Dhaka Mass Rapid Transit Development Project

SMCC-ITD JV Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR


Mr.Takayuki FUJITOMI DAILY REPORT Working Date:
Time:

Subject :

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty
Air Compressor Engineer
Trailer 12 m. Foreman Mostly Sunny
Mobile Crane Asst. Foreman
Water Pump Chief Survey Rain Drizzle
Generator Surveyor
Electric Welding Set Team Leader Heavy Rain
Crane Mounted Truck Heavy Equipment Operator
Pick Up Carpenter
Farm Tractor Bar Bender Temperature
Water Truck Mason
Survey Equipment Welder Max : ………..°C
Excavator Fitter
Jack Hammer Electrician Min : ………...°C
Compactor Labour
Dump Truck Safety
Backhoe Flagman
Crane 80 Ton Technician
Crane 90 Ton QC
Boring Crane Security
Boring Machine Other labour ___________
Total Equipment Total Manpower

Item Description Location Q’ty Unit Problems and Obstruction

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)


(…..……………………………) (…..……………………………) (…..……………………………)

Date : …………………….. Date : …………………….. Date : ……………………..


Dhaka Mass Rapid Transit Development Project
SMCC-ITD JV P.1/1
Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR


Mr.Takayuki FUJITOMI DAILY REPORT Working Date : 12/03/2019
Time : 8.00 - 20.00

Subject : DIRECT (Site Personnel and Operatives) / TSC Laboratory

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty
SMCC-ITD JV Lab team
Pic up car 1 TH Engineer 1 Sunny
TH Lab Technicial 1
BD Lab Technicial 1 Cloudy
BD Worker 1
Driver 1 Rain / Heavy Rain

Temperature

Max : …32……..°C

Min : …22……...°C

TOTAL MANPOWER & TOTAL WORK


Total Equipment 1 5
HOURS THIS DATE
CUMULATIVE TOTAL OF WORK HOURS
FROM PREVIOUS REPORT
TOTAL WORK HOURS FROM START OF
CONSTRUCTION
Problems and Obstructions
Item Description Location Q’ty Unit
Encountered
1 Compressive test concrete cylinder samping TSC Lab to Uttala yard CP-3,4 15 nos

P.496/78, P.497/82, Trial mix G35BP (352020)

at 7 Day

2 Change empty mound w/ used mould to Rig. TSC Lab to Rig.1 , 2 12 nos

No.1 and 2, Take off , Curing work , Cleaning ,

Shutering oil P.485/34, P.494/72

3 Cleaning lab TSC Lab

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)


(Narongyod Palasuk) (…..……………………………) (…..……………………………)

Date : ……12/03/2019….. Date : …………………….. Date : ……………………..


Dhaka Mass Rapid Transit Development
SMCC-ITD JV Project
Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR -00001

Mr.Takayuki FUJITOMI DAILY REPORT Working Date:

Time:

Subject : INDIRECT (Office and Admin Personnel)

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty MH

Sunny

Cloudy

Rain / Heavy Rain

Temperature

Max : ………..°C

Min : ………...°C

Total Equipment 0 Total Manpower & Manhours 0 0


Problems and Obstructions
Item Description Location Q'ty Unit
Encountered

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)


(…..……………………………) (…..……………………………) (…..……………………………)

Date : …………………….. Date : …………………….. Date : ……………………..


Dhaka Mass Rapid Transit Development
SMCC-ITD JV Project
Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR -00001

Mr.Takayuki FUJITOMI DAILY REPORT Working Date:

Time:

Subject : INDIRECT (Office and Admin Personnel)

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty MH

Sunny

Cloudy

Rain / Heavy Rain

Temperature

Max : ………..°C

Min : ………...°C

Total Equipment 0 Total Manpower & Manhours 0 0


Problems and Obstructions
Item Description Location Q'ty Unit
Encountered

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)


(…..……………………………) (…..……………………………) (…..……………………………)

Date : …………………….. Date : …………………….. Date : ……………………..


Dhaka Mass Rapid Transit Development
SMCC-ITD JV Project
Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR-00001

Mr.Takayuki FUJITOMI DAILY REPORT Working Date:

Time:

Subject : INDIRECT (Office and Admin Personnel)

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty MH
Service Vehicle Van 3 Project Manager 1 8
Service Vehicle SUV 3 Co-Project Manager 1 8 Sunny
Service Pick-up 1 Chief Construction Manager 1 8
Computers 30 Construction Manager 1 8 Cloudy
Printers 2 Safety Manager 1 8
Safety Officer 1 8 Rain / Heavy Rain
Admin & Accounting Manager 2 16
Admin Manager 1 8
Admin Staff 4 32 Temperature
Accounting Manager 1 8
Procurement Manager 1 8 Max : ………..°C
Procurement Staff 1 8
Document Control Manager 1 8 Min : ………...°C
Document Control Staff 2 16
Technical Engineer 1 8
Cadd Operator 1 8
QA Engineer 1 8
Senior Site Engineer 2 16
Site Engineer 1 8
Civil Engineer 2 16
QS Engineer 1 8
Survey Engineer 1 8
Service Drivers 8 64
Office and Accommodation Helpers 9 72

Total Equipment 39 Total Manpower & Manhours 46 368

Problems and Obstructions


Item Description Location Q'ty Unit
Encountered

1.0 Administrative works and preparations. Temporary site office n/a


Procurement process, includes canvassing,
2.0 --do-- n/a
quotations and P.O. preparations
Drawings preparations, such as traffic management
3.0 --do-- n/a
plans, etc.
Documentations and correspondence, such as
4.0 --do-- n/a
Letters and Submittals.

5.0 QA/QC works preparations and documentations. --do-- n/a

6.0 EHS preparation works. --do-- n/a

7.0 Manpower pooling and interviews. --do-- n/a

8.0 Accounting works and documentations. --do-- n/a

9.0 Survey works preparations and documentations. --do-- n/a

Daily site works / activities monitoring and


10.0 --do-- Proposed Site Construction Yards
documentations
(Gabtoli, 0.5Ha, & 0.3Ha) not yet
handover

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)


(…..……………………………) (…..……………………………) (…..……………………………)

Date : …………………….. Date : …………………….. Date : ……………………..


Dhaka Mass Rapid Transit Development Project
SMCC-ITD JV Contract No. CP-06

Attention: Ref./No.: SMCC-ITD JV/CP06/DR

Mr.Takayuki FUJITOMI DAILY REPORT Working Date: 09/02/2019

Time: 08:00 - 17:00

Subject : DIRECT (Site Personnel and Operatives) / TSC Batching Plant

Equipment and Manpower Report


Weather Report
Equipment Q'ty Manpower Q'ty MH
Sub-Contractor
Concrete mixer 3 Batching plant team (SMCC-ITD JV) Sunny
- Engineer 2
- Technician, Supervisor & Operator 11 Cloudy
- Safety officer 1
SMCC-ITD JV - Security 2 Rain / Heavy Rain
Office container 2 - Flag man 2
Office container for survey 1 DCDL (Drainage and Access road work)
Generator 1 - Engineer 1 Temperature
Drinking Water tank 2 - Foreman 1
Welding machine 2 - Skill labor 6 Max : ………..°C
Wheel Loader 1 - Unskill labor 4
Batching Plant 2 Foundation work(Abid Enterprise) Min : ………...°C
Mobile crane 2 - Engineer 0
Silo 2 - Supervisor 0
- Skill labor 4
Total Equipment 18 - Unskill labor (daily hire) 0
Toilet, Lab ,Pond (Abid Enterprise)
Material - Engineer 1
- Foreman 1
Cement mortar 0 - Skill labor 20
Formwork 0 - Unskill labor 7
Concrete 0 Stockpile,Curing pond, Office building (Abid Enterprise)
- Engineer 1
- Foreman 0
- Skill labor 8
Rebar 0 - Unskill labor 18
Brick 0 Integrety
Sand for compacted 0 - Engineer 0
- Skill labor 0
Concrete Technology
- Engineer 7
- Supervisor 3
- Foreman 2
- Skill labor 2
Silo Installation (Bashundhora Group)
- Engineer 7
- Supervisor 2
- Foreman 0
- Skill labor 3
Confidence
- Engineer 0
- Foreman 1
- Skill labor 2
- Unskill labor 0
TOTAL MANPOWER & TOTAL WORK HOURS
119
THIS DATE
CUMULATIVE TOTAL OF WORK HOURS FROM
PREVIOUS REPORT
TOTAL WORK HOURS FROM START OF
CONSTRUCTION
Problems and Obstructions
Item Description Location Q'ty Unit
Encountered
Batching plant 2 : Installation batching plant work is
1.0 being continue Have a lot of trees on site.

Laboratory : Plastering and fioor net finishing work is Crane's boom cannot move easily
2.0
being continue. because of trees.

Office building : Earth excavation in being continue Wheel loader cannot move some
3.0
for foundation place because there's too many trees.

Internal road : Earth excavation work is being


4.0 Batching plant
continue.
Stockpile : Earth excavation work is being continued
5.0
and casting concrete lean.
Curing pond : Re-bar bending continued for
6.0
foundation

7.0 Drainage : Earth excavation work is being continue.

Note :

Report by (SMCC-ITD JV) Review by (SMCC-ITD JV) Received by (NKDM)

( Panomthong Jantamee ) ( Tawatchai Veerapradit ) (…..……………………………)

Date : …………………….. Date : …………………….. Date : ……………………..


DAILY PRODUCTION REPORT
CONTRACT NO.: TITLE AND LOCATION:

CONTRACTOR: SUMITOMO MITSUI CONSTRUCTION CO., LTD. PROJECT SUPT.:

AM WEATHER: PM WEATHER: MAX. TEMP.

WORK PERFORMED TODAY

WORK LOCATION AND DESCRIPTION EMPLOYER

WAS A JOB SAFETY MEETING HELD THIS DATE? YES NO


(If YES attach copy of the meeting minutes)
JOB SAFETY
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE? YES NO
(If YES attach copy of completed OSHA report)

WAS TRENCHING/SCAFFOLD/HV ELECTRICAL/HIGH WORK DONE? YES NO


(If YES attach a statement or checklist showing inspection performed)

WAS HAZARDOUS MATERIAL/WASTE RELEASED TO THE ENVIRONMENT? YES NO

(If YES attach a description of incident and proposed action)


LIST SAFETY ACTION TAKEN TODAY/SAFETY INSPECTION CONDUCTED:

EQUIPMENT/MATERIAL RECEIVED TODAY TO BE INCORPORATED IN JOB:

CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY, INCLUDE NUMBER AND HOURS USED TODAY:

CONTRACTOR REPRESENTATIVE
DATE:

REPORT NO.:

MIN. TEMP.

NUMBER TRADE HOURS

TOTAL WORK HOURS ON JOBSITE THIS


DATE: 0

CUMULATIVE TOTAL OF WORK HOURS


FROM PREVIOUS REPORT: 0

TOTAL WORK HOURS FROM START OF


CONSTRUCTION: 0
YES SAFETY REQUIREMENTS HAVE BEEN MET

D TODAY:

TOR REPRESENTATIVE DATE


DATE:
DAILY REPORT
CONTRACT NO.: TITLE AND LOCATION: REPORT NO.:

CONTRACTOR: SMCC-ITD JV PROJECT SUPT.:

AM WEATHER: PM WEATHER: MAX. TEMP. MIN. TEMP.

WORK PERFORMED TODAY

WORK LOCATION AND DESCRIPTION EMPLOYER NUMBER TRADE HOURS

WAS A JOB SAFETY MEETING HELD THIS DATE? YES NO TOTAL WORK HOURS ON JOBSITE THIS
DATE: 0
(If YES attach copy of the meeting minutes)
JOB SAFETY
WERE THERE ANY LOST TIME ACCIDENTS THIS DATE? YES NO
(If YES attach copy of completed OSHA report)
CUMULATIVE TOTAL OF WORK HOURS
FROM PREVIOUS REPORT: 0

WAS TRENCHING/SCAFFOLD/HV ELECTRICAL/HIGH WORK DONE? YES NO


(If YES attach a statement or checklist showing inspection performed)

TOTAL WORK HOURS FROM START OF


0
WAS HAZARDOUS MATERIAL/WASTE RELEASED TO THE ENVIRONMENT? YES NO CONSTRUCTION:

(If YES attach a description of incident and proposed action)


LIST SAFETY ACTION TAKEN TODAY/SAFETY INSPECTION CONDUCTED:
YES SAFETY REQUIREMENTS HAVE BEEN MET

EQUIPMENT/MATERIAL RECEIVED TODAY TO BE INCORPORATED IN JOB:

CONSTRUCTION AND PLANT EQUIPMENT ON JOB SITE TODAY, INCLUDE NUMBER AND HOURS USED TODAY:

1 - Boom Truck 5T -------- 8 Hours ----- Hauling of Concrete Barriers


1 - Generator 25kVA ------ 8 Hours ----- Power supply for Temp. satelite office
1 - Generator 10kVA ------ 8 Hours ----- Chipping & Cutting of Pavement
1 - Concrete Cutter -------- 8 Hours ----- Cutting of Pavement
1 - Demolition Hammer -- 8 Hours ------ Chipping of Pavement

Reported by (SMCC-ITD JV) Review by (SMCC-ITD VJ) Received by (NKDM)

Name: Name: Name:


Date: Date: Date: