1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 13.125 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 11.55 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 4.81 $US
SUB TOTAL COSTO DE POSECION= 29.49 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 29 LTS 0.53 $US/LTS 15.37 $US
LUBRICANTES:
CARTER 0.029 LTS 3.5 $US/LTS 0.10 $US
TRANSMISION 0.178 LTS 3.5 $US/LTS 0.62 $US
MANDOS FINALES 0.013 LTS 3.5 $US/LTS 0.05 $US
SISTEMAS
HIDRAULICOS 0.03 LTS 3.5 $US/LTS 0.11 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.08 0.08 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 0 $US
TREN DE RODAJE F.B.(I+A+Z) 9.09 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 8.45 $US
ELEMENTOS DE DESGASTE ESPECIAL 0.25 $US
SUB TOTAL COSTO OPERACIÓN 34.19 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 12.225 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 10.89 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 4.54 $US
SUB TOTAL COSTO DE POSECION= 27.65 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 31 LTS 0.53 $US/LTS 16.43 $US
LUBRICANTES:
CARTER 0.136 LTS 3.5 $US/LTS 0.48 $US
TRANSMISION 0.14 LTS 3.5 $US/LTS 0.49 $US
MANDOS FINALES 0.121 LTS 3.5 $US/LTS 0.42 $US
SISTEMAS
HIDRAULICOS 0.032 LTS 3.5 $US/LTS 0.11 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.16 0.16 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 1.5 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 9.98 $US
ELEMENTOS DE DESGASTE ESPECIAL 0.37 $US
SUB TOTAL COSTO OPERACIÓN 30.01 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 10.4 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 9.24 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 3.85 $US
SUB TOTAL COSTO DE POSECION= 23.49 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 24 LTS 0.53 $US/LTS 12.72 $US
LUBRICANTES:
CARTER 0.012 LTS 3.5 $US/LTS 0.04 $US
TRANSMISION 0.05 LTS 3.5 $US/LTS 0.18 $US
MANDOS FINALES 0.064 LTS 3.5 $US/LTS 0.22 $US
SISTEMAS
HIDRAULICOS 0.114 LTS 3.5 $US/LTS 0.40 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.25 0.25 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 1 $US
TREN DE RODAJE F.B.(I+A+Z) 5.58 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 3.20 $US
ELEMENTOS DE DESGASTE ESPECIAL 0.95 $US
SUB TOTAL COSTO OPERACIÓN 24.61 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 5.31 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 4.79 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.99 $US
SUB TOTAL COSTO DE POSECION= 12.09 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 20 LTS 0.53 $US/LTS 10.60 $US
LUBRICANTES:
CARTER 0.01 LTS 3.5 $US/LTS 0.04 $US
TRANSMISION 0.05 LTS 3.5 $US/LTS 0.18 $US
MANDOS FINALES 0.05 LTS 3.5 $US/LTS 0.18 $US
SISTEMAS
HIDRAULICOS 0.1 LTS 3.5 $US/LTS 0.35 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.16 0.16 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 1.25 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.28 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 13.94 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 4.38 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 3.96 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.65 $US
SUB TOTAL COSTO DE POSECION= 9.99 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 20 LTS 0.53 $US/LTS 10.60 $US
LUBRICANTES:
CARTER 0.01 LTS 3.5 $US/LTS 0.04 $US
TRANSMISION 0.05 LTS 3.5 $US/LTS 0.18 $US
MANDOS FINALES 0.05 LTS 3.5 $US/LTS 0.18 $US
SISTEMAS
HIDRAULICOS 0.1 LTS 3.5 $US/LTS 0.35 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.16 0.16 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 1.25 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.92 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 14.74 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 3.63 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 3.30 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.38 $US
SUB TOTAL COSTO DE POSECION= 8.30 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 20 LTS 0.53 $US/LTS 10.60 $US
LUBRICANTES:
CARTER 0.01 LTS 3.5 $US/LTS 0.04 $US
TRANSMISION 0.05 LTS 3.5 $US/LTS 0.18 $US
MANDOS FINALES 0.05 LTS 3.5 $US/LTS 0.18 $US
SISTEMAS
HIDRAULICOS 0.1 LTS 3.5 $US/LTS 0.35 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.16 0.16 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 1.25 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.92 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 14.74 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 4.83 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 4.29 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.79 $US
SUB TOTAL COSTO DE POSECION= 10.90 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 19 LTS 0.53 $US/LTS 10.07 $US
LUBRICANTES:
CARTER 0.113 LTS 3.5 $US/LTS 0.40 $US
TRANSMISION 0.06 LTS 3.5 $US/LTS 0.21 $US
MANDOS FINALES 0.051 LTS 3.5 $US/LTS 0.18 $US
SISTEMAS
HIDRAULICOS 0.043 LTS 3.5 $US/LTS 0.15 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.18 0.18 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 0.5 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.28 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 13.03 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 4.06 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 3.80 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.58 $US
SUB TOTAL COSTO DE POSECION= 9.44 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 13 LTS 0.53 $US/LTS 6.89 $US
LUBRICANTES:
CARTER 0.15 LTS 3.5 $US/LTS 0.53 $US
TRANSMISION 0.1 LTS 3.5 $US/LTS 0.35 $US
MANDOS FINALES 0.06 LTS 3.5 $US/LTS 0.21 $US
SISTEMAS
HIDRAULICOS 0.05 LTS 3.5 $US/LTS 0.18 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.20 0.20 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 2.5 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.28 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 12.20 $US
1.COSTO DE POSECION
DEPRESIACION: D=(Va-Vr)/Vu= 2.81 $US
INVERSION: I=(Vt*(n+1)*i)/(2*n*Ha)= 2.48 $US
SEGURO: S=(Vt*(n+1)*s)/(2*n*Ha)= 1.03 $US
SUB TOTAL COSTO DE POSECION= 6.32 $US
2.COSTO DE OPERACIÓN
COMBUSTIBLE 23 LTS 0.53 $US/LTS 12.19 $US
LUBRICANTES:
CARTER 0.182 LTS 3.5 $US/LTS 0.64 $US
TRANSMISION 0.085 LTS 3.5 $US/LTS 0.30 $US
MANDOS FINALES 0.095 LTS 3.5 $US/LTS 0.33 $US
SISTEMAS
HIDRAULICOS 0.584 LTS 3.5 $US/LTS 2.04 $US
GRASA 0.02 LTS 3.5 $US/LTS 0.07 $US
FILTROS=FACTOR DE COSTO HORARIO= 0.16 0.16 $US
NEUMATICOS ( COSTO/VIDA UTIL)= 0 $US
TREN DE RODAJE F.B.(I+A+Z) 0.00 $US
REPARACIONES FAC. DE REP.*MULT. VIDA UTIL 1.28 $US
ELEMENTOS DE DESGASTE ESPECIAL 0 $US
SUB TOTAL COSTO OPERACIÓN 17.01 $US
3.COSTO HORARIO DE OPERACIÓN
SALARIO MENSUAL/HRAS. TRAB. MES 350 176 2.29 $US
99.4029267
CALCULO DE PRODUCTIVIDAD DE CARGADOR FRONTAL
MODELO: CARGADOR FRONTAL 966G serie II
CAPACIDAD DEL CUCHARON 4.00
TIEMPO DE DURACION DEL CICLO DE CARGA 0.75
TIEMPOD DE VIAJES 0.80
CONSTANTE K 0.85
CORRECCION POR PENDIENTE 1.00
CORRECCION POR EFECIENCIA 0.83
CORRECCION POR RODADURA 0.90
VELOCIDAD DE AVANCE (mts/min) 210.00
VELOCIDAD DE RETROCESO(mts/mIn) 238.33
PRODUCTIVIDAD REAL Q(m3/hra)= 131.83
PRODUCTIVIDAD REAL Q(m3c/hra)= 118.64
92.11
94.0673441
CALCULO DE PRODUCTIVIDAD DE CARGADOR FRONTAL
MODELO: CARGADOR FRONTAL 966G serie II
CAPACIDAD DEL CUCHARON 4.00
TIEMPO DE DURACION DEL CICLO DE CARGA 0.75
TIEMPOD DE VIAJES 0.80
CONSTANTE K 0.85
CORRECCION POR PENDIENTE 1.00
CORRECCION POR EFECIENCIA 0.83
CORRECCION POR RODADURA 0.90
VELOCIDAD DE AVANCE (mts/min) 210.00
VELOCIDAD DE RETROCESO(mts/mIn) 238.33
PRODUCTIVIDAD REAL Q(m3/hra)= 131.83
PRODUCTIVIDAD REAL Q(m3c/hra)= 118.64
41.1992522
CALCULO DE PRODUCTIVIDAD DE LA PLANTA DE ASFALTO
MODELO: XINDA MACHINERY YWBS300
RENDIMIENTO (TON/HRA) 130.00
FACTOR DE EFICIENCIA E 0.85
DENSIDAD DE LA MEZCLA ASFALTICA (TON/M3) 2.20
PRODUCTIVIDAD REAL Q(m3/hra)= 50.23