EIA Standard RS-222 latest revision, and include (1) dead
load, (2) ice load, (3) wind load, and (4) limit values of twist, sway, and displacement.
In addition to its own weight, the dead load includes all permanently attached fixtures,
antenna assemblies, transmission lines, reflectors, conduits, lighting, climbing
facilities, platforms and signs. This standard does not specifically state an ice
thickness required. Consideration to its location and the climatic conditions should the
given to an ice thickness requirement in preparing the specifications.
Wind loads are defined as the force and torques produced by a specified unit
horizontal wind pressure acting on the tower, antenna assemblies, reflectors, and other
fixtures attached. In all cases, the specified ice coating should be included as part of
the projected area. Minimum horizontal wind pressure in pounds per square foot (psf)
are referred to on a map chart called "Wind Loading Zones" which is part of the
standard. For towers under 300 ft. (92 m), Zone A —30 psf (1.4 kPa); Zone B — 40
psf (1.9 kPa); Zone C — 50 psf (2.4 kPa); the pressure is assumed to be applied
uniformly over the entire height of the structure.
Tower twist is defined as the horizontal angular displacement of the tower from its no
wind load position at that elevation. Tower sway is defined as the angular
displacement of a tangent to the tower axis at that elevation from its no wind load
position at that elevation. Tower displacement at any elevation is defined as the
horizontal displacement of a point on the tower axis from its no wind load position at
that elevation. A table of allowable twist and sway values for microwave tower-
antenna reflector systems is attached to the standard.
Manufacturing process of pre-stressed electric poles
The successful manufacture of pre-stressed concrete poles depends on the local
conditions and available equipment. It can be done in specialized factories using the
sophisticated spinning method with steam and/or water tank curing, or as in India, in
remote areas on site locations, using portable pre-tensioning beds, local untrained
labour, air curing and specially designed bullock carts for transporting and erecting
the poles.
The following are the principal manufacturing methods.
1. Industrial manufacturing of complete poles at specialized factories: (a) By
centrifugal casting method with demountable steel forms; (b) By vibration,
compacting on a bed with the moulds laid horizontally; (c) By compaction in a
machine with either transverse or longitudinal vibration.
2. Manufacture may be on site with poles placed horizontally.
3. Poles maybe made from precast sections
which are assembled on site by post-
tensioning or by splicing, or may be partly
preassembled in special casting yards.
In most of Europe and Japan, concrete poles
are economically mass produced by well-
equipped plants using the centrifugal
casting method. The basic manufacturing
equipment needed is the spinning machine
and the steel forms. The spinning machines
are of heavy-duty, roll-bench type and have
sets of spinning wheel assemblies at 10 Ft
(3 m) intervals.
The spinning wheel assemblies are hard
face, long wearing wheels mounted on
extra-large antifriction rollers and ball
bearings in totally sealed pillow blocks. The
machine is normally driven by a full length
drive-shaft with ball type universal joints
and a single drive station located at the
middle of the machine. Some of the more modern machines are equipped with
automatic form loader.
Unloader for maximum efficiency. The demountable steel forms usually consist of
two halves, but some plants use a single piece form. These forms are made in 10 ft. (3
m) sections and are bolted end to end to the required pole length. The forms are
precision designed and built for ruggedness; they are statically and dynamically
balanced for smooth, vibration-free running. Forms are available in a wide range of
sizes, lengths and shapes. The usual shape is round with a uniform taper from top to
bottom. Other shapes used are hexagonal, octagonal, square with chamfered corners,
triangular with chamfered edges, and cylindrical.
They are normally tapered to any dimension from 0.15 to 0.180 in. /ft. (12.5 to 15
mm/m). The process of making a spun concrete pole is to lay out the oiled half of the
form, to place full length spiral wire wrap, to pull reinforcing strand or wire through
spiral wrap to anchor heads, then to chuck and apply a small amount of stress, In
plants using "open form filling", the form is closed after it has been filled with a pre-
calculated amount of concrete and final pre-stressing takes place after the form has
For slack-reinforced poles, a specified number of high strength steel bars are
mechanically or manually prefabricated into cages following the shape of the desired
pole. A left-hand and a right-hand spiral is then wrapped the full length of the cage.
Spacial concrete or plastic spacers are positioned at intervals on the longitudinal bars
to provide a concrete cover of a minimum of 20 mm over the reinforcement and to
keep the cage centered in the mold. The finished cage is placed in the lower half of the
steel form which has been oiled with special quick-drying form-oil compound.
For pre-stressing poles, the reinforcement (strand or wire) is assembled directly in the
previously oiled lower half of form. Each end of the strand or wire is drawn through
the anchor heads, chucked and a small amount of stress is applied. A set of supporting
steel rings is positioned at intervals from top to bottom within the strands or wires to
keep them from sagging. After this a single spiral is wrapped the full length of the
pole.
If the plant is using “open-form filling“, the form is closed after it has been filled. For
pre-stressing poles, final pre-stressing takes place after the form has been filled and
fully assembled. If the plant is using “closed-form filling “, the form is closed
immediately after placing the reinforcement as described under Step-One. For pre-
stressing poles, final pre-stressing takes place after the form has been fully assembled,
but before filling. The pre-stressing reinforcement is pre-stressing up to 70 percent of
its ultimate tensile strength.
By the “open-form filling“, the form is taken to the filling station and the pre-
calculated amount of concrete is fed into the lower half of the form. The lower half is
then cleaned, the upper half is lowered into position and the form is closed. By
“closed-form filling“, the form is brought to the filling area fully assembled and a pre-
calculated amount of concrete is pumped into it.
Step Four - Spinning
The form is transported to the spinning machine where it is spun for several minutes at
high peripheral velocity. The tremendous centrifugal force created by spinning
extracts excess water and consolidates the mix to an extremely dense, high-strength
concrete, solely attainable through centrifugal casting.
After centrifugation the pole is taken to the steam curing area where it is artificially
cured in the form .with low pressure saturated steam for a period of two to four hours.
Releasing of the pre-stress wires is not done until the strength of the concrete in the
pole has attained a value of at least 3,500 psi (245 kg/q.cm). After steam curing the
pole is removed from the form and kept in a moist condition for eight - ten days,
following by a period of twenty days outdoor air curing before being shipped. The use
of high early strength cement will result in a considerably shorter curing period.
Two types of testing are used to determine the flexural behavior and flexural capacity
of poles under static loading conditions: pole testing and structure testing. Pole testing
is used to verify the design and quality of production of the poles. A test frame is
used. Here, the butt of the pole is fixed and the pole is pulled from a point below the
tip, usually 2 ft. (0.6 in), about a reaction point ground line distance from the butt. By
adding the load in increments of the ultimate design, the cracking moment and
physical behavior of the pole to destruction can he checked. It is good practice to
include in the specifications some random pole testing to a percentage of the ultimate
strength of the pole as a quality assurance check. A pole can be tested up to 90 percent
of ultimate, and when the load is released, show no effect of the loading. Structure
testing is the simulation of the structure as it is to be used, loaded in increments to its
design loadings, in a static condition, to check its structural strength and behavior.
Although pre-stressing concrete poles are resilient and resist cracking, they require
special care in handling, transporting and erecting. Some guidelines for safe handling
of pre-stressing concrete poles are:
1. Always handle pre-stressing concrete poles with the major axis in the horizontal
direction, with a two-point balanced pickup.
2. While unloading from trucks, railroad cars or waterway barges, handle the poles
gently. Under no circumstances should they be thrown onto a pile.
3. Poles should be stacked level and supported so their own dead weight will not cause
them to sag.
4. While transporting by pole trailer, the poles should he held as rigid as possible to
keep them from oscillating, which could cause them to crack. The use of a strong back
is suggested, if necessary.
5. When erecting single poles, it is suggested that they be rigged
6. H-frame structures should be assembled and lifted with the use of a spreader bar.
With structures over 80 ft. (24 m), a second pick point should be used to get the pole
butts off the ground when lifting the structure to the vertical position.
Most studies have indicated that the first cost of pre-stressing concrete poles is greater
than timber, but less than steel, in the range of sizes of pre-stressing concrete poles
designed and used today. It must be emphasized that numerous circumstances affect
their economy, especially transportation and availability. From the data collected, the
facts indicate that every country surveyed in the report is using pre-stressing concrete
poles more and more frequently.
Future technology into higher strength concrete with a 28-day strength in the 69 to 83
MPa range may become standard as efforts to produce stronger poles with slender
profile develop. Pole weights may also decrease with the use of lighter weight
concrete. Sectionalized poles will reduce shipping and handling problems. The
development of concrete admixtures that provide concrete with acceptable electrical
insulating and mechanical strength properties may open the way for innovative
integrated design. The increasing market for wood products may eventually eliminate
wood from the pole marketplace; this will un-doubtedly cause wood pole users to look
at concrete poles as an attractive alternative.
Future technological developments in concrete pole design, manufacturing, and
costing will have a very definite impact on the future use of pre-stressing concrete
poles.
Advantages of using Pre-stressing Concrete in Electric Poles:
• Pre-stressed concrete poles are lighter and stronger, so they require less reinforcing
steel.
• The concrete is generally in compression, so cracking is unlikely except from rough
handling, and the concrete used is of higher strength so it can withstand the pre-
stressing operation.
• The poles are spun at high speeds during the manufacturing process, because of this
they have a smoother surface that is denser and less permeable.
• Pre-stressing Concrete poles offer a cost effective, permanent solution for the
lighting, utility and surveillance industries.
• The pre-stressing concrete poles have consistent material properties throughout their
length. These are not susceptible to rot and decay.
• The pre-stressing concrete pole has the same strength throughout its service life.
• The poles are ecofriendly and require very low maintenance.
• It is helpful from the stand point of both users and designers.
• Fire resistant, particularly to grass and bush fires near the ground line.
• Electric safety and Safe Earthing.
• Flexible for all locations for erection
RCC Poles:
• P.S.C. is more durable since there are no tensile cracks, whereas in R.C.C tensile
cracks are unavoidable, hence there is greater danger of adverse environmental
effects.
• As high strength concrete is used and also since dead load moments can be
neutralized P.S.C., dead weight of P.S.C. member is much less compared to what is
required for R.C.C. member. The dead weight of P.S.C member is about one-third of
equivalent R.C. members.
• The material cost in P.S.C. is much less than that in equivalent R.C. members.
• The deformation of P.S.C. members is much less compared to that for an equivalent
R.C. member. In case of beams deflection of P.S.C. beams is about one - Fourth of
that of equivalent R.C. beams.
• P.S.C has high resilience that is., a considerable capacity for recovering completely
from the effect of occasional over loadings, without suffering any serious harm. In
case of P.S.C. cracks in such situation which develop temporarily will close up
completely.
References:
1. Pre-stressing Concrete Poles: State-of-the-Art by Thomas E. Rodgers, Jr.
Director Structural Engineering VEPCO, Electric and Power Company
Richmond, Virginia
2. Pre-stressing Concrete by N. Krishnaraju.
3. www.nptel.ac.in
4. www.niir.org
5. www.acuitysupport.zendesk.com
6. www.happho.com
7. http://megandlo.tripod.com/Synopsis.pdf
8. https://3.imimg.com/data3/MI/YH/MY.../pre-stressing-concrete-electric-
poles.pdf
9. https://www.ergon.com.au/__data/assets/pdf.../Manufacture-of-Concrete-
Poles.pdf