ROL 1C1D : Construction of Sullage Water Treatment Plant & Pump Sum

ID Task Name Duration Start Finish 2018 2019 2020


1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
951 INTERCEPTOR WORK 829.5 days 5/1/17 3/10/19
952 Preliminaries 819.5 days 5/1/17 21/9/19
953  Site survey 14 days 17/7/17 1/8/17
954  Soil investigation 63 days 7/6/17 18/8/17
955  Protection of adjacent building 5.6 days 11/12/17 16/12/17
956 Utilities piloting 0 days 5/1/17 6/9/17
957  Confirmation of interceptor coordinate 1 day 10/11/17 10/11/17
958 Environmental Management Plan 279.4 days 1/2/18 12/1/19
961 Settlement monitoring after completion 7 days 17/4/18 24/4/18
962 Inspection and maintenance 254.51 days 13/11/18 21/9/19
965 Sullage Water Treatment Plant 492.5 days 1/1/18 29/8/19
966 Site preparation 131 days 1/1/18 11/6/18
967 Site clearing & demolition works 25 days 1/1/18 31/1/18
968  Relocation of Utilities 118 days 17/1/18 11/6/18
969 Relocation of CELCOM utilities 81 days 6/3/18 11/6/18
970  Relocation of TNB cable 8 days 17/1/18 11/2/18
971  Relocation of TIME DOT COM cable 81 days 17/1/18 11/5/18
972  Sub‐Structure 189.5 days 6/3/18 24/10/18
973 Excavation & Platform preparation 6 days 6/3/18 12/3/18
974 Micropile for wall  & hacking (300mm) 150 days 21/3/18 8/10/18
975 Capping beam 35 days 12/9/18 24/10/18
976  Structure 174 days 24/10/18 25/5/19
977 Micropile for foundation (250mm) 118 days 24/10/18 19/3/19
978 RC foundation 35 days 2/3/19 12/4/19
979 Beam and Slab 35 days 27/3/19 8/5/19
980  Waterproofing to structure 7 days 8/5/19 16/5/19
981 Installation of biomedia 7 days 16/5/19 25/5/19
982  Architectural 25 days 25/5/19 26/6/19
983  Brickworks 14 days 25/5/19 13/6/19
984 Install overflow box and pipe to river 7 days 7/6/19 15/6/19
985 Door installation 2 days 15/6/19 18/6/19
986 Stairs installation 7 days 18/6/19 26/6/19
987 Installation of oil coeleascer media 7 days 15/6/19 24/6/19
988  Electrical 63 days 15/6/19 29/8/19
989  Cabling works 14 days 15/6/19 2/7/19
990  Installation of Distribution Board & Local  7 days 2/7/19 10/7/19
Control Panel
991  Motor Control Center @ Jalan Bunus 21 days 10/7/19 5/8/19
992  Cabling works & busbar installation 7 days 10/7/19 18/7/19
993  Installation of Motor Control Center 7 days 18/7/19 26/7/19
994  Installation TNB meter panel 7 days 26/7/19 5/8/19
995  Switchroom & Blower Room 21 days 5/8/19 29/8/19
996  Cabling works 7 days 5/8/19 13/8/19
997  Installation of light fittings 7 days 13/8/19 21/8/19
998  Earthing 7 days 21/8/19 29/8/19
999  Mechanical 50 days 15/6/19 14/8/19
1000 Grit & Grease Chamber 7 days 2/7/19 10/7/19
1001 Installation of float switch 7 days 2/7/19 10/7/19
Page 1
ROL 1C1D : Construction of Sullage Water Treatment Plant & Pump Sum
ID Task Name Duration Start Finish 2018 2019 2020
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
1002 Bioreactor 28 days 15/6/19 18/7/19
1003 UPVC diffuser Piping works 14 days 15/6/19 2/7/19
1004 Installation of diffuser c/w accessories 14 days 2/7/19 18/7/19
1005  Outlet facilities 14 days 10/7/19 26/7/19
1006  Installation of recycle pump (2 nos) 7 days 10/7/19 18/7/19
1007  Cabling works c/w accessories 7 days 18/7/19 26/7/19
1008 Blower room 14 days 18/7/19 5/8/19
1009 Installation of HDG steel pipe c/w accessor7 days 18/7/19 26/7/19
1010 Installation of blower 2 nos 7 days 26/7/19 5/8/19
1011  Fire protection equipment 1 day 26/7/19 29/7/19
1012  Supply 2 nos fire extinguishers 1 day 26/7/19 29/7/19
1013  Ventilation system 14 days 29/7/19 14/8/19
1014  Installation of ventilation fan c/w accesso 7 days 29/7/19 6/8/19
1015  Cabling works 7 days 6/8/19 14/8/19
1016  SCADA 28 days 19/7/19 22/8/19
1017  Cabling works 21 days 19/7/19 14/8/19
1018  Supply and install SCADA system to the site 7 days 14/8/19 22/8/19
1019 Pump Sum 194.99 days 27/3/18 22/11/18
1020 Testing and commisioning 7 days 13/11/18 22/11/18
1021 Lorong Bunus 85.99 days 27/3/18 10/7/18
1022 Structure 57.99 days 27/3/18 5/6/18
1023 Excavation 2 days 27/3/18 28/3/18
1024 Construction of bases and slab 7 days 29/3/18 5/4/18
1025 Construction of wall & top slab 7 days 6/4/18 20/4/18
1026 Installation of manhole & trash screen 1 day 20/4/18 21/4/18
1027 Micropile for river wall 21 days 21/4/18 17/5/18
1028 Skin wall 7 days 17/5/18 25/5/18
1029 Capping beam 7 days 25/5/18 5/6/18
1030 Force main works 49 days 21/4/18 23/6/18
1031  Excavation of trench 35 days 21/4/18 5/6/18
1032  Laying of HDPE pipe 21 days 17/5/18 13/6/18
1033  Road reinstatement works 7 days 13/6/18 23/6/18
1034  Submersible pump 14 days 23/6/18 10/7/18
1035  Installation of Submersible pump at small 7 days 23/6/18 2/7/18
pump station
1036  Cabling works 7 days 2/7/18 10/7/18
1037 Jalan Melayu 116 days 23/6/18 13/11/18
1038 Structure 67 days 23/6/18 14/9/18
1039 Excavation 3 days 23/6/18 27/6/18
1040 Construction of bases and slab 7 days 27/6/18 5/7/18
1041 Construction of wall & top slab 7 days 5/7/18 13/7/18
1042 Installation of manhole & trash screen 1 day 13/7/18 14/7/18
1043 Micropile for river wall 21 days 14/7/18 8/8/18
1044 Skin wall 14 days 8/8/18 25/8/18
1045 Capping beam 14 days 25/8/18 14/9/18
1046 Force main works 84 days 14/7/18 26/10/18
1047   Excavation of trench 35 days 14/7/18 25/8/18
1048   Laying of HDPE pipe 35 days 8/8/18 24/9/18
Page 2
ROL 1C1D : Construction of Sullage Water Treatment Plant & Pump Sum
ID Task Name Duration Start Finish 2018 2019 2020
1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1
1049   Road reinstatement works 28 days 24/9/18 26/10/18
1050  Submersible pump 14 days 26/10/18 13/11/18
1051  Installation of Submersible pump at small 7 days 26/10/18 3/11/18
pump station
1052  Cabling works 7 days 3/11/18 13/11/18
1053 Non‐Return Valve 7 days 24/9/18 2/10/18
1054 500 mm DN non‐return valve 7 days 24/9/18 2/10/18
1055 1500 mm DN non‐ return valve 7 days 24/9/18 2/10/18
1056 Motor control center @ Jalan Melayu (2 nos)35 days 14/9/18 26/10/18
1057 Cabling works 14 days 14/9/18 2/10/18
1058 Installation of MCC 14 days 2/10/18 18/10/18
1059 Installation of TNB meter 7 days 18/10/18 26/10/18
1060  External Works 63 days 2/7/19 17/9/19
1061  Laying Subbase 14 days 2/7/19 18/7/19
1062  Laying Roadbase 14 days 18/7/19 5/8/19
1063  Laying Asphaltic Concrete 14 days 5/8/19 21/8/19
1064 Tiling and turfing works 21 days 21/8/19 17/9/19
1065 Finalization works 21 days 7/9/19 3/10/19
1066 Testing and commisioning  14 days 17/9/19 3/10/19
1067 Design submission and shop drawing 21 days 7/9/19 3/10/19
1068 O&M manual 21 days 7/9/19 3/10/19