Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
Manila

MAR 0 5 2019'
DEPARTMENT ORDER ) SUBJECT: Cost Estimation Manual for High
Rise Buildings
NO. 28 ~
)
Series of ~Ol~ Cl3.II'. {i

In line with the Department's Quality Policy to implement projects at the right cost, all
Implementing Offices are hereby directed to adopt the herein Cost Estimation Manual For
High Rise Buildings in the determination of unit cost of Pay Items of Work involved in the
construction and repair/retrofitting of high-rise building projects.

This Manual aims to enhance the technical capability of DPWH engineers in the preparation
and review of Program of Works (POW) and Approved Budget for the Contract (ABC) and to
establish consistency in the format of preparation and serve as a uniform basis/reference in
the derivation of unit cost for each item of work. It shall be distributed to all concerned
offices of the Department and uploaded in the DPWH Intranet.

This Order shall be consistent with the implementation of D.O. No. 163, Series of 2015
"Standard Forms of Program of Works (POW) and Approved Budget for the Contract (ABC)"
with modification on its format and description of item number and scope of works (Annex
A) to conform with the DPWH Standard Specifications for Public Works Structures, Volume
III (Buildings, Ports and Harbors, Flood Control and Drainage Structures and Water Supply
Systems) and Standardized Pay Items of Work for Buildings as embodied in D.O. 143/
Series of 2017.

This Order shall take effect immediately.

~~
MARK A. VILLAR
-
Secretary

6.1.3 ECG/AMD/WRO
Departtrent of Public Works and Highways
Office of the Secretary

1111111111111111111111111111111111111
WIN9W02111
2019

Bureau of Construction

Cost Estimation Manual


for High Rise Buildings

Department of Public Works and Highways


COST ESTIMATION MANUAL FOR HIGH RISE BUILDINGS or

TABLE OF CONTENTS

FOREWORD ------------------------------------------------------------------------------------------------------------------------
ii i

DEFINITION OF TERMS -----------------------------------------------------------------------------------------------------


v iii

UNITS, ABBREVIATIONS AND ACRONYMS-----------------------------------------------------------------


i v
PREFACE------------------------------------------------------------------------------------ vivii

INTRODUCTION-----------------------------------------------------------------------------------------------
viii1

GENERAL NOTES----------------------------------------------------------------------------------------------
i 3

A. COST ESTIMATION PROCESS ---------------------------------------------------------------------------------------------


15

B. STANDARD DETAILED UNIT PRICE ANALYSIS (DUPA) SHEETS ----------------------------------


6 13

B.1 Summary Table of Items of Work and Description ------------------------------------------------------


7 15
Part A - Earthworks --------------------------------------------------------------------------------------------
1626
Part B - Plain and Reinforced Concrete Work -------------------------------------------------------------------------
6737
Part C - Finishing----------------------------------------------------------------------------------------
7641
Part D - Electrical ----------------------------------------------------------------------------------------------
133
187
Part E - Mechanical --------------------------------------------------------------------------------------------------------
1 237
B.2 Derivation of DUPA Cost Sheet----------------------------------------------------------------------------------------
1 257

C. COSTING OF SUPPORT EQUIPMENT -----------------------------------------------------------------------------------


1 259

D. CALCULATION OF CYCLE TIME FOR HAULING EQUIPMENT -----------------------------------------


243
263

D.1 Estimated travel speed, loading/unloading time & allowance for delay ----------------------------------
244
265
D.2 Formula for the calculation of dump truck travel time ---------------------------------------------------------
244
265
D.3 Computation of cycle time ----------------------------------------------------------------------------------------
244
265

E. COMPUTATION OF LABOR RATES ---------------------------------------------------------------------------------


245
264

E.1 Basis of Computation --------------------------------------------------------------------------------------------


246
265
E.2 Condition for the usage of the labor rates ------------------------------------------------------------------------
246
265
E.3 Sample tabulation of labor rates for NCR --------------------------------------------------------------------------
247
265
F. EQUIPMENT RENTAL RATES ---------------------------------------------------------------------------------------------
248
269
FOREWORD

Aligned with the current administration's "Build, Build, Build" program and consistent with its
commitment to excellence, the Department of Public Works and Highways (DPWH) has

continuously formulated and developed guides and techniques in various fields of the
construction process. This is to ensure the highest standards of its outputs at the right cost.

This Cost Estimation Manual for High Rise Buildings provides Standard Cost Sheets for pay
items of work used in high-rise building construction in accordance with the DPWH Standard
Specifications for Public Structures (Volume III). This manual was purposely developed to
provide uniform reference/basis in unit cost estimation and in the preparation of Program of
Works (POW) and Approved Budget of Contract (ABC) for future projects of the Department.

~R~<::"'-----
Secretary
Department of Public Works and Highways
Office of the Secretary

1111111111111111111111111111111111111
WIN9W02111
DEFINITION OF TERMS

Program of Works (POW)

- is the total estimated cost of the project which covers the Civil Works Cost,
Engineering Supervision and Administrative Overhead, Road Right-of-Way Acquisition Cost,
Construction Contingency, etc. The POW shall include information about the project location
and limits, quantity and unit cost for each item of work, construction duration, funding
source, equipment requirements, etc.

Approved Budget for the Contract (ABC)

- is the total estimated agency estimate (direct cost, indirect cost and tax) for civil
works contract of infrastructure projects, wherein it is the ceiling of award of contract for
government locally-funded projects and reference for comparison of bid costs of contractors
for both locally-funded and foreign-assisted projects.

Detailed Unit Price Analysis (DUPA)

- is the determination of reasonable unit cost of each item of work which reflects the
breakdown showing the quantities of work items, unit prices of materials, equipment rental
rates, labor rates and DPWH-prescribed indirect costs including taxes.

Standard Labor Rates

- are matrices prepared and issued by Department of Public Works and Highways
(DPWH) periodically showing the required compensation for manpower workforce of
different categories, which comprises the minimum wage as approved by the NWPC, DOLE
plus the monetary benefits.

ACEL Guidebook 2014

- is a guidebook where rental rates of commonly used equipment for infrastructure


projects are based. It is published by Association of Carriers and Equipment Lessors, (ACEL)
Inc..

Construction Materials Price Data (CMPD)

- is a compilation of unit prices of construction materials updated quarterly per


District Engineering Office to be used as reference in the pricing of materials component of
the pay items of work in the preparation of DUPA, ABC & POW, including new items of work
involved in a VO.

iii
DPWH Standard Specifications for Public Works and Highways

- commonly called as “Blue Book”, is a compilation of detailed descriptions of work


items in constructing public works and highways projects such as roads, bridges, buildings,
etc. In other words, a compilation of specifications of standard works acceptable to the
DPWH.

- is composed of specifications containing detailed description of the workmanship,


material requirements, technical dimensions, materials proportion, datum lines and grades
and other established references to follow or adhere to, e.g. AASHTO, ASTM, etc.; basis of
measurement, payment and unit of measure/measurement; and basis of acceptance and
special details that would give the user a clear view of the work to be done.

High Rise Building

“16-Storeys or taller in height, i.e. from 48.00 meters above established grade;
elevators, fire escapes, sprinkler systems, arrester, beacons and other safety systems,
particularly if near airports, are mandatory for all high-rise buildings/structure”

Source: Implementing Rules and Regulations of


the National Building Code of the
Philippines (PD 1096), 2005 Revised
Edition

iv
UNITS AND ABBREVIATIONS ACRONYMS

Ø diameter AASHTO American Association of State Highway


" inch and Transportation Officials
' foot ABC Approved Budget for the Contract
% percent ACCU Air Cooled Condensing Unit
A ampere ACEL Association of Carriers and Equipment
bd-ft board-foot Lessors, Inc.
cfm cubic foot per minute ACP Asphalt Concrete Pavement
cm centimeter ASTM American Society for Testing and Materials
cyl cylinder BI Black Iron
ea each BOC Bureau of Construction
ft foot BOD Bureau of Design
ft³ cubic foot CFL Compact Fluorescent Lamp
Ga/# Gauge CHB Concrete Hollow Block
gal gallon CI Curb Inlet
h hour CMPD Construction Materials Price Data
ha hectare CP Contractor's Profit
hp horsepower CPMC Central Price Monitoring Committee
kg kilogram CWN Common Wire Nail
km kilometer DEO District Engineering Office
L liter DO Department Order
ls lump sum DOLE Department of Labor and Employment
m meter EAG Exhaust Air Grilles
m² square meter ECC Employer's Compensation Contribution
m³ cubic meter ECOLA Emergency Cost Of Living Allowance
min minute EDC Estimated Direct Cost
mm millimeter EMT Electrical Metal Tubing
mt metric ton FAG Fresh Air Grille
pc piece FCU Fan Coil Unit
PhP Philippine Peso GI Galvanized Iron
psi pound per square inch HDPE High Density Polyethylene
thk thick IMC Intermediate Metal Conduit
tph ton per hour LED Light Emitting Diode
yd³ cubic yard NCR National Capital Region
NEMA National Electrical Manufacturers
Association
NWPC National Wages and Productivity
Commission
OCM Overhead, Contingencies & Miscellaneous
OS & Y Outside Screw/Stem and Yoke Valve
PACU Package Type Airconditioning Unit
PCCP Portland Cement Concrete Pavement
PE Polyethylene
PN Pressure Nominal
POW Program of Works
PPR-C Polyprophylene Random Copolymer
PVC Polyvinyl Chloride

v
ACRONYMS

RC Reinforced Concrete
RCD Return Ceiling Diffuser
RCPC Reinforced Concrete Pipe Culvert
RLD Return Linear Diffuser
RO Regional Office
RPM Raised Pavement Markers
RSB Reinforcing Steel Bar
RSC Rigid Steel Conduit
SCD Supply Ceiling Diffuser
SLD Supply Linear Diffuser
SPT Standard Penetration Test
SSS Social Security System
THHN Thermoplastic High Heat Nylon-coated
TW Thermoplastic Wire
TWHN2Thermoplastic Water and Heat resitant
Nylon-coated
UPMO Unified Project Management Office
UPVC Unplasticized Polyvinyl Chloride
VO Variation Order
VRF Variable Refrigerant Flow
XLPE Cross-Linked Polyethylene

vi
PREFACE

The Department of Public Works and Highways, in pursuit of continuous


development in performing its mission, formulates standards and guidelines to establish
common bases in attaining desired outputs. This manual, Cost Estimation Manual for High
Rise Buildings, encloses the scheme of deriving the unit cost of items of work specialized for
high rise building construction using actual average productivity rates for labor-intensive or
equipment-based works in accordance with the guidelines established by the Department in
the preparation of Approved Budget for the Contract (ABC).

In anticipation of the Department to the probability of implementing high-rise


government buildings and to cope up with the “Build, Build, Build” program of the current
administration and thriving construction industry, the Bureau of Construction sees the
necessity of establishing guidelines in estimating cost for high-rise buildings aligned with the
Department’s mantra of implementing projects at the right cost. Generation of this manual
aims to provide a uniform basis in the preparation of reasonable cost estimates specifically
for High Rise Buildings which the Department will be involved in the future. Likewise, this
manual will aid in facilitating a more efficient review and evaluation of Detailed Unit Price
Analysis (DUPA) and Program of Works (POW).

Guidelines presented in this manual are structured to be more applicable for high rise
building projects to be implemented by the DPWH and other government agencies. Sources
in the formulation of this manual were collated data from previously programmed projects of
the Bureau, with the help of some private construction companies with expertise in
construction of high-rise buildings.

vii
viii
INTRODUCTION

Development in construction technology drives the society to invest in building structures


designed with new innovations. In keeping up with the continuous progress in the construction
industry, the government likewise has been instituting measures in building structures
upgraded for resiliency at a reasonable cost.

Dealing with the “Build, Build, Build” program, many government agencies started to propose
development on their infrastructures to improve their public service and to level competencies
amongst private entities. As the construction arm of the government, the DPWH has been
involved in providing technical assistance on building construction not only to its own
Implementing Offices but also with other government agencies. Hence, as a tool to improve
efficiency through facilitating the preparation, review and evaluation of Detailed Unit Price
Analysis (DUPA) and Approved Budget for the Contract (ABC) particularly for government
building projects, this cost estimation manual is formulated to establish a uniform basis or
reference.

This manual covers only the common pay items of work in building construction with details
on the breakdown for costing of materials, labor, equipment including the overhead cost and
contingencies. Usage of this manual in the derivation of unit cost for DPWH projects requires
the user’s input for unit rates of materials and labor based on the Department’s Construction
Materials Price Data (CMPD) and Standard Labor Rates that are variable for different locations
(i.e. Regional and District Engineering Offices). It is limited only to unit cost derivation, thus,
methods and techniques in quantity take off are not discussed. It also provides guidelines in
the selection of support equipment for construction of high-rise building. This intends not to
establish a uniform cost but serves only as a reference on the means of unit cost derivation
thus, the estimators may indicate their logical discretion as needed.

1
2
GENERAL NOTES

1. The capacity of equipment as presented in the standard cost sheet for each item of
work may be adjusted to a higher or lower capacity, provided the resulting unit cost is
more economical. Rental rates shall still be based on ACEL Guidebook of 2016.

Example: In hauling of materials, use of Dump Truck with higher capacity of fifteen
(15) m3 instead of ten (10) m3 capacity as presented will result to a lower price, as the
capacity gets bigger, the lower the resulting cost of P45.46/m3 of hauling cost from
P54.10/m3. Furthermore, the utilization of a Payloader will be optimized.

2. The capacity of ten (10) m3 for the Dump Truck as presented, may be reduced in cases
of extraordinary conditions where the road has a very steep gradient, in a severely
deteriorated condition or in cases of bridges with load limitations. It is impractical
during the actual hauling to load the full capacity of the Dump Truck. A proper
explanation/justifications shall be made, however, in the preparation of estimate.

3. For items of work that involves hauling and disposal of materials where hauling distance
was indicated, in cases when actual hauling distance is shorter or longer than the
assumed hauling distance of 3 km in the standard cost sheets, corresponding
equipment hours for Dump Truck shall be adjusted based on the cycle time analysis.
The actual hauling distance should be the nearest possible disposal site determined by
the Implementing Office prior to the preparation of the ABC/POW and shall be indicated
in the DUPA.

4. For equipment utilization of less than one (1) day, the scheduled operating hours shall
be paid at operated cost per hour and the remaining hours of the minimum 8 hours a
day shall be considered for payment as bare rental rates.

5. The utilization of equipment other than the equipment model and capacity presented in
the standard cost sheets may be allowed, provided there is a corresponding justification
in the substitution. Rental rates of equipment should be based from ACEL Guidebook or
the Bureau of Equipment Rental Rates guidelines.

6. The presented DUPA is based on a one (1) gang of labor and equipment with the
specified output per unit. To increase the output, additional equipment and labor may
be added or an equipment with a higher capacity may be adopted.

7. The production outputs per item of work were established based on normal condition
and study conducted by the Bureau of Construction (BOC) in collaboration with some
construction companies expertise in construction of high-rise buildings. Any deviation to
suit actual site condition that tends to increase the total unit cost shall be subjected for
approval by the BOC.

3
8. For item of work involving the exposure of workers in the outside environment and
height hazards, production output from Cost Estimation Manual for Low Rise Building
were adopted but adjusted with additional labor as compensation to the efficiency lost
due to such hazards.

9. For items of work involving interior works, production output from Cost Estimation
Manual for Low Rise Building were adopted. It is suggested that hauling of materials on
such items be facilitated through support equipment (i.e. Construction Elevator) and
delivered on assigned staging area inside the building prior to enclosure of the building
perimeter.

10. The application of Mark-Up (OCM and Profit) shall be in accordance with the ranges of
the Total Estimated Direct Cost (EDC) of the project as prescribed under D.O. No. 197,
Series of 2016 or latest issuance.

11. The cost of materials component in the Standard Cost Sheets shall be based on the
latest Construction Materials Price Data submitted quarterly by the District Engineering
Offices, which includes payment of local taxes and hauling/delivery cost to site.

12. The cost of labor shall be based on the labor rates established for each District
Engineering Office, following the minimum labor wage as approved by the NWPC,
DOLE, plus monetary benefits calculated in accordance with D.O. No. 72, Series of 2018
or latest issuance.

4
SECTION A

COST ESTIMATION PROCESS

5
6
A. COST ESTIMATION PROCESS

DEO Consultant

Yes

Is the project
within the limits of
authority delegated to
the DEO?

No
RO UPMO

Yes

Is the project
Assistant Secretary
within the limits of
BOD & BOC Undersecretary
authority delegated to No Secretary
the RO?

District Engineering Office (DEO):

1. The Estimator shall determine the items of work involved based on the Approved Plans.
2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved based on the latest standard labor rates & CMPD, standard
cost sheets and D.O. 22, Series of 2015.
3. The District Engineer shall approve the ABC & POW, if the project is within the limits of
authority delegated to him/her.
4. If beyond the authority of the DEO, forward the DUPA, ABC & POW and Approved
Construction Plans together with the required attachments to the Regional Office for
review/evaluation and approval, if the project is within the limits of the delegated
authority of the Regional Director.
5. If Planning and Design Division of the Regional Office will make an adjustment in the
quantities and delete/add pay item/s in the submitted construction plans, the ABC &
POW shall be adjusted accordingly by the District Engineering Office and resubmit the
same for approval.

Regional Office (RO):

1. The Estimator shall determine the items of work involved based on the Approved Plans.
2. The Estimator shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved based on the latest standard labor rates & CMPD, standard
cost sheets and D.O. 22, Series of 2015.
3. The Regional Director shall approve the ABC & POW, if the project is within the limits of
authority delegated to him/her.

7
4. If beyond the authority of the RO, forward the DUPA, ABC & POW and Approved
Construction Plans together with the required attachments to the Bureau of Construction
(BOC) and Bureau of Design (BOD) respectively, for review/evaluation for approval of
the Assistant Secretary for Technical Services, Undersecretary for Technical Services or
Secretary depending on the limits of authority.
5. If Bureau of Design shall make an adjustment in the quantities and delete/add pay
item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly
by the Regional Office and resubmit the same for approval.

Unified Project Management Office (UPMO):

1. The Consultant shall determine the items of work involved based on the Approved Plans.
2. The Consultant shall prepare the DUPA, ABC & POW including its attachments applying
the items of work involved.
3. The Project Director shall conduct review/evaluation of the proposed ABC & POW and
recommends its approval to the authorized approving official concerned.
4. Forward the ABC & POW and Approved Construction Plans together with the required
attachments to the Bureau of Construction (BOC) and Bureau of Design (BOD)
respectively, for review/evaluation to be approved by the Assistant Secretary for
Technical Services, Undersecretary for Technical Services or Secretary depending on the
limits of authority.
5. If the Bureau of Design shall make an adjustment in the quantities and delete/add pay
item/s in the submitted construction plans, the ABC & POW shall be adjusted accordingly
by the concerned UPMO and resubmit the same for approval.

Approval of the ABC & POW shall be based on the following (or its latest
issuance):

1. Department Order No. 91, Series of 2012 – Authority of the Assistant Secretary for
Technical Services to Approve Plans, Program of Works and Approved Budget for the
Contract for DPWH Locally-Funded and Foreign-Assisted Civil Works Projects Costing
more than PhP50 Million up to PhP100 Million.
2. Department Order No. 95, Series of 2013 – Reissuance of D.O. No. 9, S. 2011 Re:
Conduct of Pre-Procurement, Procurement, and Implementation Activities for DPWH
Foreign-Assisted Civil Works Projects.
3. Department Order No. 109, Series of 2014 – Approval of Plans, Program of Works
(POW) and Approved Budget for the Contract for DPWH Locally-Funded Projects
Costing PhP50 Million and below Implemented by Unified Project Management
Offices.
4. Department Order No. 140, Series of 2014 – Increased Limits of Delegated Authority
to Regional Directors to Approve Plans, Program of Work (POW) and Approved
Budget for the Contract (ABC) of Locally-Funded Projects.
5. Department Order No. 54, Series of 2011 – Revised Limits of Responsibilities and
Authorities of Concerned DPWH Offices and Officials in the Conduct of Pre-
Procurement, Procurement, and Implementation Activities for DPWH Locally-Funded
Civil Works Project.

8
PREPARATION OF DETAILED UNIT PRICE ANALYSIS
1. General

a. Determine the scope of works based on approved plans and specification including
other requirements adopting the standard pay items of works per Department Order
No. 143, Series of 2017.
b. Calculate the quantity and cost of material component of every item of work based
on plans and specifications and prevailing prices of construction materials in the
Construction Materials Price Data (CMPD) with consideration of allowance for waste
and/or losses not to exceed 5% of the material’s requirement.
c. Determine the appropriate quantity based on best norms and practices in the
construction industry and cost for manpower and equipment requirement to be used
based on Standard Labor Rates per Region and latest ACEL rates.
d. Determine the unit cost per item of work as presented in Item 5.

2. Determination of category of work supervisor

The appropriate number and category of supervisor including unskilled labor to be


deployed depends on the specific type and complexity of an item of work to be done. In
this manual, the labor force (crew or gang) were established based on actual study and
best practices observed during the construction of BOC implemented projects.
Example: Item 900-Concrete Works

Foreman------------------------------------1
Skilled Worker (Mason, carpenter)----- 2
Unskilled Labor---------------------------- 6

3. Calculation of production output per hour of an item of work

The production output per hour of an item of work should be derived based on the
number of days and appropriate manpower and equipment utilized to complete the work
in accordance with the right construction methodology. In this manual, the production
output was derived by the Bureau of Construction (BOC) Engineers based on actual study
and best practices during the construction of BOC implemented projects.

Example: Item 900-Concrete Works

Volume of Concrete = 21.50 cubic meter

Number of hours to complete the work which includes setting of equipment and
accessories, batching, delivery and pouring of concrete= 6 hours and 21 minutes
(6.85 hr)

Type and number of manpower utilized during pouring


Foreman---------------------------------- 1
Skilled Worker (Mason, Carpenter) --- 2
Unskilled Labor--------------------------- 6

9
Type and number of equipment and tools including lightings utilized during pouring:

Transit Mixer ------------------------------4


Pump-Crete --------------------------------1
Concrete Vibrator--------------------------2
Lighting System (if applicable) ----------1

Production output per hour=volume of concrete poured/number of


hours consumed to complete the
pouring session
= 25.5 cu.m/ 6.85 hr
= 3.72 cu.m/hr

4. Determination of percentages of Overhead, Contingency and Miscellaneous


(OCM) expenses, Profit and Value-Added Tax (VAT)

The percentages of OCM, Profit and VAT to be applied to the estimated direct cost (i.e.
cost of material, labor and equipment rental) should be based on Department Order
(DO) No. 197, Series of 2016 (Guidelines in the Preparation of Approved Budget for the
Contract) or latest issuance.

5. Determination of unit cost per item of work

Unit Cost=total unit direct cost (i.e. cost of materials, labor,


Equipment) plus indirect cost (i.e. OCM, Profit and
VAT)
Example: Item 900-Concrete Works

10
6. Cost estimation techniques and best practices

a. Skills in the interpretation of the plans and specifications


b. Wide experience in actual construction and estimating works
c. Familiarity with different types of construction materials and
equipment
d. Consideration on actual site condition in the preparation of DUPA
i.e. hauling distance, terrain, etc.
e. Familiarity on laws, policies, guidelines and procedures
pertaining to the implementation of government infrastructure
projects to ensure cost estimates are done at the right cost

11
12
SECTION B

STANDARD DETAILED UNIT


PRICE ANALYSIS (DUPA)
SHEETS

13
14
B.1 SUMMARY TABLE OF ITEMS OF WORK AND DESCRIPTION

ITEM NO. DESCRIPTION PAGE NO.

PART A EARTHWORKS

800(1) Clearing and Grubbing (m2) 26

800(2) Clearing and Grubbing (l.s.) 27

803(1)a Structure Excavation (Common Soil) 28

803(1)b Structure Excavation (Soft Rock) 29

803(1)c Structure Excavation (Hard Rock) 30

803(2) Trimming Works 31

803(3) Soil Stablization - a. Jet Grouting (0.80 m diameter) 32


Soil Stablization - b. Structural Steel Sheet Piles, furnished and
803(3) 33
driven
804(1)a Embankment from Structure Excavation 34

804(1)b Embankment from Common Borrow by Equipment 35

804(4) Gravel Bedding 36

PART B PLAIN AND REINFORCED CONCRETE WORKS


Structural Concrete (Ready Mix, Class AA/Class A/Class
900 B/Class C/Class P/Seal Concrete, 37
7 days/14 days/ 28 days)

901(1) Lean Concrete (Ready Mix, 28 days) 38

Reinforcing Steel of Reinforced Concrete Structures for Two


902(1) 39
upto Five Storey , Grade 40/Grade 60
903(2) Formworks and Falseworks (for two to five-storey building) 40

PART C FINISHING

1000(1) Soil Poisoning 41

50 mm Ø -100 mm Ø PVC Pipe and Fittings, Series 600/ Series


1001(1)a 42
1000
150 mm - 300 mm Ø PVC Pipe and Fittings, Series 600/ Series
1001(1)a 43
1000

1001(1)b1 150 mm Ø Concrete Pipe 44

1001(1)b2 200 mm Ø Concrete Pipe 45

15 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1001(1)b3 250 mm Ø Concrete Pipe 46

1001(1)b4 300 mm Ø Concrete Pipe 47

1001(1)b5 350 mm Ø Concrete Pipe 48

1001(1)c 50 mm Ø - 100 mm Ø High Density Polyethylene (HDPE) Pipe 49

1001(1)c 150 mm Ø - 300mm ØHigh Density Polyethylene (HDPE) Pipe 50

1001 PVC/HDPE Fittings 51

1001(2) Concrete Gutter 52

1001(5) Catch Basin (Concrete/CHB) 53

1001(7) Junction Box (Concrete/CHB) 54

1001(8) Sewer Line Works (lump sum) 55

1001(9) Storm Drainage and Downspout (lump sum) 56

1002(1) 13 mm Ø - 50 mm Ø Galvanized Iron Pipe and Fittings 57

1002(1) 65 mm Ø - 150 mm Ø Galvanized Iron Pipe and Fittngs 58

1002(2) Galvanized Iron Fittings 59

13mmØ - 50mm ØPolyprophylene Random Copolymer (PPR-C)


1002(2)a 60
Pipe and Fittings, PN 16/ PN 20
63mmØ - 100mm Ø Polyprophylene Random Copolymer (PPR-
1002(2) 61
C) Pipe and Fittings PN 16/ PN 20

1002(3) Polyprophylene Random Copolymer (PPR-C) Fittings 62


13 mm Ø - 50 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings,
1002(3) 63
Blue
65 mm Ø - 100 mm Ø Polyvinyl Chloride (PVC) Pipe and
1002(3) 64
Fittings, Blue
1002(4) Polyvinyl Chloride (PVC) Fittings, Blue 65

1002(4) Plumbing Fixtures 66

1002(5) Water Closet/ Urinal with Complete Accessories 67

Kitchen Sink/Scrub Up Sink/Slop Sink with Complete


1002(11) 68
Accessories

Wall Hung/Countertop/Under Counter Lavatory with Complete


1002(14) 69
Accessories

16 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1002(16) Floor Drain Plates 70

1002(5) Soap Holder ( Toilet Soap/ Liquid Soap) 71

1002(5) Toilet Tissue Holder/Dispenser 72

1002(17) Bidet/ Faucet/ Hose Bibb 73

1002(18) Stainless Steel Grab bar 74

1002(19) Shower head/ Shower Valve 75

1002(20) Facial Mirror 76

1002(24) Cold Waterline Pipes and Fittings 77

1002(25) Hot Waterline Pipes and Fittings 78

4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm


1003(1) 79
Marine Plywood/ 6mm Ordinary Plywood on Metal Frame Ceiling

4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm


1003(1)a Marine Plywood/ 6mm Ordinary Plywood in Wood Framing 80
Ceiling

1003(1)e Gypsum Board on Metal Frame Ceiling 81

4.5mm/ 6.0 mm Fiber Cement Board/ 4.5mm/ 6.0 mm 4' X 8' thk
fiber cement board/ 4.5mm Marine Plywood/ 6.0 mm Marine
1003(2) 82
Plywood/ 6.0 mm Ordinary Plywood on Metal Frame Double
Wall Partition

1004(2) Finishing Hardware 83

Residential Casement Steel Windows/ Heavy Duty Side-hinged


1005 84
Ventilator/ Projected Ventilator/ Awning Ventilator/ Grille Window

Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver
1006 85
Door
1006(5) Fire Rated Fire Exit Steel Door 86

1007 Aluminum Glass Door (Sliding Type/Swing Type) 87


Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed
1008 88
Type)
1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions) 89

1010(2)a Hollow Core Flush Door 90

1010(2)b Wooden Panel Door 91

17 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1011(1) Steel/ Aluminum Roll Up Door 92

1012(1) Tempered Glass Door (10 mm/ 12mm) 93

1012(1) Tempered Glass Windows (8 mm/ 10mm) 94

1013(1) Corrugated Metal Roofing 95

Fabricated Metal Roofing Accessory (Ridge/Hip


1013(2) 96
Rolls/Flashings/Counter Flashing/Valley Roll)

1013(2)c Fabricated Metal Roofing Accessory (Gutter) 97

Prepainted Metal Sheets (Corrugated, Short Span/ Long Span,


1014 98
below 0.427 thk/ above 0.427 thk)
Prepainted Metal Sheets (Rib Type, Short Span/ Long Span,
1014 99
below 0.427 thk/ above 0.427 thk)
1016(1)a Waterproofing Cement Base 100

1016(1)b Liquid Waterproofing 101

1016(2) Built-up and Preformed Membrane 102


50mm ø - 100mm ø Roof Drain/Canopy Drain/ Gutter
1017 103
Drain with Strainer
1018(1) Glazed Tiles and Trims 104

1018 Unglazed Tiles/ Granite Tiles/ Synthetic Granite Tiles 105

1019(1) Wood Tiles (Narra, Tanguile, others) 106

1019(1)d Laminated Wood Tiles 107

1020(1) Vinyl Tiles 108

1021(1)a Plain Cement Floor Fnish 109

1021(3) Floor Topping 110

1023(1) Granolithic Marble Work 111

1024(1) Pea Gravel Finish 112

1026(1) Pebble Washout Finish 113

1027(1) Cement Plaster Finish 114

1032(1)a Painting Works (Masonry Painting) 115

1032(1)b Painting Works (Wood Painting) 116

18 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1032(1)c Painting Works (Metal Painting) 117

1032(2) Varnishing Works 118

1032(4) Ducco Finish 119

1034(1) Damproofing ( Polyethylene Sheets) 120

1038(1) Reflective Insulation 121

1042(1) Stainless Steel Door and Frames 122

1043(1) PVC Doors and Frames 123

1045(1) Perforated Aluminum Ceiling Panels 124


100 mm CHB Non Load Bearing/Load Bearing (including
1046 125
Reinforcing Steel)
150mm CHB Non-LoadBearing/ Load Bearing (including
1046 126
Reinforcing Steel)
1047(1) Structural Steel Roof Framing 127

1047(2)a Structural Steel Roof Framing 128

1047(2)b Structural Steel Roof Truss 129

1047(2)c Structural Steel Purlins 130

1047(3)a Metal Structure Accessories (Anchor Bolts) 131

1047(3)b Metal Structure Accessories (Sagrods) 132

1047(3)c Metal Structure Accessories (Turnbuckle) 133

1047(3)d Metal Structure Accessories (Crossbracing, ) 134

1047(4) Metal Structure Accessories (Crossbracing) 135

1047(5) Metal Structure Accessories (Steel Plates) 136

1048(1)a Carbon Fiber (1 layer) 137

1048(2) Glass Fiber 138

1049(1) Jet Grouting (0.80 m diameter) 139

Precast Concrete Piles, furnished


1052(4)a.1 140
(400mm x 400mm -type A)
Precast Concrete Piles, furnished
1052(4)a.2 141
(400mm x 400mm -type B)

19 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

Precast Concrete Piles, furnished


1052(4)b.1 142
(450mm x 450mm -type C)
Precast Concrete Piles, furnished
1052(4)b.2 143
(450mm x 450mm -type D)

Precast, Prestressed Concrete Piles, furnished


1052(5)a 144
(400 mm x 400 mm)

Precast, Prestressed Concrete Piles, furnished


1052(5)b 145
(450 mm x 450 mm)

1052(6) Structural Steel Sheet Piles, furnished 146

1052(7)a Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m) 147


Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m),
1052(7)b 148
(Ready Mix Concrete)
1052(11) Steel Pipe Piles, furnished and driven 149

1052(12) Structural Steel Sheet Piles, driven 150

1052(13) Precast Concrete Sheet Piles, driven 151

1052(14)a Precast Concrete Piles, driven (soft strata) 152

1052(14)b Precast Concrete Piles, driven (hard strata) 153

1052(15)a Precast, Prestressed Concrete Piles, driven (soft strata) 154

1052(15)b Precast, Prestressed Concrete Piles, driven (hard strata) 155

1052(16)a Test Piles, furnished and driven (type A, B, C or D), soft strata 156

1052(16)b Test Piles, furnished and driven (type A, B, C or D), hard strata 157

Concrete Piles cast in Drilled Holes, 0.80 m. Ø, fc' = 28 MPa


1052(17)a 158
(ordinary soil condition)
Concrete Piles cast in Drilled Holes, 1.00 m. Ø, fc' = 28 MPa
1052(17)b 159
(ordinary soil condition)
Concrete Piles cast in Drilled Holes, 1.20 m. Ø, fc' = 28 MPa
1052(17)c 160
(ordinary soil condition)
Concrete Piles cast in Drilled Holes, 1.50 m. Ø, fc' = 28 MPa
1052(17)d 161
(ordinary soil condition)
Concrete Piles cast in Drilled Holes, 1.80 m. Ø, fc' = 28 MPa
1052(17)e 162
(ordinary soil condition)
Concrete Piles cast in Drilled Holes, 2.00 m. Ø, fc' = 28 MPa
1052(17)f 163
(ordinary soil condition)

20 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1052(18)a Concrete Piles cast in Steel Shells, furnished and driven 164

Concrete Piles cast in Steel Shells, furnished and driven (Ready


1052(18)b 165
Mix Concrete)

1052(19)a Concrete Piles cast in Steel Pipes, furnished and driven 166

Concrete Piles cast in Steel Pipes, furnished and driven (Ready


1052(19)b 167
Mix Concrete)
1052(20) Pile Shoes 168

1052(23)a Bored Piles, 0.80 m. Ø (ordinary soil condition) 169

1052(23)b Bored Piles, 1.00 m. Ø (ordinary soil condition) 170

1052(23)c Bored Piles, 1.20 m. Ø (ordinary soil condition) 171

1052(23)d Bored Piles, 1.50 m. Ø (ordinary soil condition) 172

1052(23)e Bored Piles, 1.80 m. Ø (ordinary soil condition) 173

1052(23)f Bored Piles, 2.00 m. Ø (ordinary soil condition) 174

1052(24)a Permanent Casing (0.80 m Ø) 175

1052(24)b Permanent Casing (1.00 m Ø) 176

1052(24)c Permanent Casing (1.20 m Ø) 177

1052(24)d Permanent Casing (1.50 m Ø) 178

1052(24)e Permanent Casing (1.80 m Ø) 179

1052(24)f Permanent Casing (2.00 m Ø) 180

1052(25) Splicing of RC Piles with Epoxy (400 mm x 400 mm) 181

1052(26) Splicing of RC Piles with Epoxy (450 mm x 450 mm) 182

1052(27)a Pile Integrity Testing (Sonic), ordinary soil condition 183

1052(27)b Pile Integrity Testing (PIT), ordinary soil condition 184

1052(22)b High Strain Dynamic Testing (PDA), ordinary soil condition 185

1052 (29) Micro Piles In Drilled Holes, 0.20m Ø (ordinary soil condition) 186

D. ELECTRICAL

15 mm Ø - 25 mm Ø Rigid Steel Conduit (RSC)/Intermediate


1100(1) metal Conduit (IMC)/ 187
Electrical Metal Tubing (EMT)

21 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

32 mm Ø - 40 mm Ø Rigid Steel Conduit (RSC)/ Intermediate


1100(1) metal Conduit (IMC)/ 188
Electrical Metal Tubing (EMT)
50 mm Ø - 65 mm Ø Rigid Steel Conduit/ Intermediate metal
1100(1) Conduit (IMC)/ 189
Electrical Metal Tubing (EMT)
80 mm Ø - 100 mm Ø Rigid Steel Conduit (RSC)/ Intermediate
1100(1) metal Conduit (IMC)/ 190
Electrical Metal Tubing (EMT)

1100(3) 15 mm Ø - 25 mm Ø Flexible Metal Conduit 191

1100(6) 15 mm Ø - 32 mm Ø Polyvinyl Chloride (PVC) Pipes 192

1100(9) PVC/RSC/ IMC/ EMT Conduit Fittings 193

1100(11) Junction/ Utility/ Pull/ Square Box 194

1100(10) Conduit Works, Boxes and Fittings 195

1101(1) 1.6 mm2 - 5.5 mm2 Electric Wire (TW/THHN/TWHN2) 196

1101(1) 8.00 mm2 - 22 mm2 Electric Wire (TW/THHN/TWHN2) 197

1101(1) 30.00 mm2 - 38 mm2 Electric Wire (TW/THHN/TWHN2) 198

1101(1) 50.00 mm2 - 60 mm2 Electric Wire (TW/THHN/TWHN2) 199

1101(1) 80.00 mm2 - 125 mm2 Electric Wire (TW/THHN/TWHN2) 200

1101(1) 150.00 mm2 - 250 mm2 Electric Wire (TW/THHN/TWHN2) 201

1101(1) 325.00 mm2 - 400 mm2 Electric Wire (TW/THHN/TWHN2) 202

1101(1)b19 500.00 mm2 Electric Wire (TW/THHN/TWHN2) 203

1101(2) XLPE Electric Wires 204

1109(4) 2.00 mm2 - 5.5 mm2 Bare Copper Wire 205

1109(4) 8.00 mm2 - 22.00 mm2 Bare Copper Wire 206

1109(4) 30.00 mm2 - 38.00 mm2 Bare Copper Wire 207

1109(4) 50.00 mm2 - 60.00 mm2 Bare Copper Wire 208

1109(4) 80.00 mm2 - 125.00 mm2 Bare Copper Wire 209

1109(1) 200.00 mm2 - 250.00 mm2 Bare Copper Wire 210

1101(33) Switches 211

22 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

Single Convenience Outlet/Receptacle, Grounding Type (GT)/


Heavy Duty Convenience Outlet/Receptacle, Grounding Type
1101 (15) (GT)/ Weather Proof Single Convenience Outlet/Receptacle, 212
Grounding Type (GT)/ Pop-up Type/Floor Triplex Convenience
Outlet/Receptacle, Grounding Type (GT)

Duplex Convenience Outlet/Receptacle, Grounding Type (GT) /


Weather Proof Duplex Convenience Outlet/Receptacle,
Grounding Type (GT)/ Special Purpose Convenience
1101 (16) Outlet/Receptacle, Grounding Type for ACU, WH, etc/ 213
Explosion Proof Type Duplex Convenience Outlet/Receptacle,
Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle
with Ground Fault Circuit Interupter

Pop-up Type/Floor Single Convenience Outlet/Receptacle,


Grounding Type (GT)/ Pop-up Type/Floor Duplex Convenience
Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type
1101 (21) 214
Single Convenience Outlet/Receptacle, Grounding Type (GT)/
Single Convenience Outlet/Receptacle with Ground Fault Circuit
Interrupter

1101 (33) Wires and Wiring Devices 215

Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 250


1102 (1) 216
Amp - 400 Amp
Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 50
1102 (1) 217
Amp - 200 Amp
NEMA I (Enclosed Circuit Breaker) Single Phase or Three Phase
1102 (1) 218
Commercial/Industrial Type
NEMA 3R (Enclosed Circuit Breaker) Single Phase or Three
1102 (1) 219
Phase Commercial/Industrial Type

Motor Control Center with main, branch breaker and motor


1102 (2) 220
starter (NEMA 1, NEMA 3R and 4X) Flush or Surface Mounted

Generator (Stand by and Continuous), Synchonizing Panel for


1102 (16) 221
Generator, High Voltage Switch Gear
Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT ,
1102 (1) 3P, 240V: NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface 222
Mounted

Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT ,


1102 (1) 2P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ Surface 223
Mounted

23 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205
1102 (1) AT , 225 AT, 3P, 240V NEMA I, NEMA 3R, NEMA 4x Flushed/ 224
Surface Mounted

Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200
1102 (1) AT , 2P, 225 AT, 2P, 240V NEMA I, NEMA 3R, NEMA 4x 225
Flushed/ Surface Mounted

Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA
1102 (1) 226
I with Breaker

1102 (1) Main Enclosed Automatic Breaker 250-500 Amp 227

Fluorescent Lighting Fixture with Ballast /Light Emitting Diode


1103 (1) 228
(LED) Bulb, 1 Bulb

Fluorescent Lighting Fixture with Ballast /Light Emitting Diode


1103 (1) 229
(LED) Bulb, 2 Bulbs

Fluorescent Lighting Fixture with Ballast /Light Emitting Diode


1103 (1) 230
(LED) Bulb, 3 Bulbs

Fluorescent Lighting Fixture with Ballast /Light Emitting Diode


1103 (1) 231
(LED) Bulb, 4 Bulbs

Downlight/Pinlight Fixture with One- Compact Fluorecent Lamp


1103 (1) 232
(CFL) or LED Bulb, 1 Bulb

Downlight/Pinlight Fixture with Two- Compact Fluorecent Lamp


1103 (1) 233
(CFL) or LED Bulb, 2 Bulb

1103 (1) High Bay Aluminum Reflector, Dome Luminaire 234

1103 (1) Die-Cast Aluminum Floodlight with Electrocoat Paint Finish 235

1103 (1) Lighting Fixtures 236

PART E MECHANICAL

1200(13)a Air Conditioning and Refrigiration System 237

1201(1) Water Pumping System 238

1202(1) Automatic Water Sprinkler System 239

1202(2) Fire Pump with complete control and standard accessories 240

1202(3) Jockey Pump with complete control and standard accessories 241

1202(1) Sprinkler Head, upright/pendent/wall 242

1202(1) Alarm Check Valve 243

24 Summary Table of Items of Work and Description


ITEM NO. DESCRIPTION PAGE NO.

1202(1) Flow Meter 244

1202(1) OS & Y Gate Valve 175 psi 245

1202(1) Pressure Gauge 246

1202(1) Pressure Relief Valve 247

1202(1) Floor Control Valve 248

1202(1) Inspector Test Valve 249

1202(1) Inspector Test Connection 250

1202(1) 25 mm Ø - 50 mm Ø Black Iron (B.I.) Pipe and Fittings 251

1202(1) 65 mm Ø -150 mm Ø Black Iron (B.I.) Pipe and Fittings 252

1202(1) Fittings 253

1202(7) Fire Hose Valve siames 150 mm Ø x 2 w x 65 mm Ø with cap 254

1202(5) Fire Hose Cabinet 255

1202(a1) Fire Extinguisher 256

25 Summary Table of Items of Work and Description


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(1) Clearing and Grubbing


2
Unit of Measurement : m
Output per hour : 500.00 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Unskilled Laborer 2 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Dumptruck (12 yd ) 2 1.00
3
b. Payloader (1.50 m ) 1 1.00
c. Bulldozer (155 Hp), D65A-8 1 1.00

Note:
Assumed hauling distance is 3 km. If actual
hauling distance is shorter or longer than 3 km, the time
of dump truck will be adjusted accordingly based on the
hauling cycle analysis.

Based on assumed 150 mm cut all throughout. A


corresponding adjustment in the output shall be
computed based on the actual field requirements.

Sub - Total for B


C. Total (A + B)
2
D. Output per Hour = 500.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8%
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

26 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 800(2) Clearing and Grubbing


Unit of Measurement : ls
Output per hour : 1.00 ls

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivations for Item Nos. 800(1), 800(3) and 800(4)

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivations for Item Nos. 800(1), 800(3) and 800(4)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.00 ls
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivations for Item Nos. 800(1), 800(3) and 800(4)

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 800(1),
800(3), and 800(4)

27 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)a Structure Excavation (Common Soil)


3
Unit of Measurement : m
3
Output per hour : 20.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Backhoe (0.80 m ) 1 1.00
b. Dump Truck (12 yd3) 2 1.00
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 20.00 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Additional labor and/or equipment may be added for dispossal of surplus excavated material.

28 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)b Structure Excavation (Soft Rock)


3
Unit of Measurement : m
3
Output per hour : 14.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Dump Truck (12 yd ) 2 1.00
3
b. Backhoe (0.80 m ) 1 0.50
3
c. Backhoe with Breaker (0.80 m ) 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 14.00 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

29 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(1)c Structure Excavation (Hard Rock)


3
Unit of Measurement : m
3
Output per hour : 4.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Dump Truck (12 yd ) 2 1.00
3
b. Backhoe (0.80 m ) 1 0.25
3
c. Backhoe with Breaker (0.80 m ) 1 0.75
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.00 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

30 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(2) Trimming Works


2
Unit of Measurement : m
2
Output per hour : 5.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bentonite Bin 1 0.50


b. Bentonite Mixer 1 0.50
c. Minor Tools (10 % of Labor rate)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.00 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Bentonite kg 30.72

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

31 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(3) Soil Stablization - a. Jet Grouting (0.80 m diameter)


Unit of Measurement : m
Output per hour : 1.18 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
c. Unskilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Jetting Machine 1 1.00 See latest ACEL rental rates.


b. Air Compressor 12 Bars/600 CFM 1 1.00
c. Water Tank/Pump 1 1.00
d. Agitator 1 1.00
e. Generator/Power Supply 1 1.00
f. High Pressure Pump 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bags 14.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Additives L 3.50 the locality which include payment of local
c. Consumables (5% of Material Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

32 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 803(3) Soil Stablization - b. Structural Steel Sheet Piles, furnished and driven
Unit of Measurement : m.
Output per hour : 72.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 72.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Refer to Item 1052(6) - Structural Steel Pile, furnished and Item 1052(12) - Structural Steel Pile, driven

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

33 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)a Embankment from Structure Excavation


3
Unit of Measurement : m
3
Output per hour : 9.84 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 0.75


3
b. Backhoe (0.80 m ) 1 0.75
Minor Tools (10% of Labor)

Sub - Total for B 0.00


C. Total (A + B) 0.00
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

34 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(1)b Embankment from Common Borrow by Equipment


3
Unit of Measurement : m
3
Output per hour : 9.84 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor 1 0.75


3
b. Backhoe (0.80 m ) 1 0.75
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 9.84 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Prices of materials are variable per Region/
a. Embankment Material m3 1.25 District based on the prevailing unit prices in
(w/ 25% Shrinkage Factor) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

35 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 804(4) Gravel Bedding


3
Unit of Measurement : m
3
Output per hour : 1.20 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor 1 0.50


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Prices of materials are variable per Region/
a. Gravel Bedding (G1) m3 1.05 District based on the prevailing unit prices in
(w/ 5% Shrinkage Factor) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

36 Par t A - Ear t h w o r ks
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 900 Structural Concrete (Ready Mix, Class AA/Class A/Class B/Class C/Class P/Seal Concrete,
7 days/14 days/ 28 days)
3
Unit of Measurement : m
Output per hour : 3.72

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
Labor Rates are variable per Region/District
a. Construction Foreman 1 1.00 Labor Rates
based are variable
on minimum wage per Region/District
as approved by
b. Skilled Laborer 3 1.00 based on
DOLE. minimum
Refer to the wage as approved
Schedule of Labor by
Rates.
c. Unskilled Laborer 6 1.00 DOLE.Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Concrete Vibrator 2 1.00


b. Pumpcrete 1 0.27
Minor Tools (10% of labor cost)

* if beyond reach of pumpcrete concrete bucket may be used and costing shall be considered in the support equipment

Sub - Total for B 0.00


C. Total (A + B) 0.00
3
D. Output per Hour = 3.35 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix, Class AA/Class B/Class C/Class P, 7 Prices of materials are variable per Region/
3
days/14 days/ 28 days m 1.05 District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. This cost sheet shall be used for concrete pouring by pumpcrete. Item Nos. 900(1)a1, 900(1)b1, 900(1)c1, 900(2)a,
900(2)b, 900(2)c, 900(3)a, 900(3)b, 900(3)c, 900(4)a, 900(4)b, 900(4)c, 900(5), 900(6), and 900(8) shall used this cost sheet.

37 Part B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 901(1) Lean Concrete (Ready Mix, 28 days)


3
Unit of Measurement : m
3
Output per hour : 3.72 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 6 1.00 DOLE.Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Concrete Vibrator 2 1.00 See latest ACEL rental rates.


b. Pumpcrete 1 0.27
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.72 m3
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Ready Mix Concrete, Lean Concrete, 28days m3 1.05
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

38 Part B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 902(1) Reinforcing Steel of Reinforced Concrete Structures


Unit of Measurement : kg
Output per hour : 129.094 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
c. Unskilled Laborer 12 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Bar Cutter 1 0.50


b. Bar Bender 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B 0.00


C. Total (A + B) 0.00
D. Output per Hour = 129.094 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Deformed Reinforcing Steel Prices of materials are variable per Region/


kg 1.00 District based on the prevailing unit prices in
Grade 60/Grade 40
the locality which include payment of local
b. #16 Galvanized Iron Wire kg 0.015 taxes and hauling cost to the project site.
c. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

39 Part B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 903(2) Formworks and Falseworks


2
Unit of Measurement : m
2
Output per hour : 4.5 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Installation
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 8 1.00
Stripping
a. Skilled Laborer 2 0.56
b. Unskilled Laborer 6 0.56

Sub - Total for A


Name and Capacity Quantity No. of Day/s Daily Rental Rate Amount (PhP)

B. Equipment

Area = 205.01 m2 34.50


a. H-Frame 1.7 m x 1.2m, set 40 14.00 Rental cost for scaffoldings may vary per
Region/District.
2 pcs H-frames
4 pcs diagonal cross braces
4 pcs horizontal braces
8 pcs joint pins
b. Shoring Jack , 3.8 m full extension 62 14.00
c. Adjustable U-head Jack, 0.6m 80 14.00
d. Adjustable Base Jack, 0.6m 80 14.00
e. 1-1/2" GI Pipe x 6.0 m 62 14.00
f. 1-1/2" GI Pipe x 3.0 m 16 14.00
g. 1-1/2" GI Pipe x 4.0 m 32 14.00
h. 1-1/2" GI Pipe x 1.0 m 216 14.00
i. Tie Rod x 0.60m. 278 14.00
j. Round Wing Nut 558 14.00

Sub - Total for B


C. Sub - Total for C (B ÷ Area)
D. Output per Hour =
E. Direct Unit Cost (A ÷ D) + C

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Prices of materials are variable per Region/
District based on the prevailing unit prices in
a. Phenolic Board (0.019 x 1.2 x 2.4) - 3 uses pcs 0.347 the locality which include payment of local
taxes and hauling cost to the project site.
c. Good Lumber - 3 uses bd ft 4.727 Refer to the Construction Material Price Data
b. Consumables (5% of material cost) established quarterly by Central Price
Sub - Total for F Monitoring Committee.
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. This cost sheet analysis is only applicable for Formworks and Falseworks considering steel scafoldings
2. Area of consideration includes beams, columns, and suspended slabs.

40 Part B - Plain and Reinforced Concrete Works


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1000(1) Soil Poisoning


Unit of Measurement : L
Output per hour : 5.4 L

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.4 L
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Soil Poisoning L 1.00
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

41 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)a 50 mm Ø -100 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000
Unit of Measurement : m
Output : 3.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. 50 mm - 100 mm Ø PVC Pipe and Fittings, Series
m 1.00 District based on the prevailing unit prices in
600/Series 1000 the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1001(1)a1, 1001(1)a2,1001(1)a3, 1001(1)a5, 1001(1)a5, and 1001(1)a7.

42 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)a 150 mm - 300 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000
Unit of Measurement : m
Output per hour : 4.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm Ø PVC Pipe and Fittings, Series 600/ Series 1000 m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1001(1)a4, 1001(1)a8, 1001(1)a9, 1001(1)a10 and 1001(1)a11.

43 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)b1 150 mm Ø Concrete Pipe


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.98 Labor Rates are variable per Region/District


b. Skilled Laborer 2 0.98 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 0.98

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 1 0.09


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m3 Prices of materials are variable per Region/


a. Portland Cement 0.19
District based on the prevailing unit prices in
b. Sand bags 0.01 the locality which include payment of local
c. Concrete Pipe (150 mm Ø) m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Sand Bedding/Selected sandy soil m3 0.05 established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

44 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)b2 200 mm Ø Concrete Pipe


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.07 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.07 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.07

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 0.11


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m3 Prices of materials are variable per Region/


a. Portland Cement 0.25
District based on the prevailing unit prices in
b. Sand bags 0.01 the locality which include payment of local
c. Concrete Pipe (200 mm Ø) m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d Sand Bedding/Selected sandy soil m3 0.05 established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

45 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)b3 250 mm Ø Concrete Pipe


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.17 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.17 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.17

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 0.12


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m3 Prices of materials are variable per Region/


a. Portland Cement 0.32
District based on the prevailing unit prices in
b. Sand bags 0.02 the locality which include payment of local
c. Concrete Pipe (250 mm Ø) m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d Sand Bedding/Selected sandy soil m3 0.06 established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

46 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)b4 300 mm Ø Concrete Pipe


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.26 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.26 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.26

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 0.13


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m3 Prices of materials are variable per Region/


a. Portland Cement 0.38
District based on the prevailing unit prices in
b. Sand bags 0.02 the locality which include payment of local
c. Concrete Pipe (300 mm Ø) m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d Sand Bedding/Selected sandy soil m3 0.06 established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

47 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)b5 350 mm Ø Concrete Pipe


Unit of Measurement : m
Output : 1.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.35 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.35 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.35

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Plate Compactor (5 hp) 0.14


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m3 Prices of materials are variable per Region/


a. Portland Cement 0.44
District based on the prevailing unit prices in
b. Sand bags 0.03 the locality which include payment of local
c. Concrete Pipe (350 mm Ø) m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d Sand Bedding/Selected sandy soil m3 0.07 established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

48 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)c 50 mm Ø - 100 mm Ø High Density Polyethylene (HDPE) Pipe


Unit of Measurement : m
Output per hour : 3.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50 mm Ø High Density Polyethylene (HDPE) Pipe m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1001(1)c1, 1001(1)c2, and 1001(1)c3.

49 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(1)c 150 mm Ø - 300mm ØHigh Density Polyethylene (HDPE) Pipe
Unit of Measurement : m
Output per hour : 4.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.00 m
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm Ø High Density Polyethylene (HDPE) Pipe m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1001(1)c4, 1001(1)c5,1001(1)c6 and 1001(1)c7.

50 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(2) PVC/HDPE Fittings


Unit of Measurement : ea
Output per hour : 1 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

labor cost for these items are considered in the installation of pipes. Labor Rates are variable per Region/District
based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A

Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 ea
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. PVC/HDPE Fittings ( Elbow/ Clean Out/ Coupling/ Prices of materials are variable per Region/
ea 1.00
District based on the prevailing unit prices in
Wye/ Tee/ Reducer/ P-trap/ Bushing/ Plug) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. All items under Item No 1001(2) are considered as fittings. Use this cost sheet for Item Nos. 1001(2)a to 1001(2)w.

51 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(2) Concrete Gutter


Unit of Measurement : m
Output per hour :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Item 900 - Reinforced Concrete m3


b. Item 902 - Reinforcing Steel kg
a. Item 903 - Formworks and Falseworks m2

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. This item shall be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as
Item Nos. 900,902, and 903.

52 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(5) Catch Basin (Concrete/CHB)


Unit of Measurement : ea
Output : 1.00 ea

Designation Unit Quantity Unit Cost Amount (PhP)

A. Labor

a. Item 803 - Structure Excavation m3

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Item 900 - Reinforced Concrete m3


b. Item 902 - Reinforcing Steel kg
c. Item 1046 - CHB Wall m2

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. These items are variable in dimensions based on actual condition which combines component items, hence standard estimate
should be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as Items 803, 900, 902

53 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(7) Junction Box (Concrete/CHB)


Unit of Measurement : ea
Output : 1.00 ea

Designation Unit Quantity Unit Cost Amount (PhP)

A. Labor

a. Item 803 - Structure Excavation m3

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Item 900 - Reinforced Concrete m3


b. Item 902 - Reinforcing Steel kg
c. Item 1046 - CHB Wall m2

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. These items are variable in dimensions based on actual condition which combines component items, hence standard estimate
should be based on the standard Detailed Unit Price Analysis (DUPA) of each component items such as Items 803,900,902
and 1046.

54 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(8) Sewer Line Works


Unit of Measurement : l.s.
Output : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Amount shall be derived from individual DUPA for Item Nos. 1001(1)a, 1001(1)c, and 1001(2).

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Enumerate materials and quantities involved for Item Nos. 1001(1)a, 1001(1)c, and 1001(2).

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1001(1)a, 1001(1)c,
and 1001(2)

55 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1001(9) Storm Drainage and Downspout


Unit of Measurement : l.s.
Output : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Amount shall be derived from individual DUPA for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5),
1001(6) and 1001(7).

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Enumerate materials and quantities involved for Item Nos. 1001(1)c, 1001(3), 1001(4), 1001(5),
1001(6) and 1001(7).

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1001(1)c, 1001(3),
1001(4), 1001(5), 1001(6) and 1001(7).

56 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(1) 13 mm Ø - 50 mm Ø Galvanized Iron Pipe and Fittings


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 2.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 2.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a.13 mm Ø - 50 mm Ø Galvanized Iron Pipe and District based on the prevailing unit prices in
Fittings pc 1.00 the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1002(1)a, 1002(1)b, 1002(1)c, 1002(1)d, and 1002(1)e.

57 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(1) 65 mm Ø - 150 mm Ø Galvanized Iron Pipe and Fittngs


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.50 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.50 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.50

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 65 mm Ø - 150 mm Øx 6 m Galvanized Iron Pipe Prices of materials are variable per Region/
District based on the prevailing unit prices in
and Fittings pc 1.00 the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(1)f, 1002(1)g, 1002(1)h, and 1002(1)i.

58 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(2) Galvanized Iron Fittings


Unit of Measurement : pc
Output per hour : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

labor cost for these items are considered in the installation of pipes.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Galvanized Iron Fittings (Elbow/ Tee/ Reducer-Tee/ pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
Socket/ Coupling/ Reducer Coupling)
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(2)b to 1001(2)f.

59 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(2)a 13mmØ - 50mm ØPolyprophylene Random Copolymer (PPR-C) Pipe and Fittings, PN 16/ PN 20
Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.33 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.33 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.33

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 13 mm Ø - 50 mm Ø x 4.00 mPolyprophylene Prices of materials are variable per Region/


District based on the prevailing unit prices in
Random Copolymer (PPR-C) Pipe and Fittings, PN pc 1.00 the locality which include payment of local
16/ PN 20 taxes and hauling cost to the project site.
b. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(2)a2 to 1002(2)e3

60 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(2) 63mmØ - 100mm Ø Polyprophylene Random Copolymer (PPR-C) Pipe and Fittings PN 16/ PN 20
Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 63 mm Ø - 100 mm Ø x 4.00 m Polyprophylene Prices of materials are variable per Region/


District based on the prevailing unit prices in
Random Copolymer (PPR-C) Pipe and Fittings PN pc 1.00 the locality which include payment of local
16/ PN 20Copolymer (PPR-C) Pipe taxes and hauling cost to the project site.
b. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(2)f1 to 1002(2)h3.

61 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(3) Polyprophylene Random Copolymer (PPR-C) Fittings


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

labor cost for these items are considered in the installation of pipes Labor Rates are variable per Region/District
based on minimum
Minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output= 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Polyprophylene Random Copolymer (PPR-C) pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
Fittings (Elbow/ Tee/ Female Threaded Tee/ Female
the locality which include payment of local
Elbow/ Female Threaded Adaptor/ Male Threaded taxes and hauling cost to the project site.
Adaptor/ End Cap) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(3)b to 1001(3)l.

62 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(3) 13 mm Ø - 50 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue
Unit of Measurement : pc
Output per hour : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. 13 mm Ø - 50 mm Ø x 3 m Polyvinyl Chloride pc 1.00 District based on the prevailing unit prices in
(PVC) Pipe and Fittings, blue the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(3)a, 1002(3)b, 1002(3)c, 1002(3)d, and 1002(3)e.

63 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(3) 65 mm Ø - 100 mm Ø Polyvinyl Chloride (PVC) Pipe and Fittings, Blue
Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 LaborRates


Labor Ratesare variable
are perper
variable Region/District
Region/District
basedon
based onminimum
Minimumwagewage as as approved
approved by by
b. Skilled Laborer 1 0.75 DOLE.Refer to the Schedule of Labor Rates.
DOLE.
c. Unskilled Laborer 2 0.75

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. 65 mm Ø 100 mm Ø x 3 m Polyvinyl Chloride pc 1.00 District based on the prevailing unit prices in
(PVC) Pipe and Fittings, blue the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(3)f, 1002(3)g, and 1002(3)h.

64 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(4) Polyvinyl Chloride (PVC) Fittings, Blue


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor cost for these items are considered in the installation of pipes Labor Rates are variable per Region/District
based on minimum
Minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Polyvinyl Chloride (PVC) Fittings, Blue (Elbow/ pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
Tee/ Tee-Reducer/ Elbow Reducer/ Socket/ Coupling/
the locality which include payment of local
Reducer/ Male Threaded Adaptor/ Female Threaded taxes and hauling cost to the project site.
Adaptor/ Cap) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(4)b to 1001(4)l.

65 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(4) Plumbing Fixtures


Unit of Measurement : l.s.
Output : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Amount shall be derived from individual DUPA for Item Nos. 1002(5)a to 1002 (5)s.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivation for Item Nos. 1002(5)a to 1002 (5)s.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item Nos. 1002(5)a to
1002(5)s.

66 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Water Closet/ Urinal with Complete Accessories


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 2.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 2.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Water Closet / Urinal with complete accessories set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1002(5)a and 1002(10).

67 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(11) Kitchen Sink/Scrub Up Sink/Slop Sink with Complete Accessories
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 2.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 2.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Kitchen Sink/Scrub Up Sink/Slop Sink with Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
complete accessories the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(11)a to 1002(13).

68 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(14) Wall Hung/Countertop/Under Counter Lavatory with Complete Accessories
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 2.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 2.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Lavatory (Wall Hung/Countertop/Under Counter) set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(14)a to 1002(15)b.

69 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(16) Floor Drain Plates


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.40 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 0.40 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.40

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Floor Drain Plate set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

70 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Soap Holder ( Toilet Soap/ Liquid Soap)


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 0.75 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.75

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Soap Holder ( Toilet Soap/ Liquid Soap) set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(5)i and 1002(5)j.

71 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(5) Toilet Tissue Holder/Dispenser


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 0.75 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.75

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Toilet Tissue Holder/Dispenser set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(5)k and 1002(5)l.

72 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(17) Bidet/ Faucet/ Hose Bibb


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.40 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 0.40 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Bidet/ Faucet/ Hose Bibb set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1002(5)m, 1002(5)q, and 1002(5)r.

73 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(18) Stainless Steel Grab bar


Unit of Measurement : m
Output per hour : 0.45 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.45 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 40 mm Ø Stainless Steel Grab Bar m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

74 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(19) Shower head/ Shower Valve


Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Shower head/ Shower Valve set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

75 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(20) Facial Mirror


Unit of Measurement : m2
Output per hour : 0.4 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.4 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Facial Mirror m2 1.00
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

76 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(24) Cold Waterline Pipes and Fittings


Unit of Measurement : l.s.
Output per hour : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivation for Items 1002(1) to Items 1002(5)

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivation for Items 1002(1) to Items 1002(5)

Sub - Total for B


C. Total (A + B)
D. Output per Hour =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivation for Items 1002(1) to Items 1002(5)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1002(1)a to
Item No. 1001(5)

77 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1002(25) Hot Waterline Pipes and Fittings


Unit of Measurement : l.s.
Output per hour : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivation for Item Nos. 1002(3)a to 1002(3)l.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivation for Item Nos. 1002(3)a to 1002(3)l.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No.1002(3)a to 1002(3)l.

78 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1) 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood
on Metal Frame Ceiling
Unit of Measurement : m2
Output per hour : 1.243 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
for Installation :
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.243 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. 4.5mm Fiber Cement Board/ 4.5 mm Marine
Plywood/ 6 mm Marine Plywood/ 6mm Ordinary pc 0.365
Plywood
b.Metal Furring (size variable on plan and
pc 1.131
and specifications ) 3m length
c. Carrying Channels (size variable depends on plans Prices of materials are variable per Region/
pc 0.357 District based on the prevailing unit prices in
and specifications)
the locality which include payment of local
d. Hanger Bars/Rod (size variable depends on plans taxes and hauling cost to the project site.
pc 1 Refer to the Construction Material Price Data
and specifications)
established quarterly by Central Price
e. Channel clip pc 6 Monitoring Committee.
f. Wall Angle pc 0.238
g. Rivets pc 14
h. 1" Metal Screw pcs 4
Note:
Quantities were derived from plans and
specificartions of standard school building with carrying
channels spaced by 1.20 m and metal furring spaced by
0.40 m on center.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1003(1)a1, 1003(1)b1, 1003(1)c1, and 1003(1)d1.

79 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)a 4.5mm Fiber Cement Board/ 4.5 mm Marine Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Plywood
in Wood Framing Ceiling
Unit of Measurement : m2
Output per hour : 1.489 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum
Minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.489 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. 4.5mm Fiber Cement Board/ 4.5 mm Marine
Plywood/ 6 mm Marine Plywood/ 6mm Ordinary Prices of materials are variable per Region/
pc 0.365
District based on the prevailing unit prices in
Plywood the locality which include payment of local
b. Good Lumber bd.ft 9.257 taxes and hauling cost to the project site.
c. Assorted Nails kg 0.139 Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
Note :
Quantities are derived from a ceiling system with
ceiling nailers spaced at 0.40 m on center

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1003(1)a2, 1003(1)b2, 1003(1)c2, and 1003(1)d2.

80 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(1)e Gypsum Board on Metal Frame Ceiling


Unit of Measurement : m2
Output per hour : 1.340 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor
for Installation
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
b. Skilled Laborer 1 1.00 based on minimum
Minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.340 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. Gypsum Board pc 0.365
b.Metal Furring (size variable on plan and pc 1.13
c. Carrying Channels (size variable depends on plans Prices of materials are variable per Region/
pc 0.36 District based on the prevailing unit prices in
and specifications)
the locality which include payment of local
d. Hanger Bars/Rod ((size variable depends on plans taxes and hauling cost to the project site.
pc 1.00
and specifications) Refer to the Construction Material Price Data
e. Channel clip pcs 6 established quarterly by Central Price
Monitoring Committee
f. Wall Angle pc 0.238
g. Rivets pcs 14
h. 1" metal screw pcs 4
Note:
Quantities were derived from plans and
specificartions of standard school building with carrying
channels spaced by 1.20 m and metal furring spaced by
0.40 m on center.
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

81 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1003(2) 4.5mm/ 6.0 mm Fiber Cement Board/ 4.5mm/ 6.0 mm 4' X 8' thk fiber cement board/ 4.5mm Marine
Plywood/ 6.0 mm Marine Plywood/ 6.0 mm Ordinary Plywood on Metal Frame Double Wall Partition

Unit of Measurement : m2
Output per hour : 0.776 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 3 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.776 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
a. 4.5mm/ 6.0 mm 4' X 8' thk fiber cement board/ Prices of materials are variable per Region/
4.5mm Marine Plywood/ 6.0 mm Marine Plywood/ 6.0 pcs 0.730 District based on the prevailing unit prices in
mm Ordinary Plywood the locality which include payment of local
taxes and hauling cost to the project site.
b. Metal Studs (size variable depends on plan and Refer to the Construction Material Price Data
specs.) 3 m length pcs 1.181
established quarterly by Central Price
c. Rivets pcs 117.00 Monitoring Committee.
d. 1" Metal Screw pcs 4.00

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1003(2)a1, 1003(2)b1, 1003(2)c1, 1003(2)d1 and 1003(2)e1.

82 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1004(2) Finishing Hardware


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor cost for these items are considered in the installation of Doors, Windows, and other Fabricated Materials

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Prices of materials are variable per Region/
District based on the prevailing unit prices in
a. Finishing Hardwares (Lockset/Latches, Bolts, Door set 1.00 the locality which include payment of local
Closer, Knobs/Handles/ Hinges/ Ladder/ Grab Bar) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1004(2)a to 1004(2)i.

83 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1005 Residential Casement Steel Windows/ Heavy Duty Side-hinged Ventilator/ Projected Ventilator/
Awning Ventilator/ Grille Window
Unit of Measurement : m2
Output per hour : 0.18 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.25


Minor Tools (10% of labor cost)

Note:
It is assumed that steel windows are already
fabricated. Thus, labor and equipment output are
based on installation time only.

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.18 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Residential Casement Steel Windows/ Heavy Duty 1.00
District based on the prevailing unit prices in
Side-hinged Ventilator/ Projected Ventilator/ Awning the locality which include payment of local
Ventilator/ Grille Window taxes and hauling cost to the project site.
b. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Use this cost sheet for Item Nos. 1005(1), 1005(2), 1005(3), 1005(4), and 1005(7).

84 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006 Hollow Steel Door/ Steel Flush Door/ Grille Door/ Steel Louver Door
Unit of Measurement : m2
Output per hour : 0.26 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor


Labor Rates
Rates are
are variable
variable per
per Region/District
Region/District
based
based on
on minimum
Minimum wage
wage as
as approved
approved by
b. Skilled Laborer 1 1.00 by
DOLE.
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.25


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.26 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Hollow Steel Door/ Steel Flush Door/ Grille Door/
m2 1.00 District based on the prevailing unit prices in
Steel Louver Door the locality which include payment of local
b. Consumables (3% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1006(1), 1006(2), 1006(3) and 1006(4).

85 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1006(5) Fire Rated Fire Exit Steel Door


Unit of Measurement : m2
Output per hour : 0.26 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.25


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.26 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Fire rated Fire Exit Steel Door 1.00
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

86 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1007 Aluminum Glass Door (Sliding Type/Swing Type)


Unit of Measurement : m2
Output per hour : 0.26 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.26 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Aluminum Glass Door (Sliding Type/Swing Type) 1.00
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1007(1)a and 1007(1)b.

87 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1008 Aluminum Glass Window (Sliding/ Casement/ Awning/ Fixed Type)
Unit of Measurement : m2
Output per hour : 0.36 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.36 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Aluminum Glass Window (Sliding/ Casement/ Prices of materials are variable per Region/
District based on the prevailing unit prices in
Awning/ Fixed Type) m2 1.00 the locality which include payment of local
b. Consumables (3% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1008(1)a, 1008(1)b, 1008(1)c and 1008(1)d.

88 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(1) Frames (Jambs, Sill, Head, Transoms and Mullions)
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 2.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 2.00

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Jambs, Sill, Head, Transoms and Mullion set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

89 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)a Hollow Core Flush Door


Unit of Measurement : m2
Output per hour : 0.32 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.32 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a.Hollow Core Flush Door 1.00
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost 0 (G + H + I + J)

90 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1010(2)b Wooden Panel Door


Unit of Measurement : m2
Output per hour : 0.36 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.32 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Wooden Panel Door 1.00
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

91 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1011(1) Steel/ Aluminum Roll Up Door


Unit of Measurement : set
Output : 1.00 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 14.71 based on minimum
Minimum wage as approved by
c. Unskilled Laborer 1 14.71 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel/ Aluminum Roll Up Door Set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

92 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1012(1) Tempered Glass Door (10 mm/ 12mm)


Unit of Measurement : m2
Output per hour : 0.26 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.26 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Tempered Glass Door (10 mm/ 12mm) 1.00
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1012(1)d1 and 1012(1)d2.

93 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1012(1) Tempered Glass Windows (8 mm/ 10mm)


Unit of Measurement : m2
Output per hour : 0.36 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.36 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

m2 Prices of materials are variable per Region/


a. Tempered Glass Windows (8 mm/ 10mm) 1.00
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1012(1)e1 and 1012(1)e2.

94 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(1) Corrugated Metal Roofing


2
Unit of Measurement : m
2
Output per hour : 2.076 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 3 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.076 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Corrugated Roofing Sheet m2 1.05
District based on the prevailing unit prices in
b. teckscrew/J-bolt with washers pcs 10 the locality which include payment of local
c. Consumables ( 3% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

95 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2) Fabricated Metal Roofing Accessory (Ridge/Hip Rolls/Flashings/Counter Flashing/Valley Roll)
Unit of Measurement : m
Output per hour : 10.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 10.6 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Ridge/Hip Rolls/Flashings/Valley Roll/ Counter
m 1.05 District based on the prevailing unit prices in
Flashing (Gauge 26) the locality which include payment of local
b. Blind Rivets pcs 19.00 taxes and hauling cost to the project site.
c. Consumables (3% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this costing sheet for Item Nos. 1013(2)a, 1013(2)b, 1013(2)e, and 1013(2)f.

96 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1013(2)c Fabricated Metal Roofing Accessory (Gutter)


Unit of Measurement : m
Output per hour : 11.80 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 11.80 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Gutter(Gauge 26) m 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. 12" x 1" Plain GI Strap pcs 3.00 the locality which include payment of local
c. Blind Rivets pcs 16.00 taxes and hauling cost to the project site.
d. Consumables (3% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

97 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014 Prepainted Metal Sheets (Corrugated, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk)
2
Unit of Measurement : m
2
Output per hour : 2.076 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00
based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 2 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.076 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Prepainted Metal Sheets (Corrugated, Short District based on the prevailing unit prices in
2
Span/ Long Span, below 0.427 thk/ above 0.427 m 1.05 the locality which include payment of local
thk) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
b. teckscrew/J-bolt with washers pcs 10
established quarterly by Central Price
c. Consumables ( 3% of material cost) Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1014(1)a and 1014(2)a.

98 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1014 Prepainted Metal Sheets (Rib Type, Short Span/ Long Span, below 0.427 thk/ above 0.427 thk)
2
Unit of Measurement : m
Output per hour : 2.769 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.769 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Prepainted Metal Sheets (Rib Type, Short Span/ 2 District based on the prevailing unit prices in
m 1.00 the locality which include payment of local
Long Span, below 0.427 thk/ above 0.427 thk)
taxes and hauling cost to the project site.
b. teckscrew/J-bolt with washers pcs 10.00 Refer to the Construction Material Price Data
c. Consumables (3% of material cost) established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1014(1)b and 1014(2)b.

99 Part C - Finishing
DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(1)a Waterproofing Cement Base


2
Unit of Measurement : m
Output per hour : 1.875 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
2
D. Output per Hour = 1.875 m
E. Direct Unit Cost (C ÷ D)
Unit Quantity Unit Cost Amount (PhP)
Name and Specification

F. Materials

Prices of materials are variable per Region/


a. Cement-based waterproofing m2 1.05
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

100 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(1)b Liquid Waterproofing


Unit of Measurement : m2
2
Output per hour : 5.772 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.772 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Primer Coat gal 0.04 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Liquid Waterproofing gal 0.03 the locality which include payment of local
c. Consumables (3% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

101 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1016(2) Built-up and Preformed Membrane


2
Unit of Measurement : m
Output per hour : 4.805 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 Labor on
Rates are variable perapproved
Region/District
based minimum wage as by
b. Skilled Laborer 1 1.00 based on
DOLE. Minimum
Refer wage as approved
to the Schedule by
of Labor Rates.
c. Unskilled Laborer 1 1.00 DOLE.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.805 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials
Prices of materials are variable per Region/
a. Asphalt Primer gal 0.10 District based on the prevailing unit prices in
2
b. Preformed Membrane m 1.05 the locality which include payment of local
c. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

102 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1017 50mm ø - 100mm ø Roof Drain/Canopy Drain/ Gutter Drain with Strainer
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 0.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Unskilled Laborer 1 0.50 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50mm ø - 100mm ø Roof Drain/Canop Drain/ Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
Gutter Drain with Strainer the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1017(1)a1, 1017(1)a2, 1017(1)a3, 1017(1)a4, 1017(2)b1, 1017(2)b2, 1017(2)b3,
1017(2)b4, 1017(3)c1, 1017(3)c2 and 1017(3)c3

103 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018(1) Glazed Tiles and Trims


Unit of Measurement : m2
2
Output per hour : 1.365 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00
based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 5 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
2
D. Output per Hour = 1.365 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Glazed Tiles m2 1.050
District based on the prevailing unit prices in
b. Cement bags 0.325 the locality which include payment of local
c. Sand m3 0.026 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Tile Grout bags 0.125
established quarterly by Central Price
e. Tile Adhesive (25 kg) bags 0.143
f. Consumables (3% of Material Cost)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

104 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1018 Unglazed Tiles/ Granite Tiles/ Synthetic Granite Tiles
2
Unit of Measurement : m
Output per hour : 1.95 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
c. Unskilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Unglazed Tiles/ Granite Tiles/ Synthetic Granite m2 1.050
District based on the prevailing unit prices in
Tiles
b. Cement bags 0.325 the locality which include payment of local
c. Sand m3 0.026 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Tile Grout bags 0.125
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this costing sheet for Item Nos. 1018(2), 1018(3) and 1018(4).

105 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1019(1) Wood Tiles (Narra, Tanguile, others)


2
Unit of Measurement : m
Output per hour : 1.56 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 5 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.56 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Wood Tiles m2 1.050 District based on the prevailing unit prices in
b. Glue Adhesive L 0.500 the locality which include payment of local
c. Cement bags 0.325 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Sand m3 0.026 established quarterly by Central Price
e. Polyurethane Floor Varnish Sealer L 0.400 Monitoring Committee.
f. Polyurethane Floor Varnish Topcoat L 0.200
g. Polyurethane Reducer L 0.06
h. Consumables (5% of material cost)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

106 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1019(1)d Laminated Wood Tiles


Unit of Measurement : m2
Output per hour : 1.95 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 5 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Laminated Wood Tiles m2 1.050
District based on the prevailing unit prices in
b. Glue Adhesive L 0.500 the locality which include payment of local
c. Cement bags 0.325 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Sand m3 0.026
established quarterly by Central Price
e. Consumables (5% of material cost) Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

107 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1020(1) Vinyl Tiles


2
Unit of Measurement : m
2
Output per hour : 4.285 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 2 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.385 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Vinyl Tiles 2 Prices of materials are variable per Region/


m 1.050
District based on the prevailing unit prices in
b. Glue Adhesive L 0.500 the locality which include payment of local
c. Cement bags 0.726 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
d. Sand m3 0.055
established quarterly by Central Price
e. Consumables (3% of material cost) Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

108 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(1)a Plain Cement Floor Fnish


2
Unit of Measurement : m
Output per hour : 5.95 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 3 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bags 0.726 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Sand m3 0.055 the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

109 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1021(3) Floor Topping


2
Unit of Measurement : m
Output per hour : 6.545 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 6.545 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bags 0.693 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Sand m3 0.055 the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1021(3)a and 1021(3)b.

110 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1023(1) Granolithic Marble Work


2
Unit of Measurement : m
Output per hour : 5.95 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum
Minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Marble chips 3 Prices of materials are variable per Region/


m 0.726
District based on the prevailing unit prices in
b. Portland cement bags 0.055 the locality which include payment of local
c. Divider strips m 1.00 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

111 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1024(1) Pea Gravel Finish


Unit of Measurement : m2
2
Output per hour : 1.785 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum
Minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bags 0.795 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Pea Gravel m3 0.013 the locality which include payment of local
c. Sand m3 0.039 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitring Committee
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

112 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1026(1) Pebble Washout Finish


2
Unit of Measurement : m
2
Output per hour : 1.785 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on Minimum
Region/District based
wage
on minimum
as approved
wage
byas
c. Unskilled Laborer 2 1.00 DOLE. by DOLE. Refer to the Schedule
approved
of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.95 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bags 0.795 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Pea Gravel m3 0.013 the locality which include payment of local
c. Sand m3 0.039 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

113 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1027(1) Cement Plaster Finish


2
Unit of Measurement : m
Output per hour : 7.125 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Note :
In cases of outside wall plastering utilization of
gondolla as support equipment is recommended.

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 7.125 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cement bags 0.330 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Sand cu.m. 0.027 the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : For Exterior Plastering support equipment shall be utilized.

114 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)a Painting Works (Masonry Painting)


Unit of Measurement : m2
2
Output per hour : 2.10 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.10 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Concrete Neutralizer gal 0.02 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Concrete Sealer/Primer gal 0.04 the locality which include payment of local
c. Patching Compound gal 0.05 taxes and hauling cost to the project site.
d. Semi Gloss Latex (one coat only) gal 0.08 Refer to the Construction Material Price Data
e. Consumables (5% of material cost) established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)

K. Total Unit Cost (G + H + I + J)

115 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)b Painting Works (Wood Painting)


Unit of Measurement : m2
2
Output per hour : 1.89 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
2
D. Output per Hour = 1.89 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazzing Putty gal 0.05 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Flat Wall Enamel gal 0.04 the locality which include payment of local
c. Enamel Quick Dry gal 0.04 taxes and hauling cost to the project site.
d. Paint Thinner gal 0.01 Refer to the Construction Material Price Data
e. Tinting Color (Optional) pint 0.01 established quarterly by Central Price
Monitoring Committee.
f. Consumables (5% of material cost)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

116 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(1)c Painting Works (Metal Painting)


Unit of Measurement : m2
2
Output per hour : 2.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.00 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Red Oxide Primer gal 0.04 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Enamel Paint gal 0.10 the locality which include payment of local
c. Paint thinner lit 0.25 taxes and hauling cost to the project site.
d. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.
e. Tinting Color (Optional) pint 0.010

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

117 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(2) Varnishing Works


2
Unit of Measurement : m
2
Output per hour : 3.945 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.945 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a.Varnish gal 0.04
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

118 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1032(4) Ducco Finish


2
Unit of Measurement : m
2
Output per hour : 1.512 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.512 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Glazzing Putty gal 0.05 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Flat Wall Enamel gal 0.04 the locality which include payment of local
c. Enamel Quick Dry gal 0.04 taxes and hauling cost to the project site.
d. Paint Thinner gal 0.01 Refer to the Construction Material Price Data
e. Tinting Color (Optional) pint 0.01 established quarterly by Central Price
Monitoring Committee.
f. Consumables (5% of material cost)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

119 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1034(1) Damproofing ( Polyethylene Sheets)


2
Unit of Measurement : m
2
Output per hour : 37.559 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 37.559 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 6 mils Polyethylene Sheets 2 Prices of materials are variable per Region/


m 1.000
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

120 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1038(1) Reflective Insulation


2
Unit of Measurement : m
Output per hour : 5.56 m2

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.56 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Reflective Insulation m2 1.000
District based on the prevailing unit prices in
b. Consumbles (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

121 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1042(1) Stainless Steel Door and Frames


2
Unit of Measurement : m
2
Output per hour : 0.32 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.32 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Stainless Steel Doors and Frames m2 1.000
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

122 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1043(1) PVC Doors and Frames


Unit of Measurement : m2
2
Output per hour : 0.315 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.315 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. PVC Doors and Frames m2 1.000
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

123 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1045(1) Perforated Aluminum Ceiling Panels


2
Unit of Measurement : m
2
Output per hour : 0.763 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.763 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Perforated Aluminum Ceiling Pannel with frames m2 1.000
District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

124 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046 100 mm CHB Non Load Bearing/Load Bearing (including Reinforcing Steel)
2
Unit of Measurement : m
2
Output per hour : 3.825 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 136.93 136.93


b. Skilled Laborer 2 1.00 100.61 201.22
c. Unskilled Laborer 4 1.00 77.86 311.44

Sub - Total for A 649.59


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 3 1.00 172.00 516.00


Minor Tools (10% of labor cost)

Sub - Total for B 516.00


C. Total (A + B) 1,165.59
D. Output per Hour = 3.825 m2
E. Direct Unit Cost (C ÷ D) 101.58
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 100 mm thk CHB (Non-Load Bearing/Load pcs 13.00


b. Cement bags 0.525
c. Sand cu.m. 0.04
d. Reinforcing Steel kgs 3.24*
e. #16 Tie wire kgs 0.05

*Quantity derived from 10mm Ø. bars spaced by 0.4 m


vertically and every 3 layers of CHB

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. This cost sheet shall be used for Item Nos. 1046(1)a and 1046(2)a.

125 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1046 150mm CHB Non-LoadBearing/ Load Bearing (including Reinforcing Steel)
2
Unit of Measurement : m
2
Output per hour : 3.180 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
c. Unskilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. One-bagger mixer 3 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.180 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 150 mm thk CHB (Load Bearing) pcs 13.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Cement bags 1.500 the locality which include payment of local
c. Sand cu.m. 0.04 taxes and hauling cost to the project site.
d. Reinforcing Steel kgs 3.24* Refer to the Construction Material Price Data
e. #16 Tie wire kgs 0.05 established quarterly by Central Price
Monitoring Committee.

*Quantity derived from 10mm Ø. bars spaced by 0.4 m


vertically and every 3 layers of CHB

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. This cost sheet shall be used for Item Nos. 1046(1)b and 1046(2)b.

126 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(1) Structural Steel Roof Framing


Unit of Measurement : l.s.
Output per hour : l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivations for Item Nos. 1047(2) - 1047(6)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivations for Item Nos. 1047(2) - 1047(6)

Sub - Total for B


C. Total (A + B)
D. Output per Hour =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivations for Item Nos. 1047(2) - 1047(6)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

127 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)a Structural Steel Roof Framing


Unit of Measurement : kg
Output per hour : 85.00 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Fabrication
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 3 1.00

Erection
a. Skilled Laborer 4 0.49
b. Unskilled Laborer 4 0.49

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75


b. Cutting Outfit 1 0.25

Minor Tools (10 % of labor cost)

Lifting Equipment considered under support equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 85.00 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Framing including cross kg 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Acetylene kg 0.011 the locality which include payment of local
c. Oxygen kg 0.022 taxes and hauling cost to the project site.
d. Welding Rod kg 0.020 Refer to the Construction Material Price Data
e. Consumables (5% of material cost) established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

128 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)b Structural Steel Roof Truss


Unit of Measurement : kg
Output per hour : 85.00 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Fabrication
a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
b. Skilled Laborer 3 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 3 1.00

Erection
a. Skilled Laborer 4 0.49
b. Unskilled Laborer 4 0.49

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 1 0.75


b. Cutting Outfit 1 0.25
Lifting Equipment considered under support equipment 1 0.49
Minor Tools (10 % of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 85.00 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Truss kg 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Acetylene kg 0.011 the locality which include payment of local
c. Oxygen kg 0.022 taxes and hauling cost to the project site.
d. Welding Rod kg 0.020 Refer to the Construction Material Price Data
e. Consumables (5% of material cost) established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

129 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(2)c Structural Steel Purlins


Unit of Measurement : kg
Output per hour : 90.45 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 3 1.00 based on minimum wage as approved by
c. Unskilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine 3 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 90.45 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Structural Steel Purlins kg 1.05 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Welding Rod kg 0.020 the locality which include payment of local
c. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

130 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)a Metal Structure Accessories (Anchor Bolts)


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.10 Labor Rates are variable per Region/District


b. Skilled Laborer 1 0.10 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 0.10 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 90.45 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Anchor Bolt pc 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

131 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)b Metal Structure Accessories (Sagrods)


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.10 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 0.10 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 0.10 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sagrod with nuts and bolts pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

132 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)c Metal Structure Accessories (Turnbuckle)


Unit of Measurement : pc
Output per hour : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.15 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 0.15 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 0.15 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Standard Turnbuckle pc 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

133 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(3)d Metal Structure Accessories (Crossbracing)


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 0.25 based on minimum wage as approved by
b. Skilled Laborer 1 0.25 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.25

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cross Bracing pc 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

134 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(4) Metal Structure Accessories (Crossbracing)


Unit of Measurement : kg
Output per hour : 12.995 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per


b. Skilled Laborer 1 1.00 Region/District based on minimum wage as
approved by DOLE. Refer to the Schedule
c. Unskilled Laborer 1 1.00
of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Cross Bracing kg 1.05 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

135 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1047(5) Metal Structure Accessories (Steel Plates)


Unit of Measurement : kg
Output per hour : 12.995 kg

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
c. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 12.995 kg
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Plates kg 1.05 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Consumables (3% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

136 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1048(1)a Carbon Fiber (1 layer)


2
Unit of Measurement : m
2
Output per hour : 1.20 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


Site Preparation based on minimum wage as approved by
b. Skilled Laborer 2 0.71 DOLE. Refer to the Schedule of Labor
Rates.
c. Unskilled Laborer 4 0.71
Application
a. Skilled Laborer 2 1.00
b. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Surface Preparation
a. Portable Grinder 2 0.40 See latest ACEL rental rates.
b. Jack Hammer 1 0.20
c. Air Compressor 1 0.40
c. Speed Ventilator 1 0.40
d. Electric Drill 1 0.20
e. Chipping Gun 1 0.10
f. Paddle Mixer 1 0.20
g. Generator Set (20KVA) 1 0.10
Application
a.Saturator Machine 1 0.10
b. Generator Set (20 KVA) 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Surface Preparation Prices of materials are variable per Region/


District based on the prevailing unit prices in
a. Clear Epoxy A gal 0.27 the locality which include payment of local
b. Clear Epoxy B gal 0.13 taxes and hauling cost to the project site.
c. Kalcomine sack 0.18 Refer to the Construction Material Price Data
d. Cup Wheel pc 0.30 established quarterly by Central Office Price
Monitoring Committee.
e. Diamond Disk pc 0.10
Application
a. Carbon Fiber m2 1.05

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

137 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1048(2) Glass Fiber


2
Unit of Measurement : m
2
Output per hour : 1.20 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


Site Preparation based on minimum wage as approved by
b. Skilled Laborer 2 0.71 DOLE. Refer to the Schedule of Labor
Rates.
c. Unskilled Laborer 4 0.71
Application
a. Skilled Laborer 2 1.00
b. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment
Surface Preparation
a. Portable Grinder 2 0.40 See latest ACEL rental rates.
b. Jack Hammer 1 0.20
c. Air Compressor 1 0.40
c. Speed Ventilator 1 0.40
d. Electric Drill 1 0.20
e. Chipping Gun 1 0.10
f. Paddle Mixer 1 0.20
g. Generator Set (20KVA) 1 0.10
Application
a.Saturator Machine 1 0.10
b. Generator Set (20 KVA) 1 0.10

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Surface Preparation Prices of materials are variable per Region/


District based on the prevailing unit prices in
a. Clear Epoxy A gal 0.27 the locality which include payment of local
b. Clear Epoxy B gal 0.13 taxes and hauling cost to the project site.
c. Kalcomine sack 0.18 Refer to the Construction Material Price Data
d. Cup Wheel pc 0.30 established quarterly by Central Office Price
Monitoring Committee.
e. Diamond Disk pc 0.10
Application
a. Glass Fiber m2 1.05

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

138 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1049(1) Jet Grouting (0.80 m diameter)


Unit of Measurement : m
Output per hour : 1.18 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
c. Unskilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Jetting Machine 1 1.00 See latest ACEL rental rates.


b. Air Compressor 12 Bars/600 CFM 1 1.00
c. Water Tank/Pump 1 1.00
d. Agitator 1 1.00
e. Generator/Power Supply 1 1.00
f. High Pressure Pump 1 1.00

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m2
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Portland Cement bags 14.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Additives L 3.50 the locality which include payment of local
c. Consumables (5% of Material Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

139 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(4)a.1 Precast Concrete Piles, furnished (400mm x 400mm -type A)
Unit of Measurement : m.
Output per hour : 2.50 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 4 1.00 based on minimum wage as approved by
c. Unskilled Laborer 8 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Payloader (1.50 m3), LX80-2C 1 0.05


b. Concrete Vibrator 1 0.10
c. Plate Compactor (for Casting Bed) 1 0.28
d. Bar Bender 1 0.28
e. Bar Cutter 1 0.28
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.50 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* cu.m 0.168 Prices of materials are variable per Region/
b. Reinforced Steel Bar, Grade 60 kg. 40.45 District based on the prevailing unit prices in
the locality which include payment of local
c. Tie Wire #16 (2% of RSB) kg. 0.809
taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd.ft 15.333 Refer to the Construction Material Price Data
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.268 established quarterly by Central Price
f. Assorted CWN (1kg./100bd.ft of Lumber) kg. 0.163 Monitoring Committee.

Casting Bed
a. Ready Mix Concrete Class B cu.m 0.03
b. Good Lumber bd.ft 1.00
c. Base Course cu.m 0.06

Note:
If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

140 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(4)a.2 Precast Concrete Piles, furnished (400mm x 400mm -type B)
Unit of Measurement : m.
Output per hour : 2.50 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 8 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Payloader (1.50 m ), LX80-2C 1 0.05
b. Concrete Vibrator 1 0.10
c. Plate Compactor (for Casting Bed) 1 0.28
d. Bar Bender 1 0.28
e. Bar Cutter 1 0.28
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.50 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* cu.m 0.168 Prices of materials are variable per Region/
b. Reinforced Steel Bar, Grade 60 kg. 48.69 District based on the prevailing unit prices in
the locality which include payment of local
c. Tie Wire #16 (2% of RSB) kg. 0.974 taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd.ft 15.333 Refer to the Construction Material Price Data
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.268 established quarterly by Central Price
f. Assorted CWN (1kg./100bd.ft of Lumber) kg. 0.163 Monitoring Committee.

Casting Bed
a. Ready Mix Concrete Class B cu.m 0.03
b. Good Lumber bd.ft 1.00
c. Base Course cu.m 0.06

Note:
If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

141 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(4)b.1 Precast Concrete Piles, furnished (450mm x 450mm -type C)
Unit of Measurement : m.
Output per hour : 2.30 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 8 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Payloader (1.50 m ), LX80-2C 1 0.05
b. Concrete Vibrator 1 0.10
c. Plate Compactor (for Casting Bed) 1 0.27
d. Bar Bender 1 0.27
e. Bar Cutter 1 0.27
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.30 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* cu.m 0.213 Prices of materials are variable per Region/
b. Reinforced Steel Bar, Grade 60 kg. 50.040 District based on the prevailing unit prices in
the locality which include payment of local
c. Tie Wire #16 (2% of RSB) kg. 1.001
taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd.ft 17.25 Refer to the Construction Material Price Data
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.30 established quarterly by Central Price
f. Assorted CWN (1kg./100bd.ft of Lumber) kg. 0.183 Monitoring Committee.

Casting Bed
a. Ready Mix Concrete Class B cu.m 0.033
b. Good Lumber bd.ft 1.00
c. Base Course cu.m 0.07
Note:
If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

142 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(4)b.2 Precast Concrete Piles, furnished (450mm x 450mm -type D)
Unit of Measurement : m.
Output per hour : 2.30 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 8 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Payloader (1.50 m ), LX80-2C 1 0.05
b. Concrete Vibrator 1 0.10
c. Plate Compactor (for Casting Bed) 1 0.27
d. Bar Bender 1 0.27
e. Bar Cutter 1 0.27
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.30 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix concrete, Class AA-27.60Mpa @ 28D* cu.m 0.213 Prices of materials are variable per Region/
b. Reinforced Steel Bar, Grade 60 kg. 62.46 District based on the prevailing unit prices in
the locality which include payment of local
c. Tie Wire #16 (2% of RSB) kg. 1.249 taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd.ft 17.25 Refer to the Construction Material Price Data
e. Marine Plywood, 1/2" x 4' x 8' - 4 uses pc 0.30 established quarterly by Central Price
f. Assorted CWN (1kg./100bd.ft of Lumber) kg. 0.183 Monitoring Committee.

Casting Bed
a. Ready Mix Concrete Class B cu.m 0.033
b. Good Lumber bd.ft 1.00
c. Base Course cu.m 0.07
Note:
If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

143 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(5)a Precast, Prestressed Concrete Piles, furnished (400 mm x 400 mm)
Unit of Measurement : m.
Output per hour : 48.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 2 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 48.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Precast, Prestressed Concrete Piles m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
(delivered at site)
the locality which include payment of local
Miscellaneous (2% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

144 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(5)b Precast, Prestressed Concrete Piles, furnished (450 mm x 450 mm)
Unit of Measurement : m.
Output per hour : 48.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 48.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Precast, Prestressed Concrete Piles m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
(delivered at site)
the locality which include payment of local
Miscellaneous (2% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

145 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(6) Structural Steel Sheet Piles, furnished


Unit of Measurement : m.
Output per hour : 72.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 2 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 72.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Sheet Pile KSP II (delivered at site) kg. 48.00 Prices of materials are variable per Region/
Miscellaneous (2% of material cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

146 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(7)a Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m)
Unit of Measurement : m.
Output per hour : 1.90 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 8 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Payloader (1.50 m3), LX80-2C 1 0.03


b. One Bagger Mixer 1 0.25
c. Concrete Vibrator 1 0.25
d. Water Truck/Pump (16000 L) 1 0.03
e. Bar Cutter 1 0.15
f. Bar Bender 1 0.15
g. Plate Compactor (5 hp), for Casting Bed 1 0.03
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.90 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar kg. 41.64 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Cement bag 1.66
the locality which include payment of local
c. Sand m3 0.09 taxes and hauling cost to the project site.
d. Gravel m3 0.18 Refer to the Construction Material Price Data
established quarterly by Central Price
e. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.24
f. Good Lumber - 4 uses bd-ft 12.40
g. #16 GI Tie Wire (2% of RSB) kg 0.83
h. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.12

Casting Bed
a. Cement bag 0.296
b. Sand m3 0.019
c. Gravel m3 0.037
d. Good Lumber - 4 uses bd.ft 1.00
e. Base Course m3 0.08
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

147 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(7)b Precast Concrete Sheet Piles, furnished (0.50 m x 0.35 m), (Ready Mix Concrete)
Unit of Measurement : m.
Output per hour : 2.30 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 8 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

3
a. Payloader (1.50 m ), LX80-2C 1 0.03
b. Concrete Vibrator 1 0.10
c. Plate Compactor (5 hp), for Casting Bed 1 0.03
d. Bar Cutter 1 0.22
e. Bar Bender 1 0.22
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.30 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar kg. 41.64 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Ready Mix Concrete, fc'=27.60 Mpa m3 0.18
the locality which include payment of local
c. Plywood, 1/2" x 4' x 8' - 4 uses pc 0.24 taxes and hauling cost to the project site.
f. Good Lumber - 4 uses bd-ft 12.40 Refer to the Construction Material Price Data
g. #16 GI Tie Wire (2% of RSB) kg 0.83 established quarterly by Central Price
Monitoring Committee.
h. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.12

Casting Bed
3
a. Ready Mix Concrete, Class B m 0.037
d. Good Lumber - 4 uses bd-ft 1.00
e. Base Course m3 0.08

Note:
If no available Ready Mix Concrete at Project Site,
derive the cost of concrete using the Batching Plant or
One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

148 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(11) Steel Pipe Piles, furnished and driven


Unit of Measurement : m.
Output per hour : 3.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.58


b. Diesel Hammer (K25 or equivalent) 1 0.25
c. Drop Hammer 1 0.13
d. Welding Machine (500 A), Gas/Diesel Driven 1 0.08
e. Cutting Outfit 1 0.08
Minor Tools (5% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Tubular Pile (0.40 m Ø x 9.50 mm thk) m 1.00 Prices of materials are variable per Region/
(delivered at site) District based on the prevailing unit prices in
the locality which include payment of local
b. Welding Rod (1 kg/2000 kg of Steel) kg 0.048 taxes and hauling cost to the project site.
c. Oxygen/Acetylene (1 set/5000 kg of Steel) set 0.019 Refer to the Construction Material Price Data
d. Coco Log - 2 uses m 1.00 established quarterly by Central Price
e. Good Lumber (Falsework) - 4 uses bd-ft 16.00
f. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16
Miscellaneous (2% of Materials Cost)

Note:
Assumed weight of Tubular Pipe Pile is 95.93
kg/m

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

149 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(12) Structural Steel Sheet Piles, driven


Unit of Measurement : m.
Output per hour : 10.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 6 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 1.00


b. Diesel Hammer (K25 or equivalent) 1 1.00
c. Drop Hammer 1 1.00
d. Welding Machine (500 A), Gas/Diesel Driven 1 1.00
e. Cutting Outfit 1 0.50
Minor Tools (5% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 10.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Welding Rod (1 kg/2000 kg of Steel) kg 0.024 Prices of materials are variable per Region/
b. Oxygen/Acetylene (1 set/5000 kg of Steel) set 0.0096 District based on the prevailing unit prices in
the locality which include payment of local
c. Coco Log - 2 uses m 0.18 taxes and hauling cost to the project site.
d. Good Lumber - 4 uses bd-ft 1.55 Refer to the Construction Material Price Data
e. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.02 established quarterly by Central Price
Miscellaneous (2% of Materials Cost) Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

150 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(13) Precast Concrete Sheet Piles, driven


Unit of Measurement : m.
Output per hour : 2.80 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.56


b. Diesel Hammer (K25 or equivalent) 1 0.31
c. Drop Hammer 1 0.31
d. Jack Hammer 2 0.19
e. Air Compressor (356 - 450 cfm) 1 0.19
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.80 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 0.71 Prices of materials are variable per Region/
b. Good Lumber - 4 uses bd-ft 6.19 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.06 taxes and hauling cost to the project site.
d. Assorted CWN (1 kg/100 bd-ft of Lumber) kg 0.06 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

151 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(14)a Precast Concrete Piles, driven (soft strata)


Unit of Measurement : m.
Output per hour : 2.40 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.53


b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.40 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene kg 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

152 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(14)b Precast Concrete Piles, driven (hard strata)


Unit of Measurement : m.
Output per hour : 1.95 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.62


b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.95 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

153 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(15)a Precast, Prestressed Concrete Piles, driven (soft strata)
Unit of Measurement : m.
Output per hour : 2.40 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.53


b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.40 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

154 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(15)b Precast, Prestressed Concrete Piles, driven (hard strata)
Unit of Measurement : m.
Output per hour : 1.95 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 6 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.62


b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.95 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 1.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

155 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(16)a Test Piles, furnished and driven (type A, B, C or D), soft strata
Unit of Measurement : m.
Output per hour : 2.40 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.53


b. Diesel Hammer (K25 or equivalent) 1 0.27
c. Drop Hammer 1 0.13
d. Cutting Outfit 1 0.20
e. Jack Hammer 2 0.20
f. Air Compressor (356 - 450 cfm) 1 0.20
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.40 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 2.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16
taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
e. Fabricated RC Pile (delivered at site) m 1.00 established quarterly by Central Price
Monitoring Committee.
Note:
The unit cost of Fabricated RC Pile is dependent
on its type.
Please refer to the Direct Cost of
Item 1052(7)a

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

156 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(16)b Test Piles, furnished and driven (type A, B, C or D), hard strata
Unit of Measurement : m.
Output per hour : 1.95 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 6 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.62


b. Diesel Hammer (K25 or equivalent) 1 0.41
c. Drop Hammer 1 0.11
d. Cutting Outfit 1 0.16
e. Jack Hammer 2 0.16
f. Air Compressor (356 - 450 cfm) 1 0.16
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.95 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coco Log - 2 uses m 2.00 Prices of materials are variable per Region/
b. Good Lumber (Falsework) - 4 uses bd-ft 16.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Nail/Spike (1 kg/100 bd-ft of Lumber) kg 0.16 taxes and hauling cost to the project site.
d. Oxygen/Acetylene set 0.01 Refer to the Construction Material Price Data
e. Fabricated RC Pile (delivered at site) m 1.00 established quarterly by Central Price
Monitoring Committee.

Note:
The unit cost of Fabricated RC Pile is dependent
on its type.
Please refer to the Direct Cost of
Item 1052(7)a

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

157 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)a Concrete Piles cast in Drilled Holes, 0.80 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 1.58 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 6 1.00 Rates.
Fabrication of Cage Bar
d. Skilled Laborer 9.00 0.50
e. Unskilled Laborer 17.00 0.50

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.26


b. Crawler Crane (41 - 45 mt) 1 0.95
c. Crawler Crane (21 - 25 mt) 1 0.95
3
d. Dump Truck (12 yd ) 1 0.95
3
e. Payloader (1.50 m ), LX80-2C 1 0.95
f. Generator Set (300 KW) 1 0.95
g. Bentonite Bin 1 0.50
h. Bentonite Mixer 1 0.50
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.74
j. Water Truck (16000 L) 1 0.74
k. Bar Cutter 1 0.50
l. Bar Bender 1 0.50
m. Welding Machine (500A), Electric Driven 1 0.71
n. Cutting Outfit 1 0.71
o. Tremie Pipe Set 1 0.24
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.05
r. Air Compressor, Portable (126 - 160 cfm) 1 0.05
s. Lighting System/Tower Lights 1 0.95
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.58 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 0.55 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 205.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 4.10
taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.041 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.10 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

158 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)b Concrete Piles cast in Drilled Holes, 1.00 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 1.33 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 6 1.00 Rates.
Fabrication of Cage Bar
d. Skilled Laborer 9 0.56
e. Unskilled Laborer 16 0.56

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.31


b. Crawler Crane (41 - 45 mt) 1 0.96
c. Crawler Crane (21 - 25 mt) 1 0.96
3
d. Dump Truck (12 yd ) 1 0.96
3
e. Payloader (1.50 m ), LX80-2C 1 0.96
f. Generator Set (300 KW) 1 0.96
g. Bentonite Bin 1 0.53
h. Bentonite Mixer 1 0.53
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.78
j. Water Truck (16000 L) 1 0.78
k. Bar Cutter 1 0.56
l. Bar Bender 1 0.56
m. Welding Machine (500A), Electric Driven 1 0.73
n. Cutting Outfit 1 0.73
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126 - 160 cfm) 1 0.04
s. Lighting System/Tower Lights 1 0.96
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.33 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 0.86 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 253.59 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 5.07 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.051 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.13 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

159 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)c Concrete Piles cast in Drilled Holes, 1.20 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 1.09 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 8 0.60
e. Unskilled Laborer 15 0.60

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.35


b. Crawler Crane (41 - 45 mt) 1 0.96
c. Crawler Crane (21 - 25 mt) 1 0.96
3
d. Dump Truck (12 yd ) 1 0.96
3
e. Payloader (1.50 m ), LX80-2C 1 0.96
f. Generator Set (300 KW) 1 0.96
g. Bentonite Bin 1 0.56
h. Bentonite Mixer 1 0.56
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.82
j. Water Truck/Pump (16000 L) 1 0.82
k. Bar Cutter 1 0.60
l. Bar Bender 1 0.60
m. Welding Machine (500 A), Electric Driven 1 0.75
n. Cutting Outfit 1 0.75
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.25
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126- 160 cfm) 1 0.04
s. Lighting System/Tower Lights 1 0.96
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.09 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 1.24 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 304.30 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 6.09 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.06 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.15 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

160 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)d Concrete Piles cast in Drilled Holes, 1.50 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 0.81 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 7 0.65
e. Unskilled Laborer 13 0.65

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.39


b. Crawler Crane (41 - 45 mt) 1 0.97
c. Crawler Crane (21 - 25 mt) 1 0.97
3
d. Dump Truck (12 yd ) 1 0.97
3
e. Payloader (1.50 m ), LX80-2C 1 0.97
f. Generator Set (300 KW) 1 0.97
g. Bentonite Bin 1 0.61
h. Bentonite Mixer 1 0.61
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.86
j. Water Truck/Pump (16000 L) 1 0.86
k. Bar Cutter 1 0.65
l. Bar Bender 1 0.65
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.03
r. Air Compressor, Portable (126- 160 cfm) 1 0.03
s. Lighting System/Tower Lights 1 0.97
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.81 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 1.94 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Reinforcing Steel Bar * kg. 387.77
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 7.76 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.08 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.19 established quarterly by Central Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

161 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)e Concrete Piles cast in Drilled Holes, 1.80 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 0.62 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per


Region/District based on minimum wage as
b. Skilled Laborer 5 1.00 approved by DOLE. Refer to the Schedule
c. Unskilled Laborer 6 1.00 of Labor Rates.
Fabrication of Cage Bar
d. Skilled Laborer 6 0.68
e. Unskilled Laborer 11 0.68

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.42


b. Crawler Crane (41 - 45 mt) 1 0.98
c. Crawler Crane (21 - 25 mt) 1 0.98
3
d. Dump Truck (12 yd ) 1 0.98
3
e. Payloader (1.50 m ), LX80-2C 1 0.98
f. Generator Set (300 KW) 1 0.98
g. Bentonite Bin 1 0.64
h. Bentonite Mixer 1 0.64
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.90
j. Water Truck/Pump (16000 L) 1 0.90
k. Bar Cutter 1 0.68
l. Bar Bender 1 0.68
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.02
r. Air Compressor, Portable (126- 160 cfm) 1 0.02
s. Lighting System/Tower Lights 1 0.98
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.62 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 2.80 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Reinforcing Steel Bar * kg. 451.98
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 9.04 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.09 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.23 established quarterly by Central Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

162 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(17)f Concrete Piles cast in Drilled Holes, 2.00 m. Ø, fc' = 28 MPa (ordinary soil condition)
Unit of Measurement : m
Output per hour : 0.53 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 5 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 5 0.70
e. Unskilled Laborer 10 0.70

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.44


b. Crawler Crane (41 - 45 mt) 1 0.98
c. Crawler Crane (21 - 25 mt) 1 0.98
3
d. Dump Truck (12 yd ) 1 0.98
3
e. Payloader (1.50 m ), LX80-2C 1 0.98
f. Generator Set (300 KW) 1 0.98
g. Bentonite Bin 1 0.65
h. Bentonite Mixer 1 0.65
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.91
j. Water Truck/Pump (16000 L) 1 0.91
k. Bar Cutter 1 0.70
l. Bar Bender 1 0.70
m. Welding Machine (500 A), Electric Driven 1 0.77
n. Cutting Outfit 1 0.77
o. Tremie Pipe Set 1 0.21
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.02
r. Air Compressor, Portable (126- 160 cfm) 1 0.02
s. Lighting System/Tower Lights 1 0.98
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.53 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 3.46 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 490.33 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 9.81
taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.098 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.25 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.)

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

163 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(18)a Concrete Piles cast in Steel Shells, furnished and driven
Unit of Measurement : m
Output per hour : 1.80 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.39


b. Diesel Hammer (K25 or equivalent) 1 0.15
c. Drop Hammer 1 0.07
d. Bar Cutter 1 0.12
e. Bar Bender 1 0.12
f. Welding Machine (500A), Gas/Diesel Driven 1 0.05
g. Cutting Outfit 1 0.05
h. One Bagger Mixer 1 0.17
i. Water Truck/Pump (16000L) 1 0.04
j. Concrete Vibrator 1 0.04
k. Tremie Pipe Set 1 0.17
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.80 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* m. 1.00 Prices of materials are variable per Region/
b. Reinforcing Steel Bar kg. 29.547 District based on the prevailing unit prices in
the locality which include payment of local
c. Cement bag 1.194 taxes and hauling cost to the project site.
d. Sand m³ 0.063 Refer to the Construction Material Price Data
e. Gravel m³ 0.126 established quarterly by Central Price
f. #16 Tie Wire (2% of RSB) kg. 0.591 Monitoring Committee.
g. Welding Rod (1 kg/2000 kg of Steel) kg. 0.063
h. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025
i. Coco Log- 2 uses m. 1.00
j. Good Lumber (Falsework)- 4 uses bd-ft 16.00
k. Nail/Spike (1 kg/100 bd-ft of Lumber) kg. 0.16
Miscellaneous (2% of Materials Cost)

Note:
Assumed weight of Tubular Pipe Pile is
95.93 kg/m.
Sub - Total for F
G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

164 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(18)b Concrete Piles cast in Steel Shells, furnished and driven (Ready Mix Concrete)
Unit of Measurement : m
Output per hour : 2.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.45


b. Diesel Hammer (K25 or equivalent) 1 0.17
c. Drop Hammer 1 0.08
d. Bar Cutter 1 0.14
e. Bar Bender 1 0.14
f. Welding Machine (500A), Gas/Diesel Driven 1 0.06
g. Cutting Outfit 1 0.06
h. Concrete Vibrator 1 0.01
i. Tremie Pipe Set 1 0.05
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* m. 1.00 Prices of materials are variable per Region/
b. Reinforcing Steel Bar kg. 29.547 District
Prices ofbased on the
materials prevailing
are unit Region/
variable per prices in
the locality
District which
based include
on the payment
prevailing unitofprices
local in
c. Ready Mix Concrete fc'=20.7 MPa m³ 0.132 taxes and hauling
the locality cost to payment
which include the project
of site.
local
d. #16 Tie Wire (2% of RSB) kg. 0.591 Refer to the
taxes and Construction
hauling Material
cost to the Price
project site.Data
e. Welding Rod (1 kg/2000 kg of Steel) kg. 0.063 established quarterly by Central Price
f. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025 Monitoring Committee.
g. Coco Log- 2 uses m 1.00
h. Good Lumber (Falsework)- 4 uses bd-ft 16.00
i. Nail/Spike (1 kg/100 bd-ft of Lumber) kg. 0.16
Miscellaneous (2% of Materials Cost)

Note:
Assumed weight of Tubular Pipe Pile is 95.93
kg/m.
If no available Ready Mix Concrete at Project
Site, derive the cost of concrete using the Batching
Plant or One Bagger Mixer for small quantity.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

165 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(19)a Concrete Piles cast in Steel Pipes, furnished and driven
Unit of Measurement : m
Output per hour : 2.40 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per Region/District


a. Construction Foreman 1 1.00 based on minimum wage as approved by
b. Skilled Laborer 6 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 6 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.39


b. Diesel Hammer (K25 or equivalent) 1 0.15
c. Drop Hammer 1 0.07
d. Bar Cutter 1 0.12
e. Bar Bender 1 0.12
f. Welding Machine (500A), Gas/Diesel Driven 1 0.05
g. Cutting Outfit 1 0.05
h. One Bagger Mixer 1 0.17
i. Water Truck/Pump (16000L) 1 0.04
j. Concrete Vibrator 1 0.04
k. Tremie Pipe Set 1 0.17
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.40 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* m. 1.00 Prices of materials are variable per Region/
b. Reinforcing Steel Bar kg. 29.547 District based on the prevailing unit prices in
the locality which include payment of local
c. Cement bag 1.194 taxes and hauling cost to the project site.
d. Sand m³ 0.063 Refer to the Construction Material Price Data
e. Gravel m³ 0.126 established quarterly by Central Price
f. #16 Tie Wire (2% of RSB) kg. 0.591 Monitoring Committee.
g. Welding Rod (1 kg/2000 kg of Steel) kg. 0.063
h. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025
i. Coco Log- 2 uses m 1.00
j. Good Lumber (Falsework)- 4 uses bd-ft 16.00
k. Nail/Spike (1 kg/100 bd-ft of Lumber) kg. 0.16
Miscellaneous (2% of Materials Cost)

Note:
Assumed weight of Tubular Pipe Pile is 95.93
kg/m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

166 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(19)b Concrete Piles cast in Steel Pipes, furnished and driven (Ready Mix Concrete)
Unit of Measurement : m
Output per hour : 2.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 6 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41 - 45 mt) 1 0.45


b. Diesel Hammer (K25 or equivalent) 1 0.17
c. Drop Hammer 1 0.08
d. Bar Cutter 1 0.14
e. Bar Bender 1 0.14
f. Welding Machine (500A), Gas/Diesel Driven 1 0.06
g. Cutting Outfit 1 0.06
h. Concrete Vibrator 1 0.01
i. Tremie Pipe Set 1 0.05
Minor Tools (10% of Labor)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Tubular Pile (0.40 m Ø x 9.50 mm thk)* m. 1.00 Prices of materials are variable per Region/
b. Reinforcing Steel Bar kg. 29.547 District based on the prevailing unit prices in
the locality which include payment of local
c. Ready Mix Concrete fc'=20.7 MPa m³ 0.132
taxes and hauling cost to the project site.
d. #16 Tie Wire (2% of RSB) kg. 0.591 Refer to the Construction Material Price Data
e. Welding Rod (1 kg/2000 kg of Steel) kg. 0.063 established quarterly by Central Price
f. Oxy/Acetylene (1 kg/5000 kg of Steel) set 0.025 Monitoring Committee.
g. Coco Log- 2 uses m 1.00
h. Good Lumber (Falsework)- 4 uses bd-ft 16.00
i. Nail/Spike (1 kg/100 bd-ft of Lumber) kg. 0.16
Miscellaneous (2% of Materials Cost)
Note:
Assumed weight of Tubular Pipe Pile is 95.93
kg/m.
If no available Ready Mix Concrete at Project
Site, derive the cost of concrete using the Batching
Plant or One Bagger Mixer for small quantity

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

167 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(20) Pile Shoes


Unit of Measurement : ea
Output per hour : 4.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Welding Machine (500A), Electric Driven 1 1.00


b. Bar Cutter 1 0.25
c. Bar Bender 1 0.25

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar, Grade 40 kg. 23.86 Prices of materials are variable per Region/
District
Prices ofbased on the
materials prevailing
are unit Region/
variable per prices in
b. Steel Plate (100+100) x 300 mm, 12 mm thk kg. 6.00
the locality
District which
based include
on the payment
prevailing unitofprices
local in
c. Welding Rod ( 1 kg/2000 kg of Steel) kg. 0.015 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

168 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)a Bored Piles, 0.80 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 1.58 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 9.00 0.50
e. Unskilled Laborer 17.00 0.50

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.26


b. Crawler Crane (41 - 45 mt) 1 0.95
c. Crawler Crane (21 - 25 mt) 1 0.95
3
d. Dump Truck (12 yd ) 1 0.95
3
e. Payloader (1.50 m ), LX80-2C 1 0.95
f. Generator Set (300 KW) 1 0.95
g. Bentonite Bin 1 0.50
h. Bentonite Mixer 1 0.50
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.74
j. Water Truck (16000 L) 1 0.74
k. Bar Cutter 1 0.50
l. Bar Bender 1 0.50
m. Welding Machine (500A), Electric Driven 1 0.71
n. Cutting Outfit 1 0.71
o. Tremie Pipe Set 1 0.24
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.05
r. Air Compressor, Portable (126 - 160 cfm) 1 0.05
s. Lighting System/Tower Lights 1 0.95
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.58 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa @ 28 D cu.m. 0.55 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 205.00 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 4.10 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.041 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.10 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

169 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)b Bored Piles, 1.00 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 1.33 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 9 0.56
e. Unskilled Laborer 16 0.56

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.31


b. Crawler Crane (41- 45 mt) 1 0.96
c. Crawler Crane (21- 25 mt) 1 0.96
3
d. Dump Truck (12yd ) 1 0.96
e. Payloader (1.50 m3), LX80-2C 1 0.96
f. Generator Set (300 KW) 1 0.96
g. Bentonite Bin 1 0.53
h. Bentonite Mixer 1 0.53
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.78
j. Water Truck/Pump (16000L) 1 0.78
k. Bar Cutter 1 0.56
l. Bar Bender 1 0.56
m. Welding Machine (500 A), Electric Driven 1 0.73
n. Cutting Outfit 1 0.73
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.24
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126- 160 cfm) 1 0.04
s. Lighting System/Tower Lights 1 0.96
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.33 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

3
a. Ready Mix Concrete, fc' = 28 Mpa m 0.86 Prices of materials are variable per Region/
Prices
Districtofbased
materials
on theareprevailing
variable per
unit Region/
prices in
b. Reinforcing Steel Bar * kg. 253.59
District based
the locality on the
which prevailing
include paymentunitofprices
local in
c. Tire Wire (2% of RSB) kg. 5.07 the locality which include payment of
taxes and hauling cost to the project site.local
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.051 taxes
Refer and hauling
to the cost to the
Construction project
Material site.Data
Price
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.13 Refer to the quarterly
established Construction Material
by Central Price Data
Price
established quarterly by Central Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

170 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)c Bored Piles, 1.20 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 1.09 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 8 0.60
e. Unskilled Laborer 15 0.60

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.35


b. Crawler Crane (41- 45 mt) 1 0.96
c. Crawler Crane (21- 25 mt) 1 0.96
3
d. Dump Truck (12yd ) 1 0.96
e. Payloader (1.50 m3), LX80-2C 1 0.96
f. Generator Set (300 KW) 1 0.96
g. Bentonite Bin 1 0.56
h. Bentonite Mixer 1 0.56
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.82
j. Water Truck/Pump (16000L) 1 0.82
k. Bar Cutter 1 0.60
l. Bar Bender 1 0.60
m. Welding Machine (500 A), Electric Driven 1 0.75
n. Cutting Outfit 1 0.75
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.25
q. Portable Breaker, BHF30S 2 0.04
r. Air Compressor, Portable (126- 160 cfm) 1 0.04
s. Lighting System/Tower Lights 1 0.96
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 1.09 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

3
a. Ready Mix Concrete, fc' = 28 Mpa m 1.24 Prices of materials are variable per Region/
Prices
Districtofbased
materials
on theareprevailing
variable per
unit Region/
prices in
b. Reinforcing Steel Bar * kg. 304.30
District based
the locality on the
which prevailing
include paymentunitofprices
local in
c. Tire Wire (2% of RSB) kg. 6.09 the locality
taxes which include
and hauling cost to payment
the projectof site.
local
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.061 taxes
Refer and hauling
to the cost to the
Construction project
Material site.Data
Price
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.15 Refer to the quarterly
established Construction Material
by Central Price Data
Price
established quarterly by Central Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

171 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)d Bored Piles, 1.50 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 0.81 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 7 0.65
e. Unskilled Laborer 13 0.65

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.39


b. Crawler Crane (41- 45 mt) 1 0.97
c. Crawler Crane (21- 25 mt) 1 0.97
3
d. Dump Truck (12yd ) 1 0.97
e. Payloader (1.50 m3), LX80-2C 1 0.97
f. Generator Set (300 KW) 1 0.97
g. Bentonite Bin 1 0.61
h. Bentonite Mixer 1 0.61
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.86
j. Water Truck/Pump (16000L) 1 0.86
k. Bar Cutter 1 0.65
l. Bar Bender 1 0.65
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker, BHF30S 2 0.03
r. Air Compressor, Portable (126- 160 cfm) 1 0.03
s. Lighting System/Tower Lights 1 0.97
Minor Tools (10% of Labor)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.81 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

3
a. Ready Mix Concrete, fc' = 28 Mpa m 1.94 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Reinforcing Steel Bar * kg. 387.77
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 7.76 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.078 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.19 established quarterly by Central Price
Monitoring Committee.
Miscellaneous (3% of Materials, Bentonite and etc.)

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

172 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)e Bored Piles, 1.80 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 0.62 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 7 0.68
e. Unskilled Laborer 12 0.68

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.42


b. Crawler Crane (41- 45 mt) 1 0.98
c. Crawler Crane (21- 25 mt) 1 0.98
3
d. Dump Truck (12 yd ) 1 0.98
3
e. Payloader (1.50 m ), LX80-2C 1 0.98
f. Generator Set (300 KW) 1 0.98
g. Bentonite Bin 1 0.64
h. Bentonite Mixer 1 0.64
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.90
j. Water Truck/Pump (16000L) 1 0.90
k. Bar Cutter 1 0.68
l. Bar Bender 1 0.68
m. Welding Machine (500 A), Electric Driven 1 0.76
n. Cutting Outfit 1 0.76
o. Tremie Pipe Set 1 0.22
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker 2 0.02
r. Air Compressor, Portable (126- 160 cfm) 1 0.02
s. Lighting System/Tower Lights 1 0.98
Minor Tools (10% of labor cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.62 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa m3 2.80 Prices of materials are variable per Region/
District
Prices ofbased on the
materials prevailing
are unit Region/
variable per prices in
b. Reinforcing Steel Bar * kg. 451.98 the locality which include payment
District based on the prevailing unitofprices
local in
c. Tire Wire (2% of RSB) kg. 9.04 taxes and hauling
the locality cost to payment
which include the project
of site.
local
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.090 Refer to the
taxes and Construction
hauling Material
cost to the Price
project site.Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.23 established
Refer to the quarterly by Central
Construction Price
Material Price Data
Monitoring
establishedCommittee.
quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

173 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(23)f Bored Piles, 2.00 m. Ø (ordinary soil condition)


Unit of Measurement : m
Output per hour : 0.53 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 6 1.00 Rates.
Fabrication of Cage Bar
d. Skilled Laborer 5 0.70
e. Unskilled Laborer 10 0.70

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drilling Rig (300 hp) 1 0.44


b. Crawler Crane (41- 45 mt) 1 0.98
c. Crawler Crane (21- 25 mt) 1 0.98
3
d. Dump Truck (12 yd ) 1 0.98
3
e. Payloader (1.50 m ), LX80-2C 1 0.98
f. Generator Set (300 KW) 1 0.98
g. Bentonite Bin 1 0.65
h. Bentonite Mixer 1 0.65
i . Water Pump, 100 mm suction Ø (7.5 hp) 1 0.91
j. Water Truck/Pump (16000L) 1 0.91
k. Bar Cutter 1 0.70
l. Bar Bender 1 0.70
m. Welding Machine (500 A), Electric Driven 1 0.77
n. Cutting Outfit 1 0.77
o. Tremie Pipe Set 1 0.21
p. SPT & Desanding Machine 1 0.26
q. Portable Breaker 2 0.02
r. Air Compressor, Portable (126- 160 cfm) 1 0.02
s. Lighting System/Tower Lights 1 0.98
Minor Tools (10% of labor cost)
Sub - Total for B
C. Total (A + B)
D. Output per Hour = 0.53 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix Concrete, fc' = 28 Mpa m3 3.46 Prices of materials are variable per Region/
b. Reinforcing Steel Bar * kg. 490.33 District based on the prevailing unit prices in
the locality which include payment of local
c. Tire Wire (2% of RSB) kg. 9.81 taxes and hauling cost to the project site.
d. Oxygen/Acetylene (1 set/5000 kg. of RSB) set 0.098 Refer to the Construction Material Price Data
e. Welding Rod (1 kg./2000 kg. of RSB) kg. 0.25 established quarterly by Central Price
Miscellaneous (3% of Materials, Bentonite and etc.) Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

174 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)a Permanent Casing (0.80 m Ø)


Unit of Measurement : m
Output per hour : 3.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.082 the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 0.409 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Note: Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

175 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)b Permanent Casing (1.00 m Ø)


Unit of Measurement : m
Output per hour : 2.40 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.40 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.102
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 0.511 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Note:
Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

176 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)c Permanent Casing (1.20 m Ø)


Unit of Measurement : m
Output per hour : 2.00 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.00 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.122 District based on the prevailing unit prices in
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 0.612 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
Note: established quarterly by Central Price
Assumed length of Steel Casing without splicing Monitorng Committee.
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

177 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)d Permanent Casing (1.50 m Ø)


Unit of Measurement : m
Output per hour : 1.60 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.60 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.153 District based on the prevailing unit prices in
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 0.763 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
Note: established quarterly by Central Price
Assumed length of Steel Casing without splicing Monitoring Committee.
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

178 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)e Permanent Casing (1.80 m Ø)


Unit of Measurement : m
Output per hour : 1.33 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 6 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.33 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.025 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.163 the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 0.814 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Note: Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

179 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(24)f Permanent Casing (2.00 m Ø)


Unit of Measurement : m
Output per hour : 1.20 m.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor Rates are variable per


a. Construction Foreman 1 1.00 Region/District based on minimum wage as
b. Skilled Laborer 4 1.00 approved by DOLE. Refer to the Schedule
c. Unskilled Laborer 6 1.00 of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41- 45 mt) 1 1.00


b. Vibro Hammer w/ Hydraulic Power Pack 1 0.50
c. Welding Machine (500 A), Gas/Diesel Driven 1 0.50
d. Cutting Outfit 1 0.50
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.20 m.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Steel Casing, 10 mm thk m 1.03 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Oxy/Acetylene (1 set/2500 kg of Steel) set 0.203
the locality which include payment of local
c. Welding Rod (1 kg/500 kg of Steel) kg. 1.016 taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Note:
Monitoring Committee.
Assumed length of Steel Casing without splicing
but with full weld = 12.00 meter, 2.50% additional quantity
of Steel Casing represents the collar of 0.30 m for 12 m.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

180 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(25) Splicing of RC Piles with Epoxy (400 mm x 400 mm)
Unit of Measurement : ea
Output per hour : 0.50 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41-45 mt) 1 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.50 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar (36 mm Ø x 1.50 m)* kg. 51.83 Prices of materials are variable per Region/
b. Concrete Epoxy for RC Piles (Part A & B) set 0.70 Prices of
District materials
based on theare variable per
prevailing unit Region/
prices in
the locality
District which
based include
on the payment
prevailing unitofprices
local in
c. Silica Sand gal 1.40 taxes and hauling cost to the project site.
d. Pipe Sleeve, 50 mm Ø GI m 3.00 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price

* Depth of dowel will be as recommended by the


manufacturer of epoxy resin in order to develop
required pile joint strength.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

181 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(26) Splicing of RC Piles with Epoxy (450 mm x 450 mm)
Unit of Measurement : ea
Output per hour : 0.50 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted Crane (41-45 mt) 1 1.00


Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.50 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Reinforcing Steel Bar (36 mm Ø x 1.50 m)* kg. 51.83 Prices of materials are variable per Region/
b. Concrete Epoxy for RC Piles (Part A & B) set 0.80 Districtofbased
Prices on the
materials areprevailing unit Region/
variable per prices in
the locality
District which
based include
on the payment
prevailing unitofprices
local in
c. Silica Sand gal 1.60 taxes and hauling cost to the project site.
d. Pipe Sleeve, 50 mm Ø GI m 3.00 Refer to the Construction Material Price Data
Miscellaneous (2% of Materials Cost) established quarterly by Central Price

* Depth of dowel will be as recommended by the


manufacturer of epoxy resin in order to develop
required pile joint strength.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

182 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(27)a Pile Integrity Testing (Sonic), ordinary soil condition
Unit of Measurement : ea
Output per hour : 1.00 ea (assumed pile length = 30 m)

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 4.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 4.00
Pipe Installation
a. Skilled Laborer 2 4.00
b. Unskilled Laborer 2 4.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Pile Integrity Testing (Sonic) and accessories 1 lot


(includes professional fee of Structural Engineer
and reports)
b. Welding Machine (500A), Electric Driven 1 4.00
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Black/GI Pipe & acc. 2" Ø x 6 m, Schedule 20 m 120.00 Prices of materials are variable per Region/
District
Prices ofbased on the
materials prevailing
are unit Region/
variable per prices in
b. Welding Rod kg 0.10
the locality
District which
based include
on the payment
prevailing unitofprices
local in
Miscellaneous (2% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Note:
Materials quantity component, equipment and
labor output may vary proportionately depending on
the pile length.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

183 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(27)b Pile Integrity Testing (PIT), ordinary soil condition
Unit of Measurement : ea
Output per hour : 1.00 ea

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 2.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 2.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 2.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a.Pile Integrity Testing and accessories 1 lot


(includes professional fee of Structural Engineer
and reports)
b. Grinding Machine and accessories 1 2.00

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Grinding Disc pc 1.00 Prices of


Prices of materials
materials are
are variable
variable per Region/
per Region/
District based
District based on
on the prevailing unit
the prevailing unit prices
prices in
in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

Note:
Materials quantity component, equipment and
labor output may vary proportionately depending on
the pile length.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

184 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052(22)b High Strain Dynamic Testing (PDA), ordinary soil condition
Unit of Measurement : ea
Output per hour : 1.00 ea (assumed pile Ø = 1.50 m)

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 2 4.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 4 8.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a.Dynamic Pile Testing 1 lot


(includes professional fee of Structural Engineer)
b. Truck Mounted Crane (45 mt) 1 4.00
c. Drop Hammer w/ accessories 1 4.00
d. 1 Air Compressor w/ 2 Jack Hammer 1 8.00
e. Concrete Vibrator 1 0.60
f. Cutting Outfit 1 2.00
g. Welding Machine (500A), Electric Driven 1 2.00
Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.00 ea
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Steel Casing, L = 2 x Pile Ø, thickness = 100 mm* m 3.00
District
Prices ofbased on the
materials prevailing
are unit Region/
variable per prices in
b. Ready Mix Concrete, 3000 psi m3 5.57 the locality which include payment
District based on the prevailing unitofprices
local in
c. Welding Rod (1 kg/500 kg of Steel) kg 2.234 taxes and hauling cost to the project site.
d. Oxy/Acetylene (1 kg/2500 kg of Steel) set 0.447 Refer to the Construction Material Price Data
established quarterly by Central Price
Miscellaneous (5% of Materials Cost) Monitoring Committee.

Note:
Materials quantity component, equipment and
labor output may vary proportionately depending on
the pile length.

Sub - Total for F


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

185 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1052 (29) Micro Piles In Drilled Holes, 0.20m Ø (ordinary soil condition)
Unit of Measurement : m
Output per hour : 3.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 5 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 6 1.00
Fabrication of Cage Bar
d. Skilled Laborer 4 0.25
e. Unskilled Laborer 8 0.25

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Drill Rig, Mechanical Rotary 1 0.74


b. Truck Mounted Crane (25T) 1 0.95
c. Bar Bender 1 0.04
d. Bar Cutter 1 0.04
e. Bentonite Mixer 1 0.50
f. Bentonite Bin 1 0.50
g. Water Pump 1 0.50
h.Water Truck 1 0.50
i. Welding Machine 1 0.50
j. Tremie Pipe Set 1 0.24
k. SPT & Desanding Machine 1 0.24
l. Tower Light 1 0.50
m. Minor Tools (10% of labor cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Ready Mix 0.033 cu.m. Prices of materials are variable per Region/
b. Reinforced Steel Bar 12.626* kg District based on the prevailing unit prices in
the locality which include payment of local
c. Welding Rod (1kg/2000kg of RSB) 0.006 kg taxes and hauling cost to the project site.
d. Miscellaneous (3% of Materials, Bentonite & etc.) Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

* Its quantity is variable depending on the actual design


G. Direct Unit Cost (E + F)
H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

186 Part C - Finishing


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(1) 15 mm Ø - 25 mm Ø Rigid Steel Conduit (RSC)/Intermediate metal Conduit (IMC)/
Electrical Metal Tubing (EMT)
Unit of Measurement : length
Output per hour : 1.333 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.333 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 15 mm Ø - 25 mm Ø x 3.00 m Rigid Steel Conduit Prices of materials are variable per Region/
(RSC)/ Intermediate metal Conduit (IMC)/ Electrical m 1.00 District based on the prevailing unit prices in
Metal Tubing (EMT) the locality which include payment of local
taxes and hauling cost to the project site.
b. Consumables (5% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(1)a, 1100(1)b, 1100(1)c, 1100(2)a, 1100(2)b, 1100(2)c, 1100(4)a,
1100(4)b, and 1100(4)c.

187 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(1) 32 mm Ø - 40 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/
Electrical Metal Tubing (EMT)
Unit of Measurement : length
Output per hour : 1.250 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.250 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 32 mm Ø - 40 mm Ø x 3.00 m Rigid Steel Conduit Prices of materials are variable per Region/
(RSC)/ Intermediate metal Conduit (IMC)/ Electrical m 1.00 District based on the prevailing unit prices in
Metal Tubing (EMT) the locality which include payment of local
taxes and hauling cost to the project site.
b. Consumables (5% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(1)d, 1100(1)e, 1100(2)d, 1100(2)e, 1100(4)d and 1100(4)e.

188 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(1) 50 mm Ø - 65 mm Ø Rigid Steel Conduit/ Intermediate metal Conduit (IMC)/
Electrical Metal Tubing (EMT)

Unit of Measurement : length


Output per hour : 0.516 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.516 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50 mm Ø - 65 mm Ø x 3.00 m Rigid Steel Conduit/ Prices of materials are variable per Region/
Intermediate metal Conduit (IMC)/ Electrical Metal m 1.00 District based on the prevailing unit prices in
Tubing (EMT) the locality which include payment of local
taxes and hauling cost to the project site.
b. Consumables (5% of Materials Cost) Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(1)f, 1100(1)g, 1100(2)f, 1100(2)g, 1100(4)f and 1100(4)g.

189 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(1) 80 mm Ø - 100 mm Ø Rigid Steel Conduit (RSC)/ Intermediate metal Conduit (IMC)/
Electrical Metal Tubing (EMT)
Unit of Measurement : length
Output per hour : 0.500 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.500 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 80 mm Ø x 3 m Rigid Steel Conduit (RSC) m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(1)h, 1100(1)i, 1100(1)j, 1100(2)h, 1100(2)i, 1100(2)j, 1100(4)h,
1100(4)i, and 1100(4)j.

190 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(3) 15 mm Ø - 25 mm Ø Flexible Metal Conduit


Unit of Measurement : m
Output per hour : 2.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 15 mm Ø - 25 mm Ø Flexible Metal Conduit m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(3)a, 1100(3)b, and 1100(3)c.

191 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(6) 15 mm Ø - 32 mm Ø Polyvinyl Chloride (PVC) Pipes


Unit of Measurement : length
Output per hour : 3.534 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 3.534 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 15 mm Ø - 32 mm Ø x 3.00 mm Polyvinyl Chloride Prices of materials are variable per Region/


length 1.00 District based on the prevailing unit prices in
(PVC) Pipes
the locality which include payment of local
b. Consumables (5% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1100(6)a, 1100(6)b, and 1100(6)c.

192 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(9) PVC/RSC/ IMC/ EMT Conduit Fittings


Unit of Measurement : pc
Output : 1.00 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost for these items shall be considered/included in the installation of conduits.)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Coupling/Elbow/End Bell/Clamp or others pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

193 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(11) Junction/ Utility/ Pull/ Square Box


Unit of Measurement : pc
Output : 1.00 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 0.40 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Unskilled Laborer 1 0.40 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Junction/ Utility/ Pull/ Square Box pc 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

194 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1100(10) Conduit Works, Boxes and Fittings


Unit of Measurement : l.s.
Output : 1.00 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See Derivation for Item No.1100(1) to Item No. 1100(9)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See Derivation for Item No.1100(1) to Item No. 1100(9)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See Derivation for Item No.1100(1) to Item No. 1100(9)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1100(1) to
Item No. 1100(9).

195 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 1.6 mm - 5.5 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 25 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 25 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 1.6 mm2 - 5.5 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in
(TW/THHN/TWHN2)
the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
Price Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)a1, 1101(1)a2, 1101(1)a3, 1101(1)a4, 1101(1)b1, 1101(1)b2, and 1101(1)b3.

196 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 8.00 mm - 22 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 14.286 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 14.286 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. 8.00 mm2 Electric Wire (TW/THHN/TWHN2) m 1.00 District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
OfficePrice
Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b4, 1101(1)b5, and 1101(1)b6.

197 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 30.00 mm - 38 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 5.714 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 5.714 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 30.00 mm2 - 38 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in
(TW/THHN/TWHN2) the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b7 and 1101(1)b8.

198 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 50.00 mm - 60 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 4.615 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 4.615 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50.00 mm2 - 60mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in
(TW/THHN/TWHN2) the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b9 and 1101(1)b10.

199 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)
2 2 2
Item No./Description : 1101(1) 80.00 mm - 125 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 2.857 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 2.857 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 80.00 mm2 - 125 mm2 Electric Wire Prices of materials are variable per Region/
m 1.00 District based on the prevailing unit prices in
(TW/THHN/TWHN2)
the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
Price Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b11, 1101(1)b12and 1101(1)b13.

200 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 150.00 mm - 250 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 1.875 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.875 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.150.00 mm2 -250 mm2 Electric Wire m 1.00 Prices of materials are variable per Region/
2 District based on the prevailing unit prices in
(TW/THHN/TWHN ) the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b14, 1101(1)b15 and 1101(1)b16.

201 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2 2
Item No./Description : 1101(1) 325.00 mm - 400 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 1.60 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.60 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 325.00 mm2 - 400 mm2 Electric Wire m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
(TW/THHN/TWHN2) the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(1)b17, and 1101(1)b18.

202 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1101(1)b19 500.00 mm Electric Wire (TW/THHN/TWHN )
Unit of Measurement : m
Output per hour : 1.333 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 4 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1.333 m
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 500.00 mm2 Electric Wire (TW/THHN/TWHN2) m 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (3% of Materials Cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
Price Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

203 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101(2) XLPE Electric Wires


Unit of Measurement : m
Output per hour :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

(Labor cost shall be included in the Power Contract with MERALCO or Local Power Cooperative.)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. XLPE, Creosoted pole, anchor Rod, anchor log, (Materials cost included in the Power Contract with MERALCO
power load studs, pad mounted transformer, pole-type or Local Power Cooperative.)
transformer, transformer bracket, Aluminum
Conductor Steel-Reinforced (ACSR) powerfuse,
concrete pole, power transmission pole, pin insulator,
pole top pin, machine bolts and washers

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

204 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(4) 2.00 mm - 5.5 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 20.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 20.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2.00 mm2 - 5.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1109(4)a, 1109(4)b and 1109(4)c.

205 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(4) 8.00 mm - 22.00 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 10.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 10.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 8.00 mm2 - 22.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1109(4)d, 1109(4)e and 1109(4)g.

206 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(4) 30.00 mm - 38.00 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 12.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 12.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 30.00 mm2 - 38.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1109(4)h and 1109(4)i.

207 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(4) 50.00 mm - 60.00 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 10.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 10.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 50.00 mm2 - 60.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (3% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1109(4)j and 1109(4)k.

208 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(4) 80.00 mm - 125.00 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 6.00 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 2 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 6.00 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 80.00 mm2 - 125.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1109(4)l and 1109(4)m.

209 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

2 2
Item No./Description : 1109(1) 200.00 mm - 250.00 mm Bare Copper Wire
Unit of Measurement : m
Output per hour : 6.667 m

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Skilled Laborer 4 1.00 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 4 1.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 6.667 m
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 200.00 mm2 - 250.00 mm2 Bare Copper Wire m 1.00 Prices of materials are variable per Region/
b. Consumables (5% of Materials Cost) District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

210 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101(33) Switches


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 1.00 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Unskilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Switches set 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(3) to 1101(14).

211 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101 (15) Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Heavy Duty Convenience
Outlet/Receptacle, Grounding Type (GT)/ Weather Proof Single Convenience Outlet/Receptacle,
Grounding Type (GT)/ Pop-up Type/Floor Triplex Convenience Outlet/Receptacle, Grounding Type
(GT)

Unit of Measurement : set


Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 0.25 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Unskilled Laborer 1 0.25 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Single Convenience Outlet/Receptacle, Grounding District based on the prevailing unit prices in
Type (GT)/ Heavy Duty Convenience the locality which include payment of local
Outlet/Receptacle, Grounding Type (GT)/ Weather taxes and hauling cost to the project site.
set 1.00 Refer to the Construction Material Price Data
Proof Single Convenience Outlet/Receptacle, established quarterly by Central Office Price
Grounding Type (GT)/ Pop-up Type/Floor Triplex Monitoring Committee.
Convenience Outlet/Receptacle, Grounding Type (GT)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(17), 1101(18), 1101(23) , 1101(24)and 1101(26).

212 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101 (16) Duplex Convenience Outlet/Receptacle, Grounding Type (GT) / Weather Proof Duplex Convenience
Outlet/Receptacle, Grounding Type (GT)/ Special Purpose Convenience Outlet/Receptacle,
Grounding Type for ACU, WH, etc/ Explosion Proof Type Duplex Convenience Outlet/Receptacle,
Grounding Type (GT)/ Duplex Convenience Outlet/Receptacle with Ground Fault Circuit Interupter

Unit of Measurement : set


Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 0.30 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Unskilled Laborer 1 0.30 DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Duplex Convenience Outlet/Receptacle, Grounding Prices of materials are variable per Region/
Type (GT) / Weather Proof Duplex Convenience District based on the prevailing unit prices in
Outlet/Receptacle, Grounding Type (GT)/ Special the locality which include payment of local
taxes and hauling cost to the project site.
Purpose Convenience Outlet/Receptacle, Grounding
Refer to the Construction Material Price Data
Type for ACU, WH, etc/ Explosion Proof Type Duplex established quarterly by Central Office Price
Convenience Outlet/Receptacle, Grounding Type set 1.00 Monitoring Committee.
(GT)/ Duplex Convenience Outlet/Receptacle with
Ground Fault Circuit Interupter

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(19), 1101(20) and 1101(25).

213 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101 (21) Pop-up Type/Floor Single Convenience Outlet/Receptacle, Grounding Type (GT)/ Pop-up Type/Floor
Duplex Convenience Outlet/Receptacle, Grounding Type (GT)/ Explosion Proof Type Single
Convenience Outlet/Receptacle, Grounding Type (GT)/ Single Convenience Outlet/Receptacle with
Ground Fault Circuit Interrupter

Unit of Measurement : set


Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Skilled Laborer 1 0.15 Labor Rates are variable per Region/District


based on minimum
Minimum wage as approved by
b. Unskilled Laborer 1 DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)

Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Pop-up Type/Floor Single Convenience Prices of materials are variable per Region/
Outlet/Receptacle, Grounding Type (GT)/ Pop-up District based on the prevailing unit prices in
Type/Floor Duplex Convenience Outlet/Receptacle, the locality which include payment of local
taxes and hauling cost to the project site.
Grounding Type (GT)/ Explosion Proof Type Single
Refer to the Construction Material Price Data
Convenience Outlet/Receptacle, Grounding Type set 1.00 established quarterly by Central Offiice Price
(GT)/ Single Convenience Outlet/Receptacle with
Ground Fault Circuit Interupter

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1101(22), 1101(23), 1101(24), 1101(25) and 1101(26).

214 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1101 (33) Wires and Wiring Devices


Unit of Measurement : l.s.
Output : 1.00 l.s

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivation for Items 1101(1) to Item 1101(8).

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivation for Items 1101(1) to Item 1101(8).

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivation for Items 1101(1)- Item 1101(8).

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item No. 1101(1) to
Item No. 1101(32)

215 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 250 Amp - 400 Amp
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 9.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 9.00 Labor Rates
based are variable
on minimum wage per Region/District
as approved by
based on
DOLE. Minimum
Refer to the wage as approved
Schedule of Labor by
c. Unskilled Laborer 2 9.00 DOLE.
Rates.

Note:
Labor includes disassembling of Panel Board
component, fabrication of hole (conduit for main breaker
and branches), installation of fitting, alignment of panel
board enclosure, re-installation of circuit breaker component
and accessories, termination of wire, testing and
commissioning.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Panel Board with Main Breaker and 8 Branches Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
250 amp - 400 amp
the locality which include payment of local
b. Consumables (3% of Materials Cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
Price Price
Monitoring Committee.
Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Additional 1 hr may be added every another 2 circuit branches, 1 hr per every additional main breaker (500-600Amp),
2 hrs per additional main breaker (800-1000Amp) and 4 hrs per additional 1200 Amp main breaker.

216 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Panel Board with Main Breaker/Branches, 3 wires, 1 neutral, 50 Amp - 200 Amp
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 5.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 5.50 DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 2 5.50 Rates.

Note:
Labor includes disassembling of Panel Board
component, fabrication of hole (conduit for main breaker
and branches), installation of fitting, alignment of panel
board enclosure, re-installation of circuit breaker component
and accessories, termination of wire, testing and
commissioning.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Panel Board with Main Breaker and 8 Branches 50 Prices of materials are variable per Region/
amp - 200 amp set 1.00 District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
b. Consumables (3% of Materials Cost)
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note: 1. Additional 0.75 hr may be added every another 2 circuit branches, and deduction of 0.50 for 2 wires, 1 neutral.

217 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) NEMA I (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. NEMA I Enclosed Circuit Breaker, plug-in or bolt Prices of materials are variable per Region/
type 15AT-70AT Flushed Mounted set 1.00 District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

218 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) NEMA 3R (Enclosed Circuit Breaker) Single Phase or Three Phase Commercial/Industrial Type
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 0.75 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.75

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. NEMA 3R Enclosed Circuit Breaker, plug-in or bolt set 1.00 Prices of materials are variable per Region/
type 15AT-70AT Flushed Mounted District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

219 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (2) Motor Control Center with main, branch breaker and motor starter (NEMA 1, NEMA 3R and 4X) Flush
or Surface Mounted
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 8.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 2 8.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 8.00

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Motor Control Center with main, branch breaker Prices of materials are variable per Region/
set 1.00 District based on the prevailing unit prices in
and motor starter (NEMA 1, NEMA 3R and 4X) Flush
or Surface Mounted the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

220 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (16) Generator (Stand by and Continuous), Synchonizing Panel for Generator, High Voltage Switch Gear

Unit of Measurement : set


Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Generator (Stand by and Continuous), Materials Cost by Specialty Works or Manufacturer's/Supplier's


Synchonizing Panel for Generator, High Voltage Quotation (attach at least 3 quotations)
Switch Gear

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

221 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 3P, 240V: NEMA I, NEMA 3R, NEMA
4x Flushed/ Surface Mounted
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hours/s Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.75 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.75 based on minimum wage as approved by
c. Unskilled Laborer 1 1.75 DOLE. Refer to the Schedule of Labor Rates.

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

Main Enclosed Automatic Circuit Breaker 50 AT, 60 set 1.00 Prices of materials are variable per Region/
AT, 70 AT , 3P, 240x: NEMA I, NEMA 3R, NEMA 4x District based on the prevailing unit prices in
Flushed/ Surface Mounted the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

222 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Main Enclosed Automatic Circuit Breaker 50 AT, 60 AT, 70 AT , 2P, 240V NEMA I, NEMA 3R, NEMA
4x Flushed/Surface Mounted
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount

A. Labor

a. Construction Foreman 1 1.50 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.50 based on minimum wage as approved by
c. Unskilled Laborer 1 1.50 DOLE. Refer to the Schedule of Labor Rates.

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Main Enclosed Automatic Circuit Breaker 50 AT, 60 set 1.00 Prices of materials are variable per Region/
AT, 70 AT , 2P, 240V NEMA I, NEMA 3R, NEMA 4x District based on the prevailing unit prices in
Flushed/ Surface Mounted the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

223 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 205 AT , 225 AT, 3P, 240V NEMA I, NEMA
3R, NEMA 4x Flushed/ Surface Mounted
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount

A. Labor

a. Construction Foreman 1 5.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 5.50
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 5.50

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Main Enclosed Automatic Circuit Breaker 100 AT, set 1.00 Prices of materials are variable per Region/
125 AT, 205 AT , 225 AT, 3P, 240V NEMA I, NEMA District based on the prevailing unit prices in
3R, NEMA 4x Flushed/ Surface Mounted the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

224 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Main Enclosed Automatic Circuit Breaker 100 AT, 125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I,
NEMA 3R, NEMA 4x Flushed/ Surface Mounted
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount

A. Labor

a. Construction Foreman 1 5.00


b. Skilled Laborer 1 5.00 Labor Rates are variable per Region/District
based on minimum wage as approved by
c. Unskilled Laborer 1 5.00 DOLE. Refer to the Schedule of Labor Rates.

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Main Enclosed Automatic Circuit Breaker 100 AT, set 1.00 Prices of materials are variable per Region/
125 AT, 200 AT , 2P, 225 AT, 2P, 240V NEMA I, District based on the prevailing unit prices in
NEMA 3R, NEMA 4x Flushed/ Surface Mounted the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

225 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Low Voltage Switch Board Main 2500-4000 AT, 3P, 240V NEMA I with Breaker
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Low Voltage Switch Board Main 2500-4000 AT, 3P, Material Cost by Specialty Works or Manufacturer's/Supplier's
240V NEMA I with Breaker Quotation (attach at least 3 quotations)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

226 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1102 (1) Main Enclosed Automatic Breaker 250-500 Amp
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount

A. Labor

a. Construction Foreman 1 12.50 Labor Rates are variable per Region/District


b. Skilled Laborer 2 12.50 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 12.50

Note:
Labor Includes removal of circuit breaker,
Alignment, mounting and removal of hub/hole, installation of
pipe/fittings, re-installation of circuit breaker, termination of
wires, testing and commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount

F. Materials

a. Main Enclosed Automatic Breaker 250-500 Amp set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) 12%9%7%6% of G
I. Contractor's Profit (CP) 10%8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

227 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 1 Bulb
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 1 -20Watts-40Watts flourescent lighting fixture, Box set 1.00 Prices of materials are variable per Region/
type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in
Industrial type (Recessed and Surface Mounted) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

228 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 2 Bulbs
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.15 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.15 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.15

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2 -20Watts-40Watts flourescent lighting fixture, Box set 1.00 Prices of materials are variable per Region/
type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in
Industrial type (Recessed and Surface Mounted) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

229 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 3 Bulbs
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.25 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.25 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.25

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 3-20watts-40watts flourescent lighting fixture set 1.00 Prices of materials are variable per Region/
Box type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in
Industrial type (Recessed and Surface Mounted) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

230 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Fluorescent Lighting Fixture with Ballast /Light Emitting Diode (LED) Bulb, 4 Bulbs
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.50 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.50

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 4-20watts-40watts flourescent lighting fixture set 1.00 Prices of materials are variable per Region/
Box type, Diffuser type, Mirrorized Aluminum Louver, District based on the prevailing unit prices in
Industrial type (Recessed and Surface Mounted) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

231 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Downlight/Pinlight Fixture with One- Compact Fluorecent Lamp (CFL) or LED Bulb, 1 Bulb
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.00 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 1.00

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. 1-8watts-21watts Downlight/Pinlight, set 1.00 District based on the prevailing unit prices in
Recessed/Surface Mounted with or without glass the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

232 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Downlight/Pinlight Fixture with Two- Compact Fluorecent Lamp (CFL) or LED Bulb, 2 Bulb
Unit of Measurement : set
Output per hour : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 0.75 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 1 0.75

Note :
Labor Includes installation of scaffolding,
alignment of fixtures, disassemble of lighting fixture,
permanent Installation of insullation material, testing and
commisioning.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Minor Tools (10 % of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output per hour = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 2- 8Watts-21Watts Downlight/Pinlight, set 1.00 Prices of materials are variable per Region/
Recessed/Surface Mounted with or without glass District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

233 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) High Bay Aluminum Reflector, Dome Luminaire
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.50 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.50

Note :
Labor Includes, installation of scaffolding,
alignment of lighting fixture, termination of wire, testing,
commissioning and painting.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted, Scissor Lift, Rough Terrain 1 1.00 See latest ACEL rental rates.
(Gas/Diesel)
Minor Tools (10% of Labor Cost)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. High Bay Aluminum Reflector, Dome Luminaire set 1.00 Prices of materials are variable per Region/
70Watts - 250 Watts District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

234 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Die-Cast Aluminum Floodlight with Electrocoat Paint Finish
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 1.50 DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.50

Note :
Labor Includes, installation of scaffolding,
alignment of lighting fixture, termination of wire, testing,
commissioning and painting.

Sub - Total for A


Name and Capacity No of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

a. Truck Mounted, Scissor Lift, Rough Terrain 1 1.00 See latest ACEL rental raets.
(Gas/Diesel)

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a.Die-Cast Aluminum Floodlight with electrocoat paint set 1.00 Prices of materials are variable per Region/
finish 70Watts - 250 Watts District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/ 8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

235 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1103 (1) Lighting Fixtures


Unit of Measurement : l.s.
Output : 1.00 l.s

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See derivation for Item 1103(1)- Item 1103(12) Labor Rates are variable per Region/District
based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See derivation for Item 1103(1)- Item 1103(12)

Sub - Total for B


C. Total (A + B)
D. Output = 1.00 l.s
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See derivation for Item 1103(1)- Item 1103(12) Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Office
Price Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. The "lumpsum" unit of measurement as per Blue Book, shall be based on the derived outputs of Item 1103(1) to
Item 1103(2).

236 Part D - Electrical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1200(13)a Air Conditioning and Refrigiration System


Unit of Measurement : l.s.
Output : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for B


C. Total (A + B)
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1200(13)b and 1200(13)c

237 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1201(1) Water Pumping System


Unit of Measurement : l.s.
Output : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Equipment Rental by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for B


C. Total (A + B)
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See Items 1201(2) - 1012(12)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

238 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Automatic Water Sprinkler System


Unit of Measurement : l.s.
Output : 1 l.s.

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

See Derivations for Items 1202(2) to 1012(12)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

See Derivations for Items 1202(2) to 1012(12)

Sub - Total for B


C. Total (A + B)
D. Output = 1 l.s.
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

See Derivations for Items 1202(2) to 1012(12)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

239 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(2) Fire Pump with complete control and standard accessories
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Fire Pump, complete with reinforced concrete
District based on the prevailing unit prices in
pad and following accessories: coupling and guard, the locality which include payment of local
mounted steel base plate, pump controller, flow taxes and hauling cost to the project site.
meter autorelease valve, suction and discharge set 1.000 Refer to the Construction Material Price Data
gauge, flow meter and other accessories specified established quarterly by Central Price
in mechanical plan and specification

b. Consumables (5% of material cost)

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

240 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(3) Jockey Pump with complete control and standard accessories
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor by Specialty Works or Manufacturer's/Supplier's Quotation (attach at least 3 quotations)

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Jockey Pump complete with controller and set 1.000 Prices of materials are variable per Region/
NEMA 3R and other accessories: valve, suction District based on the prevailing unit prices in
and discharge gauge, flow meter and other the locality which include payment of local
taxes and hauling cost to the project site.
accessories specified in mechanical plan and Refer to the Construction Material Price Data
specifications established quarterly by Central Price
b. Consumables (5% of material cost) Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

241 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Sprinkler Head, upright/pendent/wall


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.25 Labor Rates are variable per Region/District


b. Skilled Laborer 1 0.25 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Sprinkler Head, upright/pendent/wall pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

242 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Alarm Check Valve


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 4.00 Labor Rates are variable per Region/District


based on minimum wage as approved by
b. Skilled Laborer 1 4.00
DOLE. Refer to the Schedule of Labor Rates.
c Unskilled Laborer 1 4.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Alarm Check Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

243 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Flow Meter


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 3.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 3.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c Unskilled Laborer 1 3.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Flow meter pc 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

244 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) OS & Y Gate Valve 175 psi


Unit of Measurement : pc
Output per hour : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 3.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 3.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c Unskilled Laborer 1 3.00 Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. OS & Y Gate Valve 175 psi pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

245 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Pressure Gauge


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.50 Labor Rates are variable per Region/District


b. Skilled Laborer 1 0.50 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Pressure Gauge pc 1.00 Prices of materials are variable per Region/


District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

246 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Pressure Relief Valve


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 3.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 3.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c Unskilled Laborer 1 3.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour =
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Pressure Relief Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

247 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Floor Control Valve


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 3.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 3.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c Unskilled Laborer 1 3.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Pressure Relief Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

248 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Inspector Test Valve


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 0.75 Labor Rates are variable per


Region/District based on minimum wage
b. Skilled Laborer 1 0.75 as approved by DOLE. Refer to the
c Unskilled Laborer 1 0.75 Schedule of Labor Rates.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Inspector Test Valve pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

249 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Inspector Test Connection


Unit of Measurement : pc
Output : 1 pc

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 6.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 6.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c Unskilled Laborer 1 6.00 Rates.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 pc
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Inspector Test Connector pc 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

250 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) 25 mm Ø - 50 mm Ø Black Iron (B.I.) Pipe and Fittings


Unit of Measurement : length
Output per hour : 0.80 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Note :
Straight line installation, ceiling height of upto 3.5m.
Labor output includes setting, scafolding, cutting, fixing
of pipe from elbow, tee, flange, valve and painting.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.80 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 25 mm Ø - 50 mm Ø x 6.00 m Black Iron (B.I.) Prices of materials are variable per Region/
length 1.00 District based on the prevailing unit prices in
Pipe and Fittings the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1202(4)a1, 1202(4)a2, 1202(4)a3 and 1202(4)a4.

251 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) 65 mm Ø -150 mm Ø Black Iron (B.I.) Pipe and Fittings
Unit of Measurement : length
Output per hour : 0.75 length

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 1.00

Note :
Straight line installation, ceiling height of upto
3.5m. Labor output includes setting, scafolding, cutting,
fixing of pipe from elbow, tee, flange, valve and painting.

Sub - Total for A

Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0.75 length
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. 65 mm Ø -150 mm Ø x 6.00 m Black Iron (B.I.) Prices of materials are variable per Region/
length 1.00 District based on the prevailing unit prices in
Pipe and Fittings the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1202(4)a5, 1202(4)a6, 1202(4)a7 and 1202(4)a8.

252 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(1) Fittings


Unit of Measurement : pc
Output per hour :

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

Labor cost for these items are considered in the installation of pipes

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output per Hour = 0
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. B.I. 90 elbow/B.I. Tee/ Bell Reducer/ Blind Prices of materials are variable per Region/
District based on the prevailing unit prices in
Flange/ Slip Flange/ Riser Nipple/ Threadolet/ Pipe pc 1.00 the locality which include payment of local
Sleeve taxes and hauling cost to the project site.
b. Consumables (5% of material cost) Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1202(4)b, 1202(4)c, 1202(5)a, 1202(5)b, 1202(6)a, 1202(6)b, 1202(7)a, 1202(8)a and
1202(9)a.

253 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(7) Fire Hose Valve siames 150 mm Ø x 2 w x 65 mm Ø with cap
Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 3.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 3.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.
c. Unskilled Laborer 2 3.00

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

Prices of materials are variable per Region/


a. Fire Hose Valve siames 150 mm Ø x 2 w x 65 set 1.00 District based on the prevailing unit prices in
mm Ø with cap the locality which include payment of local
b. Consumables (5% of material cost) taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

254 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(5) Fire Hose Cabinet


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Construction Foreman 1 1.00 Labor Rates are variable per Region/District


b. Skilled Laborer 1 1.00 based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor
c. Unskilled Laborer 1 1.00
Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Hose Cabinet set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
b. Consumables (5% of material cost) the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)

255 Part E - Mechanical


DETAILED UNIT PRICE ANALYSIS (DUPA)

Item No./Description : 1202(a1) Fire Extinguisher


Unit of Measurement : set
Output : 1 set

Designation No. of Person/s No. of Hour/s Hourly Rate Amount (PhP)

A. Labor

a. Unskilled Laborer 1 0.50 Labor Rates are variable per Region/District


based on minimum wage as approved by
DOLE. Refer to the Schedule of Labor Rates.

Sub - Total for A


Name and Capacity No. of Unit/s No. of Hour/s Hourly Rate Amount (PhP)

B. Equipment

Sub - Total for B


C. Total (A + B)
D. Output = 1 set
E. Direct Unit Cost (C ÷ D)
Name and Specification Unit Quantity Unit Cost Amount (PhP)

F. Materials

a. Fire Extinguisher set 1.00 Prices of materials are variable per Region/
District based on the prevailing unit prices in
the locality which include payment of local
taxes and hauling cost to the project site.
Refer to the Construction Material Price Data
established quarterly by Central Price
Monitoring Committee.

G. Direct Unit Cost (E + F)


H. Overhead, Contingencies & Miscellaneous (OCM) Expenses 15%/ 12%/ 10%/ 8% of G
I. Contractor's Profit (CP) 10%/8% of G
J. Value Added Tax (VAT) 5% of (G + H + I)
K. Total Unit Cost (G + H + I + J)
Note : 1. Use this cost sheet for Item Nos. 1202(a2), 1202(a3), 1202(a4), and 1202(a5)

256 Part E - Mechanical


DERIVATION OF THE DUPA COST SHEET

CALCULATION OF PRODUCTIVITY OUTPUT


1. Set the output that you will measure. Works completed are useful aid for the computation
of the output productivity if it could be quantified well.
2. Create a gang composed of a combination of Skilled Laborers and Unskilled Laborers and/or
Equipment that will be used.
3. Set a monitoring period and monitor activities that are relative to the Item of work e.g., for
Item 1003(1) – Ceiling Works relative works are the installation of frames and installation of
boards.
4. Divide the total output by the input to get the productivity output.

CALCULATION OF MATERIALS FACTORS


1. Set the total quantity of work to be considered.
2. Estimate all the materials necessary for that certain output. Consider 5% waste factor.
3. Divide each material component by the total quantity of work.

Table 1.0 Derivation of DUPA


1. Quantity = 63 sq.m.

2. Materials TOTAL QTY UNIT FACTOR


a. 4.5mm Fiber Cement Board/ 4.5 mm Marine
Plywood/ 6 mm Marine Plywood/ 6mm Ordinary 23 pcs 0.365
Plywood
b.Metal Furring (size variable on plan and
71.25 pcs 1.131
and specifications ) 3m length
c. Carrying Channels 22.5 pcs 0.357
d. Hanger Bars/Rod 63 pcs 1.000
e. Channel clip 378 pcs 6.000
f. Wall Angle 15 pcs 0.238
g. Rivets 882 pcs 14.000
h. 1" Metal Screw 252 pcs 4.000

3. Labor
a. Construction Foreman 1
b. Skilled Laborer 1
c. Unskilled Laborer 2

ACTIVITIES DURATION OF ACTIVITIES (in hrs)


28.4
1. Installation of metal frames
22.28
2. Installation of Boards
50.68
CEILING WORKS
hrs

Production Output:
Quantity of Work = 63 square meter = 1.243 sq.m./hr
Time 50.68 hrs

257
258
SECTION C

COSTING OF SUPPORT EQUIPMENT

259
260
C. 1 Guidelines in Considering Support Equipment (Lifting
Equipment) for Construction of High-Rise Buildings
In this manual, outputs in the DUPA were adjusted to compensate the difficulty of work (e.g.
concrete works) for the construction of High-Rise Building. In cases where items of work shall
need support equipment (lifting equipment) to finish the work, this manual provides guidelines in
costing of such.

Unlike with the construction of low-rise buildings, construction of high-rise buildings requires
vertical transportation of resources (i.e. materials, labor, and equipment) in the construction site.
Typically, vertical transportation is mainly achieved by the use of temporary lifting hoist, tower
cranes and concrete pumping systems. Thus, this support equipment shall be included in the cost
of the project as separate pay item of work.

For this manual, it is suggested that the following costs shall be considered in the DUPA of Support
Equipment:

1. Rental Rate of the Equipment


2. Installation and Dismantling Cost
3. Operation and Maintenance Cost
4. Mobilization and Demobilization

In considering Support Equipment as separate item of work, choosing the most cost-efficient
model/capacity and proper planning in the utilization are the major factors that affect the cost of
the project.

Different models/capacity have different costs, thus, choosing the right capacity and model will
be beneficial for the project. Consideration in choosing the right equipment for costing in all your
project may be guided by the following:

1. Resources to be lifted.

It should be determined what resources shall be transported by the support equipment,


be material, workers and/or equipment.

Passenger hoists are preferably used to transport workers to the designated construction
floor level. However, if considering that the construction elevator shall be used to deliver
both materials and people, the estimator shall check the volume/weight of people versus
the materials to be delivered.

In cases wherein vast volume of building parts, construction materials (e.g. wide flanges,
reinforcing bars, or even concrete) and equipment are required to be delivered vertically
on the construction site, tower cranes are recommended to be utilized in the project.

261
2. Range, Height, and Weight Requirement

Another factor to be considered is the range, height and weight requirement of the
equipment to be utilized. The estimator should consider how to attain optimum resources
delivery on the project. Temporary construction elevators/hoists are used to lift resources
on a fixed point of the construction site, thus require manual efforts to move resources
horizontally. Unlike construction elevators/hoists, tower cranes are more versatile since
resources can be transported vertically and horizontally at the project site. Take into
considerations that the equipment will be supported by the structure as the building rises,
thus, coordination with the structural designer shall be undertaken.

To use tower cranes, the following factors should be considered:


 Maximum free-standing height of the crane
 Maximum braced height of the crane
 Weight, dimensions, lift height and radius of the heaviest loads

3. Safety Regulations and other Local Ordinances

Utilization of these equipment may cause safety hazards not only within the construction
premises but also with the surrounding environment. Such hazards are crush and falling
hazard. To mitigate such risk, most of the local government units requires assemble and
dismantling plan as well as strict safety certification. For example in utilizing tower cranes,
maximum height and possible available headroom which can be developed are need to
be considered specially to areas near airports.

Another vital factor which affects the cost for the support equipment is the duration of usage of
the equipment. It requires proper planning when such equipment will be utilized. For example,
during the structural works, tower cranes may be used in lifting structural members, RSB and
even delivery of fresh concrete by the used of buckets. However, during lifting of materials
involved in the architectural works, construction elevator/hoist are more likely being used. It is
also recommended to haul materials for interior works prior to enclosure of the building perimeter.

As a requirement in the approval of POW/DUPA and ABC, Project Schedule may be an aid for the
estimator in determining the duration of usage of the equipment.

262
SECTION D

CALCULATION OF CYCLE TIME


FOR HAULING EQUIPMENT

263
264
E. COMPUTATION OF LABOR RATES

E.1 BASIS OF COMPUTATION

The estimated labor rates for each region/district office were computed in accordance with D.O.
40, Series of 2009, Re: Guidelines for the establishment of Construction Materials Price Data,
Standard Labor and Equipment Rental Rates (or latest issuance), and based on the minimum
wage rate as published by the National Wages and Productivity Commission, Department of
Labor and Employment (DOLE).

The computed labor rates including all component costs such as basic wage plus emergency cost
of living allowance (ECOLA) and worker's statutory monetary benefits and others are in
accordance with the existing laws and government regulations. It shall be updated as the need
arises based on the latest issuances for new minimum wages by the NWPC/DOLE and/or any
amendments to the benefits of the workers.

E.2 CONDITIONS IN THE USAGE OF THE LABOR RATES

CASE I - In cases where project/s traverse/s certain barangays, municipalities, towns or


cities (with varying labor rates) of a concerned DEO, the average labor cost of
the said places shall be utilized by the DEO.

CASE II - In cases wherein project/s traverse/s certain provinces within the jurisdiction of
only one (1) Regional Office, the average labor cost of the said Regional Office
shall be utilized.

CASE III - In cases wherein project/s passes numerous provinces within the jurisdiction of
two (2) or more Regional Offices, the average labor cost of the said Regional
Office with the longest work coverage or with largest major scope of works
shall be utilized.

265
266
E.3 SAMPLE TABULATION OF LABOR RATES
DPWH - NCR
LOCATION : Cities of Caloocan, Las Piñas, Makati, Malabon, Mandaluyong, Manila, Marikina, Muntinlupa, Navotas, Parañaque, Pasay, Pasig, Quezon, San Juan, Taguig and
Valenzuela and the Municipality of Pateros
DATE OF ESTIMATE : February 2015
RESOURCE 13TH RATE RATE RATE
LABOR COST BASIC WAGE SOCIAL BENEFITS
CODE DESCRIPTION LEAVES MONTH PER PER PER
FACTOR
NO. DAILY MONTHLY PAY SSS/EC PHILHEALTH PAG-IBIG MONTH DAY HOUR
1 Foreman 1.80 838.80 20,970.00 838.80 1,747.50 1,090.00 250.00 100.00 24,996.30 999.85 124.98
2 Leadman 1.65 768.90 19,222.50 768.90 1,601.88 1,090.00 237.50 100.00 23,020.78 920.83 115.10
3 Heavy Equipment Operator 1.50 699.00 17,475.00 699.00 1,456.25 1,090.00 212.50 100.00 21,032.75 841.31 105.16
4 Highly Skilled Labor 1.50 699.00 17,475.00 699.00 1,456.25 1,090.00 212.50 100.00 21,032.75 841.31 105.16
5 Light Equipment Operator 1.40 652.40 16,310.00 652.40 1,359.17 1,090.00 200.00 100.00 19,711.57 788.46 98.56
6 Driver 1.30 605.80 15,145.00 605.80 1,262.08 1,090.00 187.50 100.00 18,390.38 735.62 91.95
7 Skilled Labor 1.30 605.80 15,145.00 605.80 1,262.08 1,090.00 187.50 100.00 18,390.38 735.62 91.95
8 Semi-skilled Labor 1.20 559.20 13,980.00 559.20 1,165.00 999.30 162.50 100.00 16,966.00 678.64 84.83
9 Unskilled Labor 1.00 466.00 11,650.00 466.00 970.83 822.70 137.50 100.00 14,147.03 565.88 70.74

NOTE:

Minimum Wage Rate = PhP 466.00


Basic Daily Compensation = Minimum Wage multiplied by the Labor Cost Index of each category
Leaves (Service Incentive Leave/
= Basic Daily Wage * 25 days per month* 12/300 days
Maternity/Paternal)
Bonus, 13th Month Pay = Basic Monthly Wage / 12
SSS Contribution = Graduated Amount Representing Employee's Contribution
Philhealth = Graduated Amount Representing Employee's Contribution
Pag-Ibig = 2% of Basic Monthly Compensation below P5,000.00 and P100.00 above P5,000.00
Employer's Compensation Contribution = P 10.00
Monthly Rate = Basic Monthly Wage + Leaves + 13th Month Pay + Social Benefits
Daily Rate = Monthly Rate / 25 days per month
Hourly Rate = Daily Rate / 8 h per day
268
SECTION F

EQUIPMENT RENTAL RATES

269
270
F. EQUIPMENT RENTAL RATES

Rental of equipment presented in the Detailed Unit Price Analysis (DUPA) are based on the prevailing “Association of
Carriers and Equipment Lessors, (ACEL) Inc.” rental rates approved for use by the DPWH (Presently it is the 2014
ACEL Rates). Rental rates of equipment not indicated in the ACEL booklet shall be taken from the rental rates
prepared by the Bureau of Equipment. For simplicity in computation, the operated rental rates are preferred over the
bare rental rates as the former includes operator’s wages, fringe benefits, fuel, oil, lubricants and equipment
maintenance.

F.1 List of equipment adopted in the standard DUPA with make, model and capacity

FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
1. Earthmoving Equipment
1.1 Bulldozer D6H SERIES II PSDS/DD 165 PhP 3,379.00
3 3
1.2 Payloader LX80-2C 1.50 m /1.95 yd 110 PhP 1,733.00
1.3 Motorized Road Grader G710A 140 PhP 2,173.00
2. Compaction Equipment
2.1 Plate Compactor 400-500 Gasoline Engine 5 PhP 123.00
3. Lifting Equipment
3.1 Crawler Crane All Models 21-25 mt 145 PhP 1,522.00
3.2 Crawler Crane All Models 36-40 mt 190 PhP 1,902.00
3.3 Crawler Crane All Models 41-45 mt 190 PhP 2,151.00
3.4 Truck Mounted Crane All Models 20-25 mT 200 PhP 1,631.00
3.5 Truck Mounted Crane All Models 31-35 mt 238 PhP 1,861.00
3.6 Truck Mounted Crane All Models 41-45 mt 246 PhP 2,606.00
3.7 Truck Mounted, Scissor Lift, Terrain Gas/Diesel Driven 40 ft hts x 46 ft range PhP 1,386.00
4. Excavating Equipment
4.1 Backhoe SE 130 LC-2 0.80 m3/1.04 yd3 99 PhP 1,537.00
3 3
4.2 Backhoe w/ Breaker SE 130 LC-2 0.80 m /1.04 yd 99 PhP 1,998.10
3 3
4.3 Backhoe, Wheel Mounted PW60N-1 0.28 m /0.37 yd 50 PhP 922.00
4.4 Portable Breaker WACKER PORTABLE PETROL BREAKER, BHF30S 4 PhP 129.38
5. Foundation Equipment
5.1 Diesel Hammer K25 - DSL 7500 kg-m PhP 1,286.00
5.2 Vibro Hammer DPD600T Hydraulic Pile Driver 60 ton 201 PhP 2,123.00
Vibro Hammer w/ Hydraulic Power
5.3 MHF12 w/ Hyd Power Pack 120 kN-m 222 PhP 4,118.00
Pack
5.4 Vibro Hammer VIBRO FONCEUR, PTC25H1A 45000 kg-m 272.22 PhP 3,069.00
C.M.V. TH18/65, 200 mm Ø 65
5.5 Drilling Rig m depth & 18000 kg-m Drill 300 PhP 12,637.00
Torque
6 Concreting Equipment
6.1 Concrete Screeder Wacker Truss Screed 5.50 PhP 545.00
6.2 Concrete Paver COMMANDER III, FOUR-TRACK PhP 6,765.00
6.3 One Bagger Mixer 4-6 ft3/min PhP 172.00
6.4 Transit Mixer All Models 5-6 yd3 175 PhP 1,318.00
7 Hauling Equipment
3
7.1 Dump Truck All Models 12 yd 290 PhP 1,420.00
7.2 Cargo/Service Truck All Models 2-5 mt 160 PhP 783.00
7.3 Boom Truck All Models 2-5 mt 160 PhP 1,017.90
7.4 Cargo/Service Truck All Models 9-10 mt 270 PhP 1,212.00
7.5 Water Truck/Pump All Makes 16000 L 360 PhP 2,450.00
8 Air Equipment
8.1 Air Compressor All Models 356-450 cfm 130 PhP 965.00
8.2 Air Compressor All Models 161-185 cfm 69 PhP 502.00
8.3 Air Compressor, Portable All Models 120-160 cfm 51 PhP 450.00
8.4 Air Compressor All Models 15-35 cfm 20 PhP 205.00
8.5 Diamond Drill CP-8 PhP 201.25
8.6 Jackhammer PhP 150.00
8.7 Pneumatic Drilling Machine PhP 170.00

271
SOLID SIZE FLYWHEEL
DESCRIPTION OUTPUT/DISCHARGE (lpm) RENTAL RATE
CAPACITY (mm) HORSEPOWER
9 Pumping Equipment
9.1 Water Pump, 100 mm suction Ø 2,667 50 16 PhP 266.25
9.2 Water Pump, 100 mm suction Ø 1,800 7.50 PhP 123.38
9.3 Pumpcrete PhP 2,076.00
CAPACITY
DESCRIPTION MODEL RENTAL RATE
kW kVA
10 Power Generating Equipment
10.1 Generator Set All Makes 301-350 kW 375 PhP 872.87
10.2 Generator Set All Makes 700 kW 875 PhP 2,147.27
FLYWHEEL
DESCRIPTION MODEL AMPERES RENTAL RATE
HORSEPOWER
11 Shop Equipment
11.1 Welding Machine Electric Driven/DC Output 500 PhP 391.00
11.2 Welding Machine Gas/Diesel Driven 300 48 PhP 371.00
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
12 Special Support Equipment
12.1 Chainsaw HUSQVARNA 2100 CD with CR22, 7 ft Reach, 9 in Standard Blade PhP 75.36
13. Miscellaneous Equipment
13.1 Concrete Vibrator Flexible Shaft Type 2" Head Ø with 5 Amperes Gasoline Drive Unit PhP 91.25
13.2 Bar Cutter 25 mm Maximum Rebar Ø (Grade 40), Single Phase PhP 219.75
13.3 Bar Bender 25 mm Maximum Rebar Ø, Three Phase PhP 351.50
14. Others
14.1 Drop Hammer w/ accessories 20 mt PhP 5,000.00
14.2 1 Air Compressor w/ 2 Jack Hammer PhP 1,265.00
14.3 Cutting Outfit PhP 45.45
Pile Integrity Testing (Sonic) &
accessories
14.4 PhP 65,000.00
(includes professional fee of Strcutural
Engineer and reports)

Pile Integrity Testing & accessories


14.5 (includes professional fee of Strcutural PhP 37,000.00
Engineer and reports)

Dynamic Pile Testing


14.6 (includes professional fee of Structural PhP 103,000.00
Engineer)
Tower Height = 28 ft, No. of Lights = 4 x 1000 watts, hp = 10.50
14.7 Lighting System/Tower Lights PhP
Generator = 5 kW 543.50
14.8 Bentonite Bin PhP 280.00
14.9 Bentonite Mixer PhP 173.00
15 SPT & Desanding Machine PhP 559.00
15.1 Tremie Pipe Set PhP 320.00
FLYWHEEL
DESCRIPTION MODEL CAPACITY RENTAL RATE
HORSEPOWER
16 Tower Crane
16.1 Topless Tower Crane MDT 98-1.2M 55M x 6T/1.2T PhP 4,221.00
16.2 Topless Tower Crane MDT 128 55M x 6T/1.6T PhP 5,664.00
16.3 Topless Tower Crane MDT 132 G8 55M x 8T/1.6T PhP 8,605.00
16.4 Topless Tower Crane MDT 162 H8 60M x 8T/ 1.8T PhP 8,895.00
16.5 Topless Tower Crane MDT 178 60M x 8T/ 1.5T PhP 6,419.00
16.6 Topless Tower Crane MDT 192 - H12 60M x 12T/ 2.2T PhP 8,390.00