Beruflich Dokumente
Kultur Dokumente
ABSTRACT OF COST
Name of the Project: Purkot Gadhimai View Tower and Park Construction
S.N.
Description Unit Quantity Rate Amount
A. Eathworks
A.01. Earthwork in excavation in foundation etc. in hard clay or
gravel mixed sandy soils including dressing of sides,
timbering, ramming of bottom, lift of upto 1.5m and
disposal of upto 10m, all complete work.
m3 685.74 592.25 406,129.51
A.02. Providing and leveling with excavated or burrowed earth in
150mm layers including watering, ramming with 85%
compaction, consolidating, dressing etc., all complete
work.
m3 73.26 359.38 26,328.17
Sub-total (A) 432,457.68
B. Concreting Works
B.01. Providing and laying M20 concrete in substructure
including haulage upto 30m, all complete work. m3 10.61 17,073.05 181,145.06
B.02. Providing, laying, fixing, bending and binding TMT
reinforcement bars (Fe500) in position including necessary
binding wire, all complete work. MT 0.92 124,702.33 114,726.14
B.03. Centering and shuttering 19 mm thick commercial plywood
formwork for reinforced concrete elements as per drawings
including all necessary propping, shoring, removal of
formwork and hauling upto 30m, all complete work.
m2 42.58 1,192.33 50,769.41
Sub-total (B) 346,640.61
C. Soling/ Masonry Works
C.01. Providing and laying 250mm or thicker first class chimney
made brick masonry walls in 1:6 cement-sand mortar in the
sub-structure including haulage upto 30m all complete
m3 4.89 11,660.36 57,019.16
Sub-total (C) 57,019.16
D. Metal Works
D.01. Providing and laying 10mm steel plate in superstructure as kg 10526.968 219.67
Slab all complete 2,312,459.00
D.02. Providing and laying ISMB300 (IB1) in superstructure as kg 6202.456 219.67
Main Beam all complete 1,362,493.50
D.03. Providing and laying ISMB300 (IB2) in superstructure as kg 657.8 219.67
Landing Beam all complete 144,498.92
S.N.
Description Unit Quantity Rate Amount
D.04. Providing and laying ISMB300 (IB10 and IB11) in kg 4186 219.67
superstructure as Staircase Beam all complete 919,538.62
D.05. Providing and laying ISMC75 in superstructure as support kg 64.974 219.67
to cantilever all complete 14,272.83
D.06. Providing and laying Tubular Section (350x350x16) in kg 13104 219.67
superstructure as Column all complete 2,878,555.68
D.07. Providing and laying ISMC 150 in superstructure as kg 1275.456 219.67
Bracing all complete 280,179.41
D.08. Providing and laying ISMB 150 (as roof post) in kg 234 219.67
superstructure as Column all complete 51,402.78
D.09. Providing and laying ISMC 75 in superstructure as kg 900.354 219.67
Secondary Beam all complete 197,780.76
Sub-total (D) 8,161,181.50
E Roofing Works
E.01. Providing and laying MS tubular sections in trusses,
rafters, purlins and posts including welding up to the
required standards, nuts & bolts and two coats of red oxide
anti-corrosive paint and two coats of enamel paint of
approved quality and colour all complete
kg 1,695.06 256.35 434,528.63
E.02. Providing and fixing CGI sheets on the roof including self-
tapping screws, washers, etc. all complete m2 108.00 988.16 106,721.28
E.03. Providing and fixing CGI sheet ridge cap on the roof
including self-tapping screws, washers, etc. all complete
m 6.00 1,627.56 9,765.36
E.04. Providing, fabricating and fixing 24-gauge plain GI sheet
gutter on the roof including MS clamps, nut-bolts etc. all
complete m 40.00 1,181.39 47,255.60
Sub-total (E) 598,270.87
S.N.
Description Unit Quantity Rate Amount
F. Flooring Works
F.01. Providing and laying 1 layer flat brick soling including sand
blasting of the joints all complete m2 48.87 983.37 48,053.35
F.02. Providing and laying 75mm thick 1:3:6 cement-sand-
aggregate concrete in the foundation including haulage of
up to 10m all complete m2 23.87 953.55 22,757.42
F.03. Providing and laying 50mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including haulage of up to
10m all complete m2 25.00 846.79 21,169.75
F.04. Providing and laying 38mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including Neat Cement
Punning (NCP) finishing all complete m2 25.00 920.92 23,023.00
Sub-total (F) 115,003.52
G. Finishing Works
G.01. Providing and laying 20mm thick 1:4 cement-sand plaster
on the external walls all complete m2 6.76 504.26 3,406.78
G.02. Providing and laying 2 coats of weather coat paint over
one coat of primer on all metal works and wall of uniform
finishing all complete m2 136.72 259.86 35,527.51
Sub-total (F) 38,934.29
H. Miscellaneous Works
H.01. Providing and fixing Plate of 6mm thickness as tread of
staircase all complete kg 1,983.85 219.67 435,792.76
H.02. Providing Handrail and posts of appropriate size and
spacing along the staircase and top of the deck rm 749.35 4,554.93 3,413,236.79
Sub-total (G) 3,849,029.55
Total Cost of Civil Works (A+B+C+D+E+F+G+H) ###
H. Provisional Sum
H.01. Provison for insurance of works. PS 1 25,000.00 25,000.00
H.02. Provison for information hoarding board at site PS 1 8,000.00 8,000.00
H.03. Provisonal sum for unforseen works. PS 1 200,000.00 200,000.00
Total of Provisional Sum 233,000.00
Total Cost including Provisional Sum ###
S.N.
Description Unit Quantity Rate Amount
I. Contingencies
I.01. 5% Contingency for Construction Supervision 725,573.20
I.02. 10% Physical Contingency 1,451,146.40
Total of Contingencies 2,176,719.61
VAT @ 13% of Total Cost including Provisonal Sum and Contingencies 2,169,463.87
Remarks
Remarks
Remarks
Remarks
QUANTITY ESTIMATE OF CIVIL WORKS
VIEW TOWER
Plinth Level
Plinth Beam 4 3.294 0.229 0.305 0.918
Column 4 0.356 0.356 0.457 0.231
TOTAL 1.149 m3
S.N. Description Nos. Length Width Height Quantity Unit Remarks
First Floor
Beam 4 5.289 0.229 0.204 0.985
Column 4 0.3556 0.3556 2.743 1.388
Slab 1 38.440 0.152 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3
Second Floor
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3
Third Floor
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3
Roof Level
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3
B.02.
Plinth Level
Columns 128 2.377 1.578 480.259 16
Roof Level
Columns 128 4.663 1.578 942.092 16
Second Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
Slab
Horizontal 1 27.440 0.152 4.182
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Vertical 1 36.000 0.152 5.486
Stairs
Inclined 1 5.776 1.000 5.776
Horizontal 1 1.000 1.000 1.000
Vertical 2 6.776 0.355 4.811
Steps 15 1.000 0.250 3.750
TOTAL 60.495 m2
Third Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Slab
Horizontal 1 27.440 0.152 4.182
Vertical 1 36.000 0.152 5.486
Stairs
Inclined 1 5.776 1.000 5.776
Horizontal 1 1.000 1.000 1.000
Vertical 2 6.776 0.355 4.811
Steps 15 1.000 0.250 3.750
TOTAL 60.495 m2
Roof Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
Slab
Horizontal 1 27.440 0.152 4.182
Vertical 1 36.000 0.152 5.486
TOTAL 45.158 m2
First Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3
Second Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Third Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3
Ground Level
Columns 4 1.422 2.743 15.608
Walls 1 3.62 3.620
Beams 4 3.294 0.203 2.678
TOTAL 21.906 m2
Roof Level
Columns 4 1.422 2.743 15.608
Beams 4 3.294 0.203 2.678
Slab 1 5.5 5.5 30.250
TOTAL 48.536 m2
D.02.
I. VIEW TOWER
TOTAL
F.04.
Providing and laying 38mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including Neat
Cement Punning (NCP) finishing all complete 1 25.000
TOTAL
G Finishing Works
G.01. Providing and laying 20mm thick 1:4 cement-sand
plaster on the external walls all complete
Wall 4 5.63 0.3
TOTAL
S.N. Description Nos. Length Width Height
G.02. Providing and laying 2 coats of weather coat paint
over one coat of primer on all metal works and wall of
uniform finishing all complete
Wall
Metal Works
First Floor 1 15.54
Second Floor 1 15.54
Third Floor 1 15.54
Fourth Floor 1 15.54
Fifth Floor 1 22.63
Roof level 1 45.18
TOTAL
H Miscellaneous Works
H.01. Providing and fixing Plate of 6mm thickness as tread
of staircase all complete
90 1.2 0.3 0.006
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
H.02.
Providing Handrail and posts of appropriate size and
spacing along the staircase and top of the deck
Staircase
Handrail 15 24.45
Post 150 1.3
Deck
Handrail 12 10
Post 52 1.3
TOTAL
IVIL WORKS
32.000
2.640
651.100
685.740 m3
28.545 30%
14.625 30%
30.090
73.26 m3
4.332
2.523
2.183
1.573
10.611 m3
188.927 12
Quantity Unit Remarks
360.255 20
170.618 8
93.114 12
65.343 8
43.913 5%
922.170 kg
9.120
5.244
13.860
10.488
3.871 10%
42.583 m2
Quantity Unit Remarks
1.180
0.891
2.814
4.885 m3
535.37
535.37
535.37
535.37
5,956.19
2,429.30 30%
10,526.968 kg
804.080
804.080
804.080
804.080
1,554.800
1,431.34 30%
6,202.456 kg
101.200
101.200
101.200
101.200
101.200
151.80 30%
Quantity Unit Remarks
657.800 kg
644.000
644.000
644.000
644.000
644.000
966.00 30%
4,186.000 kg
49.980
14.99 30%
64.974 kg
2,016.000
2,016.000
2,016.000
2,016.000
2,016.000
3,024.00 30%
13,104.000 kg
196.224
196.224
196.224
196.224
196.224
294.34 30%
1,275.456 kg
Quantity Unit Remarks
180.000
54.00 30%
234.000 kg
35.700
471.240
185.640
207.77 30%
900.354 kg
112.992
60.360
49.840
65.504
1,015.200
391.17 30%
1,695.065 kg.
108.000
108.000 m2
Quantity Unit Remarks
6.000
6.000 m
40.000
40.000 m
16.000
7.866
25.000
48.866 m2
16.000
7.866
23.866 m2
25.000
25.000 m2
25.000
25.000 m2
6.756
6.756 m2
Quantity Unit Remarks
6.756
15.540
15.540
15.540
15.540
22.626
45.176
136.718 m2
1526.04
457.81 30%
1983.852 kg
366.75
195
120
67.6
749.35 rm
Summary of Rate Analysis
FY: 75/76
Final Rate
S.N. Description of Works Unit
NRs.
1 Earthwork in excavation in foundation etc. in hard clay or gravel mixed sandy soils
including dressing of sides, timbering, ramming of bottom, lift of upto 1.5m and disposal
of upto 10m. m3 592.25
2 Providing and leveling with excavated or burrowed earth in 150mm layers including
watering, ramming for compaction, consolidation, dressing etc. m3 359.38
3 Providing and laying M20 concrete in superstructure and substructure including haulage
upto 30m all complete. m3 17,073.05
4 Providing, laying, fixing, bending and binding reinforcement TMT (Fe500) in position
including all necessary binding wire all complete. MT 124,702.33
5 Centering and shuttering 19mm thick commercial plywood formwork for reinforced
concrete elements as per drawings including all necessary metal pipes and wooden
batons for propping and shoring, removal of formwork and hauling upto 30m all
complete
m2 1,192.33
6 Providing and laying first class chimney made brick masonry walls in 1:6 cement-sand
mortar in the sub-structure including preparation of mortar and haulage upto 30m all
complete m3 11,660.36
7 Providing and laying MS tubular sections in trusses, rafters, purlins and posts including
welding up to the required standards, nuts & bolts and two coats of red oxide anti-
corrosive paint and two coats of enamel paint of approved quality and colour all
complete
kg 256.35
8 Providing and fixing CGI sheet ridge cap on the roof including self-tapping screws,
washers, etc. all complete m 1,627.56
9 Providing, fabricating and fixing 24-gauge plain GI sheet gutter on the roof including MS
clamps, nut-bolts etc. all complete m 1,181.39
Providing and fixing 26 Gauge CGI sheets on the roof including self-tapping screws,
washers, etc all complete m2 988.16
11 Providing and laying 1 layer flat brick soling including sand blasting of the joints all
complete m2 983.37
12 Providing and laying 75mm thick 1:3:6 cement-sand-aggregate concrete in the
foundation including haulage up to 30m all complete m2 953.55
13 Providing and laying 50mm thick 1:2:4 cement-sand-aggregate concrete on the floor
including mixing and haulage up to 30m all complete m2 846.79
14 Providing and laying 38mm thick 1:2:4 cement-sand-aggregate screed on the floor
including 3mm thick neat cement punning (NCP) finishing all complete m2 920.92
15 Providing and laying 20mm thick 1:4 cement-sand plaster on the external walls all
complete m2 504.26
16 Providing and laying 2 coats of plastic emulsion paint over one coat of primer on internal
walls of uniform finishing all complete m2 259.86
17 Providing, fabricating and installing all metal angles/channels including primer, all
complete Kg 219.67
18 Providing, fabricating and installing 50 mm dia stainless steel vertical posts at 2 m c/c
distance in 38 mm dia same stainless steel Handrail and 3 layers 25 mm dia stainlesss
steel member with 2'-6" to 3'-0" height railingincluding paint of approved quality and
colour, all complete work.
Rm 4,554.93
Rate Analysis
FY: 75/76
A. EARTHWORKS
A.01. Earthwork in excavation in foundation etc. in hard clay or gravel mixed sandy soils including dressing of sides,
timbering, ramming of bottom, lift of upto 1.5m and disposal of upto 10m.
ANALYSIS FOR : 1 m3
Norms No. 11 B-1
A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF A 500.00
C. TOOLS & EQUIPMENTS QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF C 15.00
A.02. Providing and leveling with excavated or burrowed earth in 150mm layers including watering, ramming for
compaction, consolidation, dressing etc.
ANALYSIS FOR : 1 m3
TOTAL OF A 312.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
same site
1 Earth for backfilling - m3 - - material
TOTAL OF B -
TOTAL OF A 5,087.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 9,759.13
B.02. Providing, laying, fixing, bending and binding reinforcement TMT (Fe500) in position including all necessary binding
wire all complete.
ANALYSIS FOR : 1 MT
TOTAL OF A 18,180.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 90,256.81
ACTUAL RATE 108,436.81
15% CONTRACTOR'S PROFIT & OVERHEAD 16,265.52
124,702.33
ANALYSIS FOR : 10 m2
TOTAL OF A 4,876.30
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 5,491.83
ACTUAL RATE 10,368.13
15% CONTRACTOR'S PROFIT & OVERHEAD 1,555.22
11,923.35
TOTAL OF A 2,710.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 7,429.45
ACTUAL RATE 10,139.45
15% CONTRACTOR'S PROFIT & OVERHEAD 1,520.92
11,660.36
SAY RATE PER m3 11,660.36
D. ROOFING WORKS
D.01. Providing and laying MS tubular sections in trusses, rafters, purlins and posts including welding up to the required
standards, nuts & bolts and two coats of red oxide anti-corrosive paint and two coats of enamel paint of approved
ANALYSIS FOR : 59.34 kg
TOTAL OF A 5,170.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 8,057.46
D.03. Providing and fixing CGI sheet ridge cap on the roof including self-tapping screws, washers, etc. all complete
ANALYSIS FOR : 10 m
TOTAL OF A 3,655.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF A 3,655.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 6,617.98
D.04. Providing, fabricating and fixing 24-gauge plain GI sheet gutter on the roof including MS clamps, nut-bolts etc. all
complete (contd.)
D.05. Providing and fixing 26 Gauge CGI sheets on the roof including self-tapping screws, washers, etc all complete
ANALYSIS FOR : 10 m2
TOTAL OF A 1,760.25
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
E.01. Providing and laying 1 layer flat brick soling including sand blasting of the joints all complete
ANALYSIS FOR : 10 m2
TOTAL OF A 1,070.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 7,481.04
D.01. Providing and laying 75mm thick 1:3:6 cement-sand-aggregate concrete in the foundation including haulage up to 30m
all complete
ANALYSIS FOR : 10 m2
TOTAL OF A 2,542.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF A 2,675.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 4,688.43
D.03. Providing and laying 38mm thick 1:2:4 cement-sand-aggregate screed on the floor including 3mm thick neat cement
punning (NCP) finishing all complete
ANALYSIS FOR : 10 m2
TOTAL OF A 3,877.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 4,130.53
TOTAL OF A 24,335.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 19,514.00
F.04. Providing and laying 2 coats of plastic emulsion paint over one coat of primer on internal walls of uniform finishing all
complete
ANALYSIS FOR : 100 m2
TOTAL OF A 11,135.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 11,461.60
F. MISCELLANEOUS WORKS
I.03. Providing, fabricating and installing all metal angles/channels including primer, all complete
ANALYSIS FOR : 18.94 Kg
TOTAL OF A 1,099.56
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS
TOTAL OF B 2,518.32
Source: Dumre
Destination: Purkot
Truck Tractor
Paved Road Unpaved RoadAll
Rates (/kg/km): 0.012 0.019 0.066
Distance (km): 18.5 4 1
Rates per kg: 0.222 0.076 0.066
Total
Haulage Loading Unloading Transport
Rates Rates Rates Rates
Items From Bazar 0.364 0.2211 0.2208 0.8059 per kg
Items from River 528.00 0.2211 0.2208 528.4419 per cum
Weight Calculation:
Materials Unit in Kg
Bricks No. 1.15
19 mm Plywood sq.m 10.45
Aggregates cu.m 1,600.00
Note: 5% addition over district rates for items of which the weight cannot be determined
RATE ANALYSIS FOR COLLECTION OF MATERIALS
Aggregates
Works: Collection and sieving of gravel of size 5 mm to 70 mm including stacking within 10 m Unit :
hauling distance, all complete work. 1 cu.m
Spec. cl. No: 800
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.1A Unskilled md 2.00 625.00 1250.00 Plants Cost= 37.50
Sub total of A = 1250.00 Sub total of B = 0.00 Sub total of C = 37.50
Sub total of A +B + C = 1287.50 Unit Rate = 1287.50
Sand
Works: Collection, quarrying and sieving sand in local river, all complete work. Unit :
Spec. cl. No: 800 1 cu.m
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.3D Unskilled md 1.50 625.00 937.50 Plants Cost= 28.13
Sub total of A = 937.50 Sub total of B = 0.00 Sub total of C = 28.13
Sub total of A +B + C = 965.63 Unit Rate = 965.63
Stone
Works: Collection of rubble of required size including stacking within 110m hauling distance, all Unit :
complete work. 1 cu.m
Spec. cl. No: 800
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.2 Unskilled md 1.40 625.00 875.00 Plants Cost= 30.00
8.8 Unskilled md 0.20 625.00 125.00 << haulage up to 100 m
Sub total of A = 1000.00 Sub total of B = 0.00 Sub total of C = 30.00
Sub total of A +B + C = 1030.00 Unit Rate = 1030.00
DISTRICT RATES
References:
Approved District Rate of Tanahu, FY 75/76
FY: 75/76
Remarks
###
###
###
###
###
collection and
haulage
###
###
###
###
###
###
5% extra
###
###
5% extra
''
''
''
''
''
''
###
###
5% extra
Remarks
###
''
''
''
50 in packet
5% extra
###
###
###
###
###
###
###
###
###
''
###
Government of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit
Grant Management and Local Infrastructure
Jwagal, Lalitpur
Equipment Hourly Hire Rates
FY : 2075
Total Equipment Hire Rate= Hire Rate + Operator's Wage + Fuel Cost + Lubricants Cost
S. Power Fuel (Diesel) Lubricants (Grease) Fuel Lubricants Operator's DoR Hire Total Rate
Machine/ Equipment
No. (in HP) (in Ltr) (in Kg) Cost Cost Wage Rate per Hr
1 WHEEL LOADER (1.75 cu.m capacity) 160 =0.120 Ltr/HP= 19.20 =0.003 Kg/HP= 0.48 1,872.00 336.25 97.50 1000.00 3,305.75
2 EXCAVATOR 145 =0.125 Ltr/HP= 18.13 =0.003 Kg/HP= 0.44 1,767.19 304.73 97.50 1800.00 3,969.42
3 DOZER 120 =0.120 Ltr/HP= 14.40 =0.003 Kg/HP= 0.36 1,404.00 252.19 97.50 1800.00 3,553.69
4 MOTOR GRADER 135 =0.120 Ltr/HP= 16.20 =0.003 Kg/HP= 0.41 1,579.50 283.71 97.50 1600.00 3,560.71
5 THREE WHEELED ROLLER (12 ton) 47 =0.120 Ltr/HP= 5.64 =0.003 Kg/HP= 0.14 549.90 98.77 97.50 500.00 1,246.17
6 TRIPPER/ TRUCK (8 MT) 110 =0.120 Ltr/HP= 13.20 =0.003 Kg/HP= 0.33 1,287.00 231.17 97.50 853.00 2,468.67
7 TRACTOR 85 =0.120 Ltr/HP= 10.20 =0.003 Kg/HP= 0.26 994.50 178.63 97.50 300.00 1,570.63
8 CONCRETE MIXER 20 =0.120 Ltr/HP= 2.40 =0.003 Kg/HP= 0.06 234.00 42.03 97.50 500.00 873.53
9 BITUMEN BOILER (2 KL) 8 =0.120 Ltr/HP= 0.96 =0.003 Kg/HP= 0.02 93.60 16.81 97.50 180.00 387.91
10 GENERATOR (10 KVA) 13 =0.120 Ltr/HP= 1.56 =0.003 Kg/HP= 0.04 152.10 27.32 97.50 150.00 426.92
11 ASPHALT MIXER 20 =0.120 Ltr/HP= 2.40 =0.003 Kg/HP= 0.06 234.00 42.03 97.50 1,000.00 1,373.53
Government of Nepal
al Reconstruction Authority
el Project Implementation Unit
gement and Local Infrastructure
Jwagal, Lalitpur
pment Hourly Hire Rates
FY : 2075/76
DoR Code
068-
042-
031-
055-
094-
116-
123-
Market Rate
062-
054-
003-
Rates for Collection of Locally Available Materials
Manpower
S.N. Material Unit 3% Tools Total Amount Remarks
Type Unit Qty Rate Amount
Manual Collection of Sand, Gravel, Boulder and Aggregates:
1 Sand m3 Unskilled Labour md 3.00 700.00 2,100.00 63.00 2,163.00 DoR Norms No.: 8.3
2 Stone / Boulder m3 Unskilled Labour md 1.40 700.00 980.00 29.40 1,009.40 DoR Norms No.: 8.2
3 Gravel (63 mm down) m3 Unskilled Labour md 2.00 700.00 1,400.00 42.00 1,442.00 DoR Norms No.: 8.1
4 Gravel (40 mm) m3 Unskilled Labour md 3.00 700.00 2,100.00 63.00 2,163.00 DoR Norms No.: 8.2
5 Gravel (20 mm) m3 Unskilled Labour md 4.00 700.00 2,800.00 84.00 2,884.00 DoR Norms No.: 8.3
Rates for Transportation of Materials
Load/Unload
Loading rate= 0.1155 per kg
Unloading rate= 0.11 per kg
Density Transportation
SN Material Unit
(kg/m3) Rate (T)
1 Sand m3 1600 106.40
2 Stone / Boulder m3 1600 106.40
3 Gravel (70 mm down) m3 1750 116.38
Conversion Transportation
SN Material Unit
to Kg Rate (T)
1 Cement bag 50 26.45
2 Bitumen litre 1
3 Reinforcement kg 1 0.529
4 Plywood sq m 49.13 25.98977
5 Local softwood cu m 0
6 Plank 38 mm thickk cu m 0
7 Elastomeric bearing No. 0
8 compression m 0
9 110 HDPE pipe RM 2.5 1.3225
10 Filler materials cu m 0
11 GI pipe(100mm) RM 0
12 GI pipe(50mm) RM 0
13 Geotextile sq m 0.2 0.1058
14 Enamel' litre 0
15 Water per 4000l 735