Weekly Meeting Minutes

Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 1

Date of Meeting December 12, 2016 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager
Follow up of permits.
Engr. Rogen Dano Section Chief
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 1st-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Permit application under review, building permit is in hand, occupational permit is in hand,
demolition permit is in hand. Site has been investigation by the Geotechnical Engineer.
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 2

Date of Meeting December 19, 2016 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager Reports for investigation and
soil reports, structural design
Engr. Rogen Dano Section Chief
and analysis,
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 2nd-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Permit application has been reviewed, building permit is in hand, occupational permit is in hand,
demolition permit is in hand, and now ready for the work.
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 3

Date of Meeting December 26, 2016 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager
Start of site survey
Engr. Rogen Dano Section Chief
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 3rd-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Temporary facilities (bunkhouse, material storage, water and electric connection)
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 4

Date of Meeting January 2, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 4th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Material and Equipment for earthwork, clearing and grubbing has been delivered to the site.
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 5

Date of Meeting January 9, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 5th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
To distribute 3-week look ahead to project team weekly.
Start Clearing and Grubbing, Removal of Actual Structure and Structure Excavation and
fabrication of bars
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 6

Date of Meeting January 16, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 6th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
On-going work for (Clearing, Grubbing), Removal of Actual Structure and Structure Excavation
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 7

Date of Meeting January 23, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 7th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Continuation of Removal of actual structures, structure excavations
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 8

Date of Meeting January 30, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 8th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Continuation of Structure Excavation
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 9

Date of Meeting February 6, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 9th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Continuation of structure excavation
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.
Weekly Meeting Minutes
Staff Meeting
Held in Allmedyl Hall

Meeting Name Meeting No. 10

Date of Meeting February 13, 2017 Time 1:00 PM

Discuss Project Meeting Leader Engr. Geneca Baclado


Meeting Purposes Accomplishment and
Proceeding Activities Engr. Hannah Mae
Prepared By
Abanilla

1. Attendance at Meeting (add rows as necessary)


Name Position Note
Engr. Geneca Baclado Chairman
Engr. Beverly
Site Engineer
Castroverde
Engr. Jeany Rose Balute General Manager UPDATE: To distribute overall
project schedule monthly with
Engr. Rogen Dano Section Chief
progress payments
Engr. Jl Carl Joanic del
Surveyor
Rosario
Engr. Ronabelle Anne Marketing, Sales &
Laurente Advertisement

2. Meeting Notes, Decisions, Issues


The 10th-week Project Schedule was distributed and discussed. The following Schedule items
need follow up:
Continuation of structure excavation
Facilities for the Engineer has been issued.
Project safety issues were discussed, with the following key points:
All Hands safety meeting will be held Monday mornings starting @ 7:00am
Proper PPE must be worn at all times on jobsite including (Hard Hats, Safety Glasses and High
Visibility Vests or T-shirts, Over the Ankle Work Boots.