Current Date : 4th April 2019 Company: Macrospec Sdn Bhd Gantt CHART - 19_0138

Vendor RBR Valvole WEEK NO


Vendor PO 19_0138
Start Finish Duration 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31

Order Processing 1/3/2019 22/3/2019 21 days

Engineering Drawing & Specs 8/3/2019 12/4/2019 42 days

GA Drawing 8/3/2019 12/4/2019 42 days


Inspection Test Plan 8/3/2019 12/4/2019 42 days

Raw Materials Quotation/Order/Receiving 22/3/2019 24/5/2019 53 days

Ball & Seat 22/3/2019 24/5/2019 53 days


Ball
Request For Quoatation
Ordering
Raw Material & Machining
Shipment

Seat 22/3/2019 24/5/2019 53 days


Request For Quoatation
Ordering
Raw Material & Machining
Shipment

Body & Closure


Closure 22/3/2019 24/5/2019 53 days
Request For Quoatation
Ordering
Raw Material & Machining
Shipment

Body 22/3/2019 24/5/2019 53 days


Request For Quoatation
Ordering
Raw Material & Machining
Shipment
Machining 3/5/2019 28/6/2019 63 days

Machining Component
Request For Quoatation
Ordering
Raw Material
Shipment
Machining

Production & Testing 1/7/2019 12/7/2019 12 days


Valve Component assembly
Assembly & Testing

Factory Acceptance Test


FAT

Finishing & Delivery 12/7/2019 26/7/2019 14 days

Blasting & Painting


Final Inspection
Packing/Ex-work

DDP ELCC Bintulu 26/7/2019 9/8/2019 14 days

Planned
Actual
Current Week
Itemized Progress