Beruflich Dokumente
Kultur Dokumente
Emergency Handling
1. Loss of Feed
2. Loss of Wash Water
3. Loss of Recycle Gas / Compressor
4. Recycle gas flow low-low
5. Loss of Make Up Gas
6. Loss of Quench Gas
7. High Temperature at the Charge Heater Outlet
8. Temperature Excursions
9. Loss of Rx Effluent Air Cooler
10.Charge Heater Trip
11.Loss of Amine System
12. Steam Failure
13. Instrument Air Failure
14. Power Failure
15. Cooling Water Failure
16. Major leak / Fire or Line Rupture
17. Charge Heater Tube Rupture
18. External Fire
19. Emergency Shutdown
20. RGC Seal Gas Supply Failure
Introduction.
1
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
Emergencies that occur in units must be recognized and acted upon immediately.
The operators and supervisory personnel should carefully study in advance, and
become thoroughly familiar with, the proper steps to be taken in such situations.
Some of the emergency conditions described here will not only result in a unit
shutdown, but if the situation is not handled properly, can lead to serious
damage to the catalyst and equipment.
These procedures are intended as guidelines for the development of detailed
emergency instructions for each particular equipment. It is strongly recommended that
they be understood by all persons involved in the operation. In general, the objective
of the emergency procedures is to avoid damage to equipment and catalyst.
This is accomplished by rapid cooling of the catalyst beds below reaction
temperature and by reducing the pressure whenever there is a possibility of a
temperature excursion.
In addition, specific rules cannot be made to cover all situations that might arise.
Therefore, the following procedures cover only those emergency situations that
are the most common and, for the most part, only the immediate steps to be taken
are listed. It should be noted that the procedures outlined here concentrate on
the reactor section. In most cases, the corrective actions will result in upsets in
the fractionation section. It is advised that care be taken to adjust the
fractionation section operation whenever flows and/or severity are reduced.
It should also be noted that the protection of austenitic stainless steel equipment
must always be kept in mind. The proper precautionary measures must be taken to
prevent oxygen and water from coming into contact with any austenitic
material that has sulfide scale. These measures should not conflict with the
immediate steps required as a result of the emergency condition.
Any time an emergency situation occurs, especially when a reduction in space
velocity or capability of removing the heat of reaction from the catalyst is involved, a
condition exists which could lead to the generation of localized high temperatures.
Therefore, if during any type of emergency there is a rapid temperature rise in the
reactor or catalyst bed, immediate steps should be taken to depressurise the
system to suppress the reactions. The objective is to prevent a further rise in
temperature and minimize the danger of damage to the reactor and other
equipments.
1. Loss of Feed
Loss of can be due to various reasons such as
* Feed Pump failure / Low discharge pressure / Low Surge drum level
Loss of one Feed Pump (GA-33301A/B) will first affect the Reactor Heater (BA-
33301) which will trip it on very low feed flow. It is necessary to keep the Reactor
inlet temperature under control and try to restore feed to the unit. If it is not
possible, the normal shutdown procedure shall apply.
2
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
3
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
the other reactant, hydrogen. This is accomplished via the manual depressurizing
system upon loss of recycle gas compressor.
Very low recycle gas flow rate will activate IS-02 (stop feed pumps, isolates
reactor feed, trips the reactor heater & Wash water pump). In this case, the heat of
reaction cannot be controlled and a temperature increase will occur which is likely
to damage the catalyst. An immediate operator action is to attempt to restart the
recycle compressor (GB-33301) as quickly as possible, in order to restore the
recycle gas flow.
The Operator should attempt to restart the machine as soon as possible
but only after finding the cause & attending the same.
Start decreasing the temperatures to 300°C in the reactor.
If the recycle gas compressor (GB-33301) can be restarted within 5-10
minutes after the failure
Restart feed pump (GA-33301 A/B).Open the discharge valve and oil-in
after having fired the charge heater.
If the recycle gas compressor cannot be restarted in 5 minutes or any bed
temperature is rising quickly, then reduce the reactor temperature by
opening the recycle gas purge valve on manual and stop the make-up
compressor.
When the recycle gas compressor becomes available, re-establish
recycle gas flow and line out catalyst temperatures 260-290°C. Then,
continue with normal procedure for startup with used catalyst.
4
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
system pressure declines, the capacity of the recycle gas compressor will be
reduced and control of reactor temperatures will become more difficult.
Lower reactor temperature sufficiently to reduce hydrogen consumption.
Restore reactor pressure as quickly as possible. After the pressure has
returned to normal, adjust reactor temperature to obtain as much
desulphurization as is possible with the available hydrogen.
If there is a total loss of makeup hydrogen, it will be necessary to shutdown.
Lower reactor temperatures to 300°C and follow normal shutdown
procedures.
If the makeup compressors shut down (i.e. due to a dip in power) and can be
immediately restarted, a shutdown may not be necessary. Lower
temperatures and feed rate as quickly as possible to minimize hydrogen
consumption. Restart the makeup gas compressors GB-33302A/B and
restore system pressure as soon as possible. If the HP Separator FA-33304
pressure drops to less than 70 percent (Approx. 45 Kg/cm 2g) of its normal
pressure it is advisable not to start the compressor and proceed with the unit
shut down, to prevent excessive catalyst coking and deactivation.
8. Temperature Excursions
A temperature excursion is a serious situation that requires immediate attention.
During a temperature excursion highly exothermic cracking reactions can take
place. These temperatures can rise rapidly to well above the equipment design
temperature. Hence the thrust is to prevent catalyst temperatures from exceeding
the design limits. A temperature excursion can be brought about by equipment or
utility failures that result in any one of the following problems:
A significant reduction in space velocity over the catalyst.
A reduction in capability of removing the heat of reaction from the catalyst.
By overheating during a startup or during normal operation.
5
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
The period during a fresh catalyst startup, before the catalyst has been thoroughly
sulphided, is perhaps the most critical time when very special care should be taken
to control the reactor temperatures, as outlined in the startup procedure.
Desulphurising Catalysts have been formulated to provide a high desulphurization
activity with very little hydrocracking activity, and therefore they are much
less susceptible to temperature runaways than a hydrocracking catalyst.
The possibility of a temperature runaway still does exist, however, and all
appropriate precautions should be taken.
In order to sustain a temperature runaway, both hydrocarbons and heat must be
available. Therefore, removing one or the other will cause the reactions to stop. The
quickest way to achieve this, and still maintain hydrogen pressure in order to
minimize coke formation, is to remove the feed from the unit and to cool the
catalyst with recycle gas. However, if the temperature rise cannot be controlled, then
the unit should be rapidly depressurised to suppress the reactions and to minimize
the danger of damage to the reactor and other equipments.
If a temperature in the reactor starts to rise above normal, the following steps
should be taken:
Reduce the inlet temperature of the bed in which the high temperature
occurs. Also, reduce inlet temperatures to the catalyst beds below.
If the temperatures are not controlled by the corrective action of step
(1), reduce the reactor inlet temperature by reducing firing rate of the
charge heater.
If the temperatures continue to rise 28°C above normal, remove feed from
the unit.
If the catalyst bed temperatures are 28°C above normal and continue to
rise despite the above corrective actions, or if the temperatures exceed the
maximum allowable operating temperature of the reactor, then
depressuring will be necessary to regain control of the reactor. If the
operator decides to manually depressurise the unit via the
manual emergency depressuring system, the following should
occur automatically:
o The feed pump GA-33301 A/B shuts down.
o The shutoff control valves in the fuel gas and fuel oil lines to the
charge heaters close, the pilots will stay lit.
o The control valve in the makeup gas line will close, or the spillback
valve in the last stage of makeup gas compression will fully open.
Manual unloading of the makeup gas compressor and subsequent
shutdown may be necessary.
o The wash water pump will shut down.
o The lean amine pump will shut down.
NOTE: When manual depressurising system is activated, the recycle gas
compressor will continue to operate.
Verify that the charge heater burners are out. Open the stack damper and
all air registers to the full open position to establish the maximum flow of
6
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
7
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
8
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
9
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
In case of major leak, fire or line rupture, the section has to be shut down, by
stopping the feeds (refer to "Immediate Shutdown") to minimize the possible
extension of the hazard. As a consequence, the upstream section has to be
shutdown.
10
Mangalore Refinery and Petrochemicals Ltd, Mangalore Doc No.
DHDT Unit – Phase-3 - Operating Manual F ……
Section-1-Chapter VIII –Emergency Handling 20-6-2012
11