Sie sind auf Seite 1von 6

Notice of Retraction

After careful and considered review of the content of this paper by a duly
constituted expert committee, this paper has been found to be in violation of
IEEE's Publication Principles.

We hereby retract the content of this paper. Reasonable effort should be made to
remove all past references to this paper.

The presenting author of this paper has the option to appeal this decision by
contacting TPII@ieee.org.
Construction Project Schedule Risk Analysis and Assessment Using Monte Carlo
Simulation Method

12 1 2 12
Dezhi Jin , , Zhuofu Wang , Xun Liu \ Jianming Yang , Meigui Han ,
1. Institute of Construction P roject Management, Hohai University,Nanjing, China
2. School of Engineering, Nanjing Agricultural University, Nanjing, China
jindezhi@njau.edu.cn

Abstract-Construction projects are initiated in complex and uncertainty associated with construction development in
dynamic environments resulting in circumstances of high terms of time. When specifically considering the execution
uncertainty and risk, which are compounded by demanding of a construction project, controlling risks resulting from the
time constraints. This paper describes an application of Monte uncertainty is accomplished through the achievement of
Carlo simulation method to consider and quantify uncertainty reliable project schedules. In reality, failure to fulfill the
in construction scheduling. This paper points out the
project objectives within cost and on time is quite common.
importance of the construction project scheduling risk analysis
As a result of techniques, such as probabilistic scheduling,
and assessment from the perspective of contractor and points
and stochastic process (Monte Carlo simulation), being
out the limitations of project management network techniques
systematically employed at the start of a project's
(CPMlPERT). Based on analyzing the principle of construction
development, the uncertainty related to duration is
project scheduling risk analysis and assessment using Mote
Carlo simulation method, the evaluating steps of Mote Carlo
considerable due to the probability of future complicated
simulation method are given. Ultimately, the outcomes of the
conditions and changing environments. One main concern of
paper are illustrated by an instance. a project manager or decision maker is not to exceed the
approved project's cost and schedule. Indeed, a project
Keywords-construction project; scheduling risk; Me; risk control effort is devoted to ensuring that the actual cost does
assessment not deviate from the planned cost and that the project is
completed on schedule.
I. INTRODUCTION
II. LIMITATIONSOF CPM ANDPERT
In today's construction industry, the engineering
construction project, especially the large investment project, A. Limitations o/CPM
often has huge investment, long construction period, The basic assumption of CPM is that each activity'S
technological and economy risk, the great potential impact to duration as well as the logical relationships between
the ecological environment, uncertain factors. So these activities is determined in a network schedule. However,
characteristics incur that the factual project deviate from the there exist a lot of uncertainty factors such as politics,
consequence that people expect by a certain degree. The economy, meteorological and hydrological conditions,
losses result from risks increasing with the size and construction scheme, resource supply, construction
complexity of construction projects, even determine the environment and so on, which may cause that construction
success or failure of the construction projects. The site conditions are difficult to be completely accurately
preparation of the construction project schedule is primarily proven and that project implementation will be influenced by
based on engineering quantity and resources allocation, storm, flood, typhoon, etc. These uncertain factors in the
construction quota and other factors. However, these factors construction project make both the durations of activities and
are uncertainty in actual construction. The objective of the logical relationships between them in highly uncertain
project schedule, as one of the three control objectives, status.
affects the cost targets and quality targets. When the Therefore, it is necessary for us to focus on how to
construction project schedule risk occurs, the contractor in calculate the time parameters and determine whether the
order to rush the progress is bound to increase the human and construction project can be completed on time. When the
material resources, make the cost of the project will increase, construction plan can not be realized, the so-called schedule
and the project quality is also easy to problems. When the risk has been formed. As to this kind of network schedule
progress of the out of control, resulting in significant problem with uncertain activity durations, the basic salvation
schedule delays, so that the project can not be put into methods include PERT and Monte Carlo (MC).
production on schedule to benefit not only to owners to pay
the contractor the tender stated in the annex to the B. Limitations o/PERT
corresponding amount as damages for breach of schedule Based on mathematical statistics theory, PERT is often
delay costs, but also seriously affect the company's used to solve network schedule problems with definite
reputation, the company bid in the future rather than reactive. logical relationships and uncertain activity durations. It is
In today's construction industry, one of the important simple, but still with some obvious deficiencies as follows:
goals is the quantification and minimization of the

978-1-4244-6932-1/10/$26.00 ©2010 IEEE

597
(i) It requests that activity durations should obey � the probability models of each random variance are
distribution or normal distribution and that the critical path's constructed, which are done sampling and then each
duration should obey normal distribution. When an actual activity's duration will be determined, this process is
project does not meet the conditions, the calculation equivalent to simulation for one time [7]. Every time when
precision will be obviously influenced. The activity durations doing an experiment, we use sampling technique fIrst and get
in PERT are assumed to be random and obey � distribution. the random data of activity durations, then we can calculate
Therefore, the activity durations can be estimated by three­ the random project duration r; with CPM. After simulating
point method [1]. It is mainly for the calculation convenience for N times, we can get random duration
to assume that the activity durations obey � distribution,
serialization {r; Xi 1,2,.··, N) , and then we make on the
=

which can be only determined by the most optimistic and the


most conservative time. Actually we can also assume the random values of project duration, and get its expected value
durations obey triangle distribution, normal distribution or and variance as well as the schedule risk under required
Gamma distribution, etc. As long as you don't choose a very duration. Z. Xu and Y. C. Feng made a statistical analysis on
extreme random variable, the random distribution of project the simulation results of total duration and obtained a
duration will not be influenced by it [2-3]. Under these histogram, which was approximately regarded as the
circumstances, as existing research shows, the project probability density function curve of total duration [8].
basically obey normal distribution when there are no more C. Steps of schedule risk assessment using MC method
than 20 critical activities [4]. In PERT, after obtaining all the
Based on the research results of Z. F. Wang and D. X.
activity durations, we can calculate the time parameters,
expected duration and schedule risk by CPM. Chen [9], we can get the general steps of schedule risk
(ii) It does not take into account the interaction of paths assessment using MC method as follows:
in the network diagram, so that the expected duration is (i) Determine the distribution type of activities, such as �
calculated relatively small while the variance is relatively distribution, and determine the simulation times N .
large. PERT undermines the probability characteristic of (ii) Calculate the three time estimations of activity
activity durations, which results in low reliability in scheme durations, denoted as a, b and m .
implementation. In fact, PERT needs several requirements (iii) According to the distribution of activity durations,
such as (a) the activity durations are independent random get the sampling time ui of each activity by sampling,
variables and (b) only one path dominates while the other
paths will hardly become critical paths i.e. the probability namely the random time Ui •

can be neglected. In practical projects, we may encounter


problems with considerations of several critical paths, for
(iv) Calculate the project duration 1; with CPM
which some people put forward several salvation algorithms. according to the sampling time of each activity U i •

In this respect, Bajis Dodin did some research [5-6].


(v) Repeat steps 3 and 4 and achieve {r; Xi = 1,2,.··,N)
III. ADVANTAGES, ApPLICATION PREMISE AND (vi) Make statistical analysis on {r;} and get the expected
CALCULATION STEPSOFMc METHOD value and standard deviation of duration.
(vii) Calculate the schedule risk using (1) and (2)
A. Advantages according to the known or assumed required duration.
MC method can overcome the shortcomings of PERT, it
is suitable for all kinds of distribution of activities, � O'n T2
5, Ts -Te) l
_e-2 dT
distribution is not a must. When the number of simulation is peT =
J (1)
_

big enough, the calculation result has high accuracy. When a u -00 .J27r
n
project has large scale or many activities, the computing
Pr =l-P (2)
quantity is large under a certain requirement of calculation
accuracy. What's more, when the accuracy requirement Where Ts is required duration, Te is the expected
increases one magnitude, the calculation quantity should
increase two magnitudes, which can be realized by computer. duration on the critical path, u is the standard deviation on
n
Clearly, with the development of computer technology, using the critical path, P is completion probability while Pr is
MC method to assess schedule risk of a project has obvious
the schedule risk.
advantage.
B. Basic principle to evaluate schedule risk with MC IV. CASE STUDY

method A certain schedule network graph is shown in Fig. 1, the


MC method assumes that each activity is randomly time estimations of activities in which are calculated as
independent. It is a computer simulation method suitable for shown in Table 1.
all kinds of distribution of activities. Its basic principle is to
do plenty of tests and statistical analysis on computer, firstly,

598
Figure 1. A Certain Schedule Project Network Graph

TABLE I. THE TIME ESTIMATIONS OF ACTIVITIES IN A CERTAIN SCHEDULE NETWORK GRAPH

Activity Optimistic duration (a) Most likely duration Pessimistic duration (b)
(i, j) (m)

1,2 8 10 12

1,3 4 5 6

1,4 4 7 9

1,5 4 5 6

2,3 4 5 7

2,6 16 18 20

3,4 2 4 5

3,7 3 6 9

4,7 2 3 5

5,7 7 8 9

5,8 7 9 10

6,7 14 16 18

6,8 2 3 5

6,9 3 4 5

7,8 6 9 11

8,9 9 11 13

8,10 3 5 8

8,11 2 7 12

8,12 3 5 6

9,10 3 5 7

9,13 17 19 21

10,11 2 4 6

10,14 2 4 5

Activity Optimistic duration (a) Most likely duration Pessimistic duration (b)
(i, j) (m)
11,14 2 7 9

599
12,14 7 9 10

12,15 8 9 10

13,14 13 15 17

13,15 2 3 4

13,16 2 4 5

14,15 7 9 11

15,16 8 10 12

15,17 2 5 8

15,18 3 7 12

15,19 4 5 6

16,17 2 5 6

16,20 16 18 20

17,18 3 4 6

17,21 3 6 9

18,21 2 3 5

19,21 7 8 9

19,22 7 9 10

20,21 14 16 18

20,22 2 3 5

21,22 8 10 12

Due to determine the critical path need to calculate the


latest finish time (LF) and the earliest fmish time (EF), the
latest start time (LS) and the earliest start time (ES) of each
activity, the progress is complex. For the sake of brevity, by
a simple transformation, network diagrams by solving the
critical path conversion For the sake of the shortest path, and
use the Dijstra algorithm, and then the shortest path is
converted to the critical path [10]. Use the tool of MATLAB
calculates the expected duration and variance of project, the
flowchart as shown in Figure 2.

600
Determining the times of simulation schedule risks can be calculated accordingly. For example,
when the regulated duration of schedule is 155 days, the
completion probability is 0.68%, and that is to say, the risk
of project can not be completed on time is 99.32%.
Acquiring the parameters of each activity for the
construction project V. CONCLUSIONS

MC method is a kind of numerical calculation method; it


Constructing the adjacency matrix of critical path can only give a feasible solution to the problem, but not a
according to the parameters of each activity general solution. In order to get the optimal solution or
satisfactory solution, we need to carry on multiple
simulations. MC method determines the numerical relation
Transforming the adjacency matrix of critical path between variables through mathematical models, but not by
into the matrix of the shortest path peer mathematic method. It is a kind of method to solve
problem by experiment on computer. It can give the fmal
solution to the model test, but cannot get some intermediate
Calculating the shortest path of project network results. In the simulation process of project schedule risk, we
using the algorithm method of Dijstra can get some parameters related with project duration, but
cannot get the detailed time parameters of each activity. MC
method requires that each random variable should be
independent. The whole simulation process is a repeated
Transforming the shortest path into critical
path, obtain the total duration of project
operation process. The calculation needs to occupy much
computer memory and burden.

ACKNOWLEDGMENT

NO This paper is supported by agricultural machinery bureau


of Jiangsu province foundation, P roject Number: gxs08007

REFERENCES
[I] Li Qinghua, The Collection of Chinese Network Plan. Beijing:
Earthquake Press, 1993, pp.807-8I2.
Calculating the expected value and variance of
total duration for project
[2] T. K. Littlefield, and P. H. Randolph, "An answer to sasieni's
question on PERT times, " Management Science, vol. 33, issue. 10,
October 1987, pp. 1357-1359.
[3] K. R. MacCrimmon, and C. A. Ryavec, "An analytical study of the
Figure 2. Simulation flow chart of the progress of the project
PERT assumptions," Operations Research, vol. 12, issue. I, 1964, pp.
16-37.
The results of simulated 10000 times are shown in Table [4] Li Gansheng, Wang Zhuofu, and Bai Hongkun, "Network planning
2 and Fig. 3. computer simulation and risk analysis, " Journal of Hohai University,
vol. 29, issue. 1, 2001, pp. 65-69.
TABLE II. The DURATION and variance of project SIMULATED 10000
[5] Bajis Dodin, "Determining the k most critical paths in PERT
TIMES
network, " Operations Research, vol. 32, issue. 4, 1984, pp. 859-877.
[6] Bajis Dodin, "Bounding the project completion time distribution in
Simulated times Mean (day) Variance (day)
PERT network," Operations Research, vol 33, issue 4, 1985, pp. 862-
881.
10000 160.8467 2.3670
[7] Jamal F. AI-Babar, Keith C. Crandall, "Systematic risk management
approach for construction project, " Journal of Construction
Engineering and Management, vol. 116, issue 3, 1990, pp. 533-546.
[8] Xu Zhe, and Feng Yuncheng, "Risk analysis of network project, "
Systems Engineering Theory and Practice, 1998, issue. 4, pp. 25-28.
[9] Wang Zhuofu, and Chen Dengxing, "risk analysis of water
conservancy and hydropower construction schedule," Journal of
Hohai University, vol. 27, issue. 4, 1999, pp.83-84.
[l0] Shu Xingming, "Seeking Critical path through the shortest path
method and And its implementation of SAS," Journal of Guangxi
University, vol. 27, issue. 1,2002, pp. 264-269
Figure 3. The line of chart total duration simulated 10000 times

If the schedule of the construction be simulated 10000


times, can be obtained the mean of construction project
duration is 160.85 days, and the variance is 2.37 days. Given
a required time limit, the probability of completion and the

601

Das könnte Ihnen auch gefallen