6) Describe the nature of the area where the project was carried out
Name courses whose content was utilized in the project both directly and indirectly. If
you name academic courses, make sure that they are in your transcripts. If you have
undergone other training courses you can also state them here:
(c) Which engineering manuals or standards did you refer to during the project?
Sequence Diagrams of Switch board Control Panels.
Data sheets of all equipments used in Control Panels.
Installation instruction provided by contractors.
Manufacturers Designers reference handbooks of all equipments.
ANSI /IEEE Standard C37.2 Standard for Electrical Power System.
11) How did you prepare for the project? (eg. I met with my supervisor and discussed....
I prepared a project schedule ...etc)
When I was nominated in the commissioning team I was so excited to work on this
project because it was a different type of project where I have to learn many new things
and face the difficult challenges. So I started studying the technical articles related to
commissioning of power plants. I start collecting the standards of IEEE for
commissioning of Steam power plants.
12) The tasks assigned to you and how you went about accomplishing them. Please
include at least 4 tasks and sub tasks. Explain how each task was carried out.
Task-1
In the erection of above listed switchboard panels I was assigned a sub task to draw a
layout and Sequence arrangement of panel’s. Which I designed in CorelDraw and its
design is attached.
Task-2
Commissioning:
I prepare a control cable schedule for termination of control signals between Machines
field and central control room as per provided sequence diagrams of panels by vendors.
This schedule was calculated with reference to signals type, length of cable, route of
cables etc. i.e.4 core 4mm² flexible armored cables was selected for Current transforms
Secondary signals where total length of cable was 80m from Current transformer to
Protection Relay Panel.
Task-3
Following Protections were set and programmed through protection unit interfacing
software (Utility software 3) provided by vender (DEIF Denmark)
Attachment Task-3
Task-4
13) Technical difficulties/problems you encountered during the project and how you
solved them by applying engineering principles/knowledge. Below is an example of how
this question might be answered (note that this is just an example)
Ans:
This was the project of some different type where supply of equipments and control
panels was from different vendors across different countries and commissioning staff
from these vendors was also involved for commissioning supervisory of project. It was
very difficult and challenging for commissioning team to coordinate and interconnect the
control panels with each other. These control panels were designed as to use them as
universal control system not specially designed for this project. Sequence diagram and
drawings of these control panels were not designed to coordinate with each other
Solutions:
These matters were forwarded to the concern vendors of supplied equipments. They
make some amendments in their design, in sequence diagram and drawings with
suggestions to make changes on site in the control panels to coordinate with each
other. So many of control signals and there works of operations were modified as per
plant requirement. Such as power transducer was added in control panels to provide
load signal to WOODWARD 505 turbine speed control unit.
14) Strategies devised by you including any original or creative design work. Here you
can be creative and develop a practical case.
16) Briefly state how you observed the following in your projects:
3. loyalty
7. Accountability.
Ans:
This was a great time for me whom I spend in this project; this project had taught me
lot of skills and builds my career in a new way. Following are some lesson that i learn
in this project, This was the first time for me to generator start-up by the vendor and the
one that would conclude our functional testing. It also included the load bank testing,
alarm verification, and operational testing that included the ATSs. I felt comfortable
sharing this test with him so that on the next time out, he would remember me and have
a better understanding of any load bank testing that was required.
Ans :
I play a key role in the project that was the very crucial and important than all
others tasks. In execution phase, major job was erection testing & commissioning of
the machinery in a time bound manner without compromising on quality which i
perform very well as per the overall commissioning reports of the project.
(a) Two engineering Formulas that you used in your project and what they were used to
calculate:
1.
Ans:
2.
Ans:
this formula was used during secondary injection test of the Protections Relays to
calculate the CT/PT RATIO Test.
(b) Any other additional data you deem important (can be graphical results, pictures of
CAD models, circuits etc)