MASTER DOCUMENT REGISTER

Project Tittle : KAMPUNG BARU BOOSTER COMPRESSOR PROJECT


Contractor : PT. Slipform Indonesia
Client : PT. Energy Epic Equity Sengkang (EEES) Pty. Ltd

current progress
No Document Number DOC/NO. TITLE MAN
Discipline Document Type Ongoing IDC A01
HOURS
% Hours

PROCESS
DESIGN BASIS
1 Process Design Basis KB-CPP-PS-DBS-0001 Process Design Basis 32 √ 70 22.4
STUDY
1 Process Study KB-CPP-PS-SDY-0001 Process Simulation Train I & Train II 32 √ 70 22.4
2 Process Study KB-CPP-PS-SDY-0002 Operating & Controlling Philosophy Gas Compressor Train I & Train II 32 √ 50 16
3 Process Study KB-CPP-PS-SDY-0003 Back Pressure & Relief Study Checking 48 √ 50 24
4 Process Study KB-CPP-PS-SDY-0004 Flare Radiation Study Checking 32 √ 50 16
5 Process Study KB-CPP-PS-SDY-0005 Adequecy Check Study (Instrument & Utility Air, Fuel Gas, Fire Water) 32 √ 50 16
6 Process Study KB-CPP-PS-SDY-0006 Precommissioning, Commissioning & Start-Up Procedure 48 0
7 Process Study KB-CPP-PS-SDY-0007 Review HAZOP Study Report from COMPANY Third Party 40 0
8 Process Study KB-CPP-PS-SDY-0008 Review HAZID Study Report from COMPANY Third Party 40 0
9 Process Study KB-CPP-PS-SDY-0009 Review HAZOP Close Out Report from COMPANY Third Party 40 0
10 Process Study KB-CPP-PS-SDY-0010 Review HAZID Close Out Report from COMPANY Third Party 40 0
CALCULATION
1 Process Calculation KB-CPP-PS-CAL-0001 Line Sizing for Gas Compressor Train I & Train II 40 √ 50 20
2 Process Calculation KB-CPP-PR-CAL-0002 Fire Water Hydraulic Calculation 40 0
4 Process Calculation KB-CPP-PR-CAL-0004 Inlet Separator Check Sizing 30 √ 50 15
DRAWING
PFD
1 Process Drawing KB-CPP-PS-PFD-0001 PFD Central Processing Plant Train #1 and Patila Metering System Train #1 32 √ 50 16
2 Process Drawing KB-CPP-PS-PFD-0002 PFD Central Processing Plant Train #2 and Patila Metering System Train #2 24 √ 50 12
3 Process Drawing KB-CPP-PS-PFD-0003 PFD CPP Wellhead Area 24 √ 50 12
4 Process Drawing KB-CPP-PS-PFD-0004 SH 1 PFD Gas Compressor Packages U-8110/U-8120/U-8130 24 √ 50 12
5 Process Drawing KB-CPP-PS-PFD-0004 SH 2 PFD Gas Compressor Packages U-8140/U-8150 24 √ 50 12
PID
1 Process Drawing KB-CPP-PS-PID-0000 SH1 Piping And Instrumentation Diagram - Symbols and Legend_sheet 1 32 √ 50 16
2 Process Drawing KB-CPP-PS-PID-0000 SH2 Piping And Instrumentation Diagram - Symbols and Legend_sheet 2 32 √ 50 16
3 Process Drawing KB-CPP-PS-PID-0001 P&ID V-103 Inlet Separator, F-900 Coalescing Filter 32 √ 50 16
4 Process Drawing KB-CPP-PS-PID-0002 P&ID Back Up TEG Unit 32 √ 50 16
5 Process Drawing KB-CPP-PS-PID-0003 P&ID V-101 ABC Pig Receivers 32 √ 50 16
8 Process Drawing KB-CPP-PS-PID-0006 P&ID CPP Train-2 Inlet Metering FE-1011/1012/1013 32 √ 50 16
9 Process Drawing KB-CPP-PS-PID-0007 P&ID CPP Train-2 Inlet Separator V-1030 (sheet 1 of 2) 32 √ 50 16
10 Process Drawing KB-CPP-PS-PID-0008 P&ID CPP Train-2 Coalescing Filter F-9000 (sheet 2 of 2) 32 √ 50 16
11 Process Drawing KB-CPP-PS-PID-0009 P&ID Air Compressor Package CPP Train-2 Air Compressor K-3020A/B,Plant Air Receiver V-3200A Air dryer X-3100A/B,Inst.Air Receiver V-3200B 32 √ 50 16
12 Process Drawing KB-CPP-PS-PID-0010 P&ID CPP Train-2 Natural Gas Engine G-2510,Coalescing Filter F-2510,Gas Generator Skid SK-GG-0800 32 √ 50 16
13 Process Drawing KB-CPP-PS-PID-0011 P&ID CPP Train-2 Fire Water Distribution 32 √ 50 16
14 Process Drawing KB-CPP-PS-PID-0012 P&ID CPP Gas Compression System U-8110 Gas Compression Package Train-1 32 √ 50 16
15 Process Drawing KB-CPP-PS-PID-0013 P&ID CPP Gas Compression System U-8120 Gas Compression Package Train-1 32 0
16 Process Drawing KB-CPP-PS-PID-0014 P&ID CPP Gas Compression System U-8140 Gas Compression Package Train-2 32 0
17 Process Drawing KB-CPP-PS-PID-0015 P&ID CPP Gas Compression System U-8150 Gas Compression Package Train-2 32 0
18 Process Drawing KB-CPP-PS-PID-0016 P&ID CPP Gas Compression System U-8130 Gas Compression Package ( Back Up) 32 √ 50 16
19 Process Drawing KB-CPP-PS-PID-0017 P&ID CPP Gas Compression System Gas Compressor Package ,Inlet and Outlet Header 32 √ 50 16
20 Process Drawing KB-CPP-PS-PID-0018 P&ID Skimmer Tank S-619 Kampung Baru 32 √ 50 16
22 Process Drawing KB-CPP-PS-PID-0020 P&ID CPP Train 2 Test Separator V-1020 32 √ 50 16
HMB
1 Process HMB KB-CPP-PS-HMB-0001 Heat Material Balances Train I & Train II (Overall) 32 √ 50 16
SAFECHART
1 Process Safechart KB-CPP-PS-LOG-0001 Safechart Train I 40 0
2 Process Safechart KB-CPP-PS-LOG-0002 Safechart Train II 40 0
LIST
1 Process List KB-CPP-PS-LST-0001 Tie-in List 32 √ 50 16
2 Process List KB-CPP-PS-LST-0002 Line List 32 √ 40 12.8
3 Process List KB-CPP-PS-LST-0003 Process Equipment List 32 0
DATA SHEET
1 Process Datasheet KB-CPP-PS-DS-1001 Fire Hydrant data Sheet 16 0
2 Process Datasheet KB-CPP-PS-DS-1002 Hose Box data Sheet 16 0
3 Process Datasheet KB-CPP-PS-DS-1003 Fire Monitor data Sheet 16 0
DRAWING
1 Process Drawing KB-CPP-PS-DWG-1001 Escape Route & Fire Safety Equipment Layout - Gas Compressor Train I & train II 100 0
2 Process Drawing KB-CPP-PS-DWG-1002 Fire & Gas Detector Mapping Layout 70 √ 50 35
ELECTRICAL
DESIGN BASIS
1 Electrical Design Basis KB-CPP-EL-DBS-0001 Electrical Design Basis 80 √ 70 56
REPORTS AND CALCULATIONS
1 Electrical Report & Calculation KB-CPP-EL-LST-0001 Electrical Load List 40 0
2 Electrical Report & Calculation KB-CPP-EL-CAL-0002 Electrical Power System Study Report (LF,SC,MS,Transient) -ETAP (HOLD) 80 0
current progress
No Document Number DOC/NO. TITLE MAN
Discipline Document Type Ongoing IDC A01
HOURS
% Hours

3 Electrical Report & Calculation KB-CPP-EL-CAL-0003 Electrical Main Equipment Sizing 40 0


4 Electrical Report & Calculation KB-CPP-EL-CAL-0004 Restudy availablity of rating AC UPS and DC Battery Charger (HOLD) 40 0
5 Electrical Report & Calculation KB-CPP-EL-CAL-0005 Lighting Calculations 40 0
7 Electrical Report & Calculation KB-CPP-EL-CAL-0006 Power Cable Sizing & Voltage Drop Calculations (AC,DC,& lighting) 40 √ 40 16
8 Electrical Report & Calculation KB-CPP-EL-CAL-0007 Relay Coordination study (when required) (HOLD) 80 0
SPECIFICATION (REVIEW & UPDATE)
DATASHEET (REVIEW & UPDATE)
1 Electrical Datasheet .KB-CPP-EL-EDS-0004 Data Sheet - Distribution Transformer 20 √ 50 10
2 Electrical Datasheet .KB-CPP-EL-EDS-0005 Data Sheet - Neutral Grounding Resistor 20 √ 50 10
3 Electrical Datasheet .KB-CPP-EL-EDS-0006 Data Sheet - 6.6 KV MV Switchgear 20 √ 50 10
4 Electrical Datasheet .KB-CPP-EL-EDS-0007 Data Sheet - 415 LV Switchgear/MCC 20 √ 40 8
5 Electrical Datasheet .KB-CPP-EL-EDS-0008 Data Sheet - 110 VDC UPS Single Line Diagram (HOLD) 20 0
6 Electrical Datasheet .KB-CPP-EL-EDS-0009 Data Sheet - Lighting or Small Power DB 20 √ 50 10
7 Electrical Datasheet .KB-CPP-EL-EDS-0003 Data Sheet - Cable tray 20 √ 50 10
8 Electrical Datasheet .KB-CPP-EL-EDS-0001 Data Sheet - Lighting and Receptacle 20 √ 50 10
9 Electrical Datasheet KB-CPP-EL-EDS-0002 Data Sheet - Bulk Material 20 √ 50 10
DRAWINGS
1 Electrical Drawing Electrical Legends & Symbols (deleted, include inside SLD)
2 Electrical Drawing KB-CPP-EL-ONE-0001 Electrical Overall Single Line Diagram 40 √ 70 28
3 Electrical Drawing KB-CPP-EL-ONE-0002 Electrical 6.6 KV Single Line Diagram 40 √ 40 16
4 Electrical Drawing KB-CPP-EL-ONE-0003 Electrical 0.415 KV Single Line Diagram 40 √ 40 16
5 Electrical Drawing KB-CPP-EL-ONE-0004 Electrical 110 VDC UPS Single Line Diagram (HOLD) 40 0
LAYOUTS
1 Electrical Layout KB-CPP-EL-LAY-0001 Electrical Switchrooms, Substation/Equipment Layout 30 √ 40 12
2 Electrical Layout KB-CPP-EL-LAY-0002 Electrical Switchrooms, Grounding Layout 30 √ 40 12
3 Electrical Layout KB-CPP-EL-LAY-0003 Earthing and Lightning layout drawings - Overall Plant 60 0
4 Electrical Layout KB-CPP-EL-LAY-0004 Indoor Lighting Layout (c/w Connection Diagram & Panel Schedule) 30 0
5 Electrical Layout KB-CPP-EL-LAY-0005 Outdoor Lighting Layout (c/w Connection Diagram & Panel Schedule) 30 0
6 Electrical Layout KB-CPP-EL-LAY-0006 Power and Control Cable Layout 30 0
7 Electrical Layout KB-CPP-EL-LAY-0007 Cable Tray Routing layout 30 0
TYPICAL SCHEMATIC CONTROL DRAWINGS
1 Electrical Schematic KB-CPP-EL-WIR-0001 Typical LV Motor Starter Schematic Drawings (400V) 55 0
2 Electrical Schematic KB-CPP-EL-WIR-0002 Typical MV Motor Starter Schematic Drawings (6.6kV) 55 0
TYPICAL AND STANDART
1 Electrical Typical and Standart KB-CPP-EL-STD-0001 Typical Installation Standards - Power 25 0
2 Electrical Typical and Standart KB-CPP-EL-STD-0002 Typical Installation Standards - Lighting 25 0
3 Electrical Typical and Standart KB-CPP-EL-STD-0003 Typical Installation Standards - Earthing 25 0
4 Electrical Typical and Standart KB-CPP-EL-STD-0004 Typical Installation Standards - Tray 25 0
LIST
1 Electrical List KB-CPP-EL-EQL-0001 Electrical Equipment List 20 √ 40 8
SCHEDULES
1 Electrical Schedules KB-CPP-EL-SCM-0001 Cable Schedule - Power & Control 60 0
2 Electrical Schedules KB-CPP-EL-SCM-0001 Cable Schedule - Lighting 50 0
INTERCONNECTION WIRING DIAGRAM
1 Electrical Wiring Diagram KB-CPP-EL-WIR-0003 MV Switchgear/MCC Interconnection & Wiring Diagram 30 0
2 Electrical Wiring Diagram KB-CPP-EL-WIR-0004 LV Switchgear/MCC Interconnection & Wiring Diagram 30 0
3 Electrical Wiring Diagram KB-CPP-EL-WIR-0005 AC UPS Interconnection & Wiring Diagram - Update (hold) 30 0
MTO
1 Electrical MTO KB-CPP-EL-MTO-0001 MTO - Electrical MV & LV Power and Control Cables 40 0
2 Electrical MTO KB-CPP-EL-MTO-0002 MTO - Lighting Fixtures & Accessories & Lighting Poles 40 0
3 Electrical MTO KB-CPP-EL-MTO-0003 MTO - Cable Trays & Perforated Trays 40 0
4 Electrical MTO KB-CPP-EL-MTO-0004 MTOs - Electrical Bulk Materials 40 0
RFQ PREPARATION
1 Electrical RFQ KB-CPP-EL-REQ-0001 Requisition for Distribution Transformer 20 0
2 Electrical RFQ KB-CPP-EL-REQ-0002 Requisition for Neutral Grounding Resistor 20 0
3 Electrical RFQ KB-CPP-EL-REQ-0003 Requisition for 6.6 kV Switchgear/MCC 20 0
4 Electrical RFQ KB-CPP-EL-REQ-0004 Requisition for 415 kV Switchgear/MCC 20 0
5 Electrical RFQ KB-CPP-EL-REQ-0005 Requisition for 110 VDC UPS 20 0
6 Electrical RFQ KB-CPP-EL-REQ-0006 Requisition for Lighting Distribution Board 20 0
PROCUREMENT ASSISTANCE
1 Electrical Procurement Assistance TC/TBE - Distribution Transformer 10 0
2 Electrical Procurement Assistance TC/TBE - Neutral Grounding Resistance 10 0
3 Electrical Procurement Assistance TC/TBE - 6.6 kV Switchgear/MCC 10 0
4 Electrical Procurement Assistance TC/TBE - 0.4 kV Switchgear/MCC 10 0
5 Electrical Procurement Assistance TC/TBE - 110 VDC UPS 10 0
6 Electrical Procurement Assistance TC/TBE - Lighting & Small Power DB 10 0
7 Electrical Procurement Assistance TC/TBE - Electrical Power,Control, Lighting Cables 10 0
8 Electrical Procurement Assistance TC/TBE/PS - Lighting Fixtures& Accessories & lighting Poles 15 0
9 Electrical Procurement Assistance TC/TBE/PS - Cable Trays & Ladders 15 0
10 Electrical Procurement Assistance TC/TBE/PS - Electrical Bulk Material 15 0
AS BUILT SUBMISSION
1 Electrical As Built Submission Preparation of Final Documentation for Electrical Packages [OPTION - HOLD] 150 0
current progress
No Document Number DOC/NO. TITLE MAN
Discipline Document Type Ongoing IDC A01
HOURS
% Hours

MECHANICAL
GENERAL
1 Mechanical General IDCs of Process P & ID review 20 √ 40 8
2 Mechanical General IDCs of Instrument Deliverables (Instrument Specification etc.) 20 √ 40 8
3 Mechanical General IDCs of Electrical Deliverables (Power list, Specification, Motor DS, etc.) 20 √ 40 8
4 Mechanical General IDCs of Civil / Structural Drawings 10 √ 40 4
5 Mechanical General IDCs of Piping plot plan / layouts 10 √ 40 4
6 Mechanical General IDCs of Safety Drawings 10 √ 40 4
7 Mechanical General HAZOP Participation 10 √ 40 4
8 Mechanical General Internal project meetings 60 √ 40 24
9 Mechanical General Meetings with vendors/ manufacturers 80 √ 40 32
10 Mechanical General Mechanical Equipment List 60 √ 40 24
VENDOR DOCUMENT REVIEW
1 Mechanical Vendor Document Review Vendor Document Review of Gas Booster Compressor Train 1, 2, 3, & 4 100 0
2 Mechanical Vendor Document Review Vendor Document Review of Pulsation bottle for Compressor Train 1, 2, 3, & 4 80 0
3 Mechanical Vendor Document Review Vendor Document Review of Suction Scrubber for Compressor Train 1, 2, 3, & 4 80 0
4 Mechanical Vendor Document Review Vendor Document Review of Discharge Scrubber for Compressor Train 1, 2, 3, & 4 80 0
5 Mechanical Vendor Document Review Vendor Document Review of Fan Cooler for Compressor Train 1, 2, 3, & 4 80 0
6 Mechanical Vendor Document Review Vendor Document Review of Lube Oil System 50 0
SPECIFICATION
0
DATA SHEET
0
RFQ
0
TBE
0
INSTRUMENTATION
SPECIFICATION
1 Instrumentation Specification KB-CPP-IN-SPE-0002 Specification for FGS Panel And OWS 50 √ 70 35
2 Instrumentation Specification KB-CPP-IN-SPE-0003 Typical Configuration for Fire & Gas System and Operator Workstation 50 √ 70 35
CALCULATION
1 Instrumentation Calculation KB-CPP-IN-CAL-0001 Instrument Power Consumption 30 0
LIST
1 Instrumentation List KB-CPP-IN-LST-0001 Instrument Index 40 √ 70 28
2 Instrumentation List KB-CPP-IN-LST-0002 Instrument I/O List 30 √ 70 21
3 Instrumentation List KB-CPP-IN-LST-0003 Cable Schedule Gas Compressor Project 40 √ 50 20
DRAWING
41 Instrumentation Drawing KB-CPP-IN-DWG-1001 SHUTDOWN LOGIC DIAGRAM 20 √ 70 14
42 Instrumentation Drawing KB-CPP-IN-DWG-1002 FIRE AND GAS LOGIC DIAGRAM 20 √ 50 10
43 Instrumentation Drawing KB-CPP-IN-DWG-1003 CONTROL SYSTEM ARCHITECTURE DIAGRAM 20 √ 40 8
44 Instrumentation Drawing KB-CPP-IN-DWG-1004 OVERALL CABLE BLOCK DIAGRAM 20 √ 40 8
45 Instrumentation Drawing KB-CPP-IN-DWG-1005 JUNCTION BOX WIRING DIAGRAM 20 √ 40 8
46 Instrumentation Drawing KB-CPP-IN-DWG-1006 INSTRUMENT INSTALLATION AND MOUNTING DETAIL 20 √ 40 8
47 Instrumentation Drawing KB-CPP-IN-DWG-1007 INSTRUMENT CABLE ROUTING AND TRAY LAYOUT 20 √ 40 8
48 Instrumentation Drawing KB-CPP-IN-DWG-1008 FIRE & GAS DETECTOR LAYOUT 20 √ 40 8
49 Instrumentation Drawing KB-CPP-IN-DWG-1009 TROUBLESHOOTING LOOP DIAGRAM 20 √ 40 8
MTO
3 Instrumentation MTO KB-CPP-IN-MTO-0001 INSTRUMENT MTO for KBBCS 40 √ 50 20
RFQ
1 Instrumentation RFQ KB-CPP-IN-RFQ-1001 RFQ FOR FIRE & GAS SYSTEM AND OPERATOR WORKSTATION 100 √ 50 50
TBE
1 Instrumentation TBE KB-CPP-IN-TBE-1001 TBE FOR FIRE & GAS SYSTEM AND OPERATOR WORKSTATION 100 0
CIVIL
STUDY
1 Civil Study Topographic Survey Report 200 √ 40 80
2 Civil Study Soil Investigation Report 200 √ 40 80
SPECIFICATION
1 Civil Specification Civil and Structure General Specification & Design Criteria 80 √ 40 32
2 Civil Specification Civil and Structure Construction Specification 80 0
CALCULATION
1 Civil Calculation Typical Foundation for Gas Compressor A/B/C/D/E 80 √ 40 32
2 Civil Calculation Foundation for Shelter Gas Compressor c/w Hoist Crane 80 0
3 Civil Calculation Structure for Shelter Gas Compressor 80 0
4 Civil Calculation Foundation for Pipe Rack and Pipe Bridge (new) 40 0
5 Civil Calculation Structure for Pipe Rack and Pipe Bridge (new) 40 0
6 Civil Calculation Foundation for Pipe Rack (modification existing) 40 0
7 Civil Calculation Structure for Pipe Rack (modification existing) 40 0
8 Civil Calculation Foundation for Lighting Pole 30 0
9 Civil Calculation Foundation & Structure for Typical Pipe Support 30 0
10 Civil Calculation Foundation for Fire Hydrant & Hose Box 30 0
11 Civil Calculation Typical Foundation for PLN Substation 40 0
12 Civil Calculation Foundation for Pole of Power Line 20 0
13 Civil Calculation Design for Cable Trench 20 0
current progress
No Document Number DOC/NO. TITLE MAN
Discipline Document Type Ongoing IDC A01
HOURS
% Hours

DRAWING
1 Civil Drawing KB-CCP-CV-GEN-0000 General Notes 20 √ 40 8
4 Civil Drawing KB-CCP-CV-STD-0001 Standard Drawing for Civil 20 √ 40 8
5 Civil Drawing KB-CCP-CV-STD-0002 Standard Drawing for Structure 20 √ 40 8
6 Civil Drawing KB-CCP-CV-LAY-0002 Foundation Drawing for Typical Gas Compressor A/B/C 20 0
7 Civil Drawing KB-CCP-CV-LAY-0003 Foundation Drawing for Gas Compressor Shelter c/w Hoist Crane 40 0
8 Civil Drawing KB-CCP-CV-LAY-0004 Steel Structure Drawing for Gas Compressor Shelter c/w Hoist Crane 80 0
9 Civil Drawing KB-CCP-CV-LAY-0005 Foundation Drawing for Pipe Rack and Pipe Bridge 40 0
10 Civil Drawing KB-CCP-CV-LAY-0006 Steel Structure Drawing for Pipe Rack and Pipe Bridge 80 0
11 Civil Drawing KB-CCP-CV-LAY-0007 Foundation Drawing for Pipe Rack and Pipe Bridge (modification existing) 40 0
14 Civil Drawing KB-CCP-CV-LAY-0010 Foundation Drawing for Lighting Pole 20 √ 40 8
15 Civil Drawing KB-CCP-CV-LAY-0011 Foundation & Steel Structure Drawing for Typical Pipe Support 20 0
16 Civil Drawing KB-CCP-CV-LAY-0012 Foundation Drawing for Fire Hydrant & Hose Box 20 √ 40 8
17 Civil Drawing KB-CCP-CV-LAY-0013 Foundation and Steel Structue Drawing for Fencing and Gate 40 √ 40 16
18 Civil Drawing KB-CCP-CV-LAY-0014 Foundation for Pole of Power Line 40 0
20 Civil Drawing KB-CCP-CV-LAY-0001 General Layout Plan 20 0
MTO
1 Civil MTO Civil Material Take-Off 80 √ 40 32
2 Civil MTO Structure Material Take-Off 80 √ 40 32
PIPING
ENGINEERING WORK PACKAGE
1 Piping General Engineering Design Basis - Piping 64 √ 40 25.6
2 Piping General Engineering Work Package - Pipe Stress Analysis 64 0
3 Piping General Engineering Work Package - Fabrication & Erection 57 0
4 Piping General Engineering Work Package - SandBlasting & Coating 57 0
5 Piping General Engineering Work Package - Testing & PreCommissioning 57 0
CALCULATION & REPORT
1 Piping Calculation Flare line to Train #1- Flexibility & Stress Calculation Report 104 0
2 Piping Calculation Flare line to Train #2- Flexibility & Stress Calculation Report 104 0
3 Piping Calculation Process gas line In & Out Train #1- Flexibility & Stress Calculation Report 104 0
4 Piping Calculation Process gas line In & Out Train #2- Flexibility & Stress Calculation Report 104 0
5 Piping Calculation PSV Lines analysis- Flexibility & Stress Calculation Report 104 0
6 Piping Calculation Allowable Load - Nozzle Compressor 120 0
CONSTRUCTION DRAWINGS
1 Piping Drawing Gas Process Outlet Train #1 - Isometric Drawing Series 80 √ 40 32
2 Piping Drawing Gas Process Outlet Train #2 - Isometric Drawing Series 80 √ 40 32
3 Piping Drawing Gas Process Inlet Train #1 - Isometric Drawing Series 80 √ 40 32
4 Piping Drawing Gas Process Inlet Train #2 - Isometric Drawing Series 80 √ 40 32
5 Piping Drawing Flare Gas To Train #1 - Isometric Drawing Series 80 √ 40 32
6 Piping Drawing Flare Gas To Train #2 - Isometric Drawing Series 64 √ 40 25.6
7 Piping Drawing Drain Line To Train #1 - Isometric Drawing Series 64 √ 40 25.6
8 Piping Drawing Drain Line To Train #2 - Isometric Drawing Series 64 √ 40 25.6
9 Piping Drawing Instrument air line - Isometric Drawing Series 80 √ 40 32
10 Piping Drawing Firewater line - Isometric Drawing 64 √ 40 25.6
11 Piping Drawing Piping Layout Train #1 to Compressor Building - Plan View & Section Details 128 √ 40 51.2
12 Piping Drawing Piping Layout Train #2 to Compressor Building - Plan View & Section Details 128 √ 40 51.2
13 Piping Drawing Piping Layout Compressor Building - Plan View & Section Details 136 √ 40 54.4
14 Piping Drawing 3D Plant Modelling 360 √ 40 144
MATERIAL TAKE OFF
1 Piping MTO Gas Process & Utility - Summary Materials 144 √ 40 57.6
TOTAL MANHOURS 9494 2225

Overall Progres 23%