GOVERNMENT OF KARNATAKA

WATER RESOURCES DEPARTMENT


(MAJOR AND MEDIUM)

ANNUAL REPORT

2008-09

JULY 2009
INDEX
SL. PAGE
CONTENTS
NO. NO.
1 INTRODUCTION 5
2 ORGANISATIONAL STRUCTURE 6
3 ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 2008-09 7
4 ACCELERATED IRRIGATION BENEFIT PROGRAMME 9
5 SPECIAL REHABILITATION PACKAGE 15
6 WATER RESOURCES DEVELOPMENT ORGANISATION 16
7 CENTRAL MECHANICAL ORGANISATION 25
8 KARNATAKA ENGINEERING RESEARCH STATION 28
9 WATER AND LAND MANAGEMENT INSTITUTE (WALMI) 33

NIGAM
10 KRISHNA BHAGYA JALA NIGAM LIMITED 34
10.1 UPPER KRISHNA PROJECT 35
10.2 BAGALKOT TOWN DEVELOPMENT AUTHORITY, BAGALKOT 45
11 KARNATAKA NEERAVARI NIGAMA LIMITED 49
11.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 50
(NORTH), BELGAUM
11.1.1 GHATAPRABHA PROJECT 51
11.1.2 HIPPARAGI IRRIGATION PROJECT 52
11.1.3 MARKANDEYA RESERVOIR PROJECT 53
11.1.4 DUDHGANGA IRRIGATION PROJECT 54
11.1.5 LIFTING OF HIRANYAKESHI WATERS INTO G.R.B.C CANAL 55
11.1.6 BELLARYNALA PROJECT 56
11.1.7 SRI RAMESHWARA L.I. SCHEME 57
11.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MALAPRABHA 58
PROJECT ZONE, DHARWAD.
11.2.1 MALAPRABHA PROJECT 59
11.2.2 HARINALA IRRIGATION PROJECT 60
11.2.3 KALASA NALA AND BANDHURNALA PROJECT 61
11.2.4 JAVALUHALLA L.I. SCHEME 62
11.2.5 BENNIHALLA L.I. SCHEME (5 NOS.) 63
11.2.6 KOLACHI L.I. SCHEME 64
11.2.7 KONNUR L.I. SCHEME 65
11.2.8 SHIGGAON L.I. SCHEME 66
11.3 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 67
CENTRAL ZONE, MUNIRABAD

2
SL. PAGE
CONTENTS
NO. NO.
11.3.1 SINGATALUR LIFT IRRIGATION SCHEME (SLIS) 67
11.4 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER TUNGA 68
PROJECT ZONE, SHIMOGA
11.4.1 UPPER TUNGA PROJECT 70
11.4.2 TUNGA LIFT IRRIGATION SCHEME 72
11.4.3 BASAPURA LIFT IRRIGATION SCHEME 73
11.4.4 ITAGI-SASALWAD LIS 74
11.4.5 GUDDADA MALLAPURA LIS 75
11.4.6 UPPER BHADRA PROJECT (STAGE 1 & 2) 76
11.4.7 UBRANI-AMRUTHAPURA MULTIPURPOSE LIS 77
11.4.8 SANYASIKOPPA LIS 78
11.4.9 KALLUVADDAHALLA NEW TANK 79
11.4.10 TILUVALLI LIFT IRRIGATION SCHEME 80
11.5 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI PROJECT 81
ZONE, SIDDAPURA.
11.5.1 VARAHI IRRIGATION PROJECT 81
11.6. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 83
PROJECTS ZONE, GULBARGA
11.6.1 BENNITHORA PROJECT 83
11.6.2 BHIMA LIFT IRRIGATION SCHEME 84
11.6.3 GANDORINALA PROJECT 86
11.6.4 LOWER MULLAMARI PROJECT 88
11.6.5 AMARJA PROJECT 89
12 CAUVERY NEERAVARI NIGAMA LIMITED 91
12.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION (S) 92
ZONE, MYSORE
12.1.1 D. DEVARAJA URS CANAL 93
12.1.2 KABINI RESERVOIR PROJECT 94
12.1.3 HARANGI PROJECT 96
12.1.4 TARAKA PROJECT 98
12.1.5 ARKAVATHY PROJECT 99
12.1.6 CHIKLIHOLE PROJECT 101
12.1.7 UDUTHOREHALLA PROJECT 102
12.1.8 IGGALUR BARRAGE PROJECT 103
12.1.9 MANCHANABELE PROJECT 105
12.1.10 MODERNISATION OF KRISHNARAJA SAGAR 106

3
SL. PAGE
CONTENTS
NO. NO.
12.1.11 NANJAPURA LIFT IRRIGATION SCHEME 107
12.1.12 BANAHALLIHUNDI LIS 108
12.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY 109
CANAL ZONE, TUMKUR
12.2.1 HEMAVATHY CANAL ZONE, TUMKUR 109
12.3 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, HEMAVATHY 112
RESERVOIR PROJECT, GORUR
12.3.1 HEMAVATHY PROJECT 112
12.3.2 YAGACHI PROJECT 114
12.3.3 HUCHANAKOPPALU LIS 115
12.3.4 KAMASAMUDRA LIS 116
12.3.5 KACHENAHALLI LIS 117
12.3.6 VOTEHOLE PROJECT 118
ZONES 119
13 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 120
PROJECT ZONE, GULBARGA
13.1 KARANJA PROJECT 120
14 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION 121
CENTRAL ZONE, MUNIRABAD
14.1 TUNGABHADRA PROJECT 121
14.2 HIREHALLA POJECT 124
14.3 MASKINALA PROJECT 126
14.4 OTHER WORKS (NEW) 128
15 AN OVERVIEW OF PROJECTS UNDER THE ENGINEER-IN-CHIEF, UPPER TUNGA 129
PROJECT ZONE, SHIMOGA
15.1 BHADRA PROJECT 130
15.2 MODERNISATION OF CANAL SYSTEM OF TUNGA ANICUT 131
15.3 HODIRAYANAHALLA DIVERSION SCHEME 132
15.4 MODERNISATION OF CANAL SYSTEM OF AMBLIGOLA RESERVOIR 133
15.5 MADAGA –MASUR TANK 134
15.6 ERM OF BHEEMASAMUDRA TANK 135
15.7 MODERNISATION OF CANAL SYSTEM OF GONDI ANICUT (BHADRA) 136
15.8 KADUVINABYLU LIFT IRRIGATION SCHEME 136
15.9 THIMMAPURA LIFT IRRIGATION SCHEME 136
15.10 ANJANAPURA RESERVOIR PROJECT 136
16 COMMAND AREA DEVELOPMENT PROGRAMME 137

4
1. INTRODUCTION

The Annual Report is a document giving details of the annual Programme, Progress and important events
that have taken place during the year, in the Water Resources Department.

GEOGRAPHICAL AREA

The geographical area of Karnataka is 1,91,791 Sq. Km., accounting for 5.83% of the total area of the
country.

The cultivable command area of the State is 1, 40,598 sq. Km. The net sown area is 1,07,000 sq. Km and
the ultimate Irrigation Potential from Major and Medium Irrigation Projects has been estimated as 35,000 sq.
Km or 35.00 Lakh Ha.

PROGRESS IN BRIEF

Presently, the Irrigation Department is known as the Water Resources Department.

There are 133 Major and Medium Irrigation Projects in the State, out of which 47 projects are
completed, 76 are ongoing.

The Water Resources Department has established three special purpose vehicles, namely, Krishna
Bhagya Jala Nigama Limited (KBJNL), Karnataka Neeravari Nigama Limited (KNNL) and Cauvery Neeravari
Nigam Limited (CNNL), under the companies Act of 1956, to mobilize financial resources for speedy
completion of major and medium irrigation projects with-in the targeted period.

KRISHNA BHAGYA JALA NIGAM LIMITED (KBJNL):

“Krishna Bhagya Jala Nigam Limited” was formed vide G.O. No. ID/25/WBM/95, dated: 6-5-
94, to expedite the works of Upper Krishna Project (UKP). This Nigam is functioning since 19th August 1994.

KARNATAKA NEERAVARI NIGAMLIMITED (KNNL):

”Karnataka Neeravari Nigam Limited” was formed vide G.O. No. ID: 201: KBN: 98, dated: 26-11-98,
to expedite the works in Krishna Basin, except UKP. This Nigam is functioning since 9th December 1998.

CAUVERY NEERAVARI NIGAM LIMITED (CNNL):

”Cauvery Neeravari Nigam Limited” was formed vide G.O. No. WRD: 32: KBN: 2003, Dated:
12.05.2003, to expedite the works in Cauvery Basin. This Nigam is functioning since 3 rd June 2003.

INDEX

5
1. ORGANISATIONAL STRUCTURE
WATER RESOURCES DEPARTMENT

HON’BLE MINISTER FOR WATER RESOURCES

PRINCIPAL SECRETARY

SECRETARY

C.E, DIRECT CADA’S KBJNL BOARD KNNL BOARD CNNL BOARD


W.R.D.O FIELD OF DIRECTORS OF DIRECTORS OF
OFFICES DIRECTORS
ADMINISTRATOR
MALAPRABHA & REGISTERED REGISTERED
CE,
GHATAPRABHA, CORPORATE CORPORATE REGISTERED
HYDROLOGY
CE, IRRIGATION BELGAUM OFFICE CORPORATE
& CMO, OFFICE
CENTRAL ZONE, OFFICE
BANGALORE
MUNIRABAD
FIELD OFFICES FIELD OFFICES
ADMINISTRATOR FIELD
C.E, TUNGABHADRA
I.S.W.D, OFFICES
CE, IRRIGATION PROJECT,
BANGALORE CE, O&M ZONE, CE, UTP
PROJECT ZONE, MUNIRABAD
UKP, ZONE,
GULBARGA CE,
NARAYANPURA SHIMOGA IRRIGATION
(SOUTH),
ADMINISTRATOR CE, DAM ZONE, MYSORE
CE, UPPER BHADRA, UKP, ALMATTI CE, VARAHI
TUNGA SHIMOGA ZONE,
PROJECT, SIDDAPURA
SHIMOGA CE, H.P.Z,
CE, CANAL ZONE-
ADMINISTRATOR GORUR
1, UKP, B.GUDI
CAUVERY BASIN, CE, IPZ,
MYSORE GULBARGA
DIRECTOR,
CE, CANAL CE, H.C.Z,
WALMI
ZONE-2, UKP, TUMKUR
CE,
ADMINISTRATOR KEMBHAVI
IRRIGATION
UKP, B.GUDI (NORTH),
DIRECTOR,
K.E.R.S BELGAUM

ADMINISTRATOR
CE,
IRRIGATION
MALAPRABHA
PROJECT ZONE,
PROJECT
GULBARGA
ZONE,
DHARWAD

CE, UPPER
BHADRA
PROJECT,
CHITRADURGA

6
3. ACHIEVEMENTS OF WATER RESOURCES DEPARTMENT DURING 2008-09

 During 2008-09, 7 Major & medium irrigation projects are completed and irrigation potential of 47201 ha.
Is created.

 The ultimate irrigation potential is 35 lakh Ha from Major & medium irrigation projects. Upto end of March
2009, cumulative irrigation potential of 24.28 lakh ha has been created.

 Out of the targetted irrigation potential of 6.22 Lakh Ha under Upper Krishna Project, an irrigation potential
of 5.88 lakh Ha has been created so for. The balance works of Jewargi Branch Canal, Narayanapur Right
Bank Canal, Mulwad Lift Irrigation Scheme, Almatti Right Bank Canal and Almatti Left Bank Canal of
Upper Krishna Project are nearing completion.

 To utilize Krishna waters under Upper Krishna Project, Ramthal (Marol) Lift Irrigation Scheme, Teggi-
Siddapura Lift Irrigation Scheme, Thimmapura Lift Irrigation Scheme, Sonna Lift Irrigation Scheme and
Rolli-Mannikeri Lift Irrigation Scheme are taken up in the backwaters of Almatti Reservoir and are in
progress.

 During 2008-09, Central Assistance under A.I.B.P. to the tune of Rs. 214.94 Crores for 6 Major & medium
irrigation projects has been availed and an expenditure of Rs. 418.87 Crores has been incurred.

 17 Major & Medium irrigation projects in six selected districts are posed for assistance under the Hon‟ble
Prime Minister‟s Special Rehabilitation Package out of which, 8 projects are dropped. Planning Commission
clearance in respect of three projects of Belgaum District is awaited. Up to end of March 2009 a sum of
Rs.278.77 Crores is released for 4 projects and total expenditure incurred on all 17 projects is Rs.1074.68
Crores and an irrigation potential of 59,815 Ha is created.

 To utilize its share of Godavari waters resourcefully, the State has taken up the construction of series of
Barrages like Jigrihal, Manikeshwar, Halahalli and Chandapur barrages are in progress. These barrages are
being implemented by Krishna Bhagya Jala Nigam Limited.

 Cauvery Neeravari Nigam Limited has activated the potential oriented works under Cauvery Basin. In order
to minimize the advert consequences of the Cauvery water dispute tribunal‟s award, it has been programmed
to develop 1252 minor irrigation tanks coming under the command area of major and medium irrigation
projects in Cauvery basin.

 During 2008-09, Karnataka Neeravari Nigam Limited has incurred an expenditure of Rs. 1200.98 Crores
for implementing 37 major and medium irrigation projects/Components of projects against an annual
programme of Rs.611.36 Crores.

 Upper Bhadra Project is proposed to utilise 21 .50 tmc of water to feed tank in drought prone districts of
Kolar, Tunkur and Chitradurga. Three packages amounting to Rs.825.00 crores has been taken up as per
Technical Report in Stage-I of the project. Office of the Chief Engineer is formed at Chitradurga at this
purpose.

7
 For efficient Water management 12 package tenders amounting to Rs.702.00 Crores are invited for
Modernisation of the Main canal and 5 Branch canals of Bhadra Canal Network. Modernization works are
in progress.

 For efficient & effective water management under the Command Areas of Major & medium irrigation
projects, Water Resources Department has established 2,392 Water Users Co-operative Societies.

 The works of Kalasanala diversion scheme in non-forest regions have been taken up during the current year
for supplementing drinking water resources to the twin cities of Hubli and Dharwad.

The details of the targets and achievements in respect of the Major and Medium irrigation Projects for
the year 2008-09 up to end of March 2009 are as hereunder.

Sl. Financial (Rs. In Crores) Physical (in Hectares)


Project
No Program Progress Program Progress
1 Krishna Bhagya Jala Nigama 1,014.21 946.90 10,386 4,668
2 Karnataka Neeravari Nigama 893.70 865.09 43,582 30,776
3 Cauvery Neeravari Nigama 652.76 532.60 21,032 11,757
4 Non Nigam Zones of WRD 165.19 83.17 214 0
Total 2,725.86 2,427.76 75,214 47,201

INDEX

8
4. ACCELERATED IRRIGATION BENEFIT PROGRAMME

For the early completion of some of the ongoing irrigation projects, which were lingering due to shortage
of funds for many years, the Government of India launched the Accelerated Irrigation benefit programme,
during 1996-97. Since then, eight projects in the State, namely, Upper Krishna project (UKP) Stage-I, Phase-III,
Malaprabha, Hirehalla, Ghataprabha, Karanja, Upper Krishna project (UKP) Stage-II, Maskinala, and
Gandhorinala have received Central Loan Assistance (CLA) / (CA) under Accelerated Irrigation benefit
programme (AIBP).

 During 1996-97, at the end of 8th Five Year Plan, the Government of India launched the Accelerated
Irrigation Benefit Programme (A.I.B.P.) with the intention of completing those projects lingering due to
shortage of funds. From 1996-97 to 2002-03, the sharing between the centre and the state was in the ratio
of 50:50. Since 2002-03, the sharing is in the ratio of 2/3:1/3.

 During 2008-09, UKP Stage I, Phase III, UKP Stage II, Malaprabha, Ghataparbha, Karanja and Varahi
are the 6 projects that have received / are receiving C.L.A. under A.I.B.P.
 The cumulative C.L.A. (including grants) released upto end of March 2009 is Rs. 3,351.36 Crores. The
cumulative expenditure incurred on these projects up to the end of March 2009 is Rs. 4,797.53 Crores.
 During 2004-05, loans along with grants were released to the projects in the ratio of 70: 30.
 The Central Assistance released, during 2008-09, to 6 projects namely UKP Stage I Phase III, UKP Stage
II, Malaprabha, Ghataprabha-III, Karanja and Varahi is Rs. 214.94 Crores.

 The expenditure incurred on these 6 projects during 2008-09 upto end of March 2009 is Rs.481.87
Crores.

STATEMENT SHOWING DETAILS OF C.L.A. UNDER A.I.B.P RELEASED TO MAJOR AND


MEDIUM IRRIGATION PROJECTS (SINCE 1996-97)
(Rs. in Crores)

CLA
NO. OF CLA
PERIOD PROPOSED / EXPENDITURE
PROJECTS RELEASED
SANCTIONED
1996-97 5 122.50 61.25 172.21
1997-98 5 175.00 90.50 160.49
1998-99 5 167.00 94.50 171.05
1999-00 5 190.64 157.14 190.61
2000-01 4 171.00 171.00 268.26
2001-02 7 545.00 492.50 911.38
2002-03 8 611.97 620.85 693.00
2003-04 8 266.48 266.48 440.57
2004-05 5 463.05 449.71 475.46
2005-06 5 336.70 291.23 473.24

9
2006-07 6 568.91 334.00 457.15
2007-08 5 410.22 322.20 350.59
2008-09 6 294.25 214.94 481.87
TOTAL UPTO MARCH 2009 4322.72 3566.30 5245.88
Details of Central Assistance (CA) under AIBP during 2008-09
(Rs. in Crores)

CLA CLA EXPENDITURE


Sl. No. PROJECTS
SANCTIONED RELEASED incurred during 08-09

UKP Stage-I
1 102.14 91.92 139.36
Phase-III
2 UKP Stage-II 44.14 8.019 176.72
3 Ghataprabha 57.82 52.04 44.56
4 Malaprabha 33.94 30.54 27.72
5 Gandhorinala 18.02 0.00 17.97
6 Varahi 22.41 20.17 64.76
7 Karanja 15.78 12.25 10.78
Total 294.25 214.94 481.87

10
CUMULATIVE STATEMENT
CLA Released
(Rs. in Crores)

Sl. 1999- CUMULA


Project 1996-97 1997-98 1998-99 2000-2001 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
2000 TIVE
No

UKP Stage-I
1 57.00 50.00 50.00 100.00 100.00 200.00 181.00 - 115.85 - 71.638 71.23 91.92 1088.64
Phase-III

2 UKP Stage-II - - - - - 250.00 275.05 163.48 240.72 197.76 172.53 102.07 8.019 1409.63

3 Malaprabha 1.50 12.00 10.00 13.50 - 10.00 25.56 - 12.00 20.00 13.50 54.24 30.54 202.84

4 Hirehalla 2.75 6.00 6.00 8.00 8.00 10.00 8.78 14.71 - - - - 0.00 64.24

5 Ghataprabha - 15.00 12.50 20.00 45.00 5.00 75.00 13.02 62.09 65.00 30.805 72.61 52.04 468.06

6 Karanja - 7.50 16.00 15.64 18.00 10.00 34.37 75.27 - - - - 12.25 189.03

7 Gandhorinala - - - - - 7.50 17.87 - 19.05 8.47 45.53 - 0.00 98.42

8 Maskinala - - - - - - 3.22 - - - - - 0.00 3.22

9 Varahi - - - - - - - - - - - 22.05 20.17 42.22

TOTAL 61.25 90.50 94.50 157.14 171.00 492.50 620.85 266.48 449.71 291.23 334.00 322.20 214.94 3,566.30

11
Expenditure

Sl. 1999- 2000- CUMULAT


Project 1996-97 1997-98 1998-99 2001-02 2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09
No 2000 2001 IVE

UKP Stage-I
1 155.74 92.30 77.58 116.40 187.80 235.33 214.69 94.19 92.18 61.13 46.19 49.30 139.36 1562.19
Phase-III

2 UKP Stage-II - - - - - 534.10 352.29 236.48 268.17 272.29 234.58 86.80 176.72 2161.43

3 Malaprabha 5.12 14.92 22.64 9.87 5.15 15.87 14.45 14.42 19.64 19.62 31.28 56.37 27.72 257.07

4 Hirehalla 11.35 17.12 12.06 15.82 22.68 11.41 11.69 9.94 18.45 - - - - 130.52

5 Ghataprabha - 20.47 28.82 20.04 26.96 72.77 57.57 55.45 64.68 92.47 77.29 76.90 44.56 637.98

6 Karanja - 15.68 29.95 28.48 25.67 26.55 23.62 18.64 - - - - 10.78 179.37

7 Gandhorinala - - - - - 15.35 16.82 10.09 12.34 27.73 34.96 - 17.97 135.26

8 Maskinala - - - - - - 1.87 1.36 - - - - - 3.23

9 Varahi - - - - - - - - - - 32.85 81.22 64.76 178.83

TOTAL 172.21 160.49 171.05 190.61 268.26 911.38 693.00 440.57 475.46 473.24 457.15 350.59 481.87 5245.88

12
DETAILS OF PROJECTS ASSISTED UNDER AIBP PROGRAMME (YEARLY)
(As on 31-3-2009)
(Rs. in Crores)

1996-97 1997-98 1998-99 1999-2000 2000-01 2001-02


Sl. CLA CLA CLA CLA CLA CLA
Project CLA Expendit CLA Expendi CLA Expendi CLA Expendi CLA Expendi CLA Expendi
No Sanctio Sanctio Sanctio Sanctio Sanctio Sanctio
Released ure Released ture Released ture Released ture Released ture Released ture
ned ned ned ned ned ned

UKP Stage-I
1 114.00 57.00 155.74 100.00 50.00 92.30 100.00 50.00 77.58 100.00 100.00 116.40 100.00 100.00 187.80 200.00 200.00 235.33
Phase-III

2 UKP Stage-II - - - - - - - - - - - - - - - 250.00 250.00 534.10

3 Malaprabha 3.00 1.50 5.12 24.00 12.00 14.92 20.00 10.00 22.64 27.00 13.50 9.87 - - 5.15 20.00 10.00 15.87

4 Hirehalla 5.50 2.75 11.35 6.00 6.00 17.12 6.00 6.00 12.06 8.00 8.00 15.82 8.00 8.00 22.68 10.00 10.00 11.41

5 Ghataprabha - - - 30.00 15.00 20.47 25.00 12.50 28.82 40.00 20.00 20.04 45.00 45.00 26.96 30.00 5.00 72.77

6 Karanja - - - 15.00 7.50 15.68 16.00 16.00 29.95 15.64 15.64 28.48 18.00 18.00 25.67 20.00 10.00 26.55

7 Gandhorinala - - - - - - - - - - - - - - - 15.00 7.50 15.35

8 Maskinala - - - - - - - - - - - - - - - - - -

Total 122.50 61.25 172.21 175.00 90.50 160.49 167.00 94.50 171.05 190.64 157.14 190.61 171.00 171.00 268.26 545.00 492.50 911.38

13
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08
Sl. CLA CLA CLA CLA CLA CLA CLA CLA CLA
Project CLA Expendit CLA Expendit Expend Expend CLA Expend Expend
No Sanctio Sanctio Sanction Release Sanctio Release Release Sanctio Release
Released ure Released ure iture iture Sanctioned iture iture
ned ned ed d ned d d ned d
UKP Stage-I
1 181.00 181.00 214.69 - - 94.19 115.85 115.85 92.18 39.01 - 61.13 74.87 71.64 46.19 94.46 71.23 49.30
Phase-III

2 UKP Stage-II 275.05 275.05 352.29 163.48 163.48 236.48 241.22 240.72 268.17 204.22 197.76 272.29 168.77 172.5 234.58 131.66 102.1 86.80

3 Malaprabha 25.56 25.56 14.45 - - 14.42 12.00 12.00 19.64 20.00 20.00 19.62 54.00 13.50 31.28 60.27 54.24 56.37

4 Hirehalla 9.90 8.78 11.69 14.71 14.71 9.94 12.84 - 18.45 - - - - - - - - -

5 Ghataprabha 75.00 75.00 57.57 13.01 13.015 55.45 62.09 62.09 64.68 65.00 65.00 92.47 123.21 30.81 77.29 99.33 72.61 76.90

6 Karanja 34.37 34.37 23.62 75.27 75.27 18.64 - - - - - - - - - - - -

7 Gandorinala 17.87 17.87 16.82 - - 10.09 19.05 19.05 12.34 8.47 8.47 27.73 55.87 45.53 34.96 - - -

8 Maskinala 3.22 3.22 1.87 - - 1.36 - - - - - - - - - - -

9 Varahi - - - - - - - - - - - - 18.25 - 32.85 24.50 22.05 81.22

Total 621.97 620.85 693.00 266.47 266.48 440.57 463.05 449.71 475.46 336.70 291.23 473.24 494.97 334.00 457.15 410.22 322.20 350.59

Sl. 2008-09 CUMULATIVE


Project
No CLA Sanctioned CLA Released Expenditure CLA Released Expenditure
1 UKP Stage-I Phase-III 102.14 91.92 139.36 1088.64 1562.19
2 UKP Stage-II 44.14 8.019 176.72 1409.63 2161.43
3 Malaprabha 33.94 30.54 27.72 202.84 257.07
4 Hirehalla - - - 64.24 130.52
5 Ghataprabha 57.82 52.04 44.56 468.06 637.98
6 Karanja 15.78 12.25 10.78 189.03 179.37
7 Gandorinala 18.02 - 17.97 98.42 135.26
8 Maskinala - - - 3.22 3.23
9 Varahi 22.41 20.17 64.76 42.22 178.83
Total 294.25 214.94 481.87 3566.30 5245.88
INDEX

14
5. SPECIAL REHABILITATION PACKAGE

During 2006-07, the Special Rehabilitation Package was launched by the Government of India to mitigate
the distress of farmers in selected 31 districts of the Country from where large numbers of Suicide cases by the
farmers were reported.

In Karnataka, the 6 districts viz Belgaum, Bijapur, Shimoga, Chikkamagalur, Chitradurga, Hassan and
Kodagu were identified as drought prone districts and 17 projects benefiting these 6 districts were identified and
proposals of the same have been submitted.

An allocation of Rs. 1208.71 Crores has been made towards major and medium Irrigation sector under
assured irrigation. Out of this the grant portion of Rs.725.24 Crores will be borne by the center and the loan
portion of Rs.483.47 Crores will be met-out of state funds. The funding proposed is as per revised AIBP norms.

The details of the 17 projects are as follows:


(Rs. In Crores)
SL. BALANCE COST OF THE
NAME OF THE PROJECT
NO. PROJECT
MAJOR
1 Malaprabha 120.98
2 Ghataprabha-III 159.68
3 Hipparagi 934.92
4 Markandeya 56.41
5 ERM of Bhadra Reservoir project 400.00
6 Harangi 12.57
7 Hemavathy 64.54
8 Yagachi 127.78
9 Dudhganga 37.79
MEDIUM
10 Kamasamudra LIS 18.42
11 Huchanakoppalu LIS 14.00
12 Votehole 1.50
13 Kachenahalli LIS 79.88
14 Chiklihole 1.50
15 ERM of Bheemasamudra tank 4.00
16 Srirameshwara LIS 212.38
17 Bellarynala LIS 131.36
TOTAL 2530.05

Out of this, Malaprabha and Ghataprabha are already receiving Central Assistance under AIBP. Markandeya,
Chiklihole and Votehole projects are completed. Hippargi, Dudhganga and Modernisation of Bhadra projects
for availing Central Assistance and package sine 2007-08. Approval of Planning Commission is pending to 6
irrigation projects of Cauvery Basin. Approval in 3 irrigation projects in Krishna basin is awaited. Assistance
under package is extended upto 2012.

INDEX

15
6. WATER RESOURCES DEVELOPMENT ORGANISATION

ACTIVITIES:
This Organisation is incharge of Planning and Investigation of all Major and Medium Irrigation
Projects in the State and provides all the information to the Government in respect of Inter State Water Disputes
like Cauvery, Krishna, Godavari and Mahadayi. This Organisation acts as a data Bank for all
Hydrological details of Rivers and streams in the State by collecting and processing the raingauge and River
gauge data in a systematic manner. This Organisation provides information regarding completed, ongoing and
proposed irrigation projects of the state. This organisation prepares Catchment Area Maps indicating influencing
rain guage stations, digital maps of all hydro meteorological states of Karnataka state, command area maps of
completed, ongoing and proposed irrigation projects under Cauvery and Krishna river basin using the latest
software viz., GIS, Remote sensing and Autodesk map. The work of monitoring and evaluation of existing and
ongoing projects and safety aspects of dams are monitored by this organisation. In addition, the establishment
matter of Irrigation zones regarding postings, transfer of staff and Regularisation of Daily Wages Staff and
Monthly Rated Staff as per Supreme Court order is also attended to by this Organisation.

 PLANNING AND INVESTIGATION UNIT

 This Unit is attending to the work of Technical Scrutiny of New Major and Medium Irrigation Projects,
conducting survey and investigation of major & medium irrigation projects, preparing preliminary investigation
report and detailed project report of the same, replies to C.W.C. comments and arranging for clearance of
projects and correspondence between State and Central Governments regarding Irrigation Projects.

 During 2008-09, 15 Projects under Krishna Basin and 5 Projects under West flowing River basin totally
20 Major and Medium Irrigation Projects are under different stages of investigation.

 In addition to the above investigation works, the following works are also dealt with in this unit.

 e– Governance in Water Resources Department:

Water Resources Development Organization is monitoring the e-Governance activities of entire Water
Resources Department in Karnataka. Short-term courses to use Computers for the Technical and Non-Technical
staff are being conducted regularly. This Unit manages the Website of Water Resources Department
“http://waterresources.kar.nic.in” which includes details of Nigams and the following data

a) Right to Information Act


b) Schedule of Rates
c) Preparation of material required for National Performance of dam
programme for Dam safety.
d) Salient features of Major and Medium Irrigation Projects.
e) Hierarchy of Administration in Water Resources Department and
f) Tender Bulletins.
g) Overlay of projects on Google earth.

16
 Right to Information Act:
Requisitions from public regarding Water Resources Department are answered within a stipulated period of
one month and updated periodically in the Departmental Website.

 Experts Committee for diversion projects and regarding availability of water in various River
basins:
To study the availability of water in various West Flowing River basins and also to conduct studies regarding
the projects, an Expert Committee in co-ordination with NRSA is formed. Survey works is in progress.

 Neeravari Software:
Neeravari Software needs to be stabilized and rebuilt with new platform, architecture and software as
per the latest technology.

 High Level Committee:


The Government has constituted a High Level Committee under the Chairmanship of Sri. D.N. Desai
vide G.O. No. WRD /101/ MBI/ 2008 dated 11.12.2008 to prepare “Draft Water Policy” for
distribution of water to various sectors of the State. This committee held its first meeting on 11.03.2009.
The Chief Engineer, WRDO is the member secretary to this committee. At present this committee is
functioning and report is awaited.

 Implementation of Irrigation Information System using GIS Technology:


Rs.250 crores was provided during 2007-08 in the budget for implementation of Irrigation Information
System using GIS Technology. It is proposed to have decision support system through GIS equation.
TAP meeting held on 18.12.2007 has permitted to procure digital data. Process of procurement of digital
data through Survey of India, Dehradun is in progress. Detailed architecture and request for proposal is to
be obtained from 3 private companies.

 Other activities:
This Unit corresponds with State & National level Organisations like Central Water Commission, Bureau
of Indian Standards, Indian National Committee for Irrigation & Drainage, Water & Power Consultancy
Services and Central Board of Irrigation and Power. This Unit attends to the Committee meetings conducted by
these Organisations and provides information requested by them.
This Unit provides information for attending the meetings of Subject Committee, Assurance Committee,
Estimate Committee and Petition committee.
This unit deputes officers of this organisation to various training programme, seminar, conference,
workshop etc. to update their knowledge regarding latest technology and development in the water resources
sector.

 CAUVERY UNIT
Introduction:

17
The Cauvery unit of Water Resources Development Organisation, Bangalore deals with the matters
concerning sharing of waters of the River Cauvery with the other riparian States viz., Tamil Nadu, Kerala and
Union Territory of Pondicherry.

Organisation:
The Cauvery Unit was formed during 1990 with staff of W.R.D.O. It was functioning under the then
Chief Engineer, W.R.D.O. Bangalore.

Activities:
 The Cauvery Water Disputes Tribunal was set up by the Ministry of water Resources, Government of India,
vide its order No. 21.1.90 WD dated: 2.6.1990 with Head quarters at New Delhi for adjudication of the
Cauvery Water Dispute.

 To safe guard the interests of Karnataka and to substantiate the stand of the Government before the Supreme
Court/Cauvery water Disputes Tribunal a team of Advocates along with the Advocate General of Karnataka
is appointed and their services are being utilised.

 The current team of Advocates appointed by the Government to represent Cauvery Water Disputes is as
under:

1 Advocate General of Karnataka


2 Sri. F.S.Nariman Senior Advocate
3 Sri. Anil B. Divan Senior Advocate
4 Sri. S.S.Javali Senior Advocate
5 Sri. Mohan V. Katarki Advocate
6 Sri. Shambhu Prasad Singh Advocate
7 Sri. Sanjay R. Hegde Advocate
8 Sri. S.C.Sharma Advocate
9 Sri. Ranvir Singh Advocate
10 Sri. Brijesh Kalappa Advocate

 To get technical advise in Cauvery Water Disputes matter two Technical Advisors were appointed by
the Government and their services are being continued.

 For effective participation and pleading the case of Karnataka before the Cauvery Water Dispute
Tribunal, Cauvery water Cell established in 1990 is now functioning in Karnataka Bhavan-III
(Bheema), Hudco Place, Andrews Ganj, New Delhi.

 This unit renders technical assistance to the Advocates engaged by the state to appear before the
Cauvery water Dispute Tribunal and Supreme Court. This unit also prepares documents and other
required materials for the Technical Committee, All Party Meetings and other related meetings.

In addition, this unit also carries out the following works.


 Collection and analysing data regarding Reservoir levels, inflow, etc., of the Cauvery Basin
Projects in the State.

18
 Preparation of brief and draft replies in connection with the reactions from the public and other
State Governments, which appear in press.

 Collection and updating of materials that are relevant to the Cauvery water Disputes etc.,

This unit also renders its views on the matters connected with the West Flowing River Development,
National & State Water Policy, National water Board and NWDA studies regarding Water balance whenever
such files are referred to.

Physical and Financial targets and Achievements:


The significant developments before the Cauvery Water Dispute Tribunal and Supreme Court
concerning the Cauvery water Dispute during the year 2008-09 are as follows:

Before the Cauvery Water Dispute Tribunal:

The Cauvery Water Disputes Tribunal announced its final verdict along with report on 05.02.2007. As
per the judgement the allocation of 740 tmc (available in Cauvery basin at 50% dependability) to the party States
is as under:

1 Kerala 30 tmc
2 Karnataka 270 tmc
3 Tamil Nadu 419 tmc
4 Union Territory of Pondicherry 7 tmc
5 Environmental protection 10 tmc
6 Inevitable escapages into sea 4 tmc
Total 740 tmc

Further it is ordered in the judgement that Karnataka should ensure 192 tmc at Biligundlu (gauging
station maintained by CWC) as under:

Month TMC Month TMC


June 10 December 8.00
July 34 January 3.00
August 50 February 2.50
September 40 March 2.50
October 22 April 2.50
November 15 May 2.50
Total 192.0 tmc

Aggravated by the final orders of the Tribunal Karnataka Government filed review petition under
Section 5(3) of Inter State Water Disputes Act on 03.05.2007 before the Cauvery Water Dispute Tribunal. All
other party States have also filed review petition under Section 5(3). In addition to review petition, State of
TamilNadu had filed CMP No.1/2007 before the Tribunal on 31.05.2007 praying to restrain the State of

19
Karnataka from execution or commissioning any new check dams or Irrigation works, L.I. Schemes and de-
silting of M.I. tanks.

The CWDT which met on 10.07.2007 accepting the petitions of all the party States and that of Central
Government ordered them to be listed for orders after disposal of the appeals by the Supreme Court. Further it
also disposed off the CMP No.1/2007 filed by Tamil Nadu.

Before the Supreme Court of India:

Aggrieved by the final orders of the Cauvery Water Disputes Tribunal dated 05.02.2007, Karnataka
filed Civil Appeal No. 2453/2007 (Vol. I to III – pages 1 to 1038) against the final orders of the Tribunal under
Article 136 of Constitution on 23.04.2007. Thereafter additional documents (Vol. IV to XXV – pages 1039 to
6759) have been filed between 04.05.2009 and 11.02.2009 in support of issues that are to be argued before the
Supreme Court.
Further, conferences in this respect were held both in Bangalore and ta New Delhi frequently
throughout the year with Senior Counsel Sri. F.S .Nariman and Sri. Anil.B.Divan in preparation for the ensuing
arguments.

I. A No. 3 of 2008 filed by Tamil Nadu in Civil Appeal No. 2453/2007:


Tamil Nadu filed the above I.A in Supreme Court regarding taking up of Shivanasamudram Hydro Electric
Project by the State of Karnataka. The State of Tamil Nadu insisted that the four Hydro Electric Schemes viz.,
Shivanasamudram, Mekedatu, Rasimalai and Hogenekal (the first two lie entirely in Karnataka area, whereas the
other two lie in the common reach between Karnataka and Tamil Nadu) be taken up as a joint venture by the
Government of India and that Shivanasamudram and Mekedatu should not be individually taken up by the
State of Karnataka.
The replies to the above I.A have been prepared and approved by the Government. The same is to be
finalized by the Senior Counsel Sri. F.S. Nariman and has to be filed before the Supreme Court.

Before the Cauvery River Authority:


After the Final Award of the CWDT on 05.02.2007 Karnataka is of the opinion that neither the Interim
Order nor the final order is under operation as the Tribunal in its interim order had stated that the interim order
will be in effect till the final order is pronounced but the final order has not yet been notified by the Government
of India, whereas Tamil Nadu is of the contention that the interim order dated: 25.06.1991 still survives.

The Government of India had indicated that till the final Order is notified, the interim order holds sway.
Karnataka has differed on this and has urged that the matter can only be resolved by CRA.

Under such circumstances, whether the regime of flows is to be regulated as per Interim order or as per
final order remained unresolved. As such during the year 2008-09 the regime of flows to be regulated to Tamil
Nadu under distress condition was requested for from the CRA. In this respect several letters were addressed to
Government of India to convene the CRA meeting at the earliest. But till to date it is not been convened.

20
During the year the gauging at Biligundlu have shown that a quantity of 199.96 tmc has flown to Tamil
Nadu to end of 3/2009. The computations of Tamil Nadu at Mettur indicate the flow reaching Mettur as 195.55
tmc during the corresponding period.

 KRISHNA - GODAVARI UNIT

The Krishna Godavari Unit under the jurisdiction of the Water Resources Development Organisation, is
working on the following Inter-State Water Disputes:
1. Krishna Water Dispute
2. Mahadayi Diversion Scheme
3. Godavari Water Dispute
4. Palar and Pennar Basin
5. Inter-linking of rivers

KRISHNA WATER DISPUTES:


As per Bachawat Award under Scheme „A‟, the allocations are as follows:
Maharashtra 560 TMC
Karnataka 700 TMC
Andhra Pradesh 800 TMC

The Bachawat Tribunal had also devised the Scheme 'B' to allocate surplus waters available in the Krishna Basin.
As per this Scheme „B‟ the basin States were earmarked the shares, in the surplus waters available above 2130
tmc, as per the following percentages:
Maharashtra 25%
Karnataka 50%
Andhra Pradesh 25%

 Karnataka filed a letter of Complaint for constituting a Water Dispute Tribunal in the matter of sharing
of surplus water of Krishna River Basin on 26.09.2002 before the Government of India. Considering
the complaints of the States, the Central Government issued a Notificat ion dated 02.04.2004
constituting the Krishna Water Disputes Tribunal Shri Justice Brijesh Kumar as Chairman with Shri
Justice S.P.Srivastava and Shri Justice D.K.Seth as Members. A Technical Committee and legal team
comprising of 11 Advocates including the Advocate General under the leadership of Sri F.S.Nariman
and Sri. Anil B. Divan, Senior Counsel to has been constituted by the Government.

MAHADAYI WATER DISPUTES: (DIVERSION SCHEME)


 Malaprabha dam was constructed during 1972 across river Malaprabha at Naviluteertha, Belgaum
district. The utilisation contemplated was 44 tmc and it has a gross and live capacity of 37.7 tmc.

 A draft counter statement opposing the request of Goa, in O.S.No.4/2006, to transfer the Mahadayi
Water Dispute to Tribunal, has been prepared by the Advocates and has been approved by the
Government. The same will be filed before.the Supreme Court shortly.
 To meet the expenditure towards the above water disputes works a revised estimate amounting to Rs.
700.00 Lakh, for the year 2007-08, has been administration approvied by the Government. An
expenditure of Rs.630.00 lakhs has been incurred upto end of March, 2008. The main object of the

21
struggle is to mitigate the drought in the North Karnataka region in Krishna Basin by providing
good quality drinking water supply and [water for Irrigation.

GODAVARI WATER DISPUTE:


As per the final decision of Godavari Water Disputes Tribunal, 22.37 tmc of water is available in the
Godavari Basin to the State of Karnataka. Further, 23 tmc of additional water can be utilized by the State of
Karnataka in Krishna basin from the date of approval to polavaram Diversion Scheme is accorded by
Government of India. Government

 HYDROLOGY UNIT:

To assess Water Resources in Karnataka State in a scientific manner, the studies of flow data at various
points in different river basins and rainfall data are most essential. As such, the Government of Karnataka has
established a separate Hydrology Unit under Water Resources Development Organisation, with the
responsibility to collect data from various gauging stations spread all over the State for analyzing and validation
of Hydrometric and Hydrometeorological data.

The following Meteorological stations are working under the Jurisdiction of WRDO:
A. Hydrological Stations:

1. Current Meter Gauging Stations - 42


2. Stage Discharge Stations - 12
3. Silt and Sedimentation observations stations - 31
B. Hydrometeorological Stations:
1. Fully Climatic Stations - 86
2. Autographic Rain gauge Stations - 165
3. Standard Rain gauge Stations - 758

The data obtained from these Hydrological and Hydrometeorological stations are scrutinized, analysed
and processed. The data of Rain gauge Stations maintained by Water Resources Development Organisation are
published by the Department of Economics and Statistics after obtaining the data from the concerned Tahasildar
office‟s of the respective Taluks. The monthly statement of daily inflow, outflow and utilization of water from
the major and medium reservoirs are being received from respective Project Authorities. The yield studies are
being carried out for the irrigation, drinking and power projects as and when proposed by the planning unit.
 The Surface Water samples from various rivers are collected at 12 locations and analysed for 6
parameters namely colour, odour, temperature, electrical conductivity, dissolved oxygen and PH
value, at Level – I labs.

 Further, analysis of surface water for chemical parameters (27 Nos) conducted once in 2 months
done at Level – II labs established at KERS and at Munirabad for 10 different locations from the
rivers of south and 7 different locations from the rivers of North Karnataka. The data are being
received at Surface water data centre, Bangalore.

ADDITIONAL WORK TAKEN: The National committee on Dam Safety has recommended to carry
out the Hydrological review of design flood of all the large dams in the state as per the guidelines issued by

22
CWC. The Hydrological review involves calculation of revised design flood and comparing the same with the
value adopted while designing the flood. This task of Hydrological review has been entrusted hydro unit of
WRDO. There are 236 dams identified for carrying on the Hydrology review.

Hydrology Project – Phase – I:


Government of India took up the Hydrology Project – I under the World Bank Aid, which envisaged
the setting up of reliable and well designed network in the country for the collection of Hydrological and
Hydrometeorological datas, both for Surface as well as Ground Water for quantity and quality. The data from
the above network of stations is being collected, validated and stored in the data centre of Hydrology Unit.

The project started on 10.12.1996 and closed on 31.12.2003.

During the current financial year of 2006-07, a budget grants of Rs.3.50 Crores has been allocated for
maintenance of Stations, Laboratory, Vehicles, Computers etc., established under the World Bank assisted
Hydrology Project-I and for payment of salaries of Staff created under this project. A total of Rs.2.69 Crores
expenditure is during 2006-07.

Hydrology Project-I was envisaged for setting up of data collection network only.

Hydrology Project Phase – II:

The Central Government has included the State of Karnataka for participating in the Hydrology Project
Phase – II. It has allocated a provision of Rs. 29.19 crores for this purpose. This has again been divided into
two components.

Surface Water Component - Rs11.54 Crores


Ground Water Component - Rs. 17.65 Crores
Total: - Rs. 29.19 Crores

A review of the various activities, which are proposed to be taken up under Hydrology Project – II
indicates that a majority of the expenditure is concentrated for development of software packages and trainings.

The Government in their order No.WRD/8/Rajyo/2004, Bangalore Dated 24.12.2004 has accorded
approval to the implementation of the project. The legal agreement and the project agreement for the Hydrology
Project – II has been signed with the Bank on 10.01.2006. The effectiveness date of the project is from
05.04.2006 and the project is to be completed by 30.06.2012. The project t is currently under implementation.

 GEOMATICS CENTER
Projects taken up for Investigation by adopting the latest techniques through Geomatics Centre are as
follows.
 Survey and Investigations of potentials flows from West to East and North Eastern part
of Karnataka, the work is entrusted to N.R.S.A., Hyderabad. Till date 13 thematic maps of 6 themes
each have been supplied. So far, the Executive Engineer, I.I.Division, Mysore have paid Rs.257.84
Lakhs to N.R.S.A., Hyderabad.

23
 For implementation of State Water Policy Water Resources Data Center has to be established.

 Geomatics lab has been equipped with 3 workstations and one plotter along with one P.C. with Auto
CAD, GIS and ERDAS software for water resources planning and investigations. Further the center has
been strengthened by procuring One A0 scanner. During the year 2008-09 two more Arc GIS 9.3
version software with 3D and spatial analyst extension have been procured for the Geomatics Center
along with upgrading of existing Arc GIS 9.0 to 9.3 version. Two more Hp work stations and One Hp
server has been procured for the center‟s use.

 Different maps based on the available data in K.G., Cauvery and Hydrology Units and maps for Inter
State Tribunal have been generated and given for their use from time to time
 Maps showing position of Hydrometerlogical Stations in Karnataka is under preparation.
 Assisting Hydrology Unit of Central Office in preparation of Catchment area delineation indicating
the influencing rain gauges for all dams and M.I. Tanks under Dam Safety preparedness in Karnataka
State.
 Web Enabled GIS based water Resources Information System pertaining to Karnataka State is to be
generated on 1:50,000 scale for 29 layers of information and furnished to the CWC as per the Central
Government request. Relevant date from all the Major and Medium Minor Irrigation Projects is being
asked by the concerned head of the zones of different projects.

 Generation of Action plan for Dam safety/Technical preparedness for large /medium dams of the state
using the GIS technology is in progress.

INDEX

24
7. CENTRAL MECHANICAL ORGANISATION

Central Mechanical organization (CMO) has one circle office, three divisions, 14 sub-divisions and 36
Sections/Work shops under its jurisdiction.

I. The main duties and functions of the organization are briefly as follows:
a) Optimum utilization of Machinery/Equipment available in the department.
b) Stream lining the purchase of spare parts of Machinery/Equipments.
c) Centralization and Stream lining of purchase of new Machinery/Equipments.
d) Reduction in the inventory of the spare parts held in stock of various divisions.
e) Plugging the leakages of revenue.
f) Disposal of surplus and unserviceable machinery.
g) Inspection of sick machinery in the Public Works and Water Resources Department and scrutiny/sanction of
repair estimates.
h) Review of efficiency and performance of Machinery/Equipments.
i) Calculation of hire charges of machinery/equipment and recommendation to the Government for the
adoption of hire charges from time to time.
j) Rehabilitation of surplus Vehicles/ Machinery/Equipments.

 PROGRESS ACHIEVED BY C.M.O DURING 2008-09:

In order to ensure optimum utilization of Machinery/Equipments, available in Public works and Water
Resources Department, the monthly returns of machinery of divisions are being obtained and reviewed regularly
for its various performance aspects such as

1) Fuel usage
2) Oil usage
3) Km run with reference to standards fixed.
4) Idleness, surplus ness and rehabilitation.
5) Sick vehicles/equipments identification and its speedy repairs
6) Disposal of unserviceable machinery is reviewed and follow up action ensured until their disposal.

Purchase of spare parts required for repairs to machinery is being streamlined and only such spares, which
are absolutely required and not available in the stock, are procured. The Chief Engineer, CMO is the Member-
Secretary of the Purchase Committee. Any new purchase of machinery is being screened thoroughly and
recommended to Government for approval.

CMO is making efforts in utilisation of the available spare parts in stock of several Divisions of PWD and
WRD thereby causing reduction in the inventory.
Every effort is being made by the CMO to check and plug the loss of revenue to the Government by the
utilisation and hiring of machinery to contractors, thus bringing revenue to Government.

25
Central Mechanical Organisation is also inspecting vehicles / equipment pertaining to Board, Corporations
and Central Government after levying inspection fees and remitting to the same to the Government Treasury.

DISPOSAL OF SURPLUS AND UNSERVICEABLE MACHINERY

No.of No. of vehicle/ Amount of revenue


Sl. Balance equipment/
Vehicle / equipment Equipment/ through disposal
No. machinery
declared unserviceable Machinery disposed off (Rs. In Lakhs)

(a) Water Resources Department:


75
1 245 174 6.83 (Disposal is under various
stages)
(b) Public work Department:
146
1 964 0 57.39 (Disposal is under various
stages)

Surplus Machinery Declared and their Rehabilitation

Sl.
Nigam / Zone No. Remarks
No.
1 WRDO 5
2 Hemavathy Project Zone 06
3 PWD 11 Includes 8 Jeeps,24
4 Other department 06 Cars 3 Maruti vans
5 ZP 01 &1 Tipper
6 ISZ 02
7 M.I (N) 05
TOTAL 36

Disposal of unserviceable machinery in Water Resources & Public Works Department, which
have been recommended for scrap during routine course of inspection:

Sl.
Description No. Remarks
No.
Unserviceable machinery identified for
1 159
disposal during 2008-09 Rs. 1,24,48,583.00
Revenue Realized
2 Disposed during 2008-09 155

26
ACHIEVEMENT OF CENTRAL MECHANICAL ORGANISATION DURING 2008-09

Sl. Achievements
Subject
No (Numbers)
1 Repair of Machinery/Equipments (Major and Minor)
a) Opening Balance (01.04.2008) 252
b) Receipts 3398
c) Total 3650
d) Repaired & dispatched 71(includes major repairs) 3394
e) Closing balance 256
2 Inspection
a) Total General Inspection 236
b) Recommended for repair 77
c) Recommended for discard 159
3 Repairs Estimate
a) Initial Estimates ---
b) Estimates Inspected and granted 167
c) Amount of Inspected estimates Rs. 212.09 lakhs
d) Number of reports given by inspecting the estimates 24
e) Total amount of estimates after inspecting the reports Rs.17.20 lakhs
f) Amount of Granted Estimates 143
g) Granted amount of estimates Rs. 194.89 lakhs
4 Spare parts utilization
a) Cost of Identified Spare parts Rs. 30.96 lakhs
b) Cost of spare parts utilized on works Rs. 1.49 lakhs
c) Balance Rs. 29.47 lakhs

INDEX

27
8. KARNATAKA ENGINEERING RESEARCH STATION

Karnataka Engineering Research Station was started during 1944 as a small Research Unit. The
Research Station, which forms a wing of the State Water Resources Department, had a phenomenal growth and
today it is one of the oldest Research Organisations of its kind in the country. The main objectives of the
Research Station are to find solutions to various problems encountered by the field Engineers in Civil
engineering discipline. The Research Station has solved many intricate problems posed by Public Works
Department, Water Resources Department, other Civil Engineering Departments, other agencies etc. The
Research Station has well equipped laboratories supported with good Computer facilities and Library.

The Director of the rank of Chief Engineer heads the Research Station. He is assisted by the Joint
Director, who is also the Principal of Engineering Staff College, which is a wing of K.E.R.S.

The activities of the Research Station are grouped under 4 divisions as under.
 Hydraulics Division
 Technical Services Division
 Soil Mechanics & Foundation Engineering Division
 Coastal Engineering Division
Chief Research Officer of the rank of Executive Engineer heads each Division. There are 4 Chief
Research Officers (Executive Engineer), 19 Research Officers (Assistant Executive Engineer), 62 Assistant
Research Officers (Assistant Engineer), and 19 Junior Research Officers (Junior Engineer). Of these sanctioned
posts, 04 Chief Research Officers, 17 Research Officers, 45 Assistant Research Officers and 12 Junior Research
Officers are working at present.

 HYDRAULICS DIVISION
Model studies of various components of Irrigation & Power Projects like spillway and energy dissipating
arrangements, Assessment of carrying capacity of canal system by backwater computation, Gauging of canals,
calibration of current meters, Capacity Evaluation of Reservoir by conventional Hydrographic survey as well as
remote sensing techniques are the studies entrusted to this division.

 TECHNICAL SERVICES DIVISION

This division is entrusted with the work of conducting, non-destructive tests on cement, concrete, Mix
design, steel, sand coarse aggregate etc. Tests on water samples, cement mortar and cement concrete samples
for chemical analysis, collection of daily Rainfall and Hydrometerological data, maintenance of buildings and
quarters of KERS, maintenance of library are other works entrusted to this division.

28
 SOIL MECHANICS & FOUNDATION DIVISION
This division deals with problems related to foundations, suitability of soils to embankments, foundations of
bridges and buildings and that related to MI tanks. This division also deals with problems related to rocks & its
properties, roads etc.

 COASTAL ENGINEERING DIVISION


The main objective of this division is to investigate the causes of coastal erosion along coastal line of
Karnataka, to collect field data, to suggest remedial measures to contain coastal erosion and to conduct model
studies if necessary. Also pre-monsoon and Post-monsoon monitoring of Sea Walls, monthly monitoring of Sea
Walls being constructed by port authorities are being done by this Division. In addition, this division is also
conducting silt and sedimentation survey of Kabini reservoir.

Through the above Divisions, the Research Station has been playing a key role in solving many
Engineering problems in the field of Hydraulics, Concrete, Testing of building materials- concrete, Soils, Rock,
problems connected with roads, Sea Erosion etc.

DAM SAFETY CELL


A Dam Safety Cell is working in the Research Station under the direct control of the Director, K.E.R.S. The
Cell is headed by Assistant Executive Engineer supported by technical staff and deals with the safety aspects of
Dams as per the guidelines of Central Water Commission.

A proposal for creation of Dam Safety Organisation (DSO) headed by a Superintending Engineer is under
consideration by the Government.

PROGRESS ACHIEVED BY KERS DURING 2008-09:

During the year 2008-09, up to end of March 2009, 85 Nos. of studies covering Hydraulic studies,
Rating of current meters (40 Nos), Gauging of canals, Capacity evaluation of reservoirs, Testing of Building
Materials, Soils, Water quality testing, etc., referred by different agencies have been completed and reports sent
to concerned authorities and 26 studies are under progress. Major studies undertaken at the Research Station
during the current year are as follows.
1. As per the request of Tungabhadra Board and directions from Government, the Hydrographic survey of
T.B. Reservoir was completed during the current year. The draft report has been prepared which will be
finalized in consultation with Andhra Pradesh Engineering Research Laboratory (APERL) authorities.
2. Gate operation studies of Yagachi Reservoir have been completed and report submitted to concerned
project authorities.
3. Gate operation studies of Uduthorehalla Reservoir project has been completed and report submitted to
concerned project authorities.
4. Current meter gauging was conducted at chainage 102.83 kms of Hemavathi Left bank canal and report
sent to concerned project authorities.

29
5. The test result data collected at the level-II Water quality Lab at K.R.Sagar from year 2001-2006 in
respect of Cauvery River at Krisharajasagara dam site was analysed and a report on analysis of water
quality has been sent to concerned authorities.
6. The study report on analysis of regionalization of Cauvery river basin in Karnataka by flood frequency
analysis was prepared and sent to various institutions for their expert comments.
7. Report on sedimentation of Kabini Reservoir using inflow and outflow method has been prepared. As
it is proposed to conduct the Hydrographic survey of Kabini Reservoir using Hitech Boat & IBS
equipments, a proposal has been submitted to Government to shift the Head Quarter of Silt and
sedimentation sub division Kabini from Kabini colony to Krishnarajasagara.

Also the Coastal Engineering Division has been conducting monthly monitoring sea walls being
constructed by port authorities and submitting monthly reports to the concerned. Also the monitoring of
emergency sea protection works carried out under D C grants are also being undertaken by this division at
Dakshina Kannada and Udupi District.
Under Hydrology project, two Level II Water Quality laboratories have been setup at K.R.Sagara &
Munirabad. The laboratory is made functional by using the services of regular Assistant Engineers and Water
Quality studies have been commenced during the current year. In the lab at K.R.Sagara, studies have been
completed on the 35 samples received. In the lab at Munirabad 11 studies have been completed on the stipulated
27 parameters.

Important events during the year:

During 2008-09. tests on 130 samples have been completed and reports sent to concerned authorities
and 09 studies are under progress/Reports to be sent

1. The Karnataka Engineering Research station has entered


into and MoU with Administrative Training Institute
(ATI) Mysore as a Third party agency for conducting the
quality control tests on the materials used for
development works taken up under the grants allotted
under 12th finance commission.

2. Similarly proposals have been initiated by KERS to


utilize the services of Research Institute as a Third party
agency for quality control of works being undertaken by
various agencies viz Mysore University, Mysore city
corporation, Karnataka police housing corporation,
Karnataka Health system development improvement
project, Bangalore etc.

30
3. The KERS has been enrolled as a life member of the
prestigious International commission on Large Dams,
India (INCOLD) during the current year.

4. A training workshop for Policemen, Police officers(civil),


Police officers(armed), Engineers and Technical staff on
„Water Resources Infrastructure Protection‟ was
conducted at K.E.R.S., K.R.Sagara from Date:05.02.2009
to 07.02.2009 organized jointly by vigilance wing of
Water Resources Department, CNNL and KERS.,
K.R.Sagara.

5. One day training programme on the tests to be conducted


on the road construction materials and test to be
conducted during the construction of the road was
conducted at the Research Station for the Engineers of
Pradana Manthri Gram Sadak Yojana (PMGSY).

6. As per the request of Department of Water Shed


development, one day laboratory training was conducted
at the KERS for the Officers of Mysore Division on 10-
02-2009.

7. As per the request of Department of Water Shed


development, one day laboratory training was conducted
at the KERS for the Officers of Mysore Division on 06-
03-2009.

Strengthening of Research Station:

A Grant of Rs. 250.00 lakhs has been released for the year 2008-09 under the plan Head in connection
with strengthening of the Research Station.
Action was taken by KERS to implement the programme approved by Government in respect of the
above.
Accordingly necessary equipments like Hand held GPS, Core drilling Machine with diamond drill bits,
Digital camera, 1000 KN UTM, 2000 KN capacity digital compression testing machine, Rebar locator, Spilt air
conditioner, Universal triaxial testing machine, Total station equipment etc., have been procured. Also solar
lamps have been installed in view of safety and solar heater has been installed at Engineering Staff College
hostel.
Also the following civil works have been undertaken.
1. Renovation of existing open shed into seminar hall at Brindavan area of KERS.

2. Renovation of existing office building of Hydraulics Division in Brindavan area of KERS.

3. Construction of additional Rating tank in Brindavan area for carry out rating of current meters.

4. Providing Rain water harvesting to Main Building of KERS.

31
5. Renovation of existing hostel building of KERS.

The balance works/procurement of equipments yet to be commenced as per the approved


programme will be taken up during 2009-10 as spill over works and completed.
Since the objective of K.E.R.S. is to find solution to various incidental Civil Engineering
problems referred by Government, Quasi Government and other agencies etc., accordingly the same are
being attended to as and when refer by the said Departments/ agencies and will also be continued in future.

Activities:-

The Engineering Staff College conducts mainly three types of training Courses.
(i) Orientation course for newly appointed Asst. Executive Engineers/Asst. Engineers/Junior
Engineers (Duration - 6 weeks for Asst. Executive Engineers and 4 weeks for Asst. Engineers
and Junior Engineers)

(ii) Refresher courses for in - service Engineers and others in different subjects (Duration – 5 to 6
days). On special circumstances these courses will be extended upto 10 days.

(iii) Short term courses under Continuing Education Programme (C.E.P) (Duration - 5 days).

Besides, Basic Computer Course of 12 days duration are also being conducted by the College for the
benefit of Engineers & other staff working in the Department.

PROGRESS ACHIEVED BY ENGINEERING STAFF COLLEGE DURING 2008-09:

The details of training Programmes conducted during 2008-09 are given below.
No. of No. of No. of
Sl.
Category of training programme courses courses persons
No.
proposed conducted trained
1 Institutional Courses 26 11 596
2 C.E.P Courses 35 35 556
Total 61 46 1152

During 2008-09, upto end of March 2008, 46 different training Programmes have been conducted and
1152 officers/Staff has been trained.

In all, since inception of Staff College up to end of March 2009, the college has successfully conducted
1188 training programmes and has trained 24261 Officers/Staff of the Government Departments.

INDEX

32
9. WATER AND LAND MANAGEMENT INSTITUTE (WALMI)

Introduction:
To maximize returns from investments made in irrigation projects in the State, it is necessary to manage
water and land in a systematic and scientific way. This requires capacity building of Government Staff as well
Water Users. To meet these capacity building needs, Water and Land Management Institute (WALMI) started
functioning at Dharwad on 12-5-1986 and was later registered as a Society under the Karnataka Societies
Registration Act, 1960 on 16.06.1986. WALMI: imparts training; renders technical assistance, advises
Government on legal, policy, organizational and procedural changes; organizes demonstrations in collaboration
with other organizations; conducts special studies and brings out publications.

Training:
WALMIs training activities focused on the training required for implementation of the State Water
Policy and the Irrigation Sector Reforms. Special emphasis was laid on training on Participatory Irrigation
Management, Water Management and Land Development. Office bearers of Water Users Cooperative Societies
throughout the State as well as some farmers were also trained by WALMI. As against a target of 1200 persons
to be trained, 1806 persons were trained during 2008-09.

Technical Assistance:
WALMI rendered technical assistance to the Water Resources Department and organizations coming
under the Department on implementation of State Water Policy, Participatory Irrigation Management and
necessary legal and policy changes.

Demonstrations in Collaboration with the University of Agricultural Sciences, Dharwad:


Demonstrations pertaining to irrigation methods for different crops- Cotton, Soyabean, Paddy,
Sunflower, Wheat, Maize, Groundnut, Guava, Mango, Sapota and vegetable crops were laid. Water saving
technolgies like drip, sprinkler and Raingun were demonstrated in the WALMI Farm to support training
activities.

Financial Progress:
During the year, WALMI received Grant-in-aid of Rs. 27.66 lakhs under 2705-00-800-1-03

Command Area Development. Total expenditure of Rs. 106.17 lakhs was incurred during the year.

INDEX

33
PROJECTS UNDER

KRISHNA BHAGYA JALA NIGAM


LIMITED

34
10.1 UPPER KRISHNA PROJECT
(A) BRIEF DESCRIPTION:

In order to speed up the implementation of the Upper Krishna Project (UKP) in the State of Karnataka,
by mobilising resources from the capital markets, KBJNL was incorporated on 19 th August 1994 under the
Companies Act, 1956 as a Company, wholly owned by the Government of Karnataka for planning,
investigation, estimation, execution, operation and maintenance of all irrigation projects coming under the UKP.
The Company is funding the rehabilitation and resettlement of the people affected by the Project. The company
is authorised to let-out water and recover revenues from individuals, groups of farmers including Water Users
Co-operative Societies, towns, city municipalities and industries.

(B) ADMINISTRATIVELY APPROVED COST AND THE YEAR OF APPROVAL ALONG WITH
REVISED COST DETAILS:

(a) Stage-1 work of UKP has been approved by Planning commission vide letter No.2 (10) /88-
I&CAD/ dated 24.09.90 for Rs. 1214.97 Crores. The revised project cost approved by the
Nigam‟s Board is Rs.6003.19 Crores as on 30th September-2005.

(b) Stage-II work of UKP has been approved by Planning commission vide letter no: 2 (10) /99-
WR/ dated 13.12.2000 for Rs. 2358.86 Crores. The revised project cost approved by the
Nigam‟s Board is Rs.3476.40 Crores as on 30th September-2005.The revised updated cost
submitted to CWC for Rs.3618.96 crores includes escalations.

(C) EXPENDITURE INCURRED / POTENTIAL CREATED ON THE PROJECT :

So far a sum of Rs.10545.00 Crores has been spent on the project upto March 2009 and an amount of
Rs. 4869.06 Crores is spent towards payment of interest to bond holders / term Loan. Out of contemplated 6.22
lakh Ha. of command area under UKP potential of 5.99 lakh Ha. has been created upto March 2009.

(D) BARRAGES ACROSS RIVER BHIMA , KRISHNA & MANJRA RIVER:

Krishna Bhagya Jala Nigam Limited is implementing the following barrages across River Bhima,
Krishna (Krishna basin) and across River Manjra (Godavari basin).

(a) Across River Bhima (Krishna Basin)

Sl.
Barrage Status of work
No.
1 Ghattarga Barrage Completed
2 Kallur „B‟ Barrage Completed
3 Yadgir Barrage Completed
4 Joladagi - Gudur Barrage Completed
Civil work of barrage almost completed.
Fabrication and erection of 37 vertical gates is in
Modified Sonthi Barrage LI progress. Also, construction of head work including
5
Scheme intake channel, providing pumping machinery, sub-
station, raising main, etc. awarded on turnkey basis
is in progress.

(b) Across River Krishna (Krishna Basin)

Sl.
Barrage Status of work
No.
Civil work of barrage completed. Fabrication and
1. Gugal Barrage
erection of 70 vertical gate work is in progress.

35
(c) Across River Manjra (Godavari Basin)

Sl.
Barrage Status of work
No.
1. Jirgihal Barrage Construction of four series of barrages taken up across river
2. Manikeshwar Barrage Manjra in Bidar district of Godavari basin to utilize allocated
4.80 TMC.
3. Halhalli Barrage
The civil works of all four barrages and works of providing
4. Chandapur Barrage
automatic tilting Godbole gates are under progress.

KBJNL, DAM ZONE, ALMATTI


Dam Zone Almatti was established on 30.01.1977. One Circle Office, Six Division offices with 20 Sub
divisions, One Senior Health Office (Class-I) with its 4 Anti-Malaria Units and Deputy Conservation of Forest
with its 3 Sub-Divisions are working under this zone.

The works of Almatti Dam, Lift Irrigation Schemes of UKP such as ALBC, ARBC and Mulwad LIS,
other LI Schemes such as Marol, Timmapur, Teggi-Siddapur, Sonna and Rolli-Mannikeri LI Schemes, filling up
of MI Tanks in Bijapur & Bagalkot and landscape and garden development works at downstream of Almatti
Dam are coming under the jurisdiction of this Zone. Status of projects under KBJNL Dam Zone is as under:

1) Almatti Dam:

The work is already completed and Gates are also erected. The water is being stored upto FRL 519.60
m and being utilized for irrigation and generation of electric power.

2) Almatti Left Bank Canal :

Head work already commissioned. The total length of Main Canal is 85.00 Kms out of which 67.00
Kms is completed. Further the works from KM 67.00 to 85.00 is also completed except the reach in Km 72. The
distributaries 1 to 27 are completed and the works of distributary No.28 to 40 are also almost completed.

An area of 18,784 ha. is notified for for Rabi 2008-09 and water has been let out for irrigation.

3) Almatti Right Bank Canal :

Head work already commissioned. The Main Canal of 67.50 Km is completed including Distributary
No.1 to 24. Out of 9,900 ha, area of 8,859 ha. is notified for Rabi 2008-09 and water has been let out for
irrigation.

About 6,200 Ha. of ARBC command beyond Malaprabha River is included in Marol Lift Irrigation
Scheme.

4) Mulwad Lift Irrigation Scheme:

The water will be lifted in two stages under this scheme. Two head works viz; Baluti and Hanumapur
head works were already commissioned. The lead off canal from Km 0.00 to 5.00 which leads water from 1 st
jackwell to 2nd jackwell completed.

East Canal is of total 17.40 Km length and is completed. Out of 6 No. distributaries on East Canal
Distry.No.1 to 5 are completed and Distry.No.6 is nearing completion. West Canal is of total 78.00 Km length
and is completed. All 43 Distributaries under West Canal are also completed except certain balance works
under Distry.No.7 & 11 which are in progress.

36
Out of contemplated 30,850 ha of command area, potential of 21,346 ha is already created and 16,280
ha is notified for Rabi 2008-09 and water has been let out for irrigation.

5) Ramthal (Marol) Lift Irrigation Scheme:

This LI Scheme is taken up on the foreshore of Narayanapur Reservoir. The Scheme contemplates
providing irrigation to 26,200 ha. of command area of Hunagund Taluk of Bagalkot District. Estimated cost of
this project is Rs.218.00 Crores.

Construction of 1st jackwell and its allied works is almost completed. Further the work of construction
of 1 Stage West Main Canal KM 0.00 to 8.00 awarded on package tender is in progress. Construction of 2nd
st

Jackwell including intake channel, providing pumping machinery, sub-station, raising main etc, on turn key
basis was awarded on turn key tender basis is under progress. Tenders for 1 st stage West Main Canal KM 8.00
21.00 and Disty.No.1, 2, 3, 5 & 6 are invited. Further, the survey investigation and preparation of estimates for
further canal network is under progress.

6) Thimmapur Lift Irrigation Scheme:


This LI Scheme takes off at KM 5.40 of main canal of ARBC. The Scheme contemplates providing
irrigation to 20,100 ha. of command area of Bagalkot Taluk.

The work of construction of Jackwell, providing pumping machinery, sub-station, raising main,
delivery chamber etc, entrusted on turn key tender basis is under progress. Tenders for Main Canal Km 0.00 to
10.00 from Delivery Chamber-1 are invited. Detailed survey and investigation of canal network is under
progress.

7) Teggi-Siddapur Lift Irrigation Scheme :


This Lift Irrigation Scheme is taken up on the foreshore of Almatti Reservoir, near Teggi village of
Bilgi Tq. to provide irrigation benefits to about 3,000 ha area of Bilgi Taluk.

For the construction of balance works of Jackwell (civil works) & for providing pumping machinery,
substation, rising main, delivery chamber etc, turn key tenders invited. Further, for the Main Canal from Km.
0.00 to 12.00, tenders in two packages are re-invited as the tenders invited earlier were cancelled.

8) Sonna and Rolli-Mannikeri Lift Irrigation Schemes:


These LI Schemes are taken up on the foreshore of Almatti Reservoir. Sonna and Rolli-Mannikeri LI
Schemes provide irrigation benefits to about 3,000 ha area in Bilgi Taluk.

For Sonna LI scheme construction of Jackwell, providing pumping machinery, sub-station, raising
main, delivery chamber etc, entrusted on turn key tender basis is under progress. For Rolli- Mannikeri LI
Scheme, work of construction of Jackwell, providing pumping machinery, sub-station, raising main, delivery
chamber etc, tenders on turn key basis re-invited as the agency to whom the work was awarded earlier has not
commenced the work and tender agreement rescinded duly forfeiting the EMD amount.

9) Landscape and Garden works on D/s of Almatti Reservoir:

Landscape Development of Almatti Dam environs have been taken up to create the avenues for
economic development of project area by attracting the tourist. A Committee is formed under the Chairmanship
of the Commissioner, R&R, Bagalkot to monitor and supervise the landscape and garden works.

The project has been phased out in multiple stages and development of 77 Acres of land along the left
bank on the D/s of Dam is taken under Phase-I. The works of providing illumination and commissioning of
musical fountains are under progress. In the later phase of landscape development works of providing water
theme parks, courts etc., are planned in about 220 Acres.

37
10) Filling up of M.I.Tanks of Bagalkot and Bijapur District :

The work of filling up of 16 MI tanks and 5 bandaras of Bijapur District and 7 MI tanks of Bagalkot
district, awarded on turnkey basis during Janauary 2009 and the work commenced. Period of completion of
work is 36 months.

11) SCP-TSP Works:

Under this programme, it is proposed to provide Sprinkler irrigation facilities to the SC/ST
beneficiaries coming under ALBC, ARBC and MLIS command area. Totally 22 works are taken up under the
scheme and out of which 21 No. of works are completed and commissioned. 1 work is under progress.

DETAILS OF IRRIGATION POTENTIAL:

( Area in Ha)
Created
Sl. upto Programm Prgoress Programme
Name of District Planned
No March e 2008-09 2008-09 for 2009-10
2008
1 2 3 4 5 6 7
Almatti Left Bank Canal (
1 20235 21406 728 484 244
KM 0 to 85)
Almatti Right Bank Canal
2 9900 9037 258 100 85
(KM to 67 KM)
Mulwad Lift Irrigation
3 30850 20970 1285 471 814
Scheme
TOTAL 60985 51413 2271 1055 1143

KBJNL, OPERATION & MAINTENANCE ZONE, NARAYANPUR :


Considering the vast area that is already notified and the place of development of irrigation in the
subsequent phases, the Government has accorded sanction for creation of separate Zone to look after Operation
and Maintenance activities of UKP vide G.O. No.ID/115/WBM/91 Dated: 14/10/1991. Owing to the
Government order, the office of the Chief Engineer, O&M Zone, UKP Narayanpur came into existence on
03.01.1992. This Zone is working under Krishna Bhagya Jala Nigam Limited with effect from 15.11.1995. One
Circle, four Divisions and Twelve Sub-Divisions are working under the control of Zone.

This Zone has the responsibility to monitor the water management for an irrigated area of 4.25 lakhs
hectares under Stage-I of UKP. As the project work is under progress, the irrigable area under this zone is
increasing year by year. This year an area of 98,964 ha. has been declared as notified are for irrigation during
Kharif and Rabi season respectively. The canal wise details of Notified area as under:

Sl.
Canal Kharif 2008-09 Rabi 2008-09
No
1 Narayanpur Left Bank Canal 27,961 27,961
2 Hunasagi Branch Canal 22,172 22,172
3 Rampur Lift Irrigation Scheme 19,271 19,271
4 Narayanpur Right Bank Canal 30,224 30,224
Total 99,269 99,269

The Maintenance of following irrigation camps in the project area also come within the preview of this
zone.

38
1) Narayanpur 2) Kodekal 3) Rajankollur 4) Kakkera 5) Hunasagi 6) Devapur
7) Devatkal 8) Mudunoor 9) Rodalabanda 10) Amarapur Camp

The Maintenance of 108.00 Km length of Major District road 247.32 Km of other roads, 16 VHF
wireless stations, etc., are the other works which are being looked into by this Zone.

Apart from Operation and Maintenance of canal network in NLBC from Km. 0.00 to 78.00, NRBC
Km. 0.00 to 82.00 & Rampur Lift Irrigation Scheme, this Zone is also looking after the following works:

1) Rajan-Kollur Lift Irrigation Scheme:

The Scheme takes off from the D/s of Rajan-kollur Tunnel at Km 40.06 of NLBC. The scheme
contemplates to provide irrigation for 1,295 ha of command area in Shorapur taluk. The construction of
head work including intake channel, providing pumping machinery, sub-station, rising main etc,
awarded on turnkey basis and also work of Distributary network awarded on tender basis are in
progress.

2) Bonal Lift Irrigation Scheme:

This scheme contemplates providing irrigation to about 2,500 ha of the suffering achcut under SBC
Distry.No.6 by lifting water on the D/s of Bonal Mini Hydel Scheme near Bonal tank of Surpur taluk.
The tender invited on turnkey basis is under process.

DETAILS OF IRRIGATION POTENTIAL


(Area in Ha.)
Progress of
Created upto Additional
Sl. Name of the Planned creation
March- creation during
No District potential in Ha during
08(Notified) 2008-09
2008-09
1 Bijapur 27 27 - -
2 Gulbarga 47196 50106 - -
3 Raichur 50325 49331 2061 535
TOTAL 97548 99464 2061 535

39
KBJNL, CANAL ZONE NO. 1, BHEEMARAYANAGUDI:

1. CONTEMPLATED IRRIGATION POTENTIAL:

The irrigable command areas contemplated under various canals of this Zone are as under:
Name of the Canal ICA envisaged
(i) Shahapur Branch Canal. : 1,22,120 Ha.
(ii) Mudbal Branch Canal. : 51,000 Ha.
(iii) Jewargi Branch Canal : 57,098 Ha.
(iv) Narayanapur Right Bank Canal : 53,997 Ha.
(KM 82.00 to 95.00 & Dy.No.15 to 18)
Total : 2,84,215 Ha.

The command areas of Shorapur, Shahapur and Jewargi Taluks of Gulbarga district and Deodurga
Taluks of Raichur district will be covered in the above mentioned canal networks.

2. PRESENT STATUS OF WORKS UPTO END OF MARCH 2009:

Shahapur Branch Canal and Mudbal Branch Canal works are completed and are in the Operation &
Maintenance stage.
Jewargi Branch Canal:

The works of this canal come under UKP Stage-I, Phase-III. The earth work of Jewargi Branch Canal
from 0.00 to 13.00 Km was first started during 1992-93, under famine works programme. But brisk activities of
the works on this canal started during the year 1995-96 with the formation of KBJNL.

All the works of Main Canal (Km0.00 to86.36) and Distrys. 1 to 18, including lining, are completed.
Works of only an aqueduct on Lateral-1 of Distry No.16 and some additional lateral works taken up on
Disty.No.12(A), 12(A1) are yet to be completed and are programmed for completion during 2009-10.

The irrigation potential created under the canal upto March 2009 since inception is 58224 Ha as
against the contemplated potential of 57,098 Ha. It was programmed to create additional potential of 1400 Ha
during 2008-09 and only potential of 488 Ha has been created during 2008-09 since some of the additional
works proposed could not be taken up due to the court cases. Out of the total created command area of 58224 ha
to the end of March-2009, 52,140 Ha. area is notified for Rabi 2008-09 and water letout for irrigation including
in the balance area wherever the basic infrastructure for irrigation potential has been created.

The cumulative financial progress achieved on the works of this canal since inception is Rs. 406.11
Crores to the end of 31-03-2009.

The balance works, (including FICs) will be completed during 2009-10.

Narayanapur Right Bank Canal:

The works of this canal were taken up under UKP Stage-II, with the Nigam funds, during the year
1995-96. The jurisdiction of NRBC from KM 82.00 to 95.00 and Dity.No.15 to 18 comes under this Zone. The
jurisdiction of NRBC from KM 0.00 to 82.00 and Disty.No.1 to 14 comes under the jurisdiction of O&M Zone,
Narayanapur.

All the works of Main Canal from Km 82.00 to 95.00 and Distry.No.15 to 18 are completed. Works of
only some additional laterals on D-15,16 & D-16 are being taken up and will be completed during 2009-10.

The total contemplated irrigation potential of 84,000 Ha has been already created on the canal. Out of
the total created command area of 84,000 ha to the end of March-2009, 75,736 Ha area is notified for Rabi 2008-
09 and water has been let out for irrigation including in the in the balance area wherever the basic infrastructure
for irrigation potential has been created.

40
The cumulative financial progress achieved on the works of this canal since inception is Rs.1058.30
Crores to the end of 31-03-2009.
All the balance works (including FICs) will be completed during 2009-10.
Bridge Cum Barrage Works:

The works of construction of one Bridge cum Barrage across River Krishna, three Barrages across
River Bhima, and four Barrages across River Manjra come under this Zone.
The work of construction of two Bridge cum Barrages (i.e. Yadgir & Joldadgi-Gudur Barrages) are
completed.

The civil portion of modified Sonthi Bridge cum Barrage across River Bhima (near village Sonthi) is
almost completed. The work of fabrication and erection of 37 vertical gates is in the advanced stage of progress.
Further, the Head work including electro-mechanical works of Sonthi LI Scheme awarded on turnkey basis is in
progress and programmed for completion by Decemebr 2009. Tenders for feeder canal KM 0.00 to 1.75 invited.

The work of construction of Bridge cum Barrage near Gugal village on River Krishna is also completed
to the extent of civil portion. However, the work of providing 70 vertical gates is under progress.

Also the works of construction four barrages across River Manjra of Godavari Basin in Bidar Dist.
including the works of providing Godbole gates are under progress. Chandapur & Manikeshwar Barrages are
programmed for completion during 2009-10.

Total expenditure incurred during 2007-08 on all the Barrage works coming under this Zone to the end
of March-2009 is Rs.10223.63 Lakhs as against the annual target of Rs.4070.00 Lakhs.

PROGRAMME AND PROGRESS DURING 2008-09:

The annual financial programme of this zone for the year 2008-09 was Rs. 123.56 Crores and the
programme of creation of irrigation potential was 4,888 Ha.

Against the programme, the financial progress achieved to the end of March-09 is Rs. 141.36 Cr and
an irrigation potential of 3,716 Ha has been created.

DETAILS OF IRRIGATION POTENTIAL


(Areas: In Ha)
Sl Name of the canal Planned Programme for Progress during
No 2008-09 2008-09
1 Shahapur Branch Canal 1,22,120 350 304
2 Mudbal Branch Canal 51,000 - -
3 Jewargi Branch Canal 57,098 1400 488
4 Narayanapur Branch Canal 53,997 3138 2924
Total 2,84,215 4888 3716
DETAILS OF FINANCIAL ESTIMATES
(Rs.in lakhs)

Budget Progress
Sl Actuals
Activity Estimate during
No 2007-08
2008-09 2008-09
1 Dam and appurtenant &
7757.51 7291.00 10239.59
Reh. Works
2 Canal: Branches/Dys/Lats. 3094.40 3015.84 1784.72
3 Roads. 235.82 - 9.92
4 Buildings. 162.06 125.00 165.73
5 Others. 1552.84 1924.16 1936.43
Total 12802.63 12356.00 14136.39

41
KBJNL, CANAL ZONE NO. 2, KEMBHAVI
The UKP Canal Zone No.2 Kembhavi is functioning with effect from 1.10.1986 vide G.O.No. PWD 60
PCO 86, Dated. 29.9.1986, for the construction of Indi Branch Canal and Mudbal Branch Canal. Subsequently,
the Mudbal Branch Canal works were transferred to the jurisdiction of UKP Canal Zone No.1
Bheemarayanagudi. Ayacut Road works were transferred to this Zone vide G.O.No. PWD 60 PCO 86, dated
15.6.1987.

At present this Zone is in-charge of the works of Indi Branch Canal from Km 0.00 to 172.00 including
Distry.No.1 to 46, Indi Lift Canal works from Km 0.00 to 147 and Ayacut Road within the Ayacut of Indi
Branch Canal. The works of IBC from Km 1 to 172, Disty.No.1 to 46 including laterals and FICs are already
completed and irrigation potential of 1,31,293 Ha. is created. Water letout for irrigation in the completed canal
network and is under operation maintenance.

The works of Head Regulator and intake canal of Indi Lift Scheme and Canal works from Km 0.225 to
97.30 are completed including Disty.No.1 to 40 except Disty.No.22 for which tenders for balance work invited
as the original tender agreement was rescinded at the risk and cost of contractor due to non completion of the
work. Irrigation potential of 41,813 Ha. created upto March 2009 and water has been out for irrigation in Indi
Lift Canal. Further, the works of Indi Lift Canal from Km 97.300 to 102.000 taken up on tender basis are under
progress. Tenders invited for Main Canal from KM 102.00 to 110.00 and Disty.No.41 and 42. Further, the
survey investigation and preparation of estimates for Indi Lift Canal from Km 110.000 to 147.000 are under
progress.

ORGANISATION :

This Zone is functioning with one circle ie., O&M Circle No.2 Rampur. Details of works taken up
under this Zone are as under.

INDI BRANCH CANAL :

The Indi Branch Canal takes off at Km 77.52 of Narayanpur Left Bank Canal, which is situated about 1
Km away from Kembhavi village of Shorapur taluka in Gulbarga District and traverses for a length of 172 Km
with a head discharge of 2,943 cusecs (83.49 cumecs) through the districts of Gulbarga and Bijapur irrigating an
area of 30,831 Ha. and 1,00,464 Ha. respectively (Total 1,31,295 Ha.)

The works of construction of Indi Branch Canal from Km 0.00 to 64.00 are tackled and completed
under Stage-I, Phase-II of UKP creating an irrigation potential of 60,721 Ha. The works of construction of Indi
Branch Canal from Km 65.00 to 172.00 are tackled and completed under Phase-III of Stage-I to create the
balance irrigation potential of 70,574 Ha. Up to March 2009 an area of 1,31,293 Ha Irrigation Potential has
been created.

On the works of Indi Branch Canal from KM 1 to 64, the expenditure incurred to end of March 2009 is
Rs.48582.23 lakhs.

The works of Indi Branch Canal from KM 65 to 172 and Distributaries 14 to 46 have been taken up on
tender as well as entrustment basis. The works are completed. The details of works taken up and completed are
as under:

(i) The works of IBC from KM 65 to 80, 101 to 113, 120, 122 to 125 and 151 to 172 are taken up
on tender basis and the works are completed.

(ii) The works of IBC from KM 81 to 88, 90 to 100, 114 to 119, 121, and 126 to 150 are taken up
on direct entrustment basis and the works are completed.

(iii) The works of Distributaries 14 to 24 and laterals coming under IBC from KM 65 to 120 are
also taken up on direct entrustment basis and the works are completed.

42
(iv) The works of distributaries 25, 26 to 34, 35 to 37, 38 to 45A and 46 are made into packages
and the works were taken up on tender basis. The works are completed.

(v) The works of providing CC lining to IBC from KM 65 to 172 also have been made into
packages and these works were taken up on tender basis. The works are completed.

INDI LIFT CANAL :


The works of Indi Lift Irrigation Scheme viz., Head Regulator, pump house, transmission line, sub-
station, ETC. and Intake Canal with structure taken up on tender basis are completed. Works of Indi lift canal
from Km 0.225 to 97.30 taken up on tender basis are almost completed. Works of Distry.No.1 to 40B & laterals
there under except Distry.No.22 of ILC are also completed. Tenders for balance works of Disty.No.22 invited.
Out of contemplated irrigation potential of 41,900 Ha. upto end of March 2009 irrigation potential of 41,813 Ha.
has been created. Notified area for Rabi 2008-09 is 32,470 Ha and water has been letout for irrigation under
Indi Lift Canal.

Further, Indi Lift Main Canal KM 97.30 to 102.00 taken up on tender basis are in progress. For Main
Canal from KM 102.00 to 110.00 & Distributary No.41 & 42 package tenders invited. Work of survey
investigation and preparation of estimates for further canal network entrusted on tender basis is in progress.

AYACUT ROADS:
Stage-I, Phase-I:

Construction of Ayacut Roads under Phase-I was of 611 kms length and all these works are completed.

Stage-I, Phase-II:
It was proposed to tackle 942 Kms of Ayacut Roads under Phase-II of Stage-I of UKP. Out of these
942 Kms, construction of 307 Kms of Ayacut Roads were handed over to CADA as per the orders of G.o.No.ID
95 Dt: 15-11-1995. Hence, 635 Kms of Ayacut Roads come under the jurisdiction of this zone. These works are
completed except the works of AR-04 Package. The contractor of AR-04 package has stopped the works for
non-finalization of workable rates. The roads coming under this package are included in the rehabilitation of
Ayacut Roads package and the works are in progress.

The amount spent on Ayacut Road works upto March 2009 is Rs. 2311.37 lakhs including
maintenance. (Excluding World Bank works which are completed).

Under this zone 10 Nos of Ayacut Roads in two packages have been taken under Rehabilitation &
Resettlement programme and these works are in progress.

BUILDINGS:

The buildings were constructed in various colonies of this zone for accommodation for staff and office.
Rs.1904.37 lakhs expenditure is incurred towards these works to end of March 2009. Two building packages
one at Rampur with bid cost of Rs.296.51 lakhs and another at Almel with bid cost of Rs.140.48 lakhs are
completed. The expenditure incurred upto end of December 2006 on the above works is as under:

1. Buildings at Rampur Package B2-01 Rs. 370.07 lakhs


2. Buildings at Almel Package B2-02 Rs. 182.76 lakhs

SCP-TSP WORKS :

Under this Zone totally 42 works on SCP-TSP is taken up during 2008-09 and all works are almost
completed.

43
DETAILS OF IRRIGATION POTENTIAL
(Areas: In Ha)
Name of the District, Programme
Potential created Progress up to
Bijapur and Total ICA during the year
to end of 3/08 March 2009
Gulbarga 2008-09
Indi Branch Canal. 131261 131295 -- --
Indi Lift Canal 41900 41813 2263 --

INDEX

44
10.2 BAGALKOT TOWN DEVELOPMENT AUTHORITY, BAGALKOT

1. SALIENT FEATURES OF BAGALKOT TOWN :

Bagalkot Town is historically famous from the glory and one of the largest town in the northern parts of
Karnataka which is situated on the right bank of Ghataprabha River at Long 75 o12‟ E and Lat 16 o12‟ N.

Bagalkot Town is getting submerged under back waters of Almatti reservoir when the Almatti Dam
height reaches RL.524.256 mtrs resulting submersion of 3/4 th of the town. Bagalkot Town Development
Authority has acquired 4,500 Acre of land for rehabilitation and resettlement of old Bagalkot town. During
2000-01 when water was stored at Almatti upto RL 519.60 mtrs, its backwater spread up to RL 520.10 mtrs. at
Bagalkot. The following are the submergence details at different elevations.

Sl. Height No. of Present acquisition of Structures.


Total Difference Population
No RL Mtrs Structures Authorized Un-authorized
1 2 3 4 5 6 7 8
1. 517.00 615 781 206 987 372 3760
2. 521.00 2337 2524 1208 3732 1395 18860
Total 2952 3305 1414 4719 1767 22620
3. 521 to 525 4225 2525 498 3023 1202 28376
4. 525 to 526 1872 -- -- 1872 -- 7021
5. 526 to 527 1482 -- -- 1482 -- 4238
Total 10531 15815 4686 62255
6. Above 527 22000 91596

Note: The figures at Sl.No.1 and 2 are as per 6(i) Notification. The figures indicated at Sl.No.3, 4 and 5 are as
per survey conducted in1986.

2. ORGAINSATION STRUCTURE:

For efficient and systematic implementation of R&R of Bagalkot Town, Govt. of Karnataka has
constituted BTDA under an Amendment to K.I.B Act functioning from 1984. BTDA is formed with one Chief
Engineer Office, 2 Divisions, 8 Sub Divisional Offices, Special Land Acquisition Office and Rehabilitation
Office.

3. AIBP PROGRAMME:

Estimated cost of Rehabilitation and Resettlement of Bagalkot Town

Sl.
Details of Component Rs.in lakh
No.
1 Structural compensation in old Bagalkot Town. 39539.06
2 Land Acquisition for new township and others etc. 2952.50
3 R&R Packages. 3000.00
4 Construction of Roads and parks etc., 6231.50
5 Providing Water Supply 4445.00
6 Providing U.G.D. 2200.00
7 Providing Electrification. 2000.00

45
8 Construction of Public Building 2200.00
9 Telecom facilities 400.00
10 Construction of Railway 1000.00
11 Maintenance of BTDA Colony and Navangar. 800.00
12 New Supply Machinery and Maintenance 250.00
13 Consultancy and training charges 90.00
14 Establishment 2591.94
Total:- 67700.00

An amount of Rs.342.70 crores towards AIBP works components has been included in the above
estimated cost. In addition to above an amount of Rs.360.49 crores is towards Special Package and the works are
being executed by BTDA. Thus, the total cost of the project works out to Rs.1037.49 crores.

The works taken up under Stage-I Phase-I & II are completed and the works under Phase-III are
nearing completion. Structures up to RL 521.00 contour have been evaluated and compensation paid. Plots for
the PDFs below RL 521.00 Mtr. Contour have been allotted in New township of Bagalkot. Most of the PDFs
constructed their houses in the allotted sites.

4. SPECIAL PACKAGE SCHEME:

Considering the problems due to backwater effect, Govt. has announced the special package of
Rs.638.00 Crores (Rs.500 Cr for Bagalkot town + Rs.138.00 Cr for R&R) Vide G.O.NO.RD1/124/REH/2002/
Dt.16.11.2002 to improve the existing conditions of Bagalkot Town. The details of special package are as
under.

Sl. Rs. in
Details of components
No. Crores
1 Structural compensation between RL.521.00 to 523.00, and development of 35
414.00
sectors of unit 2 of Navangar with all infrastructures facilities like roads.
2 Providing UGD for Non submergence of Bagalkot Town. 29.12
3 Providing Water Supply for non-submergence of Bagalkot Town. 11.70
4 Construction of link roads. 20.00
5 Development of parks in old town. 2.00
6 Construction of building under Ashraya Scheme for slum dwellers. 12.00
7 Construction of building for site less and below poverty line people. 5.00
8 Construction of 50 bedded hospital in old town. 2.00
9 Income and employment generating scheme. 4.18
Total 500.00

I. a) For Acquisition of structures between RL.521 to 523 mtrs, 6(i) Notification is published.

b) The fixing boundary stones and demarcation of various sizes of plots in 42 sectors of unit 2
are completed.

c) The estimate for infrastructures facilities like, main peripheral roads, UGD, Water supply
etc. for Unit-II of Navanagar etc. are to be prepared.

II. The U.G.D. Network in old Town for Non-submersible portion of Bagalkot is nearing
completion.

III. The work of providing water supply system including revamping of existing pipeline for non-
submersible portion of Bagalkot town is completed and is functioning.

IV. The road works in Old Bagalkot Town for 3 link roads, 5 main roads, 7 internal roads in slum
area of Bagalkot Town were taken up on tender basis and all are completed.

46
V. Development of 4 parks in old Bagalkot town are taken up. Out of which 3 garden works are
completed and one is nearing completion.

VI. Construction of 50 bedded hospitals building in old Bagalkot Town is under progress.

5) FINANCIAL PROGRESS ACHIEVED UPTO MARCH-2009 SINCE INCEPTION:

The cumulative expenditure incurred since inception (1983-84) upto March 2008 is Rs.484.39 Crores.
The expenditure incurred during 2008-09 upto end of March 2009 is Rs.142.15 Crores.

6) FINANCIAL PROGRESS ACHIVED UPTO 31-03-2009 SINCE 1996-97 FOR A.I.B.P WORKS.
The cumulative expenditure incurred on AIBP works since inception 1996-97 upto March 2008 is
Rs.16961.64 lakhs. The expenditure incurred during 2008-09 upto end of March 2009 is Rs.11465.00 lakhs.

7) DETAILS BUDGETARY PROVISIONS FOR 2008-09:


(Rs. In Lakhs)

Sl. No. Details of Component. Approved. Revised.


1 2 3 4
I Under A.I.B.P.
i) Compensation & Lok Adalat. 10661.04 9231.37
(ii) R & R Package. 10.50 5.00
(iii) Development Civil works.
(a) Roads. 2854.44 2926.29
(b) Water Supply. 394.82 423.39
© U.G.D. 191.45 191.45
(d) Electrification. 214.86 214.62
(e) Buildings. 201.76 201.70
(f) Gardens. 97.16 87.16
II Maintenance of Civil Works, & Vehicles. 100.00 327.48
III SCP & TSP Works. 70.12 70.00
Special Package works (Roads, Water Supply, UGD,
IV 374.00 2491.14
Electrification, and Buildings & Garden.
V Establishment charges. 425.00 425.00
Total: 15595.00 16595.00

47
8) DETAILS OF PROGRESS ACHEIVED DURING 2008-09 (UP TO 31-03-2009)

a) Compensation of Rs. 594.65 lakhs have been paid to 184 authorised structures coming below
521.00 Mtr. contour and Rs. 7893.51 lakhs have been paid towards compensation for 173
structures as per court award (Under Lok Adalat cases).

b) Totally 56 sectors for PDF's and 8 Sectors for Non-PDF's are developed in unit-1 at Navanagar.
During this year 4260 plots are allotted to P.D.F‟s., Non-PDFs & others. For 700 PDF‟s and 65
Non PDF‟s permission have been given to construct their houses.

c) Rs.1.32 lakhs have been paid as a house grants in the form of ex-gratia for 6 PDF‟s who are
coming below powerty line.

10) FINANCIAL PROGRESS:

Financial programme for the year 2008-09 is Rs.165.95 crores out of which an expenditure of Rs.
142.15 Crores has been made up to end of March-2009. The total expenditure incurred since inception is Rs.
598.15 Crores. The Details are as under:

(Rs. in Crores)
Sl.N Progress
Programme
o. (upto 1/09)
Under A.I.B.P. Works:
A i) Development works 4045 33.48
ii) Lok Adalat Compensation 92.36 81.18
B Revenue Head 3.28 3.69
C For Special Package 24.91 19.78
C SCP & TSP Works 0.70 0.67
D Establishment 4.25 3.35
Total 165.95 142.15

INDEX

48
PROJECTS UNDER

KARNATAKA NEERAVARI NIGAM


LIMITED

49
11. KARNATAKA NEERAVARI NIGAMA LIMITED
11.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION
(NORTH), BELGAUM

Irrigation (North) Zone was formed on 10.8.67 in pursuance of the Government order
No.PWD.114.PCO.67, dated: 24.7.1967 with a view to increase the tempo of construction work in the Irrigation
Projects as a result of increased provision of the plan allocation in the state.

Irrigation (North) Zone is incharge of the following projects.

On-going Schemes
1 Ghataprabha Project
2 Hipparagi Irrigation Project
3 Markandeya Reservoir Project
4 Dudhaganga Irrigation Project
5 Lifting of Hiranyakeshi waters into GRB Canal.
6 Bellary Nala Project
7 Sri Rameshwara L.I.S

(*) To irrigate suffering atchkat of tail end distributaries of MRBC / NBC, under Malaprabha Project

So far, an irrigation potential of 3,14,693 Ha, has been created under the above projects. An
expenditure of Rs.1945.44 Crores has been incurred under the above schemes to end of 3/2009.

Out of the above schemes, Markandeya Project is completed during 2006-07 and the remaining schemes
are under different stages of progress.

INDEX

50
11.1.1 GHATAPRABHA PROJECT

NAME OF THE PROJECT GHATAPRABHA PROJECT


Location Hidkal
Year of Inception 1972
Original Estimated cost-Rs. 90.54 Crores
Original and Latest estimated cost
Administrative approval: GO No.PWD. 147.MGP. B‟lore
(Rs. in Crores), including administrative/ Dated: 16.12.76-Rs.90.54 Crores
Technical sanction approval number & Date. Latest Estimated cost-Rs.1435.00 Crores vide GO. No. WRD 66
NIN 2006 dated 28.07.2007
Length of Canal G.R.B.C. G.L.B.C
a) Main Canal, 199 Km. 109 Km.
b) Branch Canal 88 Km 197 Km
c) Distributories 994 Km 494 Km
Length of ayacut roads/ I.T.roads 600.35 km
Districts benefited Belgaum, Bagalkot
Athani, Chikodi, Gokak, Hukkeri, Raibag, Ramadurg, Saundatti,
Number of villages and Taluks Benefitted Badami, Bagalkot, Bilagi, Hungund, Jamakhandi, Mudhol
taluks.
Number of W.U.C.S:
a) Formed 302
b) Registered 302
c) Handed over 285
Physical Financial
Programme during 2008-09
2271 Ha Rs. 153.00 Crores.
Progress achieved upto End of March 2007 - Rs. 55.49 Crores
Programme for 2009-10 (Physical & Financial). 2271 ha Rs.202.00Crores.
299777 Ha (including Stage-I,
Cumulative progress upto End of March 2009 Rs.1208.90 crores.
II & III)

INDEX

51
11.1.2 HIPPARAGI IRRIGATION PROJECT

NAME OF THE PROJECT HIPPARAGI IRRIGATION PROJECT


Location Hipparagi village
Year of Inception 1973
Original and Latest estimated cost Original Estimated cost- Rs.186.70 Crores
(Rs. in Crores), including administrative/ Latest Estimated cost-Rs. 1521.78 Crores
approval number & Date. Administrative approval: GO No. WRD / 21/ MBI/2008
dated 26.02.2008.
Length of Canal
a) Main Canal 289 Km
Districts benefited Belgaum, Bagalkot
Number of villages and Taluks Benefitted Athani, Chikodi, Jamakhandi taluks.
Physical Financial
Programme during 2008-09 2000 Rs. 237.00 Crores.
Progress achieved upto End of March 2009 - Rs. 80.87 Crores.
Programme for 2009-10 (Physical & Financial). 21,469 Rs. 220.50 Crores.
Cumulative progress upto End of March 2009 - Rs. 351.09Crores.
Brief description Central assistance under AIBP to this project is availed from
2007-08. CA received till date is Rs.140.99 crores. Barrage
works including erection of gates is completed. Water is
being imponded since 2004. Four LIS viz., Haliyal, Ainapur,
Karimasuti and Savalgi-Tungal are components of this
project. Out of these, Haliyal LIS Stage I & II, Ainapur LIS
are executed on turn key basis
Ainapur LIS: The works of pumphouse, rising main and
delivery chamber are completed. Works of East canal of 27
Km. length and West canal of 52 Km.length are at various
stages of progress.
Haliyal LIS: The works of pumphouse, jackwell, rising main
and delivery chamber under Stage I & II are completed.
Works of intake canal is nearing completion. Modified tender
is invited for combined canal. Works of East canal of 39 Km.
length and West canal of 32 Km.length are at various stages
of progress.
Karimasuthi & Savalgi-Tungal LIS: Works in these LIS are
in progress.

INDEX

52
11.1.3 MARKANDEYA RESERVOIR PROJECT

NAME OF THE PROJECT MARKANDEYA RESERVOIR PROJECT


Location Shirur village
Year of Inception 1998
Original Estimated cost-Rs.120.00 Crores
Original and Latest estimated cost Latest estimated cost- Rs.341.94 Crores
(Rs. in Crores), including administrative/ Administrative approval No. WRD 08 VEBYAMA 2003
approval number & Date. dated 28.07.2007.
Length of Canal R.B.C. L.B.C.
a) Main Canal 71 Km 15 Km
b) Distributories 183 Km -
Districts benefited Belgaum
Number of villages and Taluks Benefitted Belgam, Hukkeri, Gokak, Saundatti taluks.
Physical Financial
Programme during 2008-09 - Rs. 10.00 Crores.
Progress achieved up to end of March 2009 - Rs. 2.89 Crores.
Programme for 2009-10 (Physical & Financial). 65 Ha Rs. 7.00 Crores
Cumulative progress upto End of March 2008 14383 Ha Rs. 305.64 Crores
Brief description R & R works of 7 villages affecting 833 farmers is taken up in
2 rehabilitation centres. Shifting of PAF is completed. Third
rehabilitation centre has been identified, shifting of balance
PAF will be after completion of development works.
Chicholi-Murgod LIS is planned in balance works of this
project at estimated cost of Rs.47.13 crores to benefit 2718 ha.
and 1939 ha. Of land respectively.

INDEX

53
11.1.4 DUDHGANGA IRRIGATION PROJECT

NAME OF THE PROJECT DUDHGANGA IRRIGATION PROJECT


Location Asangaon village (Maharashtra State)
Year of Inception 1992 (Canal in Karnataka State)
Original Estimated cost-Rs.124.00 Crores
Original and Latest estimated cost
Latest Estimated cost –Rs. 124.00 Crores
(Rs. in Crores), including administrative/
Administrative approval. Ja.SAM: E-1: (VI.DN: GAM: 2000(P-2)
Technical sanction approval number & Date.
Dated.17/4-2002 (For Rs.-124.00 Crores)
Technical sanction. : (Yet to be accorded for Karnataka works).
Nidhori Branch Dattawad Branch
Length of Canal Bidri Branch canal
Canal Canal
a) Branch Canal 21.57 Km 25.155 Km 30.00 Km
Districts benefited Belgaum
Number of villages and Taluks Benefitted Chikkodi taluk.
Physical Financial
Programme during 2008-09 - Rs. 18.00 Crores

Progress achieved up to end of March 2009 - Rs. 11.68 Crores.

Programme for 2009-10 500 Ha Rs. 14.00 Crores.


Rs. 115.68 Crores. (Karnataka‟s
Cumulative progress up to end of March 2009 3800 Ha.
share)
This project is being assisted under Hon‟ble PM‟s Special
Brief description
Rehabilitation Package.

INDEX

54
11.1.5 LIFTING OF HIRANYAKESHI WATERS INTO G.R.B. CANAL.
LIFTING OF HIRANYAKESHI WATERS INTO G.R.B.
NAME OF THE PROJECT
CANAL.
Location Ghodageri village
Year of Inception 2005
Year of completion (in case of
Under progress.
Completed Projects)
Original and Latest estimated cost including Estimated cost - Rs. 30.00 Crores. Administratrive approval
administrative/Technical sanction approval number & WRD:03:NIN: 1995: Bangalore dated 23.8.2003Technical
Date. sanction CIN.109. For June 2005.
Length of Canal
a) Main Canal
b) Branch Canal
Detailed survey is taken up.
c) Distributories
d) F.I.C.
Districts benefited Belgaum
Number of villages and Taluks Benefitted Hukkeri
Physical Financial
Programme during 2008-09 - Rs. 6.00 Crores
Progress achieved up to end of March 2009 - Rs. 0.40 Crores
Programme for 2009-10 (Physical & Financial). - Rs. 4.00 Crores.
Cumulative progress up to end of March 2009 - Rs. 12.72 Crores.

INDEX

55
11.1.6 BELLARYNALA PROJECT
NAME OF THE PROJECT BELLARYNALA PROJECT
Location Kardikolla village
Year of Inception 2005
Year of completion (in case of Completed Projects) Under progress
Original and Latest estimated cost Estimated cost: Rs. 143.55 Crores
(Rs. in Crores), including administrative/ Administrative approval: No. WRD 02 VEBYAMA 2005
Approval number & Date. dated28.07.2007
Length of Canal
a. Main Canal
b. Branch Canal
Detailed survey is taken up
c. Distributories
d. F.I.C.
Districts benefited Belgaum
Number of villages and Taluks Benefitted Gokak, Saundatti.
Physical Financial
Programme during 2008-09 - Rs. 45.00 Crores
Progress achieved up to end of March 2009 - Rs. 13.56 Crores
Programme for 2009-10 (Physical & Financial). - Rs. 45.00 Crores
Cumulative progress upto End of March 2009 - Rs. 124.86 Crores

INDEX

56
11.1.7 SRI RAMESHWAR L.I. SCHEME

NAME OF THE PROJECT SRI RAMESHWAR L.I. SCHEME


Location Dhavaleshwar village
Year of Inception 2005
Year of completion (in case of Completed Projects) Under progress
Original and Latest estimated cost Original cost: Rs. 218.42 Crores
(Rs. in Crores), including administrative/ Administrative approval No: JaSamE: 14: NIN: 2001:
Technical sanction approval number & Date. Bangalore: Dated.23.8.2003.
Technical sanction: CEI (N) Reg. No. 110 for June 2005
Length of Canal
a) Main Canal
b) Branch Canal
Detailed Survey is taken up.
c) Distributories
d) F.I.C.
Districts benefited Belgaum
Number of villages and Taluks Benefitted Gokak
Physical Financial
Programme during 2008-09 - Rs. 27.00 Crores
Progress achieved up to end of March 2009 - Rs. 10.09 Crores
Programme for 2008-09 (Physical & Financial). - Rs. 14.96 Crores
Cumulative progress up to end of March 2008 Rs. 65.23 Crores

INDEX

57
11.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MALAPRABHA
PROJECT ZONE, DHARWAD

Malaprabha Project Zone, Dharwad was formed on 07.09.2007 in pursuance of the Government order
No.WRD.137.SeASu:2007, dated: 04.09.2007 with a view to increase the tempo of construction work in the
Irrigation Projects as a result of increased provision of the plan allocation in the state.

Malaprabha Project Zone is incharge of the following projects.

On-going Schemes
1 Malaprabha Project
2 Harinala Irrigation Project
3 Kalasa Nala & Bandhur Nala Diversion Schemes.
4 Javaluhalla L.I.S. *
5 Bennihalla L.I.S. *
6 Kolachi L.I.S. *
7 Konnur L.I.S. *
8 Shiggaon L.I.S

(*) To irrigate suffering atchkat of tail end distributaries of MRBC / NBC, under Malaprabha Project

So far, an irrigation potential of 2,14,841 Ha, has been created under the above projects. An
expenditure of Rs.1107.25 Crores has been incurred under the above schemes to end of 3/2009.

Out of the above schemes Harinala Project has been completed during 2006-07 and the remaining
schemes are under different stages of progress.

INDEX

58
11.2.1 MALAPRABHA PROJECT

NAME OF THE PROJECT MALAPRABHA PROJECT


Location Naviluteertha
Year of Inception 1960
Original Estimated cost Rs.20.00 Crores
Administrative approval: GO No.PWD. 59. GMP. 77, B‟lore
Dated: 4.2.1980 Rs.162.09 Crores
Original and Latest estimated cost
Technical sanction No.: CE, I(N), BGM Reg.No.CIN.7.for June
(Rs. in Crores), including administrative/
1980 Rs.162.09 Crores
Technical sanction approval number & Date.
Latest Estimated cost Rs. 1275.20 Crores vide G. O. No. WRD
/78/ MPS/ 2003 dated 28.07.2007
Length of Canal M.L.B.C. M.R.B.C
a) Main Canal, 150 Km. 142 Km.
b) Branch Canal 26 Km. 42 Km.
c) Distributories 280 Km 677 Km.
Length of ayacut roads/I.T.roads 282.62 Km
Districts benefited Belgaum, Dharwad, Gadag, Bagalkot
Number of villages and Taluks Bailhongal, Ramadurg, Saundatti, Badami, Navalgund, Hubli,
Benefitted Naragund, Ron, Gadag taluks.
Number of W.U.C.S:
a) Formed 266
b) Registered 231
c) Handed over 208
Physical Financial
Programme during 2008-09
4956 Ha Rs.59.00 Crores.
Progress achieved up to end of March 2009 2611 Ha Rs. 55.07 Crores.
Programme for 2009-10 (Physical & Financial). 2167 Ha Rs.125.00 Crores.
Cumulative progress up to End of March 2009 211361Ha Rs. 998.32 Crores.
Brief description This project is being assisted under AIBP. Central assistance
availed during 2008-09 is Rs.49.44 crores and cumulative
central assistance availed is Rs.257.07 crores.

59
11.2.2 HARINALA IRRIGATION PROJECT

NAME OF THE PROJECT HARINALA IRRIGATION PROJECT


Location Tigadi Village
Year of Inception 1998
Original Estimated cost - Rs. 0.83 Crores
Original and Latest estimated cost Latest Estimated cost-Rs.69.78 Crores
(Rs. in Crores), including administrative/ Administrative Approval No: CE: 114:MPS: 92
Technical sanction approval number & Date. Dated.11/14/9/98 (Rs.-26.95 Crores).
Technical sanction: CEI (N): BGM: Reg.No.CIN –17 for
May 1999 (Rs.26.95 Crores).
Length of Canal Left Bank Right Bank
a) Main Canal 9.00 Km 10.72 Km
Districts benefited Belgaum.
Number of villages and Taluks Benefitted Bailhongal taluk.
Physical Financial
Programme during 2008-09 - Rs.3.00 Crores
Progress achieved up to end of March 2009 - Rs. 0.86 Crores
Programme for 2009-10 (Physical & Financial). - Rs. 2.00 Crores
Cumulative progress up to end of March 2009 3480 Ha Rs. 70.46 Crores

INDEX

60
11.2.3 KALASA NALA AND BANDHUR NALA PROJECT

NAME OF THE PROJECT KALASA NALA AND BANDHUR NALA PROJECT


Location Kanakumbi – Kalasa Nala Project
Nerse village - Bhandur Nala Project
Year of Inception 2006
Year of completion (in case of Completed Projects) Under progress (Kalasa only)
Original Estimated Cost
Kalasa Nala - Rs. 44.78 Crores
Bhandur Nala - Rs. 49.20 Crores
Original and Latest estimated cost Administrative approval No.
(Rs. in Crores), including administrative/ a) Kalasa nala: ID.37.WBT. 2000: Dated.22.8.2000
Technical sanction approval number & Date. b) Bhandur nala:-.ID-4.WBT:2000: dated.22.8.2000.
Technical sanction No:
a) Kalasa nala - CIN.Reg.No.270, March 2002
b) Bhandur nala - CIN.Reg.No.269, March 2002.
Districts Benefited Belgaum, Dharwad, Gadag and Bagalkot
Number of villages and Taluks
Hubli-Dharwad & other villages (Drinking water supply)
Benefited
Physical Financial
Programme during 2008-09
- Rs.3.00Crores for KalasaNala
Rs. 12.19Crores for KalasaNala
Progress achieved upto End of March 2009 -
Rs.0.07 Crores for BhandurNala
Programme for 2009-10 (Physical & Financial). - Rs. 10.00Crores for KalasaNala
Rs.16.06 Crores under KalasaNala & Rs. 0.41
Cumulative progress upto End of March 2009
Crores under BhandurNala
Clearance from MoWR, Planning Commission and MoEF is
Brief description:
awaited.

INDEX

61
11.2.4 JAVALUHALLA L. I. SCHEME

NAME OF THE PROJECT JAVALUHALLA L.I. SCHEME


Location: Kittur village
Year of Inception: 2005
Year of completion (in case of Completed Projects) Under progress
Original Estimated: cost. Rs. 4.21 Crores
Original and Latest estimated cost Administrative approval: WRD: 03:NIN:95 dated:
(Rs. in Crores), including administrative/ 23.08.03
Technical sanction approval number & Date. Technical sanction: CE, I (N), BGM
Reg.No.CIN.10.for April – 2003
Length of Canal:
a) Main Canal
b) Branch Canal
c) Distributories Detailed survey is taken up.
d) F.I.C.
Districts benefited Belgaum
Number of villages and Taluks Benefitted Ramdurg
Physical Financial
Programme during 2008-09 - Rs. 1.00 Crores
Progress achieved upto End of March 2009 - Rs. 0.04 Crores
Programme for 2009-10 (Physical & Financial). - Rs. 1.00 Crores.
Cumulative progress up to end of March 2009 Rs. 3.98 Crores.

INDEX

62
11.2.5 BENNIHALLA L.I. SCHEME (5 NOS.)

NAME OF THE PROJECT BENNIHALLA L.I. SCHEME (5 NOS.)


Location Banahatti, Kurlageri, Surkod,Khanapur, Reddar Naganur
Year of Inception 2005
Original Estimated cost: Rs. 17.33 Crores
Original and Latest estimated cost
Administrative approval: WRD/ 58/MPS/1999 (P), B‟lore
(Rs. in Crores), including administrative/
dated: 23.08.03
Technical sanction approval number & Date.
Technical Sanction: CE I (N) Reg.No.163 for August 2005.
Length of Canal
a) Main Canal

b) Branch Canal Detailed survey is taken up.


c) Distributories

d) F.I.C.

Districts benefited Gadag

Number of villages and Taluks Benefitted Nargund

INDEX

63
11.2.6 KOLACHI L.I. SCHEME

Name of the Project KOLACHI L.I. SCHEME


Location: Asooti village
Year of Inception: 2005
Year of completion (in case of Completed Projects) Under progress
Original Estimated cost: Rs. 2.25 Crores
Original and Latest estimated cost
Administrative approval: WRD. 58.MPS.1999 (P) (K),
(Rs. in Crores), including administrative/
Bangalore dated: 23.08.03.
Technical sanction approval number & Date.
Technical Sanction: CEI (N). Reg.No.162 for August 2005.
Length of Canal
a) Main Canal
b) Branch Canal
c) Distributories Detailed survey is taken up.
d) F.I.C.
Districts benefited Gadag
Number of villages and Taluks Benefitted Ron

INDEX

64
11.2.7 KONNUR L.I. SCHEME

NAME OF THE PROJECT: KONNUR L.I. SCHEME


Location: Konnur village
Year of Inception: 2005
Year of completion (in case of Completed Projects) Under progress.
Original Estimated cost: Rs. 6.15 Crores
Original and Latest estimated cost Administrative approval: WRD. 58.MPS.1999 (P), B‟lore
(Rs. in Crores), including administrative/ dated: 23.08.03
Technical sanction approval number & Date. Technical sanction No: CE I (N) Reg.No.161 for August
2005.
Length of Canal:
a) Main Canal
b) Branch Canal
Detailed survey is taken up
c) Distributories
d) F.I.C.
Districts benefited Gadag
Number of villages and Taluks Benefitted Nargund

FOR BENNIHALLA, KONNUR L.I.S & KOLCHI LIS


Physical Financial
Programme during 2008-09 - Rs. 6.00 Crores
Progress achieved upto End of March 2009 - Rs. 5.216 Crores
Programme for 2009-10 (Physical & Financial). - Rs. 5.00Crores
Cumulative progress upto End of March 2009 Rs. 17.84 Crores

INDEX

65
11.2.8 SHIGGAON L.I. SCHEME
NAME OF THE PROJECT: SHIGGAON L.I. SCHEME
Location: Near Halasur village of Savanur taluk in Haveri district.
Year of Inception:
Year of completion (in case of Completed Projects) Under progress.
Original and Latest estimated cost Rs. 238.00 Crores
(Rs. in Crores), including administrative/ Administrative approval: No. WRD / 98 / MMB / 2008,
Technical sanction approval number & Date. Bangalore dated 13.01.2009.
Planned irrigation potential 9900 Ha.
Districts benefited Haveri
Number of villages and Taluks Benefitted Shiggaon, Hanagal and Savanur taluks
No. of MI tanks for stabilization 5
No. of bandaras 6

INDEX

66
11.3. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, MUNIRABAD

11.3.1 SINGATALUR LIFT IRRIGATION SCHEME (SLIS)

The project comprises of construction of barrage across River Tungabhadra near Hammige village of
Mundargi taluk in Gadag District to provide irrigation facility to an extent of 1,20,236Acres (1,40,677Acres of
cropped area in Bellary, Koppal and Gadag districts by utilising 18.55 TMC of water.

Stage-I comprises of utilising 7.64TMC to irrigate 76181acres and stage-II of utilising 4.39TMC to irrigate
44055acres. Government has accorded administrative approval to implement this scheme with the utilization of
12.03TMC of water vide G.O. No. WRD 115 WBP 2003 Dt.29-6-2006.

BARRAGE:. Out of 26 blocks concreting in all the blocks has reached up to crest level except in block no.6
and 7.Fabrication of 26 nos of gates is completed. Erection works are to be taken up.

The Barrage and allied works are under progress. Out of 25Nos of piers 14 Nos of piers have been concreted
up to the bearing level of Spillway Bridge. Casting of RCC pre cast beams and piers are under progress.

CANAL WORKS ON LEFT SIDE:


 Intake canal: Earth work excavation of intake canal from 0 to 6.71Km is under progress.
 The tenders are invited to take up the works of Mundwada & Hammige Lift and of the Left side 1 st Lift, on
turn key basis. The preparation of estimates and DTP are under progress for obtaining technical sanction.
 Land acquisition works on left side are under progress.

The cumulative expenditure incurred on the project since inception upto end of March 2009 is Rs.
263.34 Crores. During 2008-09 an expenditure of Rs. 14.12 crores has been incurred against a budget allocation
of Rs. 64.00 Crores.

67
AN OVER VIEW OF THE SINGATALUR LIFT IRRIGATION SCHEME:

1 NAME OF PROJECT SINGATALUR LIFT IRRIGATION SCHEME

Across River Tungabhadra near Hammige village


Mundaragi Taluk, Gadag District.
2 Location
Longitude: 70 0 50‟ E
Lattitude: 15 0 02‟ N
3 Year of inception March 1998
Original estimate-Rs. 595.00 Crores vide G.O. No.
Original and latest estimated cost in Crores ID/ 90/ MTP /98 and 29-12-2000.
4 Including administrative approval no. and date Technically sanctioned by Chief Engineer Vide CER
No. 28/2001-02
Latest cost Rs. 657.00 Crores.
Length of canal
5 a) Main canal LBC 207.34 km
b) Branch canal 31.70 Km
6 District benefited Bellary, Gadag and Koppal
70 villages of Mundargi and Gadag Tq.
7 Number of village and Tq benefited 09 villages of Koppal Taluk.
20 villages of Huvina Hadagali Taluk
Physical Financial
Programme during 2008-09
- Rs. 64.00 Crores

Progress achieved up to end of March 2009 - Rs. 14.11 Crores

Cumulative progress up to end of March 2009 Rs. 263.34Crores

INDEX

68
11.4. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER,
UPPER TUNGA PROJECT ZONE, SHIMOGA
The following are the projects under the jurisdiction and control of Upper Tunga Project circle,
Shimoga.

1) The Upper Tunga Project

2) The Tunga Lift Irrigation Scheme

3) Basapur Lift Irrigation Scheme

4) Itagi-Sasalwad Lift Irrigation Scheme

5) Guddada Mallapura Lift Irrigation Scheme

6) Upper Bhadra Project

7) Ubrani-Amrutapura Lift Irrigation Scheme

8) Sanyasikoppa Lift Irrigation Scheme

69
11.4.1 UPPER TUNGA PROJECT

The river Tunga is a major tributary of river Tunga Bhadra rises in Western Ghats and joins mother
tributary Bhadra at Kudli about 14.50KM from Shimoga. Upper Tunga project envisages construction of new
dam across Tunga River at 100.00 meter down stream of existing Tunga Anicut near Gajanur in Shimoga Taluk
and construction of Upper Tunga Main Canal; for a length of 339.50 km. It includes construction of tunnel of
4.00 km length and also distributary net work.
It is envisaged to create an irrigation potential of 80,494 hectares in Shimoga, Davanagere and Haveri
Districts by utilising 12.24 TMC of water from River Tunga.

The Government of Karnataka has accorded administrative approval for this project vide No.ID: 25:
MMM: 91: Bangalore dated: 3-10-1991 for Rs. 271.41 Crores and vide No.WRD: 38:WBP: 2005 (P):Bangalore
dated: 21.11.2006 for Rs. 1,052.33 Crores and the Revised Cost of the project is Rs. 1,644.11 Crores. The
project is under the control of Karnataka Neeravari Nigama, Bangalore since 14.6.1999.

DAM AND ALLIED WORKS: - Dam work including parapet wearing coat and asphalting works are
completed. Electrification work is completed. The major work on crest gate including fixing of switch gears is
completed. Power block portion of mini hydel project is completed. Earthwork excavation for construction of
power house and tail race channel is under progress.

Head resulator: Construction of regulator at Km.0145 is completed except for providing hoisting arrangement
for three gates out of five gates.

CANAL AND DISTRIBUTARY NETWORK: - Upper Tunga Project includes construction of 329.50 Km
lengths of Main Canal including CD works, lining and Distributory Network. At present main canal alignment is
approved up to 270 Km. Canal work up to Km 195 including tunnel work from Km 168.50 to 174.00 is under

70
different stages of progress. Estimates are being prepared for works from Km. 192 to 244. Works are under
different stages of progress in distributary No. 1 to 3 of main canals.

Main canals: Main canal works from Km.0 to 162 are almost completed except following up of bottlenecks.

 Km. 0.172 to 10.00: Earth work is completed slips are occurring of both sides of the canal, 300 mtrs.
cut and cover and balance lining works are in progress.

 Road bridge at Km.12.96: Cut & cover technology is adopted for road bridge. Tenders are at
evaluation stage.
 Km. 19 to 20.00: Cut & cover road duct is proposed now instead of framed structures. Tenders are at
evaluation stage.
 Km.74, 75 & 103: Original contract is recall and fresh agency is being entrusted.
 Km.139, 163,164 to 168.50: Original contract is rescinded and fresh tender invited.
 Km.168.50 to 174: Earth work excavation is completed. Tunnel lining is nearly completion and
grouting is in progress.

Distributory
Dist.No.1: Off-take point at Km108.35. Total length is 20.58 Km. Works are completed.

Dist.No.2: Off-take point at Km166.267. Total length is 62.50 Km. Works are completed from 0 Km. to
20 Km. Works from Km.20 to 62.50 is lingering due to rescinding of contract, Railway crossing and forest
clearance. Necessary deposits are made to railway and national highways for carrying out the work.

Dist.No.3: Off-take point at Km176.83. Total length is 23.00 Km. Works are under progress.

R & R works: Three villages of Thirthahalli taluk and two villages of N.R.Pura taluk have been
affected due to construction of Upper Tunga Project. 208 structures are affected. Necessary deposits are
paid to SUDA for formation of lay-out and site to PAF. Also, Rs.20.475 crores of ex-gratia is provided as
per the decision of R&R Committee.

During the year 2008-09 the grant allotted is Rs. 104.00 Crores and the expenditure incurred up to end
of March 2009 is Rs. 96.32 Crores. Since inception of project, cumulative expenditure to the tune of Rs. 918.32
Crores has been incurred.

INDEX

71
11.4.2 TUNGA LIFT IRRIGATION SCHEME
Tunga lift irrigation scheme is proposed at Sakrebailu village near Gajanur in Shimoga district. This
project envisages lifting of water from the backwater of UTP Reservoir to feed the suffering atchkat of 5162
Acres of Aihole, Barehalla and Gowdanakere Tanks of Shimoga Taluk. It is proposed to utilise 1.428 TMC of
water from Tunga Reservoir. For this project Government has accorded administration approval vide No. ID 68:
MMM: 95: Bangalore dated 27-2-99 for Rs. 24.12 Crores and Technical sanction was accorded for the same
amount on 30-3-99.

The Main Canal of the project runs in Sakrebylu wild life forest. Necessary proposal for Diversion of
forest Land has been made with forest authorities and this project will be implemented soon after obtaining
necessary clearance from the Government. In the meantime survey is under progress for alternative means for
avoiding forest area.

During the year 2008-09 the grant allotted is Rs. 50.00 lakhs and an expenditure of Rs. 8.89 lakhs has
been incurred during the current year. The project is yet to be started. Cumulative expenditure of Rs. 8.89 lakhs
has been incurred till date.

INDEX

72
11.4.3 BASAPURA LIFT IRRIGATION SCHEME

This project envisages lifting of water from River Varada near Basapura village in 2 stages to irrigate
5600 Acres of Land, pertaining to 13 villages of Hangal Taluk, Haveri District. An allocation of 0.60 TMC of
water for utilisation in provided for this project by the Krishna Water Tribunal. Administrative approval has
been accorded for this project vides G.O. No. ID 20/MMM/96-97 dated.9-4-96 for Rs. 936.00 Lakhs. CE, UTP
Zone, Shimoga has accorded technical sanction for Rs. 936.00 Lakhs on 31-6-1996. Latest estimated cost of the
project is Rs. 26.96 crores.

The project is transferred to KNNL during August-03. Presently, Stage I work of Electro-Mechanical
Components & other head works have been entrusted on turnkey basis and are ready for commissioning. Main
Canal work of Stage I, in the reach Km 0.00 to 0.56 & Km. 5.00 to 5.35 & Aqueduct in Ch.0.56 to 1.87 Km is
completed. Balance canal works are under different stages of progress. Distributory works are also entrusted on
tender basis, which are under different stages of progress. The estimates of Stage II are prepared and Tenders are
being invited to take up the work on Turnkey basis.

During the year 2008-09 the grant allotted is Rs. 500.00 Lakhs and the expenditure incurred is Rs. 111.13
Lakhs. Since inception up to end of March 2009, cumulative expenditure of Rs. 1218.66 Lakhs has been
incurred on the project.

INDEX

73
11.4.4 ITAGI-SASALWAD LIS

This project envisage lifting of water from River Tungabhadra near Itagi village, Shirahatti Taluk, Gadag
Distrist, in one stage to cater the irrigation requirements of Khariff & semi dry crops to an extent of 4900 acres
belonging to Shirahatti, Mundargi and Haveri Taluk. The Government accorded Administration approval for
Rs. 427.00 Lakhs on 21-09-1992 and subsequently revised administrative approval was accorded for Rs. 800
lakhs on 24-4-96. Chief Engineer, UTP Zone, Shimoga accorded technical sanction for Rs. 800 Lakhs to the
Project, on 5-6-96. An allocation of 0.55 TMC of water for utilization is provided for this project by the Krishna
water Tribunal. Latest estimated cost of the project is Rs. 18.55 crores.

The project was transferred to KNNL during August 2003. Presently the Headwork like Jack well, In-
take arrangements, Raising Main, Pump house, pumping Machineries etc., has been entrusted on Turnkey basis
and the works are nearing completion. Right bank canal to length of 25.52 Km, left bank canal to a length of
10.90 Km and its distributary network were entrusted to different agencies and are completed.

During the year 2008-09 the grant allotted is Rs. 600.00 Lakh and the expenditure incurred up to end of
March 2009 is Rs. 127.69 Lakhs. Since inception of the project an amount of Rs. 1849.47 Lakhs has been spent.

INDEX

74
11.4.5 GUDDADA MALLAPURA LIS

The lift irrigation scheme is proposed near Kusnur village in Hanagal taluk of Haveri district. This
Project envisages creation of Irrigation potential of 5263 Ha of Byadagi Taluk with an ultimate utilization of
1.00 TMC of water from River Varada. The Estimated cost of this project is Rs. 60.00 Crores.

Technical sanction is accorded for Rs. 56.16 Crores and work is taken up on turnkey basis. Presently the
agency has stopped the work and tender rescinding is under progress.

During the year 2008-09 the grant alloted is Rs. 100.00 Lakhs and no expenditure has been incurred
during the current year. Since inception, cumulative expenditure of Rs. 1563.78 Lakhs has been incurred for this
project.

INDEX

75
11.4.6 UPPER BHADRA PROJECT (STAGE 1 & 2)

This project envisages to lift 15 TMC of water from Tunga river to Bhadra reservoir, in two stages, and
lifting of 21.5 TMC of water from Bhadra reservoir to delivery chamber near Ajjampur in three stages.
Thereafter by gravity flow through canal, irrigation will be provided to 1,04,989 Ha. of land in Hosadurga,
Hiriyur, Chitradurga and Challekere taluks and 2276 Ha. of land in Kadur and Tarikere taluks, totaling to
1,07,265 Ha. by utilizing 15.9 TMC of water.

It is also proposed for restoration of 119 tanks of Tumkur and Kolar districts and 37 tanks in
Chickmagalur and Chitradurga districts and providing water to an extent of 75% of live capacity by utilizing 5.6
TMC of water to recharge the ground water table to facilitate drinking water.

Estimated cost of the projects is Rs. 5985.00 crores. 21.5 TMC of water is allocated to this project under
Scheme – A.

Modified cost of the project as per SR of 2007-08 of Rs.5985.00 crores, out of which, Rs.3388.00 crores
is for irrigation component and Rs.2597.00 crores is for drinking water component.

Tender for the following package of Upper Bhadra Project are finalized and survey works are under
progress.

 Diverting 15 tmc of water from Tunga to Bhadra reservoir – Package (I).

 Lifting 21.50 tmc of water for Bhadra reservoir to delivery chamber near Ajjampura (proposed
new tunnel) – Package (II).

 Construction of tunnel at 6.90 km length near Ajjampura (Package-III).

During the year 2008-09 the grant allotted is Rs. 100.00 Crores and the expenditure incurred up to end of
March 2009 is Rs. 54.30 Lakhs.

INDEX

76
11.4.7 UBRANI-AMRUTHAPURA MULTIPURPOSE LIS

This scheme was a part of Upper Bhadra Project Stage-1, which was separated as per Government order.
The Main aim of this project is (a) drinking water purpose and (b) Filling of Tanks of Ubrani and Kasaba hobli
of Tarikere Taluk.

This project comprises of 3 stages costing Rs. 92.40 Crores. It is planned to lift water from Bhadra River
to Gangur in Ist Stage and is technically sanctioned for Rs. 36.00 Crores and work is taken up on turnkey basis.
The work is under different stages of progress. In 2nd Stage, water is pumped from a storage cistern at Gangur to
Mahalal valley and part to Guddadamalladevanakere and is technically sanctioned for Rs. 56.40 Crores and
work is taken up on turnkey basis. The works are nearing completion. In 3rd stage, water is directly lifted from
Guddadamalladevanakere tank to feed water to Medikere tank.

During the year 2008-09 the grant allotted is Rs. 2600.00 lakhs and the expenditure incurred up to end of
March 2009 is Rs. 2684.16 lakhs. Since inception upto end of March 2009, cumulative expenditure of Rs.
5668.10 lakhs has been incurred for this project.

INDEX

77
11.4.8 SANYASIKOPPA LIS

Sanyasikoppa lift irrigation scheme envisages construction of anicut across Kumudavathi River near
Sanyasikoppa village in Shikaripura Taluk, Shimoga District to irrigate 1791 hectares. The Government has
accorded administrative approval Vide G.O.No.ID/ 161/MMI/2003 dated: 25-3-2006 for Rs.10.00 Crores for
this Project. Technical sanction is accorded for Rs. 9.97 Crores. Agency is fixed to take up works on turnkey
basis and works are under different stages of progress.

During the year 2008-09 the grant allotted is Rs. 800.00 lakhs and the expenditure incurred is Rs.101.49
lakhs up to end of March 2009.

INDEX

78
11.4.9 KALLU VADDAHALLA NEW TANK

This project envisages construction of new tank across Kalluvaddahalla in Shikaripura taluk of Shimoga district
to irrigate 1450 hectares of land. Project estimated cost of Rs. 33.42 crores has been prepared and placed before
Technical Sub Committee for approval.

79
11.4.10 TILUVALLI LIFT IRRIGATION SCHEME

This project envisages lifting of 0.26 TMC of water from Varada River to provide irrigation facilities to 2500
acres of land in Iangal taluk.. Project estimated cost of Rs. 42.50 crores has
been prepared and placed before Technical Sub Committee for approval.

INDEX

80
11.5. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, VARAHI
PROJECT ZONE, SIDDAPURA.

11.5.1 VARAHI IRRIGATION PROJECT

BREIF DESCRIPTION:

The Varahi Irrigation Project envisages Construction of Diversion Weir across Varahi River at Horriabbe
near Siddapura Village, Udupi District to create irrigation potential to an extent of 15,702 Ha. (38,800 acres) in
Kundapura and Udupi taluks of Udupi District, by utilizing the daily release of 1100 Cusecs of tail race water
from Varahi underground hydro electric project situated in the upstream of the river at Hosangadi.

The Varahi Irrigation Project is administratively approved by the Government of Karnataka vide G.O.No.
PWD 71 GIP 76, Bangalore dated 27-3-1979 for Rs. 943.00 lakhs. Later administrative approval was accorded
to the re-revised estimate cost of Rs. 569.00 crores.

For speedy implementation, the Project was transferred to Karnataka Neeravari Nigam Ltd. Vide G.O. No.
WRD 1 MMM 2003, Bangalore dated 6-11-2003.

VARAHI DIVERSION WEIR:

A concrete diversion weir 145 meters long and 17.50 meters high above the deepest foundation level is
proposed to be constructed at Horriabbe site near Siddapura Village, Udupi District. Administrative approval
for the Construction of Diversion Weir has been accorded by the Government of Karnataka vide G.O.No. WRD
30 MMM 2001 dated 3-2-2003 for Rs. 2900.00 lakhs and technical sanction has been accorded on 27-2-2003.

Due to Construction of Diversion Weir, 121.58 Ha. of land will be submerged along with two villages which
will be submerged partially. Works are entrusted on tender basis and are under progress.

81
CANALS:
Varahi Right Bank Canal takes off from the Dam and runs for a length of 42.8 Km. A branch canal
takes off from Right Bank Canal at Km 19 and crosses the River Varahi through an aqueduct. The Left Bank
Canal takes off from this aqueduct and runs for a length of 44.35 Km. The Lift Canal takes off from the Left
Bank Canal at Km 7 and runs for a length of 33 Km.

The proposed atchkat to be covered in Udupi District is as detailed below:


Sl. Canal details Length, Km Irrigable area,
No Ha
1 Varahi Right Bank Canal 42.80 1992
Varahi left bank canal
2. 44.350 10987
(From off-take at 20th Km of Right Bank Canal)
3 Lift canal (From off-take at 7th Km of Left Bank Canal) 33.00 2723
Total 15702
Villages benefited:
1 Kundapura Taluk 33 villages 8324
2 Udupi Taluk 35 villages 7378
Total 68 villages 15702

This project is received central assistance under AIBP since 2007-08.

PROGRESS DURING 2008-09:

The total estimated cost of the project is Rs. 569.53 Crores. Cumulative expenditure incurred on the
project up to end of March 2009 is Rs. 273.02 Crores.

During 2008-09, against the programme of Rs. 10100.00 lakhs, expenditure of Rs. 6502.81 lakhs has
been incurred up to end of March 2009.

The Varahi Left bank works from 0 to 21 Km are nearing completion further 22 to 30 Km works are started
Tender for Construction of Aqueduct across Varahi river connecting Varahi Right bank Canal and Varahi
Left Bank Canal is under progress. Works of Varahi right bank canal from Km. 0 to 8.40 is under progress.
Works from Km. 8.40 to 14.00 are in the stage of tender approval. The project is proposed to be completed
during 2012.

INDEX

82
11.6. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION
PROJECTS ZONE, GULBARGA

11.6.1 BENNITHORA PROJECT

Bennithora project is a major irrigation project, which comprises of construction of dam across River
Bennithora near Heroor village, Chittapur taluk, Gulbarga District. There are two canals covering an Irrigable
area of 20,234 Ha in Gulbarga District. The utilisation for the project is 5.75 TMC.

The works of dam embankment and spillway are completed and water is being stored in reservoir since
2001 and works of right bank canal are completed except CD laterals and 2 sub distributories which are under
progress. Works of left bank canal are completed except 4 distributories which are under progress.

The revised estimate cost of this project is 355.00 Crores. Cumulative expenditure upto end of March
2009 is Rs. 332.35 Crores. A dry potential of 19978 Ha has been created to end of 3/2009.

The details of target and achievement of the project for 2007-08 and 2008-09 are as follows:

Sl. Financial (Rs. in Crores) Physical (In hectares)


Year
No. Target Achievement Target Achievement
1 2007-08 5.00 14.74 1427 1118
2 2008-09 21.00 16.05 309 309

INDEX

83
11.6.2 BHIMA LIFT IRRIGATION SCHEME

Bhima Lift Irrigation envisages construction of Earthen Dam with central concrete spillway with crest
gates to discharge 9.00 Lakh Cusecs of water. The Dam site is proposed near Sonna (K) village of Afzalpur
Taluk in Gulbarga District and providing two lift irrigation points to draw water from the Reservoir, for creation
of 24,292 hectares of irrigation Potential.

The Project is administratively approved for Rs. 94.17 Crores by the Government vide Govt. Order No. ID 39
MMM 92, dated 18-4-1992, and technically sanctioned for Rs.107.70 Crores by the Chief Engineer, WRD,
I.P.Zone, Gulbarga vide CER No. 5/93-94 dated13-01-1994. The Revised Estimate costing Rs. 592.50 Crore is
submitted for approval. This project is under Karnataka Neeravari Nigam Ltd., since 1999.

Stage of the project as on March 2009:

I. Earthen Dam:
The length of barrage is 2250 meters including the central over flow section (spillway) of 418 meters
with earthen flanks on either side. The length of left earthen flank is 612 meter and length of right flank is 1183
meter. Both the earthen embankments are completed.

II. Barrage:
The work of construction of the barrage is awarded to M/s G.J. Fernandez, Class-I Contractor on 21-02-
2003 for Rs. 25.93 crores. The total cost for completion is Rs. 46.30 Crores and works are under progress. The
foundation of Barrage is completed including left abutment. The spillway body wall comprises of 30-blocks are
completed (crest level 396.40). All 28 piers are completed. Casting of girders and launching of girders and slabs
are completed. The work of MHS on right flank is in progress. The financial progress achieved up to end of
March-2009 is Rs. 42.52 Crores.

84
III. Gates:
The fabrication of 29 Nos. of vertical gates is entrusted to Karnataka State Construction Corporation
and work order is issued on 06-07-2005. The fabrication and erection of embedded parts for service gates, stop
log gates is completed. The financial progress achieved up to end of March-2009 is Rs. 47.10 Crores.

HEAD WORKS:
I. Balundagi Lift:
The construction of Balundagi Lift is entrusted to Kirloskar Brothers Limited for Rs. 12.39 Crores. The
work order is issued on 27-07-2005 and works are under progress.

The excavation of jack well portion is completed and construction of jackwell is nearing completion.
Delivery chamber is completed. Excavation for raising main is completed. Pumps, motors and transformers are
supplied. Erection of pumps and motors are completed. The supply and laying of PSC pipes for rising main is
nearing completion. The financial progress achieved up to end of March-2009 is Rs. 8.50 Crores.

II. Allagi (B) Lift:


The construction of Allagi (B) lift is entrusted to Laxmi Civil Engineering Pvt. Ltd. for Rs. 691.25
Lakhs. The work order is issued on 29.07.005 and works are under progress.

The excavation of jack well portion is completed and construction of jackwell is nearing completion.
Delivery chamber is complete. Excavation for raising main is completed. Pumps, motors and transformers are
supplied. Erection of pumps and motors are completed. The supply and laying of PSC pipes for rising main is
nearing completion. The financial progress achieved up to end of March-2009 is Rs. 4.71 Crores.

The construction of intake channel is taken up and is in progress.

CANALS – Length of Balundagi Lift canal is 61.02 Km. & Allagi Lift Canal is 34.40. Works are under
progress.
Revised estimated cost of the project is Rs.275.53 crores and cumulative expenditure incurred upto end of
March 2009 is Rs.154.03 crores.
During the year 2008-09, budget allocation made is Rs.32.00 crores and expenditure incurred upto March
2009 is Rs.21.23 crores.
The details of target and achievement of the project for 2007-08 and 2008-09 are as follows: -

Sl. Financial (Rs. in Crores) Physical (In hectares)


Year
No. Target Achievement Target Achievement
1. 2007-08 30.00 29.31 - -
2. 2008-09 32.00 21.23 - -

INDEX

85
11.6.3. GANDORINALA PROJECT

Gandorinala project is a medium irrigation project in Gulbarga District. This project envisages
construction of dam near Belkota village in Gulbarga taluk, across River Gandorinala, a tributary to River
Bennithora, which in turn joins River Bhima of Krishna Basin. The utilisation under this project is 1.97 TMC.
The area covered for irrigation under this project is 8094 Hectares.

The project is administratively approved vide Government Order No. ID 110 MTZ 85, Bangalore dated
23.05.1992 for Rs. 66.00 crores. The revised estimate of the project is Rs. 239.00 Crores and
expenditure upto March 2009 is Rs. 209.79 Crores. The dry irrigation potential of 7943 Ha has been created upto
March 2009.

DAM: Earthen dam, embankment and spillway works are completed, and water is stored in the Reservoir.
CANAL:
Main Canal : Total length of Right bank canal is 7 km, which is completed and total length of left bank canal
is 90 km., out of which works in km.0.00 to 23.00 are completed. Works of Km. 24 & 25 are nearing
completion. Works of remaining length are under progress.

Distributary: There are 3 number of Distributary under RBC and works of all the 3 distributaries are
completed. No. of distributaries under LBC is 40, of which works of 17 are completed, 19 are under progress
and 4 are under initial stage.

FIC: Out of contemplated atchkat of 8094 Ha. FIC provided up to end of March 2009 is 4037 Ha. It is
programmed to complete FIC for balance area of 4057 Ha. during 2009-10
The details of target and achievement of the project for 2007-08 and 2008-09 are as follows

Sl. Year Financial (Rs. in Crores) Physical (in hectares)

86
No. Target Achievement Target Achievement
1) 2007-08 25.00 15.92 1831 716
2) 2008-09 16.00 17.97 1115 964

INDEX

87
11.5.4. LOWER MULLAMARI PROJECT.

Lower Mullamari Project envisages construction of a dam across the River Mullamari a tributary to
River Bhima in Krishna basin. The project is located near Nagaral village in Chincholi Taluk of Gulbarga
District. The utilisation under this project is 2.61 TMC and it is planned to provide irrigation facilities to 9713
Ha. of land in Chincholi taluk.

The project has been originally estimated for Rs. 45.00 crores at 1990-91 schedule of rates. The latest
estimated cost of the project is Rs. 210.00 Crores and expenditure to end of March 2009 is Rs. 174.74 Crores.

DAM: Earthen dam including spillway is completed and water is being stored since August 2001.

CANAL: The total length of Right Bank canal is 80 Kms. And all these works are completed. The improvement
and protection works to right bank canal from Km. 0 to 40 are nearing completion. Strengthening works of main
canal from Km. 40 to 80 are under approval stage. Total number of distributaries are 66, out of which 65 are
completed and Work of remaining 1 distributary is nearing completion.

R & R WORKS: 7 rehabilitation centers are formed, out of which 6 are completed and the villages are shifted.
Work of remaining 1 centre is nearing completion.

The irrigation potential of 9000 Ha has been created up to March 2009 and it is programmed to create
balance irrigation potential of 713 Ha. during 2008-09.

The details of target and achievement during 2007-08 and target during 2008-09 is as under:

Sl. Financial (Rs.in Crores) Physical (in hectares)


Year
No. Target Achievement Target Achievement
1) 2007-08 5.00 7.47 264 -

2) 2008-09 9.00 7.13 264 1164

INDEX

88
11.6.5. AMARJA PROJECT

Amarja irrigation project envisages construction of a dam across the River Amarja, a tributary to River
Bhima in Krishna Basin, near Sangolgi village in Aland Taluk of Gulbarga District with canals on both banks to
provide irrigation facilities to an extent of 8903 Ha. The utilisation proposed under this project is 1.554 TMC.

As per 1975-76 schedules of rates, the original cost of the project is Rs. 5.70 crores. The project was
technically sanctioned for Rs. 82.50 crores by the Chief Engineer, Irrigation Project Zone, Gulbarga vide order
dated 24.07.1992. The present cost of the project is Rs. 214.00 Crores.

DAM: The 960 m long and 31.85 m high earthen dam with a storage capacity of 43.87 Mcum will submerge
641 ha of land, affecting 3 villages and a population of 4,500. Dam works are completed and water is being
stored since 2001.

CANALS: The 54.784 Km long Left Bank Canal and the 42.48 Km long Right Bank Canal will irrigate 4,856
Ha. and 4,047 Ha. of land, respectively. The total length of right bank canal is 42.48 kms. and left bank Canal is
54.784 kms. Total number of distributaries under RBC are 29 Nos. and 20 Nos. and under LBC are 33 Nos. &
19 Nos. are respectively.

The work for the rectification of existing canal system comprising of main canal and distributaries
including construction of new FIC‟s from Km.0.00 to 7.00 of RBC of Amarja project for Rs. 538.30 Lakhs is
under progress. Further works from Km.7 to 20 is withdrawn from KLAC and fresh tenders are called for;
tenders accepted and works is entrusted to Venkob Yadav; works are under progress. Works from 20 to 42.48
kms is entrusted on tender basis for Rs. 26.00 crores, and works are under progress.

The work for the rectification of existing canal system comprising of main canal and
distributaries including construction of new FIC‟s from Km.0.00 to 30.00 of LBC of Amarja project is entrusted
on tender basis for Rs. 35.00 crores and work is in progress.

89
The details of the target and achievement of the project for 2007-08 and 2008-09 is as follows:

Financial (Rs. in Crores) Physical (in hectares)


Sl.
Year
No. Target Achievement Target Achievement
1) 2007-08 10.00 11.43 2000 350
2) 2008-09 13.00 11.04 1650 850

INDEX

90
PROJECTS UNDER

CAUVERY NEERAVARI NIGAM LIMITED

91
12 CAUVERY NEERAVARI NIGAMA LIMITED

12.1 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, IRRIGATION (S) ZONE,
MYSORE

The Cauvery Neeravari Nigama Limited (CNNL) is established by the Government of Karnataka in
03.06.2003 under Company Act 1956 as a special purpose to accelerate the implimentation of Cauvery Basin
Projects in Karnataka. The Cauvery basin in Karnataka is 34,273 Sq.Kms which constitutes about 17.99% of the
geographical area of 1,91,791Sq.Km in Karnataka Major Rivers flowing in this basin are Harangi (50 KM),
Hemavathy (245 KM), Lakshmanatheertha (131 KM), Kabini (230 KM), Shimsha (221 KM), Suvarnvathi (88
KM), Arkavathy (161 KM) and the main river Cauvery (381 KM). The Cauvery Basin has spread in 11 districts.

Main Objective of the CNNL are: to complete the works of the ongoing Irrigation projects including
Lift Irrigation works, and such works of Minor Irrigation and CADA (Command Area Development Authority).
Also to maintain, operate, improve or modernize the irrigation projects including Lift Irrigation works and such
works of Minor Irrigation and CADA in the Cauvery Basin entrusted to it by the Government of Karnataka.

Three zones viz., Irrigation (S) zone, Mysore, Hemavathy Canal Zone, Tumkur and Hemavathy Project
Zone, Gorur are coming under the jurisdiction of CNNL. The details of on going projects coming under
each zone are as below:
Sl.
Name of the Project
No
A Irrigation (S), Mysore.
1 D.D. Urs Canal
2 Kabini Project
3 Harangi Project
4 Taraka Project
5 Arkavathy
6 Chiklihole Project
7 Uduthorehalla Project
8 Iggalur Project
9 Manchanabele Project
10 K.R.S. Modernisation
11 Nanjapura LIS
12 Bannahallyhundi LIS
B. Hemavathy Canal Zone, Tumkur
13 Hemavathy Canal Project
C Hemavathy Project Zone, Gorur
14 Hemavathy Project
15 Yagachi Project
16 Huchanakoppalu LIS
17 Kamasamudra LIS
18 Kachenahally LIS
19 Votehole Project

92
12.1. 1. D.DEVARAJA URS CANAL

D. Devaraja Urs Canal project envisages construction of 126 km long Right Bank Canal from
Krishnarajasagar reservoir. Administrative approval has been accorded to the Original estimate amounting to
Rs.18.50 Crores. vide G.O. No.PWD/145/MKS/77, dtd: 23.04.1979. The work was started during 1979.
Administrative approval has been accorded to the revised estimate amounting to Rs.58.10 Crores. vide G.O.
No.PWD/145/MMR/86 dtd: 08.08.1988.

The planned utilization from this project is 10.5 TMC to create an ultimate potential of 80000 acres
(32375 ha.) with a cropping area of Khariff semidry 80000 acres and Rabi semidry 59500 acres totalling to
139500 acres. The taluks benefited by this project are Nanjangud, T. Narasipur & H.D. Kote of Mysore district
and Srirangapatna taluk of Mandya district.

The main canal work has been completed upto 126 km and the work of distributaries completed in all
respects. The water allowed upto the tail end on trail basis.

The total irrigation potential created is / 78432 acres (31741 ha.) as against the contemplated potential of
80000 acres (32375 ha.) A balance potential of 1568 acres (634 ha.) has not been created due to Urban
and industrial development and high mounds.

During 2008-09, a grant of Rs.5.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.12.14 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2008 is
Rs.449.64 Crores.
INDEX

93
12.1.2. KABINI RESERVOIR PROJECT

This project envisages the construction of a composite dam across kabini River near Beechanahally
village in H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original
estimate amounting to Rs.3.20 Crores. vide G.O. No. PWD/1/KRS/57 dated: 02.02.1959. The work was started
during 1960. Administrative approval has been accorded to the revised estimate amounting to Rs.390.00 Crores.
vide G.O. No.PWD/22/MMR/86 dtd: 24.02.1986

This project comprises of both flow and lift irrigation schemes. The planned utilization is 59.65 TMC
which comprises of 32.350 TMC in flow and 27.300 TMC in lift to create the ultimate potential of 233347 acres
(94434 ha.), which comprises of 110000 acres (44516 ha.) in flow and 123347 acres (49918 ha.) in Lift. The
taluks benefited by this project are H.D.Kote, Nanjangudu and T. Narasipura of Mysore District and Gundlupet,
Chamarajanagara, Yalandhuru and Kollegala of Chamarajanagara District.

FLOW: The Dam and allied works are completed. The Length of LBC is 26 Km. and of RBC is 202 Km. and
the potential to be created is 3000 acres (1214 ha.) and 107000 acres (43302 ha.) respectively.

The works of entire length of 26 Km. of LBC are completed. The works of entire length of 202 Km. of
RBC are completed. The lining works in vulnerable reaches to a length of 67 Km are completed. The C.C. lining
works of KRBC from Ch: 0.00 to 40.00 Km are in progress.

94
The total irrigation potential created under flow from this project since inception to the end of March
2009 is 109273 acres (44222 ha.) as against the contemplated potential of 110000 acres (44516 ha.) under flow.
A balance potential of 727 acres (294 ha.) has not been created due to mounds and village limits.

During 2008-09, a grant of Rs.40.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.17.02 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.578.82 Crores.

LIFT IRRIGATION SCHEME: Survey works of Kabini Lift irrigation scheme are completed.

INDEX

95
12.1.3 HARANGI PROJECT

This project envisages the construction of a composite dam across Harangi River near Hulugunda village
in Somawarpet Taluk of Kodagu District. Administrative approval has been accorded to the Original estimate
amounting to Rs.11.00 Crores. vide G.O. No.PWD/02/GHK/63 dtd: 14.11.1969. The work was started during
1964. Administrative approval has been accorded to the revised estimate amounting to Rs.230.00 Crores. vide
G.O. No.PWD/23/MMH/91 dtd: 19.06.1992. Further, Administrative approval has been accorded to the Re-
revised estimate amounting to Rs.545.00 Crores. vide G.O. No.PWD/14/MMH/2007 dtd: 30.07.2007.

This project comprises of both flow and lift irrigation schemes. The planned utilization is 18.00 TMC
which includes of 11.38 TMC in flow and 6.62 TMC in lift to create. The details of ultimate potential to be
created are as below.

Length of Ultimate Potential to be


Type Canals
Canal in Km. created in acres (ha.)
Flow
1 LBC 153.00 29472 (11927)
2 RBC 138.50 71323 (28863)
3 MI tanks - 2600 (1053)
Lift
1 Somwarapet LIS 10.00 1500 (607)
2 Periyapatana LIS 50.00 30000 (12141)
Total 134895 (54591)

96
The taluks benefited by this project are Hunsur, K.R. Nagara, Periyapatna of Mysore District :
Arkalgudu of Hassan District and Somawarpet of Kodagu District.
It was proposed to create an irrigation potential of 30000 acres (12141 ha) under Periyapatna LIS, 1500
acres (607 ha) under Somwarpet lift irrigation scheme and 2600 acres (1,053 ha) under Minor Irrigation. The
total potential created after the completion of these schemes is 134895 acres (54,591 ha).

FLOW: The Dam and allied works are completed. The works of entire length of 153 Km. of LBC are completed
and the works of entire length of 138.5 Km. of RBC are completed.

LIFT IRRIGATION SCHEMES: Somawarpete LIS and Piriyapatana LIS are coming under this project.
1. Somawarpete LIS: it is proposed to lift 0.800 TMC of water at 12.20 Km of LBC to create a potential of
1500 acres (607 ha.).
The head works including 10 Km long canal works are completed and commissioned.
2. Periyapatana LIS: It is proposed to lift 324.00 Cusecs of water from Karadilakkanakere tank to create a
potential of 30000 acres (12141 ha.). The utilization under this scheme is 5.82 TMC.
The head works and alied works are completed. The total length of the canal is 50 Km and the canal
works are completed. The works of Distributory 1 to 37 excluding D-16, D-17 (A) and D-26 (A) are almost
completed. The Earth work excavation and CD works of distributary 38 are nearing completion.

The total irrigation potential created including flow and lift under this project since inception to the end of
March 2009 is 131934 acres (53393 ha.) as against the contemplated potential of 134895 acres (54591 ha.). A
potential of 1891 acres (765 ha.) has not been created due to Mounds and village limits. A Balance potential of
1070 acres (433 ha.) under Periyapatana LIS is programmed to be created during 2009-10.

During 2008-09, a grant of Rs.35.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.36.12 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.528.52 Crores.

97
12.1.4 TARAKA

This project envisages the construction of a composite dam across Taraka River near Penjahally village in
H.D. Kote Taluk of Mysore District. Administrative approval has been accorded to the Original estimate
amounting to Rs.1.70 Crores. vide G.O. No.PWD/23/GIP/67 dtd: 12.04.1970. The work was started during 1970.
Administrative approval has been accorded to the Revised estimate amounting to Rs.51.00 Crores. vide G.O.
No.PWD/36/MMF dtd: 15.04.1996.

The planned utilization from this project is 3.94 TMC to create an ultimate potential of 17396 acres
(7040 ha.). H.D. Kote taluk of Mysore District is benefited by this project.
The Dam and allied works are completed. The Length of LBC is 50 Km. and of RBC is 38.50 Km. and
the potential to be created is 6000 acres (2428 ha.) and 11400 acres (4612 ha.) respectively. To augument
the short supplies in the reservoir, lifiting of 2.04 TMC water from foreshore of Kabini is done through Taraka
Lift irrigation Scheme which is completed and trail run has been conducted.

The total irrigation potential created under this project since inception to the end of March 2009 is
17396 acres (7040 ha.).

During 2008-09, a grant of Rs.1.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.2.16 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.59.26
Crores.
INDEX

98
12.1.5. ARKAVATHY PROJECT

This project envisages the construction of a composite dam across Arkavathy River a tributary to River
Cauvery near Arobele village in Kanakapura Taluk of Ramanagara District. Administrative approval has been
accorded to the Original estimate amounting to Rs.22.25 Crores. vide G.O. No.PWD/126/MMK/83 dtd:
27.06.1984. The work was started during 1983-84.

This project comprises of both flow and lift irrigation schemes. The total planned utilization from flow
and lift is 3.10 TMC.The planned potential to be creatrd is 15400 acres (6232 Ha) which includes 7500 acres
(3035 Ha) in Flow and 7900 acres (3197 Ha) in Lift. Kanakapura taluk of Ramanagara District is benefited by
this project.

FLOW: The Dam and allied works are completed. The Length of LBC is 23 Km. and of RBC is 22 Km. and the
potential to be created is 4500 acres (1821 ha) and 3000 acres (1214 Ha) respectively totaling to 7500 acres
(3035 Ha). The works for entire length of 23 Km of LBC and 22 Km of RBC are completed. Potential creatrd is
7490 acres(3031 Ha).

LIFT IRRIGATION SCHEMES: Arkavathy LBLC LIS and Arkavathy RBLC LIS are coming under this
project.
1. Arkavathy LBLC, it is proposed to lift 32.98 Cusecs of water on the foreshore of the Arkavathy reservoir
to create a potential of 3600 acres (1457 Ha) Kanakapura Taluk of Ramanagara District is benefited by this

99
project. The head works and lift canals are completed. The total length of LBLC is 21 Km. The canal works
from 0.00 Km to 10.00 Km are completed and the worksof 10.00 Km to 21.00 Km are in progress.

2. Arkavathy RBLC, it is proposed to lift 39.98 Cusecs of water on the foreshore of the Arkavathy reservoir
to create a potential of 4300 acres (1740 Ha) Kanakapura Taluk of Ramanagara District is benefited by this
project.

The total length of the RBLC is 34 Km. From 0.00 to 22.00 Km the canal works are in different stages
of progress. The process of land aquisition is in progress from 23 rd Km to 32th Km. The canal from 29.00 to 30.6
Km and from 31.7 Km to 34.475 Km are coming in the forest area. The works for head works, Jack well, process
of VT Pump, Rising main, supply and erection of transformer are under tendering progress.

The total irrigation potential created under this project since inception to the end of March 2009 is 9535
acres, (3859 Ha) from flow as against the total contemplated potential of 15400 acres (6232 Ha) A balance
potential of 5865 acres (2373 Ha) is programmed to be completed during 2009-10.

During 2008-09, a grant of Rs.20.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.11.35 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.150.70 Crores.
INDEX

100
12.1.6. CHIKLIHOLE PROJECT

This project envisages the construction of a composite dam across Chiklihole River, a tributary of River
Cauvery near Rangasamudra village in Somawarpet Taluk of Kodagu District. Administrative approval has been
accorded to the Original estimate amounting to Rs.3.40 Crores. vide G.O. No.PWD/25/GIP/71 dtd26.08.1977.
The work was started during 1978. Administrative approval has been accorded to the revised estimate amounting
to Rs.19.20 Crores.
The planned utilization from this project is 0.45 TMC to create an ultimate potential of (2137 acres) 865
ha. Somawarapet taluk of Kodagu District is benefited by this project.

The Dam and allied works are completed.

The works of new LBC for a length of 29 Km are completed including CD works.

The total irrigation potential created under this project since inception to the end of March 2007 is 2138
acres (865 ha.)

The cumulative expenditure incurred since inception upto end of 3/2007 is Rs. 19.20
Crores.
INDEX

101
12.1.7. UDUTHOREHALLA PROJECT

This project envisages the construction of a composite dam across Uduthorehalla River near Ajjipura
village in Kollegal Taluk of Chamarajanagara District. Administrative approval has been accorded to the
Original estimate amounting to Rs.7.55 Crores. vide G.O. No.PWD/60/GIP/71 dtd: 30.11.1979. The work was
started during 1979. Administrative approval has been accorded to the revised estimate amounting to Rs.32.30
Crores. vide G.O. No.PWD/134/MMK/85 dtd: 25.11.1985.
The planned utilization from this project is 1.23 TMC to create an ultimate potential of 16314 acres
(6602 ha.). Kollegala taluk of Chamarajanagara District is benefited by this project.
The Dam and allied works are completed. The Length of LBC is 10.20 Km. and of RBC is 9.10 Km.
and the potential to be created is 6200 acres (2509 ha.) and 10114 acres (4093 ha.) respectively.
The works of entire length of LBC and RBC are completed.

The total irrigation potential created under this project since inception to the end of March 2009 is
15352 acres (6213 ha.) as against the contemplated potential of 16314 acres (6602 ha.). A balance potential of
962 acres (389 ha.) has not been created due to hillocks and villages.

During 2008-09, a grant of Rs.5.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.4.88 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.225.70
Crores.

102
12.1.8. IGGALUR BARRAGE PROJECT

This project envisages the construction of a Barrage across Shimsha River near Iggalur village in
Channapattana Taluk of Ramanagara District. Administrative approval has been accorded to the Original
estimate amounting to Rs.3.42 Crores. vide G.O. No.PWD/17/GIP/71 dtd: 06.12.1977. The work was started
during 1977. Administrative approval has been accorded to the revised estimate amounting to Rs.10.75 Crores.
vide G.O. No.PWD/33/MMH/86/ dtd: 23.12.1986.

This project comprises of both flow and lift irrigation schemes. The planned utilization is 1.80 TMC.
The ultimate potential to be created is 10532 acres (4263 ha.) which comprises of 3650 acres (1477 ha.) in flow
and 6882 acres (2786 ha.) in Lift. The taluks benefited by this project are Channapatana of Ramanagara District
: Maddur and Malavally of Mandya District.

FLOW: The Barrage and flow works are completed. The Length of LBC is 35 Km. and the works for the entire
length of LBC is completed. The potential created is 3650 acres (1477 ha.)

LIFT IRRIGATION SCHEMES: 8 No. of LIS schemes are coming under this project. Out of this 5 LIS Viz.,
Point A, Point C, Point C-2, Point D and Hulikere LIS are used for lifting water on the foreshore to irrigate 6882
acres (2786 ha.).

103
In balance of 3 LIS Viz., Point B LIS is used to provide water to the atchkat of point –A where as Nittur
LIS and Garkahalli LIS are for tank feeding.

The details of 5 LIS used for irrigation pupose are as under:

Ultimate Potential to
Sl. Potential created
Name of LIS be created in acres.
No. in acres. (ha)
(ha)
1 Point A 2243 (908) 2204 (892)
2 Point C 1255 (508) 1255 (508)
3 Point C-2 1000 (405) 1000 (405)
4 Point D 1890 (765) 1890 (765)
5 Hulikere 494 (200) 371 (150)
Total 6882 (2786) 6719 (2719)

In LIFT Components: Point A, C, C-2, D LIS are completed. Potential Created is 6719 acres (2719 ha.)

The total irrigation potential created including flow and lift under this project since inception to the end
of March 2009 is 10368 acres (4196 ha.). The balance potential of 164 acre (66 ha.) has not been created due to
Mounts and village limits.

During 2008-09, a grant of Rs.5.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.2.31 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.79.35
Crores.
INDEX

104
12.1.9. MANCHANABELE PROJECT

This project envisages the construction of a composite dam across Arkavathy River near Manchanabele
village in Magadi Taluk of Ramanagara District. Administrative approval has been accorded to the Original
estimate amounting to Rs.2.37 Crores vide G.O.No. PWD/12/GIP/64 dated: 30.09.1969. The work was started
during 1969. Administrative approval has been accorded to the Revised estimate amounting to Rs.5.00 Crores
vide G.O.No. PWD/28/GIP/71, dated: 05.01.77. Administrative approval has been accorded to the Re-Revised
estimate amounting to Rs.18.50 Crores vide G.O.No. PWD/14/MMK, dated: 25.08.86.

The planned utilization from this project is 0.80 TMC to create an ultimate potential of 6012 acres
(2433 ha.). The taluks benefited by this project are Magadi and Ramanagara of Ramanagara District.

The Dam and allied works are completed. The Length of LBC is 35.00 Km. and of RBC is 36.00 Km.
and the potential to be created from these canals are 2768 acres (1120 ha.) and 3244 acres (1313 ha.)
respectively.

The works for the entire length of LBC and RBC are completed. The project is physically completed.

The total irrigation potential created under this project since inception to the end of March 2009 is 6009
acres (2432 ha.).
During 2008-09, a grant of Rs.0.10 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.0.63 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.84.93
Crores.
INDEX

105
12.1.10 KRS MODERNISATION

The Krishnarajasagar Reservoir is constructed across the River Cauvery near Kannambaadi village in
Srirangapattana Taluk of Mandya District, with Canals on both the flanks for providing irrigation to an extent of
196000 acres (79312 Hectares) to Mandya and Mysore District. The Left Bank High Level Canal, which is
named as Vishweshvaraya Canal was originally proposed for providing Irrigation to an extent of 120000 Acres
(48,564 Hectares). However, due to various factors like construction of pickup channels, lowering of local
mounds in the command area, subsequent extension of certain branch canals etc., there has been considerable
increase in the command area of Vishweshvaraya Canal. This has resulted in increased withdrawal in various
branches, causing a strain on the canal system.
Due to this the supply of water to the atchkat in the tail end reaches was inadequate. The condition of the
existing canal does not lend itself to higher discharges being drawn. Also two major Aqueducts along the canal
were not able to carry discharges beyond 67 Cumecs (2366 Cusecs). In order to limit the excess utilisation of
water in the atchkat it was programmed to modernise the Vishweshvaraya Canal and also to create fresh atchkat
of 5250 Acres (2125 Hectares).
Administrative approval has been accorded to the Original estimate amounting to Rs.14.80 Crores. The
work was started during 1987. Administrative approval has been accorded to the Revised estimate amounting to
Rs.55.00 Crores vide G.O.No. PWD/13/MMG/86, dated: 06.03.1987.

Modernization works are completed. The total additional irrigation potential created under this project
since inception to the end of March 2009 is 5250acres (2125 Ha.).

During 2008-09, a grant of Rs. 5.00 Crores has been allocated. Upto end of 3/2009, an expenditure of
Rs.6.11 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs. 420.13
Crores.

106
12.1.11. NANJAPURA LIFT IRRIGATION SCHEME

This project envisages to lift 119 Cusecs of water from Cauvery River near Nanjapura village in
T.Narasipura taluk (Bannur Town) of Mysore District to feed Turuganur Branch of Vishveshwaraia Canal.
Administrative approval has been accorded to the Original estimate amounting to Rs.28.00 Crores. vide G.O.
No.PWD/197/MMK/1996 dtd: 27.05.1997. The work was started during 1997. Administrative approval has been
accorded to the Revised estimate amounting to Rs.31.60 Crores. and technically sanctioned vide CER
No:119/1998-99.
The ultimate potential to be created is 10000 acres (4049 ha.) which comprises of the (New Potential
Created is 8000 acres (3239 ha.) and Suffering atchkat of 2000 acres (810 ha.)) The taluks benefited by this
project are T.Narsipura of Mysore District and Mallavali of Mandya District.

The scheme is completed in all respects. This Scheme is commissioned during March 2009.
The total irrigation potential created under this project since inception to the end of March 2009 is 10000
acres (4049 ha.) as against the contemplated potential of 10000 acres (4049 ha.).

During 2008-09, a grant of Rs.5.00 Crores has been allocated. Upto end of 3/2009, an expenditure of
Rs.4.03 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.55.23
Crores.

INDEX

107
12.1.12. BANNAHALLYHUNDI LIS

This project envisages to lift 0.50 TMC of water from Right Bank of Kabini River near Tayur Village in
Nanjangudu Taluk of Mysore District. Administrative approval has been accorded to the Original estimate
amounting to Rs.16.25 Crores. vide G.O. No.ID 272/MMK/97 dtd: 2.02.2001. The work was started during
2000-01.

The ultimate potential to be created is 4384 acres (1774 ha.). The taluks benefited by this project are
T.Narasipura of Mysore District and Chamarajanagara of Chamarajanagara District.
The works for Ridge Cistern, secondary Cistern and feeder Canal are completed. The works for pump
house, intake channel, forebay, Raising main and inlet canal are completed. The total length of canal is 14.86
Km. The Canal works are almost completed. This project is physical completed.

The total irrigation potential created under this project since inception to the end of Mar 2009 is 4384
acres (1774 ha.) as against the contemplated potential of 4384 acres (1774 ha.).
During 2008-09, a grant of Rs.15.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.5.66 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.13.94
Crores.

INDEX

108
12.2 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER,
HEMAVATHY CANAL ZONE, TUMKUR

12.2.1 HEMAVATHY CANAL ZONE, TUMKUR

Hemavathy Canal Zone, Tumkur, was formed as per Government order No. PWD 11 PCO 87 Bangalore,
dated 14-1-1987, for execution of canal works in Tumkur, Mandya and Hassan Districts and is functioning since
23-04-1987.This is a part of Hemavathy project for the execution of canal works viz., Y-Alignment, Tumkur
Branch canal, Nagamangala Branch Canal and Lift irrigation scheme at the exit of Baggur – Navile tunnel and
providing water supply to Tumkur and Tiptur town from Hemavathy left Bank Canal. Administrative approval
has been accorded to the Original estimate amounting to Rs.16.30 Crores. vide G.O. No.PWD/1/GKH/63 dtd:
18.09.1967 for Hemavathy Project. The work was started during 1967. Administrative approval has been
accorded to the Revised estimate amounting to Rs.3877.00 Crores. vide G.O. No.WRD/46/NHP/2007 dtd:
30.07.2007. This amount comprises of Rs.1751.00 crores towards Hemavathy Project Zone- Gorur and Rs.
2126.00 crores towards Hemavathy Canal Zone, Tumkur.

109
The canal details are as under :
Ultimate Planned
Total
Sl. Potential to be utilization in
Canal Details length in Taluks Benefited
No. created in TMC /
Km.
acres (Ha) Remarks
a) „Y‟ -Alignment. 5.50 Km - -

236990 Turuvekere, Tiptur, Gubbi,


240.00
b) Tumkur Branch Canal. (95,909) 18.07 Tumkur, Kunigal of Tumkur
Km
Distrcit

Turuvekere, Tiptur, Gubbi,


78.325 146994 Kunigal of Tumkur Distrcitl
c) Nagamangala Branch Canal. 11.19
Km (59,488) & Nagamangala in Mandya
District
13.97
C.R. Patna, in Hassan District
Lift Irrigation Scheme at the exit of (RBC) 5828
d) 0.29 and Tiputur taluk in Tumkur
Bagur – Navile Tunnel 16.25 (2,358)
District
(LBC)
Providing Water Supply to Tumkur &
e) - - 1.44.
Tiptur Town.
389812
Total 30.99
(1,57,755)

FLOW:
Y- alignment: The total length of Y alignment is 5.50 Km. Earth work and CD works completed. 2.80 Km
lining works are completed.

Tumkur Branch Canal (0-240 Km):


The total Length of Tumkur Branch Canal is 240 Km and the potential to be created is 236990 acres
(95909 ha). Out of this 240 Km., the canal alignment has been approved 200 Km. The earth work excavation &
C.D.works are completed upto 187 Km and the earth work excavation from 188Km to 194Km is under progress.
The lining works of main canal for about 175 Km is completed and further lining works are under progress.

There are 44 Distributaries. Out of which, the works of 9 Distributaries are completed and the works of
24 Distributaries are almost completed. The Distributary works from 23 to 27A (8 Nos.) are under different
stages of progress. The works of remaining 3 distributaries are yet to be started.

110
NAGAMANGALA BRANCH CANAL (0 TO 78.325 Km)

The total Length of Nagamangala Branch Canal is 78.325 Km and the potential to be created is 146994
acres (59488 ha). Out of this 78.325 Km., the earth work excavation & CD works are completed for the entire
length of 78.325 Km. except for aqueduct in KM 65 & 66 which is near in completion. The lining works of
main canal for about 29.40 KM is completed.

There are 22 Distributaries. Out of which, works of Distributary 1 to 14 (16 Nos.) are completed. The
works of Distributary 15 to 20 (6 Nos.) are under different stages of progress.

LIFT IRRIGATION SCHEME AT EXIT OF BAGUR – NAVILE TUNNEL:


It is proposed to lift 0.345 TMC of water to create a potential of 5828 acres (2358 ha.) from Y-
alignment canal at exit of Bagur- Navile tunnel near Navile village in C.R. Patna Taluk of Hassan District. The
Taluks benefited are Tiptur of Tumkur district and C.R. Patna of Hassan District.
The work of raising main, distribution chamber and jack well cum pump house are completed and this
scheme has been commissioned during February –2004.

The total length of LBC is 13.97 Km. and the works for entire length is completed. The total length of
RBC is 16.25 Km. out of which upto 9 Km. the works are completed. The works from 9 Km to 16.25 Km are
under progress and the balance works are programmed to be completed during 2009-10.

The total irrigation potential created including flow and lift under this project since inception to the end
of March 2009 is 290241 acres (117459 ha.) as against the contemplated potential of 389812 acres (157755 ha.)
and a potential of 5221 acres (2113 ha.) is programmed to be created during 2009-10.

During 2008-09, a grant of Rs. 100.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.79.92 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.1240.75 Crores.

INDEX

111
12.3 AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER,
HEMAVATHY RESERVOIR PROJECT, GORUR

12.3.1 HEMAVATHY PROJECT – GORUR

This project envisages the construction of a composite dam across Hemavathy River near Gorur village in
Hassan taluk of Hassan District. Administrative approval has been accorded to the Original estimate amounting
to Rs.16.30 Crores. vide G.O. No.PWD/1/GKH/63 dtd: 18.09.1967. The work was started during 1967.
Administrative approval has been accorded to the revised estimate amounting to Rs.3877.00 Crores. vide G.O.
No.WRD/46/NHP/2007 dtd: 30.07.2007. This amount comprises of Rs.1751.00 crores towards Hemavathy
Project Zone- Gorur and Rs. 2126.00 crores towards Hemavathy Canal Zone, Tumkur.

The planned utilization from this project is 56.67 TMC which includes the planned utilization of 30.99
TMC to Hemavathy Canal Zone, Tumkur. The balance planned utilisation available to Gorur Zone is 25.68
TMC. The ultimate potential to be created under this project are 310943 acres (125837 ha.) which comprises of
271000 acres (109672 ha.) under flow and 39743 acres (16165 ha.) under lift. The taluks benefited by this
project are Hassan, Alur, Arkalagud, Holenarsipura, Channarayapatna of Hassan District : Mandya, K.R.Pet,
Pandavapura, Nagamangala of Mandya District : K.R.Nagara of Mysore District and Somwarapete of Kodagu
District.

The Dam and allied works are completed.

112
FLOW:
The Details of Canals coming under this project are as below.
Sl. Atchkat in Acres
Name of the Canal Length
No. (Hectares)
1 Hemavathy Left Bank Canal 214 Km. 195000 ( 78,915)
91 Km
2 Hemavathy Right Bank Canal 20000 (8,094)
(Full length)
Hemavathy Right Bank High Level 106 Km
3 56000 (22,663)
Canal (Full length)
Sub-Total 2,71,000 (1,09,672)

4 LIS Schemes - 39,943 (16,179)

Total - 3,10,943 (1,25,837)

Out of 214 Km of Left Bank Canal, Earthwork excavation & C.D. works upto 212 Km are completed.
Works of all distributories are completed. The lining work is under progress.
Out of 91 Km of Right Bank Canal, Earthwork excavation & C.D. works upto 91 km are completed. The
lining work is under progress.

Out of 106 Km of Right Bank High level Canal, Earthwork excavation, C.D.works and distributaries to a
length 96 km are completed. Lining works for bed upto a length of 60 km bed and lining for sides to a length
upto 50 km are completed.

Out of the 14 LIS, 3 Lift Irrigation Schemes Viz., Ganjigere, Ramenahalli, and BNT Approach are
commissioned. LIS at the exit of Bagur-Navile tunnel has been taken up under Hemavathy Canal Zone-Tumkur.
Balance 10 LIS are in different stages of progress.

The total irrigation potential created is 307104 acres (124283 ha.) from flow and lift as against the
contemplated potential of 310943 acres (125837 ha.) It is programmed to complete all the balance works
including LIS schemes by the end of 2010-11.

During 2008-09, a grant of Rs.60.00 Crores has been allocated. Upto end of 3/2009, an expenditure of
Rs.90.41 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.1482.64 Crores.

INDEX

113
12.3.2. YAGACHI PROJECT

This project envisages the construction of a composite dam across Yagachi River a tributary of
Hemavathy near Chikkabyadagere village in Belur Taluk of Hassan District. Administrative approval has been
accorded to the Original estimate amounting to Rs.35.38 Crores. vide G.O. No.PWD/91/NHP/83 dtd:
27.06.1984. The work was started during 1984-85. Administrative approval has been accorded to the revised
estimate amounting to Rs.440.00 Crores. vide G.O. No.WRD/40/NHP/2007 dtd: 30.07.2007.

The planned utilisation from this project is 5.74 TMC to creat an ultimate potential of 37000 acres
(14973 ha.).

The details of canals coming under this project are as under:

Sl. Length in Potential to be created


Name of the Canal
No. Km in acres(Ha)
1 Yagachi Left Bank Canal 100 29085 (11832)
2 Mosale Branch Canal 10 2500 (950)
3 Kamasamudra Branch Canal 35 5415 (2191)
Total 37000 (14973)

The taluks benefited by this project are Hassan, Belur and Alur of Hassan District.

Flow: The Dam and allied works are completed

Out of 100 Km. in YLBC, the works of Earth work excavation are completed upto 82.5 Km. and EWE
from 83 Km to 100.00 Km is under progress. The CD works upto 83rd Km are completed except for the
rd

aqueduct work in 61 - 64Km which is under progress. The lining works are completed upto 24th Km and lining
works in other reachs are in progress. Out of 61 Distributaries D1 to D33 are completed. The works of balance of
28 distributaries are in different stages of progress.

Works of Mosale Branch Canal and Kamasamudra Branch Canal at the exit of the tunnel is yet to be
started. The tunnel work is under progress.
The irrigation potential created under this project since inception to the end of March 2009 is 7528
acres (3047 Ha) as against the total contemplated potential of 37000 acres (14973 Ha) A potential of 19029 acres
(7701 Ha) is programmed to be created during 2009-10.
During 2008-09, a grant of Rs.35.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.18.68 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is
Rs.262.50 Crores.

INDEX

114
12.3.3. HUCHANAKOPPALU LIS

This project envisages to lift 0.936 TMC of water in II stages from Hemavathy River near
Huchanakoppalu Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded
to the Original estimate amounting to Rs.6.90 Crores. vide G.O. No.LIS/86 dtd: 14.07.1986. The work was
started during 1985-86. Administrative approval has been accorded to the revised estimate amounting to
Rs.50.00 Crores. vide G.O. No.WRD/38/NHP/2007 dtd: 30.07.2007.
The ultimate potential to be created is 8305 acres (3361 ha.) which comprises of 3785 acres (1532 ha.)
from Ist stage and 4520 acres (1829 ha.) from IInd stage respectively. The taluks benefited by this project are
Holenarasipura and Arkalgudu taluk of Hassan District.
The works of Stage I are completed and commissioned. Regarding Stage II, the canal networks are
under progress and the head works are yet to be taken up. The project is programmed to be completed during
2009-10.
The total irrigation potential created under this project since inception to the end of March 2009 is 3788
acres (1533 ha.) as against the contemplated potential of 8305 acres (3361 ha.) A Balance potential of 4517
acres (1828 ha.) is programmed to be completed during 2009-10.
During 2008-09, a grant of Rs.15.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.1.70 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.39.47
Crores.

INDEX

115
12.3.4. KAMASAMUDRA LIS
This project envisages to lift 1.451 TMC of water in III stages from Hemavathy River near Kamasamudra
Village in Holenarasipura taluk of Hassan District. Administrative approval has been accorded to the Original
estimate amounting to Rs.0.995 Crores. vide G.O. No.PWD/180/LIS/84 dtd: 12.06.1984. The work was started
during 1984-85. Administrative approval has been accorded to the Revised estimate amounting to Rs.70.00
Crores. vide G.O. No.WRD/39/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to complete I &
II stage LIS on priority and to take up III stage LIS depending on the availability of water.
The ultimate potential to be created is 12670 acres (5128 ha.) which comprises of 2450 acres (992 ha.)
from Ist stage, 7220 acres (2922 ha.) from IInd stage and 3000 acres (1214 ha.) from III stage. The taluks
benefited by this project are Hassan and Holenarasipura taluks of Hassan District.
The details of the Canal system are as under.
Sl. Length of Canal
Stage Name of the Canal Atchkat in acres (ha.)
No in Km.
st
1 1 stage LBC 14.20 1820.00 (737)
RBC 7.00 630.00 (255)
2 2nd Stage Mallali Branch Canal 54.00 5220.00 (2113)
Nagenahalli Branch Canal 12.40 2000.00 (809)
3 3rd stage Heragu Canal & RBC 11.00 3000.00 (1214)
Total 12670 acres (5128)

The works of Stage I are completed and commissioned. In Stage II, Head works are completed and
commissioned. The Canal works of Malalli and Nagenahalli Branch Canal are in progress.
The total irrigation potential created under this project since inception to the end of March 2009 is 8048
acres (3257 ha.) as against the contemplated potential of 12670 acres (5128 ha.) A potential of 1656 acres (670
ha.) is programmed to be created during 2009-10.

During 2008-09, a grant of Rs.8.05 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.3.09 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.51.12
Crores.

INDEX

116
12.3.5. KACHENAHALLY LIS

This project envisages to lift 0.73 TMC of water in III stages from Hemavathy River near Kachenahalli
Village in Channarayapatna taluk of Hassan District. Administrative approval has been accorded to the Original
estimate amounting to Rs.8.90 Crores. vide G.O. No.PWD/1/NHP/92 dtd:27.12.1991. The work was started
during 1991. Administrative approval has been accorded during 2002 to the revised estimate amounting to
Rs.68.30 Crores. Further, Administrative approval has been accorded to the Re-revised estimate amounting to
Rs.165.00 Crores. vide G.O. No.WRD/37/NHP/2007 dtd: 30.07.2007. Approval accorded with a condition to
complete I & II stage LI Schemes on priority and to take up III stage LIS depending on the availability of water.

The ultimate potential to be created is 12600 acres (5100 ha.) which comprises of 1390 acres (563 ha.)
from Ist stage, 6610 acres (2675 ha.) from IInd stage and 4600 acres (1862 ha.) from III stage respectively. The
taluks benefited by this project are Holenarasipura, Hassan, Arasikere and Channarayapatna of Hassan District.

The details of the Canal system are as under.

Sl. Length of Canal Atchkat in


Stage Name of the Canal
No in Km. acres (ha.)
1 1st Stage Samudravalli Main Canal 1.875 1390 (563)

2 2nd Stage Dandiganahalli Branch Canal 22.50 5385 (2179)

Bijamaranahalli Branch Canal 8.00 1225 (496)

3 3rd Stage Gandsi Branch Canal 32.00 4600 (1862)

Total 12600 (5100)

In stage I the Earth work excavation of Samudravalli Main Canal is partially completed. Head works viz.,
intake canal, pump and jack well cum pump house are in progress. In stage II earth work excavation for
Dandiganahalli and Bijamaranahalli are partially completed. In III stage, survey works are completed. A
potential of 1236 acres (500 ha.) is programmed to be created during 2009-10.

During 2008-09, a grant of Rs.20.00 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.0.86 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs. 9.44
Crores.

INDEX

117
12.3.6. VOTEHOLE PROJECT

This project envisages the construction of a composite dam across Votehole River near Lakkenahally
village in Belur Taluk of Hassan District. Administrative approval has been accorded to the Original estimate
amounting to Rs.2.05 Crores. vide G.O. No. 5/GIP/64, dtd: 15.12.1971. The work was started during -1971.
Administrative approval has been accorded during 22.02.1996 to the Revised estimate amounting to Rs.38.00
Crores. Further, Administrative approval has been accorded to the Re-revised estimate amounting to Rs.59.75
Crores. vide G.O. No.WRD/47/NHP/2007 dtd: 30.07.2007.

The planned utilization from this project is 2.40 TMC to create an ultimate potential of 18500 acres
(7487 ha.). The details of Canals coming under this project are as below.

Sl. Atchkat in Acres


Name of the Canal Length in Km
No. (Hectares)
1 Left Bank Canal 10 500 (202)
2 Right Branch Canal 45 10582 (4283)
3 Nakalgud Branch Canal 15 7418 (3002)

Total 18500 (7487)

The taluks benefited by this project are Belur and Alur of Hassan District.

The Dam and allied works are completed. The Canal works are also completed physically.

The total irrigation potential created under this project since inception to the end of March 2009 is
18500 acres (7487 ha.).

During 2008-09, a grant of Rs.0.10 Crores has been allocated. Upto end of 3/2009 an expenditure of
Rs.0.66 Crores is incurred. The cumulative expenditure incurred since inception upto end of 3/2009 is Rs.60.48
Crores.

INDEX

118
PROJECTS UNDER

ZONES OF WATER RESOURCES


DEPARTMENT

119
13. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER,
IRRIGATION PROJECT ZONE, GULBARGA

13.1. KARANJA PROJECT

Karanja Irrigation project envisages construction of storage reservoir across River Karanja, tributary of
River Manjra in Godavari Basin near Byalhalli village, Bhalki Taluk of Bidar District. The gross storage
capacity of the reservoir is 7.691 TMC. The utilisation under this project is 9.27 TMC. The area covered for
irrigation under this project is 35,614 hectares.
The Revised estimated cost of the project is Rs. 522.00 Crores as per the schedule rates of 2008-09.

The Dam works comprising of earthen dam, C. C. Spillway, R.C.C. Sluices and parapet wall are
completed. Construction of is also completed.
Works of LIS in the backwaters of the dam like rising main, intake canal , pump house, cistern,
delivery chamber are completed.

CANALS: Works of left bank canal upto 31.00 kms. And right bank canal upto 124.00 km. are completed.
Works in Km. 3.00 are under progress.

The details of target and achievement of the project for 2007-08 and the target 2008-09 are as follows:

Financial (Rs. in Crores) Physical (in hectares)


Sl.
Year
No
Target Achievement Target Achievement
1) 2007-08 11.23 10.92 - -

2) 2008-09 11.57 10.78 - -

During 2008-09, central assistance of Rs.12.25 crores is availed under AIBP. Cumulative central assistance
availed for the project is Rs.189.03 crores.

INDEX

120
14. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER,
IRRIGATION CENTRAL ZONE, MUNIRABAD
Tungabhadra Project, Hirehalla Project, Maskinala Project, Singatalur Lift Irrigation Scheme,
Kanakanala Project, Narihalla Project, Hagaribommanahalli Project, Rajolibanda Diversion Scheme,
Vijayanagar Canals and other LIS comes under the Irrigation Central Zone, Munirabad. Hirehalla Project,
Maskinala Project, Singatalur Lift Irrigation Scheme projects are on-going projects. The original works of
Tungabhadra Project have been completed. But improvement/Modernisation works of Left bank canal are to be
completed.

14.1. TUNGABHADRA PROJECT

The Tungabhadra Project comprises of reservoir across the River Tungabhadra, a tributary to River
Krishna, near Mallapuram in Hospet taluk, Bellary District, with canals on both banks to provide irrigation to an
extent of 3,62,715 Ha in Bellary, Koppal and Raichur Districts. The utilisation is 3736 M.cum (133.00 TMC).
This is an inter-state multipurpose project started in 1945 as a joint venture of the then Governments of Madras
and Hyderabad. After reorganisation of States, the project became a joint venture of Mysore (Now Karnataka)
and Andhra Pradesh. The irrigation and utilisation indicated above pertain to Karnataka only.

The Dam and Canal works are completed. Originally most of the reaches of Tungabhadra Left Bank
Canal have been constructed out of available soil in the adjoining borrow areas. For the embankment sections,
since Zonal section is not provided breaches and bongas were occurring. In order to avoid frequent breaches and
bongas in the canal. Government constituted an expert committee to advice regarding strengthening of the canal.
As per the Expert Committee Report I.S. works have been taken up in stages from 1982 to 2007 with an
expenditure of Rs.205.34 Crores.
During 2008-09, an amount of Rs.50.00 crores is allocated for modernization works. Due to elections in
May 2009, modernization works were not taken up only urgent repair works were taken up. An expenditure of
Rs.208.84 crores is incurred upto end of March 2009.

MODERNISATION OF DISTRIBUTARIES OF TBLBC, TBRBLLC AND TBRBHLC


Modernisation of distributaries of Tungabhadra Project (L/S & R/S) is being taken up from 2005 to 2007
the expenditure is Rs. 40.00 crores. During 2008-09 grants of Rs. 30.00 crores was allocated for modernization
of distributaries.

Due to the election in May 2008 works could taken up but only emergent works to a tune of Rs. 3.60 crores
were taken up. Total expenditure from 2005 to 2008 is Rs. 43.63 crores. During 2009-10 grants of Rs. 70.00
crores has been allocated modernization of distributaries.
Balancing reservoir at Mile 109 of TLBC has been constructed and water is being stored in order to
supplement the tail end ayacut and to supply drinking water to Raichur city.

During 2008 closure period Govt. has allocated Rs. 50.00crores for modernization works. But due to
election held during May 2008 the works were not taken up. Hence only emergent nature of works for smooth
flow of water were taken up. The Modernisation of distributaries of TBP is being taken up from 2005 to 2007.

121
All the distributories of RB HLC have completed including Sub Distributory 16 A and Hagari bridge and
related works. From the TLBC, Irrigation potential has been created to an extent of 2,44,668 Ha, & there is no
balance to be created. From RB HLC Irrigation potential has been created to an extent of 72,443 Ha. Since
creation of Irrigation Potential is restricted to Railway line Irrigation Potential is not created beyond Railway
line. From RBHLC 37503 Ha Irrigation Potential has been created. (Total 3,54,615 Ha)
From the Tungabhadra project, an Irrigation Potential of 3,54,615 Ha. has been created up to 3/2008.

EXPENDITURE:-
Upto end of 3/2009 an expenditure of Rs.393.48 Crores has been incurred comprising Rs. 310.47 Crores
on the Left Bank High Level and Low Level Canals, Rs. 6.15 Crores on the Right Bank Low Level Canal and
Rs.76.86 Crores on the Right Bank High Level Canal. The above amount includes the expenditure of Dam also.

AN OVER VIEW OF THE TUNGABHADRA PROJECT


TUNGABHADRA LEFT BANK CANAL

1. Name of Project TUNGABHADRA LEFT BANK CANAL


2. Location Left Bank of T.B.Dam
3. Year of inception 1945
4. Year of completion Completed in stages upto 1968 (Original works)
Original cost: Rs. 17.44 Crores (Sanctioned by Nizam
Original and latest estimated cost in Crores Government in 1951)
5. Including administrative approval no. and Revised Cost: Rs. 194.40 Crores (ID 122 MTP 92 Dated:
date/Technical Sanction. 05-06-1996)
Latest cost: Rs. 302.00 Crores
Length of canal
6. a) Main canal 226.00 km
b) Distributaries 707.00 km
7. Length of ayacut roads 1150 Km
8. District benefited Raichur and Koppal
Gangavathi Tq, Sidhnoor Tq, Manvi Tq, Devadurga &
9. Number of village and Tq benefited
Raichur Taluk
No of WUCS
a) Formed 585
10.
b) Registered 244
c) Handed over 46
11. Programme during 2008-09 Rs. 357.00 lakhs
12. Progress achieved during 2008-09 Rs. 48.43 Lakhs
TUNGABHADRA RIGHT BANK HIGH LEVEL CANAL

1. Name of Project TUNGABHADRA RIGHT BANK HIGH LEVEL CANAL


2. Location Right Bank of T.B. Dam
3. Year of inception 1959
4. Year of completion 1999-2000

122
Original cost
1) Rs. 2.20 Crores (Administrative approval PWD 83 TBP
57 Dated: 14-8-59)
2) PWD 22 NTP 65 Dated: 18-9-65 For Rs.3.00 Crores
Original and latest estimated cost in (Stage-I and II)
5. Crores 3) Stage-I Technical approved No. CER 72 Dated: 16-11-
Including administrative approval no. 1996 for Rs. 1.80 Crores
4) Stage-II Technical approved No. CER/10/72 Dated: 8-8-
and date/Technical Sanction. 1972; Rs.1.20 Crores
Revised Cost: Rs. 26.00 Crores
(PWD 149 Dated: 2-3-89)
Latest Cost: Rs. 153.60 Crores. (Submitted to Government for
approval)
Length of canal
6. a) Main canal 196.34 km
b) Distributaries 171.66 km
7. Length of ayacut roads 294.55 km
8. District benefited Bellary
9. Number of village and Tq benefited Siruguppa and Bellary Tq.
No of WUCS
a) Formed 126
10.
b) Registered 81
c) Handed over 39
11. Programme during 2008-09 Rs. 70.99 lakhs
12. Progress achieved during 2008-09 Rs. 68.15 Lakhs

INDEX

123
14.2. HIREHALLA POJECT
The Hirehalla Project comprises of a reservoir across the Hirehalla, a tributary to the River Tungabhadra
near Kinnal village in Koppal Taluk of Koppal District, with canals on both banks, to provide irrigation to an
extent of 8330 Ha in Koppal Taluk. The proposed utilisation is 64.24 M.Cum (2.27TMC). Administrative
approval to the project amounting to Rs. 6.35 Crores has been accorded vide G.O.No.PWD 164 MTP 73, dated:
24-5-1979 and the latest estimated cost of the project for Rs. 272.00 Crores is under preparation.

DAM AND CANALS

DAM: The length of the dam is 3.6 Km, with a height of 15mtr having a storage capacity of 47.23 M.Cum. The
submergence area is 1247 Ha, affecting Arakera village with a population of 1500 and rehabilitation work is
taken up.

CANALS: 24.60 Km. long Left Bank Canal and a 25.00 Km. long Right Bank Canal will provide irrigation to
5000 Ha and 3330 Ha, respectively.

COST: The project had been originally estimated at a cost of Rs.635.00 lakhs at 1977-78 levels of rates. The
latest cost of project is Rs.272.00 Crores.

STAGE OF WORK

DAM: Earthen embankment is completed. Spillway work including installation of 6 radial gates is completed.
Water is stored to the full capacity. The project was dedicated to the nation on 26-12-2001 by the then Hon‟ble
Chief Minister of Karnataka.

CANALS AND DISTRIBUTARIES:

1) RBC: Out of a total length of 25Km, works in respect of 22.30 Km are completed. Out of 37 distributaries,
33 Nos are completed and balance of 4 Nos is under progress.

2) LBC: Works of the entire canal length of 24.60 Km are completed. Out of 27 Distributaries, 26 Nos are
completed and balance 1 is under progress.

National Highway crossing under Dy. No. 17 are yet to be taken up by the concerned department.

REHABILITATION WORKS: Rehabilitation work of Arakera village is completed. For rehabilitation for
Mudlapur, Veerapur, Sirur and Muttal, an amount of Rs. 12.78 crores is deposited to Revenue Department, land
acquisition is under process.

So far an irrigation potential of 8116 Ha. has been created, out of total atchkat of 8330 Ha. Balance 214
Ha. is planned to be created during this year.

EXPENDITURE: Expenditure incurred during 2008-09 is Rs. 353.80 Lakhs. Cumulative expenditure upto
3/2009 is Rs. 23074.65 Lakhs.

124
AN OVER VIEW OF THE HIREHALLA PROJECT

1 Name of Project Hirehalla Project


Across Hirehall and Veerpurhalla 4 Km U/s of Kinnal
2 Location
village.
3 Year of inception 1979
Original cost: Rs. 6.35 Crores.
Original and latest estimated cost in Crores. PWD 164 MTC 73 Dated 24-5-1979
4. Including administrative approval no. and Revised cost: Rs. 272.00 Crores.
date (Administrative approval to be obtained from
Government)
Length of canal
LB- 24.60 Km;
a) Main canal
RB- 25 Km
5. b) Distributaries 63 Km

c) Branch canal 15 Km

d) FIC Under progress

6. Length of ayacut roads 65 Km

7. District benefitted Koppal

8. Number of village and Tq benefited Kinnal

No of WUCS

9. a) Formed 7

b) Registered 3

10. Programme during 2008-09 Rs. 383.73lakhs


Progress achieved during 2008-09 upto
11. Rs. 376.93lakhs
3/2009.

Details of Irrigation Potential in Ha

Sl. Name of On full Programme during Created during Total potential created
No District development 2008-09 2008-09 upto 3/2009
1. Koppal 8330 214 0 8116

INDEX

125
14.3. MASKINALA PROJECT
BRIEF DESCRIPTION:
The Maskinala Project comprises of a reservoir across the Maskinala, a tributary to River Tungabhadra,
near Maraladinni Village in Lingasugur taluk of Raichur District, with canals on both banks, to provide
irrigation to an extent of 3001 Ha in Lingasugur taluk. Administrative approval has been accorded to the Project
for Rs.311.00 lakhs. Revised administrative approval has accorded for Rs. 2357.00 lakhs. The latest revised cost
of the project is Rs. 4835.00 lakhs.

DAM & CANALS


DAM: Dam is 814 m long (spillway length being 57 m) and 23.74 m high above the nala bed level with a gross
storage capacity of 13.11 M.cum with submergence to an extent of 173 Ha without affecting any village.

CANALS: All the works of main canals on either side are completed. Irrigation potential capacity is 1940 Ha
under LBC and 1061 Ha under RBC, total from the project being 3001 Ha
COST: The project had been originally estimated to Rs. 311 lakhs at 1975-76 level of rate. The revised cost of
the project is has been administratively approved for Rs. 2357.00 lakhs and the latest revised cost of the project
is Rs. 4835.00 lakhs.

EXPENDITURE: Expenditure incurred during 2008-09 is Rs. 102.89 Lakhs. Cumulative Expenditure up to
3/2009 is Rs. 4968.66 Lakhs.
The project is completed. Contemplated irrigation potential of 3001 ha.is already created.

Expenditure
Upto 03/2008 Rs.4865.77 lakhs

During 2008-09 Rs.102.89 lakhs

Cum. Exp. Upto 3/2009 Rs.4968.66 lakhs

INDEX

126
AN OVER VIEW OF MASKINALA PROJECT

1 Name of Project MASKINALA PROJECT


2 Location Near Maraladinni village of Lingasugur Tq.
3 Year of inception 1976
Original and latest estimated cost in Original cost: Rs. 3.11 Crores.
Crores. G.O. No.PWD 52 GIP 78 Dated: 22-01-1979
4
Including administrative approval no. Revised cost: Rs. 48.35 Crores. (Administrative approval to
and date be obtained from Government)

Length of canal LBC RBC

a) Main canal 10 Km 11.50 Km


5
b) Distributaries 27 Km

c) FIC Under progress

6 Length of ayacut roads 1 Km

7 District benefited Raichur

8 Number of village and Tq benefited 1 No. Lingasugur

No of WUCS

9 a) Formed 5

b) Registered 5

10 Programme during 2008-09 Rs. 123.24lakhs

Progress achieved during 2008-09 up to


11 Rs. 102.89Lakhs
3/2009.

The project has been completed

INDEX

127
14.4 OTHER WORKS (NEW)
(Rs. in Lakhs.)
Cumula
tive
Expendi
Expendi
Sl. Name of the Latest Grant for ture Likely date of Present Stage of
ture Irrigation Potential in Ha
No. Project Cost 2008-09 during completion Project
upto
2008-09
March
2009
1 2 3 4 5 6 7 8 9

1 Kolur (D-13) LIS 74.00 24.37 18.42 86.99 Completed Stabilization of 324 Ha of Kolur Completed
branch of D-13 of RBHLC

2 T.S. Kadlur LIS 135.00 40.49 30.49 143.89 Completed Stabilization of 410 Ha of 8 TE Completed
of T.S. distributory of RBHLC

3 Raravi LIS 67.00 47.54 6.27 56.27 Completed Stabiilization of 210 Ha of 7 TE- Completed
1 of Kote hall distri. of RBHLC

4 Kolur (D-7) LIS 394.00 43.52 47.77 213.50 Completed Stabilization of 1518 Ha of tail
Completed
end of distry No. 7 of RBHLC

Hagari D/S (D- Stabilization of 1214 Ha of tail


5 90.00 72.54 110.99 124.60 Completed end of Hagari Aqueduct D/S of Completed
16) LIS
D- 16 A

6 Katharaki LIS 58.00 12.91 9.25 59.63 Completed Stabilization of 182 Ha Sub Completed and yet to be
distributory 89/8/1&2 of TLBC commissioned
Boylmerched Stabilization of 479 Ha Sub distri.
7 73.00 12.91 8.71 37.09 Completed Completed
LIS 89/7 of TLBC
Jackwell, transition
completed. Balance
8 Y Kaggal LIS 1167.00 46.00 16.74 271.72 - 6643 Ha work estimates & DTP
are to be approved by
TAC
Modified drainwall DTP
9 Wala Bellary LIS 594.00 350.00 - - - 2541 Ha submitted to Govt. for
approval.

10 Jalibenchi LI 245.00 214.86 163.02 163.02 - Stabilisation of 123 Ha of tail end


Work under progress
Scheme of DP-36 of RBHLC

INDEX

128
15. AN OVERVIEW OF PROJECTS UNDER THE CHIEF ENGINEER, UPPER
TUNGA PROJECT ZONE, SHIMOGA

15.1 BHADRA PROJECT CIRCLE


Bhadra Project Circle is functioning at B.R.Project in Bhadravathi taluk, since 07.11.1969. This Circle
is under the control of the Engineer-in-Chief, KNNL, Upper Tunga Project Zone, Shimoga
Three Divisions, namely Executive Engineer, No.3, Canal Division Malebennur; No.4 BRLBC Division,
Bhadravathi & No.5 Canal Division, Davanagere and fifteen Sub-Divisions comes under the Jurisdiction of this
Circle.
The following Projects come under the Jurisdiction of this Circle.

I. Major Irrigation Project


1) Bhadra Reservoir Project
2) Vanivilas Sagar Project

II. Medium Irrigation Project


1) Gondi Anicut Project {Bhadra Anicut}
2) Jambadahalla Reservoir Project
3) Feeder Canal to Ranikere Tank Project
4) Gayathri Reservoir Project
5) Ambligola Reservoir Project
6) Thimmapura Lift Irrigation Scheme
7) Anjanapura Project
8) Dharma Project
9) Tunga Anicut Project
10) Kaduvinabylu Project
11) D.B.Kere Pickup
III. TANKS
1) Sulekere tank (Shanti Sagar).
2) Bheemasamudra tank
3) Asundi tank
4) Madaga Masur tank

INDEX

129
15.1. BHADRA RESERVOIR PROJECT

Bhadra Dam is constructed across River Bhadra near Lakkavalli village, Tarikere Taluk, Chikamagalur
District. This project is a Multi-purpose Project providing Irrigation facility to an extent of 1,05,570 Ha and a
power generation capacity of 39.20 M.W.

The major works under the Bhadra reservoir project are completed. The water is allowed through the
both canals since 1965 and irrigation facility to the total extent of 1, 05,570 Ha. is already achieved.

The details of canals coming under this project is as follows.


Sl. No. Canal Length in Km Atchkat in Ha
1. Bhadra Right Bank Canal 103.00 17109
2. Bhadra Left Bank Canal 77.00 8270
3. Anveri Branch Canal 67.00 6514
4. Malebennur Branch Canal 48.00 23774
5. Davanagere Branch Canal 90.00 30286
6. Harihara Branch Canal 20.40 15337
7. Devarabelakere Pickup Canal 59.20 4280
Total: 464.60 1,05,570

Bhadra Project is allocated 61.70 TMC of water as per KWDT. Under the Project, Irrigation potential of
1,05,570 Ha has been achieved in 1989. The revised cost of the project was 33.53 Crores and Re-revised cost
of estimate is Rs. 170.00 Crores.

Modernisation of Bhadra Reservoir Project Canals: -

Modernisation of canal system of Bhadra reservoir project comprises of providing CC lining to sides and
bed of main canal, distributaries and minors. It also includes strengthening / reconstruction of the structures like
aquaducts, super passages, bridges cover ducts and other structures coming in main canal and distributaries.

The Bhadra modernisation works were taken up in 25 packages during 2007. The administrative
approval for the modernisation of canal systems of Bhadra reservoir amounting to Rs. 951.00 crores was
accorded by Government vide G.O. No. WRD 20 MBI 2008, Bangalore dated 26.02.2008. The DPR was
submitted to Central Water Commission and approval has been obtained from Planning Commission,
Government of India.

Modernisation of canal systems of Bhadra reservoir is receiving central assistance under Hon‟ble Prime
Ministers Special Rehabilitation package.

Grant allocated for modernisation of Bhadra canal during the year 2008-09 is Rs.27121.00 and an
expenditure of Rs. 18385.00 lakhs has been incurred upto the end of March-2009.

INDEX

130
15.2. MODERNISATION OF CANAL SYSTEM OF TUNGA ANICUT

Modernisation of Tunga canals amounting to Rs. 211.00 crores is prepared and submitted for
administrative approval. Modernisation works of Tunga canal systems has been entrusted by Government to
Karnataka Neeravari Nigam during 2007-08. No grant has been allotted for Modernisation of Canal system of
Tunga Anicut Project during the year 2008-09. The cumulative expenditure incurred on this project up to end of
March 2009 is Rs. 443.65 Lakhs.

131
15.3. HODIRAYANAHALLA DIVERSION SCHEME

Jambadahalla Reservoir is located near Duglapura village, Tarikere Taluk, Chikkamagalore district. This
project was contemplated to provide irrigation to 2428 Ha.

But due to less flow only 1133 Ha of land under right bank is being irrigated. Remaining 1295 Ha of
land is to be irrigated by diverting supplement water from Hodirayanahalla, an adjacent valley to Jambadahalla.
Addition to this, 243 Ha Land will also be benefited by this scheme. Administrative approval for the above said
Hodirayanahalla diversion Scheme is accorded by the Government dated: 10.08.1987 for Rs. 248.00 lakhs.
About 12.98 Ha of land comes under the jurisdiction of forestland. Clearance has been obtained by Central
Forest & Environment Ministry.

Survey and investigation of Hodirayanahalla diversion scheme has been conducted on tender basis
through private consultancy services as per the administrative approval obtained from the Government
amounting to Rs. 35.00 lakhs.

During 2008-09, a grant of Rs. 78.00 Lakhs is allocated. The expenditure incurred up to the end of
3/2009 is Rs. 15.71 lakhs. The expenditure incurred on the project for preliminary survey and investigation
including payment made to Forest Department for release of forest land up to the end of March 2009 is Rs.
152.90 lakhs.

INDEX

132
15.4. MODERNISATION OF CANAL SYSTEM OF AMBLIGOLA RESERVOIR

During 2008-09, Government has allotted Rs. 335.00 Lakhs grants for this project for improvements and
modernization of canal system. The works includes improvements, strengthening, and reconstruction of canal
structures and lining of canals. An expenditure of Rs. 335.00 lakhs has been incurred during 2008-09 up to end
of March 2009.

A grant of Rs. 20.00 lakhs has been allotted during 2008-09 for improvements of 7 tanks coming under
this project. The works include strengthening of tank bund, silt removal, providing revetment, lining to canals
and repairs to sluice. An expenditure of Rs. 116.22 lakhs has been incurred up to end of March 2009.

INDEX

133
15.5. MADAGA –MASUR TANK

Madaga Masur Tank is a very old tank located in Haveri District in Hirekerur Taluk, across River
Kumudvathi. 2855 Ha of Land is irrigated under this tank. This tank is very old constructed during
Vijayanagara dynasty. LBC of this tank is 14.00 Km long and RBC is 37.00 Km Long. Improvements and
repairs to embankment, canal works, and removal of silt have to be taken up. Rs. 100.00 Lakhs is allotted in the
budget during 2008-09 for improvements of this tank. Modernisation of Madaga Masur Tank canal systems are
taken up on tender basis and works are under progress. The expenditure incurred during the year 2008-09 up to
the end of 3/2009 is Rs. 119.00 Lakhs. Cumulative expenditure incurred up to end of March 2009 is Rs. 470.85
lakhs.

INDEX

134
15.6. ERM OF BHEEMASAMUDRA TANK

Bheemasamudra tank has been constructed 500 years ago in Bheemasamudra village, Chitradurga Taluk,
Chitradurga district. The storage capacity of the tank is 0.905 TMC. The Irrigation potential created under this
tank is 1235 Ha (3050 Acres). The tank has left Bank canal and right Bank canal and distributary system. The
total length of canal is 68 Km.

At present the Bheemasamudra tank is filled up with silt since the tank is 500 year old. Due to this, the
storage capacity of tank is reduced to 0.18 TMC. The catchment area of tank has scanty rainfall.

In order to augument the inflow in to the tank it is proposed to construct feeder canal from
Bettadanagenahalli and Jogerahalla dams by constructing pickup. Works are entrusted on tender basis and are
under progress. The grant allotted for the year 2008-09 for this project was Rs. 50.00 Lakhs. The project is
included under Prime Minister‟s special rehabilitation package and Government has accorded administrative
approval for Rs. 400.00 lakhs and technical sanction to the estimate is awaited.

INDEX

135
15.7. MODERNISATION OF CANAL SYSTEM OF GONDI ANICUT (BHADRA)

Modernisation of Gondi canals amounting to Rs. 84.50 crores is prepared and submitted for
administrative approval. Modernisation works of Gondi canal systems has been entrusted by Government to
Karnataka Neeravari Nigam during 2007-08. No grant has been allotted for Modernization of canal system of
Gondi Anicut during 2008-09. The cumulative expenditure incurred on this project up to end of 3/2009 is Rs.
378.02 Lakhs.

15.8. KADUVINABYLU LIFT IRRIGATION SCHEME

Kaduvinabylu Lift irrigation Scheme is located in N.R.Pura taluk, Chikkamagalore District. The Project
has been administratively approved by the State Government vide G.O.No.WRD 223 MMB 2004 Bangalore
dated 10.5.2005 for Rs. 690.00 Lakhs. The Master plan committee has allocated 0.21 TMC of water to this
project under Krishna scheme- A. The Chief Engineer, KNNL, Upper Tunga Project Zone Shimoga,
technically sanctioned the estimate amounting to Rs.690.00 Lakhs, Vide CER No.83/2005-06 dated. 29.9.2005.

During the year 2008-09, a grant of Rs. 156.00 Lakhs has been allotted and no expenditure is incurred
till date.

15.9. THIMMAPURA LIFT IRRIGATION SCHEME

The scheme envisages providing irrigation facility to an extent of 4176 Acres (1691 Ha) of land
coming under the villages of Kanavelli, Bharadi, Kurugunda and Basapura of Haveri taluk (this includes 159.00
Acres of suffering atchkat under Kannavalli tank). The revised estimated cost is Rs.2313.00 Lakhs. Grant of
Rs. 90.00 Lakhs is allotted in the year 2008-09 and no expenditure is been incurred during the current year.
NABARD assistance to this project has been rejected.

15.10. ANJANAPURA RESERVOIR PROJECT

Anjanapura Reservoir project is constructed across Kumudawathi River in Anjanapura village in


Shikaripura taluk, Shimoga District. The area irrigated is 6736 Ha. The original estimated cost of the project
was Rs. 27.68 Lakhs. The right bank canal runs for a length of 45.00 Km. and has an irrigation potential of
5919 Ha The Left bank canal runs for a length of 14.00 Km. and has an irrigation potential of 817 Ha.

Erection of automatic godbole gates on the spillway of the reservoir has been completed during 2006 and
water in the reservoir is stored for extra height of 1 meter.

Improvements to canal system:

NABARD grant of Rs. 1500.00 Lakhs is allotted during 2008-09. Works are taken up on tender basis.
The expenditure incurred upto end of 3/08 is Rs. 681.98 Lakhs. Additional grant allotted is Rs.10.00 crores.
Tender process is under progress.

Improvements of 13 tanks under the atchkat Anjanapura project:

Grant of Rs. 150.00 Lakhs is allotted during 2008-09 for improvement of 13 tanks coming under this
Project. Works are taken up on Tender basis. The expenditure incurred upto the end of 3/2009 is Rs. 535.24
Lakhs.

INDEX

136
16. COMMAND AREA DEVELOPMENT PROGRAMME
Agriculture is the backbone of Indian Economy and it is the pillar of the Economic development. At the
commencement of the Fifth Five Year Plan (1974-80), in pursuance of the policy of the Government of India,
the Command Area Development Programme was launched in the State for integrated and comprehensive
development of the Command Areas of Major and Medium Irrigation Projects. As per the objectives laid down
by the National Commission on Irrigation, 1971 and the National Commission on Agriculture, 1976, the CADP
ensures rapid and optimum utilization of Irrigation Potential created under Major and Medium Irrigation
Projects thereby increasing the agriculture production as also reducing the gap between the potential area
created and the actual area utilised.

THE OBJECTIVES
Irrigation Management is a multi-disciplinary activity involving major department like Irrigation,
Agriculture, Cooperation and other organization engaged in training and research activities. Against this
perspective, CADA was constituted in the year 1970 to work as a catalyst between the various organizations to
reduce the gap between irrigation potential created and utilized, to increase production per unit of water and
land, to reduce the loss of irrigation water in the conveyance system, to improve its efficiency at the farm level
and to ensure equitable distribution of water. The objectives of the CADA, as envisaged under section 10 of the
Karnataka Command Areas Development (K.C.A.D.) Act 1980, are listed below:

To formulate and implement schemes for the Comprehensive Development of the Command Area;

To prevent land erosion and water logging;

To improve soil fertility and regulation of cropping pattern;

To ensure the efficient maintenance of Field channels and Field Drains by the Farmers within the
Command Area;

Localisation and de-localisation of lands for various crops;

Ensuring supply of all inputs and services;

Promotion and setting up of rural growth centres for integrated development of the Command Area;

Development of marketing, processing and storage facilities and adequate communication system;

Arranging for credit facilities to the farmers and artisans;

Organizing agricultural Co-operatives and Associations;

Construction of Field channels and connected drains;

To borrow and lend money necessary for the due discharge of its functions;

Conjunctive use of surface and ground water;

To determine the payment of compensation as provided in sub section [4] of section 12 of KCAD Act
1980;

137
To setup agricultural demonstrations farms and promote extension activities; and

To execute such other acts, consistent with the provisions of this Act.

The Six CADA’S that are established in Karnataka are:

 Malaprabha and Ghataprabha Projects, Belgaum

 Tungabhadra project, Munirabad

 Upper Krishna projects, Bheemarayanagudi

 Cauvery basin projects, Mysore

 Bhadra project, Shimoga

 Irrigation Project Zone, Gulbarga

BRIEF DETAILS OF CADA

Sl. Name of CADA with Year of Irrigation


Districts covered
No. headquarters Starting Projects
Malaprabha and
Malaprabha & Belgaum, Dharwad,
1 Ghataprabha Projects, 1974
Ghataprabha Bagalkot, Gadag
Belgaum
Tungabhadra Project, 1974 Tungabhadra, Hirehalla, Bellary, Raichur &
2 Munirabad 12.11.1979 Maskinala Koppal.
Upper Krishna Projects, 1977 Gulbarga, Bijapur,
Upper Krishna
3 Bheemarayanagudi 11-12-1979 Raichur & Bagalkot.
Kabini, Harangi, Hemavathy, Mysore, Kodagu,
KRS. , Nugu, Taraka, Gundal, Chamarajnagar,
Cauvery Basin Projects, 1974
4 Votehole, Marconahally, Hassan, Mandya,
Mysore 1.3.1974
Manchanabele, Kanva and Tumkur,
Byramangala. Bangalore(Rural)
Shimoga,
5 Bhadra Reservoir Project,
1979 Tunga, Bhadra & Gondi Chikkamagalore,
Shimoga
Davangere.
Chandrampalli, Hattiguni,
Irrigation Project Zone, Soudagar, Upper Mullamari,
6 2000 Gulbarga, Bidar
Gulbarga Amarja, Bennethora, Bhima,
Gondorinala, Kagna, Karanja

138
MALAPRABHA AND GHATAPRABHA PROJECTS, BELGAUM

Command Area Development Authority, Malaprabha and Ghataprabha projects, Belgaum, came into
existence during 1974-75.

During 2008-09, the budget allocation is Rs. 1401.67 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 709.55 lakhs has been incurred.

TUNGABHADRA PROJECT, MUNIRABAD

Command Area Development Authority, Tungabhadra project, Munirabad, came into existence during
1974.

During 2008-09, the budget allocation is Rs. 1243.50 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 1015.99 lakhs has been incurred.

UPPER KRISHNA PROJECTS, BHEEMARAYANAGUDI

Command Area Development Authority, Upper Krishna projects, Bheemarayanagudi, has come into
force since 11-12-1979.

During 2008-09, the budget allocation is Rs. 1300.91 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 639.20 lakhs has been incurred.

CAUVERY BASIN PROJECTS, MYSORE

Command Area Development Authority, Cauvery basin projects, Mysore, came into existence during
1974-75.

During 2008-09, the budget allocation is Rs. 1402.95 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 941.63 lakhs has been incurred.

BHADRA PROJECT, SHIMOGA

Command Area Development Authority, Bhadra project, Shimoga, came into existence during 1979.

During 2008-09, the budget allocation is Rs. 1556.10 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 952.99 lakhs has been incurred.

IRRIGATION PROJECT ZONE, GULBARGA

Command Area Development Authority, Irrigation Project Zone, Gulbarga, came into existence during
2000-01.

During 2008-09, the budget allocation is Rs. 1281.20 lakhs (under head 2705 & 4705) out of which an
expenditure of Rs. 1123.11 lakhs has been incurred.

139
The details of the Physical programme & Progress and Financial Programme & progress for
the year 2008-09 up to the end of 3/2009

(Physical in hectares) (Financial Rs. in Lakhs)


Field
Sl. Field Drains Warabandi
Name of the CADA’s Irrigation channels
No.
Program Progress Program Progress Program Progress

H/A 2705

Tungabhadra Project, P 1320 1622 1250 2021 - -


1
Munirabad F 132.00 103.59 50.00 73.22 - -

Malaprabha and P 13301 1865 6700 5448 - -


2 Ghataprabha Projects,
Belgaum F 1995.24 251.89 268.00 141.20 - -

Upper Krishna Projects, P 20000 18366 5000 1148 22667 7987


3
Bheemarayanagudi F 3000.00 2548.06 200.00 45.94 68.00 23.96

Cauvery Basin Projects, P - - 1000 523 500 200


4
Mysore F - - 40.00 20.91 2.00 0.80

Bhadra Reservoir P 24670 4518 5000 4021 - -


5
Project, Shimoga F 3700.50 451.79 200.00 160.77 - -

Irrigation Project Zone, P 8553 757 10859 10859 - -


6
Gulbarga F 761.00 100.89 434.36 434.36 - -

H/A 4705 (Special Development Plan)

Tungabhadra Project, P - - 2495 1067 - -


1
Munirabad F - - 99.78 17.69 - -

Malaprabha and P - - 1899 - - -


2 Ghataprabha Projects,
Belgaum F - - 76.00 - - -

Upper Krishna Projects, P - - 6205 800 - -


3
Bheemarayanagudi F - - 248.21 31.08 - -

Cauvery Basin Projects, P 1785 65 750 450 - -


4
Mysore F 134.02 4.70 30.00 17.98 - -

Bhadra Reservoir P 940 - 1575 - - -


5
Project, Shimoga F 94.00 - 63.00 - - -

140
Irrigation Project Zone, P - - 9500 8067 - -
6
Gulbarga F - - 380.00 322.67 - -

INDEX