1. GENERAL .......................................................................................................................... 2
2.1. General..................................................................................................................... 3
2.2. PART 0 OVERALL................................................................................................... 4
2.3. PART 1 SAFETY, HEALTH & ENVIRONMENTAL (SHE) REPORT .......................... 4
2.4. PART 2 PROJECT STATUS ..................................................................................... 7
2.5. PART 3 LOCAL CONTENT REPORT....................................................................... 7
2.6. PART 4 MISCELLANEOUS REPORT........................... Error! Bookmark not defined.
5. ATTACHMENTS................................................................................................................ 7
OPTIONAL ATTACHEMENTS FOR THIS SPECIFICATION:
1. GENERAL
1.2. Reference
The following procedures shall be referred to when called for by this procedure:
?? PP-MN-GG-003 Project Control Procedure
?? PP-MN-GG-006 Change Order Procedure
?? PP-MN-GG-008 Filling Procedure
?? PP-MN-GG-009 Communication Procedures Between COMPANY and
CONTRACTOR
1.3. Terminology
In this specification, the following words and terms shall have the meanings hereby
assigned to them, unless noted otherwise.
1.3.1. COMPANY
Refers to PT. CALTEX PACIFIC INDONESIA, as the ultimate user and owner,
the authorized representative of COMPANY or COMPANY third party
inspection.
1.3.2. CONTRACTOR
Refers to company selected by COMPANY, which may be responsible for the
detailed engineering design, material and equipment procurement, and
construction as specified by Contract, Scope of Work, or Work order.
1.3.3. Vendor
Refers to the company selected by COMPANY or CONTRACTOR, which is
responsible for the purchase agreement or purchase order of the goods/services
specified in this specification
Note:
2.1. General
The Monthly Report will consist of five (5) main parts which consisting of the following
parts and sections:
PART 0 OVERALL
SECTION 0 - 1 EXECUTIVE SUMMARY
2.4.2.1 General
The above sections will consist of the following items:
?? Summary
?? Efforts in This Month
?? Efforts for the Next 30 Day
Item Summary will present the physical progress achieved that compared
to the planned progress. Major topics will also be covered in this Section.
For calculation of physical progress, refer to Engineering Deliverables
Tracking System, Procurement Deliverables Tracking System,
Construction Progress Tracking System and Project Management
Deliverables Tracking System.
Item Efforts in This Month and Efforts for the Next 30 Days will briefly
cover achievements for the reported month and items scheduled thirty
(30) days a head. The following subsections supplement the description
of each of the Engineering, Procurement, Construction are Project
Management sections.
2.4.2.2 SECTION 2 – 2 ENGINEERING PROGRESS REPORT
In the Summary Section, Efforts in This Month and Efforts for the Next
30 days will be presented according to the following discipline-oriented
categories:
?? General/Process
?? Vessel/Heat Exchangers
?? Machinery
?? Package Equipment
?? Piping
?? Civil
?? Building and Structural
?? Electrical
?? Instrumentation
Page 5 of Attachment (Section 2 – 2) show the Exhibits to be included in
this Section.
2.4.2.3 SECTION 2 – 3 PROCUREMENT PROGRESS REPORT
In this Section, following the Summary, Efforts in This Month and
Efforts for the Next 30 Days will be presented according to the following
procurement activity categories:
?? Purchasing : covers purchasing status by procurement milestones,
such as :
a. Release inquires
b. Receive quotation
c. Complete bid evaluation
d. Compliance bid tabulation submitted to COMPANY for
approval
e. Commitment or placement of purchase orders
?? Shipping : covers shipping status for each cargo
?? Expediting : covers topics as to the expediting activities.
Page 6 of Attachment (Section 2 – 3) show the Exhibits to be included in
this Section
2.4.2.4 SECTION 2 – 4 CONSTRUCTION PROGRESS REPORT
In the Summary Section, construction manpower assignment status will
be summarized accompanied by the construction manpower histogram as
an Exhibit. Achieved progress will be shown and compared to the
planned schedule with area breakdown.
Efforts in This Month and Efforts for the Next 30 Days will present
achievements and efforts for the next period.
Page 7 of Attachment (Section 2 – 4) show the Exhibits to be included in
this Section
2.4.2.5 SECTION 2 – 5 PROJECT MANAGEMENT DELIVERABLES
PROGRESS REPORT
In this Section, achieved progress will be shown and compared to the
planned schedule. Efforts in This Month and Efforts for the Next 30
Days will be presented achievements and efforts for the next period.
Page 8 of Attachment (Section 2 – 5) show the Exhibits to be included in
this Section.
2.4.3. SECTION 2 – 6 PROJECT COST REPORT
Major topics related to the Project Cost Status will be described in this Section as
well as change order report and manpower report.
The actual progress vs. planned progress will be shown in this Section by a
summary table indicating overall progress approval.
Page 9 of Attachment (Section 2 – 6) show the detail items to be included in this
Section.
2.4.4. SECTION 2 – 7 PROJECT SCHEDULE REPORT
Major topics related to the project schedule status will be described in this
Section with a breakdown for engineering, procurement and construction. In
addition to the above data, any significant delays in the schedule will be
highlighted with an explanation of the impact on the overall project schedule and
the planned corrective action.
In this Section, the Project Master Schedule indicating the current actual progress
will be included as Exhibits for Contract Project Master Schedule.
Page 10 of Attachment (Section 2 – 7) show the detail items to be included in this
Section.
2.4.5. SECTION 2 – 8 QUALITY PROGRAM REPORT
3. SUBMISSION TO COMPANY
Not later than the 7th calendar day of every month, a draft copy of the Monthly Report will be
submitted to COMPANY for review and approval.
5. ATTACHMENTS
Attachment : Cover, Contents and Forms of Monthly Report