Progress Assessment Report

Project Name: Al baha Hotel Location: Al Baha


Owner: Al baha Holding Company Represented by: Engr. Safer Al Zaharani
Consultant: Engr. Mosbeh Al-assaf Represented by: Engr. Mohammad Ali
Engineering Consultant Engr. Ronie Medel
& Soil Testing
Contractor: Mawten Al-Emar Holding Co. Represented by: Engr. Hussain

Contract duration: (Dec. 13, 2016 - July 30, 2017)

Major job Accomplishments inclusive date: ( dec.13,2016 - April 01,2017) based on item mentioned on the BOQ
Division Item Percent of
Accomplishments
Bill 1-Div 1 Preliminaries All items ( except general notes for turnover) 100%
Bill 1-Div 2 Preliminaries - Demolition Page 1, Item A - C 100%
Page 1, Item D 50%
Page 2, Item E 0%
Page 2, Item F 60%

Bill 2-Div 2 Main Building - Site works All Items 100%

Bill 2-Div 3 Main Building - Concrete All items 80%


works

Bill 2-Div 4 Main Building - Masonry All items 90%


works

Bill 2-Div 5 Main Building - Metal works All items 35%

Bill 2-Div 6 Main Building - Wood / All items 0%


Carpentry works

Bill 2-Div 7 Main Building - Thermal and All Items 0%


Moisture Protection

Bill 2-Div 8 Main Building - Doors and All Items 5%


Windows

Bill 2-Div 9 Main Building - Floor Wall All items Page 1 (Floor Finishes) 10%
Ceiling Finishes
All items Page 2 (Floor Finishes, skirting's) 0%
All Items Page 3 (Wall Finishes) 30%

1
All Items Page 4,5,6 ( external wall Finishing) 0%

All Items Page 7 & 8 ( Ceiling Finishes) 0%

Bill 2-Div 10 Main Building - Mechanical All Items (Specialties/accessories) 0%


Engineering

Bill 2-Div 11 Main Building - Mechanical All Items Page 1 (Fire Fighting) 0%
Engineering
All Items Page 2 ( Domestic Water supply) 90%
All Items Page 3 (Sanitary Drainage System) 65%
All Items Page 4&5 (Plumbing Fixtures) 0%
All Items Page 6 ( AC units) 35%
All Items Page 7 (Ventilation and exhaust System) 0%
All Items Page 8 (AC diffusers) 0%
All Items Page 9 (Elevators) 0%

Bill 2-Div 12 Main Building - Electrical All Items (Satellite, Telephone, Lighting, switches, 5%
Engineering power outlets, Panel boards, cabling, internet)

Overall Progress Assessment 15-18% progress based on the BOQ items delivered on the site and work done

Time spent for the Progress 111 days out of 227days ( 48.90%)

Manpower and Site Activities Record for the month of March 2017
Activities Starting Date End Date Average Daily
Manpower
Retaining Wall building (carpenter and steel man) March 05 March 25 7
Skeleton Concrete structure (carpenter and steel man) Previous month continuous 7
Internal Wall Plaster Previous month continuous 3
Internal Wall building Previous month continuous 3
Electrical works Previous month continuous 2
Cleaning Previous month continuous 6
Carpentry ( door frames) March 05 March 20 2
Plumbing works Previous month continuous 1
Mechanical (Air condition, internal units and line fixing) Previous month continuous 2
Steel structure (ground floor storage and emergency exit) March 12 continuous 4
Internal Wall paintings (first layer) March 22 continuous 4
Demolition on slab for exhaust duct March 20 continuous 4

2
Other extra works being done on the site (items not on the BOQ or on original plan)
Description Location Percentage of
work done
Building of retaining wall Beside service elevator 90%
Building of extra emergency exit including finishing Back of baskin and 20%
Robins
Building of kitchen on the roof level including finishing Roof level 10%
Building of 2 units suites on top of laundry area Rear side 0%
Units and Suite rearrangements such as arch room, units on 3rd level, Multiple areas 80%
and new emergency exit
Parapet remodeling and plastering Roof parapet walls 0%
Demolition and replacement of existing exterior cornice. Exterior elevation 0%

Items of interest
 Installation of pipe sleeves on all toilets and all related sanitary items.
 Insulation of wet areas such as kitchen and toilets.
 Building of Model Suite for all item approval.
 GRC demolition on exterior elevation.
 Gypsum Wall finishing on all rooms and hallways
 Demolition and rebuilding of the wall attached to the rocks causing moisture penetration to the existing wall.
 Reshaping of the parapet according to the approved shop drawing given.
 Exhaust system testing.
 Concrete plaster fixing specially on the bottom end of the wall and on corners.
 Air condition exit pipes replacement on all units at first floor. All pipes should be at minimum of size of 1".
 Building of concrete structure for the 2 unit suites on top of laundry.
 Installation of the approved items such as windows and elevators.
 Submission of ceramic samples for toilets.
 Replacement of project banners/bulletin with a bigger size and with contact numbers of the owner, consultant
and contractor.