(c) General Matters (continued)

CLASSIFICATION TABLE MEASUREMENT RULES DEFINITION RULES COVERAGE RULES SUPPLEMENTARY


INFORMATION
18. Injury to Persons and 1. Responsibility of the Item
Damage to Property Contractor for injury to
persons and damage to
property including public
or private roads

19. Insurances, etc. 1. Insurances against or Item


allowances to be made
Requirements in respect
of the following
insurances are given:
(a) Fire and extraneous
perils Contractors’ all
risks insurance of the
Works
(b) Injury to persons and
property Third party
liability insurance
(c) Workmen's
Employees’
compensation insurance
(d) Any other items of
insurance or guarantee
required by the
Conditions of Contract or
the Employer
2. Special requirements in
respect of minimum
acceptable limits of
liability and excesses are
stated.
3. Where insurances are to
be extended to cover
professional fees,
particulars are given.

14
III PRELIMINARIES 15

(c) General Matters (continued)


CLASSIFICATION TABLE MEASUREMENT RULES DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
INFORMATION
20. Provisional and Prime 1. Provisional and Prime Prov'l 1. Where the cost of
Cost Sums Cost (P.C.) Sums and Sum cartage, unloading,
the method of adjustment storing and returning
------- packing material is to be
P.C. included in the sum, it is
Sum so stated.

21. Conditions of Payment 1. Conditions of payment Item


22. Surety or Bond 1. Any surety or bond Item
required by the Employer

23. Watching 1. Care of the Works Item


generally, employment of
watchmen and protective
lighting
24. Protection 1. Protection of the work Item
and materials from
weather
2. Casing or covering up
and protecting
25. Treasure, Trove, 1. Disposal of any treasure Item
Coins, etc. Antiquities trove, coins or objects of
antiquity
26. Variations and Method 1. Particulars relating to Item
of Measuring and variations and the orders
Valuing for and method of
measuring and valuing
the same
2. Particulars relating to
dayworks accounts
27. Samples 1. Submission of samples Item

28. Testing of Materials 1. Conditions relating to the Item


testing of materials
(c) General Matters (continued)
CLASSIFICATION TABLE MEASUREMENT RULES DEFINITION RULES COVERAGE RULES SUPPLEMENTARY
INFORMATION
29. Removal of Water 1. Keeping the site and all 1. Water levels, where Item C.1 applies. S.1 Dewatering
excavations thereon free known, are stated. requirements, where not
from storm and at the discretion of the
percolating water by Contractor.
pumping or otherwise,
including any necessary
temporary drainage and
disposal of water
2. Where springs or running Prov’l
water are likely to be Sum
encountered.
-------
Prov’l
numb
er of
pump
ing
hours

30. Water 1. Water for the Works, Item 1. If made available by the C.1 applies.
including that for Employer, details and
Nominated Sub- conditions are stated.
Contractors, Specialist
Contractors employed by
the Employer, statutory
undertakers and utility
companies and any
necessary temporary
plumbing and storage
31. Lighting and Power 1. Lighting and power for Item
the Works, including that
for Nominated Sub-
Contractors, Specialist
Contractors employed by
the Employer, statutory
undertakers and utility
companies and any
necessary temporary
wiring and meters