Structural repairs & Up-gradation of Sagbaug municipal school at Sakinaka andheri (e) in K/E ward

Daily Progress Report (DPR)


Sr.no Date Discription Remark
JANUARY
3/1/2017 NO WORK
4/1/2017 NO WORK
5/1/2017 NO WORK
6/1/2017 NO WORK
7/1/2017 NO WORK
8/1/2017 SUNDAY
9/1/2017 NO WORK
10/1/2017 NO WORK
11/1/2017 NO WORK
12/1/2017 NO WORK
13/1/2017 NO WORK
14/1/2017 NO WORK
15/1/2017 SUNDAY
16/1/2017 NO WORK
17/1/2017 NO WORK
18/1/2017 NO WORK
19/1/2017 NO WORK
20/1/2017 NO WORK
21/1/2017 Inventory of classRooms.
2 22/1/2017 SUNDAY
3 23/1/2017 Inventory of classRooms.
4 24/1/2017 Shifting of materials.
5 25/1/2017 Shifting of materials.
6 26/1/2017 Republic day (holiday)
7 27/1/2017 Removing of internal side plaster of compound wall SRA building side.
8 28/1/2017 Removing of internal side plaster of compound wall SRA building side.
9 29/1/2017 SUNDAY
10 30/1/2017 Removing of internal side plaster of compound wall rear side of small building.
11 31/01/2017 Removing of internal side plaster of compound wall entrance gate side.
FEBURARY
12 1/2/2017 Removing of internal side plaster of compound wall SRA building side.
13 2/2/2017 Removing of internal side plaster of compound wall entrance gate.
14 3/2/2017 Removing of internal side plaster of compound wall left side of long building.
15 4/2/2017 Removing of internal plaster of Room no 9,Room no 10
16 5/2/2017 SUNDAY
17 6/2/2017 Removing of external plaster of short wing P4
Removing flooring of Room no 9 & 10
Removing existing weather shade of short wing rear side
Removing internal plaster in care taker room
18 7/2/2017 Demolishion / removing plaster of caretakers Room.
19 7/2/2017 Removing of external plaster of short wing P1
20 8/2/2017 Removing external plaster near entrance 1 of compound wall
21 9/2/2017 Excavation for septic tank.
Removing external plaster near entrance 1,2 of compound wall
Removing fencing from compound wall
22 10/2/2017 Cleaning of chamber and site.
23 11/2/2017 Cleaning of septic tank.
24 12/2/2017 SUNDAY
25 13/2/2017 Demolishion of brick masonary at entrance side 1 & 2.& Cmpound wall South
1st coat internal Plaster at south compound wall entrance 1 side.
Brick masonary for filling the gaps in compound wall.
26 14/02/2017 1st coat internal plastering at south/W side of long building.
1st coat internal Plaster at south/w compound wall entrance 2 side.
27 15/2/2017 1st coat External plaster of south/W compound wall near entrance 2
28 16/02/2017 1st coat External plaster of south/W compound wall near entrance 2
29 17/02/2017 Brick masonary of demolished compound wall south entrance 2 side.
30 18/02/2017 1st coat External plaster of new compound wall south/E entrance 2
19/02/2017 No work CORPORATION ELECTION
20/02/2017 No work
21/2/2017 No work
22/2/2017 No work
31 23/02/2017 1st coat Internal side Plastering of new and existing compound wall South/E entrance 2
32 24/02/2017 HOLIDAY
33 25/02/2017 1st coat Inside plastering of East compound wall rear side of small building
1st coat external plaster of rear side short wing P1.
34 26/02/2017 SUNDAY
35 28/02/2017 Brick masonary for raising compound wall near SRA side building
MARCH
36 1/3/2017 Brick masonary for raising compound wall near SRA side building,
Demolishion of existing wall at caretakers Room for passage and door.

37 2/3/2017 1st coat Internal side Plastering of raise d compound wall and existing compound wall on North
SRA side.
38 3/3/2017 1st coat Internal side Plastering of existing compound wall on North SRA side.
Excavation for drainage line for Proposed toilet near short wing and removing flooring.
39 4/3/2017 2nd coat Inside plastering of East compound wall rear side of small building
Brick masonary for foundation and super structure of caretakers Room outer wall.
Excavation for proposed watchmans cabin.
P.C.C for watchmans cabin
Demolishion and excavation of existing Electric meter Room.
Excavation for drainage line for Proposed toilet.
40 2nd coat internal plastering of compound wall south entrance 1.
2nd coat I nternal side Plastering of raised compound wall and existing compound wall on
North SRA side.
2nd coat Internal side Plastering of existing compound wall on North SRA side.
Brick masonary for foundation and super structure of proposed watchmans cabin.
P.C.C for electric meter Room.
Excavation for drainage line for Proposed toilet.
5/3/2017 SUNDAY
41 6/3/2017 Brick masonary for foundation and super structure of Electric meter Room.
2nd coat plastering at south/W side of long building.
Excavation for drainage line for Proposed toilet.
Removing of flooring at open gr level near small building.
42 7/3/2017 2nd coat internal plastering of compound wall south entrance 1.
Brick masonary for Electric meter Room.
P.C.C for Draine line chambers.
Removing external plaster of small building P1 9.
43 8/3/2017 2nd coat External plaster of south/W compound wall near entrance 2
Brick masonary for inspection chamber.
44 9/3/2017 2nd coat External plaster of new and existing compound wall south/E entrance 2
Brick masonary for inspection chamber.
proposed toilet drainage line. P.C.C bedding.
2nd coat Internal side Plastering of new and existing compound wall South/E entrance 2
2nd coat Internal side Plastering of new and existing compound wall South/W entrance 2
45 10/3/2017 Brick masonary for inspection chamber.
P.C.C for Draine line chambers.
46 11/3/2017 Plastering of internal chamber.
Brick masonary for inspection chamber.
Fillings the joints of sewer line.
1st coat Internal plaster Room no 9 Science lab
Removing of flooring near compound pavement at SRA side. (paver)
47 P.C.C OF DRAINAGE LINE.
2nd coat Plastering of Raised and existing compund wall at north SRA side.
Plastering internal side of chember
Fillings the joints of sewer line.
P.C.C of compound pavement at SRA side. (paver)
1st coat Internal plaster Room no 10 Computer room
Filling of soil at drainage line.
12/3/2017 SUNDAY
48 13/3/2017 HOLIDAY
49 14/3/2017 2nd coat Internal side plastering of compound wall South/W entrance 2
Excavation for paver front side of short wing.
1st coat external plaster of corridor P4
50 15/03/2017 P.C.C of compound pavement front of short wing. (paver)
2nd coat Internal plaster Room no 9 Science lab
2nd coat Internal plaster Room no 10 Computer room
51 16/03/2017 P.C.C of compound pavement front of short wing. (paver)
brick masonry for garden boundary. Tree guard
Rubbel Soling in front of small building.
2nd coat e xternal plaster of corridor P4
52 17/03/2017 Removing of wheather shade of long building
Removing flooring near compound pavement front of long building.
Rubble Soling near smal building.
1st coat internal plaster of N/W compound wall
53 18/03/2017 P.C.C of compound pavement near small building SRA side.
54 P.C.C of compound pavement left of long building.
P.C.C of compound pavement front of long building. Entrance 1 (right)
2nd coat internal plaster of N/W compound wall
Removing of wheather shade of small building
19/03/2017 SUNDAY
55 20/03/2017 P.C.C of compound pavement front of long building.Entrance 1 (left)
2nd coat external plaster of rear side short wing P1.
Removing of wheather shade of short building
56 21/03/2017 1st coat external plaster of caretakers outerwall
57 22/03/2017 Laying paver at small building SRA side.
1st coat internal plaster of caretakers wall.
58 23/3/2018 Laying paver at small wing SRA side.
1st coat external side plaster of raised compound wall SRA side.
2nd coat internal plaster of caretakers wall.
59 24/03/2017 Laying paver at small wing SRA side.
60 2nd coat external plaster of caretakers outerwall
Removing syntax tank from uthala 01
14/3/2017 Excavation of compound pavement near small building
61 Laying paver at small wing SRA side.
Rubble soling near small building
2nd coat external side plaster of raised compound wall SRA side.
26/3/2016 7
62 27/03/2017 Rubble soling near small building
63 29/03/2017 P.C.C for Compound Pavement Part 6
Rubble soling near small building
64 31/03/2017 P.C.C for Compound Pavement Part 6
Rubble soling near small building
APRIL
1/4/2017 No work
2/4/2017 No work
3/4/2017 No work
4/4/2017 No work
5/4/2017 No work
6/4/2017 No work
7/4/2017 No work
8/4/2017 No work
9/4/2017 SUNDAY
65 10/4/2017 P.C.C for Compound Pavement Part 6
Fixing of compound wall fencing
66 P.C.C for Compound Pavement Part 6
Fixing of compound wall fencing
67 11/4/2017 Fixing of compound wall fencing
Removing window of room no 09&10 in short building
68 12/4/2017 Fixing of compound wall fencing
13/4/2017 NO work
14/4/2017 NO work
4/15/2017 NO work
68 4/16/2017 SUNDAY
69 17/4/2017 Removing external plaster of small building P1 9.
Removing door from electric room
70 20/4/2017 Laying of paver block front of long building
71 21/4/2017 Laying of paver block front of long building
72 22/4/2017 Laying of paver block front of long building
23/4/2017 SUNDAY
73 24/4/2017 Laying of paver block front of long building
74 25/4/2017 1st coat external and internal plaster of electric meter Room
Laying of paver block south west side of long building
75 26/4/2017 Removing doors and windows of small building
Removing External plaster of small building P2 0
75 27/4/2017 Removing internal plaster of small building Room no 4
77 28/4/2017 Removing doors and windows of small building
Removing internal plaster of small building Room no 4
78 29/4/2017 Removing internal plaster of small building Room no 5
Laying of paver bolck at shotwing passage
Removing internal plaster of small building Room no 6
79 Removing internal plaster of small building Room no 6
Removing coalibal door from small building
Laying of paver block near Entrance 2 South side.
30/4/2017 SUNDAY
MAY
80 1/5/2017 HOLIDAY
80 2/5/2017 Removing internal plaster of small building Room no3
1st coat external plaster of small buildng P1 9
Laying of paver block near Entrance 2 South side.
81 3/5/2017 Removing internal plaster of small building Room no3
Fixing of indian W/C at caretakers toilet.
1st coat external plaster of small buildng P2 0
Removing door from care takers room
82 4/5/2017 1st coat internal plaster of small building Room no 4
Laying paver front of small building part 6
83 5/5/2017 1st coat internal plaster of small building Room no 5
Laying paver front of small building part 6
84 6/5/2017 1st coat internal plaster of small building Room no 6
2nd coat e xternal plaster of small building P2 0
Removing external plaster of small building P1 4,P15
removing door from room no 09&10
5/7/2017 SUNDAY
85 8/5/2017 1st coat internal plaster of small building Room no 6
86 9/5/2017 1st coat internal plaster of small building Room no 3
87 10/5/2017 1st coat internal plaster of small building Room no 3
88 11/5/2017 2nd coat internal plaster of small building Room no 4
89 12/5/2017 2nd coat internal plaster of small building Room no 4
Removing external plaster of Long building P4 corridor side
13/5/2017 SUNDAY
90 14/5/2017 2nd coat internal plaster of small building Room no 5
Removing external plaster of Long building building P1 , P5
91 15/5/2017 2nd coat internal plaster of small building Room no 6
Removing external plaster of small building P2 1
92 16/5/2017 2nd coat e xternal plaster of small buildng P1 9
93 17/5/2017 2nd coat internal plaster of small building Room no 3
94 18/5/2017 1st coat external plaster of small building P1 4, P1 5
2nd coat e xternal plaster of small buildng P1 9
1st coat external plaster of small building P1
Removing the celing plaster.
95 19/5/2017 2nd coat e xternal plaster of small building P1 4, P1 5.
Brick masonary of caretakers toilet.
1st coat external plaster of small building P5
96 20/5/2017 2nd coat e xternal plaster of Long building P1,P5
Demolishion of existing Sintex uthala
1st coat external and internal plaster of Watchmans cabin
1st coat external plaster of small building P2 1
21/5/2017 SUNDAY
97 22/5/2017 Brick masonary for foundation and super structure of sintex uthala
Brick masonary for proposed girls toilet
1st coat internal plaster of caretakers toilet
1st coat internal plaster of caretakers toilet outer wall
98 23/5/2017 Brick masonary for super structure of sintex uthala
Cleaning of small building ceiling and ponding for seepage.
Brick masonary for proposed girls toilet window
99 24/5/2017 1st coat external plaster of sintex uthala
Brick masonary of proposed girls toilet.
2nd coat external and internal plaster of electric meter room.
Preparing window frame for small building.
100 25/5/2017 1st coat external plaster of Long building P4 corridor side
2nd coat e xternal plaster of small building P2 1
101 26/5/2017 Removing existing roofing of small building and short wing
2nd coat external plaster of sintex uthala
102 27/5/2017 Removing existing roof of small building
Grouting of paver
28/5/2017 SUNDAY
29/5/2017 Removing existing roof of short wing
Grouting of paver
30/5/2017 Roofing of small building.
Grouting of paver
2nd coat e xternal plaster of Long building P4 corridor side
Removing internal plaster of small building room no 1
31/5/2017 Removing internal plaster of small building room no 1
Roofing of small building.
JUNE
1/6/2017 Removing internal ceiling plaster of small building corridor for structural repair.
Roofing of small building.
2/6/2017 Applying rusticide to the exposed steel in ceiling slab.
Roofing of Short wing.
Fixing door frames In small building.
3/6/2017 Roofing of Short wing.
Fixing door frames In small building.
6/4/2017 SUNDAY
5/6/2017 No work
6/6/2017 No work
7/6/2017 Applying rusticide to the exposed steel in ceiling slab.
Polymer on the ceiling slab.
1st coat internal plas ter of s mall building Room no 1
Rectification of chamber and drainage line
8/6/2017 Fixing small building window frame.
Polymer on the ceiling slab.
9/6/2017 Polymer on the ceiling slab.
Fixing of small building Window frames.
Rectification of chamber and drainage line
10/6/2017 Plaster of small building ceiling slab.
Fixing of small building doors frames and doors
1st coat internal plas ter of s mall building Room no 1
Fillng gaps of roofing in small building
Plaster of small building ceiling slab.
Fixing of small building doors frames and doors
Structural repairs & Up-gradation of Sagbaug municipal school at Sakinaka andheri (e) in K/E ward
Daily Progress Report (DPR)
Sr.no Date Discription Remark
Fillng gaps of roofing in small building
Painting in small building room no 4,5
11/6/2017 SUNDAY
12/6/2017 Fixing of small building doors frames and doors
Plaster of small building ceiling slab.
Painting in small building room no 4,5
13/6/2017 Painting in small building room no 3,6
Plaster of small building ceiling slab.
1st coat internal plas ter of s mall building Room no 1
14/6/2017 1st coat internal plas ter of s mall building Room no 1
15/6/2017 2nd coat inte rnal plaster of small building Room no 1
16/6/2017 1st coat internal plaster of proposed girls toilet
Grouting and rendering of small building slab for waterproofing
17/6/2017 2nd coat inte rnal plaster of small building Room no 1
Fixing window frames in small buildinging
Rectification of chamber and drainage line
18/6/2017 SUNDAY
19/6/2017 No work
20/6/2017 Lintel of door and window of small building room no 1
Paver block part 7 front of short wing
Rectification of chamber and drainage line
21/6/2017 Rectification of chamber and drainage line
Paver block part 7 front of short wing
22/6/2017 Fixing window frames in small building room no 1
Filling gaps under Roofing
23/6/2017 Filling gaps under Roofing
lintel of electric meter room and roofing
24/6/2017 Grouting of paver
Paver block part 7 front of short wing
25/6/2017 SUNDAY
26/6/2017 HOLIDAY
27/6/2017 No work
28/6/2017 Lintel for girls toilet ventilation
1st coat external plaster of girl toilet window
29/6/2017 Caretaker room lintel of door anf fixing door frame
fixing collapsable gate at small building entrance.
30/6/2017 2nd coat external plaster of girl toilet window
Filling gaps under Roofing
JULY
1/7/2017 Windows shutter fixing on small building
windows frame fixing on Short wing.
shuttering for watchmans cabin slab
windows shutter fixing on short wing
7/2/2017 SUNDAY
3/7/2017 shuttering for watchmans cabin slab
Kota in short wing corridor
4/7/2017 shuttering for watchmans cabin slab
windows shutter fixing on short wing
5/7/2017 Kota in short wing corridor
6/7/2017 Kota in short wing corridor
Reinforcement for watchmans cabin slab
7/7/2017 Kota in short wing corridor
Reinforcement for watchmans cabin slab
8/7/2017 Removing existing kota of long building corridor
Kota skirting in short wing corridor
7/9/2017 SUNDAY
10/7/2017 Kota in Small corridor
Kota skirting in short wing corridor
11/7/2017 Kota in long building Small corridor
windows shutter fixing on short wing
12/7/2017 Brick batt waterproofing on small building slab
Kota in long building corridor
13/7/2017 Brick batt waterproofing on small building slab
Kota in long building corridor
14/7/2017 Kota in long building corridor
15/7/2017 Kota in long building corridor
girls toilet drainage line
7/16/2017 SUNDAY
17/7/2017 Painting work (Putty) in small building room no 4
18/7/2017 Kota in long building corridor
Brick batt waterproofing on small building slab
Painting work (Putty) in small building room no 5
19/7/2017 Painting work (Putty) in small building corridor
20/7/2017 Painting work (Putty) in small building corridor
Kota in long building corridor
21/7/2017 Painting work (Putty) in small building room no 1
Kota in long building corridor
22/7/2017 Fixing Window shutter on short building.
Painting work on compound wall
Kota in long building corridor.
Fixing Window shutter on short building
Painting work in small building corridor
Painting work on compound wall
23/7/2017 SUNDAY
24/7/2017 Kota in long building corridor.
Painting work on windows small building.
Painting work of small building purlins.
25/7/2017 MS grill fixing in Small building.
Kota skirting in long building corridor.
Painting work of small building purlins.
Painting work on compound wall.
Laying nahani Trap in girls toilet.
26/7/2017 Painting work (Putty) in Science lab
Laying Nahani Trap in Science lab.
Laying Nahani Trap in caretakers room.
Painting work on compound wall.
27/7/2017 Painting work on compound wall fencing.
MS grill fixing in short wing.
Painting work on compound wall.
28/7/2017 Painting work on compound wall fencing.
Cleaning of rear side of small building for paver.
29/7/2017 Cleaning of rear side of small building for paver.
Kota Sill for small building corridor windows.
PCC for paver rear side of small building
7/30/2017 SUNDAY
31/7/2017 Kota Sill for small building corridor windows.
AUGUST
1/8/2017 Painting work on compound wall fencing.
Providing vetrified tiles for Flooring in science lab.

2/8/2017 Providing tiles at Dado portion in science lab


Painting work on compound wall fencing.

3/8/2017 Providing Rubbber Soiling in laberary

4/8/2017 Providing Pcc in Laberery

5/8/2017 Providing vetrified tiles for Flooring in Laberery


Providing tiles at Dado portion in laberery

6/8/2017 Sunday

7/8/2017 Holiday

8/8/2017 Providing tiles at Dado portion in laberery


Painting work on collapsible gate at small building

9/8/2017 Providing Paver block on long wings

10/8/2017 Providing Pcc at SRA side building


Providing tiles at Dado portion in laberery
Grauting of paver block

11/8/2017 Providing Paver block on SRA side Building.


FixingPlumbing work in girls toilet
Rectification of chamber

12/8/2017 Providing Pcc in caretaker room


Providing vetrified tiles for flooring in caretaker room
Providing rubber soiling in girls toilet
Providing internal Plaster in girls toilet
Door fixing in scince lab

13/8/2017 Sunday

14/08/2017 Grauting of paver block in electric room


Door fixing in Laberery
Providing tiles for flooring in caretaker room
Providing Pcc in girl toilet

15/08/2017 HOLI DAY

16/08/2017 Providing Paver block on back side of small building


Providing granite for toilet door frame in girls toilet
Grauting paver block
Door fixing in girls toilet
Paver block on electric room

17/08/2017 Providing tiles for flooring in girls toilet


Providing granite for toilet door frame in girls toilet

18/08/2017 Providing tiles for flooring in caretaker room

Providing Weather shed in short building


Providing tiles for flooring in girls toilet
19/08/2017 NO WORK (DUE TO RAIN)
20/08/2017 Sunday heavy rain

21/08/2017 Providing Weather shed in short building

22/08/2017 Providing Brick work at tree gard side


Pcc work on caretaker entrence side
Providing Weather shed in small building

23/08/2017 Providing Weather shed in small building


Providing Pcc and plaster of electric room
Providing Paver block at caretaker entrence side

24/08/2017 Providing Pcc at paasage of short cariddor


Providing Paver block at caretaker entrence side
Providing Weather shed in small building

25/08/2017 Removing & providing internal Plaster in staff toilets


Providing Weather shed in small building

26/08/2017 Removing of windows in staff toilets


Providing Brick work in staff toilets
Fixing main gate no 1
Removing Main Gate no 1

27/08/2017 Sunday

28/08/2017 Removing Main Gate no 2


Providing Pcc In staff Toilets
Providing Brick work in staff toilets for wc Partion
Providing tiles for flooring in girls toilet

Fixing Main Gate no 2


Providing Internal Plaster In staff toilets
29/8/2017 no work (due to rain)
30/8/2017 no work (due to rain)
31/08/2017 Providing granite for toilet door frame in staff toilet
Providing External Plaster & Ventilator fixing in Staff Toilets
SEPTEMBER AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
1/9/2017 providing gally traps outer side of Caretaker room
2/9/2017 Holiday
3/9/2017 SUNDAY
4/9/2017 providing plaster on main gate column
Decentering of watchmen cabin
Providing brick work at uthala at SRA side building
5/9/2017 providing Paver Block at main gate side
Providing brick work at uthala at SRA side building
6/9/2017 providing Pcc work in Watchman Cabin
providing Paver Block at main gate side
7/9/2017 No Work
8/9/2017 No Work
9/9/2017 providing Kitchan Platform in caretaker room
providing kotah floorin in watchmen cabin
providing platform in science lab
9/10/2017 SUNDAY
11/9/2017 providing platform in science lab
12/9/2017 providing platform in science lab
13/9/2017 providing internal plaster in watchman cabin
providing platform in science lab
14/9/2017 providing platform in science lab
providing internal plaster in watchman cabin
15/09/2017 providing Urinal platform work in staff toilet
providing Kota patti remp & step on enterance small building
16/09/2017 providing tiles for Flooring in staff toilets
17/09/2017 SUNDAY
18/09/2017 providing Kota patti remp & step on enterance small building
providing tiles for dado portion in girls toilets
providing Putty work in class room & passage at short building
19/09/2017 No Work (due to rain)
20/09/2017 No Work (due to rain)
21/09/2017 providing tiles for dado portion in staff toilets
providing Putty work in class room & passage at short building
22/09/2017 providing tiles for dado portion in girls toilets
providing oil paint on trusS & purlins Long carridore
23/9/2017 providing tiles for dado portion in girls toilets
Fixing sliding windows in small building
24/09/2017 SUNDAY
25/09/2017 Fixing sliding windows in small building
26/09/2017 providing tiles in bath room in care taker room
Shifting of material from room at small building
27/09/2017 providing tiles for dado portion in girls toilets
Removing internal plaster in class room no 02 in small building
28/09/2017 providing tiles for dado portion in girls toilets
Removing internal plaster in class room no 02 in small building
29/09/2017 Fixing of wooden window frame in class room no 02 at small building
providing kotah patti at sill level of window.
providing tiles for flooring in girls toilets
30/09/2017 HOLIDAY
OCTOBER
1/10/2017 SUNDAY
2/10/2017 Moalding of kotah steps
Providing tiles for dado portion in staff toilets
Removing internal plaster in room no 05 in big building
3/10/2017 Providing 1 st coate internal plaster in room no 02 small building
4/10/2017 providing 2nd coate internal plaster in class room no 02 in small building
5/10/2017 providing internal plaster in class room no 02 in small building
Removing internal plaster in room no 08 in big building
providing 1st coate internal plaster in room no 05 in big building
6/10/2017 providing1 coate internal plaster in room no 08 in Long building
Removing internal plaster in room no 04
fixing of wooden window sutter in class room no 02 at small building
7/10/2017 providing FRB door in staff toilet & Girls Toilet & Watch man cabin
Fixing of syntax water tank& Related Pulming work
8/10/2017 SUNDAY
9/10/2017 Providing internal plaster in room no 08
providing 2nd coate internal plaster in room no 05 in big building
providing 2nd coate internal plaster in room no 08 in Long building
10/10/2017 Fixing sliding windows in room No 02 small building
providing kotah patti at sill level of window in Watchman cabin
11/10/2017 Removing exetarnal plaster West side of long building
12/10/2017 Providing 1st coate exetarnal plaster West side of long building
13/10/2017 Cleaning work
providing Putty work in class room 08 of Long building
14/10/2017 Gully trap iron cover work for girls toilet & Staff Toilet
Rectification of kotah in Science lab
Polymer work outside of Room No 08 of Long building
15/10/2017 SUNDAY
16/10/2017 Providing 2nd coate exetarnal plaster West side of long building
Removing door and window from room no08
17/10/2017 fixing of wooden window &Door frame in class room no 08 at long building
18/10/2017 fixing of wooden window &Door frame in class room no 05at long building
19/10/2017 DIWALI
20/10/2017 DIWALI
21/10/2017 removing wooden window &Door frame in class room no 04at long building
removing external plaster of long Paasage At room 2&5
22/10/2017 SUNDAY
23/10/2017 fixing wooden window &Door frame in class room no 04at long building
24/10/2017 Providing cupbord of brickwork room no 02&03 small building
25/10/2017 Providing cupbord of brick work room no 04 small building
Providing cupbord of brick work room no 08 long building
Remvoing Roof of long building
26/10/2017 Providing cupbord of brick work room no 06&05small building
Fixing of Roof of Long Building
Removing external plaster form front of room no06& 07 long building
Structural repairs & Up-gradation of Sagbaug municipal school at Sakinaka andheri (e) in K/E ward
Daily Progress Report (DPR)
Sr.no Date Discription Remark
Providing plaster on cupboard in room no 02,03&04 in small building
27/10/2017 Provinding putty in room no 03 small building
Providing cupbord of brick work roon 04 of long builing
providing exeternal plaster in front of room no 08 in long building
28/10/2017 Provinding putty in room no 02 long building
Providing cupbord of brick work science lab & computer room
Providing 1st coat external plaster form front of room no06& 07
Providing 1st coat of external plaster in fornt room no 02& 05,long wing
Providing plaster on cupboard in room no 06&05 in small building
29/10/2017 SUNDAY
30/10/2017 Excess brickwork & coaping in Compound wall on left side of gate no 02
Poviding wooden door in room no 04 in long building
31/10/2017 Excess brickwork & coaping in Compound wall in front of long building
Putty work in room no 08 in long building
Providing plaster on cupboard in science lab & computer room
providing 2nd coat of external plaster in fornt room no 02& 05 long building
NOVEMBER
1/11/2017 providing plaster on Excess Brick work on Compound wall on left side of gate no 02
Providing wooden door in girls toilet
providing 2nd coat of external plaster in fornt room no 02& 05 long building
2/11/2017 Applying kota in Electric room small building
Providind plaster on cupboard in room no 08 long building
3/11/2017 Providing wooden door in Electric room
Removing internal plaster in room no 07 in long building
fixing of wooden window &Door frame in class room no 07 at long building
Providing plaster on Excess Brick work & coaping in boundry wall in front of long building
4/11/2017 Providing plaster on Excess Brick work & coaping in boundry wall form outside
Providing back coat in room no07 in long building
Putty work in scince lab and computer room
Providing internal paint in room no 02 ,04 ,in small building
5/11/2017 SUNDAY
6/11/2017 Providing internal paint in scince lab & computer room
Floor tile work in room no 07 in long building
7/11/2017 Floor tile work in room no 07 in long building
Providing window suttering in long building
8/11/2017 Providing dado tiles in office room(room 7) in long building
Providing water closet in handicap & staff toilet
Providing window suttering in long building
9/11/2017 Providing dado tiles in office room(room 7) in long building
Providing window suttering in long building
10/11/2017 Providing dado tiles in office room(room 7) in long building
11/11/2017 Removing interenal plaster in marathi room
Providing exeternal plaster on compound wall
Providing internal paint in room no 07 in long building
Water proofing work on terrace of small building
12/11/2017 SUNDAY
13/11/2017 Providing china cheaping on terrace of small building
Removing plaster in marathi office
Providing window suttering in long building
Painting in passage of small building
14/11/2017 Providing china cheaping on terrace of small building
Providing paint on wooden door in long building
Removing door and window from room no04 in long building
15/11/2017 Providing 1st coate internal plaster in marathi office
Providing 1st coate of paint on wooden door in long building
16/11/2017 Fixing door and window in room no 04 in long building
Painting on purlins of room no 07 oof long building
17/11/2017 Providing 2nd coate internal plaster in marathi office
Providing rain water pipe on terrace of small building
18/11/2017 painting on purlins of room no 02 of small building
19/11/2017 SUNDAY
20/11/2017 Providing internal paint in roon n 04,05 in long building
Providing primer on window suttering in long building
Fixing window suttering in long building
21/11/2017 Providing primer on window suttering in long building
providing plaster on brickwork uthala
Providing internal paint in passage of small building
22/11/2017 Providing primer on window suttering in long building
Providing internal paint in passage of small building
23/11/2017 Providing black paint on m.s grill in small building
Providing primer on window suttering in long building
Fixing safty grill in room no 4 in long building
Providing 1st coat of internal plaster at room no. 1 long building.
24/11/2017 Fabrication work for passage
Putty work above weather shed
Providing 2nd coat of internal plaster at room no. 1 long building.
25/11/2017 Fabrication work for passage
Fixing door and window in room no 01 in long building

Providing plaster on excess of brickwork in compound wall from outside in front of long building
Providing 1st coat of plaster in room no 06 in long building
26/11/2017 SUNDAY
27/11/2017 Removing interenal plaster in room 01 of long building
Providing primer on external surface of small building
Providing 1st coate of internal paint in room no 01 in small building
28/11/2017 Providing 2nd coate of internal paint in room no 01 in small building
Providing primer on external surface of small building
29/11/2017 Providing primer on external surface of small building
Providing 2nd coat of plaster in room no 06 in long building
30/11/2017 Providing primer on internal surface of compound wall
DECEMBER
1/12/2017 Providing primer on internal surface of compound wall on sra side
2/12/2017 Providing primer on internal surface of compound wall in front of long building
3/12/2017 SUNDAY
4/12/2017 Providing primer on external surface of long building behind staff toilet
5/12/2017 No Work (due to cycolone)
6/12/2017 Providing red oxide on purlin & bracat of weather shed
7/12/2017 Providing red oxide on fabrication between passage of small and short building
Providing primer in long building in front of girls toilet
8/12/2017 Providing primer in long building in front face
9/12/2017 Providing black paint on fabrication of passage
10/12/2017 SUNDAY
11/12/2017 Providing black paint on fabrication of passage
providing primer on outer side of compound wall
12/12/2017 Providing first coat of external paint on small building
13/12/2017 Providing first coat of external paint on small building
14/12/2017 PCC work behind proposed girls toilet
Providing first coat of external paint on compound wall
15/12/2017 Providing first coat of external paint on front face of long building
16/12/2017 Providing first coat of external paint on compound wall sra side
Table work of computer room
17/12/2017 SUNDAY
18/12/2017 Carpentry work for Table of computer room
19/12/2017 kota polishing in passage of small building
20/12/2017 Table work of computer room
kota polishing in passage of small building
21/12/2017 Carpentry work for Table of computer room
Providing second coat of exteranl paint in small build
22/12/2017 Providing second coat of exteranl paint in small build
Carpentry work for Table of computer room
23/12/2017 kota polishing in room no 01 in small building
Carpentry work for Table of computer room
24/12/2017 SUNDAY
25/12/2017 HOLIDAY
26/12/2017 Providing roofing long building (remaing part)
Providing roofing in passage betwwen small builing and short building
27/12/2017 Carpentry work for Table of computer room
Debris removal from site
28/12/2017 kota polishing in passage of Long building
29/12/2017 Providing weather shed behind the long building
kota polishing in passage of small building room no 03
30/12/2017 Providing paint on wooden door in small building
kota polishing in passage of long building
31/12/2017 SUNDAY
JANUARY
1/1/2018 Debris removal from site
Cleaning work
Providing 1st coat of external paint on short building
providing plaster on watchmen cabin slab
2/1/2018 Providing 2nd coat of paint on window suttering in small building
3/1/2018 No Work (due to maharastra band)
4/1/2017 kota polishing in front of water fountain
Providing 1st coat of external paint on short building
5/1/2018 Providing 1st coat of external paint on long building
Providing 2nd coat of paint on window suttering in short building
6/1/2018 kota polishing in front of water fountain
Carpentry work for Table of computer room
7/1/2018 SUNDAY
8/1/2018 Carpentry work for Table of computer room
9/1/2018 2nd coat of external paint in short building
10/1/2018 Carpentry work for Table of computer room
kota polishing in front of water fountain
11/1/2018 Carpentry work for door of cupboard
12/1/2018 Carpentry work for door of cupboard
13/1/2017 Garden work in progress.
14.01.1018 Sunday
15.01.2018 Garden work in progress.
Kota polish in front of scince lab
Painting work is in progress.
16/01/2018 Garden work in progress.
Kota polish in front of liberary
Providing door to cupboard
17/01/2018 Providing 2nd coat of paint on back side of long building
brick work for tree gard
18/01/2017 material sifting from passage
Providing putty in room no 01 in long building
19/01/2018 brick work in passage of small building
1st caot of exteranl paint in short building
providing internal paint in room no 01 in long buildng
20/01/2018 watch man cabin painting
21/01/2018 Sunday
22/01/2018 Providing 1st coat of external paint in long building
Demolisiton of wall at short building entrance
23/01/2018 Brickwork for wall at short building entrance
24/01/2018 Rcc jali repair in front of main gate
Providing plaster on brickwork short building entrance
25/01/2018 Garden work in progress.
26/01/2018 REPULIC DAY (HOLIDAY)
27/01/2018 computer chair inventry
Providing 1st coat of external paint in long building
Providing paint on cupbord door
28/01/2018 Sunday
29/01/2018 Providing paint on cupbord door
30/01/2018 providing mirror polish on kota skirting
31/01/2018 providing mirror polish on kota skirting
eletrical work inventry
Providing 1st coat of external paint in long building
FEBURARY
1/2/2018 Providing 1st coat of plaster on brickwork at short building entrance
2/2/2018 Debris removal from site
3/2/2018 no work
4/2/2018 Sunday
5/2/2018 internal wiring in principal office
6/2/2018 internal wiring in roomno 06 in long building
7/2/2018 Providing weather shed behind the long building
internal wiring in roomno 07 in long building
8/2/2018 internal wiring in computer room (room no 09)
9/2/2018 internal wiring in scince lab (room no 10)
10/2/2018 internal wiring in room no04 small building
Providing overflow to exiting septic tank
11/2/2018 Sunday
12/2/2018 internal wiring in room no05 small building
13/02/2018 HOLIDAY mahashivratri
14/02/2018 providing overflow to exiting septic tank
internal wiring in balwadi
15/02/2017 providing overflow to exiting septic tank
internal wiring in long building romm no 04
Providing soft board in small building in room no 2-6
16/02/2018 providing overflow to exiting septic tank
internal wiring in long building romm no 05
17/02/2018 internal wiring in long building romm no 03
providing vent pipe to exiting septic tank
18/02/2018 Sunday
19/02/2018 HOLIDAY shivaji jayanti
20/02/017 providing vent pipe to exiting septic tank
internal wiring in short building scince lab
21/02/2017 internal wiring in small building passage
providing vent pipe to exiting septic tank
22/02/2017 Providing soft board in long building in room no 3-8
23/02/2017 Providing soft board in short building in room no 9-11
24/02/2017 Providing anti termite treatment in inside & out side of all building primises
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST AUGUST
2/5/2017

4/5/2017

5/5/2017

6/5/2017

9/5/2017
11/5/2017

13/5/2017

15/5/2017

16/5/2017
17/5/2017
18/5/2017

19/5/2017

20/5/2017

22/5/2017
24/5/2017

25/5/2017

26/5/2017

30/5/2017
31/5/2017
Removing internal plaster of small building Room no3
1st coat external plaster of small buildng P19
Laying of paver block near Entrance 2 South side.
Fixing of indian W/C at caretakers toilet.
1st coat external plaster of small buildng P20
1st coat internal plaster of small building Room no 4
Laying paver front of small building part 6
1st coat internal plaster of small building Room no 5
Laying paver front of small building part 6
1st coat internal plaster of small building Room no 6
2nd coat external plaster of small building P20
Removing external plaster of small building P14,P15
1st coat internal plaster of small building Room no 3
2nd coat internal plaster of small building Room no 4
Removing external plaster of Long building P4 corridor side
2nd coat internal plaster of small building Room no 5
Removing external plaster of Long building building P1, P5
2nd coat internal plaster of small building Room no 6
Removing external plaster of small building P21
2nd coat external plaster of small buildng P19
2nd coat internal plaster of small building Room no 3
1st coat external plaster of small building P14, P15
1st coat external plaster of small building P1
2nd coat external plaster of small building P14, P15.
Brick masonary of caretakers toilet.
1st coat external plaster of small building P5
2nd coat external plaster of Long building P1,P5
Demolishion of existing Sintex uthala
1st coat external and internal plaster of Watchmans cabin
1st coat external plaster of small building P21
Brick masonary for foundation and super structure of sintex uthala
Brick masonary for proposed girls toilet
1st coat internal plaster of caretakers toilet
1st coat internal plaster of caretakers toilet outer wall
Cleaning of small building ceiling and ponding for seepage.
1st coat external plaster of sintex uthala
Brick masonary of proposed girls toilet window.
2nd coat external and internal plaster of electric meter room.
Preparing window frame for small building.
1st coat external plaster of Long building P4 corridor side
2nd coat external plaster of small building P21
Removing existing roofing of small building and short wing
2nd coat external plaster of sintex uthala
Removing existing roof of small building
Roofing of small building.
Removing internal plaster of small building room no 1

Removing internal ceiling plaster of small building corridor for structural repair.
Roofing of small building.
Applying rusticide to the exposed steel in ceiling slab.
Fixing door frames In small building.
Polymer on the ceiling slab.
1st coat internal plaster of small building Room no 1
Rectification of chamber and drainage line
Fixing of small building doors frames and doors
1st coat internal plaster of small building Room no 1
Fillng gaps of roofing in small building
Plaster of small building ceiling slab.
Painting in small building room no 4,5
2nd coat internal plaster of small building Room no 1
Grouting and rendering of small building slab for waterproofing
Lintel of door and window of small building room no 1
Paver block part 7 front of short wing
lintel of electric meter room and roofing
Lintel for girls toilet ventilation
Caretaker room lintel of door anf fixing door frame
2nd coat external plaster of girl toilet window
Windows shutter fixing on small building
windows frame fixing on Short wing.
shuttering for watchmans cabin slab
Kota in short wing corridor
Reinforcement for watchmans cabin slab
Removing existing kota of long building corridor
Kota skirting in short wing corridor
Kota in long building Small corridor
windows shutter fixing on short wing
Brick batt waterproofing on small building slab
fixing girls toilet drainage line
Painting work (Putty) in small building room no 1,4,5
Painting work (Putty) in small building corridor
Painting work on compound wall
MS grill fixing in Small building and short wing windows
Painting work of small building purlins.
Painting work on compound wall fencing.
Laying nahani Trap in girls toilet, science lab
Kota Sill for small building corridor windows.
PCC for paver rear side of small building