CE TE 3 (Database Management in Construction) Instructor
Make a database for steel truss, wood truss and flat (concrete slab) roofing for the same floor
area of 7.5 sq.m. Consider materials, manpower and program of work. Use actual/present prices
of materials and rates of manpower. Equipment is not necessary.
Presuming that finance or budget is not a constraint, answer the following questions based on
your stablished data:
GOOD LUCK!
3.0 m x 2.5 m (7.5 sq.m.) FLOOR PLAN WITH GABLE TYPE ROOF
STEEL TRUSS
NO. OF 4mm thick x 38mm x 38mm x 6.0m A.B. = (12.9427x2)x3 = 77.66 m/6.0 = 13 pcs
NO. OF 50mm x 100mm 6.0m GA. #16 C PURLIN FASCIA BOARD = [(2.2809x4)+ (4.6x2)]
2= 36.64 m/6.0 = 6.11 or 7 pcs
NO. OF 5mm thick x 38mm x 6.0 m FLAT BAR FOR GUSSET PLATE = (8 x 3) x 6" = 144"/6
m = 1 pc
NO. OF RIDGE CAP = 5 m or 2 pcs
NO. OF RIDGE ROLL = 5 m or 2 pcs
NO. OF GUTTER = 4.6x2 = 9.2 m/2.44 = 3.77 or 4 pcs
NO. OF FLASHING = 2.2809x 4 = 9.12 m/2.44 = 3.74 or 4 pcs
TOTAL LENGTH OF G.I. SHEET = [(4.6/.8)x2]x2.2809 = 26.23 m or 27 m
NO. OF 50mm x 100mm 6.0m GA. #16 C PURLIN = 4.6x4 = 18.4 m/6.0 = 3.06 or 4 pcs
TOTAL NO. OF RIVETS = 11.5 x 18 = 207 pcs or 1 box
WOOD TRUSS
NO. OF 2"x4" B.C., WEB MEMBERS and COLLAR PLATE = (7.38 x 3)+(0.6x2x3) = 25.74
m or 84.43 ft./8 = 10.55 or 11 pcs
NO. OF 2" x 6" K.P. and T.C. = 5.36x3 = 16.08 m or 52.74ft./8 = 6.59 or 7 pcs
NO. OF 2" x 3" PURLINS = 4.6x4 = 18.4 m or 60. 35 ft./8 = 7.54 or 8 pcs
NO. OF 1" x 10" FASCIA BOARD = (2.2809x4)+ (4.6x2) = 18.32 m or 60.09 ft./8 = 7.5 or 8
pcs
NO. OF RIDGE CAP = 5 m or 2 pcs
NO. OF RIDGE ROLL = 5 m or 2 pcs
NO. OF GUTTER = 4.6x2 = 9.2 m/2.44 = 3.77 or 4 pcs
NO. OF FLASHING = 2.2809x 4 = 9.12 m/2.44 = 3.74 or 4 pcs
TOTAL LENGTH OF G.I. SHEET = [(4.6/.8)x2]x2.2809 = 26.23 m or 27 m
TOTAL NO. OF NAILS = 11.5 x 18 = 207 pcs or ( ) = 1.15 Kg
CONCRETE SLAB ROOFING
MANPOWER
DESCRIPTION RATE/DAY RATE/HOUR
IRON WORKERS (STEELMEN) 500.00/day 62.50/hr
WELDER 750.00/day 93.75/hr
WOOD TRUSS
MANPOWER
DESCRIPTION RATE/DAY RATE/HOUR
LABORER 400.00/day 50.00/hr
SKILLED CARPENTER 650.00/day 81.25/hr
CONCRETE SLAB
MANPOWER
DESCRIPTION RATE/DAY RATE/HOUR
LABORER 400.00/day 50.00/hr
IRON WORKERS (STEELMEN) 500.00/day 62.50/hr
SKILLED MASON 650.00/day 81.25/hr
1. Which is the most expensive in terms of materials?
- The most expensive in terms of materials is the Steel Truss Roofing with a total material
cost of ₱ 39,232.50
- The cheapest in terms of materials is the Concrete Slab Roofing with a total material
cost of ₱ 13,176.25
- The most expensive in terms of manpower cost is the Wood Truss Roofing with a total
manpower cost of ₱ 5,800.00
- The cheapest in terms of manpower cost is the Concrete Slab Roofing with a total
manpower cost of ₱ 1,950.00
- The fastest to construct is the Concrete Slab Roofing with a total of 2 working days.
- The most expensive in terms of total construction cost is the Steel Truss Roofing with a
total construction cost of ₱ 44,482.50
- The cheapest in terms of total construction cost is the Concrete Slab Roofing with a
total construction cost of ₱ 15,126.25
8. Which will last the longest? Support your answer. Indicate reference.
- The Steel Truss will last the longest because Wood Truss and Concrete Slab Roofing
are more likely to age more quickly than Steel Truss; Wood Trusses are prone to termite
infestation while Concrete Slab Roofing is prone to weathering which causes the concrete
to crack or weakens as it ages. While the Steel Truss is not prone to these causes.
Reference: https://prezi.com/6tfvak-hyixw/wood-steel-concrete/