ASAHI KOKUSAI TECHNEION INDONESIA

PROJECT NAME : 400KTA NEW SWING PLANT HDPE, LLDPE AND MLLDPE
CLIENT : PT. INTI KARYA PERSADA TEHNIK
USER : PT. CHANDRA ASRI PETROCEMICALS
WORK TITLE : INSTRUMENT WORKS
WORK METHOD AND STATEMENT LIST
DATE : 21-Sep-18
IKPT APPROVAL
NO DESCRIPTION DOCUMENT NUMBER REVISION NO. TARGET SUBMISSION ACTUAL SUBMISSION IKPT REMARK
DATE STATUS

1 Work Method and Statement For Temporary Facility Installation NPE-SD-INC-WMS-AX4501-0001 0 25-Aug-18 30-Aug-18 05-Sep-18 Approved

2 Work Method and Statement For Scaffolding Installation NPE-SD-INC-WMS-AX4501-0002 1 14-Sep-18 18-Sep-18 20-Sep-18 Approved

3 Work Method and Statement For Calibration Instrument Equipment NPE-SD-INC-WMS-AX4501-0003 1 14-Sep-18 18-Sep-18 20-Sep-18 Approved

4 Work Method and Statement For Fabrication NPE-SD-INC-WMS-AX4501-0004 1 14-Sep-18 18-Sep-18 20-Sep-18 Approved

5 Work Method and Statement For Cable Way Installation NPE-SD-INC-WMS-AX4501-0005 1 14-Sep-18 18-Sep-18 20-Sep-18 Approved

6 Work Method and Statement For DCS Panel Installation NPE-SD-INC-WMS-AX4501-0006 0 1-Sep-18 1-Sep-18

7 Work Method and Statement For Instrument Package & Local Panel Installation NPE-SD-INC-WMS-AX4501-0007 0 1-Sep-18 1-Sep-18

8 Work Method and Statement For Junction Box Installation NPE-SD-INC-WMS-AX4501-0008 0 1-Sep-18 1-Sep-18

9 Work Method and Statement For Cable Pulling NPE-SD-INC-WMS-AX4501-0009 0 1-Sep-18 1-Sep-18

10 Work Method and Statement For Local Instrument Installation NPE-SD-INC-WMS-AX4501-0010 0 1-Sep-18 1-Sep-18

11 Work Method and Statement For Air Supply Piping Installation NPE-SD-INC-WMS-AX4501-0011 0 8-Sep-18

12 Work Method and Statement For Pressure Lead Piping/Tubing Installation NPE-SD-INC-WMS-AX4501-0012 0 8-Sep-18

13 Work Method and Statement For CCTV Installation NPE-SD-INC-WMS-AX4501-0013 0 8-Sep-18

14 Work Method and Statement For Analyzer Installation NPE-SD-INC-WMS-AX4501-0014 0 8-Sep-18

15 Work Method and Statement For Termination NPE-SD-INC-WMS-AX4501-0015 0 8-Sep-18

16 Work Method and Statement For Insulation Resistance & Continuity Test NPE-SD-INC-WMS-AX4501-0016 0 8-Sep-18

17 Work Method and Statement For Leak Test NPE-SD-INC-WMS-AX4501-0017 0 8-Sep-18

18 Work Method and Statement For Loop Test NPE-SD-INC-WMS-AX4501-0018 0 8-Sep-18

19 Work Method and Statement CCTV Relocation NPE-SD-INC-WMS-AX4501-0019 0 21-Sep-18