DAFTAR HARGA SATUAN BAHAN

URAIAN BAHAN Keterangan HRG SATUAN SATUAN


MATERIAL SEMEN naik 5%
Semen PC / 50 kg 65,000.00 /zak
Semen Putih 40 kg (ex Tiga Roda) 84,000.00 /zak
Semen warna 10,500.00 /Kg
Semen Merah 183,750.00 /M3
MATERIAL MORTAR UTAMA (MU) naik 5%
Plester premium (MU 100) 63,000.00 /zak 40Kg
Plester trasraam (MU 101) 94,500.00 /zak 40Kg
Acian plesteran / beton expose (MU 200) 166,425.00 /zak 40Kg
Acian plesteran (MU 250) 101,850.00 /zak 40Kg
Acian profil (MU 260) 200,025.00 /zak 25Kg
Acian putih (MU 270) Perekat keramik area lembab 163,800.00 /zak 25Kg
Finish plester (MU 290) 101,850.00 /zak 40Kg
Pasangan bata (MU 300) 53,025.00 /zak 40Kg
Pasangan & plesteran bata (MU 301) 60,375.00 /zak 40Kg
Perekat bata ringan (MU 380) 157,500.00 /zak 40Kg
Perekat keramik dinding (MU 400) 142,800.00 /zak 25Kg
Pengisi naad keramik (MU 408) 12,075.00 /Kg
Perata lantai (MU 440) 56,700.00 /zak 40Kg
Perata lantai premium (MU 445) 103,950.00 /zak 40Kg
Perekat keramik lantai (MU450) 204,750.00 /zak 40Kg
Perekat keramik daerah basah (MU 460) 449,400.00 /zak 25Kg
Perekat keramik diatas keramik (MU 480) 241,500.00 /zak 25Kg
Multi Purpose Tile Adhesive (MU 485) 1,155,000.00 /40Kg set
Fast Setting Tile Adhesive (MU 490) 336,000.00 /zak 25Kg
Perekat mortar & beton / Bonding Agent (MU L-500) 210,525.00 / 2Kg
Pelapis kedap air (MU 600) 1,113,000.00 /30Kg set
Floor Hardener (MU 700) 144,375.00 /zak 25Kg
Non shrink grout (MU 800) 161,700.00 /zak 40Kg
Perbaikan permukaan beton (MU 830) 269,850.00 /zak 40Kg
Pengisi celah beton / Finish Coat Repair (MU 840) 336,000.00 / 25Kg set
MATERIAL PASIR, BATU & BATA naik 5%
Pasir beton 270,375.00 /M3
Pasir extra beton 273,000.00 /M3
Pasir Putih (Bangka) 315,000.00 /M3
Pasir Pasang 265,125.00 /M3
Kapur Padam 210,000.00 /M3
Pasir Urug darat 291,375.00 /M3
Sirtu 256,200.00 /M3
Batu pecah / Split ukuran 1-2 cm 267,750.00 /M3
Batu pecah / Split ukuran 2-3 cm 269,500.35 /M3
Koral beton 286,125.00 /M3
Batu kali belah 257,250.00 /M3
Makadam / batu pecah 5-7 cm 262,500.00 /M3
Abu batu 5 mm 241,500.00 /M3
Sreening 5-13 mm 255,937.50 /M3
Batu bata press mesin 700.35 /bh
Batu bata uk. 5 x 11 x 23 cm (ukuran besar) proses tangan 630.00 /bh
Batu bata uk. 4 x 9.5 x 20 cm (ukuran kecil) proses tangan 512.40 /bh
Batu bata ringan (ex Hebel), 10x16x60 cm 889,875.00 /M3
8,542.80 /bh
Batu bata ringan (ex Hebel), 7x16x60 cm 889,875.00 /M3
5,979.96 /bh
Batu bata ringan (ex Broco), 10x16x60 cm 889,875.00 /M3
8,542.80 /bh
Batu bata ringan (ex Broco), 7x16x60 cm 880,687.50 /M3
5,918.22 /bh
Batako Semen (semen, pasir, abu batu) 9x19x39 cm 4,200.00 /bh
Batako Semen (semen, batu apung, pumis) 9x19x39 cm 4,987.50 /bh
Glassblock 20/20 31,500.00 /bh
Rooster beton 20x20x7 cm 6,063.75 /bh
Rooster bata merah 12x11,5x24 cm 5,075.70 /bh
Lempengan garis uk. 9x19x39 cm 3,675.00 /bh
Tanah merah 262,500.00 /M3
I j u k 31,500.00 /kg
MATERIAL BESI naik 5%
Besi beton polos 13,125.00 /kg
Besi beton ulir 13,125.00 /kg
Besi plat strip 14,542.50 /kg
Baja profil siku 14,455.35 /kg
Baja WF 13,125.00 /kg
Baja H Beam 14,437.50 /kg

RAB - 01
Baja Kanal C (Channal) 14,568.75 /kg
Besi plat hitam (segala ukuran) 15,750.00 /kg
Besi plat putih (segala ukuran) 14,595.00 /kg
Besi plat bordes 26,512.50 /kg
Kanal C galvaspan HI-TEN, type C 100.16 70,612.50 /M'
Kanal C galvaspan HI-TEN, type C 100.20 84,525.00 /M'
Kanal C galvaspan HI-TEN, type C 125.16 73,500.00 /M'
Kanal C galvaspan HI-TEN, type C 125.20 85,050.00 /M'
Kanal C galvaspan HI-TEN, type C 150.16 83,737.50 /M'
Kanal C galvaspan HI-TEN, type C 150.20 105,000.00 /M'
Kanal C galvaspan HI-TEN, type C 150.25 115,500.00 /M'
Kanal C galvaspan HI-TEN, type C 200.16 105,000.00 /M'
Kanal C galvaspan HI-TEN, type C 200.20 131,250.00 /M'
Kanal C galvaspan HI-TEN, type C 200.25 162,750.00 /M'
Besi Wire Mesh DM-8F1, 540 x 210 cm (11,34 M2) 567,541.00 /lembar 52,550.09 /M2
Besi Wire Mesh DM-7F1, 540 x 210 cm (11,34 M2) 434,542.00 /lembar 40,235.37 /M2
Besi Wire Mesh DM-6F1, 540 x 210 cm 319,271.00 /lembar 29,562.13 /M2
Besi Wire Mesh DM-5F1, 540 x 210 cm 224,381.00 /lembar 20,776.02 /M2
Besi Wire Mesh DM-4, 540 x 210 cm 166,126.00 /lembar 15,382.04 /M2
Kawat beton 20,212.50 /kg
Kawat Las 31,500.00 /m
Kawat duri 10 kg (60 m') 165,375.00 /roll
Paku halus (2 - 3 cm) 19,950.00 /kg
Paku ukuran sedang (4 - 5 cm) 18,637.50 /kg
Paku ukuran sedang (6 - 7 cm) 15,356.25 /kg
Paku ukuran (10-15 cm) 15,356.25 /kg
Seng Gelombang 180x90x0,05 47,250.00 /lmbr
Seng Gelombang 180x90x0,03 64,050.00 /lmbr
Plat Seng tebal 0,5 mm, lebar 90 cm 31,500.00 /M'
Plat Seng tebal 0,3 mm, lebar 90 cm 36,750.00 /M'
Paku Seng 26,250.00 /kg
Hollow 40x40 mm galvanized (tebal standart) Rgk plafond/Partisi 5,250.00 /M'
Hollow 20x40 mm galvanized (tebal standart) Rgk plafond/Partisi 5,250.00 /M'
Hollow 40x40 mm dimenie (tebal standart) Rgk plafond/Partisi 6,300.00 /M'
Hollow 20x40 mm dimenie (tebal standart) Rgk plafond/Partisi 4,725.00 /M'
Metal Furing 75 mm Rgk plafond/Partisi 9,450.00 /M'
Hollow 40x40x1 mm Rgk. Pintu besi/konstruksi 219,450.00 /btg/6m
Hollow 20x40x1 mm Rgk. Pintu besi/konstruksi 110,250.00 /btg/6m
Besi Hollow 40x40x1,2 (rangka utama) Rgk. Pintu besi/konstruksi 225,750.00 /btg/6m
Besi Hollow 20x40x1,2 (rangka pembagi) Rgk. Pintu besi/konstruksi 115,500.00 /btg/6m
Folding Gate :
- Folding Gate, bahan besi plate tbl. 0.3 mm lengkap dg finishing & kunci dll. 336,000.00 /m2
- Folding Gate, bahan besi plate tbl. 0.4 mm lengkap dg finishing & kunci dll. 357,000.00 /m2
- Folding Gate, bahan besi plate tbl. 0.5 mm lengkap dg finishing & kunci dll. 367,500.00 /m2
- Folding Gate, bahan galvalum, tbl. 0.3 mm lengkap dg finishing & kunci dll. 372,750.00 /m2
- Folding Gate, bahan galvalum, tbl. 0.4 mm lengkap dg finishing & kunci dll. 393,750.00 /m2
- Folding Gate, bahan galvalume, tbl. 0.5 mm lengkap dg finishing & kunci dll. 414,750.00 /m2
Rolling Door :
- Folding Gate, bahan besi plate tbl. 0.3 mm lengkap dg finishing & kunci dll. 241,500.00 /m2
- Folding Gate, bahan Galvalum tbl. 0.3 mm lengkap dg finishing & kunci dll. 294,000.00 /m2
- Folding Gate, bahan Allumunium tbl. 0.3 mm lengkap dg finishing & kunci dll. 336,000.00 /m2
MATERIAL KAYU naik 5%
Kayu Meranti basah
- Balok Meranti basah (8/15,8/12,6/15,6/12, 5/10x400 cm) 3,360,000.00 /M3
- Kasau Meranti basah (5/7x400, 4/6x400 cm) 2,730,000.00 /M3
- Reng (3/4x400, 2/3x400) 2,625,000.00 /M3
- Papan Meranti basah (3/30, 3/20 & 2/30x400 cm) 4,200,000.00 /M3
Kayu Rimba Campuran (KRC) basah
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) 2,415,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) 1,995,000.00 /M3
- Reng (3/4x400, 2/3x400) 1,890,000.00 /M3
- Papan (3/30, 3/20 & 2/30x400 cm) ( u/. Bekisting ) 3,045,000.00 /M3
- Kayu Dolken (kayu Galam 8-10cm, L=4m) ( u/. Bekisting ) 36,750.00 /btg
- Plastik cor ( u/. Bekisting ) 6,300.00 /M2
Kayu Terentang
- Papan uk. 3/30x400, 3/20x400 & 2/30x400 cm ( u/. Bekisting ) 2,835,000.00 /M3
Kayu Kamper Samarinda basah
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,350,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 6,825,000.00 /M3
- Reng (3/4x400) (u/. Rngk.Atap) 5,250,000.00 /M3
- Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 8,505,000.00 /M3
Kayu Borneo/Meranti Super
- Balok Borneo/Meranti Super, kelas-3 (u/. Rngk.Atap) 4,725,000.00 /M3
- Kasau Borneo/Meranti Super (u/. Rngk.Atap) 4,462,500.00 /M3
Kayu Kruing
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 5,040,000.00 /M3

RAB - 02
- Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 4,725,000.00 /M3
- Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 6,825,000.00 /M3
Kayu Kamper Medan
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 5,775,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 5,512,500.00 /M3
- Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 6,037,500.00 /M3
Kayu Bengkirai
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,350,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 7,140,000.00 /M3
- Papan (3/20 & 2/30x400 cm) (u/. Rngk.Atap) 7,612,500.00 /M3
Kayu Kamper Singkil
- Balok (8/15,8/12,6/15,6/12, 5/10x400 cm) (u/. Rngk.Atap) 7,350,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) (u/. Rngk.Atap) 7,140,000.00 /M3
Kayu Jati Kelas I (Jawa Timur)
- Balok Jati Jawa Timur, Kelas-I (u/. Kosen/pintu) 57,750,000.00 /M3
- Papan Jati Jawa Timur, Kelas-I (u/. Kosen/pintu) 60,375,000.00 /M3
- Balok Jati Jawa Timur, Super (u/. Kosen/pintu) 68,250,000.00 /M3
- Papan Jati Jawa Timur, Super (u/. Kosen/pintu) 70,875,000.00 /M3
Kayu Jati Kelas II Basah (Jawa Tengah)
- Balok uk. 6x15x100 - 190 cm 38,850,000.00 /M3
- Balok uk. 6x15x200 - 240 cm 47,250,000.00 /M3
- Balok uk. 6x15x240 - 290 cm 52,500,000.00 /M3
- Balok uk. 6x15x240 - 340 cm 52,500,000.00 /M3
- Balok uk. 6x15x340 - 390 cm 63,000,000.00 /M3
Kayu Kruing oven
- Balok Kamper Kruing (oven) (u/. Kosen/pintu) 6,300,000.00 /M3
- Balok Kamper Medan (oven) (u/. Kosen/pintu) 6,300,000.00 /M3
Kayu Kamper Singkil oven
- Balok Kamper Singkil (oven) (u/. Kosen/pintu) 7,875,000.00 /M3
- Papan Kamper Singkil (oven) (u/. Kosen/pintu) 8,137,500.00 /M3
Kayu Kamper Samarinda (kering oven)
- Balok (8/12 x400 & 6/15x400 cm) (u/. Kosen) 9,975,000.00 /M3
- Kasau (5/7x400, 4/6x400 cm) 9,240,000.00 /M3
- Reng (3/4x400) 7,140,000.00 /M3
- Papan (3/20x400 cm) 10,395,000.00 /M3
- Papan (4/30, 4/25x400 cm) (u/. Pintu) 10,395,000.00 /M3
- Balok Kamper Samarinda, super (oven) (u/. Kosen/pintu) 10,500,000.00 /M3
- Papan Kamper Samarinda, super (oven) (u/. Kosen/pintu) 11,025,000.00 /M3
- Papan Meranti oven (u/. Kosen/pintu) 6,300,000.00 /M3
Kayu Bengkirai
- Balok Bengkirai (u/. Kosen/pintu) 7,875,000.00 /M3
- Papan Bengkirai (u/. Kosen/pintu) 8,137,500.00 /M3
Kayu Merbau
- Balok Merbau (oven) (u/. Kosen/pintu) 10,500,000.00 /M3
- Papan Merbau (oven) (u/. Kosen/pintu) 10,762,500.00 /M3
MATERIAL MULTIPLEKS naik 5%
Multipleks, 1220x2440x25 mm 299,250.00 /lmbr
Multipleks, 1220x2440x22 mm 278,250.00 /lmbr
Multipleks, 1220x2440x20 mm 252,000.00 /lmbr
Multipleks, 1220x2440x18 mm 207,900.00 /lmbr
Multipleks, 1220x2440x15 mm 187,950.00 /lmbr
Multipleks, 1220x2440x12 mm 156,450.00 /lmbr
Multipleks, 1220x2440x9 mm 110,250.00 /lmbr
Multipleks, 1220x2440x6 mm 80,850.00 /lmbr
Multipleks, 1220x2440x4 mm 57,750.00 /lmbr
Teakwood 1220x2440x3 mm 105,000.00 /lmbr
Plywood Sungkai, uk. 1220x2440x3 mm 105,000.00 /lmbr
Plywood Sungkai, uk. 1220x2440x4 mm 110,250.00 /lmbr
Plywood Sungkai, uk. 1220x2440x18 mm (1 muka) 232,575.00 /lmbr
Plywood Sungkai, uk. 1220x2440x18 mm (2 muka) 269,850.00 /lmbr
Bloktik, uk. 1220x2440x18 mm (1 muka) 248,587.50 /lmbr
Melamin, uk. 1220x2440x3 mm (mengkilap) 82,425.00 /lmbr
Formika, 92 x 212 mm 89,250.00 /lmbr
HPL 4' x 8' 183,750.00 /lmbr
MATERIAL GYPSUM, CALSIUM, GRC naik 5%
Gypsum board 9 mm (water resistants) 102,500.00 /lmbr
Gypsum board 9 mm 59,000.00 /lmbr
Gypsum board 12 mm 78,750.00 /lmbr
Calcium Silikat 6 mm 106,365.00 /lmbr
Gypsum Tile 600x1200x9mm 18,375.00 /lmbr
AcousticTile 600x1200x15 mm Ex Armstrong 37,800.00 /lmbr
Profil allumunium Main Tee (p. 3,6m) 7,291.67 /m'
Profil allumunium Cross Tee (p. 1,2 m) 6,562.50 /m'
Profil allumunium Cross Tee (p. 0,60 m) 8,750.00 /m'
Gypsum bubuk (compound) 4,725.00 /kg
Paku skrup gypsum 42,000.00 /Kg

RAB - 03
Textile tape 18,375.00 /roll
List gypsum profil 5-10 cm 5,250.00 /m'
List plafond allumunium (Wall angle) 6,825.00 /m'
GRC BOARD, 1220x2440x5 mm 73,500.00 /lmbr
GRC BOARD, 1220x2440x6 mm 84,000.00 /lmbr
GRC BOARD, 1220x2440x8 mm 115,500.00 /lmbr
GRC BOARD, 1220x2440x10 mm 136,500.00 /lmbr
GRC SPR PANEL, 1220x2440x9 mm 183,750.00 /lmbr
GRC SPR PANEL, 1220x2440x12 mm 210,000.00 /lmbr
GRC SPR PANEL, 1220x2440x15 mm 262,500.00 /lmbr
Compound GRC (A +B) 60,375.00 /kg
Asbes plat 100x100x0,4 cm 47,250.00 /M2
Lem kayu 42,000.00 /Kg
MATERIAL KACA naik 5%
Kaca polos tempered 12 mm, ex Asahi Mas harga terpasang 619,500.00 / M2
Kaca warna tempered 12 mm, ex Asahi Mas harga terpasang 813,750.00 / M2
Kaca polos tempered 12 mm (lubang dll), khusus pintu harga terpasang 672,000.00 / M2
Kaca warna tempered 12 mm (lubang dll), khusus pintu harga terpasang 866,250.00 / M2
Kaca tempered 10 mm, ex Asahi Mas harga terpasang 558,600.00 / M2
Kaca polos 12 mm, ex Asahi Mas harga terpasang 446,250.00 / M2
Kaca polos 10 mm, ex Asahi Mas harga terpasang 393,750.00 / M2
Kaca polos 8 mm, ex Asahi Mas harga terpasang 236,250.00 / M2
Kaca polos 8 mm tempered, ex Asahi Mas harga terpasang 404,250.00 / M2
Kaca warna 8 mm, ex Asahi Mas harga terpasang 262,500.00 / M2
Kaca warna 8 mm, ex Asahi Mas (Reflective) harga terpasang 393,750.00 / M2
Kaca polos 6 mm tempered, ex Asahi Mas harga terpasang 215,000.00 / M2
Kaca polos 6 mm, ex Asahi Mas harga terpasang 168,000.00 / M2
Kaca warna 6 mm, ex Asahi Mas harga terpasang 183,750.00 / M2
Kaca polos 5 mm, ex Asahi Mas harga terpasang 147,000.00 / M2
Kaca Stopsol Plat Laminated, polos tebal 6 mm harga terpasang 420,000.00 / M2
Kaca Stopsol Plat Laminated, polos tebal 8 mm harga terpasang 708,750.00 / M2
Kaca Stopsol Plat Laminated, polos tebal 10 mm harga terpasang 1,076,250.00 / M2
MATERIAL ALLUMUNIUM naik 5%
ALLUMUNIUM PRODUK YKK
Profil kosen Allumunium 1 3/4 x 3", Silver Clear Anodized ex YKK 94,500.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Silver Clear Anodized ex YKK 115,500.00 / M'
Profil Frame Allumunium Pintu kaca, Silver Clear Anodized ex YKK 105,000.00 / M'
Profil Frame Allumunium Jendela kaca, Silver Clear Anodized ex YKK 89,250.00 / M'
Profil kosen Allumunium 1 3/4 x 3", Black/Brown Anodized ex YKK 115,500.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Black/Brown Anodized ex YKK 157,500.00 / M'
Profil Frame Allumunium Pintu kaca, Black/Brown Anodized ex YKK 147,000.00 / M'
Profil Frame Allumunium Jendela kaca, Black/Brown Anodized ex YKK 105,000.00 / M'
Profil kosen Allumunium 1 3/4 x 3", Powder Coating ex YKK 147,000.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Powder Coating ex YKK 168,000.00 / M'
Profil Frame Allumunium Pintu kaca, Powder Coating ex YKK 161,700.00 / M'
Profil Frame Allumunium Jendela kaca, Powder Coating ex YKK 126,000.00 / M'
ALLUMUNIUM PRODUK ALEXINDO
Profil kosen Allumunium 1 3/4 x 3", Silver Clear Anodized ex Alexindo 52,500.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Silver Clear Anodized ex Alexindo 68,250.00 / M'
Profil Frame Allumunium Pintu kaca, Silver Clear Anodized ex Alexindo 63,000.00 / M'
Profil Frame Allumunium Jendela kaca, Silver Clear Anodized ex Alexindo 52,500.00 / M'
Profil kosen Allumunium 1 3/4 x 3", Black/Brown Anodized ex Alexindo 68,250.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Black/Brown Anodized ex Alexindo 78,750.00 / M'
Profil Frame Allumunium Pintu kaca, Black/Brown Anodized ex Alexindo 73,500.00 / M'
Profil Frame Allumunium Jendela kaca, Black/Brown Anodized ex alexindo 63,000.00 / M'
Profil kosen Allumunium 1 3/4 x 3", Powder Coating serat kayu, ex Alexindo 136,500.00 / M'
Profil kosen Allumunium 1 3/4 x 4", Powder Coating serat kayu, ex Alexindo 168,000.00 / M'
Profil Frame Allumunium Pintu kaca, Powder Coating serat kayu, ex Alexindo 157,500.00 / M'
Profil Frame Allumunium Jendela kaca, Powder Coating serat kayu, ex Alexindo 126,000.00 / M'
Sealant kaca 8,531.25 / M'
Karet kaca 2,887.50 / M'
Allumunium plat tebal 0,4 mm, uk. 1000x2000 mm 129,675.00 /lmbr
Allumunium plat tebal 0,4 mm, uk. 1220x2440 mm 192,675.00 /lmbr
Allumunium plat tebal 0,5 mm, uk. 1000x2000 mm 162,225.00 /lmbr
Allumunium plat tebal 0,5 mm, uk. 1220x2440 mm 240,975.00 /lmbr
Allumunium Bordes tebal 2 mm, uk. 1000x2000 mm 752,325.00 /lmbr
Allumunium Bordes tebal 3 mm, uk. 1000x2000 mm 1,128,225.00 /lmbr
MATERIAL ATAP naik 5%
Genteng Plentong Glazur, ex Jatiwangi 4,462.50 /bh
Nok Genteng Plentong Glazur, ex Jatiwangi 7,875.00 /bh
Genteng Plentong tidak Glazur, ex Jatiwangi 3,675.00 /bh
Nok Genteng Plentong tidak Glazur, ex Jatiwangi 6,300.00 /bh
Genteng Keramik Glazur ex Kanmuri Standar Espanica Natural 12,285.00 /bh
Genteng Keramik Glazur ex Kanmuri Standar Espanica Medium 13,125.00 /bh
Genteng Keramik Glazur ex KIA Stadar Natural 13,125.00 /bh
Nok Genteng Keramik Glazur, ex KIA Stadar Natural 26,565.00 /bh

RAB - 04
Genteng Keramik ex Cisangkan type Victoria 12,600.00 /bh
Nok Genteng Keramik, ex Cisangkan 26,250.00 /bh
Genteng Morando Glazur, ex Jatiwangi 3,675.00 /bh
Genteng Morando tidak Glazur, ex Jatiwangi 4,200.00 /bh
Nok Genteng Morando tidak Glazur, ex Jatiwangi 10,500.00 /bh
Genteng Beton ex Karangpilang (berwarna) 12,600.00 /bh
Genteng Nok Beton Karangpilang (berwarna) 26,250.00 /bh
Djabes gelombang kecil (B100) uk. 300x105, tbl. 6mm 141,750.00 /Lbr
Djabes gelombang kecil (B100) uk. 300x105, tbl. 5mm 126,000.00 /Lbr
Djabes gelombang kecil (K200) uk. 300x105, tbl. 4mm 94,500.00 /Lbr
Skrup + ring 472.50 /bh
Atap Sirap 236,250.00 /M2
Paku sirap 31,500.00 /Kg
Atap Gelombang GALVALUME, type SPANDEK LYSAGHT, tebal 0,75 (ex. CV. Cipta Prima Sentosa) 177,975.00 /M2
Atap Gelombang GALVALUME, type SPANDEK LYSAGHT, tebal 0,50 (ex. CV. Cipta Prima Sentosa) 91,875.00 /M2
Atap Metal ZINCALUM, type ada sterofoam 5cm 210,000.00 /M2
Atap Metal Spandex Zincalum tebal 0,5 mm (ex. CV. Cipta Prima Sentosa) 121,800.00 /M2
MATERIAL WATERPROOFING
Lapisan Coating PF Primer waterproofing atap beton 18,375.00 /M2
Waterproofing Membrane, Sopralene 4 mm waterproofing atap beton 157,500.00 /M2
Waterproofing Membrane, Gardigum 4 mm waterproofing atap beton 141,750.00 /M2
Waterproofing jenis coating ex Sika/AM/setara 52,500.00 /Kg
MATERIAL KERAMIK, MARMER, GRANIT & HOMOGENOUS TILE
Granit Import
- Granit Import (Red China & Black China) jenis Slab 577,500.00 /M2
- Granit Import (Nero Absolute India) jenis slab 1,023,750.00 /M2
Homogenous Tile Niro Granite
- Niro Granite 80x80 Cm 257,250.00 /M2
- Niro Granite 60x60 Cm 231,000.00 /M2
- Niro Granite 60x60 Cm (un-polish) 210,000.00 /M2
- Niro Granite 40x40 Cm 168,000.00 /M2
Homogenous Tile Granito
- Granito Salsa 60x60 Cm (polished) W : Pearl White, Ivory 255,255.00 /M2
- Granito Salsa 60x60 Cm (polished) W : Water stone, White stone 313,005.00 /M2
- Granito group Diamon 60x60 Cm (polished) W : Water stone, White stone 272,580.00 /M2
- Granito Palazzo 60x60 Cm (polished) W : Sanrosa 331,485.00 /M2
- Granito Aurora group Silver 60x60 Cm (polished) W : Slamon type miror 301,455.00 /M2
- Granito Aurora Group Gold 60x60 Cm (polished) W : Astro 371,910.00 /M2
- Granito Lunar group Silver 60x60 Cm (un-polished) W : Terra, Zephyr type Rustic 259,875.00 /M2
- Granito Lunar group Gold 60x60 Cm (un-polished) W : Amber, Quartz type Rustic 307,461.00 /M2
- Granito Lunar group Bronze 60x60 Cm (un-polished) W : Solar, Helium type Rustic 248,325.00 /M2
- Granito Lunar 60x60 Cm (un-polished) W : Alumina, Oxide 358,050.00 /M2
- Granitto Aurora 30x60 Cm (polished), Group Silver W : Waffel, Latte type miror 310,695.00 /M2
- Granitto Lunar 30x60 Cm (Un-polished), Group Bronze W : Solar, Helium type Rustic 257,565.00 /M2
- Granitto Lunar 30x60 Cm (Un-polished), Group Silver W : Terra, Zephyr type Rustic 269,115.00 /M2
- Granitto Lunar 30x60 Cm (Un-polished), Group Gold W : Amber, Quartz type Rustic 307,461.00 /M2
- Granitto 40/40 Cm (polish) Group Silver, type Crystal W : Pearl White, Ivory, Mustand 170,940.00 /M2
- Granitto 40/40 Cm (polish) Group Silver W : Greystone, Line 197,505.00 /M2
- Granitto 40/40 Cm (polish) Group Gold, type Crysta W : Black 225,750.00 /M2
- Granitto 40/40 Cm (Un-polish) Group Gold, type Oasis W : Forest Green, Brick, Cocoa, Black 192,885.00 /M2
- Granitto Gastello 30x30 Cm (Un-polish) Group Silver, type rustic W : Capucino, expreso, crème 157,080.00 /M2
- Homogenous Tile 60x60 Cm, ex China 136,500.00 /M2
Homogenous Tile Inesa
- Inesa, 30/30,40/40, Onix (Un-Polished) 102,375.00 /M2
- Group A (Pearl, Opal, Agate, Cateye, Topaz, Zamrud)
Inesa, uk. 30/30 & 40/40 (Polished) 144,900.00 /M2
- Group A (Pearl, Opal, Agate, Cateye, Topaz, Zamrud)
Inesa, 30/30,40/40 UP (Onix, Phyrus, Ruby, Jade) Group C 132,300.00 /M2
- Inesa, 30/30, 40/40 P (Onix, Phyrus, Ruby, Jade) Group C 146,265.00 /M2
- Inesa, 40/40 Group A (Corypha polish) 169,575.00 /M2
- Inesa, 60 x 60 Group A (Corypha polish) 214,987.50 /M2
- Inesa, 40x40 (Polish), warna Topaz 159,075.00 /M2
- Inesa, 60/60 (P), Raphia 214,987.50 /M2
Homogenous Tile Essenza
- Essenza 30/30, Papper Grey (Un-Polished) 157,500.00 /M2
- Essenza 30/30, Papper Grey (Polished) 183,750.00 /M2
- Essenza Group A 40x40, Papper Grey (Un-Polished) 173,712.00 /M2
- Essenza Group A 40x40 polish warna : prince rubber, silver star 198,660.00 /M2
- Essenza 60x60, Blak Orchid (Polished) 288,750.00 /M2
- Essenza Group B 60x60 (Polished) warna : Corypha 300,646.50 /M2
- Essenza Group A 60x60 polish warna : prince rubber, silver star 243,936.00 /M2
Homogenous Tile Uero Grace
- Uero Grace 60/60, FHQ 6207 (pgnt Raphia) 178,500.00 /M2
- Uero Grace 30/30, FHQ 6207 131,250.00 /M2
- Uero Grace 60/60, Golden Black (pgnt Onix) 236,250.00 /M2
Marmer

RAB - 05
- Marmer Import Crema Evory Jenis slab 682,500.00 /M2
- Marmer Import Golden Perlanto Jenis slab 682,500.00 /M2
- Marmer Import Volacas Jenis slab 997,500.00 /M2
- Marmer Import Travertine Jenis slab 1,365,000.00 /M2
- Marmer Import Rossi Vietnam Jenis slab 630,000.00 /M2
- Marmer Tulung Agung, 60/60 cm 420,000.00 /M2
- Marmer Tulung Agung Jenis slab 498,750.00 /M2
- Marmer Ujung Pandang (acid wash), 600x600 mm Jenis slab 609,000.00 /M2
- Marmer ex Citatah, 30/30 170,625.00 /M2
- Marmer ex Citatah, 60/60 275,625.00 /M2
- Teralux Marmer 60x60 cm 367,500.00 /M2
Floor Hardener
- Floor Hardener (Gan's Floor) 9,450.00 /kg
- Epoxy Resin 12,600.00 /kg
Keramik Tile
- Porselen 11 x 11 cm 57,750.00 /M2
- Keramik Artistik 5x20 Cm 68,250.00 /M2
- Keramik lokal 10x20 Cm (ex Roman) 57,750.00 /M2
- Keramik lokal 20/20 Cm (ex Roman) Gol A 86,100.00 /M2
- Keramik lokal 20/25 Cm (ex Roman) Gol A 79,800.00 /M2
- Keramik lokal 30x30 Cm (ex Roman) Gol B 73,500.00 /M2
- Keramik lokal 33,3x33,3 Cm (ex Roman) Gol A 97,650.00 /M2
- Keramik lokal 30x60 Cm (ex Roman) Gol A Wall tile 134,925.00 /M2
- Keramik lokal 20x40 Cm (ex Roman) Gol A 84,000.00 /M2
- Keramik lokal 40/40 Cm (ex Roman) Gol A 82,500.00 /M2
- Keramik Homogenous 30/30 Cm (ex Roman Gress) Gol. D 96,600.00 /M2
- Keramik Homogenous 60/60 Cm (ex Roman Gress) Gol. B 176,400.00 /M2
MATERIAL LANTAI PARQUET
- Red Oak lam parquet uk. 1,5 x 6 x 30 cm 121,380.00 /M2
- Red Oak lam parquet uk. 1 x 5 x 30 cm 110,775.00 /M2
- Jati lem parquet uk. 1 x 5 x 30 cm 145,923.75 /M2
- Jati lem parquet uk. 1 x 7 x 35 cm 156,187.50 /M2
- Jati lem parquet uk. 1 x 5 x 25 cm 103,635.00 /M2
- Tg. Parquet Jati uk. 1,8 x 5 x 30 cm 107,730.00 /M2
- Graculad 174,510.00 /M2
- Gracewood 144 188,685.00 /M2
- Parkit (Kronospan) uk. 19 x 120 cm 189,000.00 /M2
- Parkit (Dream Wood) uk. 19 x 120 cm 189,000.00 /M2
- Underlayer / Rubber corrugated Dasaran lantai karpet 31,500.00 /M2
- Karpet Sheet ex Lokal Kualitas baik 52,500.00 /M2
- Carpet Tile 50x50, ex Leiko 236,250.00 /M2
- Vinyl tile 30x30 cm, ex ………….. 157,500.00 /M2
- Parket sintetis uk. 10 x 90 cm 78,750.00 /M2
MATERIAL BATU ALAM
- Batu Candi 20x40 cm 133,000.35 /M2
- Batu alur Candi 20x40 cm 156,187.50 /M2
- Batu Alam susun hitam 3x30 cm 157,500.00 /M2
- Batu alam Paliaman 20X40 147,000.00 /M2
- Batu acak Sukabumi 110,250.00 /M2
- Batu acak Garut 110,250.00 /M2
- Batu acak Purwakarta 110,250.00 /M2
- Batu alam Purwakarta 136,500.00 /M2
- Batu alam Andesit 20/20 & 15/30 cm 168,000.00 /M2
- Batu alam Andesit 20/30 cm 178,500.00 /M2
- Batu alam Andesit 20/40 s/d 30/40 cm 189,000.00 /M2
- Paras Jogja 20/30s/d40/40 (cream/putih) 99,750.00 /M2
- Paras Jogja 20/40s/d40/60 (cream/putih) 115,500.00 /M2
MATERIAL CONBLOCK / INTERBLOCK (Ex. INTERNUSA)
Interblock 16.6, warna abu-abu 99,750.00 /M2
Interblock 16.6, warna Mrh, Htm, Kng, Klasik 131,250.00 /M2
Interblock 16.6, warna Hijau 141,750.00 /M2
Interblock 16.8, warna abu-abu 136,500.00 /M2
Interblock 16.8, warna Mrh, Htm, Kng, Klasik 147,000.00 /M2
Interblock 16.8, warna Hijau 157,500.00 /M2
Zurich 12.6 / Tiga berlian 6, abu-abu 124,110.00 /M2
Zurich 12.6 / Tiga berlian 6, (Mrh, Htm, Kng, Klasik) 143,010.00 /M2
Zurich 12.6 / Tiga berlian 6, Hijau 157,500.00 /M2
Zurich 12.8 / Tiga berlian 8, abu-abu 144,900.00 /M2
Zurich 12.8 / Tiga berlian 8, (Mrh, Htm, Kng, Klasik) 163,800.00 /M2
Zurich 12.8 / Tiga berlian 8, Hijau 181,440.00 /M2
Grassblock 20.10.40 (abu-abu) 143,010.00 /M2
Grassblock 20.8.40 (abu-abu) 117,810.00 /M2
Kansteen 15 x 30 x 40 39,900.00 /Bh
MATERIAL BUIS BETON
Buis beton dia. 20 cm tanpa tulang, panjang 1 m 63,525.00 /Bh
Buis beton dia. 30 cm tanpa tulang, panjang 1 m 88,935.00 /Bh
Buis beton 1/2 dia. 20 cm tanpa tulang, panjang 0,50 m 38,115.00 /Bh

RAB - 06
Buis beton 1/2 dia. 30 cm tanpa tulang, panjang 0,50 m 53,130.00 /Bh
MATERIAL CAT
Cat Duco Danagloss 88,725.00 /Kg
Cat Duco Nippe 2000 49,875.00 /Kg
Dempul Duco Sanpolac 36,750.00 /Kg
Tinner Up 28,875.00 /Kg
Cat Tembok Catylac (Acrilyc Emulsion), putih 26,250.00 /Kg
Cat Tembok Dulux ICI (Acrilyc Emulsion) Dulux Pentalite warna standart 44,257.50 /Kg
Cat Tembok Dulux ICI (Acrilyc Emulsion) Dulux Pentalite warna khusus 51,292.50 /Kg
Cat Tembok Dulux ICI (Acrilyc Emulsion), warna tua 47,250.00 /Kg
Cat Tembok luar (ICI Dulux Weathershield) Warna standart 60,375.00 /Kg
Cat Tembok luar (ICI Dulux Weathershield) Warna khusus 80,398.50 /Kg
Cat Tembok luar (ICI Dulux Weathershield), warna tua 86,992.50 /Kg
Alkali Resistants Dulux ICI 45,596.25 /Kg
Cat Tembok Mowilex (Acrilyc Emulsion) 39,375.00 /Kg
Cat Tembok Mowilex (Wather Coat) 57,750.00 /Kg
Cat Tembok (cat minyak) ex Mowilex 60,000.00 /Kg
Cat Tembok Vinilex Super 20,000.00 /Kg
Plamur Tembok Matex (5 kg) 18,375.00 /Kg
Cat Kayu/besi (ICI Dulux Super Gloss) 57,750.00 /Kg
Cat Kayu/besi (ex Danapaint, Gloss) 52,500.00 /Kg
Cat Kayu / besi (kwalitas sedang, Ftalit, Kuda Terbang) 47,250.00 /Kg
Plamur kayu 26,250.00 /Kg
Pelitur 52,500.00 /Kg
Melamik Ultran 63,000.00 /Kg
Cat warna Ultran 52,500.00 /Kg
Sanding Ultran 55,125.00 /Kg
Filler Ultran 52,500.00 /Kg
Menie Kayu 23,625.00 /Kg
Residu 18,375.00 /Kg
Kuas Roll 36,750.00 /Bh
Kuas 15,750.00 /Bh
Ampelas 2,887.50 /Bh

DAFTAR UPAH TENAGA KERJA Jakarta, Juni 2013

DAFTAR PEKERJA BIDANG PEKERJAAN UPAH


Mandor Berlaku untuk keseluruhan 110,000.00 /org/hari
Kepala Tukang Kayu 105,000.00 /org/hari
Tukang Kayu (konstruksi) Pek. Rangka atap 90,000.00 /org/hari
Tukang Kayu halus Pek. Kosen, pintu & jendela 95,000.00 /org/hari
Tukang Kayu Mebel Pek. Furniture 100,000.00 /org/hari
Kepala Tukang Batu 100,000.00 /org/hari
Tukang batu Pek. Pasangan batu/bata 90,000.00 /org/hari
Tukang batu halus Pek. Finishing 95,000.00 /org/hari
Kepala Tukang Gypsum 95,000.00 /org/hari
Tukang Gypsum Pek. Plafond / Partisi 90,000.00 /org/hari
Kepala Tukang Besi Pembesian konstrusi beton 90,000.00 /org/hari
Tukang besi 85,000.00 /org/hari
Tukang Las konstruksi 100,000.00 /org/hari
Kepala Tukang Gali 90,000.00 /org/hari
Tukang Gali Pek. Galian tanah 109,960.00 /org/hari
Kepala Tukang Cat 90,000.00 /org/hari
Tukang Cat Finishing pengecatan 100,000.00 /org/hari
Tukang Pelitur/melamik 100,000.00 /org/hari
Kepala Tukang Allumunium 90,000.00 /org/hari
Tukang khusus allumunium 100,000.00 /org/hari

Kepala Tukang pipa 90,000.00 /org/hari


Tukang pipa 109,960.00 /org/hari
Pekerja Berlaku untuk keseluruhan 75,000.00 /org/hari

RAB - 07
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

I. PEK. PERSIAPAN & TAPAK


1.1. PEK. BOWPLANK / M' BOW
Bahan : Kayu Meranti Palembang papan 0.007 M3 4,200,000.00 27,720.00
Kayu Meranti Palembang kaso 0.010 M3 2,730,000.00 26,276.25
Paku biasa 2"-5" 0.020 Kg 15,356.25 307.13
Sub - Bahan 54,303.38 Rp 54,303.38
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang Kayu 0.100 Org 90,000.00 9,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,100.00 Rp 18,100.00
TOTAL Rp 72,403.38

1.2. PAGAR SEMENTARA dari Seng Gelombang tg. 2 m / M'


Bahan : Semen PC 2.500 zak 1,300.00 3,250.00
Pasir beton 0.005 M3 270,375.00 1,351.88
Batu pecah/split 2/3 0.009 M3 269,500.35 2,425.50
Seng gelombang 3x6 ft BJLS 20 (0,2 mm) 1.200 lbr 47,250.00 56,700.00
Kayu dolken Ø 8-10/400 cm 1.250 btg 36,750.00 45,937.50
Kayu Meranti Palembang kaso 0.014 M3 2,730,000.00 38,220.00
Paku biasa 2"-5" 0.060 Kg 15,356.25 921.38
Cat meni besi 0.450 Kg 23,625.00 10,631.25
Sub - Bahan 159,437.50 Rp 159,437.50
Upah : Kep. Tukang Kayu 0.020 Org 105,000.00 2,100.00
Tukang Kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 52,300.00 Rp 52,300.00
TOTAL Rp 211,737.50

1.3. PEMB. JALAN SEMENTARA, tebal 20 cm / M2


Bahan : Batu belah 15/20 0.150 M3 257,250.00 38,587.50
Batu pecah 5/7 0.090 M3 262,500.00 23,625.00
Pasir pasang 0.010 M3 265,125.00 2,651.25
Sub - Bahan 64,863.75 Rp 64,863.75
Upah : Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 80,500.00 Rp 80,500.00
TOTAL Rp 145,363.75

1.4. PEMB. KANTOR SEMENTARA, lantai plesteran, atap Seng / M2


Bahan : Kayu dolken Ø 8-10/400 cm 1.250 btg 36,750.00 45,937.50
Kayu Meranti Palembang kaso 0.018 m³ 2,730,000.00 49,140.00
Paku biasa 2"-5" 0.850 kg 15,356.25 13,052.81
Besi pelat strip 1.100 kg 14,542.50 15,996.75
Semen portland 35.000 kg 1,300.00 45,500.00
Pasir pasang 0.150 m³ 265,125.00 39,768.75
Pasir beton 0.100 m³ 270,375.00 27,037.50
Batu pecah/split 2/3 0.150 m³ 269,500.35 40,425.05
Bata merah 30.000 bh 630.00 18,900.00
Seng gelombang 3x6 ft BJLS 20 (0,2 mm) 0.250 Lbr 47,250.00 11,812.50
Jendela nako (rangka) 7.000 daun 15,000.00 105,000.00
Kaca 3 mm 0.080 m² 75,000.00 6,000.00
Kunci tanam sederhana 0.150 bh 60,000.00 9,000.00
Teakwood 4x8 ft 3 mm 0.060 lbr 105,000.00 6,300.00
Sub - Bahan 433,870.87 Rp 433,870.87
Upah : Kep. Tukang Kayu 0.300 Org 105,000.00 31,500.00
Tukang Kayu 2.000 Org 90,000.00 180,000.00
Tukang Batu 1.000 Org 90,000.00 90,000.00
Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 382,000.00 Rp 382,000.00
TOTAL Rp 815,870.87

1.5. GUDANG SEMEN & PERALATAN, lantai plesteran, atap Seng / M2


Bahan : Kayu dolken Ø 8-10/400 cm 1.700 btg 36,750.00 62,475.00
Kayu Meranti Palembang kaso 0.021 m³ 2,730,000.00 57,330.00
Paku biasa 2"-5" 0.300 kg 15,356.25 4,606.88
Semen portland 10.500 kg 1,300.00 13,650.00
Pasir beton 0.030 m³ 270,375.00 8,111.25
Batu pecah/split 2/3 0.050 m³ 269,500.35 13,475.02
Seng gelombang 3x6 ft BJLS 20 (0,2 mm) 1.500 Lbr 47,250.00 70,875.00
Sub - Bahan 230,523.14 Rp 230,523.14
Upah : Kep. Tukang Kayu 0.200 Org 105,000.00 21,000.00
Tukang Kayu 2.000 Org 90,000.00 180,000.00
Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 281,500.00 Rp 281,500.00
TOTAL Rp 512,023.14

1.6. PAGAR PERIMETER, dari kawat duri tinggi 70 cm / M'


Bahan : Besi siku 6.750 kg 14,455.35 97,573.61
Semen portland 2.000 kg 1,300.00 2,600.00
Pasir beton 0.005 m³ 270,375.00 1,351.88
Batu pecah/split 2/3 0.009 m³ 269,500.35 2,425.50
Paku biasa 2"-5" 0.060 kg 15,356.25 921.38
Kawat duri (10kg/60m/rol) 0.050 kg 16,537.50 826.88
Sub - Bahan 105,699.24 Rp 105,699.24

RAB - 08
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Upah : Kep. Tukang Kayu 0.020 Org 105,000.00 2,100.00


Tukang Kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 44,800.00 Rp 44,800.00
TOTAL Rp 150,499.24

1.7. PEK. TANAH DILAKSANAKAN SECARA KONVENSIONAL


1 PEMBERSIHAN LAPANGAN dan PERATAAN / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 13,000.00 Rp 13,000.00
2 PENGUPASAN LAPISAN ATAS / M2
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.012 Org 110,000.00 1,320.00
Sub - Upah 20,070.00 Rp 20,070.00
3 GALIAN TANAH BIASA, sedalam 1 m / M3 SNI
Upah : Pekerja 0.750 Org 75,000.00 56,250.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 59,000.00 Rp 59,000.00
4 GALIAN TANAH BIASA, sedalam 2 m / M3 SNI
Upah : Pekerja 0.900 Org 75,000.00 67,500.00
Mandor 0.045 Org 110,000.00 4,950.00
Sub - Upah 72,450.00 Rp 72,450.00
5 GALIAN TANAH BIASA, sedalam 3 m / M3 SNI
Upah : Pekerja 1.050 Org 75,000.00 78,750.00
Mandor 0.067 Org 110,000.00 7,370.00
Sub - Upah 86,120.00 Rp 86,120.00
6 GALIAN TANAH KERAS, sedalam 1 m / M3 SNI
Upah : Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.032 Org 110,000.00 3,520.00
Sub - Upah 78,520.00 Rp 78,520.00
7 GALIAN TANAH CADAS, sedalam 1 m / M3 SNI
Upah : Pekerja 1.500 Org 75,000.00 112,500.00
Mandor 0.060 Org 110,000.00 6,600.00
Sub - Upah 119,100.00 Rp 119,100.00
8 GALIAN TANAH LUMPUR, sedalam 1 m / M3 SNI
Upah : Pekerja 1.200 Org 75,000.00 90,000.00
Mandor 0.045 Org 110,000.00 4,950.00
Sub - Upah 94,950.00 Rp 94,950.00
9 STRPPING TEBING, setinggi 1 m / M2 SNI
Upah : Pekerja 0.050 Org 75,000.00 3,750.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 4,300.00 Rp 4,300.00
10 MEMBUANG TANAH, sejauh 150 m / M3 SNI
Upah : Pekerja 0.516 Org 75,000.00 38,700.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 44,200.00 Rp 44,200.00
11 URUGAN TANAH KEMBALI / M3 SNI
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 19,630.00 Rp 19,630.00
12 PERATAAN & PEMADATAN URUGAN TANAH
Upah : meratakan & memadatkan
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 43,000.00 Rp 43,000.00

13 URUGAN TANAH DARI LUAR / M3 BOW


Bahan : Tanah Urug 1.200 M3 262,500.00 315,000.00
Angkutan Truk 1.200 M3 25,000.00 30,000.00
Sub - Bahan 345,000.00 Rp 345,000.00
Upah : menimbun, meratakan & memadatkan
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 16,100.00 Rp 16,100.00
TOTAL Rp 361,100.00
14 PEK. GALIAN TANAH (CUT) dengan Alat Berat / M3 SNI
Upah : Pekerja 0.109 Org 75,000.00 8,175.00
Mandor 0.054 Org 110,000.00 5,940.00
Sub - Upah 14,115.00 Rp 14,115.00
Harga pemakaian alat berat
- EXCAVATOR 150 HP Kobelco SK200 0.054 jam 469,389.80 25,347.05
- DUMP TRUCK 3-4 M3 / 6 ton 0.100 jam 242,640.20 24,264.02
- Alat bantu 1.000 ls 10,000.00 10,000.00
Sub - Sewa Peralatan 59,611.07 Rp 59,611.07
TOTAL Rp 73,726.07

15 PEK URUGAN TANAH (FILL) dengan Alat Berat / M3 SNI


Bahan : Tanah Urug 1.200 M3 262,500.00 315,000.00
Sub - Bahan 315,000.00 Rp 315,000.00
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
Harga pemakaian alat berat
- WHEEL LOADER 1-1,6 m3 0.020 jam 267,270.30 5,345.41
- DUMP TRUCK 3-4 M3 / 6 ton 0.331 jam 242,640.20 80,313.91

RAB - 09
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

- MOTOR GRADER 100 HP 0.007 jam 288,512.40 2,019.59


- VIBRATOR ROLLER 5-8 Ton 0.011 jam 247,328.40 2,720.61
- WATER TANK TRUCK 0.008 jam 145,530.00 1,164.24
- Alat bantu 1.000 ls 10,000.00 10,000.00
Sub - Sewa Peralatan 101,563.75 Rp 101,563.75
TOTAL Rp 438,063.75

1.8. PEK. URUGAN PASIR URUG / M3 SNI-2008


Bahan : Pasir Urug 1.200 M3 291,375.00 349,650.00
Sub - Bahan 349,650.00 Rp 349,650.00
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 23,600.00 Rp 23,600.00
TOTAL Rp 373,250.00
1.9. PEK. URUGAN SIRTU / M3 SNI-2008
Bahan : Sirtu 1.200 M3 256,200.00 307,440.00
Sub - Bahan 307,440.00 Rp 307,440.00
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
TOTAL Rp 328,940.00

1.10. PEK. URUGAN PASIR EXTRA BETON / M3 SNI-2008


Bahan : Pasir Extra beton 1.200 M3 273,000.00 327,600.00
Sub - Bahan 327,600.00 Rp 327,600.00
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
TOTAL Rp 349,100.00
1.11. PEK. URUGAN PENETRASI /SPLIT 2-3 cm / M3 SNI-2008
Bahan : Batu split 2-3 cm 1.200 M3 269,500.35 323,400.42
Sub - Bahan 323,400.42 Rp 323,400.42
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
TOTAL Rp 344,900.42
1.12. PEK. LAPISAN MAKADAM BATU BELAH / M3 SNI-2008
Bahan : Makadam/batu pecah 5-7 cm 1.200 M3 257,250.00 308,700.00
Sub - Bahan 308,700.00 Rp 308,700.00
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
TOTAL Rp 330,200.00

1.13. PEK. LAPISAN MAKADAM BATU PECAH 5-7 cm / M3 SNI-2008


Bahan : Makadam/batu pecah 5-7 cm 1.200 M3 262,500.00 315,000.00
Sub - Bahan 315,000.00 Rp 315,000.00
Upah : Pekerja 0.250 Org 75,000.00 18,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 21,500.00 Rp 21,500.00
TOTAL Rp 336,500.00
1.14. PEK. LAPISAN IJUK TEBAL 10 CM (u/. Dinding resapan) SNI-2008
Bahan : I j u k 6.000 kg 31,500.00 189,000.00
Sub - Bahan 189,000.00 Rp 189,000.00
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 12,900.00 Rp 12,900.00
TOTAL Rp 201,900.00

1.15. PEKERJAAN BONGKARAN

1 Pek. Bongkar beton bertulang / M3


Upah : Pekerja 6.667 Org 75,000.00 500,025.00
Mandor 0.333 Org 110,000.00 36,630.00
Sub - Upah 536,655.00 Rp 536,655.00
TOTAL Rp 536,655.00
2 Pek. Bongkar dinding tembok bata merah / M3
Upah : Pekerja 0.667 Org 75,000.00 50,025.00
Mandor 0.033 Org 110,000.00 3,630.00
Sub - Upah 53,655.00 Rp 53,655.00
TOTAL Rp 53,655.00
3 Pek. Bongkar dinding 1/2 bata / M2
Upah : Pekerja 0.073 Org 75,000.00 5,475.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 5,915.00 Rp 5,915.00
TOTAL Rp 5,915.00
4 Pek. Bongkar plat beton bertulang / M2
Upah : Pekerja 0.800 Org 75,000.00 60,000.00
Mandor 0.040 Org 110,000.00 4,400.00
Sub - Upah 64,400.00 Rp 64,400.00
TOTAL Rp 64,400.00
5 Pek. Bongkar batu kali (tebal kurang dari 50 cm) / M3
Upah : Pekerja 1.500 Org 75,000.00 112,500.00
Mandor 0.075 Org 110,000.00 8,250.00
Sub - Upah 120,750.00 Rp 120,750.00
TOTAL Rp 120,750.00

RAB - 010
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

6 Pek. Bongkar batu kali (tebal lebih dari 50 cm) / M3


Upah : Pekerja 3.000 Org 75,000.00 225,000.00
Mandor 0.150 Org 110,000.00 16,500.00
Sub - Upah 241,500.00 Rp 241,500.00
TOTAL Rp 241,500.00
7 Pek. Bongkar finishing lantai / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 8,600.00 Rp 8,600.00
TOTAL Rp 8,600.00
8 Pek. Bongkar paving block / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 8,050.00 Rp 8,050.00
TOTAL Rp 8,050.00
9 Pek. Bongkar plesteran / M2
Upah : Pekerja 0.075 Org 75,000.00 5,625.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 6,175.00 Rp 6,175.00
TOTAL Rp 6,175.00
10 Pek. Bongkar Atap genteng / M2
Upah : Pekerja 0.020 Org 75,000.00 1,500.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 2,600.00 Rp 2,600.00
TOTAL Rp 2,600.00
11 Pek. Bongkar karpusan Atap genteng / M'
Upah : Pekerja 0.060 Org 75,000.00 4,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 6,150.00 Rp 6,150.00
TOTAL Rp 6,150.00
12 Pek. Bongkar Atap Seng/Asbes / M2
Upah : Pekerja 0.050 Org 75,000.00 3,750.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 6,500.00 Rp 6,500.00
TOTAL Rp 6,500.00
13 Pek. Bongkar kaso reng kayu (kayu akan dipakai lagi) / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Tukang kayu 0.025 Org 90,000.00 2,250.00
Kepala Tukang 0.003 Org 105,000.00 315.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 10,615.00 Rp 10,615.00
TOTAL Rp 10,615.00
14 Pek. Bongkar kaso reng kayu (kayu tidak dipakai lagi) / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 8,050.00 Rp 8,050.00
TOTAL Rp 8,050.00
15 Pek. Bongkar kuda2 & loteng kayu (kayu akan dipakai lagi) / M3
Upah : Pekerja 2.666 Org 75,000.00 199,950.00
Tukang kayu 4.000 Org 90,000.00 360,000.00
Kepala Tukang 0.400 Org 105,000.00 42,000.00
Mandor 0.133 Org 110,000.00 14,630.00
Sub - Upah 616,580.00 Rp 616,580.00
TOTAL Rp 616,580.00
16 Pek. Bongkar kuda2 & loteng kayu (kayu tidak dipakai lagi) / M3
Upah : Pekerja 4.000 Org 75,000.00 300,000.00
Mandor 0.400 Org 110,000.00 44,000.00
Sub - Upah 344,000.00 Rp 344,000.00
TOTAL Rp 344,000.00
17 Pek. Bongkar rangka plafond kayu / M2
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 8,050.00 Rp 8,050.00
TOTAL Rp 8,050.00
18 Pek. Bongkar penutup plafond / M2
Upah : Pekerja 0.030 Org 75,000.00 2,250.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 2,580.00 Rp 2,580.00
TOTAL Rp 2,580.00

III. PEKERJAAN BETON


3.1. BETON TIDAK BERTULANG
1 MEMBUAT 1 M3 BETON, mutu f'c = 7,4 Mpa (K 100) SNI-2008
(Slump 12 cm, w/c = 0,87)
Bahan : Semen PC 247.00 kg 1,300.00 321,100.00
Pasir beton (BD 1400) 869.00 kg 193.13 167,825.63
Kerikil / split (2-3 cm) (BD 1350) 999.00 Kg 199.63 199,430.26
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 709,855.88 Rp 709,855.88
Upah : Pekerja 1.650 Org 75,000.00 123,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Kepala Tukang batu 0.028 Org 100,000.00 2,800.00
Mandor 0.083 Org 110,000.00 9,130.00
Sub - Upah 160,430.00 Rp 160,430.00
TOTAL Rp 870,285.88
2 MEMBUAT 1 M3 BETON, mutu f'c = 7,4 Mpa (K 100) SNI-2008

RAB - 011
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

(Slump 3-6 cm, w/c = 0,87)


Bahan : Semen PC 230.00 kg 1,300.00 299,000.00
Pasir beton 893.00 kg 193.13 172,460.63
Kerikil / split (2-3 cm) 1,027.00 Kg 199.63 205,019.90
Air 200.00 liter 100.00 20,000.00
Sub - Bahan 696,480.52 Rp 696,480.52
Upah : Pekerja 1.200 Org 75,000.00 90,000.00
Tukang batu 0.200 Org 90,000.00 18,000.00
Kepala Tukang batu 0.020 Org 100,000.00 2,000.00
Mandor 0.060 Org 110,000.00 6,600.00
Sub - Upah 116,600.00 Rp 116,600.00
TOTAL Rp 813,080.52
3 MEMBUAT 1 M3 BETON, mutu f'c = 9.8 Mpa (K 125) SNI-2008
(Slump 12 cm, w/c = 0,78)
Bahan : Semen PC 276.00 kg 1,300.00 358,800.00
Pasir beton 828.00 kg 193.13 159,907.50
Kerikil / split (2-3 cm) 1,012.00 Kg 199.63 202,025.45
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 742,232.95 Rp 742,232.95
Upah : Pekerja 1.650 Org 75,000.00 123,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Kepala Tukang batu 0.028 Org 100,000.00 2,800.00
Mandor 0.083 Org 110,000.00 9,130.00
Sub - Upah 160,430.00 Rp 160,430.00
TOTAL Rp 902,662.95
4 MEMBUAT 1 M3 BETON, mutu f'c = 12,2 Mpa (K 150) SNI-2008
(Slump 12 cm, w/c = 0,72)
Bahan : Semen PC 299.00 kg 1,300.00 388,700.00
Pasir beton 799.00 kg 193.13 154,306.88
Kerikil / split (2-3 cm) 1,017.00 Kg 199.63 203,023.60
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 767,530.47 Rp 767,530.47
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 927,960.47
5 MEMBUAT 1 M3 BETON, mutu f'c = 14,5 Mpa (K 175) SNI-2008
(Slump 12 cm, w/c = 0,66)
Bahan : Semen PC 326.00 kg 1,300.00 423,800.00
Pasir beton 760.00 kg 193.13 146,775.00
Kerikil / split (2-3 cm) 1,029.00 Kg 199.63 205,419.16
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 797,494.16 Rp 797,494.16
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 957,924.16
6 MEMBUAT 1 M3 BETON, mutu f'c = 16,9 Mpa (K 200) SNI-2008
(Slump 12 cm, w/c = 0,61)
Bahan : Semen PC 352.00 kg 1,300.00 457,600.00
Pasir beton 731.00 kg 193.13 141,174.38
Kerikil / split (2-3 cm) 1,031.00 Kg 199.63 205,818.42
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 826,092.79 Rp 826,092.79
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 986,522.79
7 MEMBUAT 1 M3 BETON, mutu f'c = 19,3 Mpa (K 225) SNI-2008
(Slump 12 cm, w/c = 0,58)
Bahan : Semen PC 352.00 kg 1,300.00 457,600.00
Pasir beton 731.00 kg 193.13 141,174.38
Kerikil / split (2-3 cm) 1,031.00 Kg 199.63 205,818.42
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 826,092.79 Rp 826,092.79
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 986,522.79
8 MEMBUAT 1 M3 BETON, mutu f'c = 21,7 Mpa (K 250) SNI-2008
(Slump 12 cm, w/c = 0,56)
Bahan : Semen PC 384.00 kg 1,300.00 499,200.00
Pasir beton 692.00 kg 193.13 133,642.50
Kerikil / split (2-3 cm) 1,039.00 Kg 199.63 207,415.45
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 861,757.95 Rp 861,757.95
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 1,022,187.95
9 MEMBUAT 1 M3 BETON, mutu f'c = 24,00 Mpa (K 275) SNI-2008
(Slump 12 cm, w/c = 0,53)
Bahan : Semen PC 406.00 kg 1,300.00 527,800.00
Pasir beton 684.00 kg 193.13 132,097.50
Kerikil / split (2-3 cm) 1,026.00 Kg 199.63 204,820.27
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 886,217.77 Rp 886,217.77
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 1,046,647.77
10 MEMBUAT 1 M3 BETON, mutu f'c = 26,4 Mpa (K 300) SNI-2008
(Slump 12 cm, w/c = 0,52)
Bahan : Semen PC 413.00 kg 1,300.00 536,900.00
Pasir beton 681.00 kg 193.13 131,518.13
Kerikil / split (2-3 cm) 1,021.00 Kg 199.63 203,822.12
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 893,740.24 Rp 893,740.24
Upah : Sama dengan upah kerja beton K-125 Sub - Upah Rp 160,430.00
TOTAL Rp 1,054,170.24

RAB - 012
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

11 MEMBUAT 1 M3 BETON, mutu f'c = 28,8 Mpa (K 325) SNI-2008


(Slump 12 cm, w/c = 0,49)
Bahan : Semen PC 439.00 kg 1,300.00 570,700.00
Pasir beton 670.00 kg 193.13 129,393.75
Kerikil / split (2-3 cm) 1,006.00 Kg 199.63 200,827.67
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 922,421.42 Rp 922,421.42
Upah : Pekerja 2.100 Org 75,000.00 157,500.00
Tukang batu 0.350 Org 90,000.00 31,500.00
Kepala Tukang batu 0.035 Org 100,000.00 3,500.00
Mandor 0.105 Org 110,000.00 11,550.00
Sub - Upah 204,050.00 Rp 204,050.00
TOTAL Rp 1,126,471.42
12 MEMBUAT 1 M3 BETON, mutu f'c = 31,2 Mpa (K 350) SNI-2008
(Slump 12 cm, w/c = 0,48)
Bahan : Semen PC 439.00 kg 1,300.00 570,700.00
Pasir beton 670.00 kg 193.13 129,393.75
Kerikil / split (2-3 cm) 1,006.00 Kg 199.63 200,827.67
Air 215.00 liter 100.00 21,500.00
Sub - Bahan 922,421.42 Rp 922,421.42
Upah : Sama dengan upah kerja beton K-325 Sub - Upah Rp 204,050.00
TOTAL Rp 1,126,471.42
13 MEMBUAT 1 M3 BETON KEDAP AIR, dengan Strorok-100 SNI-2008
Bahan : Semen PC 400.00 kg 1,300.00 520,000.00
Pasir beton 0.48 m3 270,375.00 129,780.00
Kerikil / split (2-3 cm) 0.80 m3 269,500.35 215,600.28
Strorok-100 1.20 kg 50,000.00 60,000.00
Air 210.00 liter 100.00 21,000.00
Sub - Bahan 946,380.28 Rp 946,380.28
Upah : Sama dengan upah kerja beton K-325 Sub - Upah Rp 204,050.00
TOTAL Rp 1,150,430.28

3.2. BETON BERTULANG (Lengkap)


1 MEMBUAT 1 M' KOLOM PRAKTIS (11 x 11 cm) SNI-2008
Bahan : Semen PC 4.000 kg 1,300.00 5,200.00
Pasir beton 0.006 m3 270,375.00 1,622.25
Kerikil / split (2-3 cm) 0.009 m3 269,500.35 2,425.50
Kayu kelas III (kayu papan Terentang) 0.002 M3 3,045,000.00 6,090.00
Paku 5-12 cm 0.010 Kg 15,356.25 153.56
Besi beton polos 3.000 Kg 13,125.00 39,375.00
Kawat beton 0.045 Kg 20,212.50 909.56
Sub - Bahan 55,775.88 Rp 55,775.88
Upah : Pekerja 0.180 Org 75,000.00 13,500.00
Tukang batu 0.020 Org 90,000.00 1,800.00
Tukang kayu 0.020 Org 90,000.00 1,800.00
Tukang besi 0.020 Org 85,000.00 1,700.00
Kepala Tukang batu 0.006 Org 100,000.00 600.00
Mandor 0.009 Org 110,000.00 990.00
Sub - Upah 20,390.00 Rp 20,390.00
TOTAL Rp 76,165.88
0.0121 Harga/m3 Rp 6,294,700.67
2 MEMBUAT 1 M' RING BALOK PRAKTIS (11 x 15 cm) SNI-2008
Bahan : Semen PC 5.500 kg 1,300.00 7,150.00
Pasir beton 0.009 m3 270,375.00 2,433.38
Kerikil / split (2-3 cm) 0.015 m3 269,500.35 4,042.51
Kayu kelas III (kayu papan Terentang) 0.003 M3 3,045,000.00 9,135.00
Paku 5-12 cm 0.020 Kg 15,356.25 307.13
Besi beton polos 3.600 Kg 13,125.00 47,250.00
Kawat beton 0.050 Kg 20,212.50 1,010.63
Sub - Bahan 71,328.63 Rp 71,328.63
Upah : Pekerja 0.297 Org 75,000.00 22,275.00
Tukang batu 0.033 Org 90,000.00 2,970.00
Tukang kayu 0.033 Org 90,000.00 2,970.00
Tukang besi 0.033 Org 85,000.00 2,805.00
Kepala Tukang batu 0.010 Org 100,000.00 1,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 33,670.00 Rp 33,670.00
TOTAL Rp 104,998.63
0.0165 Harga/m3 Rp 6,363,553.35
3 MEMBUAT 1 M3 SLOOF BETON BERTULANG SNI-2008
(200 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.270 M3 3,045,000.00 822,150.00
Paku 5-12 cm 2.000 Kg 15,356.25 30,712.50
Minyak bekisting 0.600 liter 35,000.00 21,000.00
Besi beton polos 210.000 Kg 13,125.00 2,756,250.00
Kawat beton 3.000 Kg 20,212.50 60,637.50
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Sub - Bahan 4,491,847.78 Rp 4,491,847.78
Upah : Pekerja 5.650 Org 75,000.00 423,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.560 Org 90,000.00 140,400.00
Tukang besi 1.400 Org 85,000.00 119,000.00
Kepala Tukang batu 0.323 Org 100,000.00 32,300.00
Mandor 0.283 Org 110,000.00 31,130.00
Sub - Upah 771,330.00 Rp 771,330.00
TOTAL Rp 5,263,177.78

RAB - 013
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

4 MEMBUAT 1 M3 PONDASI BETON BERTULANG SNI-2008


(150 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.200 M3 3,045,000.00 609,000.00
Paku 5-12 cm 1.500 Kg 15,356.25 23,034.38
Minyak bekisting 0.400 liter 35,000.00 14,000.00
Besi beton polos 157.500 Kg 13,125.00 2,067,187.50
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Sub - Bahan 3,559,797.78 Rp 3,559,797.78
Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.262 Org 100,000.00 26,200.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 683,850.00 Rp 683,850.00
TOTAL Rp 4,243,647.78

5 MEMBUAT 1 M3 KOLOM BETON BERTULANG SNI-2008


(300 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.400 M3 3,045,000.00 1,218,000.00
Paku 5-12 cm 4.000 Kg 15,356.25 61,425.00
Minyak bekisting 2.000 liter 35,000.00 70,000.00
Besi beton polos 315.000 Kg 13,125.00 4,134,375.00
Kawat beton 4.500 Kg 20,212.50 90,956.25
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.150 M3 3,360,000.00 504,000.00
Plywood/multiplex 9mm 3.500 lmbr 110,250.00 385,875.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 20.000 btg 36,750.00 735,000.00
Sub - Bahan 8,000,729.03 Rp 8,000,729.03
Upah : Pekerja 7.050 Org 75,000.00 528,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.650 Org 90,000.00 148,500.00
Tukang besi 2.100 Org 85,000.00 178,500.00
Kepala Tukang batu 0.403 Org 100,000.00 40,300.00
Mandor 0.353 Org 110,000.00 38,830.00
Sub - Upah 959,630.00 Rp 959,630.00
TOTAL Rp 8,960,359.03

5.a MEMBUAT 1 M3 KOLOM BETON BERTULANG SNI-2008


(250 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.400 M3 3,045,000.00 1,218,000.00
Paku 5-12 cm 4.000 Kg 15,356.25 61,425.00
Minyak bekisting 2.000 liter 35,000.00 70,000.00
Besi beton polos 262.500 Kg 13,125.00 3,445,312.50
Kawat beton 4.500 Kg 20,212.50 90,956.25
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.150 M3 3,360,000.00 504,000.00
Plywood/multiplex 9mm 3.500 lmbr 110,250.00 385,875.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 20.000 btg 36,750.00 735,000.00
Sub - Bahan 7,311,666.53 Rp 7,311,666.53
Upah : Pekerja 7.050 Org 75,000.00 528,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.650 Org 90,000.00 148,500.00
Tukang besi 1.750 Org 85,000.00 148,750.00
Kepala Tukang batu 0.403 Org 100,000.00 40,300.00
Mandor 0.353 Org 110,000.00 38,830.00
Sub - Upah 929,880.00 Rp 929,880.00
TOTAL Rp 8,241,546.53

5.b MEMBUAT 1 M3 KOLOM BETON BERTULANG SNI-2008


(200 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.400 M3 3,045,000.00 1,218,000.00
Paku 5-12 cm 4.000 Kg 15,356.25 61,425.00
Minyak bekisting 2.000 liter 35,000.00 70,000.00
Besi beton polos 210.000 Kg 13,125.00 2,756,250.00
Kawat beton 4.500 Kg 20,212.50 90,956.25
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.150 M3 3,360,000.00 504,000.00
Plywood/multiplex 9mm 3.500 lmbr 110,250.00 385,875.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 20.000 btg 36,750.00 735,000.00
Sub - Bahan 6,622,604.03 Rp 6,622,604.03
Upah : Pekerja 7.050 Org 75,000.00 528,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.650 Org 90,000.00 148,500.00
Tukang besi 1.400 Org 85,000.00 119,000.00
Kepala Tukang batu 0.403 Org 100,000.00 40,300.00
Mandor 0.353 Org 110,000.00 38,830.00
Sub - Upah 900,130.00 Rp 900,130.00

RAB - 014
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

TOTAL Rp 7,522,734.03

6 MEMBUAT 1 M3 "BALOK PLAT" BETON BERTULANG SNI-2008


(200 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.320 M3 3,045,000.00 974,400.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 210.000 Kg 13,125.00 2,756,250.00
Kawat beton 3.000 Kg 20,212.50 60,637.50
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.140 M3 3,360,000.00 470,400.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 16.000 btg 36,750.00 588,000.00
Sub - Bahan 6,064,625.28 Rp 6,064,625.28
Upah : Pekerja 6.350 Org 75,000.00 476,250.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.650 Org 90,000.00 148,500.00
Tukang besi 1.400 Org 85,000.00 119,000.00
Kepala Tukang batu 0.333 Org 100,000.00 33,300.00
Mandor 0.318 Org 110,000.00 34,980.00
Sub - Upah 836,780.00 Rp 836,780.00
TOTAL Rp 6,901,405.28

7 MEMBUAT 1 M3 "PLAT LANTAI" BETON BERTULANG SNI-2008


(150 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.320 M3 3,045,000.00 974,400.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 157.500 Kg 13,125.00 2,067,187.50
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.120 M3 3,360,000.00 403,200.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 32.000 btg 36,750.00 1,176,000.00
Sub - Bahan 5,881,203.41 Rp 5,881,203.41
Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.265 Org 100,000.00 26,500.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 684,150.00 Rp 684,150.00
TOTAL Rp 6,565,353.41

8 MEMBUAT 1 M3 "PLAT LANTAI" BETON BERTULANG SNI-2008


(150 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.320 M3 3,045,000.00 974,400.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 157.500 Kg 13,125.00 2,067,187.50
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.120 M3 3,360,000.00 403,200.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 32.000 btg 36,750.00 1,176,000.00
Sub - Bahan 5,881,203.41 Rp 5,881,203.41
Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.265 Org 100,000.00 26,500.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 684,150.00 Rp 684,150.00
TOTAL Rp 6,565,353.41
8.a MEMBUAT 1 M3 "PLAT LANTAI" BETON BERTULANG SNI-2008
(125 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.320 M3 3,045,000.00 974,400.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 131.250 Kg 13,125.00 1,722,656.25
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.120 M3 3,360,000.00 403,200.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 32.000 btg 36,750.00 1,176,000.00

RAB - 015
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Bahan 5,536,672.16 Rp 5,536,672.16


Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.265 Org 100,000.00 26,500.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 684,150.00 Rp 684,150.00
TOTAL Rp 6,220,822.16
8.b MEMBUAT 1 M3 "PLAT LANTAI" BETON BERTULANG SNI-2008
(100 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.320 M3 3,045,000.00 974,400.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 105.000 Kg 13,125.00 1,378,125.00
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.120 M3 3,360,000.00 403,200.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 32.000 btg 36,750.00 1,176,000.00
Sub - Bahan 5,192,140.91 Rp 5,192,140.91
Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.265 Org 100,000.00 26,500.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 684,150.00 Rp 684,150.00
TOTAL Rp 5,876,290.91
9 MEMBUAT 1 M3 "DINDING" BETON BERTULANG SNI-2008
(150 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.240 M3 3,045,000.00 730,800.00
Paku 5-12 cm 3.200 Kg 15,356.25 49,140.00
Minyak bekisting 1.600 liter 35,000.00 56,000.00
Besi beton polos 157.500 Kg 13,125.00 2,067,187.50
Kawat beton 2.250 Kg 20,212.50 45,478.13
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.160 M3 3,360,000.00 537,600.00
Plywood/multiplex 9mm 2.800 lmbr 110,250.00 308,700.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 24.000 btg 36,750.00 882,000.00
Sub - Bahan 5,478,003.41 Rp 5,478,003.41
Upah : Pekerja 5.300 Org 75,000.00 397,500.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.300 Org 90,000.00 117,000.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Kepala Tukang batu 0.262 Org 100,000.00 26,200.00
Mandor 0.265 Org 110,000.00 29,150.00
Sub - Upah 683,850.00 Rp 683,850.00
TOTAL Rp 6,161,853.41

9.a MEMBUAT 1 M3 "DINDING" BETON BERTULANG SNI-2008


(200 kg besi + bekisting)
Bahan : Kayu kelas III (kayu papan Terentang) 0.250 M3 3,045,000.00 761,250.00
Paku 5-12 cm 3.000 Kg 15,356.25 46,068.75
Minyak bekisting 1.200 liter 35,000.00 42,000.00
Besi beton polos 210.000 Kg 13,125.00 2,756,250.00
Kawat beton 3.000 Kg 20,212.50 60,637.50
Semen PC 336.000 kg 1,300.00 436,800.00
Pasir beton 0.540 m3 270,375.00 146,002.50
Kerikil / split (2-3 cm) 0.810 m3 269,500.35 218,295.28
Kayu kelas II (kayu Meranti basah Balok) 0.105 M3 3,360,000.00 352,800.00
Plywood/multiplex 9mm 2.500 lmbr 110,250.00 275,625.00
Dolken kayu Galam, dia. 8-10cm, panjang 4m 24.000 btg 36,750.00 882,000.00
Sub - Bahan 5,977,729.03 Rp 5,977,729.03
Upah : Pekerja 5.650 Org 75,000.00 423,750.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Tukang kayu 1.560 Org 90,000.00 140,400.00
Tukang besi 1.400 Org 85,000.00 119,000.00
Kepala Tukang batu 0.323 Org 100,000.00 32,300.00
Mandor 0.283 Org 110,000.00 31,130.00
Sub - Upah 771,330.00 Rp 771,330.00
TOTAL Rp 6,749,059.03

10 MEMASANG 1M' PVC WATERSTOP, lebar 20 cm SNI-2008


Bahan : Waterstop lebar 20 cm 1.05 m' 60,000.00 63,000.00
Sub - Bahan 63,000.00 Rp 63,000.00
Upah : Pekerja 0.070 Org 75,000.00 5,250.00
Tukang batu 0.035 Org 90,000.00 3,150.00
Kepala Tukang batu 0.004 Org 100,000.00 400.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 9,240.00 Rp 9,240.00
TOTAL Rp 72,240.00

11 PEK. BETON TUMBUK (1 : 3 : 5) / M3 (slump = 12 cm)

RAB - 016
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Bahan : Semen PC 247.000 kg 1,300.00 321,100.00


Pasir beton 0.500 M3 270,375.00 135,187.50
Koral beton 1.000 Kg 286,125.00 286,125.00
Air 215.000 ltr 100.00 21,500.00
Sub - Bahan 763,912.50 Rp 763,912.50
Upah : Kep. Tukang Batu 0.028 Org 100,000.00 2,800.00
Tukang batu 0.275 Org 90,000.00 24,750.00
Pekerja 1.650 Org 75,000.00 123,750.00
Mandor 0.083 Org 110,000.00 9,130.00
Sub - Upah 160,430.00 Rp 160,430.00
Rp 924,342.50
Lantai kerja tebal 5 cm Rp 46,217.13

12 PEK. BETON SIKLUP SUMURAN / M3 (40% bt.belah + 60% beton 1:2:3) SNI-2008
Bahan : Semen PC 194.00 Kg 1,300.00 252,200.00
(beton) Batu kali 0.480 M3 257,250.00 123,480.00
Pasir beton 0.312 M3 270,375.00 84,357.00
Koral beton 0.468 M3 286,125.00 133,906.50
Besi beton 126.00 Kg 13,125.00 1,653,750.00
Kawat beton 1.800 M3 20,212.50 36,382.50
Sub - Bahan 2,284,076.00 Rp 2,284,076.00
Upah : Pekerja 3.400 Org 75,000.00 255,000.00
Tukang batu 0.850 Org 90,000.00 76,500.00
Kep. Tukang Batu 0.085 Org 100,000.00 8,500.00
Mandor 0.170 Org 110,000.00 18,700.00
Sub - Upah 358,700.00 Rp 358,700.00
TOTAL Rp 2,642,776.00

13 PEK. BETON LT. KERJA (1 : 3 : 5) + TUL. RINGAN / M3


Bahan : Semen PC 5.300 zak 65,000.00 344,500.00
Pasir beton 0.500 M3 270,375.00 135,187.50
Koral beton 1.000 Kg 286,125.00 286,125.00
Sub - Bahan 765,812.50 Rp 765,812.50
Upah : Kep. Tukang Batu 0.050 Org 100,000.00 5,000.00
50% Tukang batu 0.500 Org 90,000.00 45,000.00
Pekerja 6.000 Org 75,000.00 450,000.00
Mandor 0.300 Org 110,000.00 33,000.00
Sub - Upah 533,000.00 Rp 266,500.00
Bahan : Besi beton (45 kg) 45.000 Kg 13,125.00 590,625.00
(besi) Kawat beton 0.400 M3 20,212.50 8,085.00
Sub - Bahan 598,710.00 Rp 598,710.00
Upah : 100 kg pembesian (75%)
Kep. Tukang Besi 0.350 Org 90,000.00 31,500.00
Tukang besi 1.050 Org 85,000.00 89,250.00
Pekerja 3.150 Org 75,000.00 236,250.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 359,200.00
Sub-Upah 100kg (75% 269,400.00 Rp 121,230.00
Rp 1,752,252.50
14 BETON PLAT (diatas tanah) (1 : 2 : 3) + TUL. RINGAN / M3
Bahan : Semen PC 7.000 zak 65,000.00 455,000.00
Pasir Beton 0.540 M3 270,375.00 146,002.50
Split 0.820 M3 269,500.35 220,990.29
Sub - Bahan 821,992.79 Rp 821,992.79

Upah : Kep. Tukang Batu 0.040 Org 100,000.00 4,000.00


Tukang batu 0.400 Org 90,000.00 36,000.00
Pekerja 4.000 Org 75,000.00 300,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 342,200.00 Rp 342,200.00
Bahan : Besi beton (tul 8-20, 1 lps) 75.000 Kg 13,125.00 984,375.00
(besi) Kawat beton 0.500 M3 20,212.50 10,106.25
Sub - Bahan 994,481.25 Rp 994,481.25
Upah : untuk pembesian 75 kg Rp 202,050.00
Rp 2,360,724.04

3.3 PEKERJAAN BEKISTING


1 MEMASANG 1 M2 BEKISTING untuk BALOK SNI-2008
Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.040 M3 2,415,000.00 96,600.00
Balok kayu kelas II (kayu Rimba Campuran) 0.018 M3 2,415,000.00 43,470.00
Kayu Dolken (kayu Galam 8-10cm - 400cm 2.000 btg 36,750.00 73,500.00
Plywood tebal 9 mm (122x244 cm) 0.350 M2 110,250.00 38,587.50
Minyak bekisting 0.200 liter 30,000.00 6,000.00
Paku 5-12 cm 0.400 Kg 15,356.25 6,142.50
Sub - Bahan 264,300.00 Rp 264,300.00
Upah : Kep. Tukang Kayu 0.033 Org 105,000.00 3,465.00
Tukang kayu 0.330 Org 90,000.00 29,700.00
Pekerja 0.660 Org 75,000.00 49,500.00
Mandor 0.033 Org 110,000.00 3,630.00
Sub - Upah 86,295.00 Rp 86,295.00
TOTAL Rp 350,595.00
2 MEMASANG 1 M2 BEKISTING untuk KOLOM SNI-2008
Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.040 M3 2,415,000.00 96,600.00
Balok kayu kelas II (kayu Rimba Campuran) 0.015 M3 2,415,000.00 36,225.00
Kayu Dolken (kayu Galam 8-10cm - 400cm 2.000 btg 36,750.00 73,500.00
Plywood tebal 9 mm (122x244 cm) 0.350 M2 110,250.00 38,587.50
Minyak bekisting 0.200 liter 30,000.00 6,000.00

RAB - 017
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Paku 5-12 cm 0.400 Kg 15,356.25 6,142.50


Sub - Bahan 257,055.00 Rp 257,055.00
Upah : Kep. Tukang Kayu 0.033 Org 105,000.00 3,465.00
Tukang kayu 0.330 Org 90,000.00 29,700.00
Pekerja 0.660 Org 75,000.00 49,500.00
Mandor 0.033 Org 110,000.00 3,630.00
Sub - Upah 86,295.00 Rp 86,295.00
TOTAL Rp 343,350.00
3 MEMASANG 1 M2 BEKISTING untuk PLAT LANTAI SNI-2008
Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.040 M3 2,415,000.00 96,600.00
Balok kayu kelas II (kayu Rimba Campuran) 0.015 M3 2,415,000.00 36,225.00
Kayu Dolken (kayu Galam 8-10cm - 400cm 6.000 btg 36,750.00 220,500.00
Plywood tebal 9 mm (122x244 cm) 0.350 M2 110,250.00 38,587.50
Minyak bekisting 0.200 liter 30,000.00 6,000.00
Paku 5-12 cm 0.400 Kg 15,356.25 6,142.50
Sub - Bahan 404,055.00 Rp 404,055.00
Upah : Sama dengan upah bekisting Kolom/balok Sub - Upah Rp 86,295.00
TOTAL Rp 490,350.00

4 MEMASANG 1 M2 BEKISTING untuk TANGGA SNI-2008


Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.030 M3 2,415,000.00 72,450.00
Balok kayu kelas II (kayu Rimba Campuran) 0.015 M3 2,415,000.00 36,225.00
Kayu Dolken (kayu Galam 8-10cm - 400cm 2.000 btg 36,750.00 73,500.00
Plywood tebal 9 mm (122x244 cm) 0.350 M2 110,250.00 38,587.50
Minyak bekisting 0.150 liter 30,000.00 4,500.00
Paku 5-12 cm 0.400 Kg 15,356.25 6,142.50
Sub - Bahan 231,405.00 Rp 231,405.00
Upah : Sama dengan upah bekisting Kolom/balok Sub - Upah Rp 86,295.00
TOTAL Rp 317,700.00

5 MEMASANG 1 M2 BEKISTING untuk DINDING SNI-2008


Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.030 M3 2,415,000.00 72,450.00
Balok kayu kelas II (kayu Rimba Campuran) 0.020 M3 2,415,000.00 48,300.00
Kayu Dolken (kayu Galam 8-10cm - 400cm 3.000 btg 36,750.00 110,250.00
Plywood tebal 9 mm (122x244 cm) 0.350 M2 110,250.00 38,587.50
Minyak bekisting 0.200 liter 30,000.00 6,000.00
Paku 5-12 cm 0.400 Kg 15,356.25 6,142.50
Formite/spacer/penjaga jarak bekisting 4.000 bh 10,000.00 40,000.00 bekisting 2x pakai
Sub - Bahan 321,730.00 Rp 321,730.00
Upah : Sama dengan upah bekisting Kolom/balok Sub - Upah Rp 86,295.00
TOTAL Rp 408,025.00

6 MEMASANG 1 M2 BEKISTING untuk PONDASI SNI-2008


Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.040 M3 2,415,000.00 96,600.00
Minyak bekisting 0.300 liter 30,000.00 9,000.00
Paku 5-12 cm 0.100 Kg 15,356.25 1,535.63
Sub - Bahan 107,135.63 Rp 107,135.63
Upah : Kep. Tukang Kayu 0.026 Org 105,000.00 2,730.00
Tukang kayu 0.260 Org 90,000.00 23,400.00
Pekerja 0.520 Org 75,000.00 39,000.00
Mandor 0.026 Org 110,000.00 2,860.00
Sub - Upah 67,990.00 Rp 67,990.00
TOTAL Rp 175,125.63

7 MEMASANG 1 M2 BEKISTING untuk SLOOF SNI-2008


Bahan : Kayu kelas III (Kayu Rimba Campuran) 0.045 M3 2,415,000.00 108,675.00
Minyak bekisting 0.300 liter 30,000.00 9,000.00
Paku 5-12 cm 0.100 Kg 15,356.25 1,535.63
Sub - Bahan 119,210.63 Rp 119,210.63
Upah : Kep. Tukang Kayu 0.026 Org 105,000.00 2,730.00
Tukang kayu 0.260 Org 90,000.00 23,400.00
Pekerja 0.520 Org 75,000.00 39,000.00
Mandor 0.026 Org 110,000.00 2,860.00
Sub - Upah 67,990.00 Rp 67,990.00
TOTAL Rp 187,200.63
3.4 PEK. PEMBESIAN
1 PEMBESIAN (10 Kg) dengan besi polos atau ulir SNI-2008
Bahan : Besi beton 10.50 Kg 13,125.00 137,812.50
Kawat beton 0.15 Kg 20,212.50 3,031.88
Sub - Bahan 140,844.38 Rp 140,844.38
Upah : Pekerja 0.070 Org 75,000.00 5,250.00
Tukang besi 0.070 Org 85,000.00 5,950.00
Kep. Tukang Besi 0.007 Org 90,000.00 630.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 12,270.00 Rp 12,270.00
SUB-TOTAL Rp 153,114.38
atau / KG Rp 15,311.44
2 MEMASANG 10 Kg KABEL PRESSTRESED SNI-2008
POLOS/STARNDS
Bahan : Besi beton 10.50 Kg 13,125.00 137,812.50
Kawat beton 0.10 Kg 20,212.50 2,021.25
Sub - Bahan 139,833.75 Rp 139,833.75
Upah : Pekerja 0.050 Org 75,000.00 3,750.00
Tukang besi 0.050 Org 85,000.00 4,250.00
Kep. Tukang Besi 0.005 Org 90,000.00 450.00
Mandor 0.003 Org 110,000.00 330.00

RAB - 018
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Upah 8,780.00 Rp 8,780.00


SUB-TOTAL Rp 148,613.75
atau / KG Rp 14,861.38
3 MEMASANG 1 KG JARING KAWAT BAJA / WIRE MESH SNI-2008
Bahan : Jaring kawat baja dilas (wire mesh) 1.02 Kg 12,500.00 12,750.00
Kawat beton 0.05 Kg 20,212.50 1,010.63
Sub - Bahan 13,760.63 Rp 13,760.63
Upah : Pekerja 0.025 Org 75,000.00 1,875.00
Tukang besi 0.025 Org 85,000.00 2,125.00
Kep. Tukang Besi 0.002 Org 90,000.00 180.00
Mandor 0.001 Org 110,000.00 110.00
Sub - Upah 4,290.00 Rp 4,290.00
SUB-TOTAL Rp 18,050.63

4 PEMBESIAN (115 Kg) / M3 BETON


Bahan : Besi beton 126.50 Kg 13,125.00 1,660,312.50
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 1,700,737.50 Rp 1,700,737.50
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 141,105.00
SUB-TOTAL Rp 1,841,842.50

5 PEMBESIAN (125 Kg) / M3 BETON


Bahan : Besi beton 137.50 Kg 13,125.00 1,804,687.50
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 1,845,112.50 Rp 1,845,112.50
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 153,375.00
SUB-TOTAL Rp 1,998,487.50

6 PEMBESIAN (150 Kg) / M3 BETON


Bahan : Besi beton 165.00 Kg 13,125.00 2,165,625.00
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 2,206,050.00 Rp 2,206,050.00
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 184,050.00
SUB-TOTAL Rp 2,390,100.00

7 PEMBESIAN (175 Kg) / M3 BETON


Bahan : Besi beton 192.50 Kg 13,125.00 2,526,562.50
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 2,566,987.50 Rp 2,566,987.50
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 214,725.00
SUB-TOTAL Rp 2,781,712.50

8 PEMBESIAN (200 Kg) / M3 BETON


Bahan : Besi beton 220.00 Kg 13,125.00 2,887,500.00
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 2,927,925.00 Rp 2,927,925.00
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 245,400.00
SUB-TOTAL Rp 3,173,325.00

9 PEMBESIAN (225 Kg) / M3 BETON


Bahan : Besi beton 247.50 Kg 13,125.00 3,248,437.50
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 3,288,862.50 Rp 3,288,862.50
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 276,075.00
SUB-TOTAL Rp 3,564,937.50

10 PEMBESIAN (250 Kg) / M3 BETON


Bahan : Besi beton 275.00 Kg 13,125.00 3,609,375.00
Kawat beton 2.00 Kg 20,212.50 40,425.00
Sub - Bahan 3,649,800.00 Rp 3,649,800.00
Upah : Dasar upah / Kg, sama dengan upah besi 100 Kg Rp 306,750.00
SUB-TOTAL Rp 3,956,550.00

3.5. REKAPITULASI PEKERJAAN BETON TULANG


3.5.1 HARGA BETON TULANG PLAT DAK / M3, TBL. 12 CM
1. BETON PLAT DAK, TULANGAN 100 Kg /M3
A. BEKISTING 8.33 M2 490,350.00 4,086,250.00
B. BETON, mutu f'c = 19,3 Mpa (K 225) 1.00 M3 986,522.79 986,522.79
C. PEMBESIAN 100 KG 100.00 KG 15,311.44 1,531,143.75
Rp 6,603,916.54
2. BETON PLAT DAK, TULANGAN 100 Kg /M3
A. BEKISTING 8.33 M2 490,350.00 4,086,250.00
B. BETON, mutu f'c = 19,3 Mpa (K 225) 1.00 M3 986,522.79 986,522.79
C. PEMBESIAN 125 KG 125.00 KG 15,311.44 1,913,929.69
Rp 6,986,702.48

3.5.2 HARGA BETON TULANG BALOK PLAT / M3


1. BETON BALOK PLAT , TULANGAN 150 Kg /M3
A. HARGA BEKISTING 0.00
B. HARGA BETON 1Pc : 2Ps : 3Spl 0.00
C. HARGA PEMBESIAN (150 Kg) 0.00
Rp -
3.5.3 HARGA BETON TULANG KOLOM / M3
1. BETON KOLOM, TULANGAN 150 Kg / M3
A. HARGA BEKISTING 0.00
B. HARGA BETON 1Pc : 2Ps : 3Spl 0.00

RAB - 019
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

C. HARGA PEMBESIAN (150 Kg) 0.00


Rp -
3.5.4 BETON BALOK TEA-BEAM / M3
A. HARGA BEKISTING 0.00
B. HARGA BETON 1Pc : 2Ps : 3Spl 0.00
C. HARGA PEMBESIAN (175 Kg), 6 d 13 + d8-200 0.00
Rp -
3.5.5 HARGA BETON TULANG PND. POER / M3
1. BETON PONDASI POER, TULANGAN 100 Kg / M3
A. HARGA BEKISTING 0.00
B. HARGA BETON 1Pc : 2Ps : 3Spl 0.00
C. HARGA PEMBESIAN (100 Kg) 0.00
Rp -
3.5.6 HARGA BETON TULANG JEMBATAN MASUK / M3
1 BETON JEMBATAN BETON MASUK, TULANGAN 150 Kg / M3
A. BEKISTING 6.67 M2 490,350.00 3,269,000.00
B. BETON, mutu f'c = 19,3 Mpa (K 225) 1.00 M3 986,522.79 986,522.79
C. PEMBESIAN 125 KG 150.00 KG 15,311.44 2,296,715.63
Rp 6,552,238.42

IV. PEK. PASANGAN


4.1. PAS. AANSTAMPENG BATU KALI SNI-2008
Bahan : Batu kali 1.200 M3 257,250.00 308,700.00
Pasir urug 0.432 M3 291,375.00 125,874.00
Sub - Bahan 434,574.00 Rp 434,574.00
Upah : Pekerja 0.780 Org 75,000.00 58,500.00
Tukang batu 0.390 Org 90,000.00 35,100.00
Kep. Tukang Batu 0.039 Org 100,000.00 3,900.00
Mandor 0.039 Org 110,000.00 4,290.00
Sub - Upah 101,790.00 Rp 101,790.00
Total Harga Pond. Bt. Kali 1Pc : 3Ps / m3 Rp 536,364.00
4.2. PEK. PONDASI BT. KALI
1 PEK. PONDASI BT. KALI 1Pc : 3Ps
Bahan : Semen PC SNI-2008 202.000 Kg 1,300.00 262,600.00
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.485 M3 265,125.00 128,585.63
Sub - Bahan 699,885.63 Rp 699,885.63
Upah : Pekerja 1.500 Org 75,000.00 112,500.00
Tukang batu 0.750 Org 90,000.00 67,500.00
Kep. Tukang Batu 0.075 Org 100,000.00 7,500.00
Mandor 0.075 Org 110,000.00 8,250.00
Sub - Upah 195,750.00 Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 3Ps / m3 Rp 895,635.63
2 PEK. PONDASI BT. KALI 1Pc : 4Ps
Bahan : Semen PC SNI-2008 163.000 Kg 1,300.00 211,900.00
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.520 M3 265,125.00 137,865.00
Sub - Bahan 658,465.00 Rp 658,465.00
Upah : sama dengan upah Pond. 1Pc : 3Ps Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 4Ps / m3 Rp 854,215.00
3 PEK. PONDASI BT. KALI 1Pc : 5Ps SNI-2008
Bahan : Semen PC 136.000 Kg 1,300.00 176,800.00
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.544 M3 265,125.00 144,228.00
Sub - Bahan 629,728.00 Rp 629,728.00
Upah : sama dengan upah Pond. 1Pc : 3Ps Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 5Ps / m3 Rp 825,478.00
4 PEK. PONDASI BT. KALI 1Pc : 6Ps SNI-2008
Bahan : Semen PC 117.000 Kg 1,300.00 152,100.00
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.561 M3 265,125.00 148,735.13
Sub - Bahan 609,535.13 Rp 609,535.13
Upah : sama dengan upah Pond. 1Pc : 3Ps Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 5Ps / m3 Rp 805,285.13

5 PEK. PONDASI BT. KALI 1Pc : 8Ps SNI-2008


Bahan : Semen PC 91.000 Kg 1,300.00 118,300.00
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.584 M3 265,125.00 154,833.00
Sub - Bahan 581,833.00 Rp 581,833.00
Upah : sama dengan upah Pond. 1Pc : 3Ps Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 5Ps / m3 Rp 777,583.00

6 PEK. PONDASI BT. KALI 1KP : 1SM : 2Ps SNI-2008


Bahan : Kapur padam 0.170 M3 210,000.00 35,700.00
Semen Merah 0.170 M3 183,750.00 31,237.50
Batu kali 1.200 M3 257,250.00 308,700.00
Pasir pasang 0.340 M3 265,125.00 90,142.50
Sub - Bahan 465,780.00 Rp 465,780.00
Upah : sama dengan upah Pond. 1Pc : 3Ps Rp 195,750.00
Total Harga Pond. Bt. Kali 1Pc : 5Ps / m3 Rp 661,530.00

4.3. PEK. DINDING BATA MERAH (1 Batu)


1 PEK. DINDING BATA MERAH (1 Batu), 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 43.500 kg 1,300.00 56,550.00
Batu bata uk. 5 x 11 x 22 cm 140.00 Bh 630.00 88,200.00

RAB - 020
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Pasir pasang 0.080 M3 265,125.00 21,210.00


Sub - Bahan 165,960.00 Rp 165,960.00
Upah : Pekerja 0.600 Org 75,000.00 45,000.00
Tukang batu 0.200 Org 90,000.00 18,000.00
Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
Mandor 0.030 Org 110,000.00 3,300.00
Sub - Upah 68,300.00 Rp 68,300.00
Total harga / M2 Rp 234,260.00
2 PEK. DINDING BATA MERAH (1 Batu), 1Pc : 3Ps / M2 SNI-2008
Bahan : Semen PC 32.950 kg 1,300.00 42,835.00
Batu bata uk. 5 x 11 x 22 cm 140.00 Bh 630.00 88,200.00
Pasir pasang 0.091 M3 265,125.00 24,126.38
Sub - Bahan 155,161.38 Rp 155,161.38
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 68,300.00
Total harga / M2 Rp 223,461.38
3 PEK. DINDING BATA MERAH (1 Batu), 1Pc : 4Ps / M2 SNI-2008
Bahan : Semen PC 26.550 kg 1,300.00 34,515.00
Batu bata uk. 5 x 11 x 22 cm 140.00 Bh 630.00 88,200.00
Pasir pasang 0.093 M3 265,125.00 24,656.63
Sub - Bahan 147,371.63 Rp 147,371.63
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 68,300.00
Total harga / M2 Rp 215,671.63
4 PEK. DINDING BATA MERAH (1 Batu), 1Pc : 5Ps / M2 SNI-2008
Bahan : Semen PC 22.200 kg 1,300.00 28,860.00
Batu bata uk. 5 x 11 x 22 cm 140.00 Bh 630.00 88,200.00
Pasir pasang 0.102 M3 265,125.00 27,042.75
Sub - Bahan 144,102.75 Rp 144,102.75
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 68,300.00
Total harga / M2 Rp 212,402.75
5 PEK. DINDING BATA MERAH (1 Batu), 1Pc : 6Ps / M2 SNI-2008
Bahan : Semen PC 18.500 kg 1,300.00 24,050.00
Batu bata uk. 5 x 11 x 22 cm 140.00 Bh 630.00 88,200.00
Pasir pasang 0.122 M3 265,125.00 32,345.25
Sub - Bahan 144,595.25 Rp 144,595.25
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 68,300.00
Total harga / M2 Rp 212,895.25

4.4. PEK. DINDING BATA MERAH (1/2 Batu)


1 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 18.950 kg 1,300.00 24,635.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.038 M3 265,125.00 10,074.75
Sub - Bahan 78,809.75 Rp 78,809.75
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu 0.100 Org 90,000.00 9,000.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 34,150.00 Rp 34,150.00
Total harga / M2 Rp 112,959.75
2 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 3Ps / M2 SNI-2008
Bahan : Semen PC 14.370 kg 1,300.00 18,681.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.040 M3 265,125.00 10,605.00
Sub - Bahan 73,386.00 Rp 73,386.00
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 107,536.00

3 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 4Ps / M2 SNI-2008


Bahan : Semen PC 11.500 kg 1,300.00 14,950.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.043 M3 265,125.00 11,400.38
Sub - Bahan 70,450.38 Rp 70,450.38
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 104,600.38

4 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 5Ps / M2 SNI-2008


Bahan : Semen PC 9.680 kg 1,300.00 12,584.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Sub - Bahan 68,614.63 Rp 68,614.63
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 102,764.63

5 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 6Ps / M2 SNI-2008


Bahan : Semen PC 8.320 kg 1,300.00 10,816.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.049 M3 265,125.00 12,991.13
Sub - Bahan 67,907.13 Rp 67,907.13
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 102,057.13

6 PEK. DINDING BATA MERAH (1/2 Batu), 1Pc : 8Ps / M2 SNI-2008


Bahan : Semen PC 6.500 kg 1,300.00 8,450.00
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Pasir pasang 0.050 M3 265,125.00 13,256.25
Sub - Bahan 65,806.25 Rp 65,806.25

RAB - 021
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 99,956.25

7 DINDING BATA MERAH (1/2 Batu), 1Pc : 3KP : 10Ps / M2 SNI-2008


Bahan : Semen PC 4.500 kg 1,300.00 5,850.00
Kapur Padam 0.015 M3 210,000.00 3,150.00
Pasir pasang 0.050 M3 265,125.00 13,256.25
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Sub - Bahan 66,356.25 Rp 66,356.25
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu 0.100 Org 90,000.00 9,000.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 34,150.00 Rp 34,150.00
Total harga / M2 Rp 100,506.25
8 DINDING BATA MERAH (1/2 Batu), 1KP : 1SM : 1Ps / M2 SNI-2008
Bahan : Semen Merah 0.018 m3 183,750.00 3,307.50
Kapur Padam 0.018 M3 210,000.00 3,780.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Batu bata uk. 5 x 11 x 22 cm 70.00 Bh 630.00 44,100.00
Sub - Bahan 55,959.75 Rp 55,959.75
Upah : Sama dengan upah pas 1Pc : 2Ps Sub - Upah Rp 34,150.00
Total harga / M2 Rp 90,109.75

4.5. PEK. DINDING "HEBEL


1 PEK. DINDING "HEBEL" (tbl 10 cm) 1Pc : 3Ps / M2
Bahan : Semen PC (ambil koefisien pas bata 1Pc : 3Ps) 14.370 kg 1,300.00 18,681.00
Batu bata ringan (ex Hebel), 10x16x60 cm 8.340 bh 8,542.80 71,246.95
Pasir pasang (keofesien diragukan) 0.728 0.0728 M3 265,125.00 19,301.10
Sub - Bahan 109,229.05 Rp 109,229.05
Upah : Pekerja 0.350 Org 75,000.00 26,250.00
Tukang batu 0.150 Org 90,000.00 13,500.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.018 Org 110,000.00 1,980.00
Sub - Upah 43,230.00 Rp 43,230.00
Total harga / M2 Rp 152,459.05
2 PEK. DINDING "HEBEL" (tbl 7 cm) 1Pc : 3Ps / M2
Bahan : Semen PC (ambil koefisien pas bata 1Pc : 3Ps) 14.370 kg 1,300.00 18,681.00
Batu bata ringan (ex Hebel), 7x16x60 cm 8.340 bh 5,979.96 49,872.87
Pasir pasang (keofesien diragukan) 0.728 0.0728 M3 265,125.00 19,301.10
Sub - Bahan 87,854.97 Rp 87,854.97
Upah : Sama dengan upah pas Hebel 10 cm Sub - Upah Rp 43,230.00
Total harga / M2 Rp 131,084.97

3 PEK. DINDING "HEBEL" (tbl 10 cm), perekat Mortar / M2


Bahan : Batu bata ringan (ex Hebel), 10x16x60 cm 8.500 bh 8,542.80 72,613.80
Perekat PM-100 / MU-100 (perekat) 3.200 kg 1,575.00 5,040.00
Sub - Bahan 77,653.80 Rp 77,653.80
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu 0.150 Org 90,000.00 13,500.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,150.00 Rp 39,150.00
Total harga / M2 Rp 116,803.80
4 PEK. DINDING "HEBEL" (tbl 7 cm), perekat Mortar / M2
Bahan : Batu bata ringan (ex Hebel), 7x16x60 cm 8.500 bh 5,979.96 50,829.66
Perekat PM-100 / MU-100 (perekat) 2.400 M3 1,575.00 3,780.00
Sub - Bahan 54,609.66 Rp 54,609.66
Upah : Sama dengan upah pas Hebel 10 cm Sub - Upah Rp 39,150.00
Total harga / M2 Rp 93,759.66
4.6. PEK. DINDING BATACO 1Pc : 3Ps / M2
Bahan : Semen PC (ambil koefisien pas bata 1Pc : 3Ps) 14.370 kg 1,300.00 18,681.00
Bataco semen, 10x19x40 cm 12.50 Bh 4,200.00 52,500.00
Pasir pasang (keofesien diragukan) 0.728 0.0728 M3 265,125.00 19,301.10
Sub - Bahan 90,482.10 Rp 90,482.10
Upah : Pekerja 0.350 Org 75,000.00 26,250.00
Tukang batu 0.150 Org 90,000.00 13,500.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.018 Org 110,000.00 1,980.00
Sub - Upah 43,230.00 Rp 43,230.00
T O T A L Rp 133,712.10
4.7. PEK. DINDING GLASSBLOCK / M2
Bahan : Semen PC (ambil koefisien pas bata 1Pc : 3Ps) 14.370 kg 1,300.00 18,681.00
Glassblock 20/20 25.000 Bh 31,500.00 787,500.00
Pasir pasang (keofesien diragukan) 0.0420 M3 265,125.00 11,135.25
Sub - Bahan 817,316.25 Rp 817,316.25
Upah : Pekerja 0.350 Org 75,000.00 26,250.00
Tukang batu 0.150 Org 90,000.00 13,500.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.018 Org 110,000.00 1,980.00
Sub - Upah 43,230.00 Rp 43,230.00
T O T A L Rp 860,546.25
4.8. PEK. DINDING BATA KRAWANG / M2
Bahan : Semen PC 0.420 zak 65,000.00 27,300.00
Rooster bata merah 12x24x24 cm 16.000 Bh 5,075.70 81,211.20
Pasir pasang 0.050 M3 265,125.00 13,256.25
Sub - Bahan 121,767.45 Rp 121,767.45
Upah : sama dg upah pas glassblok Rp 43,230.00

RAB - 022
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

T O T A L Rp 164,997.45

4.9. PEK. DINDING ALLUMUNIUM COMPOSIT PANEL (ACP) / M2


Bahan : Allumunium Composit Panel (ACP) 1.0000 m2 400,000.00 400,000.00
Rangka allumunium hollow 5.000 m' 12,500.00 62,500.00
Paku skrup 0.580 kg 45,000.00 26,100.00
Sealant 0.8000 m' 8,531.25 6,825.00
Sub - Bahan 495,425.00 Rp 495,425.00
Upah : Pekerja 1.500 Org 75,000.00 112,500.00
Tukang allumunium 1.500 Org 100,000.00 150,000.00
Kep. Tukang 0.150 Org 90,000.00 13,500.00
Mandor 0.600 Org 110,000.00 66,000.00
Sub - Upah 342,000.00 Rp 239,400.00
Total harga / M2 Rp 734,825.00
4.10. PEK. CURTAINWALL KACA / M2
(Diambil sample 20x20 m = 400 m2)
Bahan : Curtainwall Transom Hitam (horizontal) 280.00 m' 157,500.00 44,100,000.00
Curtainwall Mulion Hitam (vertical) 240.00 m' 189,000.00 45,360,000.00
Frame Allumunium Casement Jendela m' 105,000.00 0.00
Kaca Stopsol 8mm 400.00 m' 708,750.00 283,500,000.00
Sealant 520.00 m' 8,531.25 4,436,250.00
Nilai harga untuk seluas 400m2 377,396,250.00 Rp 377,396,250.00
Total harga / M2 Rp 943,490.63

V. PEKERJAAN BAJA
1 MEMASANG BESI PROFIL / KG SNI-2008
Bahan : Besi profil (besi siku) 1.150 kg 14,455.35 16,623.65
Sub - Bahan 16,623.65 Rp 16,623.65
Upah : Pekerja 0.060 Org 75,000.00 4,500.00
50% Tukang Las konstruksi 0.060 Org 100,000.00 6,000.00
Kepala tukang 0.006 Org 90,000.00 540.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 11,370.00 Rp 5,685.00
T O T A L Rp 22,308.65
2 MEMASANG BESI BAJA IWF / KG SNI-2008
Bahan : Besi baja IWF 1.150 kg 13,125.00 15,093.75
Sub - Bahan 15,093.75 Rp 15,093.75
Upah : Pekerja 0.060 Org 75,000.00 4,500.00
50% Tukang Las konstruksi 0.060 Org 100,000.00 6,000.00
Kepala tukang 0.006 Org 90,000.00 540.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 11,370.00 Rp 5,685.00
T O T A L Rp 20,778.75
3 MENGERJAKAN 100 KG PEK. PERAKITAN SNI-2008
Bahan : Solar 1.000 liter 4,500.00 4,500.00
Minyak pelumas 0.100 liter 35,000.00 3,500.00
Sub - Bahan 8,000.00 Rp 8,000.00
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Tukang besi konstruksi 0.100 Org 85,000.00 8,500.00
Kepala tukang 0.001 Org 90,000.00 90.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 16,640.00 Rp 16,640.00
Sewa Alat 0.800 jam 50,000.00 40,000.00 Rp 40,000.00
T O T A L Rp 64,640.00
Biaya untuk perakitan / kg Rp 646.40
4 PEK. PINTU BESI DOUBLE PLAT 2MM, RANGKA SIKU / M2 SNI-2008
Bahan : Besi siku 30x30x3mm 15.000 kg 14,455.35 216,830.25
Besi plat baja 32.800 kg 15,750.00 516,600.00
Kawat Las 0.050 kg 31,500.00 1,575.00
Sub - Bahan 735,005.25 Rp 735,005.25
Upah : Pekerja 1.050 Org 75,000.00 78,750.00
Tukang Las konstruksi 1.050 Org 100,000.00 105,000.00
Kepala tukang 0.105 Org 90,000.00 9,450.00
Mandor 0.052 Org 110,000.00 5,720.00
Sub - Upah 198,920.00 Rp 198,920.00
T O T A L Rp 933,925.25
5 PEK. PENGELASAN 10 CM, dengan Las listrik SNI-2008
Bahan : Kawat las listrik 0.400 kg 31,500.00 12,600.00
Solar 0.300 liter 4,500.00 1,350.00
Minyak pelumas 0.040 liter 35,000.00 1,400.00
Sub - Bahan 15,350.00 Rp 15,350.00
Upah : Pekerja 0.040 Org 75,000.00 3,000.00
Tukang Las konstruksi 0.020 Org 100,000.00 2,000.00
Kepala tukang 0.002 Org 90,000.00 180.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 5,400.00 Rp 5,400.00
Sewa Alat 0.170 jam 50,000.00 8,500.00 Rp 8,500.00
T O T A L Rp 29,250.00
Biaya untuk 1m pengelasan Rp 292,500.00
6 MEMASANG PINTU ROLLING DOOR BESI / M2 SNI-2008
Bahan : Pintu gulung besi 1.000 M2 450,000.00 450,000.00
Sub - Bahan 450,000.00 Rp 450,000.00
Upah : Pekerja 1.200 Org 75,000.00 90,000.00
Tukang Las konstruksi 1.200 Org 100,000.00 120,000.00
Kepala tukang 0.120 Org 90,000.00 10,800.00
Mandor 0.006 Org 110,000.00 660.00
Sub - Upah 221,460.00 Rp 221,460.00

RAB - 023
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

T O T A L Rp 671,460.00
7 MEMASANG SUNSCREEN ALLUMUNIUM / M2 SNI-2008
Bahan : Sunscreen allumunium 1.000 M2 300,000.00 300,000.00
Sub - Bahan 300,000.00 Rp 300,000.00
Upah : Pekerja 0.080 Org 75,000.00 6,000.00
Tukang Allumunium 0.800 Org 100,000.00 80,000.00
Kepala tukang 0.080 Org 90,000.00 7,200.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 93,640.00 Rp 93,640.00
T O T A L Rp 393,640.00
8 MEMASANG ROLLING ALLUMUNIUM / M2 SNI-2008
Bahan : Rolling Door Allumunium 1.000 M2 550,000.00 550,000.00
Sub - Bahan 550,000.00 Rp 550,000.00
Upah : Pekerja 1.000 Org 75,000.00 75,000.00
Tukang Allumunium 1.000 Org 100,000.00 100,000.00
Kepala tukang 0.100 Org 90,000.00 9,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 189,500.00 Rp 189,500.00
T O T A L Rp 739,500.00

9 Pekerjaan Railling Besi (black steel) Teras/Balkon /M'


(modul 4,2 m / unit)
- Railling besi bahan pipa besi hitam dia. 2" (hand rail) m' 4.20 m' 142,967 600,460.00
- Railling besi bahan pipa besi hitam dia. 1,5" (tiang) m' 6.60 m' 112,800 744,480.00
- Railling besi bahan pipa besi hitam dia. 1" (pembagi) m' 16.80 m' 65,967 1,108,240.00
- Base plate + baut angkur bh 6.00 bh 40,000.00 240,000.00
- Finishing pengecatan lot 1.00 lot 245,318.00 245,318.00
- Upah lot 1.00 lot 734,624.50 734,624.50
pasang Total harga / unit 3,673,122.50
Harga / m' 874,552.98
10 Pekerjaan Railling Besi (Black steel) Tangga /M'
(modul 3,50 m'/ unit)
- Railling besi bahan pipa besi hitam dia. 2" (hand rail) 3.50 m' 142,967 500,383.33
- Railling besi bahan pipa besi hitam dia. 1,5" (tiang) 4.40 m' 112,800 496,320.00
- Railling besi bahan pipa besi hitam dia. 1" (pembagi) 14.00 m' 65,967 923,533.33
- Base plate + baut angkur 4.00 bh 40,000.00 160,000.00
- Finishing pengecatan 1.00 lot 192,023.67 192,023.67
- Upah 1.00 lot 568,065.08 568,065.08
pasang Total harga / unit 2,840,325.42
Harga / m' 811,521.55
11 Pekerjaan Railling Besi Stainless Steel, Tangga /M'
(modul 3,50 m'/ unit)
- Railling besi bahan pipa stainless steel, dia. 2,5" (hand rail) 3.50 m' 206,007 721,023.33
- Railling besi bahan pipa stainless steel, dia. 2" (tiang) 4.40 m' 185,857 817,769.33
- Railling besi bahan pipa stainless steel, dia. 1" (pembagi) 14.00 m' 85,757 1,200,593.33
- Base plate + baut angkur 4.00 bh 60,000.00 240,000.00
- Finishing pengecatan - lot 273,938.60 0.00
- Upah 1.00 lot 744,846.50 744,846.50
pasang Total harga / unit 3,724,232.50
Harga / m' 1,064,066.43
12 Pek. Louvre besi Teras/Balkon (uk. 60x420 cm)/unit
(modul 60x420 cm)
- Frame besi hollow 50x100 12.00 m' 98,335.00 1,180,020.00
- Grill besi plat tebal 2 mm 2.52 m2 650,724.17 1,639,824.90
- Finishing pengecatan 8.04 m2 #REF! #REF!
- Upah 1.00 lot #REF! #REF!
pasang Total harga / unit #REF!
Harga / m2 #REF!
13 Pek. Tralis besi hollow, Parkir Mobil PK (modul 7,50 x 0,90 m)/M2
- Frame besi hollow 60x40x2 mm 14.70 m' 38,490.83 565,815.25
- Tralis besi hollow 40x20x1,8 mm 67.50 m' 21,211.67 1,431,787.50
- Finishing pengecatan 13.50 m2 #REF! #REF!
- Upah 1.00 lot #REF! #REF!
pasang Total harga / unit #REF!
Harga / m2 #REF!
14 Pek. Dinding besi wire mesh, rangka pipa GIP
(modul : 4.6 x 3,75 m = 17,25 M2)
- Frame besi pipa dia 2" 40.90 m' 124,300.00 5,083,870.00
- Frame pintu besi pipa dia 1,5" 6.10 m' 91,133.00 555,911.30
- Tralis besi wire mesh DM-6F1 17.25 m' 29,562.13 509,946.74
- Finishing pengecatan 17.25 m2 #REF! #REF!
- Engsel bubut, kunci gembok dan dudukannya 1.00 lot 500,000.00 500,000.00
- Upah 1.00 lot #REF! #REF!
pasang Total harga / unit #REF!
Harga / m2 #REF!

V.A. PEK. KOSEN, PINTU & JND. ALLUMUNIUM


1 PROFIL KOSEN ALLUMUNIUM / M', ex YKK SNI-2008
Profil kosen All. 1 3/4 x 4", Silver Clear Anodized ex YKK
Bahan : Profil kosen All. 1 3/4 x 4", Silver Clear Anodized ex YKK 1.100 m' 115,500.00 127,050.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 139,434.38 Rp 139,434.38
Upah : Pekerja 0.043 Org 75,000.00 3,225.00
Tukang Allumunium 0.043 Org 100,000.00 4,300.00
Kepala tukang 0.0043 Org 90,000.00 387.00

RAB - 024
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Mandor 0.0021 Org 110,000.00 231.00


Sub - Upah 8,143.00 Rp 8,143.00
T O T A L Rp 147,577.38
1.a. PROFIL KOSEN ALLUMUNIUM / M', ex YKK SNI-2008
Profil kosen All. 1 3/4 x 4", Black/Brown Anodized ex YKK
Bahan : Profil kosen All. 1 3/4 x 4", Black/Brown Anodized ex YKK 1.100 m' 157,500.00 173,250.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 185,634.38Rp 185,634.38
Upah : Sub - Upah Rp 8,143.00
T O T A L Rp 193,777.38

1.b. PROFIL KOSEN ALLUMUNIUM / M', ex YKK SNI-2008


Profil kosen Allumunium 1 3/4 x 4", Powder Coating ex YKK
Bahan : Profil kosen Allumunium 1 3/4 x 4", Powder Coating ex YKK 1.100 m' 168,000.00 184,800.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 197,184.38Rp 197,184.38
Upah : Sub - Upah Rp 8,143.00
T O T A L Rp 205,327.38

2 PROFIL ALLUMUNIUM RANGKA PINTU KACA / M', ex YKK SNI-2008


Profil Frame All. Pintu kaca, Silver Clear Anodized ex YKK
Bahan : Profil Frame All. Pintu kaca, Silver Clear Anodized ex YKK 1.100 m' 105,000.00 115,500.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 127,884.38Rp 127,884.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 136,027.38

2.a. PROFIL ALLUMUNIUM RANGKA PINTU KACA / M', ex YKK SNI-2008


Profil Frame All. Pintu kaca, Black/Brown Anodized ex YKK
Bahan : Profil Frame All. Pintu kaca, Black/Brown Anodized ex YKK 1.100 m' 147,000.00 161,700.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 174,084.38Rp 174,084.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 182,227.38
2.b. PROFIL ALLUMUNIUM RANGKA PINTU KACA / M', ex YKK SNI-2008
Profil Frame All. Pintu kaca, Powder Coating ex YKK
Bahan : Profil Frame All. Pintu kaca, Powder Coating ex YKK 1.100 m' 161,700.00 177,870.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 190,254.38Rp 190,254.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 198,397.38

3 PROFIL ALLUMUNIUM RANGKA JENDELA KACA / M', ex YKK SNI-2008


Profil Frame All. Jendela kaca, Silver Clear Anodized ex YKK
Bahan : Profil Frame All. Jendela kaca, Silver Clear Anodized ex YKK 1.100 m' 89,250.00 98,175.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 110,559.38Rp 110,559.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 118,702.38
3.a. PROFIL ALLUMUNIUM RANGKA JENDELA KACA / M', ex YKK SNI-2008
Profil Frame All. Jendela kaca, Black/Brown Anodized ex YKK
Bahan : Profil Frame All. Jendela kaca, Black/Brown Anodized ex YKK 1.100 m' 105,000.00 115,500.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 127,884.38Rp 127,884.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 136,027.38
3.b. PROFIL ALLUMUNIUM RANGKA JENDELA KACA / M', ex YKK SNI-2008
Profil Frame All. Jendela kaca, Powder Coating ex YKK
Bahan : Profil Frame All. Jendela kaca, Powder Coating ex YKK 1.100 m' 126,000.00 138,600.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 150,984.38Rp 150,984.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 159,127.38

4 PROFIL KOSEN ALLUMUNIUM / M' Ex ALEXINDO SNI-2008


Profil kosen All. 1 3/4 x 4", Silver Clear Anodized ex Alexindo
Bahan : Kosen All. 1 3/4 x 4", Silver Clear Anodized ex Alexindo 1.100 m' 68,250.00 75,075.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 87,459.38 Rp 87,459.38
Upah : Pekerja 0.043 Org 75,000.00 3,225.00
Tukang Allumunium 0.043 Org 100,000.00 4,300.00
Kepala tukang 0.0043 Org 90,000.00 387.00
Mandor 0.0021 Org 110,000.00 231.00
Sub - Upah 8,143.00 Rp 8,143.00
T O T A L Rp 95,602.38
4.a. PROFIL KOSEN ALLUMUNIUM / M' (ALEXINDO) SNI-2008
Profil kosen All. 1 3/4 x 4", Black/Brown Anodized ex Alexindo
Bahan : Profil kosen All. 1 3/4 x 4", Black/Brown Anodized ex YKK 1.100 m' 78,750.00 86,625.00

RAB - 025
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Skrup fixer 2.000 bh 1,500.00 3,000.00


Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 99,009.38Rp 99,009.38
Upah : Sub - Upah Rp 8,143.00
T O T A L Rp 107,152.38
4.b. PROFIL KOSEN ALLUMUNIUM / M' (ALEXINDO) SNI-2008
Profil kosen All. 1 3/4 x 4", Coating serat kayu, ex Alexindo
Bahan : Profil kosen All. 1 3/4 x 4", coating serat kayu, ex Alexindo 1.100 m' 168,000.00 184,800.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 197,184.38Rp 197,184.38
Upah : Sub - Upah Rp 8,143.00
T O T A L Rp 205,327.38

5 FRAME ALLUMUNIUM RANGKA PINTU KACA (ALEXINDO) / M' SNI-2008


Profil Frame All. Pintu kaca, Silver Clear Anodized ex Alexindo
Bahan : Frame All. Pintu kaca, Silver Clear Anodized ex Alexindo 1.100 m' 63,000.00 69,300.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 81,684.38Rp 81,684.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 89,827.38

5.a. PROFIL ALLUMUNIUM RANGKA PINTU KACA (ALEXINDO) / M' SNI-2008


Profil Frame All. Pintu kaca, Black/Brown Anodized ex Alexindo
Bahan : Profil Frame All. Pintu kaca, Black/Brown Anodized ex Alexindo 1.100 m' 73,500.00 80,850.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 93,234.38Rp 93,234.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 101,377.38
5.b. PROFIL ALLUMUNIUM RANGKA PINTU KACA (ALEXINDO) / M' SNI-2008
Profil Frame All. Pintu kaca, Coating serat kayu, ex Alexindo
Bahan : Profil Frame All. Pintu kaca, coating serat kayu, ex Alexindo 1.100 m' 157,500.00 173,250.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 185,634.38Rp 185,634.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 193,777.38

6 FRAME ALLUMUNIUM RANGKA JENDELA KACA (ALEXINDO) / SNI-2008


Profil Frame All. Jendela kaca, Silver Clear Anodized ex Alexindo
Bahan : Frame All. Jendela kaca, Silver Clear Anodized ex Alexindo 1.100 m' 52,500.00 57,750.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 70,134.38Rp 70,134.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 78,277.38
6.a. FRAME ALLUMUNIUM RANGKA JENDELA KACA (ALEXINDO) / SNI-2008
Profil Frame All. Jendela kaca, Black/Brown Anodized ex Alexindo
Bahan : Profil Frame All. Jendela kaca, Black/Brown Anodized ex YKK 1.100 m' 63,000.00 69,300.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 81,684.38Rp 81,684.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 89,827.38
6.b. FRAME ALLUMUNIUM RANGKA JENDELA KACA (ALEXINDO) / SNI-2008
Profil Frame All. Jendela kaca, Coating serat kayu, ex Alexindo
Bahan : Profil Frame All. Jendela kaca, coating serat kayu, ex Alexindo 1.100 m' 126,000.00 138,600.00
Skrup fixer 2.000 bh 1,500.00 3,000.00
Sealant 1.100 m' 8,531.25 9,384.38
Sub - Bahan 150,984.38Rp 150,984.38
Upah : sama dengan upah pas. Kosen kaca Rp 8,143.00
T O T A L Rp 159,127.38

VI. PEK. KAYU & PLASTIK


6.1. PEK. KUDA-KUDA KAYU KONVENSIONAL
1 PEK. KUDA-KUDA KAYU KONVENSIONAL / M3
KAYU KELAS - I (Kamper Samarinda), bentang 6 m. SNI-2008
Bahan : Kayu kelas-1 (Kamper Samarinda) 1.100 M3 7,350,000.00 8,085,000.00
Paku 12 cm 5.600 Kg 15,356.25 85,995.00
Besi strip tebal 5 mm 15.000 Kg 14,542.50 218,137.50
Sub - Bahan 8,389,132.50 Rp 8,389,132.50
Upah : Pekerja 4.000 Org 75,000.00 300,000.00
Tukang Kayu 12.000 Org 90,000.00 1,080,000.00
Kep. Tukang Kayu 1.200 Org 105,000.00 126,000.00
Mandor 0.200 Org 110,000.00 22,000.00
Sub - Upah 1,528,000.00 Rp 1,528,000.00
T O T A L Rp 9,917,132.50
2 PEK. KUDA-KUDA KAYU KONVENSIONAL / M3
KAYU KELAS - II (Kamper Medan/Kruing), bentang 6 m. SNI-2008
Bahan : Kayu kelas-II (Kamper Medan / Kruing) 1.100 M3 5,040,000.00 5,544,000.00

RAB - 026
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Paku 12 cm 5.600 Kg 15,356.25 85,995.00


Besi strip tebal 5 mm 15.000 Kg 14,542.50 218,137.50
Sub - Bahan 5,848,132.50 Rp 5,848,132.50
Upah : sama dgn upah Kuda2 kayu Borneo Rp 1,528,000.00
T O T A L Rp 7,376,132.50

3 PEK. KUDA-KUDA KAYU KONVENSIONAL / M3


KAYU KELAS - III (Borneo/Meranti super), bentang 6 m. SNI-2008
Bahan : Kayu kelas-III (Borneo / Meranti super) 1.100 M3 4,725,000.00 5,197,500.00
Paku 12 cm 5.600 Kg 15,356.25 85,995.00
Besi strip tebal 5 mm 15.000 Kg 14,542.50 218,137.50
Sub - Bahan 5,501,632.50 Rp 5,501,632.50
Upah : sama dgn upah Kuda2 kayu Borneo Rp 1,528,000.00
T O T A L Rp 7,029,632.50

6.2. PEK. KUDA-KUDA EXPOSE, KAYU KELAS-I / M3 SNI-2008


KAYU KELAS - I (Kamper Samarinda), bentang 6 m.
Bahan : Kayu kelas-1 (Kamper Samarinda) 1.200 M3 7,350,000.00 8,820,000.00
Paku 12 cm 5.600 Kg 15,356.25 85,995.00
Besi strip tebal 5 mm 15.000 Kg 14,542.50 218,137.50
Sub - Bahan 9,124,132.50 Rp 9,124,132.50
Upah : Pekerja 6.700 Org 75,000.00 502,500.00
Tukang Kayu 20.100 Org 90,000.00 1,809,000.00
Kep. Tukang Kayu 2.010 Org 105,000.00 211,050.00
Mandor 0.335 Org 110,000.00 36,850.00
Sub - Upah 2,559,400.00 Rp 2,559,400.00
T O T A L Rp 11,683,532.50

6.3. PEK. KONSTRUKSI GORDENG, KAYU KELAS-II / M3 SNI-2008


KAYU KELAS - II (Kamper Medan/Kruing), bentang 6 m.
Bahan : Kayu kelas-II (Kamper Medan / Kruing) 1.100 M3 5,040,000.00 5,544,000.00
Paku 12 cm 3.000 Kg 15,356.25 46,068.75
Besi strip tebal 5 mm 15.000 Kg 14,542.50 218,137.50
Sub - Bahan 5,808,206.25 Rp 5,808,206.25
Upah : Pekerja 2.400 Org 75,000.00 180,000.00
Tukang Kayu 7.200 Org 90,000.00 648,000.00
Kep. Tukang Kayu 0.720 Org 105,000.00 75,600.00
Mandor 0.120 Org 110,000.00 13,200.00
Sub - Upah 916,800.00 Rp 916,800.00
T O T A L Rp 6,725,006.25
6.4. PEK. RANGKA ATAP
1 RANGKA ATAP, Genteng Keramik / M2 SNI-2008
Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Kasau 5/7, kayu kelas-II (Kamper Medan / Kruing) 0.014 M3 4,725,000.00 66,150.00
Reng 2/3, kayu kelas-II (Kamper Medan / Kruing) 0.0036 M3 4,725,000.00 17,010.00
Paku (5 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 86,999.06 Rp 86,999.06
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Tukang Kayu 0.100 Org 90,000.00 9,000.00
Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,100.00 Rp 18,100.00
T O T A L Rp 105,099.06
2 RANGKA ATAP, Genteng Keramik / M2 SNI-2008
Kayu kelas-II (Kayu Bengkirai)
Bahan : Kasau 5/7, kayu kelas-II (Bengkirai) 0.014 M3 7,140,000.00 99,960.00
Reng 2/3, kayu kelas-II (Bengkirai) 0.0036 M3 7,140,000.00 25,704.00
Paku (5 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 129,503.06Rp 129,503.06
Upah : sama dgn upah rangka atap ky kelas-2 Rp 18,100.00
T O T A L Rp 147,603.06
3 RANGKA ATAP, Genteng Keramik / M2 SNI-2008
Kayu kelas-III (Kayu Borneo/Meranti super)
Bahan : Kasau 5/7, kayu kelas-III (Borneo/Meranti super) 0.014 M3 4,462,500.00 62,475.00
Reng 2/3, kayu kelas-III (Borneo/Meranti super) 0.0036 M3 4,462,500.00 16,065.00
Paku (5 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 82,379.06Rp 82,379.06
Upah : sama dgn upah rangka atap ky kelas-2 Rp 18,100.00
T O T A L Rp 100,479.06

4 RANGKA ATAP, Genteng Beton / M2 SNI-2008


Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Kasau 5/7, kayu kelas-II (Kamper Medan / Kruing) 0.014 M3 4,725,000.00 66,150.00
Reng 3/4, kayu kelas-II (Kamper Medan / Kruing) 0.0072 M3 4,725,000.00 34,020.00
Paku (5 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 104,009.06 Rp 104,009.06
Upah : Pekerja 0.100 Org 75,000.00 7,500.00
Tukang Kayu 0.100 Org 90,000.00 9,000.00
Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,100.00 Rp 18,100.00
T O T A L Rp 122,109.06
5 RANGKA ATAP, Sirap / M2, Kayu kelas-II SNI-2008
Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Kayu kelas-II (Kamper Medan / Kruing) 0.165 0.0165 M3 4,725,000.00 77,962.50
Paku (5 - 10 cm) 0.200 Kg 15,356.25 3,071.25
Sub - Bahan 81,033.75 Rp 81,033.75
Upah : Pekerja 0.120 Org 75,000.00 9,000.00

RAB - 027
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Tukang Kayu 0.120 Org 90,000.00 10,800.00


Kep. Tukang Kayu 0.012 Org 105,000.00 1,260.00
Mandor 0.006 Org 110,000.00 660.00
Sub - Upah 21,720.00 Rp 21,720.00
T O T A L Rp 102,753.75
6.5. PEK. LISTPLANK
1 PEK. LISTPLANK JATI 3/20 / M'
Bahan : Papan Jati 0.007 M3 60,375,000.00 422,625.00
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 423,392.81 Rp 423,392.81
Upah : Kep. Tukang Kayu 0.020 Org 105,000.00 2,100.00
Tukang Kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 28,150.00 Rp 28,150.00
Rp 451,542.81
2 PEK. LISTPLANK JATI 3/30 / M'
Bahan : Papan Jati 0.011 M3 60,375,000.00 664,125.00
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 664,892.81 Rp 664,892.81
Upah : Kep. Tukang Kayu 0.022 Org 105,000.00 2,310.00
Tukang Kayu 0.220 Org 90,000.00 19,800.00
Pekerja 0.110 Org 75,000.00 8,250.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 30,910.00 Rp 30,910.00
Rp 695,802.81
3 PEK. LISTPLANK BENGKIRAI 3/30 / M'
Bahan : Papan Bengkirai 0.011 M3 7,612,500.00 83,737.50
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 84,505.31 Rp 84,505.31
Upah : Kep. Tukang Kayu 0.022 Org 105,000.00 2,310.00
Tukang Kayu 0.220 Org 90,000.00 19,800.00
Pekerja 0.110 Org 75,000.00 8,250.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 30,910.00 Rp 30,910.00
Rp 115,415.31
4 PEK. LISTPLANK 3/20 / M', kayu kelas-I atau II SNI-2008 0.0066
Kayu Kamper Samarinda oven
Bahan : Kayu kelas-I (Papan Kamper Samarinda oven) 0.007 M3 10,395,000.00 72,765.00
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 73,532.81 Rp 73,532.81
Upah : Kep. Tukang Kayu 0.020 Org 105,000.00 2,100.00
Tukang Kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 28,150.00 Rp 28,150.00
Rp 101,682.81
5 PEK. LISTPLANK 3/20 / M', kayu kelas-I atau II SNI-2008
Kayu Kamper Singkil oven
Bahan : Kayu kelas-II (Papan Kamper Singkil oven) 0.007 M3 8,137,500.00 56,962.50
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 57,730.31 Rp 57,730.31
Upah sama dgn listplank kamper Smrd Rp 28,150.00
Rp 85,880.31

6 PEK. LISTPLANK 3/30 / M', kayu kelas-I atau II SNI-2008


Kayu Kamper Samarinda oven
Bahan : Kayu kelas-I (Papan Kamper Samarinda oven) 0.011 M3 10,395,000.00 114,345.00
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 115,112.81 Rp 115,112.81

Upah : Kep. Tukang Kayu 0.022 Org 105,000.00 2,310.00


Tukang Kayu 0.220 Org 90,000.00 19,800.00
Pekerja 0.110 Org 75,000.00 8,250.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 30,910.00 Rp 30,910.00
Rp 146,022.81
7 PEK. LISTPLANK 3/30 / M', kayu kelas-I atau II SNI-2008
Kayu Kamper Singkil oven
Bahan : Kayu kelas-II (Papan Kamper Singkil oven) 0.011 M3 8,137,500.00 89,512.50
Paku (5 - 7 cm) 0.050 kg 15,356.25 767.81
Sub - Bahan 90,280.31 Rp 90,280.31
Upah sama dgn listplank kamper Smrd Rp 30,910.00
Rp 121,190.31

6.6. PEK. RANGKA PLAFOND


1 PEK. RANGKA PLAFOND (50x100) / M2, Kayu kelas-II / III SNI-2008
Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Kayu kelas-II (Kamper Medan / Kruing) 0.015 M3 4,725,000.00 72,765.00
Paku (7 - 10 cm) 0.200 Kg 15,356.25 3,071.25
Sub - Bahan 75,836.25 Rp 75,836.25
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang Kayu 0.300 Org 90,000.00 27,000.00
Kep. Tukang Kayu 0.030 Org 105,000.00 3,150.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 42,280.00 Rp 42,280.00

RAB - 028
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

T O T A L Rp 118,116.25
2 PEK. RANGKA PLAFOND (50x100) / M2, Kayu kelas-II / III SNI-2008
Kayu kelas-III (Kayu Borneo/Meranti super)
Bahan : Kasau 5/7, kayu kelas-III (Borneo/Meranti super) 0.015 M3 4,462,500.00 68,722.50
Paku (7 - 10 cm) 0.200 Kg 15,356.25 3,071.25
Sub - Bahan 71,793.75Rp 71,793.75
Upah : sama dgn rgk ky Kruing Rp 42,280.00
T O T A L Rp 114,073.75

3 PEK. RANGKA PLAFOND (60x60) / M2, Kayu kelas-II / III SNI-2008


Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Kayu kelas-II (Kamper Medan / Kruing) 0.016 M3 4,725,000.00 77,017.50
Paku (7 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 80,856.56 Rp 80,856.56
Upah : Pekerja 0.200 Org 75,000.00 15,000.00
Tukang Kayu 0.300 Org 90,000.00 27,000.00
Kep. Tukang Kayu 0.030 Org 105,000.00 3,150.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 46,250.00 Rp 46,250.00
T O T A L Rp 127,106.56
4 PEK. RANGKA PLAFOND (60x60) / M2, Kayu kelas-II / III SNI-2008
Kayu kelas-III (Kayu Borneo/Meranti super)
Bahan : Kasau 5/7, kayu kelas-III (Borneo/Meranti super) 0.0163 M3 4,462,500.00 72,738.75
Paku (7 - 10 cm) 0.250 Kg 15,356.25 3,839.06
Sub - Bahan 76,577.81Rp 76,577.81
Upah : sama dgn rgk ky Kruing Rp 46,250.00
T O T A L Rp 122,827.81

6.7. PEK. TALANG DATAR / JURAI, SENG BJLS 28 / M' SNI-2008


Kayu kelas-II (Kamper Medan/Kruing)
Bahan : Seng plat BJLS 28 lebar 90 cm 1.050 m' 31,500.00 33,075.00
Paku halus (1-3 cm) 0.015 Kg 19,950.00 299.25
Papan kayu kelas II (Kruing/Kamper Medan) 0.019 M3 6,825,000.00 129,675.00
Sub - Bahan 163,049.25 Rp 163,049.25
Upah : Pekerja 0.200 Org 75,000.00 15,000.00
Tukang Kayu 0.400 Org 90,000.00 36,000.00
Kep. Tukang Kayu 0.025 Org 105,000.00 2,625.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 54,725.00 Rp 54,725.00
T O T A L Rp 217,774.25

VII. PEK. PENAHAN PANAS & LEMBAB


7.1. PAS. GENTENG KERAMIK / M2 (Cisangkan)
Bahan : Genteng ex Cisangkan type Victoria 11.000 Bh 12,600.00 138,600.00
Sub - Bahan 138,600.00 Rp 138,600.00
Upah : Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
50% Tukang batu 0.200 Org 90,000.00 18,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 52,200.00 Rp 26,100.00
T O T A L Rp 164,700.00
7.2. PAS. GENTENG KERAMIK / M2 (KIA)
Bahan : Gntg. Keramik KIA Standart (Natural) 14.500 Bh 13,125.00 190,312.50
Sub - Bahan 190,312.50Rp 190,312.50
Upah : sama dengan genteng Cisangkan Rp 26,100.00
T O T A L Rp 216,412.50

7.3. PAS. GENTENG (Morando) / M2


Bahan : Genteng Morando glassur 14.500 Bh 3,675.00 53,287.50
Sub - Bahan 53,287.50Rp 53,287.50
Upah : sama dengan genteng Cisangkan Rp 26,100.00
T O T A L Rp 79,387.50
7.4. PAS. NOK GENTENG CISANGKAN / M'
Bahan : Gntg Nok Cisangkan type Victoria 2.860 Bh 26,250.00 75,075.00
Semen PC 0.050 zak 65,000.00 3,250.00
Pasir Pasang 0.006 M3 265,125.00 1,590.75
Sub - Bahan 79,915.75Rp 79,915.75
Upah : 2,5 kali upah pasangan genteng keramik Rp 65,250.00
T O T A L Rp 145,165.75

7.5. PAS. NOK GENTENG KERAMIK KIA / M'


Bahan : Genteng Nok ex KIA 5.000 Bh 26,565.00 132,825.00
Semen PC 0.050 zak 65,000.00 3,250.00
Pasir Pasang 0.006 M3 265,125.00 1,590.75
Sub - Bahan 137,665.75Rp 137,665.75
Upah : 2,5 kali upah pasangan genteng keramik Rp 65,250.00
T O T A L Rp 202,915.75

7.6. PAS. GENTENG BETON ex Karangpilang / M2


Bahan : Genteng Beton ex Karangpilang (berwarna) 10.000 Bh 12,600.00 126,000.00
Sub - Bahan 126,000.00Rp 126,000.00
Upah : sama dengan pasang genteng keramik Rp 26,100.00
T O T A L Rp 152,100.00

7.7. PAS. NOK GENTENG BETON Karangpilang / M'


Bahan : Genteng Nok Beton karangpilang (berwarna) 3.500 Bh 26,250.00 91,875.00
Semen PC 0.025 M3 65,000.00 1,625.00

RAB - 029
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Pasir Pasang 0.006 M3 265,125.00 1,590.75


Sub - Bahan 91,875.00Rp 91,875.00
Upah : 2,5 kali upah pasangan genteng beton Rp 65,250.00
T O T A L Rp 157,125.00

7.8. PAS. ATAP ASBES GELOMBANG kecil / M2


Bahan : Djabes gelombang kecil (B100) uk. 300x105, tbl. 5mm 0.500 Lmbr 126,000.00 63,000.00
Skrup + ring 4.000 Bh 472.50 1,890.00
Sub - Bahan 63,000.00 Rp 63,000.00
Upah : Tukang kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 26,050.00 Rp 26,050.00
T O T A L Rp 89,050.00
7.9. PAS. BUBUNGAN ASBES / M'
Bahan : Bubung Asbes 2.000 Lmbr 35,000.00 70,000.00
Skrup + ring 4.000 Bh 472.50 1,890.00
Sub - Bahan 70,000.00 Rp 70,000.00
Upah : Kep. Tukang kayu 0.003 Org 105,000.00 315.00
Tukang kayu 0.025 Org 90,000.00 2,250.00
Pekerja 0.025 Org 75,000.00 1,875.00
Mandor 0.001 Org 110,000.00 110.00
Sub - Upah 4,550.00 Rp 4,550.00
T O T A L Rp 74,550.00
7.10. PAS. ATAP SENG GELOMBANG / M2
Bahan : Seng Gelombang (0.9 x 1,8 x 0,004) 0.700 Lmbr 45,000.00 31,500.00
Skrup + ring 4.000 Bh 472.50 1,890.00
Sub - Bahan 31,500.00Rp 31,500.00
Upah : sama dengan pas. atap asbes Rp 26,050.00
T O T A L Rp 57,550.00

7.11. PAS. BUBUNG SENG / M'


Bahan : Seng Gelombang (0.9 x 1,8 x 0,004) 0.300 Lmbr 45,000.00 13,500.00
Skrup + ring 2.000 Bh 472.50 945.00
Sub - Bahan 13,500.00Rp 13,500.00
Upah : 2 x upah pas. atap seng Rp 52,100.00
T O T A L Rp 65,600.00

7.12. PAS. GENTENG SIRAP / M2


Bahan : Atap Sirap 1.500 M2 236,250.00 354,375.00
Paku sirap 0.500 Kg 31,500.00 15,750.00
Sub - Bahan 354,375.00 Rp 354,375.00
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang kayu 0.200 Org 90,000.00 18,000.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 35,150.00 Rp 35,150.00
T O T A L Rp 389,525.00
7.13. PAS. BUBUNG SENG SIRAP / M'
Bahan : Papan kayu 4/12 1.000 M' 49,896.00 49,896.00
Seng Gelombang (0.9 x 1,8 x 0,004) 0.400 Lmbr 45,000.00 18,000.00
Skrup + ring 4.000 Bh 472.50 1,890.00
Sub - Bahan 69,786.00Rp 69,786.00
Upah : 2 x upah pas. atap seng Rp 52,100.00
T O T A L Rp 121,886.00

7.14. PAS. WATERPROOFING MEMBRANE


1 Pas. Waterprrofing Sopralene 4 mm
Bahan : Lapisan Coating PF Primer 1.000 m2 18,375.00 18,375.00
Waterproofing Membrane, Sopralene 4 mm 1.100 m2 157,500.00 173,250.00
Sub - Bahan 191,625.00Rp 191,625.00
Upah : Sub - Upah Rp 7,500.00
T O T A L Rp 199,125.00
2 Pas. Waterprrofing Gardigum 4 mm
Bahan : Lapisan Coating PF Primer 1.000 m2 18,375.00 18,375.00
Waterproofing Membrane, Gardigum 4 mm 1.100 m2 141,750.00 155,925.00
Sub - Bahan 174,300.00Rp 174,300.00
Upah : Sub - Upah Rp 7,500.00
T O T A L Rp 181,800.00
3 Pas. Screeding pelindung 4 cm, 1Pc : 3Ps
Bahan : Semen PC 0.408 zak 65,000.00 26,520.00
Pasir pasang 0.039 M3 265,125.00 10,339.88
Kawat ayam 1.000 m2 10,000.00 10,000.00
Sub - Bahan 46,859.88 Rp 46,859.88
Upah : Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
40% Tukang batu halus 0.200 Org 95,000.00 19,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 53,200.00 Rp 21,280.00
T O T A L Rp 68,139.88
7.15. PAS. WATERPROOFING JENIS COATING
(ex SIKA, ketebalan min. 3 lapis)
Pas. Screeding, 1Pc : 3Ps (T=t. 3cm)
Bahan : Semen PC 0.340 zak 65,000.00 22,100.00
Pasir pasang 0.033 M3 265,125.00 8,616.56
Waterproofing ex Sika / setara 1.000 kg 52,500.00 52,500.00
Kuas 0.500 Bh 15,750.00 7,875.00

RAB - 030
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Bahan 91,091.56 Rp 91,091.56


Upah : Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
50% Tukang batu halus 0.200 Org 95,000.00 19,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 53,200.00 Rp 26,600.00
T O T A L Rp 117,691.56
7.16 PAS. ATAP METAL
1 PAS ATAP GEELOMBANG GALVALUME, type SPANDEK LYSAGHT, tebal 0,75 mm
Bahan : Atap GALVALUME, type Spandek Lysaght, tebal 0,75 mm 1.050 m2 177,975.00 186,873.75
Skrup + ring 4.000 Bh 500.00 2,000.00
Sub - Bahan 186,873.75 Rp 186,873.75
Upah : Tukang besi 0.200 Org 85,000.00 17,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 25,050.00 Rp 25,050.00
T O T A L Rp 211,923.75
2 PAS ATAP GEELOMBANG GALVALUME, type SPANDEK LYSAGHT, tebal 0,5 mm
Bahan : Atap GALVALUME, type Spandek Lysaght, tebal 0,5 mm 1.050 m2 91,875.00 96,468.75
Skrup + ring 4.000 Bh 500.00 2,000.00
Sub - Bahan 96,468.75Rp 96,468.75
Upah : sama dg upah pas. Spandek tbl. 0,75 mm Rp 25,050.00
T O T A L Rp 121,518.75

3 PAS. ATAP ZINCALUM SPANDEX (dgn. sterofoam 5 cm) / M2


Bahan : Atap Metal ZINCALUM SPANDEX + Sterofoam 1.100 m2 210,000.00 231,000.00
Skrup + ring 4.000 Bh 500.00 2,000.00
Sub - Bahan 231,000.00 Rp 231,000.00
Upah : Tukang besi 0.200 Org 85,000.00 17,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 25,050.00 Rp 25,050.00
T O T A L Rp 256,050.00
4 PAS. ATAP METAL SPANDEX ZINCALUM, tebal 0.5 mm / M2
Bahan : Atap Metal SPANDEX ZINCALUM, tebal 0,5 mm 1.100 m2 121,800.00 133,980.00
Skrup + ring 4.000 Bh 500.00 2,000.00
Sub - Bahan 133,980.00 Rp 133,980.00
Upah : Tukang besi 0.200 Org 85,000.00 17,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 25,050.00 Rp 25,050.00
T O T A L Rp 159,030.00

VIII. PEK. KOSEN, PINTU, JENDELA KAYU


8.1. PEK. KOSEN KAYU
1 PEK. KOSEN KAYU (Kelas-I) / M3 SNI - 2008
( Kayu JATI Jawa Timur, kelas-I)
Bahan : Balok Jati Jawa Timur, Kelas-I 1.100 M3 57,750,000.00 63,525,000.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00
Sub - Bahan 63,586,195.31 Rp 63,586,195.31
Upah : Kep. Tukang Kayu 2.100 Org 105,000.00 220,500.00
Tukang kayu halus 21.000 Org 95,000.00 1,995,000.00
Pekerja 7.000 Org 75,000.00 525,000.00
Mandor 0.350 Org 110,000.00 38,500.00
Sub - Upah 2,779,000.00 Rp 2,779,000.00
T O T A L Rp 66,365,195.31
2 PEK. KOSEN KAYU (Kelas-I) / M3 SNI - 2008
( Kayu KAMPER SAMARINDA Oven)
Bahan : Kayu kelas-I (Balok Kamper Samarinda oven) 1.100 M3 9,975,000.00 10,972,500.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00
Sub - Bahan 11,033,695.31 Rp 11,033,695.31
Upah : Kep. Tukang Kayu 2.100 Org 105,000.00 220,500.00
Tukang kayu halus 21.000 Org 95,000.00 1,995,000.00
Pekerja 7.000 Org 75,000.00 525,000.00
Mandor 0.350 Org 110,000.00 38,500.00
Sub - Upah 2,779,000.00 Rp 2,779,000.00
T O T A L Rp 13,812,695.31
3 KOSEN KAYU KELAS - II atau III / M3 SNI - 2008
( Kayu KAMPER SINGKIL Oven )
Bahan : Kayu kelas-II (Balok Kamper Singkil oven) 1.200 M3 7,875,000.00 9,450,000.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00
Sub - Bahan 9,511,195.31 Rp 9,511,195.31
Upah : Kep. Tukang Kayu 1.800 Org 105,000.00 189,000.00
Tukang kayu halus 18.000 Org 95,000.00 1,710,000.00
Pekerja 6.000 Org 75,000.00 450,000.00
Mandor 0.300 Org 110,000.00 33,000.00
Sub - Upah 2,382,000.00 Rp 2,382,000.00
T O T A L Rp 11,893,195.31
4 KOSEN KAYU KELAS - II atau III / M3 SNI - 2008
( Kayu KRUING / KAMPER MEDAN )
Bahan : Kayu kelas-II (Balok Kayu Kruing/Kamper Medan) 1.200 M3 6,300,000.00 7,560,000.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00

RAB - 031
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Bahan 7,621,195.31 Rp 7,621,195.31


Upah : sama dgn upah kayu kelas-II Sub - Upah Rp 2,382,000.00
T O T A L Rp 10,003,195.31

5 KOSEN KAYU KELAS - II atau III / M3 SNI - 2008


( Kayu BENGKIRAI )
Bahan : Kayu kelas-II (Balok Kayu Bengkirai) 1.200 M3 7,875,000.00 9,450,000.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00
Sub - Bahan 9,511,195.31
Rp 9,511,195.31
Upah : sama dgn upah kayu kelas-II Sub - Upah Rp 2,382,000.00
T O T A L Rp 11,893,195.31
6 KOSEN KAYU KELAS - II atau III / M3 SNI - 2008
( Kayu MERBAU oven )
Bahan : Kayu kelas-II, Merbau oven 1.200 M3 10,500,000.00 12,600,000.00
Paku 10 cm 1.250 Kg 15,356.25 19,195.31
Lem Kayu 1.000 Kg 42,000.00 42,000.00
Sub - Bahan 12,661,195.31 Rp 12,661,195.31
Upah : sama dgn upah kayu kelas-II Sub - Upah Rp 2,382,000.00
T O T A L Rp 15,043,195.31

8.2. PEKERJAAN PINTU PANEL KAYU


1 PAS. PINTU PANIL KAYU KELAS-I atau II, / M2 SNI - 2008
( Papan Kayu JATI Jawa Timur, kelas-I)
Bahan : Papan Jati Jawa Timur, Kelas-I 0.040 M3 60,375,000.00 2,415,000.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 2,415,767.81 Rp 2,415,767.81
Upah : Kep. Tukang Kayu 0.300 Org 105,000.00 31,500.00
Tukang kayu halus 3.000 Org 95,000.00 285,000.00
Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 397,000.00 Rp 397,000.00
T O T A L Rp 2,812,767.81
2 PAS. PINTU PANIL KAYU KELAS-I atau II, / M2 SNI - 2008
( Papan Kayu KAMPER SAMARINDA Oven )
Bahan : Kayu kelas-I (Papan Kamper Samarinda oven) 0.040 M3 10,395,000.00 415,800.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 416,567.81 Rp 416,567.81
Upah : Sub - Upah 833,135.63 Rp 397,000.00
T O T A L Rp 813,567.81
3 PAS. PINTU PANIL KAYU KELAS-I atau II, / M2 SNI - 2008
( Papan Kayu KAMPER SINGKIL Oven )
Bahan : Papan Kamper Singkil oven 0.040 M3 8,137,500.00 325,500.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 326,267.81 Rp 326,267.81
Upah : Sub - Upah 652,535.63 Rp 397,000.00
T O T A L Rp 723,267.81
4 PAS. PINTU PANIL KAYU KELAS-I atau II, / M2 SNI - 2008
( Papan Kayu MERBAU Oven )
Bahan : Papan kayu Merbau oven 0.040 M3 10,762,500.00 430,500.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 431,267.81 Rp 431,267.81
Upah : Sub - Upah 862,535.63 Rp 397,000.00
T O T A L Rp 828,267.81

8.3. PINTU KLAMP KAYU KELAS - II / M2 SNI - 2008


( Kayu KAMPER SINGGKIL )
Bahan : Kayu kelas-II (Papan Kamper Singkil oven) 0.040 M3 10,395,000.00 415,800.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 416,567.81 Rp 416,567.81
Upah : Kep. Tukang Kayu 0.105 Org 105,000.00 11,025.00
Tukang kayu halus 1.050 Org 95,000.00 99,750.00
Pekerja 0.350 Org 75,000.00 26,250.00
Mandor 0.018 Org 110,000.00 1,980.00
Sub - Upah 139,005.00 Rp 139,005.00
T O T A L Rp 555,572.81
8.4. PINTU KLAMP KAYU KELAS - III / M2 SNI - 2008
( Kayu BORNEO / MERANTI ), untuk Gudang Sementara
Bahan : kayu kelas-III (Papan Kayu Borneo/Meranti) 0.040 M3 3,360,000.00 134,400.00
Paku 5 - 7 cm 0.050 Kg 15,356.25 767.81
Sub - Bahan 135,167.81 Rp 135,167.81
Upah : Kep. Tukang Kayu 0.105 Org 105,000.00 11,025.00
Tukang kayu halus 1.050 Org 95,000.00 99,750.00
Pekerja 0.350 Org 75,000.00 26,250.00
Mandor 0.018 Org 110,000.00 1,980.00
Sub - Upah 139,005.00 Rp 139,005.00
T O T A L Rp 274,172.81
8.5. PEKERJAAN PINTU KACA
1 PAS. PINTU & JENDELA KACA, KAYU KELAS-I / II, / M2 SNI - 2008
( Kayu KAMPER SAMARINDA Oven )
Bahan : Kayu kelas-I (Papan Kamper Samarinda oven) 0.024 M3 10,395,000.00 249,480.00
List kaca
Lem Kayu 0.300 Kg 42,000.00 12,600.00
Sub - Bahan 262,080.00 Rp 262,080.00
Upah : Kep. Tukang Kayu 0.240 Org 105,000.00 25,200.00
Tukang Kayu halus 2.400 Org 95,000.00 228,000.00
Pekerja 0.800 Org 75,000.00 60,000.00
Mandor 0.040 Org 110,000.00 4,400.00

RAB - 032
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Upah 317,600.00 Rp 317,600.00


T O T A L Rp 579,680.00
2 PAS. PINTU & JENDELA KACA, KAYU KELAS-I / II, / M2 SNI - 2008
( Kayu KAMPER SINGKIL Oven )
Bahan : Kayu kelas-II (Papan Kamper Singkil oven) 0.024 M3 8,137,500.00 195,300.00
Lem Kayu 0.300 Kg 42,000.00 12,600.00
Sub - Bahan 207,900.00 Rp 207,900.00
Upah : Sub - Upah 415,800.00 Rp 317,600.00
T O T A L Rp 525,500.00

8.6. PAS. PINTU & JENDELA JALUSI KAYU (KREPYAK) / M2 SNI - 2008
Kayu kelas-I / II (KAMPER SAMARINDA Oven )
Bahan : Papan Kamper Samarinda (oven) 0.064 M3 10,395,000.00 665,280.00
Lem Kayu 0.500 Kg 42,000.00 21,000.00
Sub - Bahan 686,280.00 Rp 686,280.00
Upah : Kep. Tukang Kayu 0.300 Org 105,000.00 31,500.00
Tukang Kayu halus 3.000 Org 95,000.00 285,000.00
Pekerja 1.000 Org 75,000.00 75,000.00
Mandor 0.050 Org 110,000.00 5,500.00
Sub - Upah 397,000.00 Rp 397,000.00
T O T A L Rp 1,083,280.00
8.7. PINTU DOBEL TEAKWOOD, RANGKA KAYU KELAS-II / M2 SNI - 2008 Analisa no. 6.8, hal 5.
( Kayu KAMPER SAMARINDA Oven )
Bahan : Papan Kamper Samarinda (oven) 0.025 M3 10,395,000.00 259,875.00
Teakwood 122x244x 3mm 0.700 Lmbr 105,000.00 73,500.00
Paku halus (1 - 2,5 CM) 0.030 Kg 19,950.00 598.50
Lem Kayu 0.500 Kg 42,000.00 21,000.00
Sub - Bahan 354,973.50 Rp 354,973.50
Upah : Kep. Tukang Kayu 0.210 Org 105,000.00 22,050.00
Tukang kayu halus 2.100 Org 95,000.00 199,500.00
Pekerja 0.700 Org 75,000.00 52,500.00
Mandor 0.035 Org 110,000.00 3,850.00
Sub - Upah 277,900.00 Rp 277,900.00
T O T A L Rp 632,873.50
8.8. PINTU DOBEL TEAKWOOD, RANGKA KAYU KELAS-I / M2 SNI - 2008 Analisa no. 6.11, hal 5.
( Kayu JATI )
Bahan : Papan Kayu Jati ex Jawa Timur 0.025 M3 60,375,000.00 1,509,375.00
Teakwood 122x244x 3mm 0.700 Lmbr 105,000.00 73,500.00
Paku halus (1 - 2,5 CM) 0.030 Kg 19,950.00 598.50
Lem Kayu 0.300 Kg 42,000.00 12,600.00
Sub - Bahan 1,596,073.50 Rp 1,596,073.50
Upah : Kep. Tukang Kayu 0.240 Org 105,000.00 25,200.00
Tukang kayu halus 2.400 Org 95,000.00 228,000.00
Pekerja 0.800 Org 75,000.00 60,000.00
Mandor 0.040 Org 110,000.00 4,400.00
Sub - Upah 317,600.00 Rp 317,600.00
T O T A L Rp 1,913,673.50

8.9. PINTU TEAKWOOD RANGKAP, RANGKA EXPOSE / M2 SNI - 2008 Analisa no. 6.9, hal 5.
KAYU KELAS-I atau II (Kamper Samarinda oven)
Bahan : Papan Kamper Samarinda (oven) 0.0256 M3 10,395,000.00 266,112.00
Teakwood 122x244x 3mm 0.700 Lmbr 105,000.00 73,500.00
Paku halus (1 - 2,5 CM) 0.030 Kg 19,950.00 598.50
Lem Kayu 0.500 Kg 42,000.00 21,000.00
Sub - Bahan 361,210.50 Rp 361,210.50
Upah : Kep. Tukang Kayu 0.240 Org 105,000.00 25,200.00
Tukang kayu halus 2.400 Org 95,000.00 228,000.00
Pekerja 0.800 Org 75,000.00 60,000.00
Mandor 0.040 Org 110,000.00 4,400.00
Sub - Upah 317,600.00 Rp 317,600.00
T O T A L Rp 678,810.50

8.10. PEK. JALUSI KOSEN, KAYU KELAS - I atau II / M2 SNI - 2008 Analisa no. 6.10, hal 5.
( Kayu KAMPER SAMARINDA Oven )
Bahan : Papan Kamper Samarinda (oven) 0.060 M3 10,395,000.00 623,700.00
Paku halus (1 - 2,5 CM) 0.150 Kg 19,950.00 2,992.50
Sub - Bahan 626,692.50 Rp 626,692.50
Upah : Kep. Tukang Kayu 0.200 Org 105,000.00 21,000.00
Tukang kayu halus 2.000 Org 95,000.00 190,000.00
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.025 Org 110,000.00 2,750.00
Sub - Upah 251,250.00 Rp 251,250.00
T O T A L Rp 877,942.50
8.11. PINTU DOBEL TRIIPLEX 6 mm lapis HPL, rgk. Kamper / M2
Bahan : Papan Kamper samarinda oven 0.017 M3 10,395,000.00 176,715.00
Multiplex 122x244x6 mm 0.700 Lmbr 80,850.00 56,595.00
HPL 0.700 Lmbr 183,750.00 128,625.00
Paku halus 0.100 Kg 19,950.00 1,995.00
Lem Kayu 0.250 Kg 42,000.00 10,500.00
Sub - Bahan 374,430.00Rp 374,430.00
Upah, sama dengan rangka Kamper Smrd Rp 277,900.00
T O T A L Rp 652,330.00
8.12. DINDING / PINTU DOBEL TRIIPLEX 4 mm lapis HPL, rgk. Kamper / M2
Bahan : Papan Kamper samarinda oven 0.017 M3 10,395,000.00 176,715.00
Multiplex 122x244x4 mm 0.700 Lmbr 57,750.00 40,425.00
HPL 0.700 Lmbr 183,750.00 128,625.00
Paku halus 0.100 Kg 19,950.00 1,995.00
Lem Kayu 0.250 Kg 42,000.00 10,500.00

RAB - 033
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Bahan 358,260.00Rp 358,260.00


Upah, sama dengan rangka Kamper Smrd Rp 277,900.00
T O T A L Rp 636,160.00

IX. PEKERJAAN FINISHING


9.1. PEK. FINISHING DINDING
9.1.1 PEK. BRAFEN BATU KALI 1Pc : 3Ps / M2
Bahan : Semen PC 11.000 kg 1,300.00 14,300.00
Pasir pasang 0.030 M3 265,125.00 7,953.75
Sub - Bahan 22,253.75 Rp 22,253.75
Upah : Kep. Tukang Batu 0.007 Org 100,000.00 700.00
Tukang batu halus 0.070 Org 95,000.00 6,650.00
Pekerja 0.150 Org 75,000.00 11,250.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 19,480.00 Rp 19,480.00
T O T A L Rp 41,733.75
9.1.2 PEK. PLESTERAN DINDING 15 cm
1 PLESTERAN DINDING 15 mm, Camp. 1Pc : 1Ps / M2 SNI-2008
Bahan : Semen PC 15.504 kg 1,300.00 20,155.20
Pasir pasang 0.016 M3 265,125.00 4,242.00
Sub - Bahan 24,397.20 Rp 24,397.20
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu halus 0.150 Org 95,000.00 14,250.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,900.00 Rp 39,900.00
T O T A L Rp 64,297.20
2 PLESTERAN DINDING 15 mm, Camp. 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 10.224 kg 1,300.00 13,291.20
Pasir pasang 0.020 M3 265,125.00 5,302.50
Sub - Bahan 18,593.70 Rp 18,593.70
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 58,493.70

3 PLESTERAN DINDING 15 mm, Camp. 1Pc : 3Ps / M2 SNI-2008


Bahan : Semen PC 7.776 kg 1,300.00 10,108.80
Pasir pasang 0.023 M3 265,125.00 6,097.88
Sub - Bahan 16,206.68 Rp 16,206.68
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 56,106.68

4 PLESTERAN DINDING 15 mm, Camp. 1Pc : 4Ps / M2 SNI-2008


Bahan : Semen PC 6.240 kg 1,300.00 8,112.00
Pasir pasang 0.024 M3 265,125.00 6,363.00
Sub - Bahan 14,475.00 Rp 14,475.00
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 54,375.00

5 PLESTERAN DINDING 15 mm, Camp. 1Pc : 5Ps / M2 SNI-2008


Bahan : Semen PC 5.184 kg 1,300.00 6,739.20
Pasir pasang 0.026 M3 265,125.00 6,893.25
Sub - Bahan 13,632.45 Rp 13,632.45
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 53,532.45

6 PLESTERAN DINDING 15 mm, Camp. 1Pc : 6Ps / M2 SNI-2008


Bahan : Semen PC 4.416 kg 1,300.00 5,740.80
Pasir pasang 0.027 M3 265,125.00 7,158.38
Sub - Bahan 12,899.18 Rp 12,899.18
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 52,799.18
7 PLESTERAN DINDING 15 mm, Camp. 1Pc : 7Ps / M2 SNI-2008
Bahan : Semen PC 3.936 kg 1,300.00 5,116.80
Pasir pasang 0.028 M3 265,125.00 7,423.50
Sub - Bahan 12,540.30 Rp 12,540.30
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 52,440.30
8 PLESTERAN DINDING 15 mm, Camp. 1Pc : 8Ps / M2 SNI-2008
Bahan : Semen PC 3.456 kg 1,300.00 4,492.80
Pasir pasang 0.029 M3 265,125.00 7,688.63
Sub - Bahan 12,181.43 Rp 12,181.43
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 39,900.00
T O T A L Rp 52,081.43

9 PLESTERAN DINDING CAMPURAN MORTAR, tebal 10 mm


Bahan : Perekat mortar & beton (MU L-500) 0.110 kg 105,262.50 11,578.88
Plester premium (MU 100) 20.000 kg 1,575.00 31,500.00
Acian plesteran (MU 250) 2.000 kg 2,546.25 5,092.50
Sub - Bahan 48,171.38 Rp 48,171.38
Upah : Pekerja 0.200 Org 75,000.00 15,000.00
Tukang batu 0.100 Org 90,000.00 9,000.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 26,100.00 Rp 26,100.00
T O T A L Rp 74,271.38

9.1.3 PEK. PLESTERAN DINDING 20 cm

RAB - 034
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

1 PLESTERAN DINDING 20 mm, Camp. 1Pc : 2Ps / M2 SNI-2008


Bahan : Semen PC 13.632 kg 1,300.00 17,721.60
Pasir pasang 0.027 M3 265,125.00 7,158.38
Sub - Bahan 24,879.98 Rp 24,879.98
Upah : Pekerja 0.400 Org 75,000.00 30,000.00
Tukang batu halus 0.200 Org 95,000.00 19,000.00
Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
Mandor 0.022 Org 110,000.00 2,420.00
Sub - Upah 53,420.00 Rp 53,420.00
T O T A L Rp 78,299.98
2 PLESTERAN DINDING 20 mm, Camp. 1Pc : 3Ps / M2 SNI-2008
Bahan : Semen PC 10.368 kg 1,300.00 13,478.40
Pasir pasang 0.031 M3 265,125.00 8,218.88
Sub - Bahan 21,697.28 Rp 21,697.28
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 53,420.00
T O T A L Rp 75,117.28

3 PLESTERAN DINDING 20 mm, Camp. 1Pc : 4Ps / M2 SNI-2008


Bahan : Semen PC 8.320 kg 1,300.00 10,816.00
Pasir pasang 0.032 M3 265,125.00 8,484.00
Sub - Bahan 19,300.00 Rp 19,300.00
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 53,420.00
T O T A L Rp 72,720.00

4 PLESTERAN DINDING 20 mm, Camp. 1Pc : 5Ps / M2 SNI-2008


Bahan : Semen PC 6.912 kg 1,300.00 8,985.60
Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 18,264.98 Rp 18,264.98
Upah : sama dengan upah plesteran 1Pc : 1Ps Sub - Upah Rp 53,420.00
T O T A L Rp 71,684.98

9.1.4 PEK. PLESTERAN LAIN-LAIN


1 PLESTERAN BATU GRANIT tebal 10 mm, Camp. 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Batu granit 15.000 kg 5,000.00 75,000.00
Sub - Bahan 88,000.00 Rp 88,000.00
Upah : Pekerja 0.440 Org 75,000.00 33,000.00
Tukang batu halus 0.225 Org 95,000.00 21,375.00
Kep. Tukang Batu 0.023 Org 100,000.00 2,300.00
Mandor 0.023 Org 110,000.00 2,530.00
Sub - Upah 59,205.00 Rp 59,205.00
T O T A L Rp 147,205.00
2 PLESTERAN BATU TERASO tebal 10 mm, Camp. 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Batu Teraso 15.000 kg 4,000.00 60,000.00
Sub - Bahan 73,000.00 Rp 73,000.00
Upah : Pekerja 0.440 Org 75,000.00 33,000.00
Tukang batu halus 0.225 Org 95,000.00 21,375.00
Kep. Tukang Batu 0.023 Org 100,000.00 2,300.00
Mandor 0.023 Org 110,000.00 2,530.00
Sub - Upah 59,205.00 Rp 59,205.00
T O T A L Rp 132,205.00
3 PLESTERAN CIPRAT / KAMPROTAN, Camp. 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 4.320 kg 1,300.00 5,616.00
Pasir Pasang 0.006 m3 265,125.00 1,590.75
Sub - Bahan 7,206.75 Rp 7,206.75
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu halus 0.100 Org 95,000.00 9,500.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 34,650.00 Rp 34,650.00
T O T A L Rp 41,856.75
4 FINISHING SIAR PAS. DINDING BATA MERAH / M2 (20M') SNI-2008
Bahan : Semen PC 3.108 kg 1,300.00 4,040.40
Sub - Bahan 4,040.40 Rp 4,040.40
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang batu halus 0.075 Org 95,000.00 7,125.00
Kep. Tukang Batu 0.008 Org 100,000.00 800.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 20,055.00 Rp 20,055.00
T O T A L Rp 24,095.40
5 FINISHING SIAR DINDING CONBLOCK EXPOSE / M2 (8M') SNI-2008
Bahan : Semen PC 1.600 kg 1,300.00 2,080.00
Sub - Bahan 2,080.00 Rp 2,080.00
Upah : Pekerja 0.070 Org 75,000.00 5,250.00
Tukang batu halus 0.035 Org 95,000.00 3,325.00
Kep. Tukang Batu 0.004 Org 100,000.00 400.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 9,415.00 Rp 9,415.00
T O T A L Rp 11,495.00
6 FINISHING SIAR PAS. BATU KALI, adukan 1Pc : 2Ps / M2 SNI-2008
Bahan : Semen PC 6.340 kg 1,300.00 8,242.00
Pasir Pasang 0.012 m3 265,125.00 3,181.50
Sub - Bahan 11,423.50 Rp 11,423.50
Upah : Pekerja 0.300 Org 75,000.00 22,500.00
Tukang batu halus 0.150 Org 95,000.00 14,250.00
Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Mandor 0.015 Org 110,000.00 1,650.00

RAB - 035
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Upah 39,900.00 Rp 39,900.00


T O T A L Rp 51,323.50
7 FINISHING ACIAN / M2 SNI-2008
Bahan : Semen PC 3.250 kg 1,300.00 4,225.00
Sub - Bahan 4,225.00 Rp 4,225.00
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang batu halus 0.100 Org 95,000.00 9,500.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 22,630.00 Rp 22,630.00
T O T A L Rp 26,855.00
8 ACIAN Beton Expose, dengan Mortar / M2 SNI-2008
Bahan : Acian plesteran / beton expose (MU 200) 3.000 kg 4,160.63 12,481.88
Sub - Bahan 12,481.88 Rp 12,481.88
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang batu halus 0.100 Org 95,000.00 9,500.00
Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 22,630.00 Rp 22,630.00
T O T A L Rp 35,111.88

9.1.5 PEK. DINDING KERAMIK


1 PAS. DINDING PORSELIN 11x11 Cm / M2 SNI-2008
Bahan : Semen PC 9.300 Kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Porselin 11 x 11 cm 1.041 M2 57,750.00 60,117.75
Semen Warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 92,730.00 Rp 92,730.00
Upah : Kep. Tukang Batu 0.030 Org 100,000.00 3,000.00
Tukang batu halus 0.300 Org 95,000.00 28,500.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 54,330.00 Rp 54,330.00
T O T A L Rp 147,060.00
2 PAS. DINDING KERAMIK ARTISTIK 5x20 Cm / M2 SNI-2008
Bahan : Semen PC 9.300 Kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik Artistik 5x20 cm 1.060 M2 68,250.00 72,345.00
Semen Warna 2.900 Kg 10,500.00 30,450.00
Sub - Bahan 119,657.25 Rp 119,657.25
Upah : Kep. Tukang Batu 0.030 Org 100,000.00 3,000.00
Tukang batu halus 0.300 Org 95,000.00 28,500.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 54,330.00 Rp 54,330.00
T O T A L Rp 173,987.25
3 PAS. DINDING KERAMIK 10x20 Cm / M2 SNI-2008
Bahan : Semen PC 9.300 Kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik 10x20 cm 1.060 M2 68,250.00 72,345.00
Semen Warna 2.750 Kg 10,500.00 28,875.00
Sub - Bahan 118,082.25 Rp 118,082.25
Upah : Kep. Tukang Batu 0.030 Org 100,000.00 3,000.00
Tukang batu halus 0.300 Org 95,000.00 28,500.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 54,330.00 Rp 54,330.00
T O T A L Rp 172,412.25
4 PAS. DINDING KERAMIK 20x25 Cm, ex Roman / M2 SNI-2008
Bahan : Semen PC 9.300 kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik dinding 20x25 cm, ex Roman 1.060 M2 79,800.00 84,588.00
Semen Warna 1.940 Kg 10,500.00 20,370.00
Sub - Bahan 121,820.25 Rp 121,820.25
Upah : Kep. Tukang Batu 0.030 Org 100,000.00 3,000.00
Tukang batu halus 0.300 Org 95,000.00 28,500.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 54,330.00 Rp 40,747.50
T O T A L Rp 162,567.75
5 PAS. DINDING KERAMIK 20x20 Cm, / M2 SNI-2008
Bahan : Semen PC 9.300 kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik dinding 20x20 cm, ex Roman 1.060 M2 86,100.00 91,266.00
Semen Warna 1.940 Kg 10,500.00 20,370.00
Sub - Bahan 128,498.25 Rp 128,498.25
Upah : Upah sama pasang keramik 20x25 Rp 40,747.50
T O T A L Rp 169,245.75

6 PAS. DINDING KERAMIK 30x60 Cm, / M2 SNI-2008


Bahan : Semen PC 9.300 kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik dinding 30x60 cm, ex Roman 1.060 M2 134,925.00 143,020.50
Semen Warna 1.940 Kg 10,500.00 20,370.00
Sub - Bahan 180,252.75 Rp 180,252.75
Upah : Upah sama pasang keramik 20x25 Rp 40,747.50

RAB - 036
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

T O T A L Rp 221,000.25
7 PAS. DINDING KERAMIK 20x40 Cm, / M2 SNI-2008
Bahan : Semen PC 9.300 kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik dinding 20x40 cm, ex Roman 1.060 M2 84,000.00 89,040.00
Semen Warna 1.940 Kg 10,500.00 20,370.00
Sub - Bahan 126,272.25 Rp 126,272.25
Upah : Upah sama pasang keramik 20x25 Rp 40,747.50
T O T A L Rp 167,019.75
8 PAS. DINDING KERAMIK 30x30 Cm, / M2 SNI-2008
Bahan : Semen PC 9.300 kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Keramik dinding 30x30 cm, ex Roman 1.060 M2 73,500.00 77,910.00
Semen Warna 1.940 Kg 10,500.00 20,370.00
Sub - Bahan 115,142.25 Rp 115,142.25
Upah : Upah sama pasang keramik 20x25 Rp 40,747.50
T O T A L Rp 155,889.75

9.1.6 PEK. DINDING HOMOGENOUS TILE


1 PAS. DINDING MARMER TULUNG AGUNG 60x60 Cm SNI-2008
Bahan : Semen PC 12.440 Kg 1,300.00 16,172.00
Pasir pasang 0.025 M3 265,125.00 6,628.13
Marmer Tulung Agung, 60/60 cm 1.060 M2 420,000.00 445,200.00
Paku 12 cm 3.003 bh 300.00 900.90
Epoxy Resin/semen warna 0.650 Kg 12,600.00 8,190.00
Sub - Bahan 477,091.03 Rp 477,091.03
Upah : Kep. Tukang Batu 0.045 Org 100,000.00 4,500.00
Tukang batu halus 0.450 Org 95,000.00 42,750.00
Pekerja 0.450 Org 75,000.00 33,750.00
Mandor 0.009 Org 110,000.00 990.00
Sub - Upah 81,990.00 Rp 81,990.00
T O T A L Rp 559,081.03
2 PAS. DINDING GRANIT IMPORT Ex India (slab-Polish) SNI-2008
Bahan : Semen PC 12.440 Kg 1,300.00 16,172.00
Pasir pasang 0.025 M3 265,125.00 6,628.13
Granit Import (Nero Absolute India) jenis slab 1.060 M2 1,023,750.00 1,085,175.00
Paku 12 cm 3.003 bh 300.00 900.90
Epoxy Resin/semen warna 0.650 Kg 12,600.00 8,190.00
Sub - Bahan 1,117,066.03 Rp 1,117,066.03
Upah : Kep. Tukang Batu 0.045 Org 100,000.00 4,500.00
Tukang batu halus 0.450 Org 95,000.00 42,750.00
Pekerja 0.450 Org 75,000.00 33,750.00
Mandor 0.009 Org 110,000.00 990.00
Sub - Upah 81,990.00 Rp 81,990.00
T O T A L Rp 1,199,056.03
3 PAS. DINDING GRANIT IMPORT ex China (Slab-Polish) SNI-2008
Bahan : Semen PC 12.440 Kg 1,300.00 16,172.00
Pasir pasang 0.025 M3 265,125.00 6,628.13
Granit Import (Red China & Black China) jenis Slab 1.060 M2 577,500.00 612,150.00
Paku 12 cm 3.003 bh 300.00 900.90
Epoxy Resin/semen warna 0.650 Kg 12,600.00 8,190.00
Sub - Bahan 644,041.03 Rp 644,041.03
Upah : Upah sama pas Granit 60x60 Rp 81,990.00
T O T A L Rp 726,031.03

4 DINDING HOMOGENOUS TILE, ex Granito 30x60 (polish) SNI-2008


Bahan : Semen PC 9.300 Kg 1,300.00 12,090.00
Pasir pasang 0.018 M3 265,125.00 4,772.25
Granitto Aurora 30x60 Cm (polished), Group Silver 1.060 M2 310,695.00 329,336.70
Epoxy Resin/semen warna 1.940 Kg 12,600.00 24,444.00
Sub - Bahan 370,642.95 Rp 370,642.95
Upah : Kep. Tukang Batu 0.045 Org 100,000.00 4,500.00
Tukang batu halus 0.450 Org 95,000.00 42,750.00
Pekerja 0.450 Org 75,000.00 33,750.00
Mandor 0.009 Org 110,000.00 990.00
Sub - Upah 81,990.00 Rp 81,990.00
T O T A L Rp 452,632.95

9.1.7 DINDING BATU ALAM


1 PAS. BATU CANDI 20/40 cm / M2 SNI-2008
Bahan : Semen PC 11.750 Kg 1,300.00 15,275.00
Batu Candi 20x40 cm 1.100 M2 133,000.35 146,300.39
Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 170,854.76 Rp 170,854.76
Upah : Kep. Tukang Batu 0.035 Org 100,000.00 3,500.00
Tukang batu halus 0.350 Org 95,000.00 33,250.00
Pekerja 0.350 Org 75,000.00 26,250.00
Mandor 0.035 Org 110,000.00 3,850.00
Sub - Upah 66,850.00 Rp 66,850.00
T O T A L Rp 237,704.76
2 PAS. BATU ALAM PALIMANAN 20x40 CM / M2 SNI-2008
Bahan : Semen PC 11.750 Kg 1,300.00 15,275.00

RAB - 037
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Batu alam Paliaman 20X40 1.100 M2 147,000.00 161,700.00


Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 186,254.38 Rp 186,254.38
Upah : Setandart upah pas. Batu alam Rp 66,850.00
T O T A L Rp 253,104.38

3 PAS. BATU ALAM SUSUN 3x30 cm / M2


Bahan : Semen PC 11.750 Kg 1,300.00 15,275.00
Batu alam susun hitam 3x30 cm 1.100 M2 157,500.00 173,250.00
Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 197,804.38 Rp 197,804.38
Upah : Setandart upah pas. Batu alam Rp 66,850.00
T O T A L Rp 264,654.38
4 PAS. BATU ALAM ANDESIT 20/40, 30/40 CM / M2
Bahan : Semen PC 11.750 Kg 1,300.00 15,275.00
Batu alam Andesit 20/40 s/d 30/40 cm 1.100 M2 189,000.00 207,900.00
Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 232,454.38 Rp 232,454.38
Upah : Setandart upah pas. Batu alam Rp 66,850.00
T O T A L Rp 299,304.38
5 PAS. BATU PARAS JOGJA 20/30, 40/40 cm / M2
Bahan : Semen PC 11.750 Kg 1,300.00 15,275.00
Paras Jogja 20/30s/d40/40 (cream/putih) 1.100 M2 99,750.00 109,725.00
Pasir pasang 0.035 M3 265,125.00 9,279.38
Sub - Bahan 134,279.38 Rp 134,279.38
Upah : Setandart upah pas. Batu alam Rp 66,850.00
T O T A L Rp 201,129.38

9.1.8 PEK. DINDING PARTISI


1 PAS. PARTISI DOUBLE GYPSUM 12 MM, / M2
(Rangka hollow)
Bahan : Hollow 40x40 mm, tbl 0.35 mm 1.250 btg 21,000.00 26,250.00
Hollow 20x40 mm, tbl 0.35 mm 0.250 btg 21,000.00 5,250.00
Paku rivet 8.000 bh 300.00 2,400.00
Sekrup 6x1-1,5 8.000 bh 450.00 3,600.00
Gypsumboard 120x240 cm 12 mm 0.700 lbr 78,750.00 55,125.00
Textile tape 0.240 roll 18,375.00 4,410.00
Compound gypsum 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 24.000 bh 400.00 9,600.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 115,323.75 Rp 115,323.75
Upah : Tukang Allumunium 0.200 Org 100,000.00 20,000.00
Tukang gypsum 0.300 Org 90,000.00 27,000.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 63,650.00 Rp 63,650.00
T O T A L Rp 178,973.75
2 PAS. PARTISI DOUBLE GYPSUM 12 MM, / M2
( Rangka Metal Furing )
Bahan : Metal Furing 75 mm 1.250 btg 37,800.00 47,250.00
Paku rivet 8.000 bh 300.00 2,400.00
Sekrup 6x1-1,5 8.000 bh 450.00 3,600.00
Gypsumboard 120x240 cm 12 mm 0.700 lbr 78,750.00 55,125.00
Textile tape 0.240 roll 18,375.00 4,410.00
Compound gypsum 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 24.000 bh 400.00 9,600.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 131,073.75 Rp 131,073.75
Upah : Tukang Allumunium 0.200 Org 100,000.00 20,000.00
Tukang gypsum 0.300 Org 90,000.00 27,000.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 63,650.00 Rp 63,650.00
T O T A L Rp 194,723.75
3 PAS. PARTISI SINGLE GYPSUM 12 MM, / M2
(Rangka hollow)
Pelapis Gypsum 12 mm (1 sisi)
Bahan : Hollow 40x40 mm, tbl 0.35 mm 1.250 btg 21,000.00 26,250.00
Hollow 20x40 mm, tbl 0.35 mm 0.250 btg 21,000.00 5,250.00
Paku rivet 8.000 bh 300.00 2,400.00
Sekrup 6x1-1,5 8.000 bh 450.00 3,600.00
Gypsumboard 120x240 cm 12 mm 0.350 lbr 78,750.00 27,562.50
Textile tape 0.240 roll 18,375.00 4,410.00
Compound gypsum 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 24.000 bh 400.00 9,600.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 87,761.25 Rp 87,761.25
Upah : Tukang Allumunium 0.200 Org 100,000.00 20,000.00
Tukang gypsum 0.150 Org 90,000.00 13,500.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 50,150.00 Rp 50,150.00
T O T A L Rp 137,911.25
4 PAS. PARTISI SINGLE GYPSUM 12 MM, / M2
( Rangka Metal Furing )

RAB - 038
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Bahan : Metal Furing 75 mm 1.250 btg 37,800.00 47,250.00


Paku rivet 8.000 bh 300.00 2,400.00
Sekrup 6x1-1,5 8.000 bh 450.00 3,600.00
Gypsumboard 120x240 cm 12 mm 0.350 lbr 78,750.00 27,562.50
Textile tape 0.240 roll 18,375.00 4,410.00
Compound gypsum 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 24.000 bh 400.00 9,600.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 103,511.25 Rp 103,511.25
Upah : Tukang Allumunium 0.200 Org 100,000.00 20,000.00
Tukang gypsum 0.150 Org 90,000.00 13,500.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 50,150.00 Rp 50,150.00
T O T A L Rp 153,661.25
5 PAS. PARTISI "SINGLE" GRC BOARD 10 mm / M2
(Rangka besi hollow)
Bahan : Besi Hollow 40x40 mm, tbl 1 mm 3.000 m 36,575.00 109,725.00
Besi Hollow 20x40 mm, tbl 1 mm 1.000 m 18,375.00 18,375.00
Paku rivet 8.000 bh 300.00 2,400.00
Sekrup 6x1-1,5 8.000 bh 450.00 3,600.00
GRC-Board 120x240 cm 10 mm 0.350 lbr 136,500.00 47,775.00
Textile tape 0.240 roll 18,375.00 4,410.00
Compound GRC 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 24.000 bh 400.00 9,600.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 204,573.75 Rp 204,573.75
Upah : Tukang Allumunium 0.200 Org 100,000.00 20,000.00
Tukang gypsum 0.300 Org 90,000.00 27,000.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 63,650.00 Rp 63,650.00
T O T A L Rp 268,223.75
6 PAS. PARTISI DOBLE GRC BOARD 6mm / M2
(Rangka kayu Kamper Medan)
Bahan : Kayu Kamper Medan, kasau 0.025 m³ 5,512,500.00 137,812.50
Paku biasa 2"-5" 0.300 kg 15,356.25 4,606.88
GRC-board 120x240 cm 6 mm 0.750 lbr 84,000.00 63,000.00
Textile tape 0.240 roll 18,375.00 4,410.00
Compound GRC 0.120 zak 60,375.00 7,245.00
Sekrup gypsum 32.000 bh 400.00 12,800.00
Amplas 0.500 lbr 2,887.50 1,443.75
Sub - Bahan 231,318.13 Rp 231,318.13
Upah : Tukang kayu 0.600 Org 100,000.00 60,000.00
Pekerja 0.200 Org 75,000.00 15,000.00
Mandor 0.010 Org 110,000.00 1,100.00
Sub - Upah 76,100.00 Rp 76,100.00
T O T A L Rp 307,418.13

9.2. PEK. FINISHING LANTAI


9.2.1 PAS. LANTAI KERAMIK
1 PEK. LANTAI FLOOR HARDENER 5kg/ M2 SNI-2008
Screeding 1Pc : 3Ps dasaran (3cm) + floor hardener
Bahan : Semen PC 15.552 kg 1,300.00 20,217.60
Pasir pasang 0.046 M3 265,125.00 12,195.75
Sub - Bahan 32,413.35 Rp 32,413.35
Upah : Kep. Tukang Batu 0.020 Org 100,000.00 2,000.00
Tukang Batu halus 0.200 Org 95,000.00 19,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.020 Org 110,000.00 2,200.00
Sub - Upah 53,200.00 Rp 53,200.00
Floor Hardener
Bahan : Floor Hardener (Tesa/Gan's Floor), 5 kg/m2 5.000 Kg 9,450.00 47,250.00
Sub - Bahan 47,250.00 Rp 47,250.00
Upah : Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Tukang Batu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,550.00 Rp 18,550.00
T O T A L Rp 151,413.35
1.a. PEK. FLOOR HARDENER BETON 5kg/ M2 (langsung ke beton)
Floor Hardener
Bahan : Floor Hardener (Tesa/Gan's Floor), 5 kg/m2 5.000 Kg 9,450.00 47,250.00
Sub - Bahan 47,250.00 Rp 47,250.00
Upah : Kep. Tukang Batu 0.010 Org 100,000.00 1,000.00
Tukang Batu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,550.00 Rp 18,550.00
T O T A L Rp 65,800.00

2 PAS. LANTAI GRANIT 60X60 Cm (ex China) / M2


Bahan : Semen PC SNI-2008 9.600 kg 1,300.00 12,480.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Granit China 60x60 cm 1.116 M2 577,500.00 644,490.00
Semen warna 1.500 Kg 10,500.00 15,750.00

RAB - 039
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Sub - Bahan 684,650.63 Rp 684,650.63


Upah : Kep. Tukang Batu 0.025 Org 100,000.00 2,500.00
Tukang Batu halus 0.250 Org 95,000.00 23,750.00
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 64,300.00 Rp 64,300.00
T O T A L Rp 748,950.63

3 LANTAI HOMOGENOUS TILE 60x60 (polish), ex Granito/M2 SNI-2008


Bahan : Semen PC 9.600 kg 1,300.00 12,480.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Homogenous Tile 60x60 cm, ex Granito (polish) 1.116 M2 255,255.00 284,864.58
Semen warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 325,025.21 Rp 325,025.21
Upah : Kep. Tukang Batu 0.025 Org 100,000.00 2,500.00
Tukang Batu halus 0.250 Org 95,000.00 23,750.00
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 64,300.00 Rp 64,300.00
T O T A L Rp 389,325.21
4 LANTAI HOMOGENOUS TILE 60x60 (un-polish), ex Granito/M2 SNI-2008
Bahan : Semen PC 9.600 kg 1,300.00 12,480.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Homogenous Tile 60x60 cm, ex Granito (un-polish) 1.116 M2 259,875.00 290,020.50
Semen warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 330,181.13 Rp 330,181.13
Upah : Kep. Tukang Batu 0.025 Org 100,000.00 2,500.00
Tukang Batu halus 0.250 Org 95,000.00 23,750.00
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 64,300.00 Rp 64,300.00
T O T A L Rp 394,481.13
5 LANTAI HOMOGENOUS TILE, GRANITTO 40/40 (polish) / M2 SNI-2008
Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Homogenous Tile Granitto 40/40 Cm, polished 1.068 M2 170,940.00 182,563.92
Semen warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 223,244.55 Rp 223,244.55
Upah : Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Tukang Batu halus 0.150 Org 95,000.00 14,250.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,900.00 Rp 39,900.00
T O T A L Rp 263,144.55
6 LANTAI HOMOGENOUS TILE, GRANITTO 30x30 (un-polish) / M2 SNI-2008
Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Homogenous Tile Granitto 30/30 Cm, un-polished 1.068 M2 157,080.00 167,761.44
Semen warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 208,442.07 Rp 208,442.07
Upah : Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
75% Tukang Batu halus 0.150 Org 95,000.00 14,250.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,900.00 Rp 39,900.00
T O T A L Rp 248,342.07
7 PAS. LANTAI KERAMIK 33X33 Cm (ex Roman) / M2
Bahan : Semen PC SNI-2008 8.190 kg 1,300.00 10,647.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Keramik tile 33x33 cm, ex Roman 1.089 M2 97,650.00 106,340.85
Semen warna 1.620 Kg 10,500.00 17,010.00
Sub - Bahan 145,928.48 Rp 145,928.48
Upah : Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Tukang Batu halus 0.150 Org 95,000.00 14,250.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,900.00 Rp 39,900.00
T O T A L Rp 185,828.48
8 PAS. LANTAI KERAMIK LOKAL 20/20 Cm (ex Roman) / M2 SNI-2008
Bahan : Semen PC 10.400 kg 1,300.00 13,520.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Keramik lokal 20/20 Cm (ex Roman) 1.060 M2 86,100.00 91,266.00
Semen Warna 1.620 Kg 10,500.00 17,010.00
Sub - Bahan 133,726.63 Rp 133,726.63
Upah : Kep. Tukang Batu 0.015 Org 100,000.00 1,500.00
Tukang Batu halus 0.150 Org 95,000.00 14,250.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.015 Org 110,000.00 1,650.00
Sub - Upah 39,900.00 Rp 29,925.00
T O T A L Rp 163,651.63
9 PAS. LANTAI KERAMIK LOKAL 30/30 Cm (ex Roman) / M2 SNI-2008
Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Keramik lokal 30/30 Cm (ex Roman) 1.068 M2 73,500.00 78,498.00
Semen Warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 119,178.63 Rp 119,178.63

RAB - 040
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Upah : Sama dengan upah pas. keramik 20x20 Rp 29,925.00


T O T A L Rp 149,103.63

10 PAS. LANTAI KERAMIK LOKAL 40/40 Cm (ex Roman) / M2 SNI-2008


Bahan : Semen PC 10.000 kg 1,300.00 13,000.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Keramik lokal 40/40 Cm (ex Roman) 1.068 M2 82,500.00 88,110.00
Semen Warna 1.500 Kg 10,500.00 15,750.00
Sub - Bahan 128,790.63 Rp 128,790.63
Upah : Sama dengan upah pas. keramik 20x20 Rp 29,925.00
T O T A L Rp 158,715.63
9.2.2 PAS. PLINT KERAMIK
1 PAS. PLINT HOMOGENOUS TILE 10X60 Cm, / M' SNI-2008
Bahan : Semen PC 1.140 kg 1,300.00 1,482.00
Pasir pasang 0.003 M3 265,125.00 795.38
Homogenous Tile 60x60 cm 0.123 M2 255,255.00 31,335.10
Semen Warna 0.025 Kg 10,500.00 262.50
Sub - Bahan 33,874.98 Rp 33,874.98
Upah : Kep. Tukang Batu 0.009 Org 100,000.00 900.00
Tukang Batu halus 0.090 Org 95,000.00 8,550.00
Pekerja 0.090 Org 75,000.00 6,750.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 16,750.00 Rp 16,750.00
Ditambah upah potong ubin & tali air (1x upah) Rp 16,750.00
TOTAL Rp 67,374.98
2 PAS. PLINT KAYU KAMPER 2x10 Cm, / M' SNI-2008
Bahan : Papan kayu Kamper 0.002 m3 10,395,000.00 20,790.00
Paku / skrup 0.050 Kg 19,950.00 997.50
Sub - Bahan 21,787.50 Rp 21,787.50
Upah : Kep. Tukang Kayu 0.012 Org 105,000.00 1,260.00
Tukang Kayu halus 0.120 Org 95,000.00 11,400.00
Pekerja 0.120 Org 75,000.00 9,000.00
Mandor 0.006 Org 110,000.00 660.00
Sub - Upah 22,320.00 Rp 22,320.00
T O T A L Rp 44,107.50
9.2.3 PAS. LANTAI MARMER
1 LANTAI MARMER LOKAL 60x60 Cm (ex Tulung Agung) / M2 SNI-2008
Bahan : Semen PC 8.190 kg 1,300.00 10,647.00
Pasir pasang 0.045 M3 265,125.00 11,930.63
Marmer Tulung Agung, 60/60 cm 1.060 M2 420,000.00 445,200.00
Semen Warna 0.650 Kg 10,500.00 6,825.00
Sub - Bahan 474,602.63 Rp 474,602.63
Upah : Kep. Tukang Batu 0.025 Org 100,000.00 2,500.00
Tukang Batu halus 0.250 Org 95,000.00 23,750.00
Pekerja 0.500 Org 75,000.00 37,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 64,300.00 Rp 64,300.00
T O T A L Rp 538,902.63
9.2.4 PAS. LANTAI KARPET
1 PAS. UNDERLAYER / PELAPIS BAWAH KARPET / M2 SNI-2008
Bahan : Underlayer / Rubber corrugated 1.050 M2 31,500.00 33,075.00
Lem 0.350 Kg 42,000.00 14,700.00
Sub - Bahan 47,775.00 Rp 47,775.00
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang Kayu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 18,270.00 Rp 18,270.00
T O T A L Rp 66,045.00
2 PAS. LANTAI KARPET SHEET / M2 SNI-2008
Bahan : Karpet Sheet 1.050 M2 52,500.00 55,125.00
Lem 0.350 Kg 42,000.00 14,700.00
Sub - Bahan 69,825.00 Rp 69,825.00
Upah : Kep. Tukang Kayu 0.015 Org 105,000.00 1,575.00
Tukang Kayu halus 0.150 Org 95,000.00 14,250.00
Pekerja 0.150 Org 75,000.00 11,250.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 27,955.00 Rp 27,955.00
T O T A L Rp 97,780.00
3 PAS. LANTAI KARPET TILE 50x50 cm / M2 SNI-2008
Bahan : Carpet Tile 50x50, ex Leiko 1.050 M2 236,250.00 248,062.50
Lem 0.350 Kg 42,000.00 14,700.00
Sub - Bahan 262,762.50 Rp 262,762.50
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang Kayu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 18,270.00 Rp 18,270.00
T O T A L Rp 281,032.50
4 PAS. LANTAI VINYL TILE 30x30 / M2 SNI-2008
Bahan : Vinyl tile 30x30 cm, ex ………….. 1.050 M2 157,500.00 165,375.00
Lem 0.350 Kg 42,000.00 14,700.00
Sub - Bahan 180,075.00 Rp 180,075.00
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang Kayu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 18,270.00 Rp 18,270.00

RAB - 041
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

T O T A L Rp 198,345.00

9.2.5 PAS. LANTAI PARQUET


1 PAS. LANTAI PARQUET KAYU / M2 SNI-2008
Bahan : Parquet kayu 1.050 M2 150,000.00 157,500.00
Lem 0.600 Kg 42,000.00 25,200.00
Sub - Bahan 182,700.00 Rp 182,700.00
Upah : Kep. Tukang Kayu 0.035 Org 105,000.00 3,675.00
Tukang Kayu halus 0.350 Org 95,000.00 33,250.00
Pekerja 0.350 Org 75,000.00 26,250.00
Mandor 0.035 Org 110,000.00 3,850.00
Sub - Upah 67,025.00 Rp 67,025.00
T O T A L Rp 249,725.00
2 PAS. LANTAI PARKET SINTETIS 10X90 CM / M2 SNI-2008
Bahan : Parket sintetis 1.050 M2 78,750.00 82,687.50
Lem 0.350 Kg 42,000.00 14,700.00
Sub - Bahan 97,387.50 Rp 97,387.50
Upah : Kep. Tukang Kayu 0.010 Org 105,000.00 1,050.00
Tukang Kayu halus 0.100 Org 95,000.00 9,500.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 18,270.00 Rp 18,270.00
T O T A L Rp 115,657.50

9.2.6. PAS. LANTAI "MERO" RAISED FLOOR, Ex Germany


(Dihitung untuk kebutuhan seluas 31 m2)
Bahan : Mero Raised Floor ex Germany, type Calsium Sulphate
Modul 600x600x30mm, Finish HPL, tinggi 20 cm. 31.000 M2 1,200,000.00 37,200,000.00
Sub - Bahan 37,200,000.00 Rp 37,200,000.00
Lain2 : - Biaya Instol 1.000 lot 6,000,000.00 6,000,000.00
- Biaya pengiriman ke Pangkal Pinang 1.000 lot 13,500,000.00 13,500,000.00
Sub - Upah 19,500,000.00 Rp 19,500,000.00
Total harga untuk 31 m2 Rp 56,700,000.00
HARGA / M2 Rp 1,829,032.26

- Fascia (penutup RF di depan pintu) 1.000 lot 1,000,000.00 1,000,000.00


- Veribor (tile lifter) 1.000 unit 900,000.00 900,000.00

9.2.7. PEK. SALURAN


1 Pas. Saluran terbuka, pas. bata + buis beton 1/2 dia 30 cm / M'
Bahan : - Dinding dari pas batu bata 1Pc : 5Ps 1.000 M2 102,764.63 102,764.63
- Pas. Bata sambungan buis beton 0.120 M2 102,764.63 12,331.76
- Plesteran dinding bata 1.000 M2 71,684.98 71,684.98
- Buis beton 1/2 dia 30 cm, @ panjang 0,5 m 2.000 bh 53,130.00 106,260.00
Sub - Bahan 293,041.36 Rp 293,041.36
Upah pas buis beton :
Pekerja 0.500 Org 75,000.00 37,500.00
Tukang batu 0.100 Org 95,000.00 9,500.00
Kep. Tukang 0.010 Org 100,000.00 1,000.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 48,550.00 Rp 48,550.00
T O T A L Rp 341,591.36
2 Pas. Saluran tertutup, pas bata + buis beton 1/2 dia 30 cm, ditutup plat beton 15 cm / M'
Bahan : - Dinding dari pas batu bata 1Pc : 5Ps 1.000 M2 102,764.63 102,764.63
- Pas. Bata sambungan buis beton 0.120 M2 102,764.63 12,331.76
- Plesteran dinding bata 1.000 M2 71,684.98 71,684.98
- Buis beton 1/2 dia 30 cm, @ panjang 0,5 m 2.000 bh 53,130.00 106,260.00
- Tutup beton tulang tebal 15 cm 0.090 M3 5,263,177.78 473,686.00
Sub - Bahan 766,727.36 Rp 766,727.36
Upah pas buis beton :
Pekerja 0.500 Org 75,000.00 37,500.00
Tukang batu 0.100 Org 95,000.00 9,500.00
Kep. Tukang 0.010 Org 100,000.00 1,000.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 48,550.00 Rp 48,550.00
T O T A L Rp 815,277.36
3 Pas. Saluran tertutup, pas bata + buis beton 1/2 dia 30 cm, ditutup plat beton 10 cm / M'
Bahan : - Dinding dari pas batu bata 1Pc : 5Ps 1.000 M2 102,764.63 102,764.63
- Pas. Bata sambungan buis beton 0.120 M2 102,764.63 12,331.76
- Plesteran dinding bata 1.000 M2 71,684.98 71,684.98
- Buis beton 1/2 dia 30 cm, @ panjang 0,5 m 2.000 bh 53,130.00 106,260.00
- Tutup beton tulang tebal 15 cm 0.050 M3 5,263,177.78 263,158.89
Sub - Bahan 556,200.24 Rp 556,200.24
Upah pas buis beton :
Pekerja 0.500 Org 75,000.00 37,500.00
Tukang batu 0.100 Org 95,000.00 9,500.00
Kep. Tukang 0.010 Org 100,000.00 1,000.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 48,550.00 Rp 48,550.00
T O T A L Rp 604,750.24

RAB - 042
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

4 Pas. Saluran tertutup, buis beton dia 30 cm / M'


Bahan : - Pas. Bata sambungan buis beton 0.217 M2 102,764.63 22,264.98
- Buis beton dia 30 cm, @ panjang 1 m 1.000 bh 88,935.00 88,935.00
Sub - Bahan 111,199.98 Rp 111,199.98
Upah pas buis beton :
Pekerja 0.500 Org 75,000.00 37,500.00
Tukang batu 0.100 Org 95,000.00 9,500.00
Kep. Tukang 0.010 Org 100,000.00 1,000.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 48,550.00 Rp 48,550.00
T O T A L Rp 159,749.98

9.3. PEKERJAAN PLAFOND


1 PAS. PLAFOND GYPSUM BOARD 9 MM, RGK HOLLOW / M2
(Rangka Plafond Hollow)
Bahan : Paku peluru ramset 0.390 bh 2,500.00 975.00
Hollow 40x40x0,35mm (rangka utama) 0.459 btg 21,000.00 9,639.00
Hollow 20x40x0,35mm (rangka pembagi) 0.431 btg 21,000.00 9,051.00
Paku beton 0.010 kg 30,000.00 300.00
Sekrup 6x1-1,5 14.000 bh 400.00 5,600.00
Gypsumboard 120x240 cm 9 mm 0.364 lbr 59,000.00 21,476.00
Sekrup gypsum 21.000 bh 400.00 8,400.00
Textile tape 0.024 rol 18,375.00 441.00
Compound gypsum 0.020 zak 60,375.00 1,207.50
Amplas 0.100 lbr 2,887.50 288.75
Sub - Bahan 57,378.25 Rp 57,378.25
Upah : Kepala tukang 0.031 Org 95,000.00 2,945.00
Tukang Allumunium 0.260 Org 100,000.00 26,000.00
Tukang gypsum 0.050 Org 90,000.00 4,500.00
Pekerja 0.260 Org 75,000.00 19,500.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 54,375.00 Rp 54,375.00
T O T A L Rp 111,753.25
2 PAS. PLAFOND GYPSUM 9 MM, RGK. METAL FURING / M2
(Rangka Metal Furing)
Bahan : Paku peluru ramset 0.390 bh 2,500.00 975.00
Metal furing 1.250 btg 37,800.00 47,250.00
Paku beton 0.010 kg 30,000.00 300.00
Sekrup 6x1-1,5 14.000 bh 400.00 5,600.00
Gypsumboard 120x240 cm 9 mm 0.364 lbr 59,000.00 21,476.00
Sekrup gypsum 21.000 bh 400.00 8,400.00
Textile tape 0.024 rol 18,375.00 441.00
Compound gypsum 0.020 zak 60,375.00 1,207.50
Amplas 0.100 lbr 2,887.50 288.75
Sub - Bahan 85,938.25 Rp 85,938.25
Upah : Kepala tukang 0.031 Org 95,000.00 2,945.00
Tukang Allumunium 0.260 Org 100,000.00 26,000.00
Tukang gypsum 0.050 Org 90,000.00 4,500.00
Pekerja 0.260 Org 75,000.00 19,500.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 54,375.00 Rp 54,375.00
T O T A L Rp 140,313.25
3 PAS. PLAFOND GYPSUM 9 MM (WATER RESISTANTS) / M2
(Rangka Plafond Hollow)
Bahan : Paku peluru ramset 0.390 bh 2,500.00 975.00
Hollow 40x40x0,35mm (rangka utama) 0.459 btg 21,000.00 9,639.00
Hollow 20x40x0,35mm (rangka pembagi) 0.431 btg 21,000.00 9,051.00
Paku beton 0.010 kg 30,000.00 300.00
Sekrup 6x1-1,5 14.000 bh 400.00 5,600.00
Gypsumboard Waterresistance 120x240 cm 9 mm 0.364 lbr 102,500.00 37,310.00
Sekrup gypsum 21.000 bh 400.00 8,400.00
Textile tape 0.024 rol 18,375.00 441.00
Compound gypsum 0.020 zak 60,375.00 1,207.50
Amplas 0.100 lbr 2,887.50 288.75
Sub - Bahan 73,212.25 Rp 73,212.25
Upah : Kepala tukang 0.031 Org 95,000.00 2,945.00
Tukang Allumunium 0.260 Org 100,000.00 26,000.00
Tukang gypsum 0.050 Org 90,000.00 4,500.00
Pekerja 0.260 Org 75,000.00 19,500.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 54,375.00 Rp 54,375.00
T O T A L Rp 127,587.25
4 PAS. PLAFOND CALCIUM SILIKAT 6 MM (RGK HOLLOW) / M2
Bahan : Paku peluru ramset 0.390 bh 2,500.00 975.00
Hollow 40x40x0,35mm (rangka utama) 0.459 btg 21,000.00 9,639.00
Hollow 20x40x0,35mm (rangka pembagi) 0.431 btg 21,000.00 9,051.00
Paku beton 0.010 kg 30,000.00 300.00
Sekrup 6x1-1,5 14.000 bh 400.00 5,600.00
Calsium Board 1200x2400x6 mm 0.364 lbr 106,365.00 38,716.86
Sekrup gypsum 21.000 bh 400.00 8,400.00
Textile tape 0.024 rol 18,375.00 441.00
Compound gypsum 0.020 zak 60,375.00 1,207.50
Amplas 0.100 lbr 2,887.50 288.75
Sub - Bahan 74,619.11 Rp 74,619.11
Upah : Kepala tukang 0.031 Org 95,000.00 2,945.00
Tukang Allumunium 0.260 Org 100,000.00 26,000.00

RAB - 043
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Tukang gypsum 0.050 Org 90,000.00 4,500.00


Pekerja 0.260 Org 75,000.00 19,500.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 54,375.00 Rp 54,375.00
T O T A L Rp 128,994.11
5 PAS. PLAFOND GRC 5 MM (Rangka Hollow) / M2
Bahan : Paku peluru ramset 0.390 bh 2,500.00 975.00
Hollow 40x40x0,35mm (rangka utama) 0.459 btg 21,000.00 9,639.00
Hollow 20x40x0,35mm (rangka pembagi) 0.431 btg 21,000.00 9,051.00
Paku beton 0.010 kg 30,000.00 300.00
Sekrup 6x1-1,5 14.000 bh 400.00 5,600.00
GRC-Board 1200x2400x5 mm 0.364 lbr 73,500.00 26,754.00
Sekrup gypsum 21.000 bh 400.00 8,400.00
Textile tape 0.024 rol 18,375.00 441.00
Compound gypsum 0.020 zak 60,375.00 1,207.50
Amplas 0.100 lbr 2,887.50 288.75
Sub - Bahan 62,656.25 Rp 62,656.25
Upah : Kepala tukang 0.031 Org 95,000.00 2,945.00
Tukang Allumunium 0.260 Org 100,000.00 26,000.00
Tukang gypsum 0.050 Org 90,000.00 4,500.00
Pekerja 0.260 Org 75,000.00 19,500.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 54,375.00 Rp 54,375.00
T O T A L Rp 117,031.25
6 PAS. PLAFOND ACAUSTIC TILE 600X1200X15mm / M2
Rangka Allumunium T SNI-2008
Profil allumunium Main Tee (p. 3,6m) 3.600 m' 7,291.67 26,250.00
Profil allumunium Cross Tee (p. 1,2 m) 1.200 m' 6,562.50 7,875.00
Profil allumunium Cross Tee (p. 0,60 m) 0.600 m' 8,750.00 5,250.00
Kawat diameter 4mm 0.150 kg 17,500.00 2,625.00
Paku peluru ramset 1.050 bh 2,500.00 2,625.00
Sub - Bahan 44,625.00 Rp 44,625.00
Penutup Plafond
Bahan : Acoustic Tile 600x1200x15 mm (ex Armstrong) 1.500 lmbr 37,800.00 56,700.00
Sub - Bahan 56,700.00 Rp 56,700.00
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang Gypsum 0.500 Org 90,000.00 45,000.00
Kepala Tukang 0.050 Org 95,000.00 4,750.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 61,880.00 Rp 61,880.00
T O T A L Rp 163,205.00
7 PAS. PLAFOND GYPSUM TILE 600x1200x9mm / M2 SNI-2008
Rangka Allumunium T
Profil allumunium Main Tee (p. 3,6m) 3.600 m' 7,291.67 26,250.00
Profil allumunium Cross Tee (p. 1,2 m) 1.200 m' 6,562.50 7,875.00
Profil allumunium Cross Tee (p. 0,60 m) 0.600 m' 8,750.00 5,250.00
Kawat diameter 4mm 0.150 kg 17,500.00 2,625.00
Paku peluru ramset 1.050 bh 2,500.00 2,625.00
Sub - Bahan 44,625.00 Rp 44,625.00
Penutup Plafond
Bahan : Gypsum Tile 600x1200x9 mm (porporated) 1.500 lmbr 18,375.00 27,562.50
Sub - Bahan 27,562.50 Rp 27,562.50
Upah : Pekerja 0.150 Org 75,000.00 11,250.00
Tukang Gypsum 0.500 Org 90,000.00 45,000.00
Kepala Tukang 0.050 Org 95,000.00 4,750.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 61,880.00 Rp 61,880.00
T O T A L Rp 134,067.50
8 PAS. PLAFOND LAMBRESERING KAMPER 10 Cm / M2
(Rangka kayu Borneo Super)
Bahan : Kayu Borneo Super (kasau) SNI-2008 0.020 m3 4,462,500.00 89,250.00
Paku biasa 2"-4" 0.200 kg 15,356.25 3,071.25
Papan Kamper Samarinda oven 0.020 m3 10,395,000.00 207,900.00
Sub - Bahan 300,221.25 Rp 300,221.25
Upah : Kep. Tukang Kayu 0.031 Org 105,000.00 3,255.00
Tukang kayu halus 0.500 Org 95,000.00 47,500.00
Pekerja 0.350 Org 75,000.00 26,250.00
Mandor 0.013 Org 110,000.00 1,430.00
Sub - Upah 78,435.00 Rp 78,435.00
T O T A L Rp 378,656.25
9 PAS. PENUTUP PLAFOND MULTIPLEKS 4 MM / M2
Bahan : Multipleks 4 mm 0.364 lbr 57,750.00 21,021.00
Paku halus 0.020 Kg 95,000.00 1,900.00
Sub - Bahan 22,921.00 Rp 22,921.00
Upah : sama dengan upah pas. plafond asbes plat Rp 10,075.00
T O T A L Rp 32,996.00

10 PAS. PENUTUP PLAFOND ASBES PLAT 4 MM / M2 SNI-2008


Bahan : Asbes plat 4 mm 1.100 M2 47,250.00 51,975.00
Paku halus 0.010 Kg 95,000.00 950.00
Sub - Bahan 52,925.00 Rp 52,925.00
Upah : Kep. Tukang Kayu 0.007 Org 105,000.00 735.00
Tukang kayu halus 0.070 Org 95,000.00 6,650.00
Pekerja 0.030 Org 75,000.00 2,250.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 10,075.00 Rp 10,075.00
T O T A L Rp 63,000.00
11 PAS. PENUTUP PLAFOND LAMBRIZIRING KAYU / M2 SNI-2008

RAB - 044
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Bahan : Papan kayu Kamper Samarinda oven 0.015 m3 10,395,000.00 155,925.00


Paku halus 0.010 Kg 95,000.00 950.00
Sub - Bahan 156,875.00 Rp 156,875.00
Upah : Kep. Tukang Kayu 0.080 Org 105,000.00 8,400.00
Tukang kayu halus 0.800 Org 95,000.00 76,000.00
Pekerja 0.800 Org 75,000.00 60,000.00
Mandor 0.040 Org 110,000.00 4,400.00
Sub - Upah 148,800.00 Rp 148,800.00
T O T A L Rp 305,675.00
12 PAS. LIST PLAFOND KAYU PROFIL / M' SNI-2008
Bahan : List kayu profil 1.050 m' 15,000.00 15,750.00
Paku halus 0.010 Kg 95,000.00 950.00
Sub - Bahan 16,700.00 Rp 16,700.00
Upah : Kep. Tukang Kayu 0.005 Org 105,000.00 525.00
Tukang kayu halus 0.050 Org 95,000.00 4,750.00
Pekerja 0.050 Org 75,000.00 3,750.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 9,355.00 Rp 9,355.00
T O T A L Rp 26,055.00
13 PAS. LIST PLAFOND GYPSUM PROFIL 5-10 cm / M' SNI-2008
Bahan : List gypsum profil 5-10 cm 1.050 m' 5,250.00 5,512.50
Compound Gypsum 0.300 Kg 4,725.00 1,417.50
Sub - Bahan 6,930.00 Rp 6,930.00
Upah : Kep. Tukang gypsum 0.006 Org 95,000.00 570.00
Tukang Gypsum 0.060 Org 90,000.00 5,400.00
Pekerja 0.060 Org 75,000.00 4,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 10,800.00 Rp 10,800.00
T O T A L Rp 17,730.00
14 PAS. LIST PLAFOND ALLUMUNIUM cm / M' SNI-2008
Bahan : Wall angle allumunium 1.100 m' 2,500.00 2,750.00
Sub - Bahan 2,750.00 Rp 2,750.00
Upah : Kep. Tukang gypsum 0.004 Org 95,000.00 380.00
Tukang Gypsum 0.040 Org 90,000.00 3,600.00
Pekerja 0.113 Org 75,000.00 8,475.00
Mandor 0.007 Org 110,000.00 770.00
Sub - Upah 7,500.00 Rp 7,500.00
T O T A L Rp 10,250.00
15 PERAPIHAN/ACIAN PLAFOND BETON EXPOSE
Bahan : Semen PC 6.900 kg 1,300.00 8,970.00
Pasir pasang 0.018 m3 265,125.00 4,772.25
Sub - Bahan 13,742.25 Rp 13,742.25
Upah : Kep. Tukang batu 0.019 Org 100,000.00 1,900.00
Tukang batu halus 0.190 Org 95,000.00 18,050.00
Pekerja 0.019 Org 75,000.00 1,425.00
Mandor 0.002 Org 110,000.00 220.00
Sub - Upah 21,595.00 Rp 21,595.00
T O T A L Rp 35,337.25

9.4. PEKERJAAN PENGECATAN


1 PEK. CAT TEMBOK ACRYLIC EMULSION / M2
ICI DULUX PENTALITTE
Bahan : Cat Tembok ICI Dulux Acrilyc Emulsion 0.360 Kg 44,257.50 15,932.70
Plamur tembok 0.100 kg 18,375.00 1,837.50
Amplas besi 0.300 lbr 2,887.50 866.25
Kuas Roll 0.015 Bh 36,750.00 551.25
Sub - Bahan 19,187.70 Rp 19,187.70
Upah : Kep. Tukang Cat 0.006 Org 90,000.00 540.00
Tukang Cat 0.060 Org 100,000.00 6,000.00
Pekerja 0.030 Org 75,000.00 2,250.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 9,120.00 Rp 9,120.00
T O T A L Rp 28,307.70
2 PEK. CAT TEMBOK DINDING LUAR WEATHERSHIELD / M2
ICI DULUX WEATHERSHIELD
Bahan : Cat Tembok ICI Dulux, Wathershield 0.220 Kg 60,375.00 13,282.50
Alkali Resistants Dulux ICI 0.110 Bh 45,596.25 5,015.59
Amplas besi 0.500 Bh 2,887.50 1,443.75
Kuas Roll 0.100 Bh 36,750.00 3,675.00
Sub - Bahan 23,416.84 Rp 23,416.84
Upah : Standart upah cat tembok Rp 9,120.00
T O T A L Rp 32,536.84

3 PEK. CAT TEMBOK ACRYLIC EMULSION (ex Mowilex) / M2


Bahan : Cat Tembok Mowilex (Acrilyc Emulsion) 0.220 Kg 39,375.00 8,662.50
Plamur tembok 0.110 Bh 18,375.00 2,021.25
Amplas besi 0.500 Bh 2,887.50 1,443.75
Kuas Roll 0.100 Bh 36,750.00 3,675.00
Sub - Bahan 15,802.50 Rp 15,802.50
Upah : sama dengan upah cat ICI Rp 9,120.00
T O T A L Rp 24,922.50

4 PEK. CAT TEMBOK DINDING LUAR (Mowilex Watercoat) / M2


Bahan : Cat Tembok Mowilex (Watercoat) 0.220 Kg 57,750.00 12,705.00
Alkali Resistants 0.110 Bh 45,596.25 5,015.59
Amplas besi 0.500 Bh 2,887.50 1,443.75

RAB - 045
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Kuas Roll 0.100 Bh 36,750.00 3,675.00


Sub - Bahan 22,839.34 Rp 22,839.34
Upah : Standart upah cat tembok Rp 9,120.00
T O T A L Rp 31,959.34

5 PEK. CAT TEMBOK ACRYLIC EMULSION (Vinylex) / M2


Bahan : Cat Tembok Vinilex (Acrilyc Emulsion) 0.220 Kg 20,000.00 4,400.00
Plamur tembok 0.110 Bh 18,375.00 2,021.25
Amplas besi 0.500 Bh 2,887.50 1,443.75
Kuas Roll 0.100 Bh 36,750.00 3,675.00
Sub - Bahan 11,540.00 Rp 11,540.00
Upah : Standart upah cat tembok Rp 9,120.00
T O T A L Rp 20,660.00

6 PEK. CAT TEMBOK ACRYLIC EMULSION (Catylac) / M2


Bahan : Cat Tembok Catylac (Acrilyc Emulsion) 0.220 Kg 26,250.00 5,775.00
Plamur tembok 0.110 Bh 18,375.00 2,021.25
Amplas besi 0.500 Bh 2,887.50 1,443.75
Kuas Roll 0.100 Bh 36,750.00 3,675.00
Sub - Bahan 12,915.00 Rp 12,915.00
Upah : Standart upah cat tembok Rp 9,120.00
T O T A L Rp 22,035.00

7 PEK. CAT TEMBOK "ULANG" (ICI Dulux Pentalitte) / M2


Bahan : Cat Tembok ICI Dulux Acrilyc Emulsion 0.300 Kg 44,257.50 13,277.25
Amplas besi 0.250 Bh 2,887.50 721.88
Kuas Roll 0.050 Bh 36,750.00 1,837.50
Sub - Bahan 15,836.63 Rp 15,836.63
Upah : Kep. Tukang Cat 0.004 Org 90,000.00 360.00
Tukang Cat 0.040 Org 100,000.00 4,000.00
Pekerja 0.028 Org 75,000.00 2,100.00
Mandor 0.001 Org 110,000.00 110.00
Sub - Upah 6,570.00 Rp 6,570.00
T O T A L Rp 22,406.63
8 PEK. CAT TEMBOK "ULANG" (Super Vinylex) / M2
Bahan : Cat Tembok Vinilex (Acrilyc Emulsion) 0.300 Kg 20,000.00 6,000.00
Amplas besi 0.250 Bh 2,887.50 721.88
Kuas Roll 0.050 Bh 36,750.00 1,837.50
Sub - Bahan 8,559.38 Rp 8,559.38
Upah : sama dengan upah cat ulang ICI Rp 6,570.00
T O T A L Rp 15,129.38

9 PEK. CAT KAYU/BESI BARU, ICI Dulux Supergloss (3 kali) / M2


Bahan : Cat Kayu (ICI Dulux Super Gloss) 0.430 Kg 57,750.00 24,832.50
Menie kayu/besi 0.200 Kg 23,625.00 4,725.00
Plamur kayu 0.150 Bh 26,250.00 3,937.50
Tinner Up 0.200 Kg 28,875.00 5,775.00
Amplas besi 1.000 Bh 2,887.50 2,887.50
Kuas 0.050 Bh 15,750.00 787.50
Sub - Bahan 42,945.00 Rp 42,945.00
Upah : Kep. Tukang Cat 0.005 Org 90,000.00 450.00
Tukang Cat 0.100 Org 100,000.00 10,000.00
Pekerja 0.100 Org 75,000.00 7,500.00
Mandor 0.005 Org 110,000.00 550.00
Sub - Upah 18,500.00 Rp 18,500.00
T O T A L Rp 61,445.00
10 PEK. CAT MINYAK / EPOXY ex Mowilex (3 kali) / M2
Bahan : Cat Minyak (ex Mowilex Semi Gloss) 0.400 Kg 60,000.00 24,000.00
Plamur tembok 0.350 Kg 0.00 0.00
Tinner Up 0.200 Kg 28,875.00 5,775.00
Amplas besi 1.000 Bh 2,887.50 2,887.50
Alat semprot 1.000 Lot 5,000.00 5,000.00
Sub - Bahan 37,662.50 Rp 37,662.50
Upah : Kep. Tukang Cat 0.008 Org 90,000.00 720.00
Tukang Cat 0.080 Org 100,000.00 8,000.00
Pekerja 0.080 Org 75,000.00 6,000.00
Mandor 0.008 Org 110,000.00 880.00
Sub - Upah 15,600.00 Rp 15,600.00
T O T A L Rp 53,262.50
11 PEK. CAT DUCO DANAGLOSS / M2
Bahan : Cat Duco ex Danapaint 0.400 Kg 88,725.00 35,490.00
Dempul Duco 0.750 Kg 36,750.00 27,562.50
Tinner Up 0.800 Kg 28,875.00 23,100.00
Amplas besi 2.000 Bh 2,887.50 5,775.00
Alat semprot 1.000 Lot 10,000.00 10,000.00
Sub - Bahan 101,927.50 Rp 101,927.50
Upah : Kep. Tukang cat 0.040 Org 90,000.00 3,600.00
Tukang Cat 0.400 Org 100,000.00 40,000.00
Pekerja 0.400 Org 75,000.00 30,000.00
Mandor 0.004 Org 110,000.00 440.00
Sub - Upah 74,040.00 Rp 74,040.00
T O T A L Rp 175,967.50
12 PEK. CAT MELAMIK KAYU / M2
Bahan : Wood Filler Ultran 0.250 Kg 52,500.00 13,125.00
Sending sealer Impra 0.150 Kg 55,125.00 8,268.75
Cat warna Ultran 0.150 Kg 52,500.00 7,875.00
Melamik Impra 0.350 Kg 63,000.00 22,050.00
Tinner (High class) 0.800 Kg 28,875.00 23,100.00

RAB - 046
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Amplas besi 2.000 Bh 2,887.50 5,775.00


Alat semprot 1.000 Lot 10,000.00 10,000.00
Sub - Bahan 90,193.75 Rp 90,193.75
Upah : Kep. Tukang cat 0.030 Org 90,000.00 2,700.00
Tukang Cat 0.300 Org 100,000.00 30,000.00
Pekerja 0.300 Org 75,000.00 22,500.00
Mandor 0.003 Org 110,000.00 330.00
Sub - Upah 55,530.00 Rp 55,530.00
T O T A L Rp 145,723.75

13 PEK. CAT MENIE KAYU / M2


Bahan : Menie kayu 0.400 Kg 23,625.00 9,450.00
Kuas 0.200 Bh 15,750.00 3,150.00
Sub - Bahan 12,600.00 Rp 12,600.00
Upah : Kep. Tukang cat 0.002 Org 90,000.00 180.00
Tukang Cat 0.100 Org 100,000.00 10,000.00
Mandor 0.001 Org 110,000.00 110.00
Sub - Upah 10,290.00 Rp 10,290.00
T O T A L Rp 22,890.00
14 PEK. RESIDU KAYU / M2
Bahan : Residu 0.500 Kg 18,375.00 9,187.50
Kuas 0.200 Bh 15,750.00 3,150.00
Sub - Bahan 12,337.50 Rp 12,337.50
Upah : Kep. Tukang 0.002 Org 90,000.00 180.00
Tukang Cat 0.100 Org 100,000.00 10,000.00
Mandor 0.001 Org 110,000.00 110.00
Sub - Upah 10,290.00 Rp 10,290.00
T O T A L Rp 22,627.50

X. PEK. PRASARANA LINGKUNGAN - DRAINASE


1 Memasang pipa beton, dia 15-20 cm tiap m'
Bahan : - Buis beton dia 20 panj. 100 cm bh 1.000 41,815 41,815.00
- Bata merah 31.4 bh 32.000 630 20,160.00
- Semen portland kg 3.920 1,300 5,096.00
- Pasir pasang m³ 0.056 265,125 14,847.00
- Pasir urug m³ 0.024 291,375 6,993.00
Jumlah Harga Bahan 88,911.00
Upah : - Pekerja Oh 0.140 75,000 10,500.00
- Tukang batu Oh 0.070 90,000 6,300.00
- Kepala tukang Oh 0.007 100,000 700.00
- Mandor Oh 0.007 110,000 770.00
Jumlah Upah Tenaga 18,270.00
Jumlah Total 107,181.00
Dibulatkan 107,180.00
2 Memasang saluran buis beton 1/2 dia 20 cm dinding bata, dalam 15-25 cm tiap m'
Bahan : - Buis beton 1/2 dia 20 panj. 100 cm bh 1.000 22,452 22,452.00
- Bata merah bh 42.000 630 26,460.00
- Semen portland kg 14.785 1,300 19,220.50
- Pasir pasang m³ 0.042 265,125 11,135.25
- Pasir urug m³ 0.008 291,375 2,331.00
Jumlah Harga Bahan 81,598.75
Upah : - Pekerja Oh 0.460 75,000 34,500.00
- Tukang batu Oh 0.198 90,000 17,820.00
- Kepala tukang Oh 0.020 100,000 2,000.00
- Mandor Oh 0.027 110,000 2,970.00
Jumlah Upah Tenaga 57,290.00
Jumlah Total 138,888.75
Dibulatkan 138,880.00
3 Memasang pipa buis beton, dia 30 cm tiap m'
Bahan : - Buis beton dia 30 panj. 100 cm bh 1.000 55,157 55,157.00
- Bata merah 37.68 bh 38.000 630 23,940.00
- Semen portland kg 10.300 1,300 13,390.00
- Pasir pasang m³ 0.061 265,125 16,172.63
- Pasir urug m³ 0.069 291,375 20,104.88
Jumlah Harga Bahan 128,764.50
Upah : - Pekerja Oh 0.380 75,000 28,500.00
- Tukang batu Oh 0.190 90,000 17,100.00
- Kepala tukang Oh 0.019 100,000 1,900.00
- Mandor Oh 0.019 110,000 2,090.00
Jumlah Upah Tenaga 49,590.00
Jumlah Total 178,354.50
Dibulatkan 178,350.00
4 Memasang pipa buis beton, dia 40 cm tiap m'
Bahan : - Buis beton dia 40 panj. 100 cm bh 1.000 68,825 68,825.00
- Bata merah 43.96 bh 44.000 630 27,720.00
- Semen portland kg 10.300 1,300 13,390.00
- Pasir pasang m³ 0.061 265,125 16,172.63
- Pasir urug m³ 0.069 291,375 20,104.88
Jumlah Harga Bahan 146,212.50
Upah : - Pekerja Oh 0.380 75,000 28,500.00
- Tukang batu Oh 0.190 90,000 17,100.00
- Kepala tukang Oh 0.019 100,000 1,900.00
- Mandor Oh 0.019 110,000 2,090.00

RAB - 047
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Jumlah Upah Tenaga 49,590.00


Jumlah Total 195,802.50
Dibulatkan 195,800.00
5 Memasang pipa buis beton, dia 50 cm tiap m'
Bahan : - Buis beton dia 50 panj. 100 cm bh 1.000 110,530 110,530.00
- Bata merah 50.24 bh 50.000 630 31,500.00
- Semen portland kg 20.600 1,300 26,780.00
- Pasir pasang m³ 0.122 265,125 32,345.25
- Pasir urug m³ 0.138 291,375 40,209.75
Jumlah Harga Bahan 241,365.00
Upah : - Pekerja Oh 0.570 75,000 42,750.00
- Tukang batu Oh 0.285 90,000 25,650.00
- Kepala tukang Oh 0.029 100,000 2,850.00
- Mandor Oh 0.029 110,000 3,135.00
lah Upah Tenaga 74,385.00
Jumlah Total 315,750.00
Dibulatkan 315,750.00
6 Memasang pipa buis beton, dia 60 cm tiap m'
Bahan : - Buis beton dia 60 panj. 100 cm bh 1.000 165,375 165,375.00
- Bata merah bh 56.52 630 35,607.60
- Semen portland kg 20.600 1,300 26,780.00
- Pasir pasang m³ 0.122 265,125 32,345.25
- Pasir urug m³ 0.138 291,375 40,209.75
Jumlah Harga Bahan 300,317.60
Upah : - Pekerja Oh 0.570 75,000 42,750.00
- Tukang batu Oh 0.285 90,000 25,650.00
- Kepala tukang Oh 0.029 100,000 2,850.00
- Mandor Oh 0.029 110,000 3,135.00
lah Upah Tenaga 74,385.00
Jumlah Total 374,702.60
Dibulatkan 374,700.00
7 Memasang pipa buis beton, dia 80 cm tiap m'
Bahan : - Buis beton dia 80 panj. 50 cm bh 2.000 179,155 358,310.00
- Bata merah bh 138.16 630 87,040.80
- Semen portland kg 30.900 1,300 40,170.00
- Pasir pasang m³ 0.183 265,125 48,517.88
- Pasir urug m³ 0.207 291,375 60,314.63
Jumlah Harga Bahan 594,353.30
Upah : - Pekerja Oh 0.760 75,000 57,000.00
- Tukang batu Oh 0.380 90,000 34,200.00
- Kepala tukang Oh 0.038 100,000 3,800.00
- Mandor Oh 0.038 110,000 4,180.00
lah Upah Tenaga 99,180.00
Jumlah Total 693,533.30
Dibulatkan 693,530.00
8 Memasang pipa buis beton, dia 100 cm tiap m'
Bahan : - Buis beton dia 100 panj. 50 cm bh 2.000 189,080 378,160.00
- Bata merah bh 163.28 630 102,866.40
- Semen portland kg 30.900 1,300 40,170.00
- Pasir pasang m³ 0.183 265,125 48,517.88
- Pasir urug m³ 0.207 291,375 60,314.63
Jumlah Harga Bahan 630,028.90
Upah : - Pekerja Oh 0.760 75,000 57,000.00
- Tukang batu Oh 0.380 90,000 34,200.00
- Kepala tukang Oh 0.038 100,000 3,800.00
- Mandor Oh 0.038 110,000 4,180.00
lah Upah Tenaga 99,180.00
Jumlah Total 729,208.90
Dibulatkan 729,200.00
9 Memasang 1 bh bak kontrol pas bata, 30x30 cm tinggi 35 cm
Bahan : - Bata merah bh 82.00 630 51,660.00
- Semen portland kg 44.000 1,300 57,200.00
- Pasir pasang m³ 0.070 265,125 18,558.75
- Batu pecah/split 2/3 m³ 0.070 269,500 18,865.02
- Besi beton polos kg 1.600 13,125 21,000.00
- Pasir beton m³ 0.060 270,375 16,222.50
Jumlah Harga Bahan 183,506.27
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.015 90,000 1,350.00
- Kepala tukang Oh 0.002 100,000 200.00
- Mandor Oh 0.016 110,000 1,760.00
lah Upah Tenaga 115,810.00
Jumlah Total 299,316.27
Dibulatkan 299,310.00
10 Memasang 1 bh bak kontrol pas bata, 60x60 cm tinggi 65 cm
Bahan : - Bata merah bh 208.00 630 131,040.00
- Semen portland kg 114.000 1,300 148,200.00
- Pasir pasang m³ 0.184 265,125 48,783.00
- Batu pecah/split 2/3 m³ 0.033 269,500 8,893.51
- Besi beton polos kg 4.850 13,125 63,656.25
- Pasir beton m³ 0.120 270,375 32,445.00
Jumlah Harga Bahan 433,017.76
Upah : - Pekerja Oh 2.160 75,000 162,000.00
- Tukang batu Oh 0.720 90,000 64,800.00
- Kepala tukang Oh 0.072 100,000 7,200.00
- Mandor Oh 0.108 110,000 11,880.00
- Tk Gali Oh 0.100 109,960 10,996.00
Jumlah Upah Tenaga 256,876.00

RAB - 048
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Jumlah Total 689,893.76


Dibulatkan 689,890.00
11 SALURAN AIR, dari batu kali lebar bawah 30 cm tinggi 60 cm, tiap 1 M'
Bahan : - Batu belah 15/20 m³ 0.47 257,250 121,679.25
- Semen portland kg 94.420 1,300 122,746.00
- Pasir pasang m³ 0.227 265,125 60,183.38
Jumlah Harga Bahan 304,608.63
Pemakaian alat
- Tamper / Hand Compactor jam 0.046 27,060 1,244.76
Jumlah Harga Alat 1,244.76
Upah : - Pekerja Oh 1.241 75,000 93,075.00
- Tukang batu Oh 0.398 90,000 35,820.00
- Kepala tukang Oh 0.040 100,000 4,000.00
- Mandor Oh 0.083 110,000 9,130.00
- Tk Gali Oh 0.250 109,960 27,490.00
Jumlah Upah Tenaga 169,515.00
Jumlah Total 474,123.63
Dibulatkan 474,120.00
12 SALURAN AIR, dari batu kali lebar bawah 80 cm tinggi 100 cm, tiap 1 M'
Bahan : - Batu belah 15/20 m³ 1.01 257,250 260,337.00
- Semen portland kg 193.400 1,300 251,420.00
- Pasir pasang m³ 0.464 265,125 123,018.00
Jumlah Harga Bahan 634,775.00
Pemakaian alat
- Tamper / Hand Compactor jam 0.093 27,060 2,516.58
Jumlah Harga Alat 2,516.58
Upah : - Pekerja Oh 2.983 75,000 223,725.00
- Tukang batu Oh 0.692 90,000 62,280.00
- Kepala tukang Oh 0.069 100,000 6,900.00
- Mandor Oh 0.219 110,000 24,090.00
- Tk Gali Oh 0.500 109,960 54,980.00
Jumlah Upah Tenaga 371,975.00
Jumlah Total 1,006,750.00
Dibulatkan 1,006,750.00
13 SALURAN AIR, dari batu kali lebar bawah 100 cm tinggi 120 cm, tiap 1 M'
Bahan : - Batu belah 15/20 m³ 1.29 257,250 331,080.75
- Semen portland kg 244.980 1,300 318,474.00
- Pasir pasang m³ 0.588 265,125 155,893.50
Jumlah Harga Bahan 805,448.25
Pemakaian alat
- Tamper / Hand Compactor jam 0.104 27,060 2,814.24
Jumlah Harga Alat 2,814.24
Upah : - Pekerja Oh 4.105 75,000 307,875.00
- Tukang batu Oh 0.862 90,000 77,580.00
- Kepala tukang Oh 0.086 100,000 8,600.00
- Mandor Oh 0.309 110,000 33,990.00
- Tk Gali Oh 0.750 109,960 82,470.00
Jumlah Upah Tenaga 510,515.00
Jumlah Total 1,315,963.25
Dibulatkan 1,315,960.00
14 Pas. Pipa beton, type FJ-Dusaspun (class 2) dia 60 cm panj 250 cm / BH
Bahan : - Pipa beton FJ-Dusaspun (class 2) dia. 60 cm, panjang 250 cm bh 1.00 1,199,700 1,199,700.00
Jumlah Harga Bahan 1,199,700.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00
Total harga/bh 1,348,470.00
Harga/M' 539,388.00
15 Pas. Pipa beton, type FJ-Dusaspun (class 2) dia 100 cm panj 250 cm / BH
Bahan : - Pipa beton FJ-Dusaspun (class 2) dia. 60 cm, panjang 250 cm bh 1.00 2,457,100 2,457,100.00
Jumlah Harga Bahan 2,457,100.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00
Total harga/bh 2,605,870.00
Harga/M' 1,042,348.00
16 Pas. Pipa beton, type RJ ex Boral dia. 80 cm panj 244 cm / BH
Bahan : - Pipa beton ex Boral dia. 80 cm, panjang 244 cm bh 1.00 1,400,480 1,400,480.00
Jumlah Harga Bahan 1,400,480.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00
Total harga/bh 1,549,250.00
Harga/M' 634,938.52
17 Pas. Pipa beton, type RJ ex Boral dia. 100 cm panj 244 cm / BH
Bahan : - Pipa beton ex Boral dia. 100 cm, panjang 244 cm bh 1.00 2,759,250 2,759,250.00
Jumlah Harga Bahan 2,759,250.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00

RAB - 049
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Total harga/bh 2,908,020.00


Harga/M' 1,191,811.48
18 Pas. Pipa beton, type RJ ex Boral dia. 120 cm panj 244 cm / BH
Bahan : - Pipa beton ex Boral dia. 120 cm, panjang 244 cm bh 1.00 3,536,860 3,536,860.00
Jumlah Harga Bahan 3,536,860.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00
Total harga/bh 3,685,630.00
Harga/M' 1,510,504.10
19 Pas. Pipa beton, type RJ ex Boral dia. 150 cm panj 244 cm / BH
Bahan : - Pipa beton ex Boral dia. 150 cm, panjang 244 cm bh 1.00 5,511,460 5,511,460.00
Jumlah Harga Bahan 5,511,460.00
Upah : - Pekerja Oh 1.140 75,000 85,500.00
- Tukang batu Oh 0.570 90,000 51,300.00
- Kepala tukang Oh 0.057 100,000 5,700.00
- Mandor Oh 0.057 110,000 6,270.00
Jumlah Upah Tenaga 148,770.00
Total harga/bh 5,660,230.00
Harga/M' 2,319,766.39
20 SALURAN TERBUKA, beton U Ditch ex MAS, uk. 60x80x120 cm / BH
Bahan : - Saluran U Ditch uk. 60x80x120 cm bh 1.00 672,000 672,000.00
- Semen portland kg 115.000 1,300 149,500.00
- Pasir pasang m³ 0.345 265,125 91,468.13
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 912,968.13
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 1,093,718.13
Harga/M' 911,431.77
21 SALURAN TERBUKA, beton U Ditch ex MAS, uk. 60x60x120 cm / BH
Bahan : - Saluran U Ditch uk. 60x60x120 cm bh 1.00 561,000 561,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 752,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 933,739.38
Harga/M' 778,116.15
22 SALURAN TERBUKA, beton U Ditch ex MAS, uk. 30x40x120 cm / BH
Bahan : - Saluran U Ditch uk. 30x40x120 cm bh 1.00 249,000 249,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 440,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 621,739.38
Harga/M' 518,116.15
23 SALURAN TERBUKA, beton U Ditch ex MAS, uk. 100x100x120 cm / BH
Bahan : - Saluran U Ditch uk. 100x100x120 cm bh 1.00 1,450,000 1,450,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 1,641,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 1,822,739.38
Harga/M' 1,518,949.48
24 SALURAN TERBUKA, beton U Ditch ex MAS, uk. 120x120x120 cm / BH
Bahan : - Saluran U Ditch uk. 120x120x120 cm bh 1.00 2,277,000 2,277,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 2,468,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 2,649,739.38
Harga/M' 2,208,116.15
25 SALURAN TERTUTUP (U Ditch ex MAS, uk. 30x40x120 cm + tutup) / BH

RAB - 050
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Bahan : - Saluran U Ditch uk. 30x40x120 cm bh 1.00 249,000 249,000.00


- Tutup saluran U.30 @ 60 cm HD bh 2.00 77,500 155,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 595,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 776,739.38
Harga/M' 647,282.81
26 SALURAN TERTUTUP (U Ditch ex MAS, uk. 60x80x120 cm + tutup) / BH
Bahan : - Saluran U Ditch uk. 60x80x120 cm bh 1.00 672,000 672,000.00
- Tutup saluran U.60 @ 60 cm HD bh 2.00 197,500 395,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 1,258,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 1,439,739.38
Harga/M' 1,199,782.81
27 SALURAN TERTUTUP (U Ditch ex MAS, uk. 100x100x120 cm + tutup) / BH
Bahan : - Saluran U Ditch uk. 100x100x120 cm bh 1.00 1,450,000 1,450,000.00
- Tutup saluran U.100 @ 60 cm HD bh 2.00 338,500 677,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 2,318,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 2,499,739.38
Harga/M' 2,083,116.15
28 SALURAN TERTUTUP (U Ditch ex MAS, uk. 120x120x120 cm + tutup) / BH
Bahan : - Saluran U Ditch uk. 120x120x120 cm bh 1.00 2,277,000 2,277,000.00
- Tutup saluran U.120 @ 60 cm HD bh 2.00 398,500 797,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 3,265,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 3,446,739.38
Harga/M' 2,872,282.81
29 SALURAN TERTUTUP (U Ditch ex MAS, uk. 140x140x120 cm + tutup) / BH
Bahan : - Saluran U Ditch uk. 140x140x120 cm bh 1.00 2,778,000 2,778,000.00
- Tutup saluran U.140 @ 60 cm HD bh 2.00 568,500 1,137,000.00
- Semen portland kg 91.600 1,300 119,080.00
- Pasir pasang m³ 0.275 265,125 72,909.38
- Pasir urug m³ 0.080 291,375 23,310.00
Jumlah Harga Bahan 4,106,989.38
Upah : - Pekerja Oh 1.500 75,000 112,500.00
- Tukang batu Oh 0.600 90,000 54,000.00
- Kepala tukang Oh 0.060 100,000 6,000.00
- Mandor Oh 0.075 110,000 8,250.00
Jumlah Upah Tenaga 180,750.00
Total harga/bh 4,287,739.38
Harga/M' 3,573,116.15

XI. PEK. PRASARANA LINGKUNGAN - PAGAR


1 Pek. Pagar beton pracetak, tinggi 1,60 m, tiap 1 M'
Bahan : - Panel beton pracetak 50x400x2130 lmbr 1.778 86,108 153,100.02
- Kolom beton pracetak 160x200x2750 btg 0.445 195,107 86,822.62
- Semen portland kg 4.890 1,300 6,357.00
- Pasir beton m³ 0.010 270,375 2,703.75
- Batu pecah / split 2/3 m³ 0.017 269,500 4,581.51
Jumlah Harga Bahan 248,983.39
Upah : - Pekerja Oh 0.375 75,000 28,125.00
- Tukang batu Oh 0.125 90,000 11,250.00
- Kepala tukang Oh 0.012 100,000 1,200.00
- Mandor Oh 0.019 110,000 2,090.00
Jumlah Upah Tenaga 42,665.00
Total harga/bh 291,648.39
Dibulatkan 291,640.00
2 Pek. Pagar beton pracetak, tinggi 2,00 m, tiap 1 M'

RAB - 051
ANALISA HARGA SATUAN PEKERJAAN, BERDASARKAN SNI

ANALISA HARGA BAHAN & UPAH HARGA SATUAN


NO. URAIAN PEKERJAAN SNI
kfsn sat hrg. sat. Total harga PEKERJAAN

Bahan : - Panel beton pracetak 50x400x2130 lmbr 2.223 86,108 191,418.08


- Kolom beton pracetak 160x200x2750 btg 0.445 195,107 86,822.62
- Semen portland kg 4.890 1,300 6,357.00
- Pasir beton m³ 0.010 270,375 2,703.75
- Batu pecah / split 2/3 m³ 0.017 269,500 4,581.51
Jumlah Harga Bahan 287,301.45
Upah : - Pekerja Oh 0.375 75,000 28,125.00
- Tukang batu Oh 0.125 90,000 11,250.00
- Kepala tukang Oh 0.012 100,000 1,200.00
- Mandor Oh 0.019 110,000 2,090.00
Jumlah Upah Tenaga 42,665.00
Total harga/bh 329,966.45
Dibulatkan 329,960.00
3 Pek. Pagar beton pracetak, tinggi 2,40 m, tiap 1 M'
Bahan : - Panel beton pracetak Primacon 40x2400x5 lmbr 2.500 104,740 261,850.00
- Kolom beton pracetak Primacon170x180x2600 btg 0.445 195,107 86,822.62
- Semen portland kg 4.890 1,300 6,357.00
- Pasir beton m³ 0.010 270,375 2,703.75
- Batu pecah / split 2/3 m³ 0.017 269,500 4,581.51
Jumlah Harga Bahan 357,733.37
Upah : - Pekerja Oh 0.375 75,000 28,125.00
- Tukang batu Oh 0.125 90,000 11,250.00
- Kepala tukang Oh 0.012 100,000 1,200.00
- Mandor Oh 0.019 110,000 2,090.00
Jumlah Upah Tenaga 42,665.00
Total harga/bh 400,398.37
Dibulatkan 400,390.00

RAB - 052