Panjang = 1.50 m
Lebar = 1.50 m
Tinggi = 1.10 m
Jumlah = 93 buah
Luas Galian
= 2.25 m2
Volume Galian Per Pondasi 2.475 m3
Panjang = 1.00 m
Lebar = 2.00 m
Tinggi = 1.10 m
Jumlah = 16 buah
Luas Galian
= 2 m2
Volume Galian Per Pondasi 2.2 m3
Panjang = 935.00 m
Lebar = 0.40 m
Tinggi = 0.30 m
Luas Galian
= 374 m2
No
ITEM PEKERJAAN VOLUME
2 Urugan Tanah Kembali
a. Urugan Fondasi 1 kolom 600x600
Volume Galian = 2.475 m3
Volume Pondasi = 2.124 m3
Volume Urugan = 0.351 m3
Jumlah = 66.00 buah
Volume Urugan Pondasi 1 kolom 600x600
= 23.17 m3
b. Urugan Fondasi 1 kolom 800x800
Volume Galian = 2.475 m3
Volume Pondasi = 2.376 m3
Volume Urugan = 0.099 m3
Jumlah = 27.00 buah
Volume Urugan Pondasi 1 kolom 800x800
= 2.67 m3
c. Urugan Fondasi 2
Volume Galian = 2.2 m3
Volume Pondasi = 2.176 m3
Volume Urugan = 0.024 m3
Jumlah = 16.00 buah
Volume Urugan Pondasi 2
= 0.38 m3
PEKERJAAN BETON
No ITEM PEKERJAAN VOLUME
1 Sloof
Sloof Struktur
Panjang = 935.00
Lebar = 0.20
Tinggi = 0.20
Volume
= 37.40
2 Balok lantai 1
a. Balok B1
Balok 400x600
Panjang = 801.70
Lebar = 0.40
Tinggi = 0.60
Volume
= 192.41
b. Balok B2
Balok 700x500
Panjang = 3.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 1.05
b. Balok Anak
Balok 700x500
Panjang = 3.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 1.05
3 Balok lantai 2
a. Balok B1
Balok 400x600
Panjang = 671.15
Lebar = 0.40
Tinggi = 0.60
Volume
= 161.08
b. Balok B2
Balok 700x500
Panjang = 51.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 17.85
c. Balok Anak
Balok 700x500
Panjang = 3.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 1.05
4 Balok lantai 3
a. Balok B1
Balok 400x600
Panjang = 245.00
Lebar = 0.40
Tinggi = 0.60
Volume
= 58.80
b. Balok B2
Balok 700x500
Panjang = 3.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 1.05
b. Balok Anak
Balok 700x500
Panjang = 3.00
Lebar = 0.50
Tinggi = 0.70
Volume
= 1.05
5 Kolom Lantai 1
a. Kolom 600x600
Kolom 600x600
Panjang = 0.60
Lebar = 0.60
Tinggi = 4.60
Jumlah = 62
Volume
= 102.67
b. Kolom 800x800
Kolom 800x800
Panjang = 0.80
Lebar = 0.80
Tinggi = 4.60
Jumlah = 43
Volume
= 126.59
c. Kolom 800x800
Kolom 500x500
Panjang = 0.50
Lebar = 0.50
Tinggi = 4.60
Jumlah = 4
Volume
= 4.60
6 Kolom Lantai 2
a. Kolom 600x600
Kolom 600x600
Panjang = 0.60
Lebar = 0.60
Tinggi = 5.40
Jumlah = 87
Volume
= 169.13
b. Kolom 800x800
Kolom 800x800
Panjang = 0.80
Lebar = 0.80
Tinggi = 5.40
Jumlah = 6
Volume
= 20.74
c. Kolom 500x500
Kolom 500x500
Panjang = 0.50
Lebar = 0.50
Tinggi = 5.40
Jumlah = 4
Volume
= 5.40
7 Kolom Lantai 3
a. Kolom K3
Kolom 500x500
Panjang = 0.50
Lebar = 0.50
Tinggi = 5.30
Jumlah = 39
Volume
= 51.68
8 Plat Lantai Lt 1
a. Plat Lantai A
Plat Lantai 5mx5mx0,15m
Panjang = 5.00
Lebar = 5.00
Tinggi = 0.15
Jumlah = 76.5
Volume
= 286.88
Plat Lantai Lt 2
b. Plat Lantai A
Plat Lantai 5mx5mx0,15m
Panjang = 5.00
Lebar = 5.00
Tinggi = 0.15
Jumlah = 76.5
Volume
= 286.88
Plat Atap Lt 3
c. Plat Atap B
Plat Atap 5mx5mx0,12m
Panjang = 5.00
Lebar = 5.00
Tinggi = 0.12
Jumlah = 18
Volume
= 54.00
Panjang = 0.20
Lebar = 0.20
Tinggi = 4.60
Jumlah = 55
Volume
= 10.12
Kolom Praktis Lantai 2
a. Kolom 200x200
Kolom 200x200
Panjang = 0.20
Lebar = 0.20
Tinggi = 5.40
Jumlah = 29
Volume
= 6.26
Kolom Praktis Lantai 3
a. Kolom 200x200
Kolom 200x200
Panjang = 0.20
Lebar = 0.20
Tinggi = 5.30
Jumlah = 17
Volume
= 3.60
10 Tangga Darurat
a. Pekerjaan Anak Tangga
Volume Pekerjaan Anak Tangga
n = 21.00
Panjang = 2.10
Lebar = 0.25
Tinggi = 0.2
Volume = 2.21
n = 12.00
Panjang = 2.10
Lebar = 0.25
Tinggi = 0.22
Volume = 1.39
n = 13.00
Panjang = 2.10
Lebar = 0.25
Tinggi = 0.19
Volume = 1.30
Panjang = 3.20
Lebar = 2.10
Tinggi = 0.12
Volume = 0.81
Panjang = 3.90
Lebar = 2.10
Tinggi = 0.12
Volume = 0.98
Panjang = 4.30
Lebar = 2.10
Tinggi = 0.12
Volume = 1.08
Panjang = 4.40
Lebar = 2.10
Tinggi = 0.12
Volume = 1.11
n = 2
Panjang = 4.85
Lebar = 1.72
Tinggi = 0.16
Volume = 2.67
n = 2
Panjang = 4.85
Lebar = 2.63
Tinggi = 0.16
Volume = 4.08
n = 4
Panjang = 4.85
Lebar = 0.20
Tinggi = 0.3
Volume = 1.16
Panjang =
Lebar = 0.15
Tinggi = 0.30
PEKERJAAN KERAMIK
No ITEM PEKERJAAN VOLUME
1 Keramik Lantai 1
Keramik Glossy Krem Tua (40cmx40cm)
Luas = 258.80
Luas = 23.00
Keramik Glossy Tembaga Muda (100cmx100cm)
Luas = 1,401.00
Luas = 23.00
Luas = 18.10
Luas = 30.00
Luas = 48.40
Luas = 5.40
2 Keramik Lantai 2
Marmer Glossy Bermotif Coklat Keemasan (100cmx100cm)
Luas = 511.30
Luas = 89.55
Luas = 71.00
Luas = 34.00
Luas = 125.00
Luas = 655.00
Luas = 387.50
3 Keramik Lantai 3
Keramik Glossy Tembaga Muda (100cmx100cm)
Luas = 300.50
Luas = 11.50
Luas = 30.00
Luas = 743.00
3 Keramik Tangga
Keramik Glossy Tembaga Muda (100cmx100cm)
Luas = 300.50
Luas = 11.50
Luas = 30.00
t = 0.20
Luas Lantai 1 = 1,867.70
Volume Pasir Urug = 373.54
Spesi
t = 0.01
Luas Lantai 1 = 1,867.70
Volume Spesi = 18.68
2 Keramik Lantai 2
Spesi
t = 0.01
Luas Lantai 2 = 1,887.71
Volume Spesi = 18.88
2 Keramik Lantai 3
Spesi
t = 0.01
Luas Lantai 3 = 1,085.00
Volume Spesi = 10.85
PEKERJAAN PINTU
No ITEM PEKERJAAN VOLUME
1 PINTU YACHT CLUB
P1 = 4
P2 = 2
P3 = 1
P4 = 12
P5 = 2
P6 = 2
P7 = 2
P8 = 8
P9 = 1
P10 = 6
P11 = 9
P12 = 5
P13 = 2
P14 = 3
P15 = 2
P16 = 2
P17 = 1
P18 = 1
P19 = 1
P20 = 1
P21 = 1
P22 = 3
P23 = 4
P24 = 4
P25 = 1
P26 = 2
P27 = 1
Volume = 70.89
b. Dinding Bata Indoor Lantai 2
Dinding Bata tebal 0,15m
Luas Total = 530.40
Tebal = 0.15
Volume = 79.56
c. Dinding Bata Indoor Lantai 3
Dinding Bata tebal 0,15m
Volume = 43.455
a. Dinding Partisi Lantai 1
Dinding Partisi tebal 0,15m
Volume = 120.195
b. Dinding Partisi Lantai 2
Dinding Partisi tebal 0,15m
Volume = 69.69
c. Dinding Partisi Lantai 3
Dinding Partisi tebal 0,15m
Volume = 22.5525
1 Plesteran Keramik Lantai 1
Plesteran Dinding Lantai 1
t = 0.03
Luas = 472.60
Volume = 14.18
t = 0.03
Luas = 530.40
Volume = 15.91
3 Plesteran Keramik Lantai 3
Plesteran Dinding Lantai 3
t = 0.03
Luas = 289.70
Volume = 8.69
1 Plafond Lantai 1
Plafond lantai 1
Luas = 1,867.70
1 Plafond Lantai 2
Plafond lantai 2
Luas = 1,887.71
1 Plafond Lantai 3
Plafond lantai 3
Luas = 1,085.00
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
buah
m3
m
m
m
buah
m3
m
m
m
m3
m
m
m
buah
m3
m
m
m
buah
m3
m
m
m
buah
m3
m
m
m
petak
m3
m
m
m
petak
m3
m
m
m
petak
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
buah
m
m
m
m3
buah
m
m
m
m3
buah
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
m
m
m
m3
buah
m
m
m
m3
buah
m
m
m
m3
buah
m
m
m
m3
m3
m
m
m
m2
(30cmx30cm)
m2
a (100cmx100cm)
m2
m2
30cmx30cm)
m2
m2
Soft (20cmx20cm)
m2
40cmx40cm)
m2
m2
at Keemasan (100cmx100cm)
m2
m2
m2
Soft (20cmx20cm)
m2
m2
m2
m2
a (100cmx100cm)
m2
a (100cmx100cm)
m2
m2
Soft (20cmx20cm)
m2
m2
a (100cmx100cm)
m2
m2
Soft (20cmx20cm)
m2
m2
m
m2
m3
m
m2
m3
m
m2
m3
m
m2
m3
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
buah
m2
m
m3
m2
m
m3
m2
m
m3
m2
m
m3
m2
m
m3
m2
m
m3
m
m2
m3
m
m2
m3
m
m2
m3
m2
m2
m2