Beruflich Dokumente
Kultur Dokumente
Submitted To
Dr. Zaka Emad
Submitted By
2016-MIN-36
2016-MIN-52
2016-MIN-52
2
Table 1: site investigation cost ................................................................................................... 5
Table 2:Intact Rock Properties................................................................................................... 5
Table 3:comrasion of methods ................................................................................................. 11
Table 4:Values of A & B Underground opening Hook & Brown (1980) .... Error! Bookmark
not defined.
Table 5: support design criteria................................................................................................ 15
3
Workload Distribution
Being the residents of same hostel almost all the work was done with mutual corporation of all
members. Each idea and task presented by a member was rechecked and verified by other
members. Most of calculations were done by Mr. Ali Ejaz Qureshi, software works and poster
was prepared by Mr. Nasir Abbas. Literature review was done by Mr. Zahid Abbas.
4
Abstract
A 200 m tunnel is to be constructed through a sandstone formation in Bolan Pass Balochistan.
The tunnel is to be used for Railway passage that should have double lines. A site investigation
was conducted a moderate cost, that included site mapping, sub-surface investigations and
laboratory testing. Using the given overburden and field conditions in-situ stresses are
determined, based on measured stresses, tunnel cross-section and shape are decided. Drill and
Blast technique was selected as an Excavation Method because of its moderate cost and
efficiency. Dimensions of tunnel are decided on the basis of dimensions of train to be passed
through it. The RMR was calculated according to given conditions that indicated the rock to
be fair. Support system was designed for a fairly strong rock, 4m long bolts spaced at 1.5 m
are used for rock support.
5
Introduction and Background:
A tunnel is an underground passage that is built on
highways, railways and Hydel-power projects, for transport of
passengers, goods, sewages etc. In railway tracks short turns and
steep slopes are not possible so it becomes essential to build
tunnels in hilly and mountainous areas.
The history of tunnels is very old. The first tunnel was
constructed about 4000 years ago in Babylon to connect two
buildings. The first railway tunnel in the world was constructed
at the end of the nineteenth century to connect Switzerland and
Italy. The cross section of the tunnel was in the shape of a
horseshoe and its length was about 20 km In the early days Figure 1: Railway tunnel
1
1. Site investigation:
Site investigation is the foremost step of a construction project. It is done to gather the
facts about ground conditions such as ground water conditions, rock mass properties and
bedding mechanism etc.
2
Site Investigation Plan
Site Investigation
PKR 1428660/_
3
1.3 Cost Estimations:
Site Mapping:
In this phase we are getting the topographic maps of site.
How to get: Instead of traditional mapping methods, we are going to get the topographic maps
using the software technologies. AutoCAD latest tool “ plex.Eatrh” can be used to make precise
topographic maps.
Cost of software: $ 399 = PKR 56660/-
Geo-referencing: PKR 10,000/-
Stratigraphy of location:
Stratigraphy includes the study of bedding in the area of interest.
How to do: site visit and literature review, books and online resources
Cost: PKR 30000/-
4
Laboratory testing:
The samples core in field are finally brought to laboratory for testing.
How to do: satisfactory laboratory test re performed in UET rock mechanics laboratory.
Cost: Rs 900/- per sample
No of samples to be tested = 80
Total coast = 80 x 900 = RS 72,000/-
3 Subsurface Ultra-pure RS
Investigations Drilling company 1260,000/-
5
1.3.2 Rock Mass properties:
Rock mass properties are determine the behavior of rock bodes with discontinuities. In field
we usually have to deal with rock mass, these properties are calculated by using Hoek et
relationships.
Alternatively Rock Mass properties can be calculated by computer software “ RocLab”. We
are using this software to calculate rock mass properties.
Results
6
2. In-situ stresses:
In situ stresses are the stresses present in a rock where no engineering activity is done.
Whenever an engineering activity is performed then there is a new set of stresses produced in
that rock. There are two types of in-situ stresses produced in a rock i.e. vertical and horizontal
in-situ stresses. Vertical stresses are due to overlying rock mass and horizontal stresses are due
to lateral load. The magnitude and direction of these stresses plays an important role in
designing underground cavity and tunnels.
σh= (K) σv
𝑣
K = 1−𝑣
where,
v = poison ratio
σv = 4800 kN/m2
σv = 4.8 MPa
Horizontal Stress:
𝑣
K = 1−𝑣
0.3
K = 1−0.3
K = 0.42
σh = (0.42) 4.8
σh = 2.05
MPa
Vertical Stress:
σv = ρgz
σv = (24)(1000)
σv = 24000 kN/m2
σv = 24 MPa
Horizontal Stress:
𝑣
K=
1−𝑣
0.3
K = 1−0.3
K = 0.428
σh= (0.428) 24
σh = 10.27 MPa
2.4 Suitable method for in-situ stress determination:
As in-situ stresses are helpful in designing underground cavity and tunnels, therefore it is
important to measure in-situ stresses accurately and precisely. There are many methods for the
measurements of in-situ stresses. Some of them are discussed below:
8
2.4.1 Restoration techniques (Flat jack):
It is an instrument which is used to determine the in-situ stresses by using restoration technique.
Procedure:
➢ Install pins on drift wall and measure their spacings.
➢ Create slot with diamond blade (pins come closer by ~1 mm).
➢ Insert flat-jack into the slot.
➢ Pressurize flat-jack until the pins are back to their initial positions.
Advantages Disadvantages
Almost direct stress measurement (no Good welding required for pressures up to
calculation 100 MPa
Quick (~1 hour) The drift surface has already been disturbed
by the excavation.
Stresses averaged over ~1 m3 Need to relate the stresses measured locally
and the far-field stresses
Extremely reliable: no electronic device. Only the normal stress on the flat‐jack is
compensated, not the shear stress.
Less cost than others. Rock behavior has to be reversible.
9
Figure 12 over coring method
Advantages Disadvantages
Very precise (~5 μ strain/~0.1 MPa). Stress are not measured, but calculated
assuming the rock to behave elastically.
All stress components determined Very local strain measurement, so even small
simultaneously at one point. heterogeneous (~5 mm) may influence the
result.
Access to virgin stress because the Highly sensitive device (e.g. heat produced
measuring device is far away from the drift. by the drilling).
Advantages Disadvantages
Stress orientations well-‐determined by the High pressure required to create or stimulate
orientation of induced fracture. fractures in a highly stress environment.
Minimum stress measured out of the Expensive equipment, mostly used in oil
influence of the borehole. industry.
Stresses averaged over a volume of 1 to10m3. The major stress is generally difficult to
determine precisely.
10
Comparison of above methods:
Table 3:comrasion of methods
For the determination of in-situ stresses we use flat jack method, as it is easy to install, less
costly and reliable.
11
Table 4:Values of A & B Underground opening Hook & Brown (1980)
= (2.3 – 0.428)(24)
σθw = 44.92
12
MPa MPa
3.2. Tunnel size:
The tunnel size can be decided according to the dimensions of train to be passed. For double
line railway track.
Width of train = 9’
Distance between passing trains = 4’
man ways, maintenance and supplies = 4’
total width of tunnel = 30’
Height along central axis = 24’
Area calculation:
circle.
3.14(7.52)
= 9 x 30 + =
2
Figure 13:AutoCad sketch
358.31 ft2
Volume calculations
Volume of material to be handled = A x l
= 358.31 x656 = 71662 ft3
13
Economical and Better-quality Needs trained staff and skilled (Hiren,
control, Time of completion is less supervision Imposition of caution Pitroda et al.)
Jacked Saving in man power & Machinery order exists for a longer period No
Box No involvement of crane & heavy scope of the night working Once
equipment, Less involvement of the vertical & the lateral
other Departments. alignment of box disturbed it
becomes almost impossible to
rectify it
Preservation of the environment Not suitable for very deep (Sharma
Safe initiation and completion of excavations More dust and noise 2011,
railway tunnels Safe work progress impact may arise Cause Abdallah and
Cut & in unstable weak ground May interference with traffic and other Marzouk
Cover applied as sequential construction urban activities. 2013, Cut and
in case of most adverse Cover 2015)
geotechnical conditions Cheaper
and more practical than other
underground tunneling Small risk,
relative to other construction
techniques.
14
RMR = 55% (FAIR)
73.8
Safety factor = 1.35
15
Hoop stress = 3σh – σv = 3 × 10.27 – 24
= 6.81 MPa
Safety factor = 𝑈𝐶𝑆
ℎ𝑜𝑜𝑝 𝑠𝑡𝑟𝑒𝑠𝑠
73.8
Safety factor =
6.81
As in both cases the safety factor for tunnel is greater than 1; it means that tunnel is stable.
16
References:
Books:
1. Railway Engineering by SATISH CHANDRA Professor, Department of Civil
Engineering, Indian Institute of Technology Roorke
2. Fundamentals of Rock Mechanics by J.C.Jaeger, N.G.W.Cook, and R.W.Zimmerman.
3. Brady BHG, Brown ET (1995) Rock mechanics for underground mining.
4. Bieniawski, Z.T. 1989. Engineering rock mass classifications.
5. Site Investigation by C. R. I. Clayton, M. C. Matthews and N. E. Simons.
6. Support of underground excavations in hard rock by E. Hoek, P.K. kaiser &W.F. baw.
7. Stratigraphy of Pakistan by S.M. Ibrahim Shah.
Online resources:
8. https://www.ita-aites.org/
9. http://ultrapurepakistan.com/boring-and-drilling/
10. http://www.rockmass.net/files/classifications_of_rock_properties.pdf
11. https://www.sciencedirect.com/topics/earth-and-planetary-sciences/in-situ-stress
12. http://www.world-stress-map.org/
17
Appendix: 1: Rock Mass Rating System
18
Appendix: 2 Guidelines for excavation and support of 10 m span rock tunnels in accordance with the RMR system
(After Bieniawski 1989).
19
20
21