Beruflich Dokumente
Kultur Dokumente
J l 29,
July 29 2011
Title & Purpose
R1
• Each Transmission Planner shall provide existing model and data to the
Generator Owner within 30 calendar days of receiving an information
request
R2
• Each Generator Owner shall provide to the Transmission Planner
A verified, accurate model in accordance with the periodicity specified in
Attachment 1
R3
• The Generator Owner shall provide a written response within 90
calendar days
y of receiving
g notice from the Transmission Planner that the
model is
Not usable, or
Has technical concerns, or
Model response did not match a recorded event response
Requirement Summary
(for
( both draft standards))
R4
• The Generator Owner shall provide revised model data or plans to
perform model verification within 180 calendar days of making changes
that alter equipment response characteristic
R5
• Each Generator Owner shall provide a written response within 90
calendar days to the Planning Coordinator following receipt of a
technically justified request to perform a model review for a unit/plant not
specified
ifi d in
i the
th Standard
St d d Applicability
A li bilit section
ti
R6
• Each Transmission Planner shall provide a written response to the
Generator Owner
O ner within
ithin 90 calendar da
days
s after receipt of model
information indicating whether the model is useable or not useable
Requirement Key Points
Synchronous condensers
• Are not currently addressed in the NERC Registry Criteria
• Are not mentioned in the Generation Verification SAR
• Have extremelyy low p
penetration ((on an MVA basis))
• Installed for dynamic voltage support
Most likely to extend a dynamic voltage security limit
• Grid apparatus owned by Transmission Owners
Peer review draft requirements would not make sense
A better fit is incorporating synchronous condenser language into MOD-025
If there is a need to develop a Reliability Standard to model the
expected behavior of dynamic voltage devices typically owned by
Transmission entities, then a separate SAR should be developed
Questions ?
Industryy Webinar:
Generator Verification SDT Summary:
PRC--024
PRC 024--1
PRC
PRC-024-1
024 1 (second posting)
• Title
Generator Performance During Frequency and Voltage
Excursions
• Purpose
p
Ensure generating units remain connected during frequency
and voltage excursions and ensure expected generating unit
performance during frequency and voltage excursions is
communicated to Reliability Coordinators, Planning
Coordinators, Transmission Operators, and Transmission
y
Planners for accurate system modeling.
g
2
Applicability & Implementation
All Requirements
q
Years
1 33%
2 66%
3 100%
3
Requirement Summary
R1
• Each Generator Owner shall:
Set in service frequency protective relaying so that it does not
operate to trip the generating unit during frequency
excursions within the band described in Attachment 1
Conditions
C diti and
d exceptions:
ti
– Must operate between 59.5 and 60.5 Hz continuous
– May trip if rate of change >2.5
>2 5 Hz/sec (Aurora exclusion)
4
Frequency Excursion Limits(Attachment 1)
62
61.5
61
60.5
cy (Hz)
No Trip 60
Frequenc
59.5
59
58.5
58
57.5
0.1 1 10 100 1000 10000
Time (sec)
R2
• Each Generator Owner shall:
Set in service voltage protective relaying so that it does not
operate to trip the generating unit during voltage excursions
within the band described in Attachment 2
Conditions
C diti and
dEExceptions:
ti
– Consider 3-phase Zone 1 faults with normal clearing
– Site-specific
Site specific clearing time may be used
– Generator tripping for SPS, RAS or to clear the fault
allowed
6
Voltage Excursion Limits (Attachment 2)
7
Requirement Summary
R3
• Each Generator Owner shall:
Inform the RC,, PC,, TOP,, and TP if a non-protection
p system
y
limitation requires tripping an existing generating unit within
the No Trip Zone boundaries of Attachment 1 and
Attachment 2.
Communication must be made within 30 days of identifying
the limitation.
p
The exception to meeting
g R1 and/or R2 expires
p when:
– The equipment causing the limitation is repaired or
replaced with equipment that removes the limitation.
– The capacity rating of the unit is increased by > 10%
8
Requirement Summary
R4
• Each Generator Owner shall:
Respond to a written inquiry by the RC
RC, PC
PC, TOP
TOP, and TP
regarding a documented limitation as described in R3.
The response must be provided within 90 days of receipt of
th iinquiry.
the i
9
Requirement Summary
R5
• Each Generator Owner shall:
Provide an estimate of the unit/plant
p p
performance during
ga
voltage or frequency excursion within 30 days of a request
from the RC, PC, TOP, or TP.
p
The response must include:
– Estimate of the time the unit will remain connected
following an excursion.
– Estimate (in 25% increments) of the probability of
remaining connected.
– Basis for the estimates
10
Requirement Summary
R6
• Each Generator Owner shall:
Design,
g , build,, and maintain new units/plants
p so that theyy will
not trip during the defined frequency or voltage excursions.
Conditions and exceptions:
– Units are operating above minimum load
– At least 90% of a wind farm remains connected
– Units may
y trip
p for SPS,, RAS,, or fault clearing
g
– Unit/plant has a temporary exemption from the RC
– Unit/plant may trip for loss of synchronism or instability in
power conversion
i control t l equipment
i t
11
Requirement Summary
R7
• Each Generator Owner shall:
Provide the RC
RC, PC,
PC TOP,
TOP and TP its protection system trip
settings affected by voltage or frequency excursions
– Within 30 days of a change in settings
– Within 30 days of a request for the settings
12
Excursion Issues
13
Compliance Issues
14
VRF & Time Horizon
R2 High Long-term
Long term Planning
15
VSL
Generator
R1 Binary Set frequency relays
Owner
Generator
R2 Binary Set voltage relays
Owner
Increment for Generator Communicate
R3
tardiness Owner limitations
Increment for Generator
R4 R
Respond
d tto iinquiries
ii
tardiness Owner
Increments for
Generator Provide estimate of
R5 tardiness and
Owner unit p
performance
completeness
Generator Ride through an
R6 Binary
Owner excursion
Provide relay settings
Increment for Generator
R7 after a change or on
tardiness Owner
request 16
Questions ?
17