Beruflich Dokumente
Kultur Dokumente
COMMISSIONING PROCEDURE:
Based on the assembly Drawing the layout of panels and Installation will be
checked.
Damage and Loosed equipment or materials will be checked.
During this inspection need to ensure all the equipment on the panels are
connected to the common earth bus of the panel and the common earth bus is
Earthen properly.
After positioned the panels at site, inter panel wiring to be ensured before
commissioning.
Tightness of terminals in both Panels and equipment to be checked and the list of
equipment available on the panels to be ensured with the requirement and bill of
materials.
B) INSULATION RESISTANCE:
After completion of Panel erection and inter panel wiring, the insulation resistance
between all conductors and the ground will be measured by 500 Volts Megger.
C) DC LOGIC:
The DC Logic test contains the testing of interlocks as per schematics and
requirement.
This test contains the testing of Tripping circuits and trip logics in addition to the
Trip circuit supervision
CT / PT switching circuit to be ensured as per schematics.
Breaker operation to tested with concerned team assistance.
D) PROTECTION CHECKS:
All the protective relays to be tested as per the requirement. During testing the
relays may be tested with the final settings (if available at the time of testing). The
protective relays to be tested as per the standard formats each relay.
The relay testing to be carried out from the panel CT / PT terminals at the Panels
and from the direct to the relay terminals which will help to ensure the healthiness
of the CT / PT wiring.
The protection interlocks and the final trip relay operation to be ensured as per the
schemes.
The circuit breaker operation to be ensured thoroughly through the trip relay
operation.
The conditions of Auto reclose of the circuit breaker to be tested as per the scheme
and adopted settings.
The relay communication to be checked based on the availability.
Annunciation tests to be carried out for both Trip and Non Trip circuits
Alarm circuits to be tested with the Bell / Hotter tests for both Trip and Non Trip
functions.
The digital inputs/ outputs used for the for the SCADA purpose to be checked
with the concerned Engineer.
F) METERING CIRCUITS:
Meters healthiness to be ensured at site with the available test kit at site.
The CT / PT wiring to be ensured from the terminal blocks of panels to the meters.
G) SYNCHRONISING PROCEDURE:
The primary injection is required to ensure the cable termination and to ensure the
polarity of CTs / PTs. This test to be conducted with the plant testing team.
During this tests all the values to be recorded for panels terminals and Relay
terminals for both Meatering and Protection circuits.
This test includes the Stability and Sensitivity test for Differential protection.
Drawing No :
DC LOGIC
PROTECTION CHECKS
METERING CIRCUITS
SYNCHRONISING CHECKS:
------------------------------- -------------------------------------
----------------------- ------------------------
Date Date
Customer :
CCC No :
Date :
Main System :
Drawing No :
The Commissioning of the above mentioned Panel / Relay or System is completed according
to the applicable Drawings, Specifications and recommendation with the exception of Open
Items mentioned in the attached open item list.
Signature:
Date
Customer :
CCC No :
Date :
Main System :
Drawing No :
Signature:
Date
Site Name :
Bay / Unit Name :
Customer Name :
Intendor Name :
Running Drawing No. Sheet Required Modification Answer for Remarks
No No. Details / Purpose Requisition
Signature:
Date
Signature:
Date
TO AND FRO FARE FROM BASE STATION BY AIR/TRAIN AC FIRST CLASS/TAXI SHALL BE CHARGED
AS TRAVELLING EXPENSES. BASE STATION MEANS
THE DAILY RATE IS APPLICABLE FROM THE DAY OF DEPARTURE OF TECH PERSONNEL FROM THE
BASE STATION TO THE DAY OF RETURN TO THE BASE STATION (BOTH DAYS INCLUSIVE).
OVERTIME RATE SHALL NOT BE APPLICABLE DURING JOURNEY PERIOD.
MATERIAL SUPPLIED :
Did the Service engineer handover the catalogue for Retrofit / Training
RESPONSE TIME
QUALITY OF RESPONSE
CUSTOMER NAME :
Designation :
Seal :
Form
No: 08
Name Of Client
Address Of Client
Panel Type
Number Of Panel
Relay Type
Number of Relays
Name Of Manufacturer
Remarks
Signature :