Sie sind auf Seite 1von 47

Confidential

NEWSLETTER
Materials and Inspection Engineering
‘The Rusty Chronicle’
December 2005
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Contents

Editorial . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 3

Announcements & Upcoming Events . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4


Training Courses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Web-based Software for Fitness for Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 4
Expansion of the FAIR+ program . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5
News on the MCI-Infobase for Refineries and Gas/LNG plants . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6
Materials Technology Institute – Lofty Name, Down to Earth Products . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7
Materials & Inspection Engineering Meeting 2005 - Where Upstream and Downstream met . . . . . . . . . . . . . . . . . . . . . . 8

DOWNSTREAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Failure of LRCCU Caustic Regenerator Off Gas Return Line . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Flow Accelerated Corrosion in a Boiler Feed Water Deaerator . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
Root Cause Investigation of Hydrogen Blistering and HIC of a HCU Fuel Gas Scrubber in a Canadian Refinery . . . . . . . 12
Degradation Prediction and Assessment Models Coming to CWW . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 14
Materials analysis of Pernis FCCU 44-year-old C-0.5% Mo reactor vessel . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16
Rhineland Refinery Hydrocracker Piping Leak . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 17
Anchors away! . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 23

UPSTREAM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Discipline Leadership in EP . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 25
Capacity Enhancement of the PTT Gas Supply Network . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
Investigation of Un-Commanded Closures of EPW Surface Control Subsurface Safety Valves . . . . . . . . . . . . . . . . . . . . . 30

WATER FLOODING – MATERIALS SELECTION CHALLENGES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 31


DEP.39.01.10.11-Gen. Manual - selection of materials for life cycle performance (EP) – 2005 Revision . . . . . . . . . . . . 32
Cathodic Protection Review - Nigeria LNG Bonny Plant and Incoming Pipelines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32

STRESS RELIEF! . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34

Who’s Who - Organograms . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35


Staff Announcements . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
GSEI Materials & Inspection Engineering group . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 37
GSEI/1 Downstream Materials & Inspection Engineering . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 38
GSEI/1 Contact Information . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
GSEI/2 Upstream Materials Engineering . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
GSEI/3 Inspection Technology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
GSEI/4 Upstream Materials and Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
GSEI/5 Downstream Pressure Equipment Integrity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47

If you have any questions or comments about this Newsletter, please contact your respective focal point or the editor: Goh Gim-
Choon (gim-choon.goh@shell.com)

NOTICE
The material contained in this Newsletter is intended for the use of Shell Global Solutions and its associated companies, Shell Global Solutions International B.V. and the Shell Research
and Technology Centres in Thornton, Grand Couronne, Hamburg and Singapore and their client companies only, and is provided subject to the terms of the relevant services agreements.
It is provided for the purpose of information only and should not be applied in any specific situation without having obtained further clarification and advice from the relevant Shell Global
Solutions company. None of the associated Shell Global Solutions companies accepts responsibility for the accuracy or completeness or for the applicability or the application by anyone of
the material contained herein. Copyright of this publication is vested in Shell Global Solutions International B.V., The Hague. This document may not be reproduced without the prior written
consent of the copyright owner.


The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Editorial

You’ve most probably all heard the old cliché that “the only true constant in our lives
is change itself”. This cliché certainly rings true for me as I look back on 2005. We
have witnessed major changes in all parts of Shell during the year and in my opinion,
most have been good. Overall it has been a great year!

It has certainly been a year of significant change for Royal Dutch Shell, and it’s
associated upstream, downstream, G&P and related businesses. It has also been a
year of progress and of great success as we continue to r ecover from the difficulties
that emerged in 2004. The unification of Royal Dutch and Shell Transport into
one parent company, Royal Dutch Shell plc, was completed in July and significant
progress, and results, have been achieved towards our strategy of “more upstream
and more profitable downstream”. All segments of the business are having a successful year. Although annual
earnings have not been announced for 2005, we can certainly expect strong performance from all segments of
the RDS business. It is also reassuring to see the significant and ever increasing capital investment in the company,
19 billion USD 2006, as this will no doubt assure sustained progress towards our strategy in the years to come.

It has been a year of significant change for Shell Global Solutions as well, most all being driven by the needs
of our customers. Early in the year both Chemicals Technology and CRI/Criterion joined Shell Global Solutions
providing additional technical capabilities that allows us to span the entire hydrocarbon chain – from production
to retail. Also, an Innovation & Technology vice presidency position was created to provide a greater emphasis
in this area and to assure a strong linkage to customer needs. In addition, a decision to simplify our commercial
relationship with Shell customers was taken and efforts are underway to provide more focus in the area of non-
Shell new business development. All of these changes have been made to allow Shell Global Solutions to better
support the corporate strategy of “more upstream and more profitable downstream”. Global Solutions has grown
to include nearly 5000 employees as a result. Our core purpose continues to be to deliver value to our customers
through these technologies and our very competent staff.

The Material and Inspection Engineering global group has continued to change and grow through the year as
well and, meeting the needs of our customers continues to be our primary objective. At year-end we had 134 staff
in our global group and plan to grow to 147 by the end of 2006. A significant part of this growth will be in the
Asia Pacific service center where we will grow from our current 8 staff to 12-15 by the end of 2006 or early in
2007. Financially and otherwise we have had a very successful 2005 in our global group thanks to you, our loyal
customers, and to the hard work and dedication of our staff! Most importantly, we worked safely through the year
without any serious incidents or injuries. I look forward to an even more successful 2006!

All the best for a successful 2006 and once again, I hope you enjoy reading this issue of “The Rusty Chronicle”.

Bill Coit


The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Announcements & Upcoming Events

Training Courses We have set the following course dates for 2006:
In 2005 we ran a number of materials engineering training
courses. M276 Fitness for Service
Kuala Lumpur, 27 February - 3 March, 2006
The M183 Materials and Corrosion course was fully revised
and streamlined in 2004 into a two-week, one-site based M273 Advanced Refinery Corrosion
format, with lectures given by Cranfield University and Shell Kuala Lumpur, 6 March - 10 March, 2006
Global Solutions. The course was again held in Amsterdam
this year in October/November and was attended by a Amsterdam, 18 September - 22 September, 2006
record number of participants, coming from the four corners
of the world and from upstream, refineries, chemicals and M183 Materials and Corrosion course
gas/LNG plants, as well as other disciplines from within Amsterdam, 6 November - 17 November, 2006
Shell Global Solutions.
Information related to the courses and enrolment can be
In September we successfully ran the very first M273 found on the Shell Open University website web:
Advanced Refinery Corrosion course in Amsterdam. This http://sww-openuniversity.shell.com
was a new course, designed as a follow-up to the M183
course to develop competencies in the areas of anticipation If you to do not have access to the SWW for registration
and diagnosis of materials and corrosion problems in purposes, please use the registration form on
refineries, in particular the critical degradation mechanisms http://www.shellglobalsolutions.com/learning
and prevention strategies for the main refinery process units.
In 2006, this course will be run in Kuala Lumpur in March Specific details for the individual courses and possibilities for
and return to Amsterdam in September. export courses can be obtained from the following people:

The M276 Fitness For Service (FFS) course continues to be l M183 Materials and Corrosion - Simon Marsh

in demand as an export course and in 2005 was run in the (GSNL-GSEI/1)


United Kingdom, Thailand and the Sultanate of Oman with
participants coming from a number of locations. l M273 Advanced Refinery Corrosion – Pieter Blauvelt
(GSNL-GSEI/1)

l M276 Fitness For Service – Andrew Saunders-Tack


(GSNL-GSEI/1).

More information on all Shell Learning and Development


engineering courses can be obtained from Jan Blum
(jan.blum@shell.com)

Web-based Software for Fitness for Service

New software for assessing fitness for service (FFS) of The Vessels assessment software includes guidance on
pressure vessels has been launched on the Shell customer corrosion damage tolerance of:
wide web (CWW). The new pressure vessel application
compliments the pipework assessment software in terms l cylindrical and spherical vessels
of the tools available for assessing damaged or degraded l hemispherical, semi elliptical and torispherical ends
processing plant. l integrally reinforced nozzles

The software comes under the MCI Infobase on the CWW. The software currently covers the following design codes:
The advantage of web-based software is that it provides
the customer with the latest technology whilst eliminating l ASME VIII division 1 and 2
the administrative burden of distribution, installation and l BSPD 5500 and BS1515 vessels
maintenance of software. It is an ideal solution for both the l AS 1210 (Australia)

customer and developer. l EN13445


The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
The longer-term plan is to develop and extend the range of The M276 training course has been developed to introduce
solutions available in the FFS software. Future developments the FFS concepts to customers. In addition, the course is
will extend the number of design codes available, and the an excellent forum for customers to put forward their own
number and type of structural details. As an example, work requirements and ideas for FFS. As an example, customers
has just been completed on the assessment of damaged requested the assessment methods for pad-reinforced
pad-reinforced nozzles. There are also plans to include the nozzles be included in the FFS software. It should be noted
assessment of crack-like damage in addition to the existing that access to the FFS software is conditional on completing
corrosion loss assessments. All the assessment methods used the M276 course.
in the FFS software is based on the current Shell Global
Solutions Handbook for corroded pressure vessels. For more information please contact David Ritchie
(david.d.ritchie@shell.com) or Andy Saunders-Tack
Fitness for service assessment (FFS) is a new technology to (andrew.saunders-tack@shell.com)
many potential users in refineries, gas and chemical plants.

Screenshot of the new customer-wide web software.

Expansion of the FAIR+ program

The Focused Asset Integrity Review program (FAIR+) will be The program consists of the following review modules
upgraded to the Shell Advanced Focused Asset Reliability (1) design integrity, (2) asset integrity (existing FAIR+MS
and Integrity program (provisionally known as SAFARI), Management systems and FAIR+ER Equipment Review),
adopting the same process and methodology as applied in (3) organisational effectiveness and (4) operational integrity
the Steam Cracker Performance Review. to support the operating assets. The program is modularized
and structured in such a way that the customer can select the
Amalgamation of FAIR+ with other established review modules of interest for maximum flexibility. The modules can
processes in a structured and integrated way offers an be used in stand-alone mode with varying levels of depth,
improved assessment method of the total integrity of or they can be used in an integrated fashion, all depending
the operating assets. As such the program provides a on customer needs.
fundamental precursor to the Business Improvements
Reviews (BIR).


The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

The integrated reviews identify areas of vulnerability across Benefits:


disciplines and across technical and organisational aspects. Customers (Refineries, LNG/Gas plants, petrochemical
Gaps against Best Practices are identified and risk assessed complexes) will receive a detailed review of management
highlighting improvements across the entire business systems, design, equipment, operations and maintenance
operation. practices, and the underlying organizational structure that
underpins them. Gaps against Best Practices are highlighted
In addition to the integrated approach, another strength and a prioritised program, based on relative risk, is
of the offering is the unique manner in which technical proposed that will improve plant/unit availability through
observations from various disciplines are brought on an enhanced equipment integrity and reliability.
equal footing with observations from the organisational
effectiveness review through the use of smart keywords. This For more information, please contact Andre Blaauw
enables identification of failing management systems and (andre.blaauw@shell.com) and Arnoud van der Post
underlying behavioural patterns that are at the root cause of (a.vanderpost@shell.com), Shell Global Solutions NL
integrity flaws.

News on the MCI-Infobase for Refineries and Gas/LNG plants

2005 has been an active year for the MCI-Infobase team. l A new Corrosion Monitoring ebook has been added to
The MCI-Infobase has now successfully been rolled out the system.
through the Shell GS CWW to 60 customer sites across l The Fitness For Service (FFS) handbooks are available

28 countries. The latest verification of user lists (December though the MCI-Infobase to all MCI-Infobase licensed sites
2005) gave a total number of individual customer licenses who have sent participants to the M276 FFS course or
as 3591 (each site regulates its own users). This includes held an export version of the course on-site. Additionally
registration of most of the inspection personnel, plus others the calculation software for both pipework and pressure
such as technologists and operations personnel so that they vessels are now live and available.
are able to access the data whenever they might need it.
In 2006 we intend to build on the existing content and add
Throughout 2005 content has been added to and updated, further features such as:
and as users you see the changes immediately. The l Corrosion Prediction Models - This will be a major

following list provides highlights of the changes that you addition to MCI. Models to be made available in
have seen throughout the year: 2006 will include Shell’s proprietary models such as
HydroCorr, CORRAT, and SNAC (Shell Neutralizing
l For sites with the appropriate license agreements with Amine Corrosion), and corrosion by NH4HS, NH4Cl,
Shell Global Solutions, the globalised Best Practice Guides HCl, and H2SO4. Additional models associated with
are now made available as they are approved. SCC and metallurgical degradation such as HTHA will
l New degradation libraries have been incorporated into be developed. Access to these prediction models will be
the Refining and Gas/LNG MCI-Infobase. dependent upon the relevant service agreements.
l Incorporation of material from the globalised l Further updates to units in MCI-Infobase for Refineries

generic Corrosion Control Manuals (CCM’s) on the in-line with the globalised generic CCMs.
Crude Distilling Unit (CDU) and Hydrotreater and l Incorporation of newly approved globalised Best Practice
Hydrodesulphuriser (HTU/HDS) units. Guides (for sites with the appropriate license agreements
l Within the Gas/LNG MCI-Infobase the Dehydration unit with Shell Global Solutions).
has been updated to include glycol dehydration. l Incorporation of the API flowcharts for degradation

l Within the Inspection sections of the Gas/LNG and libraries for the MCI-Infobase.
Refining MCI-Infobase, the first significant revision to l Further updates to the Inspection section.

the paper-based Shell NDT Handbook has occurred, l Alignment between the MCI-Infobase and MATHELP.

including new/improved information on Digital


Radiography; ToFD ultrasonics; Long Range UT for both If you have any questions about the MCI-Infobase or are
short and long distances; PEC; Inspection for CUI and UT interested in receiving access to the system please contact
thickness gauging. Andrea Etheridge (andrea.etheridge@shell.com) or (for US
l The Contractors database has been completely updated. customers) Ying Xiao (ying.xiao@shell.com).


The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Materials Technology Institute – Lofty Name, Down to Earth Products

What’s this all about? presentations focusing on new ideas for evergreening RBI
The Materials Technology Institute (MTI) is an international and other risk-based processes.
consortium of companies who have interest in materials l Two state-of-the-art presentations on Stainless Steel

issues. It’s one of the organizations in which Shell GSI Casting were presented at the last meeting in October.
maintains membership and participation under the Don Bird of Stainless Foundry and Engineering and
Baselayer R&D program. There are currently 52 MTI Raymond Moore discussed a range of topics related to
member companies including major petroleum and specification, quality control, and heat treatment of alloy
chemical product producers, paper and drug manufacturers, castings. Videos of the presentations and the visual aids
materials suppliers and equipment fabricators, and can be viewed for the next few months on the MTI website.
consulting companies. Bill Fort is Shell’s representative to l The Materials Selector Series of publications is now

MTI. available on CD. Shell personnel can purchase the CD


at the discounted price of USD 20.00 (+ shipping &
MTI is headquartered in the United States, where it handling) until 1 April 2006.
traditionally held three meetings yearly. Over the last few l A project is currently underway on Statistical Analysis of

years MTI has begun holding once-yearly meetings in NDE Data.Phase I produced an audit protocol to help
Europe – 2004 and 2005 in the Netherlands. Expansion judge confidence of data. Phase II will report on statistical
into the Far East is currently under consideration. But, tools.
MTI’s website is quickly becoming a primary means of l MTI is updating its best-selling “Guidelines for Assessing

communication, reducing the criticality of face-to-face Fire & Explosion Damage”, originally published in 1990.
meetings. The update will add a ready reference guide (a list of
immediate things to do when an incident occurs), a
What’s in it for me? revised methodology for evaluating explosions, damage
MTI’s major efforts revolved around (1) helping member assessment protocols, an energy assessment evaluation
companies share non-proprietary information and methodology, discussions on deflagration-to-detonation
(2) sponsoring selected R&D to develop new technologies transitions, sabotage investigations (including sabotage
and incorporate new for the benefit of member companies. of the investigation), field testing techniques (field
The scope includes materials, corrosion, inspection, metallography, etc.), storm damage assessment, pump
equipment integrity, process safety, and fabrication issues explosions and ignition sources, and selected case
among others. MTI’s original focus on the chemical process histories. Publication is expected by end of 2006.
industries has now been broadened to include all of the l MTI conducted a workshop “From Condition Assessment

processing industries. to Real-Time Plant-Floor Prognostics and Diagnostics” in


February 2005. The workshop considered Materials
Member companies get to pool resources to do R&D. Degradation, Sensors & Measurements and Operations
MTI sponsored R&D projects by nature addresses non- & Maintenance. Results are available by link from the MTI
proprietary technologies of broad interest to the member to the PNNL website. The workshop identified (1) sharing
companies. It has resulted in best practices and standards, of asset performance data between operations and
new testing, inspection and evaluation techniques, new maintenance and (2) understanding of the consequences
materials, new construction and repair methods, and and actions by operators to off-normal conditions as key
training programs. needs – both very much in line with SGSI efforts.
l MTI will produce a handbook Materials Selector for

Member company employees have access to a wealth of Organic Solvents to provide guidance in selecting
professional education and information sharing through the materials of construction for equipment & piping handling
MTI discussion forums, technical meetings, and R&D project organic solvents. The publication will cover 52 solvents,
work with their peers in other member companies. including the neat solvent, the solvent with water and
with oxygen, and over a range of temperatures. Metal,
What’s new at MTI? polymer and elastomer compatibility information
l The
book “Implementing and Evergreening RBI in Process and corrosion rates will be included. MTI companies
Plants” has just been published. Shell personnel can are invited to contribute data and case histories. The
purchase the book at the discounted price of USD 20.00 handbook is expected to issue in about two years.
(+shipping & handling) until 1 April 2006, versus the full
price of USD 475.00. A workshop was held last year to How can I participate?
discuss new ideas around RBI. Another 1 to 1-1/2 day Employees of Shell companies having at least 50% Shell
workshop/conference is being planned for early 2006, ownership can participate in MTI activities. Your first step
which will include both MTI member company and outside is to go to the MTI website (http://www.mti-global.org) and
request member access. After confirmation, you will be


The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

given a password that allows you to fully access the website. 23-26 October in Dallas. The Orlando meeting will feature
From there you can access the on-line information exchange a presentation on Nano-Coatings Technology. The next MTI
forum, past forum exchanges, R&D project information, European meeting (EuroTAC 2006) will be held on 24 April
contacts in other member companies, and much more. 2006 in Germany. Dow-Dupont will present a one-day
Currently, about 55 Shell and Shell JV employees have course “Choosing the Right Elastomer” in conjunction with
access. the EuroTAC meeting.

This years MTI meetings in the United States will be held For more information please contact: Bill Fort
20-23 February in Orlando, 5-8 June in St. Louis and (william.fort@shell.com)

Materials & Inspection Engineering Meeting 2005 -


Where Upstream and Downstream met
From the 5 to 7 September 2005 the Global Upstream and • EP Inspection Harmonisation (EPE Inspection Quality System)
Downstream Materials & Inspection Engineering Meeting • Effectiveness of Pipework Inspection in EPEs UPGRADE Project
MIEM 2005 was held in Kuala Lumpur, Malaysia. With • Judging from the feedback rating from the participants,
overwhelming response, a total of 110 participants from which averaged at 4.03 out of 5, the MIEM was indeed a
40 companies in 20 countries attended the meeting. success.

The first day saw a combined


session for both the Upstream and
Downstream participants, with focus
on integrity related risk management
as well as project management
issues. For the second and third days,
separate sessions for the Upstream
and Downstream were held, a
wide-ranging list of topics relating to
Materials, Corrosion and Inspection
in Oil and Gas production and
Operating. Operational experience
and problems faced by the various
sties, both Shell and non-Shell, were
also actively shared and discussed.
Some of the topics presented and
discussed are shown following:

Downstream
• Fouling RRM for Relief and Depressurising system The minutes are now available:
• Impact of O2 and Oxidant to Corrosion in Amine Gas Treating (a) On the Customer Wide Web. Go to: Customer Wide
• High Temperature Corrosion in Delayed Coker Heater Web > CWW portal > Engineering > Materials and
• Best Practice for Furnace inspection inspection engineering > Events > MIEM Minutes >
• FAIR+ Fired Equipment MIEM 2005 or;
• Platformer Heaters Life Assessment using Omega Methods (b) Livelink: https://sww-knowledge.shell.com/knowhow/
• PEC corrosion monitoring – Set up and Experience livelink.exe?func=ll&objId=46288479&objAction=browse&sort=
• Rogue Weld Material Detection in Stainless Steels name
• IDMS Implementation Experience (c) If you would like a CD rom, a hard copy of the minutes
or both, please email wilma.kampschoer@shell.com
Upstream
• EP FAIR+ World wide Project For more information please contact Woon Eng Ong
• Shearwater - state of the art, but not perfect (woon-eng.ong@shell.com), Mike Thompson
• High Temperature coating and its qualification (mike.j.thompson@shell.com) or Wilma Kampschoer
• Scoter Subsea Tie-back Design vs Operation (Wilma.kampschoer@shell.com)
• Pearl Gas to Liquid materials selection
• Cost Effective ROV inspection of riser and underwater
piping systems


The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
DOWNSTREAM
Failure of LRCCU Caustic Regenerator Off Gas Return Line
Sour off gases from the Caustic Regenerator were being efficiency of the steam super heater. The 1% Cr - 0.5% Mo
disposed of by sending them to the CO Boiler via the R&R sour off gas line has an upper temperature limit to avoid
flue gas line. A leak was discovered in the sour off gas excessive oxidation resistance of around 600°C. Moreover,
return line near the tie-in point to the main duct. Inspection, as the auto-ignition temperature of CO is 610°C, conditions
after removal of the insulation, revealed this particular could have existed to support some degree of internal
section of the line to be totally disintegrated. In fact, the combustion that could explain the extent of the oxidation
last 1m of the line (at the CO Boiler end) was found to have and the porous and uneven morphology of the oxide layer.
reverted almost fully to its oxide form (see photographs
below). Remaining steel thickness was less than 1mm at the Sites that have a similar set-up mixing Caustic Regenerator
locations of detachment. The failed line was1% Cr - 0.5% sour off gas with R&R section flue gas may need to consider
Mo, schedule 80 (5.5mm nominal wall thickness). inspecting the line in question to ascertain its integrity.

The caustic regeneration sour off gases may contain up For further information please contact Cheong-Ming Tan
to 12% oxygen. It mixes with CO-rich R&R flue gases at (c-m.tan@shell.com), Port Dickson Refinery.
temperatures in the range of 550–620°C, depending on

Cross section of the above 2” line with oxide layer built up inside. Samples of the internal oxide layer.

Flow Accelerated Corrosion in a Boiler Feed Water Deaerator


Introduction
During the recent LRCCU turnaround in the Shell Refining
Company Port Dickson (SRCPD) in Malaysia, it was found
that the spargers (spray tubes) in the BFW deaerator had
corroded very severely, to the point that some of the sparger
ends were completely wasted and needed replacement.

Details of the deaerator


Design operating conditions are as follows:

Deaerated water make-up: 8400 tonnes/day


LP steam throughput: 1056 tonnes/day
LP steam temperature: 200°C (215°C actual)
Feed water outlet temperature: 150°C (operating values
slightly lower)

Figure 1. Schematic overview of the deaerator.


The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

The main sparger header (14300mm long x 273mm


OD) consists of 42 sparger arms (approx. 805mm long x
60.3mm OD). Each spider arm consists of 59 holes of 7mm
diameter and an additional 7mm diameter drain hole. The
failure of the spargers occurred on the “hot” end side of the
deaerator vessel, i.e. on the deaerator drain nozzle side
(Figure 2).

Figure 4. Results from the OD measurements. Black numbers refer to the


distance (in mm) from the sparger distribution pipe. Red numbers are
the actual diameters measured with a vernier caliper.

Figure 2. A more detailed photograph of the failed sparger arms. The whole
area, inclusive of the end-cap of the arm is corroded away. What are
left are the very sharp and very thin remains of the arm.

All sparger arms on the “cold” end side, where the feed
water enters the vessel were found to be intact and without
measurable corrosion loss (Figure 3).

Figure 5. Detailed photograph of a sparger arm at the steam outlet holes. This
sparger arm was not as heavily corroded as the sparger arms depicted
in Figure 2 and was found nearer to the center of the sparger header.
The hole size as per original construction drawing is 7mm.

By looking at the outer contours of the tube (bottom and top)


one can observe that near the holes, the material is slightly
indented as the thickness around the holes have been
reduced.

Another observation of the failed sparger is that at the


location where thinning starts (i.e. the reduction of the
Figure 3. Overview of the sparger facing the “cold” end side of the deaerator. OD becomes measurable) the external colour of the tube
On the left-hand side the centre LP steam inlet pipe is visible. changes quite abruptly from brownish-red (nearer the
sparger header) to shiny-black at the location of failure
Inspection findings (Figure 2). The sparger arms that were intact, on the side
Sparger inspection where the demin water enters, were all brownish red over
Once the failed sparger arms were removed from their the whole tube surface.
location a detailed visual inspection was carried out.
Contrary to expectation, corrosion losses were found on Internal inspection
the external side of the sparger instead of the internal side. It was difficult to understand why the sparger had corroded
Measurements were carried out on one of the removed on one side of the deaerator only, therefore, a more
sparger arms and are shown in Figure 4. detailed visual inspection was carried out. The aim was to
see if there were any deposits in the sparger arms that may
One can clearly observe that towards the area where the have hampered proper flow through one side creating a
sparger was damaged, the external diameter decreased. preferential flow towards the corroded side. [Note that no
Figure 5, shows an area where corrosion has occurred but deposits were found during the initial inspections by both
not as dramatic as on the other sparger arms. One can still plant inspectors and technologists.] This detailed visual
see the location of the holes, but that they have grown from inspection resulted in the following:
7mm to 20mm.

10
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Tube row counting started from the “cold” or good side of corrosion associated with high purity, low oxygen
the deaerator. condensate (or boiler feed water) caused by the relative
movement of the fluid against the metal surface. Metal
l Tubes first row loss results from the removal of the protective oxide film by
West: some debris inside near drain hole localised turbulence. In SRCPDs case, the corrosion was
East: some debris and wire mesh parts found inside found to be on the waterside of the deaerator near the exit
l Tubes second row of the LP steam (holes). The LP steam causes turbulence
West: debris and pieces of wire mesh inside tube end around the sparger holes and increases the relative velocity
East: clear of the water near the surface of the pipe. Critical factors for
l Tubes third row FAC (Ref. 1) are given below:
West: small amount of debris inside, pieces of wire mesh
present inside l Velocity above 2.1m/s can remove oxide film
East: clear l Damage is aggravated by localised turbulence
l Tubes sixth row l pH is usually below 9.3 (note that the feed water is
East: debris and wire mesh inside controlled between 8.5 and 9.3)
l Tubes eighth row l Maximum damage at 140ºC (one phase flow) to 180ºC
East: deposits/debris found inside (two phase flow)
l Tube ninth row l Corrosion rates between 0.10–10mm/year
East: deposits found l Oxygen levels below 15-20ppb do not allow the

l Tube eleventh row protective film to become stable


West: wire mesh particles found inside tube towards drain
hole It will be difficult to establish the liquid velocity near the
area of failure, but it would not be difficult to believe that
All other tubes on the south side not mentioned above were the relative velocity of the feed water is higher than 2.1m/s.
clear. All remains of the tubes on the north side were clear. The pH of the feed water (combined polished condensate
and demin water) is usually controlled between 8.5 and
The source of the wire mesh could not be established. 9.3, exactly in the range where FAC can be expected. As
indicated above, the temperature of the feed water outlet
Another observation was made on the shell; the water level at nozzle N3 is around 150°C right in the temperature
seemed to be higher than the level that was indicated in the window where the highest corrosion rates are expected.
drawing. The feed water level inside the drum could clearly The oxygen levels in the feed water are normally controlled
be seen as manifested by a change in colour on the vessel between 10–20ppb; at these levels it is difficult for
shell. Figure 1 shows a schematic of the deaerator vessel. magnetite (the protective film) to become stable.
The Normal Water Level (NWL) as given in the detailed
construction drawing is set at 1750mm. The actual height Discussion
of the water level appears to be 800mm higher. There is a In order to get corrosion on one side of the sparger
lower level towards the feed water outlet. From this info one header only, there has to be some kind of maldistribution.
can see that there is a slight difference between the “cold” Maldistribution can be caused by blockage of the header,
and “hot” side of the vessel. on the side where demin water is injected. During the
blockage all steam will be diverted to the side where the
According to the manufacturer, the calculated velocities of feed water take-off nozzle is located. To maintain the same
steam (based on provided data) are as follows operating duty (FW outlet temperature, FW throughput and
oxygen levels) more steam needs to be injected adding to
l Inletpipe: 80m/s the already increased steam velocity at the sparger holes.
l Horizontal headers: 68m/s each; 137m/s if one is This than leads to the flow accelerated corrosion described
blocked above.
l Sparger pipes: 79m/s each (42 in total); 151m/s if the

horizontal header at side of demin water inlet is blocked The blockage has most probably been caused due to
l Holes (59 with diameter 7mm) give the same velocity in incidents in early 2005. On 13 January 2005, the larger
all sparger pipes if all holes are opened part of Peninsular Malaysia was affected by a power grid
It was calculated that the velocities, in the case where one failure. The loss of power caused an automatic shutdown
side is blocked, are unacceptably high and will lead to of SRCPDs LRCCU, inclusive of the boiler system. During
erosion. the crash shutdown, catalyst (aluminium-silica) entered the
steam system and collected in the clean condensate tank.
Flow accelerated corrosion The following month, a superheater tube in the CO-boiler
The most likely form of degradation that has severely ruptured. A significant amount of BFW was consumed to
thinned the sparger arms is Flow Accelerated Corrosion quench the flue gas line that resulted-in a drastic drop in
(FAC). FAC is the cause of many failures in boiler / steam the clean condensate tank level. At low tank level, the silica
generating facilities. FAC manifest itself as thinning loading in the clean condensate feeding to the Mixed Bed

11
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

increased significantly, due to the leaching from the cat fines LP steam in the sparger header. A detailed visual inspection
collected at the tank bottoms. This was suspected to have led of the spargers on the demin water side of the deaerator
to high silica in the steam, which eventually fouled the Wet confirmed the presence of debris and other solids in the
Gas compressor turbine. sparger arms.

It is suspected that due to the incident above, the silica in the The power failure of 13 January 2005 is most probably
LP steam had deposited in the steam nozzles at the demin the initiator for the blockage in the sparger and certainly
water inlet side (which is the colder side). had an effect during the first days after start-up. However,
the operational data suggest that the “normal” operating
Operational data of the period around the January power window was resumed within one week after start-up with
failure suggest that immediately after the start-up, more no measurable evidence of any obstruction in the sparger
steam at higher temperature was required to deaerate less header/arms.
feed water at lower temperature, suggesting that there is
some kind of restriction in the steam sparger. Although it Under normal operating conditions without blockage
appears that these higher steam demands only lasted for a leading to preferential flow, the deaerator should be able to
couple of days and to destroy a pipe with a nominal wall perform its function without the degradation observed.
thickness of 3.6mm needs more time than that. Even at the
highest corrosion rate for FAC (10mm per year) it would Reference:
take more than 4 months to fully consume the pipe wall 1. Damage Mechanisms Affecting Fixed Equipment in the
thickness. Hence, if the events of January 2005 are the Fossil Electric Power Industry WRC Bulletin 490,
initiator of the severe corrosion, the (partial) blockage of the March 2004, Jonathan D. Dobis and David N.French.
tubes must have been sustained for months after the power
failure. For more information please contact the author:
Reggy Fransz (r.fransz@shell.com)
Conclusions
The failure of the sparger arms is caused by Flow
Accelerated Corrosion caused by a maldistribution of the

Root Cause Investigation of Hydrogen Blistering and HIC of a HCU Fuel


Gas Scrubber in a Canadian Refinery

In a 2004 Hydrocracker turnaround, hydrogen blisters were Condition of the Steel Plates
found in an amine fuel gas scrubber in a Canadian Refinery. The material for the scrubber vessel was specified as ASME
Figure 1 shows plate sample removed from the vessel. Section II-A A516 Grade 70. Chemical analyses of selected
This damage resulted in the replacement of the pressure shell courses showed that the chemical composition of the
vessel. Initial investigation by the client did not reveal any steel was within the limits specified by ASME. However,
obvious causes that could explain the observed hydrogen significant concentrations of inclusions were found existing
blistering damage. Subsequently, Shell Global Solutions was in highly banded conditions (see Figure 2). These are
requested to assist in the investigation of the root cause(s) of most likely manganese sulfide impurities (also called “MnS
the damage.

An amine gas treating process specialist and a corrosion


specialist from Shell GSUS joined the client’s investigation
team. The expanded team requested additional inspection
and non-destructive testing (NDT) of the scrubber, more
detailed metallurgical analysis, and longer-term historical
process and operating data. The additional inspection and
NDT revealed severe hydrogen induced cracking (HIC)
in addition to the hydrogen blistering. All damage was
confined to the lower section of the scrubber. Metallurgical
analysis indicated that the steel plates used for the vessel
were highly susceptible to HIC. Furthermore, the amine
scrubber vessel had historically operated with very high rich
amine loading. The combination of these factors led to the
observed hydrogen blistering and HIC damage.
Figure 1. The Plate Samples Removed from the Vessel

12
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
stringers”). They were left in the steel during the steel making
process and were elongated during the rolling operations in
making the pressure vessel plates. These stringers are known
to act as initiation sites for hydrogen blistering and HIC.

MnS Stringers

Figure 3. Cross-Section Macrographs Showing the Density of Inclusions and


Hydrogen Blistering and HIC

Figure 2. Micrographs Showing the Steel Microstructure and Manganese Sulfide


(MnS) Inclusions (Mag. 500X) used to fabricate the scrubber were highly susceptible to
hydrogen blistering and HIC damage.
Cross-section macrographs in un-etched condition (see
Figure 3) clearly show the subsurface delaminations Process and Operating Conditions
occurring at multiple planes inside the steel plates and This vessel has been used to scrub H2S from the various
features of HIC (“stepwise cracking”). These macrographs vent gases from the Hydrocracking Unit (HCU) before they
also show the high concentration of MnS stringers present are routed to the refinery fuel gas system. The system used
inside these steel plates. 15% monoethanol amine (MEA) from 1984 to 1996, then
switched to 50% dimethylethanolamine (MDEA or Ucarsol
It is worth noting that there were no shallow blisters near HS-101) in 1996, primarily for energy conservation.
the tower ID surface from these cross-section macrographs.
Nearly all of the blisters observed were created by The earlier investigation efforts by the client focused on the
subsurface delaminations located at approximately 30% rich amine loading data for the most recent two run cycles
wall from the ID surface. Hydrogen blistering caused by (i.e. between 1996 and 2004). The acid gas loading of the
short-term, accelerated corrosion often creates near-surface combined rich amine from the scrubbers (a total of 4) during
blistering and detectable metal loss. Absence of such this period has been generally less than 0.5 mole H2S/mole
shallow blisters suggests that these blisters may have been amine. The number of weekly samples where the acid gas
a result of long-term corrosion and associated hydrogen loading exceeded 0.5 mole/mole was less than 3% of the
charging. total samples.

A proprietary, semi-quantitative predictive model was used Examination of the metallurgical results prompted the team
to assess the susceptibility of these steel plates to HIC. The to investigate long-term process data, especially those prior
metallurgical variables and chemical composition were used to 1996. It was discovered that the amine circulation rates
as input to the model. The results are shown in the following were historically low before 1996 (see Figure 4). This trend
table. had at least occurred since 1988 and possibly earlier. This
had resulted in a rich amine loading in excess of 0.8 mole
Shell Course No. 3 4 5 6 8 H2S/mole amine. Highly loaded rich amines are well known
for causing hydrogen charging and associated hydrogen
Susceptibility 11.5 8 14 13.5 14 blistering and HIC. In fact, highly loaded rich amine had
caused severe corrosion in the feed section of the unit’s
downstream regenerator tower.
A score of less than 6 generally indicates that steel has a
good resistance to hydrogen blistering and HIC. A score Recommendations
of 6-8 indicates that the steel is susceptible to hydrogen In order to prevent future recurrence, the following actions
blistering and HIC. A score of 10 and above would indicate were recommended to the client: (a) establish an upper
that the steel is highly susceptible to hydrogen blistering operating limit of 0.45 mole H2S/mole amine for the rich
and HIC. Based upon these criteria, all of these steel plates amine loading; (b) benchmark the susceptible areas of the

13
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

scrubber tower and inspect with UT methods for potential For additional information, please contact Deyuan Fan at
delaminations as well as thinning in future inspections. deyuan.fan@shell.com

Rich Amine Loading


Flow of 15 wt% MEA/50 w% MDEA Reqd for 0.4 mol/mol Rich Loading
Inlet H2S @ Design Value of 42.2 lbmol/hr, Semi Lean at 110 M3/D
M3/D
500

MEA Actual, M3/D

400 MDEA Actual, M3/D


15 wt% MEA Target
15 wt% MDEA Target
300

200

100

0
Dec 92

Dec 00
Dec 90

Dec 94

Dec 98

Dec 02
Dec 96
Dec 88

Figure 4 Historical Amine Circulation Rat

Degradation Prediction and Assessment Models Coming to CWW

We have begun the development of a set of comprehensive


Corrosion and Metallurgical Degradation Prediction and
Assessment Models. These tools integrate years of Shell’s
technology development as well as industry knowledge. The
models can be used for both Downstream and Upstream
applications. The models enable field engineers to reach
expert opinion regardless of distances and time zones.

Access to the models will exclusively via the Customer Wide


Web (CWW). Once a user is authenticated by CWW for
proper license, he/she can assess the newest release of the
model. There will be no worries about updates or upgrades
as these changes will be automatic The user can store and
retrieve his/her input and outputs directly on the web or
on local discs. All the models will have similar “look and
feel” input and output user interfaces. Figures 1 and 2 Figure 1. NH4HS model input screen
show sample input and output screens for the ammonium
bisulphide corrosion prediction model.

14
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
The corrosion prediction modules currently are highly
fragmented in industry. Most engineers continue to use
the various published simple curves and charts to predict
corrosion in complex systems. The technical modules in the
API RBI software tools are known to be highly conservative.
Shell possesses over half a century of corrosion technology.
Some have evolved into predictions tools, such as
HYDROCOR and ASSET, which are well recognized in the
oil Industry.

The long-term plan is to consolidate all existing models into


a web-based environment such that the customers can have
direct access. We are also investing in additional R&D to
develop new models and add data to the existing models.
Figure 2. NH4HS model output screen When fully developed, we will have models covering the
most relevant corrosion and metallurgical degradation
We are currently working on the following models to make mechanisms occurring in oil and gas production, refining,
them ready for release1: and petrochemical facilities.

Predict-SW®2 (Ver1.0.2) - NH4HS Corrosion In the future, interfaces will be made such that these
models can be integrated with corrosion control and other
CORRAT – Simplified CO2 corrosion asset management tools. For example, interfaces will be
constructed such that these models can input real time data
HYDROCOR – CO2/H2S/O2/MIC/Organic Acids from the DCS or process computer. This will allow corrosion
rate be calculated online and damage be accumulated
HCl Corrosion – simple model based upon pH over the entire operation cycle for a piece of equipment or
piping.
H2SO4 Corrosion – Empirical data and correlations
If you have any questions about the development and access
H2SOv (II) – Advanced H2SO4 corrosion models to these models, please contact Andrea Etheridge
(andrea.etheridge@shell.com) or Bert Pots (bert.pots@shell.com).
NH4Cl – Shell proprietary data

SNAC – Shell Neutralize Amine Corrosion


1 Access to these models may be restricted based upon the
HTHA – High Temperature Hydrogen Attack business relationship and contractual agreements.
2 Predict-SW is a registered trademark of Honeywell-

Releases of these and other new models will be announced InterCorr.


via the Newsforums.

15
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Materials analysis of Pernis FCCU 44-year-old C-0.5% Mo reactor


vessel
During the April/May 2002 shutdown at SNR Pernis,
equipment from the Catalytic Cracker 2 (CC2) unit was
replaced. SNR Pernis observed upon dismantling the
equipment, that it was very brittle. Samples from the C-
0.5%Mo reactor vessel and upper riser section and from
the 310SS reactor lower riser section were sent to Shell
Global Solutions, Amsterdam. The condition of the C-
0.5%Mo reactor vessel material, after 44 years of operation,
was of particular interest for the reference of other sites
with similarly designed equipment of the same era still in
operation.

Metallurgical assessment of the C-0.5%Mo reactor


vessel weld (sample A) and wall (sample B, Figure 1)
microstructures showed no significant modification over the Figure 1. C-0.5%Mo reactor wall (sample B); fairly equiaxed fine grains of
44 year service life; however the C-0.5%Mo reactor riser ferriteand pearlite with most carbides as speroids and some remnant
(sample C, Figure 2) did seem to have undergone significant pearlite
modification.

Typically hydrocarbon feed and catalyst in a reactor riser


reaches temperatures of 650-730°C, decreasing to around
540°C at the riser outlet. The reactor generally sees a
temperature range of 510-540°C. The higher thermal
energy that would have been available to the reactor riser
is likely to explain why this material (sample C, Figure 2)
underwent significant transformation of pearlite grains to
smaller ferrite grains; while the reactor vessel (sample B,
Figure 1), operating at a lower temperature, showed the
presence of grains of both ferrite and the original pearlite.
As a consequence, where no degradation of the C-0.5%Mo
material had taken place a lower (and better) ductile-to-
brittle-transition-temperature (DBTT) in the range 0-40°C
was exhibited, with an average ambient fracture toughness Figure 2. C-0.5%Mo reactor riser (sample C); fine ferrite grains, very few
of 70J. Where degradation of the material did take place carbides within grains most located on grain boundariesv
a higher (and worse) DBTT in the range 20-100°C was
observed, with an average ambient impact toughness of 9J.
These results are shown in Figure 3 and are in line with the carbide formation at the grain boundaries, however this
SNR Pernis’ observation that it was very brittle. should be expected after 44 years of operation within the
sensitizing termperature range (370-815°C). As expected,
Hence, higher oprerating temperatures of the C-0.5%Mo neither sample exhibited a DBTT.
material leads to greater material degradation and poorer
mechanical properties. In particular, the DBTT is a critical This study has provided additional information on the
factor to consider when specifying minimum pressurization properites of C-0.5%Mo steel after long service exposure.
temperatures of C-0.5% pressurized equipment; this is However, the degradation behaviour of this equipment
especially important as the initial impact toughness is shown is already addressed properly in current SGSI operating
to be quite low even before any material degradation has procedures and the materials degration library, therefore,
taken place. there is no need to modify current practices for these
materials. The possibility of degree-of-sensitisation (DOS)
The appearance of the 310SS dissimilar metal weld material testing austenitic stainless steel material in shutdowns should
(sample D), between the 310SS lower section of the be considered to avoid soda ash wasing for polythionic
reactor riser (sample E) and the C-0.5%Mo upper section acid stress corrosion cracking (PTASCC).
of the reactor riser (sample C) was consistent with fresh
as-deposited filler material. The parent 310SS lower reactor For further information please contact Natalie Beer, GSEI/1
riser material appeared somewhat degraded with some (natalie.beer@shell.com).

16
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Absorbed Impact Energy

A: C-0.5Mo reactor weld


B: C-0.5Mo reactor wall
C: C-0.5Mo reactor riser
D: 310 dissimilar riser weld
E: 310 reactor riser

Temperature

Figure 3. Plot of Charpy (Cv) Impact values as a function of temperature for various sections of the FCCU reactor vessel and reactor riser

Rhineland Refinery Hydrocracker Piping Leak

Introduction that was measured in water collected after the unit was shut
Godorf (Rhineland Refinery North), in September down.
2005 experienced a piping leak in a small bore drain
nozzle located in the outlet piping spool from one of the The plant
Hydrocracker reactors. The failure was due to internal The Godorf Hydrocracker unit consists of two trains of
Chloride Stress Corrosion Cracking (Cl-SCC). The source of 3 reactors in series, as schematically displayed in Figure 1:
chlorides was traced to the make up hydrogen from the CCR
Platformer. Hydrogen chloride is normally removed from the Chloride related problems such as pitting corrosion or
hydrogen make-up stream in chloride guard beds. However, Cl-SCC have previously not been experienced in this unit.
it is believed that sub-optimal operation of the chloride However, NH4Cl fouling has been experienced in the
guard bed resulted in a period of high chloride carryover. recycle gas heat exchangers.
The make-up H2 gas chloride catchers were out of service
during the first three weeks after HCU start-up in May 2005.

Another key learning from this incident is the finding of low


pH water phase in the insulated drain nozzle attached to the
reactor outlet line operating at 370-390ºC. It is estimated
that the temperature of the nozzle during operation was
around 150ºC on the outboard end near the valve location.
At these conditions, one would expect the nozzle to be
‘dry’ due to low vapour pressure of water in the process.
However, it is thought that the drain nozzle filled with water
during startup. Evidence was found that water remaining
from hydrotesting was present in the furnace tubes - this
water may have been pushed into the reactor and settled
out in the low point drain nozzle. Subsequently, the water
in the nozzle absorbed a significant amount of HCl and
then may have sealed off after being covered with a layer Figure 1. Line-up of the reactor section
of heavy waxy hydrocarbon. This would explain the water
remaining in the deadleg as well as the low pH condition

17
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

The Incident Process Sampling


The 2” (DN50) drain nozzle on the outlet pipe spool of After seeing what seemed like deposits in the nozzles on
R-7405 was found leaking through the insulation. the radiographs, it was agreed to sample and analyse
Removal of the insulation from the drain nozzle revealed any fluids and solids remaining in the drain nozzles. After
hydrocarbons and hydrogen weeping from just above the depressurising, separate fluid samples were taken from
second weld above the 2” drain valve (see Figure 2). The below and above the valve in each drain nozzle. Samples
leak appeared to be coming from crack-like defects. of the deposits found in the nozzles were taken once the
nozzles were cut-off. A summary of the analysis results for
Because the leak progressively worsened and visually the the liquid samples were as follows:
leaks appeared to be from small cracks, the unit was shut
Tr a i n 1
down in a controlled manner for investigation and repair.
R - 7 40 1
A taskforce was commissioned to investigate the cause of the R e ac tor R - 7 40 5
cracking and to work out a repair proposal. After reviewing U/ V B/ V AVG B/ V A/ V AVG
the prevailing process conditions and the materials of pH 3.7 4.3 4.0 6.1 9.0 7.6
F- mg/l 26 109 67.5
construction (Werkstoff 1.4541, equivalent to stainless steel
Cl- mg/l 427 56 241.5
type 321), internal and/or external Cl-SCC were postulated SO4 -- mg/l 1853 553 1203
as the most likely causes for the cracking. pO4 --- mg/l
NO3 - mg/l 3 3
Non-destructive Testing
Tr a i n 2
Non-destructive testing (NDT) was carried out to establish
R - 7 40 6 R - 7 40 3
whether the cracking initiated internally or externally and to R e ac tor
establish the extent of cracking in the unit. This work started B/ V A/ V AVG B/ V A/ V AVG
while the unit was shutting down. pH 5.2 5.1 5.2 8.7 9.0 8.9
The scope for NDT was agreed to be the small-bore branch F- mg/l 27450 24730 26090 48 145 96.5
Cl- mg/l 2840 2920 2880 213 321 267
connections on the reactor piping from between the first
SO4 -- mg/l 87960 95130 91545 1052 1590 1321
reactors and the first feed/effluent heat exchangers in both pO4 --- mg/l 534 534 9 9
reactor trains. Furthermore it was decided to try to check
some of the welds in the main piping as well. A combination A/V = above valve, B/V = below valve, AVG = average
of Radiography, Eddy-current, Ultrasonic Flaw detection
and Liquid Penetrant techniques were employed for the
inspection.

Figure 2. Location of leak

18
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
The amount of liquid obtained from the R-7402 and
R-7404 outlet line drain valves was too little to determine the Inside surface
chemical composition. A sample of the salt-like solids found
on the inner surface of the R-7405 outlet line drain was
analysed. It too contained chlorides.

Metallographic Investigations
The failed R-7405 drain nozzle was taken to a specialised
laboratory for metallographic investigation. After cutting Cracked surface
and cleaning of the sample, various cracks in the cross-
section cuts, starting from the inner surface of the sample,
were already visible with the naked eye. The sample was
then examined in the as-cut state in a scanning electron
microscope (SEM). Fine cracking typical of Cl-SCC were Figure 5a. Crack surface
visible in the cross-section, see Figure 3. The cracking
started from the inside surface.

One of the cracks was broken open to examine the crack


surface. The crack surface was typical for Cl-SCC, running Chloride, Cl-
transgranular and showing numerous branch cracks, see
Figure 4. Finally, a map of chloride-ion occurrence on
the crack surface was made using the energy dispersion
spectrum (EDS) technique, Figures 5a/b.

Outside Surface

Figure 4 Figure 5b. Chloride map (EDS)

Crack

Inner Surface

Figure 3. Circumferential cross-section

Transgranular Crack

Figure 6. Metallography showing cracking near weld root – internal surface


of nozzle.

Branched Cracks Chloride Stress Corrosion Cracking


The conclusion from the metallographic investigation and
sampling that the cracking appeared to be Cl-SCC initiated
on the inner surface of the nozzle.
Figure 4. Opened crack surface
For Cl-SCC to initiate and propagate six conditions are
Metallography performed by Shell Global Solutions in needed:
Amsterdam confirmed Cl-SCC initiating from the inside of
the drain nozzle as the cause of cracking, Figure 6.

19
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

1. Susceptible material; the construction material used for Chlorides


the drain nozzle (and all other reactor circuit piping) The source of the chlorides found in the drain nozzles is
was Werkstoff 1.4541, welded with 1.4551 (German most probably chloride carry-over from the Godorf CCR
equivalents of stainless steel type 321 and type 347 Platformer (PFU3). This unit is the main Hydrogen supplier
respectively), which is susceptible to Cl-SCC. for the Hydrocracker unit (HCU). Chlorine/Hydrogen
chloride is normally removed from the Hydrogen make-up
2. Tensile stresses; Residual stresses due the welding stream from PFU3, but nevertheless chlorides have known
operations and hoop stresses due to the operating to still be present in the Hydrogen. Suboptimal operation of
conditions were present in the material. the Chlorine catchers may have aggravated this situation;
during the first three weeks after HCU start-up in May 2005
3. Metal temperature above 60°C; At normal operating the make-up H2 gas chloride catchers were out of service.
conditions the temperature of this branch is well over Under normal operating conditions with the chloride catcher
60°C. on line the chloride slip through the catcher beds is less then
2ppmw. However, without the chloride catcher in service
4. Chlorides; chlorides were present in the drain nozzle as the chloride content of the H2 make-up gas may be up to
could be seen from the analysis of the samples of fluids 25 ppmw.
and solids taken from the failed nozzle. chlorides were
also present in the cracks (see Figure 5b). Free water
Free water in the reactor system cannot readily be
5. Free water; Again as can be seen from the liquid samples explained. The system is normally considered to be “dry”.
taken from the drain nozzles, liquid water was present in Water will be present in the process stream, but under the
the nozzles. Explaining why and how free water could be prevailing process conditions it should not condense.
present there under the prevailing conditions however is
not straightforward and needed separate investigation. Potential sources of free water that were identified were:
• Process water; Water is being formed in the
6. Oxygen or low pH; A cathodic reaction is needed to Hydrocracking process; in the reactors any oxygen-
electrochemically balance the anodic metal dissolution containing components in the feed will be hydrogenated
reaction (the “cracking”). Under atmospheric conditions to water (O + H2 → H2O). Under the prevailing process
Oxygen takes part in this reaction, under acid conditions conditions it should however not condense out in process
H+-ions (protons, the “acidity”) can take the place of stream or at least stay dissolved in the process stream.
Oxygen. Free water from process water under the prevailing
conditions is unlikely.

370°C

20° 273°C 200 mm


C

175°C
50
60

180 mm

Figure 6. Nozzle temperature profile

20
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
• Water remaining from hydrotesting; The affected piping Causes for acidity are most likely the chlorides dissolved and
was newly installed during the last shutdown and the high levels of Fluorides found in the first two nozzles.
subsequently hydrotested. Water may have remained The most likely source of the Fluorides is the pickling process
in the system even after draining. During start-up it was carried out in the final stage of production of the stainless
found that one of the furnace passes was blocked. With steel reactor piping. Although every care was taken to
some effort this was cleared (via the reactor system). An rinse the system using demin water after the pickling and
explanation for this could be that testing water passivating operation until neutral solution pH was reached,
from the feed effluent exchangers found its way to the the only credible source of Fluorides is the pickling solution.
furnace where it blocked a furnace pass. This water was In the second pair of nozzles the pH was substantially
subsequently moved through the entire reactor system. higher, probably due to Ammonia (NH3) dissolving in the
• Water in feed; The feed is drawn from a tank, at most the water at this stage, also lower levels of Fluorides were found
feed is saturated with water, i.e. any water carried in the here.
stream is dissolved. Free water would cause problems at
the feed pumps, here the temperature is 180°C, water The difference in pH between the first and the second pair
vapour would form and the pump would cavitate. This of nozzles can explain why cracking was only found in the
is not experienced and free water from the HCU feed is first pair. At higher pH (>7), Cl-SCC can only occur in the
therefore unlikely. presence of Oxygen. The difference in pH between Train 1
• DIPA entrainment in recycle gas; Another source of water and Train 2 can explain why substantially more cracking is
could be entrainment of DIPA in the recycle gas (H2) found in the R-7405 drain compared to the R-7406 drain.
from the H2S scrubber. Water entrainment via this route
is unlikely however, it would have to pass through a Probable Root Cause
knockout drum/demister and a compressor. As mentioned the cause of the cracking in, and subsequent
Apart from free water, also a location must have existed leaking of, the R-7405 reactor outlet piping drain nozzle is
were this water could remain, below its boiling point. Due Cl-SCC. Similar cracking was found in the equivalent nozzle
to their physical dimensions the drain nozzles form potential on the outlet piping of R-7406. Cl-SCC in these two nozzles
cold-bridges. The nozzle and the valve are insulated was initiated by the presence of free water containing
under normal operating conditions, but the valve handle is chlorides at a low pH and at elevated temperatures.
protruding from the insulation. Moreover, the insulation on Water has most likely been trapped in the drain nozzle
the nozzles was only installed a few days after start-up, this during the unit start-up phase. Sources of water could have
to check for flange and valve leaks during and after start-up. been process water and/or remaining hydrotesting water.
The water was trapped and allowed to remain as a result
Initial estimates (1st order simulation) show that that the of prevailing low temperatures in the nozzle and by the fact
temperature drop in a drain nozzle like was installed, is that the water was probably covered by a layer of heavy
considerable. As can be seen from Figure 6, assuming that hydrocarbons.
the nozzle was full of stagnant liquid and evenly insulated, Chlorides were present in the water due to fact that during
the temperature drop over the nozzle is some 200°C (from start-up chloride catcher operation was suboptimal. This
370°C main process temperature to about 175°C just caused high levels of hydrogen chloride (HCl) in the process
above the drain valve). A temperature profile measured gas, which dissolved in the water trapped in the drain
on-site using a hand-held contact thermometer stuck into the nozzle. This and high levels of Fluoride found in the nozzles
insulation at the nozzle directly opposite the failed nozzle caused acidification of the trapped water (i.e. low pH).
in the vertical up position, was in good agreement with this Ammonia, increasing the pH in the water, does not seem to
result. Measurements here ranged from 300°C close to the have dissolved in the water in these nozzles yet.
main line down to around 150°C in the vicinity of the first
valve. Even at full operating temperature the liquid in the drain
nozzles stayed at temperature levels of around 150–200°C,
Under normal conditions it is thought that even when which at the prevailing operating pressure is low enough to
temperatures drop in the drain nozzles eventually the water induce chloride stress corrosion cracking
will disappear from the nozzles because to the “dry” process
gas flowing above it. It is likely however that the water in the Why now and not before?
nozzle became covered with a layer of waxy hydrocarbons This is a valid question as stainless steel drain nozzles
during operation, preventing the water from evaporating. have been in service for a long period without giving rise
problems like this. What was different this time?
Oxygen or Low pH
As can be seen from the analysis of the liquid drained from An explanation could be that due to the changed reactor
the drain nozzles, the pH in the first two drains is low (4-5). configuration after the new first reactors (R-7405/06) the
Conditions prevailing under the solid deposits found on hydrocarbons are still relatively heavy. Essentially the heavy
the inside surface of the nozzles were probably even more feedstock is at this stage only hydro-treated (i.e. Sulphur,
acidic, which can be deducted from the fact that general Nitrogen and Oxygen removed). This allowed a wax cap to
corrosion of the stainless steel surface was found there. be formed over the water in the drain nozzles.

21
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

In the past the feed at the first drain nozzle was already Remedial Actions
partially cracked into lighter hydrocarbons, maybe After establishing that the likely cause of cracking to be
incapable of forming such a stable wax cap. In the latter Cl-SCC, it was decided to eliminate all six reactor outlet
case, water, potentially even containing chlorides, would line drain nozzles and replace them with caps, minimising
have evaporated from the nozzles rather fast, not allowing the remaining potential low-point liquid trap. All remaining
time to initiate Cl-SCC. stainless steel nozzles in the reactor system were inspected
and as far as could be established crack-free. Also no
further fouling or corrosion was found. The start-up
procedures were reviewed to minimise the risk of Cl-SCC.

For more information please contact Pieter Blauvelt


(pieter.blauvelt@shell.com) or Jan Vonk (jan.vonk@shell.com).

22
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Anchors away!

A summary of the work involved replacing refractory anchors in the CO Boiler at Stanlow
Manufacturing Complex.

As part of Stanlow’s Catalytic Cracking Unit, the CO To select the most appropriate upgraded material, Group
Boiler captures energy available from CO in addition to experience was sought through Shell Global Solutions.
eliminating it as a pollutant, preventing it being released to Given availability of various alloys to the site, Inconel 601
atmosphere. This is done by converting carbon monoxide was selected as being the most suited to the application.
(CO) to carbon dioxide (CO2) by combustion. The low Supporting the material change, and to give further
pressure flue gas exhausting from the Power Recovery confidence of increased component lifetime, the anchor
Train is routed to the CO Boiler where it is utilised as fuel. design was modified such that a larger boss and thicker
Supplementary firing of the CO Boiler is by fuel gas, and section bar were used.
by maintaining a constant temperature in the boiler this fuel
firing ensures total CO combustion before the flue gases are An external laboratory performed further failure analysis.
released to atmosphere. From the investigation, it was concluded that sigma phase
had formed in the anchors. Formation of this phase made
During October 2005, the CO Boiler at Stanlow was out of the anchor material susceptible to brittle fracture.
service for an unplanned turnaround following the discovery
of a leak in the lower evaporator section. Whilst the tube There were several factors that are likely to have contributed
replacement was being carried out, significant cracking was to failure of the anchors:
found in the shell refractory lining material. Three layers
are used in the insulation system of the CO Boiler system, • The configuration of the refractory in the CO Boiler.
as depicted in Figure 1. Associated with the cracking was The regions where failure occurred are those that are
the failure of a large number of the Type 310 stainless steel likely to have experienced the highest stresses due to
refractory anchors. It was intended to replace the refractory the orientation and thermal expansion of the insulation
anchors and insulation material within the restrictive system.
turnaround time frame. • The performance of the original insulation expansion
joints is unknown. It is postulated that the poor installation
Once damaged sections of the refractory had been removed of these joints led to excessive loading of the anchors at
it was possible to obtain samples of the failed anchors. the hot face – insulation layer 2 boundary. The expansion
Typically, the anchors had failed around the boss region, joints were reinstated as per specification to help prevent
either at the weld, the threaded portion of the shaft or the problem reoccurring.
the ‘V’-shaped legs (Figure 2). This region is the interface • The quality of the original anchor fabrication weld was
between the hot face layer and insulation layer 2. The observed as poor with respect to penetration. Cracking
preliminary investigation confirmed suspicions that the had occurred in both the weld metal and from the weld
anchors were embrittled. To gain further confidence of long- toe in the majority of anchors examined. Appropriate
term anchor performance, it was resolved to replace the weld procedures were used for the fabrication and
anchors in an ‘upgraded’ material. installation welds of the reinstated anchors.

It is stated in DEP 64.24.32.30-Gen. that Type 310 stainless Despite the size of the task, with in excess of 2000 anchors
steel is an acceptable material for the manufacture of being fabricated and installed, the job was completed
refractory anchors in service temperatures below 1100°C. successfully without increasing the turnaround interval.
This implies that the original specification anchors (i.e. Type
310 stainless steel) should be sufficient for the application; For further information please contact
given the design temperature of the boiler is 950°C. Doug Conquest (douglas.conquest@shell.com) or
However, cracking of the refractory material is likely to have Andrea Etheridge (andrea.etheridge@shell.com).
accelerated degradation of the anchor material by exposing
the anchors to the flue gas environment.

23
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Hot face layer


Refractory Anchor

Insulation layer 2

Insulation layer 1
Shell wall

Figure 1. Insulation system used in the CO Boiler (schematic representation).

Th r eaded boss

Stem
Leg

Figure 2. Typical failures of CO Boiler refractory anchors discovered during the recent turnaround.

24
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
UPSTREAM FALT, and the MCII sponsor is John Mossman (those of you
who attended the MIEM in KL may remember John attended
representing the FALT and was also involved in the MCII
Discipline Leadership in EP DEN team meeting held after the MIEM). There are
11 discipline engineering teams reporting to the FALT, and
MCII is one of the bigger disciplines, with 314 people in
This article is to give an overview of the EP discipline MCII in EP, based on the most recent data.
leadership activities carried out over the last year, and will
hope fully become a regular feature in the Rusty Chronicle. The MCII DLT is chaired by Ian Rippon, nominally called at
If you get lost with all the new acronyms Please refer to the present the Global Discipline Head (GDH), though the exact
a glossary at the end of this article. This reports the facts as title still needs to be confirmed by HR in SIEP and Global
they are at this time; there still may be some minor changes, Solutions. The DLT is made up of the discipline heads from
as part of the final review by SIEP and Global Solutions the regions (called RDH) and the discipline heads from the
HR departments and the final endorsement by the Facilities GTP (also called RDH). The current structure of the MCII DLT
Asset Leadership Team. is:

New technical leadership structure EPA Maimunah Ismail


In EP our discipline is now called the materials, corrosion, WillemVan Gestel
EPE (materials and corrosion)
integrity and inspection discipline (MCII); the big change
Hans Stoops (inspection)
here is the full incorporation of inspection within the MCI
EPG Godwin Ibe
discipline. The integrity element here reflects an alignment
EPM Nasser Behlani
with the downstream engineers, and the skill blocks you EPR Not yet assigned
see in the competence based development (CBD) tool are EPW Bill Grimes
the same skill blocks as now used by the downstream MCII E P T-P Maarten Simon Thomas
engineers. Jim Smith
EPT -W Bill Grimes
GSEI/2 Gert Kerkveld
The technical leadership structure in EP has just been GSEI/3 Peter Geenen
changed – this was rolled out in the Technical and GSEI/4 Sergio Kapusta
Operating Excellence (T&OE) meetings of 5-8 December BSP Ho, Kong-Nam
2005. SCAN Girgis, Magdy
WOODSIDE Brameld, Michael
PTE Not yet assigned
Technical Leadership Team (TLT) PTE Not yet assigned
GDH Rippon, Ian

This team includes all the regions, all the main GTPs and
Facilities Asset Leadership Team (FALT) other teams who are not fully represented in the regions
or the GTPs and gives a good representation of the MCII
structure worldwide. I’ll talk more about the PTEs below. It is
recognized there are some areas that are not well covered
MCII Discipline Leadership Team (DLT)
at present e.g. EPR (Russia) is a new region, and we have
no representative on the DLT yet for EPR yet (hoping to
The main change here is that the DLTs now report directly get one assigned in Jan 2006). There are also a few MCII
to the FALT, removing one level of management in between people, particularly those working as Shell secondees in
the DLTs and the FALT. (For those of you involved in this non operated ventures, who may feel they are not well
work prior to December 2005, the discipline team was represented by this structure; we hope to ensure all these
called the discipline expertise network (DEN), and there people are covered by the end of 2006. If anyone in MCII in
was a separate DLT that the DENs reported to; on this team EP is not clear who is their representative on the DLT, please
we were represented in 2005 by Ian Hines who did some contact Ian Rippon. The bold names in the table represent
sterling work representing and supporting the MCII team a core MCII DLT that you will see published on the T&OE
to T&OE and the FALT. In December 2005 each DEN has website; this only includes the regions, the main GTPs, the
become a new DLT (there are 11 DLTs), and the old DLT has PTEs and the GDH.
been disbanded.)
The role of the DLT
The FALT is chaired by Leo van der Aar, T&OE and made The DLT work on discipline capability management and
up of engineering managers from the regions and the technical management; a large number of items fall under
global technical partners (GTP). For MCII GTP covers mainly the DLT, including new and revised CBD skills blocks and
GSEI/2, GSEI/4 and EPT-P with some other engineers in profiles, skill pool staff database (who is in the skillpool),
EPT-R, EPT-W and GSEI/3. Each DLT has a sponsor on the standards (both regional and DEPs), discipline health checks,

25
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

cross posting, technology overview, succession planning opportunity to apply for promotion to JG1 when they are
(do we have the people and skills we need for now and ready for that step. Note also that introduction of these new
the future), training overview, practices worth replicating, technical positions does not mean that these are the only
portfolio management and integration (PMI – standardizing high job group technical positions - these are additional
software usage). We also have agreed on some specific positions to those that already exist in the technical structure.
technical goals that we want to work on globally in 2006,
covering MATHELP, the technical assurance framework and The GTC and the CS are not appointed by the FALT – there
gap analysis process and improving availability of corrosion are only a handful of these positions in the company, and
inhibition systems. The DLT agrees upon a global Discipline not all disciplines have a GTC or a CE position. This is a
Improvement Plan for each year, and this gets incorporated good point to congratulate Dick Horvath on this appointment
within the regional and GTP discipline plans, so there is - it is a fine reflection of the work he has put into the
alignment between global, regional and local goals. The discipline, both within Shell and in external bodies like
DLT has a monthly teleconference and meets together face to NACE International.
face at least once a year (usually at both the MIEM and the
annual NACE International conference). The DLT members The role of the PTE
are expected to spend 10% of their time on DLT issues. 34 PTE expertise areas have been identified under the
11 discipline engineering teams reporting to the FALT. Three
Role of the Global Discipline Head of these PTE positions are in MCII – the expertise areas are:
The GDH chairs the DLT, and in this capacity reports to
the discipline sponsor on the FALT (John Mossman in our • Materials Selection and Design
case); the GDHs are appointed by the FALT. The GDH is • Materials Performance in Operations
selected as one of the PTEs in the discipline, so has roles of • Inspection Engineering
capabilities management as well as technical expertise. The
GDH coordinates the preparation of the global Discipline It is recognized that this is not the most ideal grouping of
Improvement Plan with the DLT and ensures that all the skills within MCII; but this is a start and it may be possible to
deliverables of the annual Discipline Improvement Plan build a case for additional PTE positions in the future.
are allocated to the members of the DLT and that the plan
is implemented. The GDH works with the DLT and the The people who have been selected for these positions have
Global Skill Pool Manager (Harry van Langen) to develop not yet been formally appointed, so I cannot tell you who
and maintain the Discipline Resource and Strategy Plan they are at this stage; the names will be released in the new
(addressing staff competency and skills) and maintain year. The PTEs provide technical input to the DLT, and will
an overview of the global MCII population. The GDH is have key roles to play in providing input to the R&D and
expected to spend 33% of his/her time on GDH issues (note technology programmes, providing short term consultancy
this includes any PTE work covered below). on a call-off basis, actively managing the SGN and other
discipline tools (like MATHELP), leading expert networks (of
New technical positions SMEs and other specialists), representing Shell externally
Also rolled out at this time are the new principal technical with industry, institutions and universities and other work
expert (PTE) positions. Within the technical career structure supporting the DLT. The PTE expected to spend 25% of their
we now have the following new positions: time on PTE work. The PTE appointments are to individual
engineers; it is anticipated they would keep this role for a
GTC Global Technical Consultant Letter classified None currently in
MCII
long period of time, and take the role with them if they move
CS Chief Scientist – an innovation Letter Classified One in MCII – jobs to a different location.
and technology oriented Dick Horvath
position
PTE Principal Technical Expert JG 2/1 3 PTEs in MCII
The role of the SME
SME Subject Matter Expert JG 3/2 6 expertise areas The PTEs have a large set of roles and responsibilities,
identified within and cannot achieve this without relying upon networks of
MCII
technical experts throughout Shell. Six SME positions have
Appointment to these new positions is not an automatic been identified:
promotion, and promotion would have to be progressed
following the usual promotional route; they do however • Metallic Materials Engineering
extend the technical ladder by 1-2 job groups and give • Non-Metallic Materials Engineering
positions in which promotion is possible, and give additional • Materials Corrosion Engineering
higher job group technical positions in the discipline. For • Materials Mechanical Engineering
the PTEs, most of those selected are currently JG2; this new • Materials Asset Integrity Management
position will mean a change of position description from • Inspection Engineering
principal corrosion engineer to principal technical expert,
which is minor change! But it will give these people the Again these are quite broad grouping of skill groups; this
opportunity to have a more global focus, make use of their is a starting point and there may be a case for proposing
skills more widely within the company and give them the additional types of SME in the future. Regions or GTP may

26
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
not have SMEs in all of these 6 positions, either because • Some of the regions/GTP do not yet have enough CBD
they have no one of that skill level within the region or GTP assessors in the MCII discipline. Work is required to train
(and they obtain this service from a GTP or outsource it), up sufficient assessors; in the interim period the global
or because there is no business reason to have an SME in pool of MCII CBD assessors is being used. Note assessed
that position for that region (e.g. if only minimal amount of CBD profiles are required for any promotion or transfer.
non-metallic material is used, this could either be a case for
not having a non-metallic materials SME in that region, or a • The global survey of the MCII skillpool identified
very strong case for needing an SME (as maybe more non- 51 vacancies (16%); this reflects the growth in the
metallic materials should be used)). business (e.g. in EPR) as well as what is called as “the
big crew change”, with a large number of engineers
The current status is that every region/GTP has proposed retiring within the next 5 years. The primary methods of
SMEs; now that the PTEs have been appointed, they will addressing this shortage is through bringing in graduates
have to make these networks work, and one of the first and mature hires, though other methods are also being
tasks will be to assess the proposed SMEs and see who investigated. Work is ongoing to fill these positions, but
already clearly meets the technical requirements, or what the there is a global shortage of MCII engineers, both within
development needs are. This is still work in progress and the Shell and across the industry as a whole. The employee
SME position is not as well defined as the other positions. referral programme was rolled out in 2005 – this is where
At the time of writing final draft roles and responsibilities you can make a difference to this issue, by identifying
exist for the PTEs, the RDH and the GDH; these will be people who may be potential mature hires and if they are
incorporated into their 2006 personal performance interested registering them in the referral programme.
contracts, once these individuals are formally appointed.
• There will be one global graduate early career
Other Items development and assessment programme across the whole
Some other items to be aware of: of Shell, called “Develop”. This covers the first 3-5 years
of the new technical professionals within the company. The
• Averaging over the skillpool, 75% of the skillpool have programme will be formally launched in Q1 2006.
carried out a self assessment in the CBD system. If you
have not yet carried out your own self assessment, • Practices worth replicating (PWR) is in the process of
I encourage you to do this as soon as possible, and use being rolled out. What practices do you have that could
the data for development discussions with your team be used across the region or possibly globally? Note that
leader. The CBD web site is at http://swwep-w.shell. anybody can submit a PWR, and no item is too small to
com/people_ep/content/exp/competence/index.htm. There be considered a PWR. Do you know who your PWR focal
are various help document on this site. If you select the point is, who can help you submit a PWR?
CBD Application Tool this will give you the links to the
live application sites – pick the one most appropriate • MATHELP has been rolled out in all major regions;
for you (there is no Global Solutions site – EP staff in the system will really become effective as the EP MCII
Global Solutions should use the SIEP site). You will be support tool when engineers across the company start
asked for your user name (normal log in user name) and submitting data to be included in MATHELP. Do you have
a password; for first time entry select “forgotten your a spreadsheet that other people may be interested in
password?” and a new password will be emailed to you. using? Do you have a report/standard/specification that
Once in the tool there is a notice board, which again could be used as an example for someone doing a similar
gives more guidance and some FAQs. For first time users, piece of work in a different region? Do you have training
read the introduction section. Select “my CBD” and “my material or a presentation on a particular topic that
details” to set up the link to your supervisor and your may be of interest other regions, or other people within
offline reviewer (who should be a trained CBD assessor your own region? Do you have feedback on particular
– there is a link to a list of these on the front page of equipment / vendors that should be more widely shared?
the CBD application tool ) and what your skillpool is Do you know who your MATHELP focal point is, who can
- skillpool group discipline engineering, skillpool disc help you submit information for inclusion into MATHELP?
eng materials and corrosion (this includes materials and
corrosion profiles and separate inspection profiles). Select
“my CBD”, “competence assessment” and “start a new
competence assessment” to enter the tool. You will be
asked what profile you want to be assessed against.

27
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Glossary

Where would we be in Shell without some new acronyms for a new initiative? Here are the ones from this document:

CBD Competence Based Development


CS Chief Scientist – an innovation and technology oriented position
DEN Discipline Expertise Network – the old name for the DLT, now
superceded
DLT Discipline Leadership Team – team made up of the regional
discipline head and the heads of the Ep MCII teams in global
technical partners (Global Solutions and Ep projects), plus the lead
MCII engineers in other parts of the company not yet covered by the
regional and technical partner structure.
EpR Ep Russia – a new region split off from the old EpM
FALT Facilities Asset Leadership Team – team made up of the engineering
managers from all the regions and the global technical partners
GDH Global Discipline Head – chairs the MCII DLT and reports to the
MCII sponsor on the FALT. Note this title is not yet confirmed – this
is the 4th title for this position so far, so may change again.
GTC Global Technical Consultant
GTp Global Technical partners – for MCII this covers mainly GSEI/2,
GSEI/4 and EpT-p with some other engineers in EpT-R, EpT-W and
GSEI/3
MCII Materials, corrosion, inspection and integrity – the name of the
discipline in Ep
pMI portfolio Management and Integration – standardizing software
usage. These are the people who control GID scripting.
pTE principal Technical Engineer
pWR practices Worth Replicating
T&OE Technical and Operating Excellence
RDH Regional Discipline Heads – this covers the RDH in the regions and
is also used to describe the discipline heads in the GTp
SME Subject Matter Expert - 6 expertise areas identified within MCII

For more information, please contact


Mike Thompson (mike.j.thompson@shell.com) or Ian Rippon (ian.rippon@shell.com) MCII Global Discipline Head

Capacity Enhancement of the PTT Gas Supply Network

Work has recently been completed on increasing the supply an evaluation of the effect of gas specification changes to
and distribution capacity of PTT’s gas supply network. The the customers’ burners. The project not only had to find a
project delivered an extra 9% gas throughput capacity solution, but also had to deliver the capacity increase to the
that has an estimated benefit of $100MM/year based customer. This meant working together with PTT to prepare
on the value of the extra gas delivered to PTT customers. the system for the recommended changes. The extra gas
PTT is the former Petroleum Authority of Thailand, now throughput capacity was demonstrated by trial runs of the
a Public Company. PTT owns the gas supply network in system before and after the enhancement measures were
Thailand. PTT gathers gas from fields in the gulf of Thailand adopted.
and supplies large industrial customers and power plants
throughout Thailand. Two large diameter 410 Km pipelines The major contribution to the enhancement delivered by
bring the gas onshore at Rayong. The gas is processed at Shell Global Solutions came from de-bottlenecking the two
Rayong, and then sent through an onshore network to PTT’s 410 Km offshore gas export pipelines to Rayong. Most
customers. A third offshore line delivers gas to the southwest of the de-bottlenecking work was done by cooperation
of Thailand. between GSEI in Amsterdam and GSUP in Rijswijk. The
offshore lines had run at what was believed to be their
The project was an extremely broad ranging multi- maximum capacity for many years. Doubts about their
disciplinary project that covered all disciplines from gas condition prevented attempts to increase the capacity. The
compression offshore to onshore gas processing including capacity enhancement was supported amongst others by

28
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
GSEI/2 using fitness for service methods. GSUP worked
closely with PTT to prepare the lines for inspection so that
the actual condition of the pipelines could be assessed after
many years of service. An additional obstacle was that
sections of piping on the compressor platform had not been
fully hydrotested for the required pressure and one section of
the topside pipework/riser system was slightly undersized.

System stresses were applied to detailed FEA models to estimate local weld stress
for the fitness for service assessment of critical damage for the inspection survey

a hydrotest. The results of the inspection surveys showed


that there was no critical damage in the lines, which would
prevent an increase in Maximum Allowable Operating
Pressure (MAOP). The fitness for service work on the topside
pipework and risers required pipework stress analysis to
check on the system stresses and local finite element analysis
to check on detailed stress levels at Tees. The stress analysis
Bend and Tee in the 30” Export line work was carried out by GSEM and the results were directly
input to the fitness for service assessment.
Because sections of the lines had not been fully hydrotested,
it was necessary to use fitness for service methods and The uprating of the older of the two pipelines to Rayong
inspection to justify the enhanced pressures to avoid re- ultimately was not pursued as there were issues that could
testing the lines. not be resolved. The recommended pressure enhancements
to the other line had to be first approved by PTT’s insurers
before being applied to the system. Application of the
enhancements were made incrementally following a plan
developed by GSUP and PTT. The final step was to make
a test run of the system to verify the actual additional gas
throughput achieved.

The enhancements produced by de-bottlenecking the


two main export lines were a substantial part of the
improvement. Another substantial capacity gain was
obtained by a pigging program aimed to clean the
pipelines, where the resulting smoothing of the pipe wall
helped reduce friction losses and pressure drop, thus
increasing the pipeline’s capacity. Other smaller but still
significant gains were made elsewhere. Overall, the project
was the most wide ranging in terms of scope and depth that
Pipework stress analysis of the Tee joint and top of the riser on the platform the author has been involved in, which is a good example
of multidisciplinary thinking out of the box. An additional
A re-test was not feasible due to the extended loss of service feature of the project was the depth to which Shell Global
during the hydrotest. The lines would have had to have been Solutions worked with the PTT engineers in their operations.
de-gassed, filled with water and then de-watered and then
gassed up again. This would have resulted in weeks of lost For more information, please contact David Ritchie
production, which would have been unacceptable to PTT (david.d.ritchie@shell.com)
and their customers.

Inspection programmes organized by GSEI/3 and PTT


showed that the actual delivered thickness of the nominally
undersized sections were enough for the enhanced
pressure/capacity , and that there were no critical welding
defects present, which could have failed during

29
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Investigation of Un-Commanded Closures of EPW Surface Control


Subsurface Safety Valves
EPW has experienced a series of un-commanded closures The ball-check seat areas of the SCSSV hydraulic system
(UCC) of surface control subsurface safety valves (SCSSV) were also examined using SEM. Two gross damages, large
in several subsea production wells in Gulf of Mexico. In one impression on the seat shoulder and abrasion on the ID wall,
case, the SCSSV UCC of a 20,000 bbl/day production well were observed. Improper seating of the ball likely caused
led to 5-month shut-in (or $1.2MM/day loss of production the large impression; the pin likely caused the abrasion on
at today’s oil price). EPW retrieved the SCSSV for a full the ID wall (Figure 3). Many indentation marks on the seat
examination, which cost about $13MM. A team was formed surface, especially the metal-to-metal seal surface, were
to investigate the UCC cause that included EPW engineers, observed (Figure 4).
GSEI staff, GSUA staff and the SCSSV manufacturer.

GSEI/4 was initially requested to examine the compatibility


of SCSSV materials with the hydraulic fluid. However,
during the disassembly of the HAB-2 SCSSV, visible metallic
shavings were found in the hydraulic system even though
it has sub-micron filtering devices. GSEI/4 staff analyzed
the metallic shavings using scanning electron microscopy
(SEM) and the energy dispersive analysis of X-ray (EDAX)
as shown in Figures 1 and 2. Key findings are (1) large
size, some in millimeters, and significant quantity of metallic Impression
Abrasion
shavings were found in the system at various locations and on shoulder
on ID surface
(2) seven different types of metallic shavings were positively
identified. Only three types of metallic shavings, Alloys Figure 3. Schematic drawing showing the cause of damages in the ball-check
718, 825, and 925, can be associated with the component seat area.
materials. Four other foreign materials, which included two
silver brazing materials, C-276 and MP-35N, not relating to
SCSSV components, were found present.

Figure 4. Indentation marks found on the ball-check seat area.

The positive material identification (PMI) and microscopic


Figure 1. A large metallic shaving found in the SCSSV hydraulic system examination work conducted by GSEI/4 identified the
root cause of this failure. Introduction of large metallic
shavings and cross-contamination of foreign materials in
the SCSSV was likely caused by the inadequate QA/QC
process in the SCSSV manufacturing facilities. These
transient metallic shavings trapped in the ball-check seat
areas or the damages they created provided the leak paths
and prevented proper sealing of the ball check. This led to
un-commanded closures (UCC) of surface control subsea
safety valves (SCSSV). Based on these findings, EPW has
requested the SCSSV manufacturer to revise their QA/OC
procedure in their manufacturing process.

For more information, please contact: J. Chang


(jemei.chang@shell.com)
Figure 2. The shaving was identified to be Inconel 825 using SEM/EDAX

30
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
WATER FLOODING – MATERIALS SELECTION CHALLENGES

In recent years there has been an increase in the planned De-oxygenation had historically been done with vacuum
use of water flooding to maintain reservoir pressure and deaerators, which are well established and reliable.
enhance oil recovery in future oil fields. In fact many projects Unfortunately they are rather big and heavy and thus less
are not economically viable without water floods. This suitable for most offshore operations. Use of alternative
includes Deepwater projects, even those that make use of systems such as the Seaject and Minox systems has not been
subsea wells such as Bonga, Bonga SW (Nigeria), Gumusut very successful. There appears to be some light at the end
(Malaysia) and BC-10 (Brazil). The related challenges are of the tunnel as the latest experience on the Bonga FPSO
magnified by the fact that many projects are financed jointly with the Minox system is favorable. To date a dissolved
with other companies, or supplied as “industry standard O2 concentration of 20-50ppb is achieved, the remainder
equipment” and hence designs may differ significantly. can easily be polished with oxygen scavenger. It should be
noted that the project team did a very thorough analysis
The usual threats to the integrity of water flood performance of experience in other locations and developed detailed
include reservoir plugging and corrosion due to the operating procedures. It was concluded that a key to success
presence of oxygen and bacteria. Dealing with these threats was steady flow into the units. Another interesting data point
has always been challenging, but the options are somewhat is the use of only oxygen scavenger on the Fluminense FPSO
limited in offshore fields. For Deepwater applications an (Bijupira & Salema, offshore Brazil) to control the dissolved
additional threat is (corrosion) fatigue, notably of the steel oxygen. The rather high water temperature, sufficient
catenary risers. residence time in the FPSO piping and the chemical cost
being low as compared to that of methanol needed for the
The reservoir plugging threat is related to the reservoir Minox operation justified this approach as compared to
characteristics and the completion design. Many Deepwater revamping the Minox unit.
reservoirs, e.g. those in the Gulf of Mexico, consist of
unconsolidated sands, for which Shell has selected gravel The last significant threat in conventional water injection
packs with rather fine gravel. As a result, it is felt that solid systems is that of microbial induced corrosion (MIC).
particles greater than 15 μm will cause plugging. Water Where straight oxygen corrosion typically results in a more
treatment facilities usually incorporate filtration, hence solids general mode of attack, MIC causes localized corrosion.
in the water that enters the injection piping is controlled. In Grooving corrosion that led to the failure of some North
some cases extremely fine filters are used, a case in point Sea flowlines has been attributed to MIC. Clearly this threat
is when a sulfur reduction unit (SRU) is part of the system. is most likely to cause problems in low flow and stagnant
Whether such particles will be generated in the injection systems where biofilms can form. The threat is probably
system itself due to occasional corrosion, e.g. during upsets exacerbated by the combination of bacteria and oxygen.
of the oxygen control system, is unknown, but it is clear that Since regular pigging of water injection flowlines is highly
if such particles are generated, plugging of the small gravel undesirable or even impossible it is important to design the
pack area will occur quickly. Work is in progress to evaluate system to operate at relatively high velocities. Since it is
this further, but in the meantime systems with such “tight” difficult to completely avoid stagnant areas, e.g. in valves,
reservoirs are designed such that no corrosion particles can corrosion resistant alloys have to be used. Moreover, the
be generated. presence of bacteria has to be minimized by means of good
commissioning practices to start off with a clean system and
Of the corrosion threats, oxygen attack is well understood. biocide treatments. Also, fine filtration will certainly help by
A model has been developed by Shell Global Solutions minimizing solids in the water injection system.
(Pots) to quantify the corrosion rate due to oxygen as
a function of its concentration. Almost all systems are The main additional threat to loss of integrity of deepwater
de-oxygenated in some manner, usually to a very low systems is a shift will from a fatigue to a corrosion fatigue
concentration (<10ppb), which implies that the maximum mode of the steel catenary risers. Risers are normally
dissolved oxygen concentration of about 8ppm will seldom designed for 200 year fatigue life and this shift reduce the
be experienced. Typical upset concentrations are thought to projected life by a significant factor of about 50 or more
be in the range of 100-200ppb; the duration of the upsets years. There are various ways to cope with this such as
depends on the alarm and control system and on operator using greater wall thickness, higher strength material or CRA
diligence. Enhanced oxygen corrosion due to galvanic liner. The former two options are usually less attractive as
effects between carbon steel and stainless steel (see below) they cause additional welding challenges.
may be another threat. A magnification factor of three has
been agreed for design purposes.

31
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

The list of above requirements has translated in various It is obvious that the above represent high CAPEX solutions.
designs of water injection systems as noted below: It can be argued that if we spend a lot of money on
sophisticated oxygen removal and sometimes SRU systems,
• The Bonga WI flowlines comprise of bare carbon steel supplemented with detailed operational procedures and
risers, which are clad with Alloy 825 at the hang-off operator training, the use of CRA and HDPE is over the top.
and touchdown areas to deal with the fatigue threat. Indeed other operators reportedly solely rely on operational
Part of the 825 liner is coated to eliminate galvanic control. In some cases, other operators are using different
coupling with carbon steel. The remainder of the sand control methods for their wells. At the time of writing
flowline is lined with high density polyethylene (HDPE). this article, these various options are still being hotly
debated.
• The Basis for Design of the Ursa Princess Water Flood
project calls for completely clad riser and HDPE For more details, contact: Maarten Simon-Thomas
horizontal flowline section, but the use of HDPE in most (maarten.simon-thomas @shell.com)
of the riser is under evaluation. On the platforms, the
low pressure parts of the system are typically made of
FRP, whereas the high pressure piping and accessories
make use of stainless steels with PREN greater than
42.5 and CRA.

DEP.39.01.10.11-Gen. Manual - selection of materials for life cycle


performance (EP) – 2005 Revision
The 2002 revision of DEP.39.01.10.11 was updated in It is intended to maintain the DEP.39.01.10.11, Manual
2005 to incorporate more recent Shell Group and industry - Selection of Materials For Life Cycle Performance (EP), as a
upstream E&P experience with respect to materials selection live document with annual or bi-annual updates. To ensure
and materials performance from subsurface to pipelines. that the manual contains current E&P industry and Shell
The manual is an excellent resource on materials selection Group best practices, Shell and contract staff are requested
guidelines for both new projects and existing facilities. to send proposed changes and items for inclusion in the
next revision to the document custodian – Ken Welsh
(ken.welsh@shell.com).

Cathodic Protection Review


Nigeria LNG Bonny Plant and Incoming Pipelines
Nigeria LNG (NLNG) operates a LNG plant at Bonny Island, A different natural gas producer is building each of the five
Nigeria, with plant capacity increasing steadily since its new incoming pipelines, with each one of them utilizing a
original start-up in 1997. The network of incoming pipelines different engineering and construction contractor. Of course,
is growing as well, from initially only one pipeline to six each one has its own CP design procedures, and even
operating pipeline systems expected in the near future. when Shell’s DEPs are specified as base-line documents,
NLNG requested Shell Global Solutions to conduct a health there are different interpretations and applications of the
check review of their cathodic protection (CP) systems to requirements. A short meeting at the beginning of a project
assure integrity of their existing underground assets and between the relevant specialists representing both sides
a review of the proposed designs for the new incoming can usually clarify the design process and data to be used.
pipelines. Unfortunately a plant may not have a CP specialist on staff
and therefore is not able to provide the necessary oversight.
A number of observations and recommendations were made
to NLNG that may be more or less typical for any plant Another factor to consider, especially when several projects
and pipeline system that is undergoing rapid expansion. By are being done simultaneously, is how to coordinate the
implementing these recommendations, GSEI/4 estimate that work so the most effective result is obtained. In this case,
NLNG could potentially save $300,000 USD. This article we found that each contractor wanted to install their own
provides some of the key points and recommendations that small impressed current CP system at the plant. This is not
should be useful to other cathodic protection projects based necessary and creates a whole range of problems that are
on the NLNG review. further explained below.

Consistency and coordination of the design process among


different parties

32
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Consider operating data from existing CP systems in new Is there space for new groundbeds?
designs. Impressed current groundbeds must not be too close
to earthing systems, buried piping or metallic electrical
Most cathodic protection design standards, including Shell conduits to avoid the possibility of stray current corrosion
DEPs, include basic default design standards, e.g. design on these other facilities. The efficiency of groundbeds is also
cathodic current density as a function of coating type, soil reduced if they are to close together. Therefore, it is often
resistivity, temperature and project life, current output limits difficult to find enough area for multiple, new groundbeds in
for various types and sizes of anodes, etc. The variable that an existing plant. So one large groundbed is often a better
affects the CP design the most is the design cathodic current option than many small groundbeds.
density. In a location where there is little specific design data
available or when a coating with relatively little long-term Stray current corrosion
field experience is used, any locally available data from an When pipelines with individual impressed current systems
existing plant or pipeline cathodic protection system is very cross or come very close laterally, there is a potential
helpful. for stray current corrosion to occur. The possibility of this
happening depends on many factors (coating quality,
The DEPs and most CP standards encourage CP designers distance between groundbeds and other pipelines, current
to take advantage of actual field data rather than rely output, soil resistivity, etc.). The most common solution to
solely on the default values. In the case of NLNG, the stray current corrosion is to bond the offended pipeline to
existing pipeline system has the same type of coating as the negative of the offending TRR. With fewer individual
the new pipelines and operates in the same temperature TRRs, each pipeline is by design connected to the negative
range and soil conditions. For pipelines in the swamp, the of the same TRR(s), which greatly minimizes the potential for
new projects were using CP current requirements ranging stray current corrosion problems.
from 0.01 to 0.225mA/m2 for a thirty-year life, while
the actual current requirement for the existing pipeline Monitoring facilities (test posts) and drawings at
is 0.043 mA/m2 after 8 years. Using this value, and crossings
accounting for some continued coating degradation and Test posts and good drawings of the facilities at foreign
safety factor, we recommended that all the new projects use pipeline crossings and other sources of DC (DC rail lines)
0.130mA/m2 for a 30-year design life. are necessary to monitor for stray current corrosion. Test
posts on both structures (pipelines, rail system, etc.) are
Can existing CP facilities protect new pipelines? required to perform the tests for stray currents.
There is one existing transformer-rectifier (TRR) and
groundbed on the incoming pipeline at Bonny Plant that is Owner/operator CP procedures and skill and CP
rated for 24 Amps DC output but is currently only running Contractor expertise
at an output of 4.3 Amps DC. The total future (30-year Many locations necessarily rely upon a CP contractor to
life) current requirement after all pipelines are installed is perform routine CP surveys and for general CP consulting.
estimated to be 47 Amps DC. So rather than have each Contractors normally work for many customers with different
pipeline install a separate TRR, we recommended that the specific requirements and practices, especially regarding CP
next pipeline to be constructed install a TRR and groundbed criteria, frequency of and process of performing instant-off
rated for 48 Amps DC, which would be able to provide the testing, how stray current problems should be handled
CP current requirement for all the pipelines. This would be and data reporting. To minimize the chance of inadequate
in addition to the existing 24 Amp DC TRR and groundbed procedures from being used or poor advice being provided
that would be used to provide contingency against early by local CP contractors, robust CP procedures should be
failure of anodes in the new groundbed. There are many created for each plant or pipeline along with obtaining
advantages to this approach and some disadvantages. specialist advice as required. This will also assist local
Advantages include reduced capital cost, maintenance staff in expanding their CP experience plus it help them to
cost, space savings and reduced possibility of stray current properly guide their CP contractor(s).
corrosion. One disadvantage is that the CP requirement of
each new pipeline must be coordinated through the plant For more details, contact: Paul Nichols,
personnel to make arrangements for the bonding of each (paul.r.nichols@shell.com)
new pipeline to the existing TRR.

33
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

STRESS RELIEF!

Need an urgent advice when I am not around?


Here is one of those out of office reply we recently come
across, and thought it would be nice to share with you. It
goes like this:

5. l.
1 s t D ec 200 to my e-mai )
t i l 3 c e s s y y y
ce un ve ac (ext.y
b e o u t-of offi I will not ha tact Xxxxxx llowance.
I’ll uentiall
y on A
lease c rrosion
Conseq ent matters p ith 3/4” Co
w
For urg arbon steel
c
or use
tings,
e a s o n s Gree
S
xxx
Xxxx X

Cleanliness crazy
Have you heard of this Corrosion engineering student who
suddenly became cleanliness crazy?

His wife noticed that every week he thoroughly cleaned all


the metallic items in the house, especially the ceiling fans.
He made sure that there was no dust on any of the metallic
components. She was happy, but would have been happier
if he cleaned the whole house with that regularity, as she
had to do all the other cleaning. One day while arranging
his books, she found the reason for the sudden craze of her
husband for cleaning the metallic components. The latest
book he had been reading was “Under deposit corrosion
can cause catastrophic failures”!

34
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Who’s Who - Organograms
Staff Announcements

Moved In

Keith McKinney Jorge Penso


On 16 January Keith McKinney has joined GSEI/1. Keith Jorge Penso joined GSEI/5 in July 2005 from Stress
joins us from GSEI/5 in Houston and brings with him a Engineering Services. Jorge possesses a PhD in welding with
wealth of downstream experience, most notably in the 25 years of combined academic and industrial experience
Chemicals area. In GSEI/1 Keith’s primary tasks will be in in metallurgy, corrosion and welding. He will be working in
both the Chemicals MSU and the FAIR teams. the areas of FFS, welding consultancy and failure analysis,
with specialization in coke drum cracking.
Ingrid Bos
On 1 January, Ingrid Bos has transferred out of the Business Ying Xiao
Support Team GSEI/0 and started an assignment in GSEI/1. Ying Xiao, double MS in Mathematics and Chemical
Ingrid’s tasks in this role will continue to include her FAIR Engineering with Corrosion focus, joined GSEI/5 in July
activities but she will also work on CWW and BSP R&D activities. 2005 from a research project with Conoco-Philips. She is
now working in the corrosion and materials group on the
Mike Fleming corrosion prediction models and failure analysis.
Mike Fleming, joined the Inspection Technology Business
Team GSEI/3 as the European IDMS business support Steve Roberts
specialist. Before joining Shell Global Solutions, Mike was Steve Roberts, BS Mechanical Engineer from Oklahoma
the PEI staff engineer at Martinez Refinery. The effective State University, joined GSEI/5 in October 2005. Steve
date of his move was 1st November 2005, but Mike will be has 15 years of experience in pressure equipment design.
working from the US-Martinez refinery till the end of 2005, Prior to joining Shell, he worked as a pressure equipment
to support the IDMS-implementation work from the US and engineer in Lyondell Chemical. Steve is now working in
to finalise his specialist training. the PEI PTF (project task force) group working on capital
projects.
Mike will move to SRTCA in early January.
Ayman Cheta
Mike comes to GSEI/3 with 20 years of broad PEI Ayman Cheta, MS Mechanical Engineer University of Illinois
experience and integrity management in the Downstream with 18-year experience from BP Amoco, joined GSEI/5
business. His primary task will be to provide IDMS in December 2005. Ayman will be working in the PEI PTF
implementation and support to the Downstream European group doing work on valve and piping specifications global
OU’s. alignment and major projects. He will also be involving with
FFS work.
Salim Mwachuo
Salim Mwachuo joined GSEI on 10 October 2005. He David Breitkruez
will be based in SRTCA for an initial period of training/ David Breitkruez was transferred from Mobile Refinery to
broadening in both Inspection Technologies and Materials/ GSEI/5 in Sept 2005. Dave was an Inspection Supervisor
Corrosion Engineering, followed by a second period as for Mobile and has been with Shell for 15 years in various
GSEI Service provider. Salim will be trained and working in assignments in the US and Canada in the materials
both GSEI/1 and GSEI/3 departements. Salim started his and inspection discipline. Dave is working in the PEI
training/broadening in GSEI/3. group, performing FAIR’s, RBI assessments, Asset Master
Planning, and T/A work scope reviews. He also provides
Prior to joining Shell Global Solutions, Salim worked as an administrative support to the PEI Tech-Net.
Inspection Engineer at KPRL Refinery in Kenya.

35
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Retirement

Roy Schelling
On 22nd December 2005 Roy Schelling retired from the implementation of the Process Safety Initiatives related
GSEI/1 after 30 years service. Roy started work for Billiton to equipment integrity, a pioneer in the API standards
International Metals in 1976 and held a number of positions development and inspector certification programs, the leader
there before transferring over to work for Shell, after Shell of the most awarded Technical Network (PEI Tech-Net) which
divested it’s interest in Billiton in the early 1990’s. Many developed and implemented many Shell best practices in
of you know Roy for his recent role as the backbone for the area of Pressure Equipment Integrity. He has published
the SulTAN and CORAS work in Shell Global Solutions. In and given many talks and papers in industry the world over
this capacity Roy has contributed invaluable new data and and is the author of the famous “101 Essential Elements of
insight into the high temperature sulphur and high TAN Pressure Equipment Integrity Management.”
corrosion modelling work. To mark his final day at work and
celebrate his contribution over the years, Roy was joined Dick graduated from the University of Delaware with a BS
by family, friends, plus new and old colleagues for a very degree in Chemical Engineering and joined Shell a mere
enjoyable party in the centre of Amsterdam. two weeks before John Reynolds in 1968! He started at the
Emeryville Research Center as a materials and corrosion
engineer. Dick stayed in the materials discipline for his
entire career, working in pipeline, in Head Office, at Norco,
Geismar and WTC. Dick has had a tremendous influence
on Shell’s understanding and mitigation of corrosion and
degradation of equipment in refining, distribution, and
petrochemical processes. He was deeply involved in the
1987 Norco CCU explosion investigation, and his work
led to significant effort in Shell on injection point design,
monitoring, and integrity. Dick also contributed a huge
body of knowledge to the understanding of the corrosion
chemistry of water wash systems, and was a key contributor
to our knowledge about controlling these systems. Dick has
also been a very active member of both API and NACE,
in the consensus standards-writing bodies related to our
industry and in contributions to industry publications. Dick
Farewell Maestros has been honored with numerous awards over the years,
John Reynolds and Dick Horvath such as the NACE T. J. Hull award, and the Russell A.
John Reynolds and Dick Horvath both retired effective Brannon award. Recently, he was named to the prestigious
December 31, 2005, each after 37 years of service. A joint position of Chief Scientist for Materials in Shell.
retirement party was held in their honor on December 13,
2005 at the Plaza Club on the top floor of One Shell Plaza.
Many current and retired employees, friends, and family
joined Dick and John in this celebration of 74 years of
service to Shell.

The impact that John and Dick have had on the


advancement of applied knowledge in Corrosion, Materials,
Inspection, and Pressure Equipment Integrity Management in
Shell, and in the Oil and Gas industry is beyond measure,
incalculable.

John graduated from the University of Wisconsin with


a BS in Mechanical Engineering and a MS in Materials
Engineering in 1967. He joined Shell in 1968 at the Denver
plant as a plant engineer. John worked in various technical
and managerial assignments in the Hague, Head Office,
and several US plant locations over the course of his 37 Dick Horvath (left) and John Reynolds (right) with Paul Hamilton
year career. Although his primary focus was Pressure at their farewell party.
Equipment, he also had assignments as an Engineering
Services manager and as an Asset Manager in his career.
Among his many contributions, John was the developer of
the focused asset reviews, now called FAIR’s, a leader for

36
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
GSEI Materials & Inspection Engineering group

W.G. Coit - Materials & Inspection Global Manager


+1 281 544 7912

Secretarial support to the GSEI-group in Amsterdam


W.H.A.M. Kampschöer (Wilma) +31 20 630 2121
G. Boes (Geertje) +31 20 630 2244
M. Magdi (Monique) +31 20 630 2830
M.M.A. op den Velde (Monique) +31 20 630 3355

Secretarial support to the GSEI-group in Houston


S.L. Lackey (Stacey) +1 281 544 9198 (GSEI/4)
S.E. Weems (Sharon) +1 281 544 8158 (GSEI/4)
S.M. Rodriguez (Sonia) +1 281 544 7971 (GSEI/5)

Secretarial support to the GSEI-group in Kuala Lumpur


A. Zainal-Abidin (Ayu) +60 3 2170 3781

37
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

GSEI/1 Downstream Materials & Inspection Engineering


Business Team Manager: M. Sargent
Business Leadership Team*: K. Smit, A. Blaauw, W. Fort, P. Blauvelt and A. Saunders-Tack
Product (CVP) Teams
Team Responsibilities: Product development; Product Marketing; Sales; Implementation Planning and Co-ordination

Team Leader** Team Members


FAIR (Focused Asset Integrity Reviews) A. Blaauw N. Beer, P. Blauvelt, I.Bos, M..P de Boer, N. Dowling,
R. Fransz, G.C. Goh, J.P. de Jong, W. Liek, K. McKinney,
W-E Ong, N. René de Cotret, J. van Roij, A. Saunders-Tack,
FAIR +MS+ER focal point for refineries: N. René de Cotret
ECM (External Corrosion Management) A. Etheridge J. van Bokhorst, A. Blaauw, N. Dowling, J.P de Jong,
W. Liek, K. McKinney,J. van Roij, P. van Loon, P. Rol
CORAS (Crude Oil Risk Assessment Service) N. Dowling P. Blauvelt, W. Fort, G C Goh, JP de Jong, W. Liek,
W-E Ong, N. René de Cotret, J. van Roij, A. Saunders-Tack,
S. Zhang
PCR (Process Corrosion Reviews – P. Blauvelt N. Beer, M.P. de Boer, N. Dowling, W. Fort, R. Fransz,
including Corrosion Clinics, CCMs, G.C. Goh, S. Marsh, K. McKinney, W.E. Ong,
IOW, WW reviews and N. René de Cotret, J. van Roij, K. Smit, S. Zhang
GAME implementation support)
MCI-Infobase A. Etheridge N. Beer, P. Blauvelt, I. Bos, M.P. de Boer, S. Marsh,
S. Mwachuo, S. Zhang
Low-Coking Ethylene Tubes (Daido) A. Saunders-Tack T. Wolfert, (F. Terwijn – Consultant)
PROFIT/FFS/RLA A. Saunders-Tack N. Beer, K. Smit, P. Blauvelt, K. McKinney

Business Leadership Team* - Responsibilities include Departmental business plan preparation and implementation

Team Leader** - Responsibilities include management of budgets, team member mentoring/coaching, team member performance
feedback, product/service business performance feedback (revenue, CSI etc.)

MSU and Zone Services Teams


Team Responsibilities: MSU Support, Helpdesk; Additional Services; Focal points; Project Support; Developments; Best Practices;
RBI Implementation Support
Team Leader** Team Members
Refining P. Blauvelt N. Beer, M.P. de Boer, N. Dowling, A. Etheridge,
J.P. de Jong, W. Liek, S. Mwachuo, N. René de Cotret,
J. van Roij, A. Saunders-Tack, T. Wolfert, S. Zhang
W. Fort, R. Fransz, G.C. Goh, W.E. Ong
Chemicals K. Smit K. McKinney, J. van Roij, A. Blaauw
W. Fort, G.C. Goh. W.E. Ong
LNG/Gas Processing A. Blaauw N. Beer, N. Dowling, S. Marsh, K. Smit,
R. Fransz
SMDS and Gasification K. Smit A. Saunders-Tack, T. Wolfert, Z.P. Zhang
Far East Zone Team (See specific team W. Fort R. Fransz, G.C. Goh, W.E. Ong
roles for Refining, Gas, Chemicals etc above)

Note: The Team Leader is the Projects focal point for each MSU

38
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Business Teams
Team Responsibilities Team Leader Team Members
R&D, BSP, Innovation M. Sargent N. Beer, M.P. de Boer, I. Bos, J. Van Bokhorst, N. Dowling,
A. Etheridge, W.Fort, J.P. de Jong, W. Liek, P. Van Loon,
S. Marsh, K. McKinney, N. René de Cotret, J. van Roij,
A. Saunders-Tack, K. Smit, T. Wolfert, S. Zhang
Marketing, (Advertising, Sales Pipeline etc) A. Etheridge I. Bos, A. Saunders-Tack
Quality Management M.P. de Boer R. Fransz
HSE W. Liek J.P. de Jong, T. Wolfert, Ong, Woon-Eng
Information Management & Exchange N. Beer P. Blauvelt, M.P. de Boer, R. Fransz, S. Marsh, I. Bos
(CWW Web-site, Library, Knowledge
gatekeeping)
Newsforum & Newsletter G.C. Goh R. Fransz, W.E Ong, N. Beer
MIEM K. McKinney P. Blauvelt, N. Beer, W.E. Ong, S. Mwachuo,
Training Course Staffing A. Etheridge S. Marsh, N. Dowling (M183), P. Blauvelt (M273),
A.Saunders-Tack (FFP),

Specialist Technical Services Focal Points


Technical Speciality Focal Point Alternate Focal Points
Welding & Fabrication A. Blaauw N. Dowling, S. Marsh, T. Wolfert, R. Vulla (GSEI/2)
Cathodic Protection, Pipeline Coatings J. van Bokhorst P. Rol (Pipeline Coatings), P. Nichols (CP, Houston)
Painting & Coatings P. Rol P. van Loon
Refractories T. Wolfert G.C. Goh
Non-metallics, Linings P. van Loon F. Janssen, L. De Mul (GSEI/2)
Failure Analysis, Corrosion Testing A. Saunders-Tack P. Blauvelt, N. Dowling, A. Etheridge (CIP), W. Fort (KL),
W. Liek, S. Marsh, K. McKinney
Corrosion Monitoring J. van Roij A. Etheridge, N. Beer
RBI (Co-ordination with GSCC) M. Sargent Implementation of resources from Services Teams
Standards (DEPs, MESC) K. McKinney A. Blaauw, M.P. de Boer, S. Marsh

39
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

Downstream Materials & Inspection Engineering – Customer Focal Points for MSU Services
REFINING MSU

Refinery Location SM/AE GSEI/1 Focal Pointt

AMERICAS
Argentina (CAPSA, Buenos Aires) Jos Reekes Manuel Gonzalez (HOU)
Canada (MER, Sarnia, Scotford) Kim Watson Simon Yuen (HOU)
Dominican Republic (Santo Domingo) Jos Reekes Manuel Gonzalez (HOU)
Venezuela (Caracas, CRP Cardon) Jos Reekes Manuel Gonzalez (HOU)
Colombia (Ecopetrol) Wim Deelen Manuel Gonzalez (HOU)

AFRICA
Kenya (Mombasa) John Sykes Pieter Blauvelt
Nigeria (NNPC) D. Bax Marc Paul de Boer
South Africa (Durban) John Sykes Pieter Blauvelt
MIDDLE EAST
Saudi Arabia (Al Jubail/Saudi Aramco) Dick Wesdorp Marc Paul de Boer
UAE (Takreer) Peter Verhulst Nick Dowling

ASIA
Indonesia (Cilicap) Iwan Salim Ong, Woon-Eng
Philippines (FPIC, Tabangao/SGEI) Theo Bodewes Reggy Fransz
Taiwan (Formosa/CSLC) Theo Bodewes Bill Fort/Ong, Woon-Eng
Japan (Showa Shell Tokyo, Showa Shell
Kawasaki Niigata,Yokkaichi,
Seibu Yamaguchi, TOA Kawasaki) Atsushi Kitazume/Dick Wesdorp Bill Fort
Malaysia (Port Dickson, Petronas PPTB) Siew, Hong Siang Ong, Woon-Eng
Singapore (Pulau Bukom) Mike van Beuzekom Gim Choon Goh
Brunei (ROS) Kees van Burg Reggy Fransz
Reliance Industries Limited Fred Means W. Fort
Thailand (ARC, TOC Sriracha) Theo Bodewes Gim Choon Goh

EUROPE
API (Italy) Dick Wesdorp Pieter Blauvelt
Czech Republic (Litivinov) Dick Wesdorp Nicole René de Cotret
Cyprus (Cyprus Oil Terminal Ltd.) Letty de Ungria Marc Paul de Boer
France (Berre, Pt Couronne, Reichstett) Jos Reekers Nicole René de Cotret
Germany (Shell Deutschland Oil: Elbe manufacturing:
(Harburg & Grassbrook), Heide, Rhineland
(Godorf & Wesseling)) Reiner Busch Marc Paul de Boer
Netherlands (Pernis) Dick Wesdorp Nick Dowling
Scandinavia (Fredericia, Gothenburg, Mongstad, PREEM) Frans Spijker Pieter Blauvelt
Cressier, Antwerp, Teeside (Petroplus) John Sykes Nick Dowling
United Kingdom (Stanlow) John Sykes A. Etheridge

AUSTRALIA/NEW ZEALAND
Australia (Clyde, Geelong) M. v Beuzekom R. Fransz
New Zealand (Whangarei) M. v Beuzekom R. Fransz
Refining Technology Contacts BGM
GSRC (FCCU Technology) Mart Nieskens Goh, G C / T. Wolfert
GSRH (Hydroprocessing & Base Oils) John Newsome Pieter Blauvelt
GSRD (Distillation/Thermal Conversion) Henk Vasmel Marc Paul de Boer
GSRL (Light Ends Conversion) Martiel Luther Pieter Blauvelt
GSGT (Gas/Liquid Treating & Sulphur Processes) Henk Grootjans Kees Smit
GSRU (Energy, Utility, Water & Waste) Herman Hegge Johan van Roij

40
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Downstream Materials & Inspection Engineering – Customer Focal Points for MSU Services
CHEMICALS MSU

Plant Location SM/AE GSEI/1 Focal Point


Stanlow (UK) Frank van Breukelen *Keith McKinney
Pernis/Moerdijk (Netherlands) Frank van Breukelen Johan van Roij
Berre (France) Frank van Breukelen Johan van Roij
SADAF (Al Jubail) Frank van Breukelen Keith McKinney
Seraya (Singapore) Frank van Breukelen Goh, Gim Choon
Nanhai (China) Frank van Breukelen Johan van Roij
NPC (Thailand) Harry van Dijk Goh, Gim Choon
ATC (Thailand) Harry van Dijk Goh, Gim Choon

Chemcials Technology Contacts BGM GSEI/1 Focal Point


Lower Olefins & Aromatics (GSTLO) H. Schrivers Kees Smit
EO & Derivatives (GSEOD) Ben Ramakers Johan van Roij
PO & Styrene Monomer (GSTPS) Joke Driessen Johan van Roij

* Andrea Etheridge is the focal point for Stanlow merged site with Chemicals support from Keith McKinney

Downstream Materials & Inspection Engineering – Customer Focal Points for MSU Services
GAS / SMDS MSU

Plant Location SM/AE GSEI/1 Focal Point


MLNG (Malaysia) Kees van Burg Reggy Fransz
BLNG (Brunei) Kees van Burg Reggy Fransz
OLNG (Oman) Cri Staal-Collett Natalie Beer
NLNG (Nigeria) Paul Rodenburg Simon Marsh
GASCO (Abu Dhabi) Peter Verhulst Simon Marsh
Hazira (India) Abdi Nayak Simon Marsh
Altamira Cri Staal-Collett Simon Marsh
Sakhalin LNG Kees van Burg Reggy Fransz
Woodside (Australia) Roy Nap Reggy Fransz
Emmen (Netherlands) Cri Staal-Collett Nick Dowling
St Fergus, Bacton and Mosmorran (UK) Cri Staal-Collett Natalie Beer
SMDS Bintulu (Malaysia) Kees van Burg Kees Smit

Gas Technology / Projects Contacts SM/AE GSEI/1 Focal Point


Engineering (GSG/1) Roy Nap Simon Marsh
Operations (GSG/1) Roy Nap Simon Marsh
Gas to Liquids Conversion (GSGC) Mattijs Senden Kees Smit
Gasification & Hydrogen (GSGG) Piet Zuideveld Kees Smit
LNG/Gas Processing (GSGL) Barend Pek Simon Marsh
Projects (GSP) Phil Holland Nick Dowling

41
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

GSEI/1 Contact Information

Surname Initials Telephone Location Room GSM Email:


Beer N.L. +31-20-630-2407 AMS MEB-10-11 +31 64 638 2468 Natalie.Beer@shell.com
Blaauw A. +31-20-630-3671 AMS MEB-10-09 +31 65 512 3079 andre.blaauw@shell.com
Blauvelt P.N. +31-20-630-3167 AMS MEB-10-21 +31 65 209 6413 Pieter.N.Blauvelt@shell.com
de Boer M.P. +31-20-630-2461 AMS MEB-10-24 +31 65 209 6161 marcpaul.deboer@shell.com
van Bokhorst J.R. +31-20-630-3554 AMS MEB-10-03 +31 65 209 6127 jan.vanbokhorst@shell.com
Bos I. +31-20-630-3050 AMS MEB-10-26 +31 652 096 477 Ingrid.bos@shell.com
Dowling N.J.E. +31-20-630-3082 AMS MEB-10-24 +31 65 209 6287 nicholas.dowling@shell.com
Etheridge A. +44-151-735293 CIP B304 Rm 47 +44 7789 73898 andrea.etheridge@shell.com
Fort W.C +60 3 2170 3979 KL Level 19 +60 12 326 6053 william.fort@shell.com
Fransz R, +60-3-2170-3865 KL Level 20 +60 12 303 0607 r.fransz@shell.com
Goh G.C. +65-6263-5023 KL Level 19 +60 12 321 2796 g-c.goh@shell.com
de Jong J.P. +31-20-630-2145 AMS GL-03 09 Jan-Peter.deJong@shell.com
Liek W.E. +31-20-630-2594 AMS GL-03 08 +31 65 209 6104 willem.liek@shell.com
van Loon P.J.M. +31-20-630-2627 AMS MEB-10-03 +31 65 252 1847 peter.vanloon@shell.com
Marsh S.R. +31-20-630-3157 AMS MEB-10-11 +31 65 209 6194 simon.marsh@shell.com
McKinney K. +31-20-630-2276 AMS MEB-10-33 +31 65 251 1449 keith.mckinney@shell.om
Ong W. +60-3-2170-3756 KL Level 19 +60 12 378 0821 Woon-Eng.Ong@shell.com
René de Cotret N.L. +31-20-630-2135 AMS MEB-10-26 +31 65 209 6306 n.renedecotret@shell.com
van Roij J.F.M. +31-20-630-3955 AMS MEB-10-33 +31 65 512 3078 johan.vanroij@shell.com
Rol P. +31-20-630-3569 AMS MEB-10-03 +31 61 247 7958 p.rol@shell.com
Sargent M.A. +31-20-630-3147 AMS MEB-10-10 +31 65 261 8143 margaret.sargent@shell.com
Saunders-Tack A. +31-20-630-2446 AMS MEB-10-29 +31 65 209 6216 andrew.saunders-tack@shell.com
Smit K. +31-20-630-2308 AMS MEB-10-25 +31 65 512 3082 kees.k.smit@shell.com
Wolfert A. +31-20-630-2298 AMS MEB-10-25 +31 65 512 3086 ton.wolfert@shell.com
Zhang Z.P. +31 20 630 2483 AMS MEB-10-21 +31 6 52618180 samuel.zhang@shell.com

42
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
GSEI/2 Upstream Materials Engineering

G.E. Kerkveld – Business team manager in Amsterdam, The Netherlands


+31 20 630 2438

Metallic materials corrosion & corrosion control


Amsterdam - NL
M. Brown (Madeleine) +31 20 630 2960
E.L.J.A. Hendriksen +31 20 630 3544
P.A. Hiron +31 20 630 2685
S. Huizinga +31 20 630 2449
J.G. de Jong +31 20 630 2592
C.C. Kettle +31 20 630 2456
B. McLoughlin +31 20 630 3117
J.A.M. de Reus +31 20 630 2742
D.M. Queen +31 20 630 3011
N.J. Wilcock +31 20 630 2079
M.E. Wilms +31 20 630 2479
Rijswijk - NL
I.J. Rippon +31 70 447 2719
K.A.D. Welsh +31 70 447 4617
Kuala Lumpur – Malaysia
M. Thompson +60 3 21703931
R. Vulla +60 3 21703954

Metallic materials mechanical performance, microstructural degradation & welding,


failure analysis
Amsterdam - NL
A. Deurhof +31 20 630 2065
C.J.R. Groenenberg +31 20 630 2171
R.K. Ohm +31 20 630 2628
C.G.F. Stenger +31 20 630 2422

Material degradation and failure modelling, prediction of remaining life,


Fitness For Purpose
Amsterdam - NL
R.J.W. Koers +31 20 630 2229
D. Ritchie +31 20 630 2387
C.W.M. Voermans +31 20 630 2485

Non-metallic materials performance & joining, failure analysis


Amsterdam - NL
F.A.H. Janssen +31 20 630 2228
A. Mesman +31 20 630 2282
L.M. de Mul +31 20 630 2318
K.M. Orzessek (Karin) +31 20 630 3160
J.B.W. van Zummeren +31 20 630 2493

Pipeline engineering
Amsterdam - NL
H.H.J. Wiegerinck +31 20 630 2142

43
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

GSEI/3 Inspection Technology


P.V. Geenen - Business team manager in Amsterdam, The Netherlands
Tel + 31 20 6303146

Deputy business team manager: M. Lorenz


Business support team member: M. Lorenz
Product (CVP) teams
Team responsibilities: Product development; product marketing; sales;
implementation planning and co-ordination
CVP Leader* Team Members
PEC (Pulsed Eddy Current) P. Crouzen I. Munns, J. van der Steen, D. Badoux
NII (Non Intrusive Inspection) S. Terpstra P. van de Camp, Ian Munns
PST (Pipe Support Tool) A. Visser P. van der Veer, J. van Nisselroij
NDT Guide (part of MCI-Infobase) R. Hulsey All
Pipeline/Piping Inspection P. van der Veer
NDT Consultancy M. Lorenz All

MSU focal points


Market sector unit MSU support, helpdesk; additional services; focal points; project support;
developments; best practices.
Focal points
Refining R. Hulsey For GSEI/1 customers focal points/Service Mngr’s/AE’s
see GSEI/1 org. matrix
Chemicals D. Kronemeijer Idem
LNG/Gas P. van der Veer Idem
E&P S. Terpstra Idem
Industrial Markets M. Lorenz Idem
APSC Kuala Lumpur Office (NDT-issues) J. McGregor

Specialist technical services focal points


Technical speciality Focal point Alternate focal points
Ultrasonics/Phased arry J. van Nisselroij A. Visser
Guided Waves P. van der Veer P. van de Camp
TOFD J. van Nisselroij A. Visser
PEC (Pulsed Eddy Current) P. Crouzen J. van der Steen
MFL (Magnetic Flux Leakage) P. van der Veer
EC (Eddy Current) D. Kronemeijer
Intelligent Pigs P. van der Veer
Optical Techniques P. van de Camp
Thermography P. van de Camp
Radiography I. Munns P. van der Veer
MPI/Dye Penetrant A. Visser
(AE) Acoustic Emission M. Hoekstra P. v.d. Camp
Leak Detection P. van de Camp
Inspection Data Management System M. Fleming R. Hulsey
Novel Inspection Techniques P. van de Camp

44
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
Business teams
Team responsibilities Team leader** Team members
Marketing i.e., Advertising, Sales Pipeline etc. M. Lorenz
Quality Management M. Lorenz
HSE P. van der Veer
Sample Data Base Registration/Storage P. van der Veer
Courses A. Visser
Contractor data Base A. Visser
Filing A. Visser Spec’s/Standards/Procedures
Equipment Control & Storage J. van der Steen
Calibration A. Visser
Inspection Technology gate-keeping P. van de Camp
Knowledge Management Systems P. Geenen

CVP Leader*: Responsibilities include CVP staircase/business plan preparation and implementation, management of
budgets, team member mentoring/coaching, team member performance feedback, product/service business
performance feedback (revenue, CSI etc.)
Team Leader**: Responsibilities include team member mentoring/coaching, team member performance feedback, product/
service performance feedback.

Jan 2006

45
The Materials and Inspection Engineering Newsletter December 2005 – issue 10
CONFIDENTIAL

GSEI/4 Upstream Materials and Integrity


S.D. Kapusta – Business team manager in Houston U.S.A.
+1 281 544 7633

Metals corrosion, properties & integrity


S.C. Canter +1 281 544 8258
Y. Chen +1 281 544 6295
J. Gonzalez +1 281 544 9171
R.C. John +1 281 544 7229
Y. Li +1 281 544 8733
B.P. Miglin +1 281 544 9090
W.L. Odell +1 281 544 8059
B.F.M. Pots +1 281 544 7028
D. Raghu +1 281 544 7231
P.F. Schmidt +1 281 544 8273
J.A. Stockman +1 281 544 8018
L.L. Wheaton +1 281 544 7432

Non-metals performance & properties


J. Chang +1 281 544 6034
P.F. Schmidt +1 281 544 8273

Coatings & Linings


H.R. Mitschke +1 281 544 8012
P. Nichols +1 281 544 8538
A.N. Villa +1 281 544 6778

- Materials Selection and Specification for Upstream Assets


- Tube mill/product assessment and qualification
- Development/assessment of corrosion management strategies
- Corrosion/erosion monitoring strategies/methods
- Inhibitor selection and inhibition schemes
- Non-metallic material applications
- Pipeline Integrity Risk Management (Pipe RBA)
- Focused Asset Integrity Reviews
- Failure Analysis services
- Laboratory testing services for materials properties and corrosion resistance
- Coating consultancy services for pipelines and offshore structures
- Rehab and new construction coating evaluation
- Subsea insulation selection and evaluation

46
The Materials and Inspection Engineering Newsletter December 2005 – issue 10

CONFIDENTIAL
GSEI/5 Downstream Pressure Equipment Integrity
W. Dominguez– Business team manager in Houston U.S.A.
+1 281 544 7900

Materials and corrosion management


S.K. Arensman
J.G. Edmondson
D. Fan
J. Fu
R. Hoffpauir
J.M. Jackson
H.E. Mead
R.D. Rothengass
D.W. Wang
Y. Xiao

Pressure equipment inspection, integrity


M.S. Bell
D.J. Breitkruez
G.C. Briner
K. Schoenleber
D.A. Thain
C. Whittle
T.P. Wylie

Fitness for service, mechanical design, life assessment


M.A. Gonzalez
D.S. Kim
J. Penso
P.D. Parikh
S.K. Yuen

Project Task Force*


E.A. Doe
G.M. Gallo
A.W. Humphrey
D.M. Prokopchuk
S.C. Roberts

Non-destructive evaluation
H. Figueroa
W.M. Gaasch
L.A. Whittington

* Current job titles misaligned with other GSUSI staff (i.e. Sr. Staff Eng in PTF = Advisor in GSUSI)

47

Das könnte Ihnen auch gefallen