Scope of Work:

Sidewalk Shed Exterior facade repair, brick replacement, limestone patching, window sill
replacement, stucco repair and mortar joint West 32nd Street fo mat ee re-pointing, no
change to use, egress or occupancy.
Professional Statement

Drawing List: Total 5 Pages


A-001.00 Title Sheet, Scope of work, Notes, Plot Plan
A-002.00 Proposed Repairs at North and South Facades .
-003.00 Proposed Repairs at East Facades
A-004.00 Repair Details, Re-pointing, Brick Replacement Window sill Replacement, Stucco
Repairs
A-005.00 Repair Details, Limestone Patching
Energy Code Analysis for Alteration, _ Area (SFHA) * /| 8 story Climate Zone 4 (Per 2016) in
“% A Lexterior facade repair including stucco repair
repair brick replacement, brick pointing, , SN
limestone patching and pointing, Fa
Alteration, renovations or repairs to Rear Yard
walls and floors and floors in cases where the existing structure is without framing cavities
and no new framing cavities are created:
There is no space to install additional
. General Notes
1. The contractor shall verify all existing conditions prior to the start of work.
insulation materials between lintels and bricks
2. All work shall meet the requirements of the New York City Department of Buildings and
federal requirements.
3. The Contractor shall obtain all required permits and insurances prior start
of work
7. Contractor shall comply with all wooden structural members.
8. This engineer has no control over contractor's means and methods
9. the oer Of design bas not been retained for any field supervision
To the best of my knowledge, belief and professional

which will create hazardous and unsafe conditions Bi es


: and is not judgment, these plans and specifications are in compliance responsible for
construction and will not be held responsible for any damages with the New York City
Energy Conservation Code 2016. or

Tenant Protection Plan as per - 2016 Code inspection; his responsibility is limited to the
accuracy of these plans. Building Code 28-104.8.4: 10. contractor shall ~ and verify all
conditions and dimensions and report
“Thi ' any discrepancies to the engineer prior to commencement of work.
1 The building contains . dwelling units that will be occupied during construction\ii,
ccmiractir stall ty shore, underpin and make safe all walls, sidewalks,
2. The construction work is confined to existing exterior facade.

3. There will be nobody accessing the proposed exterior constructionarea to be


renovated during the course of construction work.

4. Egress: required egress shall not be obstructed at any time. Egress at existing
corridors; fire stairs, etc. must be maintained at all times.

5. All existing means of egress may not be used to store materials, equipment and debris.
Transportation of all materials, equipment and debris must be coordinated with
building superintendent.

6. Existing fire safety for all occupied units shall be maintained and not diminished. All
building materials stored at construction area and /or in any area of the building are
to be secured in a locked area. Access to such areas are to be controlled by the building
owner and or general contractor.

7. The general contractor shall ensure that dust is controlled and that disposal of
construction debris is performed in such a manner as to not interfere with occupied
units. Debris, dirt and dust are to be kept to a minimum and be confined to the
immediate construction area, and be cleaned up and cleared from the building
periodically to avoid any excessive accumulation.

8. The general contractor shall ensure that noise is limited to acceptable levels in
accordance with the New York City noise control code.
9. Construction operations will be confined to normal working hours 9am to Spm,
Mondays thru Fridays, except legal holidays. Unless an after-hours work permit
variance is secured from the department of buildings.

10. Structural: no structural work shall be done that may endanger the occupants.

Tenant Safety Notes:


1. Egress: At all times in the course of construction, clear the halls, exits and fire escape
drop ladder landing areas so they are free of debris and obstructions. Construction
operation will not block hallways or means of egress for tenants of the building.

2. Fire Safety: All necessary laws and controls, including those with respect to occupied
dwellings, as well as additional safety measures necessitated by the construction shall
be strictly observed.

3. Health requirements. Disposal of construction debris should be conducted daily at the


end of each work day. Construction operations will not involve interruption of heating,
water, or electrical services to other tenants of the building.

4. Compliance with housing standards. All work to conform to housing and maintenance
code. The New York State Multiple Dwelling law shall be strictly observed.

5. Structural safety. No structural work shall be done that may endanger the occupants.
Noise restrictions. Construction operations will be confined to normal working hours:
8am to Spm Mondays through Fridays, except holidays.

6. Noise restrictions. Where hours of the day or the days of the week in which
construction work may be undertaken are limited pursuant to the New York city noise
control code, such limitation shall be stated.

7. If project are affected by lead and asbestos are present they should be removed
according to all the provisions and laws.

footings, foundations and adjacent property as job conditions require, except water and
rock.
all notes herein mentioned with those on the various drawings shall apply to all drawings
and specifications forming part of this project.
13. the contractor and/or owner and/or their agents shall carry out the permitted work or
use in accordance with the provisions of the building code and other applicable laws
and regulations whether specified or not, except insofar variations therefrom have
been legally permitted or authorized, it being understood that the engineer's
responsibility is limited to the accuracy of plans. all work shall conform to the
approved application and accompanying plans and papers and any approved
amendments thereto.

14. all building operations shall be conducted in accordance with and subject
to the safety requirements of this code and any other applicable laws, rules and regulations.
(n-y. state industrial code rule 23, u.s. dept. of labor, safety and health regulations for
construction, part 1518).
contractor shall obtain separate permit from the department of transportation for all work
beyond the curb line at owner's expense.
contractor is responsible for verifications of all dimensions and conditions before work
begins.
contractor shall be responsible for and changes and deviations of the approved plans.
Special and Progress Inspections:

12. Masonry BC 1704.5


13. Structural Safety, Structural Stability BC 1704.20.1

14. Final Inspection BC 110.5 Directive 14 of 1975, and 1 RCNY 101-10 EXAMINED FOR
ZONING, EGRESS AND PREVENTION ONLY AS PER DIR. NO, 7 OF ys

Legend:
1-Brick Replacement
2- Re-pointing
3 Limestone Patching
(4) Stucco Repair (
5) Window Sill Replacement

4. Dampen joints

5. Add water to p;

6. Work will take

Undamag
Cracked Mortar Joint Re-pointin Scale: N.T.S. pomeng
pulled away stucco coating Removal of Cracked Stucco Section N.T.S. Joints Notes: Teortar
mortar with a 1,1,6 mix of lime to cement
to san otha ter without any plasticizers, air entraining additives Morten Jat conte
surrounding bricks, which may result in brick damages,
Repairs Procedures:
2 Remove data ts 3” dep, taking care not o damage edges of existing brick Bs Pre lust and
debris from joint by brushing blowing with air or rineine wir er 3. Pre-hydrate new mortar
to reduce shri .
to be tuck-pointed., ; re-hydrate mortar to make a workable consistency,
6. «hea mortar tightly into joint in thin layers (1/4” max. each layer should be “thumb-
print” hard before applying next layer. .

7. After placement of last layer, tool joint to match original profile.

8. Wanical mortar joints should be scraped by hand, not by power tools,

Place only when the exterior temperature i 4 constant 45 degrees


or above for a 72-hour period from the commencement of wore
Correct Mortar Joint Pre aration Correct Mortar Joint Profile Mortar cleaned out to a
uniform Side view Front view depth-approximately 3/4"-|" deep Joints = = =
slightly
ed brick edges recessed
Remove existing facade
DUTT
Existing back-up brick/block masonry to remain
12 GA. S.S. veneer anchor secured to back-up masonry with 1/4" diameter, 2" long flat
zamac nailing fastener, two per each anchor.
3/16" diameter, 3" long S.S. "V" ties spaced 16" 0.c. vertically and 18" o.c. horizontally
staggered.
1. Adjacent masonry remain temporary
protection and shoring
as required. ee i i
Zz: inoue [_ ] | ssindicaed Page. TI T7 LI
back-up m
smooth. Replace wi(N) [ I ] brick masonry. Tooth
into adjacent masonry.
to
=II
__| Retain headers if intact. CL | ] | | |
3. Brick color, texture I
and size to match -xisting.
I I It CIT 7 tL
A7
!. Non-corrosive
elical wall ties — 1-5 GEO tl t 3 courses max. ——
rettically and becwtNncesl ik | {| orizontally .
sntered on crack. Elevation
3. Provide brick and rtar sample in
ice for engineer ‘lew,
aca,
Plan Section =a Section
rick Masonry Crack Repair ale: N.T.S,
ee
EXISTING WINDOW ASSEMBLY
TO REMAIN aa
NEW WATERPROOFING MEMBRANE
NEW CAULKING
MORTAR KEY (3/4" WIDE, 1/2" DEEP)
NEW CAST STONE WINDOWSILL
DRIP EDGE
NEW SETTING BED MORTAR
EXISTING FACE BRICK WORK TO REMAIN
EXISTING BACKUP MASONRY —~ TO REMAIN
Window Sill Replacement Detail Scale: N.T.S.
00.000 0 A
DEPT, BLDGS, 1235
ec a
EXAMINED FOR ZONING, EGRESS AND FIRE PREVENTION ONLY, AS PER DIR. NO, 2 OF
1975
Exterior facade repair, brick replacement, limestone patching,
Repair Details Re-pointing, Brick & Sill Replacement, Stucco Repairs 4 of 5
A004.00

Legend: (2) Re-pointing


(4) Stucco Repair
1) Brick Replacement
3) Limestone Patching
(5) Window Sill Replacement
EXAMINED FOR ZONING, EGRESS AND FIRE PREVENTION ONLY, AS PER DIR, NO. 2 OF
1975
Brick Masonry Crack Repair
1. Remove all loose and deteriorated masonry from the repair area plus an additional
1/4" to sound substrate prepare 1/2" min. square-cut shoulder at perimeter of patch.

2. Scarify substrate w/toothed chisel to provide greater surface area for bond.
Thoroughly clean substrate w/clean water and natural bristle brush to remove all
debris dusr, grease and/or laitance that may prevent proper adhesive.

3. Moisten porous substrates until glisten wet at vertical applications and well dampened
surface (w/no ponding water) at horizontal applications.
4. Mix repair mortar as per manufacturer's directions to the consistency of wet putty,
a.k.a. the 'peanut butter’ coat. Apply the 'peanut butter’ coat to the moistened
substrate appx. 1/8" thick. NB. ensure ‘peanut butter’ coat is applied to shoulders of
repair.

5. Whilst 'peanut butter’ coat is stil] wet, apply the (drier) repair mortar mixed according
to manufacturer's directions build up the material beyond the surface of the original
material (1/8" min.)

6. Whilst mortar is still damp pre-screed or Scrape the mortar down, leaving it appx.
1/8" proud. Allow mortar to dry before final finishing. Clean around edge of patch
w/sponge and clean water to remove €xcess mortar from adjacent masonry.

7. After achieving initial set, when repair mortar has consistency of slightly damp sand,
scrape away excess mortar a little at a time until desired profile is reached.
8. During curing process keep patch and adjacent masonry damp by misting periodically

and shading for several days after installation, according to ambient conditions.
9. Remove uncured mortar from perimeter of patch w/sponage and clean water several
times before it dries to prevent ‘halo’ effect at adjacent masonry.
NB. Provide appx. 4"x4" sample in place for engineer's review.
Limestone Spall Patch Repair - Shallow: =< 1" depth, <= 6" Face Dimension
1. Remove all loose and deteriorated masonry from the repair area plus an additional
1/4" to sound substrate prepare 1/4" min. square-cut shoulder at perimeter of patch.

2. Scarify substrate w/toothed chisel to provide greater surface area for bond.
Thoroughly clean substrate w/clean water and natural bristle brush to remove all
debris dust, grease and/or laitance that may prevent proper adhesive.

3. Install and embed stainless steel threaded rod and/or ssl. welded wire mesh
reinforcement (as appropriate) where repair depth exceeds 1" or face dimensions
exceed 6" in any direction.

4. Moisten porous substrates until glisten wet at vertical applications and well dampened
surface (w/no ponding water) at horizontal applications.

5. Mix repair mortar as per manufacturer's directions to the consistency of wet putty,
a.k.a. the 'peanut butter’ coat. Apply the 'peanut butter’ coat to the moistened
substrate appx. 1/8" thick. NB. ensure ‘peanut butter’ coat is applied to shoulders of
repair.

6. Whilst 'peanut butter’ coat is still wet, apply the (drier) repair mortar mixed according
to manufacturer's directions build up the material beyond the surface of the original
material (1/8" min.)

7. Whilst mortar is still damp pre-screed or scrape the mortar down, leaving it appx. 1/8"
proud. Allow mortar to dry before final finishing. Clean around edge of patch
w/sponge and clean water to remove excess mortar from adjacent masonry.

8. After achieving initial set, when repair mortar has consistency of slightly damp sand,
scrape away excess mortar a little at a time until desired profile is reached.

9. During curing process keep patch and adjacent masonry damp by misting periodically

and shading for several days after installation, according to ambient conditions.
10. Remove uncured mortar from perimeter of patch w/sponage and clean water several
times before it dries to prevent ‘halo’ effect at adjacent masonry.
NB. Provide appx. 4"x4" sample in place for engineer's review.
Limestone Spall Patch Repair - Deep: > 1" depth, > 6" Face Dimension Scale: N.T.S.
Job No. 889372
Exterior facade repair, brick replacement, limestone patching, window sill replacement,
stucco repair and mortar joint re-pointing, no change to use, egress or Occupancy.