Sie sind auf Seite 1von 54

Government of Nepal

Gandaki Province, Nepal


Bhanu Municipality, Ward No 9, Purkot, Tnahun

ABSTRACT OF COST

Name of the Project: Purkot Gadhimai View Tower and Park Construction

S.N.
Description Unit Quantity Rate Amount
A. Eathworks
A.01. Earthwork in excavation in foundation etc. in hard clay or
gravel mixed sandy soils including dressing of sides,
timbering, ramming of bottom, lift of upto 1.5m and
disposal of upto 10m, all complete work.
m3 685.74 592.25 406,129.51
A.02. Providing and leveling with excavated or burrowed earth in
150mm layers including watering, ramming with 85%
compaction, consolidating, dressing etc., all complete
work.
m3 73.26 359.38 26,328.17
Sub-total (A) 432,457.68
B. Concreting Works
B.01. Providing and laying M20 concrete in substructure
including haulage upto 30m, all complete work. m3 10.61 17,073.05 181,145.06
B.02. Providing, laying, fixing, bending and binding TMT
reinforcement bars (Fe500) in position including necessary
binding wire, all complete work. MT 0.92 124,702.33 114,726.14
B.03. Centering and shuttering 19 mm thick commercial plywood
formwork for reinforced concrete elements as per drawings
including all necessary propping, shoring, removal of
formwork and hauling upto 30m, all complete work.
m2 42.58 1,192.33 50,769.41
Sub-total (B) 346,640.61
C. Soling/ Masonry Works
C.01. Providing and laying 250mm or thicker first class chimney
made brick masonry walls in 1:6 cement-sand mortar in the
sub-structure including haulage upto 30m all complete
m3 4.89 11,660.36 57,019.16
Sub-total (C) 57,019.16
D. Metal Works
D.01. Providing and laying 10mm steel plate in superstructure as kg 10526.968 219.67
Slab all complete 2,312,459.00
D.02. Providing and laying ISMB300 (IB1) in superstructure as kg 6202.456 219.67
Main Beam all complete 1,362,493.50
D.03. Providing and laying ISMB300 (IB2) in superstructure as kg 657.8 219.67
Landing Beam all complete 144,498.92
S.N.
Description Unit Quantity Rate Amount
D.04. Providing and laying ISMB300 (IB10 and IB11) in kg 4186 219.67
superstructure as Staircase Beam all complete 919,538.62
D.05. Providing and laying ISMC75 in superstructure as support kg 64.974 219.67
to cantilever all complete 14,272.83
D.06. Providing and laying Tubular Section (350x350x16) in kg 13104 219.67
superstructure as Column all complete 2,878,555.68
D.07. Providing and laying ISMC 150 in superstructure as kg 1275.456 219.67
Bracing all complete 280,179.41
D.08. Providing and laying ISMB 150 (as roof post) in kg 234 219.67
superstructure as Column all complete 51,402.78
D.09. Providing and laying ISMC 75 in superstructure as kg 900.354 219.67
Secondary Beam all complete 197,780.76
Sub-total (D) 8,161,181.50
E Roofing Works
E.01. Providing and laying MS tubular sections in trusses,
rafters, purlins and posts including welding up to the
required standards, nuts & bolts and two coats of red oxide
anti-corrosive paint and two coats of enamel paint of
approved quality and colour all complete
kg 1,695.06 256.35 434,528.63
E.02. Providing and fixing CGI sheets on the roof including self-
tapping screws, washers, etc. all complete m2 108.00 988.16 106,721.28
E.03. Providing and fixing CGI sheet ridge cap on the roof
including self-tapping screws, washers, etc. all complete
m 6.00 1,627.56 9,765.36
E.04. Providing, fabricating and fixing 24-gauge plain GI sheet
gutter on the roof including MS clamps, nut-bolts etc. all
complete m 40.00 1,181.39 47,255.60
Sub-total (E) 598,270.87
S.N.
Description Unit Quantity Rate Amount
F. Flooring Works
F.01. Providing and laying 1 layer flat brick soling including sand
blasting of the joints all complete m2 48.87 983.37 48,053.35
F.02. Providing and laying 75mm thick 1:3:6 cement-sand-
aggregate concrete in the foundation including haulage of
up to 10m all complete m2 23.87 953.55 22,757.42
F.03. Providing and laying 50mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including haulage of up to
10m all complete m2 25.00 846.79 21,169.75
F.04. Providing and laying 38mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including Neat Cement
Punning (NCP) finishing all complete m2 25.00 920.92 23,023.00
Sub-total (F) 115,003.52
G. Finishing Works
G.01. Providing and laying 20mm thick 1:4 cement-sand plaster
on the external walls all complete m2 6.76 504.26 3,406.78
G.02. Providing and laying 2 coats of weather coat paint over
one coat of primer on all metal works and wall of uniform
finishing all complete m2 136.72 259.86 35,527.51
Sub-total (F) 38,934.29
H. Miscellaneous Works
H.01. Providing and fixing Plate of 6mm thickness as tread of
staircase all complete kg 1,983.85 219.67 435,792.76
H.02. Providing Handrail and posts of appropriate size and
spacing along the staircase and top of the deck rm 749.35 4,554.93 3,413,236.79
Sub-total (G) 3,849,029.55
Total Cost of Civil Works (A+B+C+D+E+F+G+H) ###

Electrification Cost = 5% of Civil Works = 679,926.86


Total Estimated Cost of Civil and Electrification Works = ###

H. Provisional Sum
H.01. Provison for insurance of works. PS 1 25,000.00 25,000.00
H.02. Provison for information hoarding board at site PS 1 8,000.00 8,000.00
H.03. Provisonal sum for unforseen works. PS 1 200,000.00 200,000.00
Total of Provisional Sum 233,000.00
Total Cost including Provisional Sum ###
S.N.
Description Unit Quantity Rate Amount
I. Contingencies
I.01. 5% Contingency for Construction Supervision 725,573.20
I.02. 10% Physical Contingency 1,451,146.40
Total of Contingencies 2,176,719.61

VAT @ 13% of Total Cost including Provisonal Sum and Contingencies 2,169,463.87

GRAND TOTAL = ###


FY: 75/76

Remarks
Remarks
Remarks
Remarks
QUANTITY ESTIMATE OF CIVIL WORKS
VIEW TOWER

S.N. Description Nos. Length Width Height Quantity Unit Remarks


A. Eathworks
A.01.
Earthwork in excavation in foundation
etc. in hard clay or gravel mixed sandy
soils including dressing of sides,
timbering, ramming of bottom, lift of upto
1.5m and disposal of upto 10m, all
complete work.

Footing F1 4 2.083 2.083 1.524 26.445


Tie Beam
Along Grid A 1 1.469 0.457 0.960 0.645
Along Grid B 1 1.469 0.457 0.960 0.645
Along Grid 1 1 1.469 0.457 0.960 0.645
Along Grid 2 1 1.469 0.457 0.960 0.645
TOTAL 29.025 m3
A.02. Providing and leveling with excavated or
burrowed earth in 150mm layers
including watering, ramming with 85%
compaction, consolidating, dressing etc.,
all complete work.

Below Ground Level =28.797-9.313 20.148


Below Plinth Level 13.323 0.457 6.091
TOTAL 26.24 m3
B. Concreting Works
B.01.
Providing and laying M20 concrete in
substructure including haulage upto 30m,
all complete work.
Ground Level
Footing F1 4 1.981 1.981 0.406 6.381
Trapazoidal Portion 4 1.280 1.280 0.167 1.094
Columns 4 0.356 0.356 0.958 0.484
Tie Beam 4 3.294 0.229 0.305 0.918
TOTAL 8.877 m3

Plinth Level
Plinth Beam 4 3.294 0.229 0.305 0.918
Column 4 0.356 0.356 0.457 0.231
TOTAL 1.149 m3
S.N. Description Nos. Length Width Height Quantity Unit Remarks
First Floor
Beam 4 5.289 0.229 0.204 0.985
Column 4 0.3556 0.3556 2.743 1.388
Slab 1 38.440 0.152 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3

Second Floor
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3

Third Floor
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3

Roof Level
Beam 4 5.2888 0.2286 0.204 0.985
Column 4 0.3556 0.3556 2.7432 1.388
Slab 1 38.44 0.1524 5.858
Stairs 1 1.809 1.809
Deduction -1 11.000 0.152 (1.676)
TOTAL 8.364 m3

B.02.

Providing, laying, fixing, bending and


binding TMT reinforcement bars (Fe500)
in position including necessary binding
wire, all complete work.
Ground Level
Footing F1 184 3.341 0.888 545.811 12

Columns 128 3.444 1.578 695.781 16

Ties 72 2.237 0.395 63.548 8


S.N. Description Nos. Length Width Height Quantity Unit Remarks
Tie Beams 4 3.294 3.555 46.851 0.65% Concrete

Stirrups 108 0.779 0.395 33.189 8

Laps and Chairs 69.259 5%


TOTAL 1,454.439 kg

Plinth Level
Columns 128 2.377 1.578 480.259 16

Ties 40 2.237 0.395 35.304 8

Plinth Beams 4 3.294 3.555 46.851 0.65% Concrete

Stirrups 108 0.779 0.395 33.189 8

Laps and Chairs 29.780 5%


TOTAL 625.383 kg
S.N. Description Nos. Length Width Height Quantity Unit Remarks
First Floor Level
Columns 128 4.663 1.578 942.092 16

Ties 184 2.237 0.395 162.399 8

Beam 4 5.289 7.658 161.997 1.2% Concrete

Stirrups 172 0.880 0.395 59.751 8

Slab 328.276 328.276


Stairs 1 213.036 213.036
Laps and Chairs 93.378 5%
TOTAL 1,960.928 kg

Second Floor Level


Columns 128 4.663 1.578 942.092 16

Ties 184 2.237 0.395 162.399 8

Beam 4 5.289 7.658 161.997 1.2% Concrete

Stirrups 172 0.880 0.395 59.751 8

Slab 328.276 328.276


Stairs 1 213.036 213.036
Laps and Chairs 93.378 5%
TOTAL 1,960.928 kg

Third Floor Level


Columns 128 4.663 1.578 942.092 16

Ties 184 2.237 0.395 162.399 8

Beam 4 5.289 7.658 161.997 1.2% Concrete

Stirrups 172 0.880 0.395 59.751 8

Slab 328.276 328.276


Stairs 1 213.036 213.036
Laps and Chairs 93.378 5%
TOTAL 1,960.928 kg

Roof Level
Columns 128 4.663 1.578 942.092 16

Ties 184 2.237 0.395 162.399 8

Beam 4 5.289 7.658 161.997 1.2% Concrete

Stirrups 172 0.880 0.395 59.751 8

Slab 328.276 328.276


Laps and Chairs 82.726 5%
TOTAL 1,737.240 kg
S.N. Description Nos. Length Width Height Quantity Unit Remarks
B.03.

Centering and shuttering 19 mm thick


commercial plywood formwork for
reinforced concrete elements as per
drawings including all necessary
propping, shoring, removal of formwork
and hauling upto 30m, all complete work.
Below Ground Level
Footing F1 4 7.925 0.406 12.883
Columns 4 1.422 0.958 5.449
Tie Beams
Sides 8 3.294 0.305 8.033
TOTAL 26.365 m2

Below Plinth Level


Columns 4 1.422 0.457 2.601
Plinth Beams
Sides 8 3.294 0.305 8.033
TOTAL 10.634 m2

First Floor Level


Columns 4 1.422 2.743 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
Slab
Horizontal 1 27.440 0.152 4.182
Vertical 1 36.000 0.152 5.486
Stairs
Inclined 1 5.776 1.000 5.776
Horizontal 1 1.000 1.000 1.000
Vertical 2 6.776 0.355 4.811
Steps 15 1.000 0.250 3.750
TOTAL 60.495 m2

Second Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
Slab
Horizontal 1 27.440 0.152 4.182
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Vertical 1 36.000 0.152 5.486
Stairs
Inclined 1 5.776 1.000 5.776
Horizontal 1 1.000 1.000 1.000
Vertical 2 6.776 0.355 4.811
Steps 15 1.000 0.250 3.750
TOTAL 60.495 m2

Third Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Slab
Horizontal 1 27.440 0.152 4.182
Vertical 1 36.000 0.152 5.486
Stairs
Inclined 1 5.776 1.000 5.776
Horizontal 1 1.000 1.000 1.000
Vertical 2 6.776 0.355 4.811
Steps 15 1.000 0.250 3.750
TOTAL 60.495 m2

Roof Level
Columns 4 1.4224 2.7432 15.608
Plinth Beams
Sides 8 5.289 0.356 15.046
Flat 4 5.289 0.229 4.836
Slab
Horizontal 1 27.440 0.152 4.182
Vertical 1 36.000 0.152 5.486
TOTAL 45.158 m2

C. Stone Soling/ Masonry Works


C.01.
Providing and laying Random rubble
masonry in cement sand
mortar[cement(1) : sand(4)] (manual
mixing) including scaffolding, curing,
preparation of mortar, lead etc., all
complete work.
below Tie beam 4 3.294 0.350 0.778 3.588
TOTAL 3.588 m3
Ground Floor
250mm thick wall at base 1 30.4 0.250 7.600
250mm thick wall for stairs 1.112 1.112
TOTAL 8.712 m3

First Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3

Second Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3
S.N. Description Nos. Length Width Height Quantity Unit Remarks

Third Floor
250mm thick wall for stairs 1.112 1.112
TOTAL 1.112 m3

C.02. Providing and laying stone soling in line


and level, all complete work.

Column Footing 4 1.981 1.981 0.200 3.140


Floor 1 36.000 0.200 7.200
TOTAL 10.340 m2
D. Finishing Works
D.01. Providing and laying 12.5mm thick 1:4
cement-sand plaster on the walls,
ceilings and other structures, all complete
work.
Plinth Level
Walls 4 3.294 0.231 3.044
TOTAL 3.044 m2

Ground Level
Columns 4 1.422 2.743 15.608
Walls 1 3.62 3.620
Beams 4 3.294 0.203 2.678
TOTAL 21.906 m2

First Floor Level


Columns 4 1.422 2.743 15.608
Walls 1 3.62 3.620
Slab and Stairs 1 5.5 5.5 30.250
Stairs Risers 1 1 3.000 3.000
Beams 4 3.294 0.203 2.678
TOTAL 55.156 m2

Second Floor Level


Columns 4 1.422 2.743 15.608
Walls 1 3.62 3.620
Beams 4 3.294 0.203 2.678
Slab and Stairs 1 5.5 5.5 30.250
Stairs Risers 1 1 3.000 3.000
TOTAL 55.156 m2

Third Floor Level


Columns 4 1.422 2.743 15.608
Walls 1 3.62 3.620
S.N. Description Nos. Length Width Height Quantity Unit Remarks
Beams 4 3.294 0.203 2.678
Slab and Stairs 1 5.5 5.5 30.250
Stairs Risers 1 1 3.000 3.000
TOTAL 55.156 m2

Roof Level
Columns 4 1.422 2.743 15.608
Beams 4 3.294 0.203 2.678
Slab 1 5.5 5.5 30.250
TOTAL 48.536 m2

D.02.

Providing and laying 2 coats of weather


coat paint over one coat of primer of
uniform finishing, all complete work.
TOTAL 238.954 m2
E. Flooring Works
E.01.

Providing and laying 75mm thick 1:3:6


cement-sand-aggregate concrete in the
foundation including haulage of up to
10m, all complete work.
Column Footing 4 1.9812 1.981 15.701
TOTAL 15.701 m2
E.02.

Providing and laying 50mm thick 1:2:4


cement-sand-aggregate concrete on the
floor including haulage of up to 10m, all
complete work.
Floor 1 38.400 38.400
TOTAL 38.400 m2
E.03.

Providing and laying 38mm thick 1:2:4


cement-sand-aggregate concrete on the
floor including Neat Cement Punning
finishing, all complete work.
Floors 5 36.000 180.000
TOTAL 180.000 m2
E.04.

Providing and laying a layer of sand on


the ground floor, all complete work.
Floors 1 36.000 36.000
S.N. Description Nos. Length Width Height Quantity Unit Remarks
TOTAL 36.000 m3
F. Miscellaneous Works
F.01. Providing, fabricating and installing 50
mm dia stainless steel vertical posts at 2
m c/c distance in 38 mm dia same
stainless steel Handrail and 3 layers 25
mm dia stainlesss steel member with 2'-
6" to 3'-0" height railingincluding paint of
approved quality and colour, all complete
work.
Handrail in Stairs 3 6.95 20.85
3 5.11 15.33
Safety Railing on each floors 3 23.4 70.2
TOTAL 106.38 m
QUANTITY & COST ESTIMATE - CIVIL WORKS

I. VIEW TOWER

S.N. Description Nos. Length Width Height


A. Eathworks
A.01.
Earthwork in excavation in foundation etc. in hard clay
or gravel mixed sandy soils including dressing of
sides, timbering, ramming of bottom, lift of upto 1.5m
and disposal of upto 10m, all complete work.
Footing F1 4 2.000 2.000 2.000
Wall Footing 4 3.000 0.550 0.400
Site levelling From Software Calculation
TOTAL
A.02.
Providing and leveling with excavated or burrowed
earth in 150mm layers including watering, ramming
with 85% compaction, consolidating, dressing etc.
Below Ground Level 1 21.958
From Ground Level to Plinth Level 1 5.000 5.000 0.45
Site levellingFrom Software Calculation
TOTAL
B. Concreting Works
B.01. Providing and laying 1:1.5:3 cement-sand-aggregate
concrete in superstructure including haulage upto
30m all complete
Below Ground Level
Footing F1
Rectangular Portion 4 1.900 1.900 0.300
Trapazoidal Portion 4 1.450 1.450 0.300
Columns 4 0.630 0.630 1.375
Tie Beams 4 4.37 0.300 0.300
TOTAL
B.02. Providing, laying, fixing, bending and binding
reinforcement TOR 40 (Fe415) in position including all
necessary binding wire all complete
Footing F1 112 1.900 0.888
S.N. Description Nos. Length Width Height
Columns 32 4.565 2.466
184 2.350 0.395
Tie Beams 24 4.370 0.888
144 1.150 0.395
Laps and Chairs
TOTAL
B.03.
Centering and shuttering 12mm thick waterproof
plywood formwork for reinforced concrete elements as
per drawings including all necessary propping,
shoring, removal of formwork and hauling upto 30m
all complete
Footing F1 4 7.600 0.300
Wall Footing 4 8.740 0.150
Columns 4 2.520 1.375
Tie Beams 4 8.740 0.300
Supports and Wood Fixtures
TOTAL
S.N. Description Nos. Length Width Height
C. Brick Masonry Works
C.01. Providing and laying 250mm or thicker first class
chimney made brick masonry walls in 1:6 cement-
sand mortar in the sub-structure including haulage
upto 30m all complete
Wall Footing 4 4.370 0.450 0.150
4 4.370 0.340 0.150
4 4.370 0.230 0.700
TOTAL
D. Metal Works
Providing and laying 10mm steel plate in
D.01.
superstructure as Slab all complete
First Floor 1 6.820
Second Floor 1 6.820
Third Floor 1 6.820
Fourth Floor 1 6.820
Fifth Floor 1 75.875
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
Providing and laying ISMB300 (IB1) in superstructure
D.02.
as Main Beam all complete
First Floor 4 4.370
Second Floor 4 4.370
Third Floor 4 4.370
Fourth Floor 4 4.370
Fifth Floor 4 8.450
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
Providing and laying ISMB300 (IB2) in superstructure
D.03.
as Landing Beam all complete
First Floor 2 1.100
Second Floor 2 1.100
Third Floor 2 1.100
Fourth Floor 2 1.100
Fifth Floor 2 1.100
Connections, Stiffner Plates, Bearing Plates and Base
Plates
S.N. Description Nos. Length Width Height
TOTAL
Providing and laying ISMB300 (IB10 and IB11) in
D.04.
superstructure as Staircase Beam all complete
First Floor 4 3.500
Second Floor 4 3.500
Third Floor 4 3.500
Fourth Floor 4 3.500
Fifth Floor 4 3.500
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
Providing and laying ISMC75 in superstructure as
D.05.
support to cantilever all complete
4 1.750
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL

Providing and laying Tubular Section (350x350x16) in


D.06.
superstructure as Column all complete
First Floor 4 3.000
Second Floor 4 3.000
Third Floor 4 3.000
Fourth Floor 4 3.000
Fifth Floor 4 3.000
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
Providing and laying ISMC 150 in superstructure as
D.07.
Bracing all complete
First Floor 2 5.840
Second Floor 2 5.840
Third Floor 2 5.840
Fourth Floor 2 5.840
Fifth Floor 2 5.840
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
S.N. Description Nos. Length Width Height
Providing and laying ISMB 150 (as roof post) in
D.08.
superstructure as Column all complete
4 3.000
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
Providing and laying ISMC 75 in superstructure as
D.09.
Secondary Beam all complete
Roof Level 1 5.000
Fifth Floor
8 8.250
16 1.625
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
E. Roofing Works
E.01.
Providing and laying MS tubular sections in trusses,
rafters, purlins and posts including welding up to the
required standards, nuts & bolts and two coats of red
oxide anti-corrosive paint and two coats of enamel
paint of approved quality and colour all complete
Truss T-1
Top Rafters, ISNB 65M 4 4.400
Bottom Chord, ISNB 50M 4 3.000
Vertical Members, ISNB 40M 4 3.500
Horizontal Members, ISNB 40M 4 4.600
Purlins, 50.8x50.8x2.5 4 56.400
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
E.02.
Providing and fixing CGI sheets on the roof including
self-tapping screws, washers, etc. all complete
Roof 4 27.000
TOTAL
E.03. Providing and fixing CGI sheet ridge cap on the roof
including self-tapping screws, washers, etc. all
complete
S.N. Description Nos. Length Width Height
Roof 4 1.500
TOTAL
E.04. Providing, fabricating and fixing 24-gauge plain GI
sheet gutter on the roof including MS clamps, nut-
bolts etc. all complete
Roof 4 10.000
TOTAL
F Flooring Works
F.01. Providing and laying 1 layer flat brick soling including
sand blasting of the joints all complete
Footing F1 4 2.000 2.000
Wall Footing 4 4.370 0.450
Floor 1 25.000
TOTAL
F.02. Providing and laying 75mm thick 1:3:6 cement-sand-
aggregate concrete in the foundation including
haulage of up to 10m all complete
Footing F1 4 2.000 2.000
Wall Footing 4 4.370 0.450
TOTAL
F.03. Providing and laying 50mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including haulage of
up to 10m all complete
Floor 1 25.000

TOTAL
F.04.
Providing and laying 38mm thick 1:2:4 cement-sand-
aggregate concrete on the floor including Neat
Cement Punning (NCP) finishing all complete 1 25.000
TOTAL
G Finishing Works
G.01. Providing and laying 20mm thick 1:4 cement-sand
plaster on the external walls all complete
Wall 4 5.63 0.3
TOTAL
S.N. Description Nos. Length Width Height
G.02. Providing and laying 2 coats of weather coat paint
over one coat of primer on all metal works and wall of
uniform finishing all complete
Wall
Metal Works
First Floor 1 15.54
Second Floor 1 15.54
Third Floor 1 15.54
Fourth Floor 1 15.54
Fifth Floor 1 22.63
Roof level 1 45.18

TOTAL
H Miscellaneous Works
H.01. Providing and fixing Plate of 6mm thickness as tread
of staircase all complete
90 1.2 0.3 0.006
Connections, Stiffner Plates, Bearing Plates and Base
Plates
TOTAL
H.02.
Providing Handrail and posts of appropriate size and
spacing along the staircase and top of the deck
Staircase
Handrail 15 24.45
Post 150 1.3
Deck
Handrail 12 10
Post 52 1.3
TOTAL
IVIL WORKS

Quantity Unit Remarks

32.000
2.640
651.100
685.740 m3

28.545 30%
14.625 30%
30.090
73.26 m3

4.332
2.523
2.183
1.573
10.611 m3

188.927 12
Quantity Unit Remarks
360.255 20
170.618 8
93.114 12
65.343 8
43.913 5%
922.170 kg

9.120
5.244
13.860
10.488
3.871 10%
42.583 m2
Quantity Unit Remarks

1.180
0.891
2.814
4.885 m3

535.37
535.37
535.37
535.37
5,956.19

2,429.30 30%
10,526.968 kg

804.080
804.080
804.080
804.080
1,554.800

1,431.34 30%
6,202.456 kg

101.200
101.200
101.200
101.200
101.200

151.80 30%
Quantity Unit Remarks
657.800 kg

644.000
644.000
644.000
644.000
644.000

966.00 30%
4,186.000 kg

49.980

14.99 30%
64.974 kg

2,016.000
2,016.000
2,016.000
2,016.000
2,016.000

3,024.00 30%
13,104.000 kg

196.224
196.224
196.224
196.224
196.224

294.34 30%
1,275.456 kg
Quantity Unit Remarks

180.000

54.00 30%
234.000 kg

35.700

471.240
185.640

207.77 30%
900.354 kg

112.992
60.360
49.840
65.504
1,015.200

391.17 30%
1,695.065 kg.

108.000
108.000 m2
Quantity Unit Remarks
6.000
6.000 m

40.000
40.000 m

16.000
7.866
25.000
48.866 m2

16.000
7.866
23.866 m2

25.000

25.000 m2

25.000
25.000 m2

6.756
6.756 m2
Quantity Unit Remarks

6.756

15.540
15.540
15.540
15.540
22.626
45.176

136.718 m2

1526.04

457.81 30%
1983.852 kg

366.75
195

120
67.6
749.35 rm
Summary of Rate Analysis
FY: 75/76
Final Rate
S.N. Description of Works Unit
NRs.
1 Earthwork in excavation in foundation etc. in hard clay or gravel mixed sandy soils
including dressing of sides, timbering, ramming of bottom, lift of upto 1.5m and disposal
of upto 10m. m3 592.25
2 Providing and leveling with excavated or burrowed earth in 150mm layers including
watering, ramming for compaction, consolidation, dressing etc. m3 359.38
3 Providing and laying M20 concrete in superstructure and substructure including haulage
upto 30m all complete. m3 17,073.05
4 Providing, laying, fixing, bending and binding reinforcement TMT (Fe500) in position
including all necessary binding wire all complete. MT 124,702.33
5 Centering and shuttering 19mm thick commercial plywood formwork for reinforced
concrete elements as per drawings including all necessary metal pipes and wooden
batons for propping and shoring, removal of formwork and hauling upto 30m all
complete
m2 1,192.33
6 Providing and laying first class chimney made brick masonry walls in 1:6 cement-sand
mortar in the sub-structure including preparation of mortar and haulage upto 30m all
complete m3 11,660.36
7 Providing and laying MS tubular sections in trusses, rafters, purlins and posts including
welding up to the required standards, nuts & bolts and two coats of red oxide anti-
corrosive paint and two coats of enamel paint of approved quality and colour all
complete
kg 256.35
8 Providing and fixing CGI sheet ridge cap on the roof including self-tapping screws,
washers, etc. all complete m 1,627.56
9 Providing, fabricating and fixing 24-gauge plain GI sheet gutter on the roof including MS
clamps, nut-bolts etc. all complete m 1,181.39
Providing and fixing 26 Gauge CGI sheets on the roof including self-tapping screws,
washers, etc all complete m2 988.16
11 Providing and laying 1 layer flat brick soling including sand blasting of the joints all
complete m2 983.37
12 Providing and laying 75mm thick 1:3:6 cement-sand-aggregate concrete in the
foundation including haulage up to 30m all complete m2 953.55
13 Providing and laying 50mm thick 1:2:4 cement-sand-aggregate concrete on the floor
including mixing and haulage up to 30m all complete m2 846.79
14 Providing and laying 38mm thick 1:2:4 cement-sand-aggregate screed on the floor
including 3mm thick neat cement punning (NCP) finishing all complete m2 920.92
15 Providing and laying 20mm thick 1:4 cement-sand plaster on the external walls all
complete m2 504.26
16 Providing and laying 2 coats of plastic emulsion paint over one coat of primer on internal
walls of uniform finishing all complete m2 259.86
17 Providing, fabricating and installing all metal angles/channels including primer, all
complete Kg 219.67
18 Providing, fabricating and installing 50 mm dia stainless steel vertical posts at 2 m c/c
distance in 38 mm dia same stainless steel Handrail and 3 layers 25 mm dia stainlesss
steel member with 2'-6" to 3'-0" height railingincluding paint of approved quality and
colour, all complete work.
Rm 4,554.93
Rate Analysis
FY: 75/76

A. EARTHWORKS
A.01. Earthwork in excavation in foundation etc. in hard clay or gravel mixed sandy soils including dressing of sides,
timbering, ramming of bottom, lift of upto 1.5m and disposal of upto 10m.
ANALYSIS FOR : 1 m3
Norms No. 11 B-1
A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Unskilled 0.80 person 625.00 500.00

TOTAL OF A 500.00
C. TOOLS & EQUIPMENTS QUANTITY UNIT RATE AMOUNT REMARKS

1 3% of A 1.00 LS 15.00 15.00

TOTAL OF C 15.00

ACTUAL RATE 515.00


15% CONTRACTOR'S PROFIT & OVERHEAD 77.25
592.25

SAY RATE PER m3 592.25

A.02. Providing and leveling with excavated or burrowed earth in 150mm layers including watering, ramming for
compaction, consolidation, dressing etc.
ANALYSIS FOR : 1 m3

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Unskilled 0.50 person 625.00 312.50

TOTAL OF A 312.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

same site
1 Earth for backfilling - m3 - - material

TOTAL OF B -

ACTUAL RATE 312.50


15% CONTRACTOR'S PROFIT & OVERHEAD 46.88
359.38
SAY RATE PER m3 359.38
B. CONCRETING WORKS
B.01. Providing and laying M20 concrete in superstructure and substructure including haulage upto 30m all complete.
ANALYSIS FOR : 1 m3

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 0.80 person 890.00 712.00


2 Unskilled 7.00 person 625.00 4,375.00

TOTAL OF A 5,087.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Cement 0.40 MT 15,205.90 6,082.36


2 20mm down aggregate 0.57 m 3
3,275.64 1,867.12
3 10mm down aggregate 0.29 m3 2,438.54 707.18
4 Sand 0.425 m 3
2,594.07 1,102.48

TOTAL OF B 9,759.13

ACTUAL RATE 14,846.13


15% CONTRACTOR'S PROFIT & OVERHEAD 2,226.92
17,073.05

SAY RATE PER m3 17,073.05

B.02. Providing, laying, fixing, bending and binding reinforcement TMT (Fe500) in position including all necessary binding
wire all complete.
ANALYSIS FOR : 1 MT

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 12.00 person 890.00 10,680.00


2 Unskilled 12.00 person 625.00 7,500.00

TOTAL OF A 18,180.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Re-bars 1.05 MT 85,075.00 89,328.75


2 GI Binding Wires 10.00 kg 92.81 928.06

TOTAL OF B 90,256.81
ACTUAL RATE 108,436.81
15% CONTRACTOR'S PROFIT & OVERHEAD 16,265.52
124,702.33

SAY RATE PER MT 124,702.33


B.03. Centering and shuttering 19mm thick commercial plywood formwork for reinforced concrete elements as per drawings
including all necessary metal pipes and wooden batons for propping and shoring, removal of formwork and hauling
upto 30m all complete

ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 2.67 person 890.00 2,376.30


2 Unskilled 4.00 person 625.00 2,500.00

TOTAL OF A 4,876.30
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Plywood 1.65 m2 1,482.54 2,446.19


2 Wood 0.039 m3 51,597.38 2,012.30
3 Metal Props 0.40 nos. 1,940.81 776.32
4 Nails 2.50 kg 102.81 257.01

TOTAL OF B 5,491.83
ACTUAL RATE 10,368.13
15% CONTRACTOR'S PROFIT & OVERHEAD 1,555.22
11,923.35

SAY RATE PER m2 1,192.33

C. BRICK MASONRY WORKS


C.01. Providing and laying first class chimney made brick masonry walls in 1:6 cement-sand mortar in the sub-structure
including preparation of mortar and haulage upto 30m all complete3
ANALYSIS FOR : 1 m

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 1.50 person 890.00 1,335.00


2 Unskilled 2.20 person 625.00 1,375.00

TOTAL OF A 2,710.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Bricks 418 nos. 13.43 5,612.40


2 Cement 0.069 MT 15,205.90 1,049.21
3 Sand 0.296 m3 2,594.07 767.84

TOTAL OF B 7,429.45
ACTUAL RATE 10,139.45
15% CONTRACTOR'S PROFIT & OVERHEAD 1,520.92
11,660.36
SAY RATE PER m3 11,660.36
D. ROOFING WORKS
D.01. Providing and laying MS tubular sections in trusses, rafters, purlins and posts including welding up to the required
standards, nuts & bolts and two coats of red oxide anti-corrosive paint and two coats of enamel paint of approved
ANALYSIS FOR : 59.34 kg

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 3.00 person 890.00 2,670.00


2 Unskilled 4.00 person 625.00 2,500.00

TOTAL OF A 5,170.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 MS tubes 62.31 kg 115.50 7,196.46


2 Nut-Bolts 5.0 nos. 31.50 157.50
3 Red Oxide Paint 1.0 LS 294.00 294.00
4 Enamel Paint 1.0 LS 409.50 409.50

TOTAL OF B 8,057.46

ACTUAL RATE 13,227.46


15% CONTRACTOR'S PROFIT & OVERHEAD 1,984.12
15,211.58

SAY RATE PER kg 256.35

D.03. Providing and fixing CGI sheet ridge cap on the roof including self-tapping screws, washers, etc. all complete
ANALYSIS FOR : 10 m

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 2.00 person 890.00 1,780.00


2 Unskilled 3.00 person 625.00 1,875.00

TOTAL OF A 3,655.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Ridge Cover 12.00 m 840.00 10,080.00


2 2" Self-Tapping Screws 85 nos. 4.18 355.22
3 Washer 85 nos. 0.74 62.48
TOTAL OF B 10,497.69
ACTUAL RATE 14,152.69
15% CONTRACTOR'S PROFIT & OVERHEAD 2,122.90
16,275.59

SAY RATE PER m 1,627.56


D.04. Providing, fabricating and fixing 24-gauge plain GI sheet gutter on the roof including MS clamps, nut-bolts etc. all
complete
ANALYSIS FOR : 10 m

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 2.00 person 890.00 1,780.00


2 Unskilled 3.00 person 625.00 1,875.00

TOTAL OF A 3,655.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 24-Gauge Plain GI Sheet 11.40 m2 494.98 5,642.73


2 MS Clamps 11.21 kg 87.00 975.25

TOTAL OF B 6,617.98
D.04. Providing, fabricating and fixing 24-gauge plain GI sheet gutter on the roof including MS clamps, nut-bolts etc. all
complete (contd.)

ACTUAL RATE 10,272.98


15% CONTRACTOR'S PROFIT & OVERHEAD 1,540.95
11,813.93

SAY RATE PER m 1,181.39

D.05. Providing and fixing 26 Gauge CGI sheets on the roof including self-tapping screws, washers, etc all complete
ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 1.10 person 890.00 979.00


2 Unskilled 1.25 person 625.00 781.25

TOTAL OF A 1,760.25
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 CGI Sheet 26 Gauge 12.00 m2 415.70 4,988.36


2 8mm nut bolt 30.00 nos. 30.00 900.00
3 J hook 25.0 nos. 36.23 905.63
4 Bitumen Washer 55.0 nos. 0.70 38.50
TOTAL OF B 6,832.48

ACTUAL RATE 8,592.73


15% CONTRACTOR'S PROFIT & OVERHEAD 1,288.91
9,881.64

SAY RATE PER m2 988.16


D. FLOORING WORKS

E.01. Providing and laying 1 layer flat brick soling including sand blasting of the joints all complete
ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 0.50 person 890.00 445.00


2 Unskilled 1.00 person 625.00 625.00

TOTAL OF A 1,070.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Brick 420 nos. 13.43 5,639.25


2 Sand 0.71 m3 2,594.07 1,841.79

TOTAL OF B 7,481.04

ACTUAL RATE 8,551.04


15% CONTRACTOR'S PROFIT & OVERHEAD 1,282.66
9,833.69

SAY RATE PER m2 983.37

D.01. Providing and laying 75mm thick 1:3:6 cement-sand-aggregate concrete in the foundation including haulage up to 30m
all complete
ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 0.75 person 890.00 667.50


2 Unskilled 3.00 person 625.00 1,875.00

TOTAL OF A 2,542.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Cement 0.17 MT 15,205.90 2,634.42


2 40mm down aggregate 0.51 m3 3,000.00 1,535.63
3 20mm down aggregate 0.19 m 3
3,275.64 619.10
4 Sand 0.37 m2 2,594.07 960.13
TOTAL OF B 5,749.27

ACTUAL RATE 8,291.77


15% CONTRACTOR'S PROFIT & OVERHEAD 1,243.77
9,535.54

SAY RATE PER m2 953.55


D.02. Providing and laying 50mm thick 1:2:4 cement-sand-aggregate concrete on the floor including mixing and haulage up
to 30m all complete
ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 1.25 person 890.00 1,112.50


2 Unskilled 2.50 person 625.00 1,562.50

TOTAL OF A 2,675.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Cement 0.17 MT 15,205.90 2,585.00


2 20mm down aggregate 0.46 m3 3,275.64 1,506.80
3 Sand 0.23 m3
2,594.07 596.64

TOTAL OF B 4,688.43

ACTUAL RATE 7,363.43


15% CONTRACTOR'S PROFIT & OVERHEAD 1,104.52
8,467.95

SAY RATE PER m2 846.79

D.03. Providing and laying 38mm thick 1:2:4 cement-sand-aggregate screed on the floor including 3mm thick neat cement
punning (NCP) finishing all complete
ANALYSIS FOR : 10 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 2.25 person 890.00 2,002.50


2 Unskilled 3.00 person 625.00 1,875.00

TOTAL OF A 3,877.50
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Cement 0.18 MT 15,205.90 2,785.72


2 12mm down aggregate 0.36 m3 2,438.54 877.88
3 Sand 0.18 m 3
2,594.07 466.93

TOTAL OF B 4,130.53

ACTUAL RATE 8,008.03


15% CONTRACTOR'S PROFIT & OVERHEAD 1,201.20
9,209.23
SAY RATE PER m2 920.92
E. FINISHING WORKS
F.03. Providing and laying 20mm thick 1:4 cement-sand plaster on the external walls all complete
ANALYSIS FOR : 100 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 14.00 person 890.00 12,460.00


2 Unskilled 19.00 person 625.00 11,875.00

TOTAL OF A 24,335.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Cement 0.81 MT 15,400.00 12,474.00


2 Sand 2.20 m 3
3,200.00 7,040.00

TOTAL OF B 19,514.00

ACTUAL RATE 43,849.00


15% CONTRACTOR'S PROFIT & OVERHEAD 6,577.35
50,426.35

SAY RATE PER m2 504.26

F.04. Providing and laying 2 coats of plastic emulsion paint over one coat of primer on internal walls of uniform finishing all
complete
ANALYSIS FOR : 100 m2

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 9.00 person 890.00 8,010.00


2 Unskilled 5.00 person 625.00 3,125.00

TOTAL OF A 11,135.00
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Primer 8.10 ltr 376.00 3,045.60


2 Plastic Emulsion Paint 16.00 ltr 526.00 8,416.00

TOTAL OF B 11,461.60

ACTUAL RATE 22,596.60


15% CONTRACTOR'S PROFIT & OVERHEAD 3,389.49
25,986.09

SAY RATE PER m2 259.86

F. MISCELLANEOUS WORKS
I.03. Providing, fabricating and installing all metal angles/channels including primer, all complete
ANALYSIS FOR : 18.94 Kg

A. LABOUR QUANTITY UNIT RATE AMOUNT REMARKS

1 Skilled 0.69 person 890.00 611.43


2 Unskilled 0.78 person 625.00 488.13

TOTAL OF A 1,099.56
B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 Metal Channel 18.94 kg 115.50 2,187.57


2 Primer 1.00 LS 330.75 330.75

TOTAL OF B 2,518.32

ACTUAL RATE 3,617.88


15% CONTRACTOR'S PROFIT & OVERHEAD 542.68
4,160.56

SAY RATE PER kg 219.67

SAY RATE PER m #REF!


F.01. Providing, fabricating and installing 50 mm dia stainless steel vertical posts at 2 m c/c distance in 38 mm dia same
stainless steel Handrail and 3 layers 25 mm dia stainlesss steel member with 2'-6" to 3'-0" height railingincluding paint
of approved quality and colour, all complete work.

ANALYSIS FOR : 1.00 Rm

B. MATERIAL QUANTITY UNIT RATE AMOUNT REMARKS

1 50mm dia stainless steel pipe handrail


fitting work
1.00 Rm 3,960.81 3,960.81
TOTAL OF B 3,960.81

ACTUAL RATE 3,960.81


15% CONTRACTOR'S PROFIT & OVERHEAD 594.12
4,554.93

SAY RATE PER Rm 4,554.93


Calculation of Transportation Rates

Source: Dumre
Destination: Purkot

Truck Tractor
Paved Road Unpaved RoadAll
Rates (/kg/km): 0.012 0.019 0.066
Distance (km): 18.5 4 1
Rates per kg: 0.222 0.076 0.066

Haulage of Aggregates and Sand:

Distance 5 km from nearest river

Total
Haulage Loading Unloading Transport
Rates Rates Rates Rates
Items From Bazar 0.364 0.2211 0.2208 0.8059 per kg
Items from River 528.00 0.2211 0.2208 528.4419 per cum

Weight Calculation:

Materials Unit in Kg
Bricks No. 1.15
19 mm Plywood sq.m 10.45
Aggregates cu.m 1,600.00

Note: 5% addition over district rates for items of which the weight cannot be determined
RATE ANALYSIS FOR COLLECTION OF MATERIALS

Aggregates
Works: Collection and sieving of gravel of size 5 mm to 70 mm including stacking within 10 m Unit :
hauling distance, all complete work. 1 cu.m
Spec. cl. No: 800
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.1A Unskilled md 2.00 625.00 1250.00 Plants Cost= 37.50
Sub total of A = 1250.00 Sub total of B = 0.00 Sub total of C = 37.50
Sub total of A +B + C = 1287.50 Unit Rate = 1287.50

Sand
Works: Collection, quarrying and sieving sand in local river, all complete work. Unit :
Spec. cl. No: 800 1 cu.m
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.3D Unskilled md 1.50 625.00 937.50 Plants Cost= 28.13
Sub total of A = 937.50 Sub total of B = 0.00 Sub total of C = 28.13
Sub total of A +B + C = 965.63 Unit Rate = 965.63

Stone
Works: Collection of rubble of required size including stacking within 110m hauling distance, all Unit :
complete work. 1 cu.m
Spec. cl. No: 800
Norms Labour (A) Material (B) Equipment (C)
No. Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Tools and 3% of Labour
8.2 Unskilled md 1.40 625.00 875.00 Plants Cost= 30.00
8.8 Unskilled md 0.20 625.00 125.00 << haulage up to 100 m
Sub total of A = 1000.00 Sub total of B = 0.00 Sub total of C = 30.00
Sub total of A +B + C = 1030.00 Unit Rate = 1030.00
DISTRICT RATES

District Rates Transportation Adopted


Description of Items Unit
Tanahun Rate Rate
Labour Rates
Unskilled 625.00 - - 625.00 md
Skilled 890.00 - - 890.00 md
Material Rates
Bricks
1st class 12.50 - 0.93 13.43 Nos.
2nd class 9.00 - 0.93 9.93 Nos.
Soil 110.00 - - 110.00 cu.m
Aggregates
40mm down 1,177.00 - 1,815.94 2,992.94 cu.m
20mm down 1,459.70 - 1,815.94 3,275.64 cu.m
10mm down 622.60 - 1,815.94 2,438.54 cu.m
Sand 1,100.00 - 1,494.07 2,594.07 cu.m

Stone 1,050.00 - 1,558.44 2,608.44 cu.m


Cement
43/53 grade PPC 720.00 - 40.30 760.30 bag
43/53 grade OPC 830.00 40.30 870.30
White Cement 30.75 40.30 71.05 kg
Reinforcement Bars
TMT 8mm 81.50 - 4.08 85.58 kg
TMT >8mm 81.00 - 4.08 85.08 kg
Binding Wire 92.00 - 0.81 92.81 kg
Wood
Local wood 49,140.36 - 2,457.02 51,597.38 cu.m
Plywood
19mm commercial waterproof 1,474.12 - 8.42 1,482.54 sq.m
Paint
Distemper Powder 180.00 9.00 189.00
Wood/metal Primer 315.00 15.75 330.75 litre
Enamel Paint 390.00 19.50 409.50 litre
Plastic Emulsion Paint 575.00 28.75 603.75 litre
Weather Coat Primer 374.00 18.70 392.70 litre
Weather Coat Paint 1,200.00 60.00 1,260.00 litre
Black Japan Paint 330.00 16.50 346.50 litre
Red Oxide 280.00 14.00 294.00 litre
Flooring Works - -
Stone Dust 1,177.00 58.85 cu.m
Roofing Works
MS Pipes & Tubes 110.00 5.50 115.50 kg
3mm thick UPVC sheet 1,775.40 88.77 1,864.17 sq.m
District Rates Transportation Adopted
Description of Items Unit
1" self tapping screw 3.10 Rate
0.16 Rate 3.26 No.
2" self tapping screw 3.98 0.20 4.18 No.
3" self tapping screw 4.87 0.24 5.11 No.
Ridge Cover Profile 800.00 40.00 840.00 r.m
Bitumen Washer 0.70 0.04 0.74 No.
Nut-bolts 30.00 1.50 31.50 No.
24-Gauge Plain GI Sheet Medium 395.90 19.80 415.70 sq.m
Iron Square Pipe 90.00 4.50 94.50 kg
Black Pipe 91.00 4.55 95.55 kg
Channel 110.00 5.50 115.50 kg
J hook 34.50 1.73 36.23 No.
Fuel
Diesel 97.00 - 97.00 Lit
Perol 110.00 - 110.00 Lit
Others
Nails 102.00 0.81 102.81 kg
8/10/12 Guage GI Wire Medium duty
94.00 0.81 94.81 kg
8/10/12 Guage GI Wire Heavy Duty
100.00 0.81 100.81 kg
50mm dia stainless steel pipe handrai 3,960.00 0.81 3,960.81 Rm
Water 0.20 - - 0.20 litre

References:
Approved District Rate of Tanahu, FY 75/76
FY: 75/76
Remarks

###
###

###
###
###

collection and
haulage

###
###
###

###
###
###

5% extra

###

###
5% extra
''
''
''
''
''
''

###

###
5% extra
Remarks
###
''
''
''
50 in packet
5% extra
###
###
###
###

###
###

###
###

###
''
###
Government of Nepal
National Reconstruction Authority
Central Level Project Implementation Unit
Grant Management and Local Infrastructure
Jwagal, Lalitpur
Equipment Hourly Hire Rates
FY : 2075

Total Equipment Hire Rate= Hire Rate + Operator's Wage + Fuel Cost + Lubricants Cost

S. Power Fuel (Diesel) Lubricants (Grease) Fuel Lubricants Operator's DoR Hire Total Rate
Machine/ Equipment
No. (in HP) (in Ltr) (in Kg) Cost Cost Wage Rate per Hr

1 WHEEL LOADER (1.75 cu.m capacity) 160 =0.120 Ltr/HP= 19.20 =0.003 Kg/HP= 0.48 1,872.00 336.25 97.50 1000.00 3,305.75

2 EXCAVATOR 145 =0.125 Ltr/HP= 18.13 =0.003 Kg/HP= 0.44 1,767.19 304.73 97.50 1800.00 3,969.42

3 DOZER 120 =0.120 Ltr/HP= 14.40 =0.003 Kg/HP= 0.36 1,404.00 252.19 97.50 1800.00 3,553.69

4 MOTOR GRADER 135 =0.120 Ltr/HP= 16.20 =0.003 Kg/HP= 0.41 1,579.50 283.71 97.50 1600.00 3,560.71
5 THREE WHEELED ROLLER (12 ton) 47 =0.120 Ltr/HP= 5.64 =0.003 Kg/HP= 0.14 549.90 98.77 97.50 500.00 1,246.17
6 TRIPPER/ TRUCK (8 MT) 110 =0.120 Ltr/HP= 13.20 =0.003 Kg/HP= 0.33 1,287.00 231.17 97.50 853.00 2,468.67

7 TRACTOR 85 =0.120 Ltr/HP= 10.20 =0.003 Kg/HP= 0.26 994.50 178.63 97.50 300.00 1,570.63

8 CONCRETE MIXER 20 =0.120 Ltr/HP= 2.40 =0.003 Kg/HP= 0.06 234.00 42.03 97.50 500.00 873.53

9 BITUMEN BOILER (2 KL) 8 =0.120 Ltr/HP= 0.96 =0.003 Kg/HP= 0.02 93.60 16.81 97.50 180.00 387.91

10 GENERATOR (10 KVA) 13 =0.120 Ltr/HP= 1.56 =0.003 Kg/HP= 0.04 152.10 27.32 97.50 150.00 426.92

11 ASPHALT MIXER 20 =0.120 Ltr/HP= 2.40 =0.003 Kg/HP= 0.06 234.00 42.03 97.50 1,000.00 1,373.53
Government of Nepal
al Reconstruction Authority
el Project Implementation Unit
gement and Local Infrastructure
Jwagal, Lalitpur
pment Hourly Hire Rates
FY : 2075/76

DoR Code

068-

042-

031-

055-
094-
116-

123-

Market Rate

062-

054-

003-
Rates for Collection of Locally Available Materials

Manpower
S.N. Material Unit 3% Tools Total Amount Remarks
Type Unit Qty Rate Amount
Manual Collection of Sand, Gravel, Boulder and Aggregates:
1 Sand m3 Unskilled Labour md 3.00 700.00 2,100.00 63.00 2,163.00 DoR Norms No.: 8.3
2 Stone / Boulder m3 Unskilled Labour md 1.40 700.00 980.00 29.40 1,009.40 DoR Norms No.: 8.2
3 Gravel (63 mm down) m3 Unskilled Labour md 2.00 700.00 1,400.00 42.00 1,442.00 DoR Norms No.: 8.1
4 Gravel (40 mm) m3 Unskilled Labour md 3.00 700.00 2,100.00 63.00 2,163.00 DoR Norms No.: 8.2
5 Gravel (20 mm) m3 Unskilled Labour md 4.00 700.00 2,800.00 84.00 2,884.00 DoR Norms No.: 8.3
Rates for Transportation of Materials

Load/Unload
Loading rate= 0.1155 per kg
Unloading rate= 0.11 per kg

A. From site to river


Distance from nearest river to site = 3.5 km
Transportation for materials by truck on earthen road = 0.019 per kg per km
Total Transportation cost for locally available materials = 0.0665 per kg

Density Transportation
SN Material Unit
(kg/m3) Rate (T)
1 Sand m3 1600 106.40
2 Stone / Boulder m3 1600 106.40
3 Gravel (70 mm down) m3 1750 116.38

B. From site to Market


Total distance from market source to site = 18.5 km
Transportation by materials by truck on earthen road = 0.019 per kg per km
Transportation by materials by truck on paved road = 0.012 per kg per km
Transportation cost along earthen road= 0.2375 per kg
Transportation cost along paved road= 0.066 per kg
Total Transportation cost from source incl load/unload = 0.529 per kg

Conversion Transportation
SN Material Unit
to Kg Rate (T)
1 Cement bag 50 26.45
2 Bitumen litre 1
3 Reinforcement kg 1 0.529
4 Plywood sq m 49.13 25.98977
5 Local softwood cu m 0
6 Plank 38 mm thickk cu m 0
7 Elastomeric bearing No. 0
8 compression m 0
9 110 HDPE pipe RM 2.5 1.3225
10 Filler materials cu m 0
11 GI pipe(100mm) RM 0
12 GI pipe(50mm) RM 0
13 Geotextile sq m 0.2 0.1058
14 Enamel' litre 0
15 Water per 4000l 735

Das könnte Ihnen auch gefallen