DAILY REPORT
SUKE/QC/WPC/F-7 Rev: 0 Page: 1/1

Date : 22/3/2019 Day : Friday


1 2 3 4 5 6 7 8 9 10 11 12 Working 1 2 3 4 5 6 7 8 9 10 11 12
Weather
13 14 15 16 17 18 19 20 21 22 23 24 Hours 13 14 15 16 17 18 19 20 21 22 23 24

Sunny Cloudy Drizzle Heavy Rain


Activities:
SECTION 2 : MB30/MC10/U1P39/MB10
1.Piling-(MB30-B3-P12-02-R)- done casting
2.Piling-MB30-B3-P11-03-R)- prebore
3.Pilecap-(MB30-B3-P16)-install mould type 7, install scaffold
4.Pilecap-MB30-B3-P17)-done clean leancon and continue install rebar
5.Piling-(MC10-U1-P36-10),hitrock at 8.1m continue rock socket (8.5m), current depth 13.1m
6.Rebar installation for pile cap U1/P39

-housekeeping at mb30
-Unloading silent piler( Taima)

Visitors :

Remarks/Instruction :

Manpower Qty Manpower Qty Machinery Qty Material Received Qty


Project Director Clerk Tower Crane
Project Manager Chainman Crawler Crane 2
Managers 1 Foreman Mobile Crane 1
Coordinator Carpenter Excavator 3
Engineers 2 Barbender Backhoe
Qty Surveyors Concretor Payloader
Land Surveyors Bricklayer Bulldozer
Officers Tiler Tractor
Supervisors 1 Steel workers Paver
Technician Plasterer Dump Truck
Assistant General workers 5 1 ton lorry
Sungeo 14 Generator Set 1
IZW 1 Bar cutting machine 2
Kalin 2 Bar bending machine 2
Waitat 10 Air compressor 1
Vibrators
BG 2

Note: Manpower and machinery listing can be tailored to contractor actual staff and machine

Prepared by: Checked by: Approved by:

________________________ ________________________ ____________________________


Name: Kumaresan/Kaavi Name: Name:
Date : 22/3/2019 Date : Date :