Sie sind auf Seite 1von 4

Estimating formwork

A realistic appraisal must be made of the kinds


and amounts of materials and the needed size of crew

T he final profit or loss on a struc-


ture is often decided in the esti-
mating or bidding stage before a job
actually starts.
Basically the cost of forming de-
pends upon thickness, height and
length of wall but there are also
many other factors involved that are
not always easy to evaluate and
some of which are even likely to be
unforeseen . Typical of much of the forming today is this job with its many offsets,
The knowledge necessary for suc- projections, ledges and box-outs. Cut-up forming such as this makes estimating
cessful formwork estimating is more complex and overall forming costs higher.
gained by trial and error—though
some is obtained by schooling. A
highly useful supplement is the as-
ufacturer have to be both honest to be of unusual design, it may
sistance offered by most manufac-
and realistic with each other. prove more economical to use spe-
turers of concrete forming equip-
cial forms if they can be reused
ment who can give estimates, cost Estimating material require- enough times to justify the cost.
quotations and layouts for the use of ments Once the estimate is started it
their equipment. Such information
To begin the estimate the con- proceeds according to the following
can be included in estimating the
tractor must consider what forming four steps, usually in this sequence
overall cost of the job. Since con-
equipment is available, how much but not always:
crete work may be as high as 75 per-
of the needed equipment he owns • analysis of the total job
cent of the total cost on some jobs
and how much he must rent or pur-
and since forming may represent 60 • examination of equipment or sys-
chase. The next step is to analyze
to 75 percent of the concrete cost tems available
the job in terms of what types of
the help given by the manufacturer • consideration of the effect of the
equipment are needed—prefabri-
should be valuable in keeping these choice of formwork on the total
cated, job-built or specials. The
costs low. Occasionally complaints job
manufacturer should be asked for
are heard that a manufacturer has
assistance and for this purpose he • consideration of factors other
misfigured the job or has not sup-
should be given all the information than formwork that can affect the
plied enough equipment so that de-
needed to make a realistic estimate. results
lays have occurred and the schedule
There are two types of formwork Reviewing these in detail we find
has had to be adjusted. When this
by which the job can be handled: the following:
happens it is usually because the
job-built or prefabricated. The 1. Analysis of the total job. To un-
contractor and manufacturer have
choice can considerably affect the derestimate a job and receive the
not understood one another, have
p re p a ration of the bid and its contract can prove to be a financial
not supplied each other enough in-
amount. Sometimes the design dic- problem to the contractor and even
formation or have not planned
tates the type of equipment re- lead to business failure.
properly. The contractor and man-
quired. For example, if columns are
The blueprints should be re-
viewed to analyze each area or seg-
ment of the job that involves con-
c re t e. If the job is large or cut up,
detailed notes should be made re-
garding any questionable areas as a
safeguard that nothing be over-
looked.
Many jobs will have some factors
about them that will immediately
indicate the job plan, the equip-
ment to use and sequence of work.
Others will not, and particular at-
tention must be given to these jobs.
Overlooking one small item or mis-
figuring a size or sizes can have a
bearing on the success of the job.
Usually the big errors are not caused In preparing the estimate or
by misfiguring but by omitting or take-off of areas to be
overlooking some key item or phase formed, careful attention
must be paid not only to the
of work.
equipment and sizes needed
Many estimators prepare a rough but to the amount of labor
estimate at this point to determine required. Job-building of
the amount of concrete to be forms for conditions such as
formed, expressing it in terms of this requires careful planning
square feet of contract area. This to minimize costs
will provide a rough indication of
what percent of the total job is con-
cerned with forming. It will also aid
in selection of forming equipment. Gang forming of large
2. Examination of available sections of forms, when
equipment or systems. If the con- possible will reduce the
tractor owns forming equipment he square foot cost in both
may prepare a detailed take-off of erection and stripping,
the job to see if his inventory is ade- Crane handling of forms
should be planned to
quate or if additional equipment
coordinate with crane
and materials are necessary. If new handling of materials to
equipment is to be rented or pur- minimize idleness of
chased, the take-off will be of great equipment.
assistance in planning and schedul-
ing. The take-off will be especially
helpful if he plans to build the forms
himself.
Best economy requires balancing
the effects of original investment,
reuse value of forms and efficiency
of erection and stripping cycles.
Here again, a little extra thought and
work can make a big difference. The
choice of job-built or prefabricated
forms may be dependent upon
these factors. The original cost of
equipment must be weighed
against expected performance, cost
per reuse, life expectancy, and cost
of finishing. Although there are
many other influencing factors the Equipment should be located as close as possible to where it will be used to
reduce moving time and costs.
others are more of a subject for formwork on the total job. With esti- alternate plans prepared in case
economy than estimating. mates on prefab forms or job-build- they are needed. No one can foresee
At this point assistance and esti- ing, or both, the contractor can e ve rything, but the key to cost re-
mates from prefabricated form compare figures and reach a con- duction is reducing labor and in-
manufacturers, most of whom offer clusion on the best and most eco- creasing the reuse of equipment.
this service, can be of great help. nomical way to proceed. Howe ve r, Since the concrete work usually pre-
Manufacturers often work closely the cost of forming cannot be con- cedes almost all other work, a delay
with the contractor in finalizing the sidered completely independently of any nature can affect the whole
cost quotation, bill of materials and because it can affect the other oper- job.
layout drawings. ations or work from the very begin- 4. Consideration of factors other
In order for the manufacturer to ning of a job. During the estimating than formwork that can affect re-
p re p a re a formwork estimate, he period consideration should be giv- sults. In making estimates calcula-
must be furnished certain supple- en to how forming operation will af- tions are often used from a previous
mentary information along with the fect such other operations as mater- job where the work appeared to be
blueprints. He will want to know the ial handling, steel work, plumbing the same, where the design was sim-
size of carpenter and labor crews, and finishing. When forming equip- ilar or where other factors suggest
number of concrete placements, the ment is first delivered to the jobsite that the figures are applicable again.
equipment available for material it should be located close to where it Yet it is rather hard to conceive that
handling, tie specifications and will first be used. If it has to be two jobs can be identical, so previ-
whether the job is to be hand-set or moved any distance at all and if the ous estimates should be used only
gang-formed. From this he can pre- quantity is large, the material han- with caution.
pare a preliminary estimate with dling cost can become significant. If One factor not directly related to
complete layouts and bill of materi- it is possible that problems might materials and job operations is de-
als when the job is awarded. arise that would reduce efficiency, l i ve ry of equipment. When it runs
3. Consideration of the effect of cost allowances should be made or into unexpected delays from strikes,
bad weather, accidents, or shortness
of supply it can cost the contractor
money.
The cost of moving onto the job-
site and the efficiency of workers
should be evaluated in terms of pro-
ductivity. This includes the cost of
supervision at all levels.
Labor relations affect the output
of work considerably. The contrac-
tor must be able to anticipate a cer-
tain amount of work each day. If
that work can become repetitious,
it adds to the economy, but only if
careful scheduling has been done so
all crews are kept moving without
undue pressure that detracts from
m o ra l e. Good working conditions
and safety aids have a bearing on
the mental attitude and efficiency of
the crews.
Se ve ral of the many other factors
that have an indirect bearing on
forming include job conditions,
weather, condition of equipment,
and strikes among the trades.
The estimator must be able to
High-rise construction make an educated evaluation of all
calls for careful planning such factors that influence or might
of equipment cycles and influence the job. He may obtain ad-
smooth scheduling ditional help from any of several es-
sequence of trades timating books available for figuring
labor, materials costs, wage rates, ure. Depending upon job condi- • length of time stringers and
fringe benefits and all types of con- tions it could perhaps be increased shoring must be supported
struction equipment. These books considerably, thereby reducing the • cycle for stripping and handling
allow for adjustment of labor rates labor force and square-foot cost.
and the cost of equipment for vari- This kind of analysis made by • adaptability of equipment from
ous parts of the country. working in reverse can insure the floor to floor
Generally speaking, the smaller most efficient production. If the re- • whether equipment can be used
the work force, the lower the labor quirements are set first and the at any location or must remain in
unit cost. In order to determine the work force is hired to meet these re- the same position for each floor
correct size of labor force an analy- q u i re m e n t s, the costs can be con- In going over this check list it will be
sis should be made, the require- trolled. The method facilitates early necessary to acquire the following
ments set and the work force hired recognition of problems so that cor- information:
to meet these requirements. rective measures may be taken be- • how many floors are typical and
fore the work has gone too far. how many atypical
Determining the size of crew
It is hard to lay down exact rules Check list • floor heights and slab thicknesses
to follow in estimating formwork The following is a general check • size and location of beams
but the following is an example of list of items that must be established • type of slab or its design
how the size of a labor force can be when figuring the forming:
determined. Job conditions will • sequence of erecting and casting
• number of concrete placements
have to be ascertained and provided columns, shear walls, core walls,
and average volume of each
for. Assume that a contractor wants spandrels and other elements
• wall dimensions
to place concrete in 4,800 square • number of concrete placements
feet of forming every third day and • surface treatment per floor
is able to strip the following morn- • construction joints • location of bulkheads
ing. The ratio of carpenters to labor-
• treatment of reinforcing bars • treatment of other materials, such
ers is one to one. The carpenter rate
is $4.50 per hour including fringe • handsetting or gang forming as whether plumbing is sleeved or
benefits and the laborer’s rate in- cast in deck
• crane time, if any
cluding fringe benefits is $3.50 per • type of ceiling finish
• ties: breakbacks, cones, washers
hour—a total of $8 for a two-man • allowable deflection
team. Let us further assume that 20 • length of time forms are required
to remain in place Each region of the country has a dif-
cents per square foot would be ade-
ferent set of standards not only for
quate for the labor of erecting and • any special conditions or equip- labor rates but also for working con-
stripping. Working backward we see ment ditions. These should be carefully
that erecting and stripping would Analysis of high-rise work or deck explored when moving from one
cost $960; spread over the three-day forming follows much the same area to another. But no matter
period this would be $320 per day. p ro c e d u re. Howe ve r, the biggest where the work is done the basic
The cost of a team of one carpenter considerations in estimating the steps outlined here provide an easy-
and one laborer is $64 per eight- working cycle for such work are the to-use formula that can serve as a
hour day. If five teams of carpenters criteria for shoring and how long the guideline for all jobs. Use of such a
and laborers are used the daily cost forms must remain in place. Form- standard procedure will help the es-
will be $320, the same amount that ing costs can vary up to 50 percent timator develop material and labor
was allowed on the assumption that because of differences in specifica- cost sheets for record-keeping pur-
the cost should be 20 cents per tions and severity of engineering re- poses and these will be of immea-
square foot. quirements. surable value for each new job.
Over the three-day period the car- In order to estimate shoring
penters and laborers will have to av- equipment for slabs with a reason-
erage 1,600 square feet per day or able degree of accuracy, the follow-
320 square feet per carpenter-labor- ing check list is needed:
er team. This amounts to 20 two- by
• casting schedule
eight-foot forms including waling
• length of time forms must be sup- PUBLICATION #C730149
and bracing during each eight-hour Copyright © 1973, The Aberdeen Group
period. This is a very reasonable fig- ported
All rights reserved

Das könnte Ihnen auch gefallen