Beruflich Dokumente
Kultur Dokumente
SPECIFICATION
GEI-QHSE-002-A4 Rev 0 Page 2 of 15
REV
DATE DESCRIPTION OF REVISION
.
A 20/04/2016 Issued for Review
0 29/04/2016 Issued for Construction
FIRE FIGHTING & PROTECTION DESIGN
SPECIFICATION
GEI-QHSE-002-A4 Rev 0 Page 2 of 15
TABLE OF CONTENTS
1. GENERAL ................................................................................................................................................ 4
2. DEFINITION ............................................................................................................................................. 5
2.1 TERMINOLOGY AND ABBREVIATIONS ......................................................................................... 6
3. CODE AND STANDARD ........................................................................................................................ 6
4. DESIGN PHILOSOPHY .......................................................................................................................... 7
5. FIRE WATER SUPPLY SYSTEM .......................................................................................................... 9
6. OUTDOOR FIRE FIGHTING SYSTEM ............................................................................................... 11
7. INDOOR FIRE FIGHTING SYSTEM ................................................................................................... 12
8. FIRE ALARM DETECTION SYSTEM.................................................................................................. 13
FIRE FIGHTING & PROTECTION DESIGN
SPECIFICATION
GEI-QHSE-002-A4 Rev 0 Page 4 of 15
1. GENERAL
This document describes for Fire Fighting and Protection Design Specification of
CONTRACTOR’s scope of work including Survey, Detailed Engineering,
Procurement, Construction, Testing, Calibration, Training, Pre-commissioning,
Commissioning and 1 (One) Year Operation & Maintenance (O&M) of
Compressed Natural Gas (SPBG) Station (PROJECT, here in after).
CONTRACTOR SHALL supply goods and related services for the Compressed
Natural Gas (SPBG) Station at SPBG, which SHALL consist of the following:
Compressed Natural Gas Compressor Packages (Including Gas Engine)
Filling Post Units
Piping System
Gas Dryer Packages
Gas Storage
Instrument Air System Package
Station Monitoring System
Fire and Gas System and Fire Fighting System
CCTV System
Telecommunication System
Point of Sale (POS) System
Switch Gear & MCC and Distribution Panel System
Public or area electrical power supply (PLN) and public water utility
(PDAM) provider connection
Electrical System (Grounding, Lightning Protection and Lighting, etc.)
Uninterruptible Power Supply (UPS) System
Gas Engine Generator set System
Instrumentation System (field instruments, ESDV, etc.)
Civil Works (land preparation, embankment, shelter, bridge access,
concrete pavement, concrete slab, fence and gates, plants, drainage,
etc.)
Building utilities (air conditioning, waste water system, clean water
system, drainage system, etc.)
Any other facilities required to meet the requirements and intent of the
Scope of Works.
FIRE FIGHTING & PROTECTION DESIGN
SPECIFICATION
GEI-QHSE-002-A4 Rev 0 Page 5 of 15
2. DEFINITION
The following words SHALL have the meaning indicated when used herein:
4. DESIGN PHILOSOPHY
the water to the desired areas at effective pressures. This means a looped or
gridded distribution piping.
b. Sizing the distribution piping to meet anticipated demands with apart of the
distribution system out of service.
c. Burying distribution piping to prevent an explosion within the facility from impairing
the system.
Extinguisher water system must have design pressure of 970 kPa(g). A conceptual
fire water loop site plan drawing shall be presented. The fire water loop shall service
all areas.
a. Fire water pump capacity shall be assumed based on single fire worst case which
happened in the determined area.
b. The pressure in main fire water distribution piping (main fire water ring) shall be
minimum 700 kPa (g) for the farthest point according to design flow condition.
1 (One) motor driven jockey pump shall be provided to maintain a pressure in the fire
main header. The rated capacity should be at least 5 % of fire water main pump rated
capacity, and the rated discharge pressure shall be the same as the fire water
pumps.
Fire extinguisher system pressure must be maintained with jockey pump that should
have pressure of 15 psig above the starting pressure of the main fire water pump
which will be fixed based on “ Detail Engineering Design’’ stage. Fire water pumps
shall be designed and installed as NFPA 20 requirements. Fire water pumps shall be
located to avoid the potential loss of all pumping supplies at the same time. The
location of the fire water pumps system shall be away from severe process hazards
so that they will not be damaged by explosion overpressures.
The following table is shown the type of fire extinguishing system or equipment based on
the area within CNG station to be protected.
Once the pre-discharge horn sounded, the building or room must be evacuated
immediately.
Re-entering a building after discharge should be done after the area has been given a
chance to ventilate properly.
The area shall be protected by clean agent is control room and panel room
The following items are the devices that comprise the system : Clean agent system
and accessories, smoke and/or heat detector, manual alarm stations, alarm bell,
alarm flashing red lights, Pre-discharge horns.
a. Smoke Detector
Smoke detection at control room and Panel room :
Smoke detection will activate alarm in F & G panel, flashing beacon and siren of
fire alarm inside building. Cross zone detection shall be applied to activated of
fixed fire extinguishing system.
b. Heat Detection
Heat detection inside control room and panel room :
Heat detection will activate alarm in F & G panel, flashing beacon and siren of fire
alarm inside building. Cross zone detection shall be applied to activated of fixed
fire extinguishing system.
c. Flame Detection
Flame detection at CNG station area will activate alarm in F & G panel, flashing
beacon and siren of fire alarm.
Hydrocarbon gas detection at CNG station area will activate alarm F & G panel at
control room, flashing beacon, and siren of fire alarm.