Sie sind auf Seite 1von 2

CONSTRUCTIVE THINKING

FIDIC 2017 – AN INTRODUCTION

For users of engineering contracts globally, 2017 was an it both tortuous and risky. Some may see this as a positive
eventful year, with both NEC4 and FIDIC publishing new attribute, and it was to some extent the drafters’ intention,
editions of their contracts, albeit that the new FIDIC and yet a contract that cannot be readily streamlined or
editions only became available as the year was ending. simplified, nor modified or amended to suit the specific
However, whilst NEC4 was launched under the banner demands of a particular project – and FIDIC contracts are
“Evolution not Revolution” with emphasis placed on the fact intended for use on a vast array of different projects in very
that the new contract was merely a further iteration of the different locations – may render it a good deal less user-
predecessor contract, the same cannot be said of the FIDIC friendly.
second edition contracts (Red, Yellow and Silver), which
It will also feel a lot less user-friendly to those who are not
represent a clear departure from the previously widely-used
native English speakers. It is only available at present in the
and highly-respected first edition forms.
English language, and it is quite an arduous read for those
Firstly, there is the increase in size – the new FIDIC of us who have English as a first language. Another issue
contracts are 50% longer than the previous versions. for those from foreign jurisdictions, in particular civil
The additional word count has been necessitated in part by code jurisdictions, will be its length. Contracts in civil
a marked change of approach. The contract now includes code countries tend to be much shorter, because a large
a great deal more process, having evolved into more of a proportion of the conditions and requirements that apply to
project management tool, necessitating the application of the works are contained within the civil code. It therefore
time bars and other procedures. There is nothing wrong has always been a hard job to persuade parties from
with this approach; the ICE withdrew its own contracts civil code countries that a contract of the length of most
as part of a strategic approach “to promote what we see as standard forms is needed. FIDIC 2017 makes it that bit
a more collaborative approach to contract management which harder.
offers value for money to clients and the construction industry at
To give you a flavour of the level of prescription and
large”, an approach which involved endorsing the NEC suite,
detail, clause 3, dealing with the Engineer, runs to
which first pioneered the concept of contract as project
6 pages plus 3 charts whilst sub-clause 3.7 (Agreement
management tool rather than a mere record of the parties
or Determination) is a step-by-step guide to the procedures
rights and obligations.
the Engineer is required to undertake, involving 5 further
The new FIDIC contracts however lack the lightness of sub-sub-clauses. Doubtless the detail was inserted with
touch of the NEC suite. Whilst neither contract should the best of intentions – the stated aim of the new draft
be left in the drawer (because the intention is that they is “Improved Clarity and Certainty” – and this is achieved
should be used to actively manage the works), engineers by highly prescriptive provisions setting out exactly what
may require use of a small wheelbarrow to keep the new is expected. However, such detailed and prescriptive
FIDIC book, weighing in at nearly 200 pages (120 + pages drafting tends to suffer most from the law of unintended
of conditions, plus appendices), readily to hand on site. consequences. The more prescriptive the drafting, the more
There is much detail in the new FIDIC contract, with many risk there is that if you have overlooked something, then the
intertwined clauses, which will render attempts to amend assumption will be that you did not intend to deal with it
because you have prescribed everything else in such detail. There are a number of areas where those who are used to
At its most basic level, more words tend to give people the 1999 forms will find changes – design liability, insurance,
more to argue over. and the claims and disputes provisions. We shall be looking
at these in more detail in future articles.
There is an irony to this, as the contract drafters have
stated that the ‘core aim’ of the “Improved Clarity and It follows that the sheer complexity of the contract will
Certainty” is to reduce the risk of disagreements regarding only make it suitable for use on large projects. Even then,
interpretation of the contract terms. But take, for example, it requires a steep learning curve, as well as parties on both
the Engineer’s Determination at clause 3.7.2. The engineer sides with a high degree of sophistication and experience
is required to give a notice of his determination stating not to mention sufficient resources to be able to put in
that it is a notice, and describing the determination in place management procedures which will allow them
detail with reasons and detailed supporting particulars. to operate the 2017 contract without falling foul of the
The prescription in that one provision could lead to various sanctions, deeming provisions and time bars. If one
numerous arguments: disregards for a moment the 1999 Red, Yellow and Silver,
there is nothing sitting between the Green book –
■■ What if the Engineer serves a notice which complies with
intended for use on relatively straightforward projects –
the detailed requirements except that it fails to state it
and the new FIDIC 2017. And yet, the vast majority
is a notice? It is still a notice in practical terms, but the
of projects will fall somewhere in between those two
Contractor may argue that it did not believe the notice
extremes, so what are the options?
was a notice, and did not act upon it, because it did not
state it was a notice in accordance with the requirements It is possible to bolster the Green Book by liberal and
of the clause. This could in turn lead to delay claims if the judicious amendments to make it suitable for use on
notice has to be formally re-issued. projects up to a value of £20 million. For projects at the
£40/50 million level, the better option may be to continue
■■ What constitutes ‘detail’ when describing the
to use the 1999 forms, and that calls into question whether
determination? The parties may have differing views on
the 2017 forms are in any way an enhancement or refresh
whether enough detail has been given (this is a frequent
of the original first editions. They are a very different form,
occurrence in relation to supporting detail for e.g. final
which in all probability will result in them being used in a
account claims). Similarly the ‘detailed’ supporting
very different way.
particulars may lead to arguments about whether
the particulars have been provided, whether they Time will tell how quickly FIDIC 2017 will be adopted in
accompanied the Notice or not and whether they were practice. In the short to medium term, there is a real risk
sufficiently detailed. that the books will largely remain on the bookshelf, and the
industry will continue to use the familiar first edition forms
The drafting in the 1999 edition was much less likely to
with amendments, at least until there has been time for
engender these sorts of arguments, and the sheer number
participants to familiarise themselves fully with the forms.
of requirements means there is a danger that compliance
Even then, it is unlikely that FIDIC 2017 will prove suitable
with the contract procedures begins to distract from the
for use on a majority of projects.
actual works, particularly when you consider that there are
70 clauses which may necessitate the serving of notices. Rachel Chaplin and Ian Doig

Ian Doig
Partner
T  +44 (0)114 283 3356
M  +44 (0)796 855 8936
ian.doig@dlapiper.com

www.dlapiper.com
DLA Piper is a global law firm operating through various separate and distinct legal entities.
Further details of these entities can be found at www.dlapiper.com.
This publication is intended as a general overview and discussion of the subjects dealt with, and does not create a lawyer-client relationship. It is
not intended to be, and should not be used as, a substitute for taking legal advice in any specific situation. DLA Piper will accept no responsibility
for any actions taken or not taken on the basis of this publication. This may qualify as “Lawyer Advertising” requiring notice in some jurisdictions.
Prior results do not guarantee a similar outcome.

Copyright © 2018 DLA Piper. All rights reserved.  |  JAN18  |  3281986

Das könnte Ihnen auch gefallen