Basic Formula:
= 120/7
= 17 1/7 days
2. A and B together can complete a piece of work in 35 days while A alone can
complete the same work in 60 days. B alone will be able to complete the same
working in ans 84 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Subtraction of fraction
a c ad − cb
- =
b d bd
∴ B’s one day’s work = (A + B)’s one days work - A’s one day’s work
1 1
= - (take LCM)
35 60
12 − 7 5
= = = 1/84
420 420
∴ B alone can complete the work = 84 days
Basic Formula:
1 1
∴ (A+B)’s 1 hour’s work = + (take LCM)
63 42
2+ 3 5
= =
126 126
∴ (A+B)’s working hours = 126/5
5
126 5
∴ Number of days 8 2/5 hours each = 126 = x =3
2 5 42
8
5
Answer = 3 days
Basic Formula:
Subtraction of fraction
∴ Remaining work = 1- ½ = ½
5. A can do 1/3 of the work in 5 days and B can do 2/5 of the work in 10 days
in how many days both A and B toether can do the wrok ans 9 3/8
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Basic Formula:
7. A and B can together finish a work in 30 days. They workd at it for 20 days
and then B left. The remaining work was done by A alone in 20 more days A alone
can finish the work in ans : 60 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s Subtraction
Basic Formula:
9. A does half as much work as B in three fourth of the time. If together they
take 18 days to complete the work, how much time shall B take to do it ?ans 30
days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
10. A can do a certain job in 12 days. B is 60% more efficient than A . The
number of days, it takes B to do the same piece of work is ans 7 ½
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Ratio multiplication
A:b:: c:d
Ad = bc
11. A can do a certain job in 25 days which B alone can do in 20 days. A stared
the work and was joined by B after 10 days. The number odays tkane in
completing the work was ans 16 2/3
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s addition
12. A is twice as good a work man as B and together they finish a piece of work
in 14 days The number of days taken by A alone to finish the work. Ans: 21 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Ratio comparison
A:b:: c:d
Ad = bc
∴ we get (A’s one day’s work) : (B’s one day’s work) = 2:1
Basic Formula:
Fraction’s Multiplication
14. A can do a piece work in 14 days which B can do in 21 days. They being
together but 3 days the completion of the work. A leaves of the total number of
days to complete the work is ans 10 1/5
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
15. If ramesh, suresh and hairsh can do a piece of work in 15 days, 10 days and
6 days respectively. How long will they take to do it, if all the three work it
together? ans 3 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s addition
16. A and B can do a piece of working 72 days : B and C and do it in 120 days ;
A and C can do it in 90 days. In what time can A alone do it ? ans 120 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
10 + 6 + 8 24
= = 1/30
720 720
(A+B+C) ‘s 1 day’s work = 1/30 x ½ = 1/60
17. A and B and C together can finish a piece of work in 4 days: alone can do it
in 12 days and B in 18 days, then C alone can do it in : ans 9 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
3+ 2
= = 5/36
36
∴ C’s one day’s work = (A+B+C)’s one day’s work – (A+B)’s 1 day’s work
= ¼ - 5/36
9− 5
= = 4/36 = 1/9
36
∴ C alone can do it in 9 days
Basic Formula:
Fraction’s addition
4+ 3+ 2 9
= = 1/8
72 72
(A+B+C) ‘s 1 day’s work = 1/8 x ½ = 1/16
∴ Altogether can do their work in 16 days.
Basic Formula:
Fraction’s multiplication
20. 45 men can complete a wok in 16 days. Six days after they started working
30 more men joined them. How many days will they now take to complete the
remaining work? Ans 6
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
21. 12 men can complete a work in 18 days six days after they started working
men joined them. How many days will all of them together complete the remaining
work? Ans 9
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
1 1
∴ 1 man’s 1 day’s work = =
12 x18 216
3− 1
Remaining work = 1 – 1/3 = = 2/3
3
2 2
2/3 work is done by them in ( x x 1) = 9 days.
27 3
22. Twelve men can complete a work in 8 days. Three days after started the
work 3 more men joined. In how many days will all of them together complete the
remaining work ans 4
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
1
∴ 1 man’s 1 day’s work = = 1/96
12 x8
3 8− 3 5
Remaining work = 1 - = =
8 8 8
96 5
∴ 5/8 work is done by them in ( x x 1) = 4 days.
15 8
23. A,B and C are employed to do apiece of work for Rs.529. A and C are
supposed to finish 19/23 of the work together. How much shall be paid to B?
Ans 9
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Ratio comparison
19 23 − 19
∴ B’s alone do the work = 1- = = 4/23
23 23
Basic Formula:
Fraction’s Addition
15 + 20
= = 7/120
600
25. A and B can do a piece of work in 5 days. B and C can do it in 7 days, A and C
can do it in 4 days. Who among these will take the least time if put to do it alone?
Answer : A
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
83 − 40 43
= 83/280 – 1/7 = =
280 280
B’s one day’s work = (A+B+C) ‘s 1 day’s work - (C+A)’s one day’s work =
83 − 70 13
83/280 – 1/4 = =
280 280
C’s one day’s work = (A+B+C) ‘s 1 day’s work - (A+B)’s one day’s work =
83 − 56 27
83/280 – 1/5 = = ⇒ Time taken by A, B, C is 280/43 , 280/13, 280/27
280 280
days respectively.
∴ The time taken by A is least.
26. A and B take 8 days, B and C 12 days. A, B and C take 6 days. A and C
take : Answer : 8 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
A alone can do the work = (A+B+C) ‘s 1 day’s work - (B+C)’s one day’s work
2− 1 1
= 1/6 – 1/12 = =
12 12
C alone do the work = (A+B+C) ‘s 1 day’s work - (A+B)’s one day’s work
4− 3 1
= 1/6 – 1/8 = =
24 24
1 1 2+ 1 3 1
∴ (A+C)’s one day’s work = + = = =
12 24 24 24 8
Basic Formula:
Fraction’s addition
5+ 4+ 3 12 1
= ⇒ (A+B+C) ‘s 1 day’s work = x ½ = 1/10
60 60 5
28. A and B can complete a work in 4 days. A alone takes 12 days, in how many
days B alone can complete the work? Answer: 6
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s subtraction
B’s one day’s work= (A+B)’s one day’s work - A’s one day’s work
= ¼ - 1/12 (take LCM 12)
3− 1 2
= = 1/6
12 12
∴ B alone can complete the work in 6 days.
29. 10 men and 15 women together can complete a work in 6 days. It takes 100
days for one man alone to complete the same work. How many days will be
required for one woman alone to complete the same work? Answer : 225
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s addition
Substitute x in (1)
10 x 1/100 + 15y = 1/6
1/10 + 15y = 1/6
10 − 6 4
15y = 1/6 – 1/10 = = = 1/15
60 60
∴ y = 1/15 x 1/15 = 1/225
30. A and B take 15 and 20 days respectively. They worked for 4 days, and then
the fraction of work left was: Answer : 8/15
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
31. X can do in 40 days. He worked for 8 days and then Y finished it in 16 days.
How long together take to finish the work? Answer : 13 1/3
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
3
(X+Y)’s one day’s work = 1/40 + 1/20 (take LCM = 40) =
40
∴ Both together will finish the work in 40/3 days = 13 1/3 days.
32. A does 4/5 of the work in 20 days. He then calls in B and they together
finish the remaining work in 3 days. How long B alone take to finish the whole
work? Answer: 37 ½
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
33. A takes 3 days and B 2 days. Both finished the work and got Rs.150. What
is the share of A ? Answer : 60
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fraction’s Multiplication
1
⇒ 3
5 x 150
6
⇒ 60
34. A can lay railway track between given stations in 16 days and B can do the
same job in 12 days. With the help of C, they did the job in 4 days only. Then, C
alone can do the job in :
1 2 3
a. 9 days b. 9 days c. 9 days d. 10 days
5 5 5
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
∴ C’s one day’s work = (A+B+C)’s one day’s – (A+B)’s one day’s work
= ¼ - 7/48 = 5/48
35. Ronald and Elan are working on an assignment. Ronald takes 6 hours to type
32 pages on a computer, while Elan takes 5 hours to type 40 pages. How much
time will they take, working together on two different computers to type an
assignment of 110 pages?
a. 7 hours 30 minutes b. 8 hours
c. 8 hours 15 minutes d. 8 hours 25 minutes
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fractions Multiplication
3
110 page will be type in 110 x x 1 = 8.25 minutes.
40
Basic Formula:
Fraction’s addition
Ie A finishes in 6 days
37. Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than
Sakshi. The number of days taken by Tanya to do the same piece of work is:
a. 15 b. 16 c. 18 d. 25
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Ratio comparison
A:b:: c:d
Ad = bc
38. A is 50% as efficient as B. C does half of the work done by A and B together.
If C alone does the work in 40 days, then A, B and C together can do the work in:
1
a. 13 days b. 15 days c. 20 days d. 30 days
3
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Fractions addition
A+ B
C’s one day’s work = --------(1)
2
39. A and B can complete a work in 15 days and 10 days respectively. They started
doing the work together but after 2 days B had to leave and A alone completed the
remaining work. The whole work was completed in:
a. 8 days b. 10 days c. 12 days d. 15 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
40. A and B can do a piece of work in 30 days, while B and C can do the same
work in 24 days and C and A in 20 day. They all work together for 10 days when B
and C leave. How many days more will A take to finish the work?
a. 18 days b. 24 days c. 30 days d. 36 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
4+ 5+ 6 15 1
= ⇒ (A+B+C) ‘s 1 day’s work = x ½ = 1/16
120 120 8
41. A, B and C are employed to do a piece of work for Rs.529. A and B together
19 8
are supposed to do of the work and B and C together of the work. What
23 23
amount should A be paid?
a. Rs.315 b. Rs.345 c. Rs.355 d. Rs.375
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
8 23 − 8
∴ A’s one day’s work = 1- = = 15/23
23 23
15
A’s share amount is Rs. = x 529
23
Rs. 345/-
42. A and B together can complete a work in 12 days. A alone can complete it in
20 days. If B does the work only for half a day daily, then in how many days A and
B together will complete the work?
a. 10 days b. 11 day c. 15 days d. 20 days
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
43. Twenty women can do a work in sixteen days. Sixteen men can complete the
same work in fifteen days. What is the ratio between the capacity of a man and
woman?
a. 3 : 4 b. 4 : 3 c. 5 : 3 d. Data inadequate
Difficulty Level : Easy Moderately easy Difficult
Basic Formula:
Ratio
Sixteen men can complete the same work in fifteen days = 15/16
320 : 240
4:3
44. 12 men can complete a piece of work in 4 days, while 15 women can complete
the same work in 4 days. 6 men start working on the job and after working for 2
days, all of them stopped working. How many women should be put on the job
complete the remaining work, if it is to be completed in 3 days?
a. 15 b. 18 c. 22 d. None of these
Basic Formula:
Ratio comparison
12 : 15 = 4 : 4
48 = 60
Members Days
Men 6 2
Women x 3
6 : x = 2:3 ⇒ 12 =3x ⇒ x = 4