w.e.f. 1.4.2003
N.B. : 1. Provisions of plinth areas are for small to medium capacity projects. For
higher capacity mines, these areas may be revised upward as per specific
requirement.
2. For projects having life more than 20 years, plinth area rates for permanent
specifications of buildings to be considered.
3. For projects having life less than 20 years, plinth area rates for temporary
specifications of buildings to be considered.
4. Plinth area rates are based on BPE guidelines and circulated by Dy.CE(C),
CMPDI HQ vide letter No.CE/F-53/2021 dt.8th October,1982.
5. Plinth area rates are with reference to Cost Index 100 base at Delhi as on
1.10.76.
ANNEXURE-I
(A) After reviewing the cost estimates details for different types of workshop, as furnished by
the members, the following norms were accepted.
a) These rates include light to medium duty electrically operated cranes normally
installed in such workshop.
b) These rates include the cost of normal machine foundations as well as light to
medium duty floors.
c) These unit rates correspond to cost index 100 at Delhi as on 1.10.1976 and may be
suitably escalated in different areas.
NOTE : These norms have been approved by BPE as per their letter No.1/44/78 – BPE(C)
dated 2.3.81
General Note : For foundation in B.C. soil strata, the rates may be increased by 10% as given
under (A), (B) & (C) above.
ANNEXURE-II
CANTEEN
Note: Where the employees per shift are reasonably more than 1201, an additional
secondary canteen of suitable capacity commensurating with the no. of
employees may be provided.
ANNEXURE-III
LAMP ROOM
ANNEXURE-IV
GARAGES
1.
Sl.No. Categories of Officers Entitlement of office
accommodation
1. Officers drawing Rs. 2000/- & above PM (for 240 sft (22 sqm)
Officers of M1 & above grade)
2. Officers drawing Rs. 1100/- PM & above but less 120 sft (11 sqm)
than Rs.2000- pm. (for Officers in E5 to E3 grade)
3. Gazetted Officers drawing pay less than Rs. 1100/- 60 sft. (5.5 sqm.)
PM excluding section officer (For Officers in E1 &
E2 grade)
4. Section officers in the secretariat/attached offices 60 sft. (5.5 sqm.)
5. Technical staff such as draughtsman, Tracer & 60 sft. (5.5 sqm.)
estimators, etc.
6. Ministerial staff such as superintendent, Head 40 sft. (3.5 sqm.)
Clerks, Asstt. Clerks & Daftries
7. Ministerial staff such as Superintendent, Head 40 sft. (3.5 sqm.) plus
clerks, Asstt. Clerks & Daftries 10% of entitlement for
current records
A. CONCRETE PAVEMENT
Specifications :
a) 9” Stone boulder soling
b) 8” Loose and 6” Compact stone metalling
c) 6” P.C.C. (1:2:4) (3/4” gauge down metals)
Rate/m2 = Rs. 45/-
B. BITUMINOUS PAVEMENT
Specifications :
a) 9” Stone boulder soling
b) 8” Loose and 6” Compact stone metalling
c) 2” Thick pre mix bituminous carpet
Rate/m2 = Rs. 33/-
4. Sub-Station
- Conventional construction, brick work and RCC beam and slab frame.
- Clear height from floor to ceiling 4 M.
- RCC Louvers for proper ventilation.
- Ducts for electric cables of adequate size.
As on 1.10.1976 at Delhi
BUILDING PORTION
BUILDING PORTION
b) Internal
water
supply &
sanitary
install-
tions 4 10 5 15 12 1/2 12 1/2 12 1/2
c) External
services 5 5 5 5 5 5 5
d) Extra for
Power wiring
& plugs 4 4 - - - - -
1 Water Tanks :
i) Levelling Rs.1.50
ii) Internal roads & paths Rs.3.50
iii) Sewerage Rs.1.50
iv) Filtered water supply Rs.1.50
v) Storm water drains Rs.1.50
vi) Horticultural operations Rs.0.65
vii) Street lighting with incandescent lamp Rs.0.35
viii) LT distributions & HT sub-station Rs.2.60
-------------------
Rs.13.10/Sqm.
-------------------
D. Electrical Installations
1. Fans 2 3 4 5 Surface wiring to be
2. Light points 6 8 10 18 provided for internal
3. Light/Power 3 4 7 10 electrical
plugs installations.
____________________________________________________
Sl. Executives Pay Scales Entitlement of
No. Grade w.e.f.1.1.97 Quarters *
____________________________________________________
1 2 3 4
____________________________________________________
_______________________________________________________
AND
THEIR ENTITLEMENT OF QUARTERS
_________________________________________________
Sl. Category NCWA-VI Pay Entitlement
No. scales w.e.f of Quarter
1.7.1996
_________________________________________________
1. I 126.92-161.28 |
|
2. II 129.79-169.57 |
|
3. III 133.75-181.63 | M.Q.(Miner's
| Quarter)
4. IV 136.46-192.98 |
|
5. V 142.13-209.27 |
|
6. VI 148.34-234.20 |
|
_________________________________________________
_______________________________________________
CMPDI, RI-IV, Nagpur 23
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
2. A 166.40-283.58 B - Type
3. B 156.75-263.85 |
|
4. C 150.09-242.43 | M.Q.
| (Miners
5. D 144.85-218.47 | Quarter)
|
6. E 135.40-185.98 |
___________________________________________________
___________________________________________________
Sl. Category NCWA-VI Pay Entitlement *
No. scales w.e.f of Quarter
1.7.1996
___________________________________________________
2. A 4652-7802 B-Type
3. B 4317-7257 B-Type
4. C 3998-6528 B-Type
5. D 3698-5878 B-Type
6. E 3545-5111 B-Type
7. F 3506-4856 B-Type
8. G 3457-4663 A-Type
9. H 3384-4464 A-Type
______________________________________________________
____________________________________________________
CMPDI, RI-IV, Nagpur 25
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
2. I 3998-6528 B-Type
3. II 3698-5878 B-Type
____________________________________________________
____________________________________________________
CMPDI, RI-IV, Nagpur 26
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
1. I 127.63 |
|
2. II 130.37 |
|
3. III 133.77 |
|
4. IV 134.43 | M.Q. (Miner's
| Quarter)
5. V 139.14 |
|
6. V-A 139.82 |
|
___________________________________________________
MQ - 40% to 50%
A Type - 50% to 60%
B Type - 60% to 75%
C & D Type - 100%
RI.IV, NAGPUR
(2) Add for extra facilities such = Rs. 550/- at Cost Index
as cistern, fan & tank, per 100 at Delhi as on 1.10.76
unit of MQ.
i) Specifications
ii) Rate : a) For sandy & silty sub grade - Rs. 81/m
b) For clayey/BC soil sub grade - Rs. 102/m
B. MINOR STRATUM `A' ROAD 3.75m wide with 1.5m Shoulder on sides.
i) Specifications
ii) Rate : a) For sandy & silty sub grade - Rs. 57/m
b) For clayey/BC soil sub grade - Rs. 79/m
i) Specifications :
PUCCA SHOULDERS : 7.5cm moorum layer over 7.5cm stone metalling blinded
with moorum Brick edging on both sides.
ii) Rate : a) For sandy & silty sub grade - Rs. 108/m
b) For clayey/BC soil sub grade - Rs. 130/m
ii) Rate : a) For sandy & silty sub grade - Rs. 261/m
b) For clayey/BC soil sub grade - Rs. 316/m
RI.IV, NAGPUR
NOTE:
1. The above estimated cost per m length excludes the cost of Lithology, land, culverts,
Arboriculture, Embankment and bitumen carpetting.
2. The above cost is based on design standard for Haul road circulated by CMPDI HQ,
Ranchi and made applicable at RI.IV w.e.f. 19/9/89.
RI.IV, NAGPUR
NOTE : The above details are as per Technical Manual on " Guidelines for Planning,
Design and Construction of Haul road" prepared by CMPDI HQ, Ranchi (Year
2000).
N.B. 1. Rates are based on cost index 100 base at Delhi as on 1.10.76
2. For every one km length of road, 2 No. culverts shall be provided, out of
which one shall be RCC slab culvert and other shall be hume pipe culvert.
CENTRAL MINE PLANNING & DESIGN INSTITUTE LIMITED
RI.IV, NAGPUR
_________________________________________________________________
Sl.No. Type of Building Consumption
per day litre
__________________________________________________________________
9. Schools
______________________________________________________________________
S.No. Particulars Quantity Rate Per Remarks
_______________________________________________________________________
1. Intake well and raw water 8 hrs. 0.17 Litre B.P.E.
pump houses with suitable raw water
raw water drawal arrangement Pumping
rate
2. Raw water boosting pump - Market
(centrifugal type) HP
3. Water rising main - As per Annexure
4. New water treatment plant - 0.28 Litre
with aerator, chemical
house, clarifloculator,
rapid gravity filter,
chlorinator etc.
5. Ground water reservoir 1 1/2 hr. 0.65* Litre B.P.E.
after treatment plant clear
(for storage of clear water
water) pumping rate
6. Pressurized type water - 0.25 Litre
treatment plant.
7. Sedimentation tank 8 hrs. 0.65* Litre B.P.E.
inflow rate
ANNEXURE
CMPDI, RI-IV, Nagpur 41
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
B. G.I. PIPES
1 20 12.25
2 25 20.00
3 40 26.25
4 50 44.90
5 65 69.65
Reference – CPWD – 1974 DSOR
RI.IV, NAGPUR
HYDRAULIC TABLES FOR FLOW OF WATER IN PIPES
BASED ON HAZEN & WILLIAMS FORMULA
Hazen-William Formula
To determine the loss of head for any value of C, multiply the loss of head obtained by equation (2)
by a value of `K’, as follows :.
CMPDI, RI-IV, Nagpur 43
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
Or
hf = 100 LQ2/3d5 = 33.33 LQ2/d5
RI.IV, NAGPUR
RI.IV, NAGPUR
________________________________________________________________
Discharge Q Velocity V Loss of head hf
litre/min. metres/sec. metres/1000 m.
________________________________________________________________
76 0.155 0.62
95 0.195 0.94
111 0.235 1.32
133 0.271 1.74
151 0.311 2.23
189 0.390 3.39
227 0.466 4.72
265 0.545 6.30
303 0.622 8.10
341 0.701 10.00
379 0.777 12.20
454 0.932 17.10
530 1.086 22.80
606 1.244 29.10
681 1.402 36.10
757 1.557 44.00
833 1.713 52
909 1.869 62
984 2.024 72
1060 2.179 82
1136 2.334 93
1211 2.493 105
1287 2.645 117
1363 2.801 131
1514 3.112 160
1703 3.502 198
1893 3.893 240
________________________________________________________________
____________________________________________________
__________________________________________
Discharge Q Velocity V Loss of head hf
litre/sec. metres/sec. metres/1000 m.
___________________________________________
4.38 0.061 0.03
8.76 0.119 0.11
13.14 0.180 0.22
17.53 0.241 0.38
21.92 0.302 0.58
26.28 0.360 0.81
30.67 0.421 1.08
35.06 0.481 1.38
35.42 0.540 1.72
43.81 0.600 2.10
48.19 0.662 2.50
52.58 0.720 2.94
56.94 0.781 3.40
61.33 0.842 3.90
65.72 0.903 4.43
70.11 0.960 5.00
74.50 1.021 5.60
78.86 1.082 6.20
83.26 1.140 6.90
87.61 1.201 7.60
96.39 1.320 9.00
105.14 1.442 10.50
113.15 1.560 12.30
122.70 1.683 14.10
131.40 1.802 16.00
153.20 2.101 21.30
175.00 2.403 27.00
197.10 2.704 33.60
219.20 3.003 41.00
241.00 3.305 49.40
262.80 3.604 58.00
306.70 4.204 77.00
350.50 4.805 99.00
394.20 5.406 122.00
438.10 6.606 150.00
_______________________________________
_____________________________________________
Discharge Q Velocity V Loss of head hf
litre/sec. metres/sec. metres/1000 m.
_____________________________________________
_______________________________________________
Discharge Q Velocity V Loss of head hf
litre/sec. metres/sec. metres/1000 m.
_______________________________________________
(A) COLONY
RI.IV, NAGPUR
1. Construction Manpower
__________________________________________________________________
Sl. Work load Manpower Remarks
No. per year __________________________________
at CI 100 Dy.CE S.E Sr.EE/ A.E. E.A
(1.10.76) EE Overseer
__________________________________________________________________
1. Rs.15 lakhs - - - 1 2
2. Rs.30 lakhs - - 1 2 4
3. Rs.60 lakhs - 1 2 4 6
4. Rs.100 lakhs 1 2 4 8 10
and above
__________________________________________________________________
ANNEXURE-L
(c) For towns from 3000 to 12000 houses (15000 to 60000 population)
Sl.No. Amenity Area (Hectares)
1. Education – 1 4.05-6.07 (10.0-15.0 Acres)
2. Hospital – 1 3.24-4.05 (8.0-10.0 Acres)
3. Shopping 3.24-4.05 (8.0-10.0 Acres)
4. Open space and play ground 12.14-16.19 (30-40 Acres)
5. Community Centre 6.07-8.08 (15-20 Acres)
6. Miscellaneous 6.07-10.12 (15-25 Acres)
Total 34.81- 48.56 (86.120 Acres)
Note : Standards for areas for town level amenities given at (a), (b), (c) & (d) above are for
townships with maximum size in each range. For smaller towns, suitable reductions
in these area may be made.
Use Percentage
(a) Net residential area (Housing cluster) 65-70
(b) Amenities 18-15
(c) Circulation 17-15
Total 100
Use Percentage
(a) Residential area 55-60
(b) Amenities 25-22
(c) Roads 20-18
Total 100
No.of storeys Town upto 3000 Town having Towns having Remarks
houses 3000-12000 more than
houses 12000 houses
2 37-54 37-49 35-49 Township
(15-22 per Acre) (15-20 per Acre) (14-20 per density is
Acre) based on the
3 49-67 49-62 44-62 entire
(20-27 per Acre) (20-25 per Acre) (18-25 per developed
Acre) area of the
4 62-79 62-74 54-72 township
(25-32 per Acre) (25-30 per Acre) (22-29 per
Acre)
Range 37-62 37-62 35-62
Recommended (15-25 per Acre) (15-25 per Acre) (14-25 per
Acre)
APPENDIX – A.2
CMPDI, RI-IV, Nagpur 67
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
(Amount in Rs’000)
Sl. Particulars Total Year wise Phasing of Capital Reference
No. Capital Provision
Provi- I II III IV V
sion Yr. Yr. Yr. Yr. Yr.
1. A. Service Buildings App. A.2.1
B. Residential Buildings App. A.2.2
Sub Total
GRAND TOTAL
APPENDIX – A.2.1
B. EXCAVATION WORKSHOP
1.
2.
3. etc
SUB-TOTAL (B) :
C. E&M WORKSHOP
1.
2.
3. etc
SUB-TOTAL (C) :
E. STORES
1.
2.
3. etc
SUB-TOTAL (E) :
Appendix-A.2.1 contd….
G. EXPLOSIVE MAGAZINE
1. Building
2. Barbed wire Fencing with gate
SUB-TOTAL (G) :
H. STATUTORY BUILDINGS
1. Canteen( seater)
2. First Aid Centre
3. Rest Shelter
4. Training Centre/Group Training
Centre
5. Lavatories & Urinals
6. Security Room
7. Garage
8. Scooter/Cycle Shed
9. Peripheral barbed wire fencing
10. Cap. Lamp Room ( lamps)
11. ETC
SUB-TOTAL (H)
I. COMMUNITY BUILDING
1. Dispensary/11 Bedded Hospital
2. Worker’s Institute
3. Shopping Centre
4. Primary School
5. Senior Club (Officer’s Club)
6. Officer’s Rest House
7. Staff Rest House
8. Post Office
9. Bus Stops
10. ETC
SUB-TOTAL (I)
Appendix-A.2.1 contd….
APPENDIX – A.2.2
Note: 1) Unit cost of `C’ type quarter includes for cost of half garage.
2) About 20% of type quarters have been considered for Hostel Type accommodation.
APPENDIX – A.2.3
Note: Base at 100 at Nagpur as on 1.1.92 is equal to cost index 600 w.r.t. 100 base at Delhi as on
1.10.76.
APPENDIX – A.2.4
----------
Total 1.50
----------
Unit cost at Nagpur at CI 100 = 13.50
Appendix-A.2.4 contd….
APPENDIX - A.8.2
(Amount in Rs.000's)
__________________________________________________________________
Sl. Particulars Total Remarks
No. Cost
__________________________________________________________________
_______________
GRAND TOTAL :
________________
APPENDIX A.8.2.1
CMPDI, RI-IV, Nagpur 79
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
Specifications
Specifications
4. Tree Guards
APPENDIX A.8.2.2
PROJECT REPORT OF______________
CMPDI, RI-IV, Nagpur 81
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
Specifications
. PUCCA SHOULDERS :
SHOULDER:
Earth work & surface dressing
Appendix-A.8.2.2 contd….
CMPDI, RI-IV, Nagpur 82
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
3. TREE GUARDS
4. R.C.C DRAIN CROSSING SLAB
(153 x 61 x 7.5 cm)
5. Extra for poor/BC soil on item(2) @10%
SUB TOTAL
6. Contingencies 3%
TOTAL
7. Tax on works contracts @ 2%
8. GRAND TOTAL :
APPENDIX A.8.2.3
PROJECT REPORT OF______________
STATEMENT SHOWING ESTIMATED CAPITAL INVESTMENT
ON HAUL ROADS
(AT COST INDEX ______ IN ____ (____ HALF)
WIDTH
Shoulder
……… thick moorum and sand filling
Appendix-A.8.2.3 contd….
8. GRAND TOTAL :
APPENDIX A.8.2.4
PROJECT REPORT OF______________
CMPDI, RI-IV, Nagpur 85
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
Specifications
Specifications
- 15 cm thick cobble soling over 22.5 cm
moorum filling (Moorum filling in case
of BC soil/clayey soil)
- 15 cm thick WBM in 2 layers
- 2.5 cm thick premix surfacing with seal coat
PUCCA SHOULDERS :
7.5 cm moorum layer over
7.5 cm stone metalling blinded with moorum. Brick
edging on both sides
1 B. CULVERTS (7.50 m wide)
i) 4.57 m span R.C.C slab culvert
ii) 3.05 m span RCC slab culvert
iii) 1.83 m span R.C.C slab culvert
iv) 1.22 m span R.C.C slab culvert
v) 0.61 m diameter hume pipe culvert
2. Road side Pucca Drain – 30 cm x 45 cm
3. Tree guards
4. Extra Provision for poor/B.C. soil on
item 1 B only @ 10%
SUB TOTAL
5. Contingencies 3%
TOTAL
6. Tax on works contract @ 2%
7. GRAND TOTAL
APPENDIX A.8.3
PROJECT REPORT OF______________
SUMMARY OF ESTIMATED CAPITAL INVESTMENT
ON WATER SUPPLY & SEWERAGE
(Amount in Rs.000's)
APPENDIX A.8.3.1
PROJECT REPORT OF______________
CMPDI, RI-IV, Nagpur 88
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
a) mm dia. CI main Km
a) mm dia. CI main Km
b) Add 7.5% for saddle supports,
valves, bends, etc.
4. Overhead Storage Kl.
5. Water distribution
i) 80 mm dia. GI main Km
ii) 50 mm dia. GI main Km
iii) 40 mm dia. GI main Km
iv) Add 7.5% for saddle
supports,
valves, bends, etc.
Appendix-A.8.3.1 contd….
APPENDIX A.8.3.1
PROJECT REPORT OF______________
CMPDI, RI-IV, Nagpur 90
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
Appendix-A.8.3.1 contd….
APPENDIX A.8.3.2
PROJECT REPORT OF______________
STATEMENT SHOWING ESTIMATED CAPITAL INVESTMENT
ON COLONY SEWERAGE
APPENDIX A.8.3.3
PROJECT REPORT OF______________
a) mm dia CI main Km
Appendix-A.8.3.3 contd….
CMPDI, RI-IV, Nagpur 94
CIVIL ENGINEERING NORMS Rev. No. 0
w.e.f. 1.4.2003
APPENDIX A.8.3.4
PROJECT REPORT OF______________
STATEMENT SHOWING ESTIMATED CAPITAL INVESTMENT
ON INDUSTRIAL SEWERAGE
* These shall include the requirement of drains for approach road and service road
Say =
= ____________ LPM
= ____________ LPS
Say =
= ____________ LPM
= ____________ LPS
HEAD
HP CALCULATION
H.P. = = QH = (here Q in
75 Lit/Sec, H in mtr.)
1. GROUND BUNKER:
Upto 2000 te. : Rs.450 per tonne
2001 to 5000 te. : Rs.350 per tonne
Above 5000 te. : Rs.300 per tonne
The ground bunker (surge bunker or storage ground bunker) includes the bunker proper,
escape tunnel, reclaim tunnel upto ground surface including the Pent House, and Steel
Structures above the bunker (tripper/shuttle conveyor gantry and portal frames) as well
as Portal foundations.
2. Conveyor Gantries :
2.1 Single conveyor gantry (upto 10m. high trestles).
Ground conveyor structure includes conveyor and pucca walkways on both sides, fully
covered at the top and partially on both sides. This includes levelling upto 3 m. clear on
either side of the shed. Trestles, Drive Unit structures, take up structures, and foundations
have been included while working the unit rates of overhead conveyor gantries.
3. Transfer House :
Av. Unit Cost : Rs.50,000/-
4. Crusher House : For underground mine, for one no. medium capacity crusher.
Unit Cost : Rs.1,50,000/-
Total size = 25 m. x 5 m.
If visual examination or preliminary data indicate poor soil conditions at site, extra
provisions for strengthening the foundations and making proper bunker slopes, etc. shall be
made.
NOTES :
1. These rates are based on cost index 100 at Delhi as on 1.10.76 and shall be updated as per
prevalent cost index at site at the time of project report preparation.
2. These norms were worked out at RI.IV and informed to Dy.CE (C), CMPDI, HQ,
Ranchi for adoption by SE (Civil) of RI.IV vide letter No.RIN/CE-82/206 dt.
25.2.1983/1.3.1983.
2. Trestle
5. Surge Bunker
______________________________________________________________________
Sr. Description Unit Rate Remarks
No. in Rs.
______________________________________________________________________
c) Escape Tunnel Per Metre 3535 | Rates based
d) Straight Portion " 4646 | on standard
e) Circular Portion (14 m dia) " 5454 | drgs. of CHP
6. Feeder Breaker Crushing Arrangement
Unloading of Coal by 35 t capacity dumper
i) Retaining wall 7.64 m ht m 8500 1) The rate is
based on design
ii) Wing wall (2 Nos, - 97000 & detailed drgs.
length = 11 m each) for UKNI &
Kolarpimpri OC
CHP of WCL
iii) Earth work & Bituminous
topping in ramp portion 2) 25% and 50%
behind retaining wall extra in the
rates may be
a) 11 m long retaining wall No. 43600 taken in case of
(for 1 feeder breaker) unloading by 50t
and 85 t dumpers
b) 20 to 24 m long retaining No. 46500 respectively.
wall (for 2 feeder breaker)
c) 37 m long retaining wall No. 52000
(for 3 feeder breaker)
iv) Grizzly and supporting No. 36000
structures
______________________________________________________________________
Sr. Description Unit Rate Remarks
No. in Rs.
______________________________________________________________________
ii) Retaining wall having No. 3,00,000 The rate is based
10.7 m long main wall, on design & detai-
ht=7.5 m, with wing led drg. for
walls and earthen ramp Durgapur OB
with bituminous topping declaying Plant
of WCL
iii) Retaining wall having No. 2,50,000 Cost based on
8.0 m long main wall, cost index 1008
ht=13.40m with wing with reference
walls. 100 base at
Delhi as on
1.10.76. Based
on work order
of Ballarpur Sand
Stowing plant of WCL
8. Screening & Picking House without Hopper
a) With 2 Screen & Picking belts 2,15,758 Based on standard
drawings of CHP
b) With single Screen & single 1,71,818
Picking belts without Hopper
______________________________________________________________________
Sr. Description Unit Rate Remarks
No. in Rs.
______________________________________________________________________
10. Drive Houses/(Tandem drive)
of large sizes
______________________________________________________________________
Sr. Description Unit Rate Remarks
No. in Rs.
______________________________________________________________________
19. Control Cabin 14141
20. Wagon Hauler 32828
21. Ground sump for dust Cum. 650
suppression
22. Pump House for above Sqm. 550
23. Ground sump for fire Cum. 650
fighting
24. Pump House for above Sqm. 550
25. Sub Station Building Sqm. 550
26. Hard stand- for ground Sqm. 31 Haul road norms
stock of 35t cap.dumper
adopted. It is
Rs.46/Sqm for
85 t cap.dumper.
However it is
Rs.22/Sqm. for
Tipping Truck,
Front end loader
and dozer.
27. CHP Office Sqm. 446
28. House for Electro- Sqm. 550
magnetic separator
29. Add for foundations in
poor soil @ 10% of cost
I N D E X
-2-