CASE STUDY

Rigless Well Intervention Helps Increase


Oil Production by 30% in Sour, Heavy Oil,
and Highly Deviated Wells
RIGLESS SOLUTION USING e-SPECTRUMSM COILED TUBING FOR
RESERVOIR MONITORING REDUCED OPERATIONAL COST BY 34%
EGYPT – RED SEA

CHALLENGE OVERVIEW

» Mature field with heavy/viscous oil The GS327 oil field is located in the southeastern El-Morgan field, Gulf of Suez (GOS).
» Offshore with logistic constraints Almost all area wells are drilled with a high deviation or horizontally. Field production uses
» History of challenging well artificial lift via a gas lift system.
environments due to heavy oil,
scale, deviation, and sour fluids The field has an extended history of unsuccessful intervention operations, although the
have led to workover objectives not production logging and pulsed-neutron data were found to be precisely processed to
being met in the past for the field identify zonal phase contribution, water source, and current saturation profiling, respectively,
in order to maximize the oilfield production.
SOLUTION
CHALLENGE
» Halliburton recommended using the
e-SPECTRUMSM unit to perform all
The major challenge in GS327 wells is the viscous/
services (cleanout, treatment, and heavy oil accompanied by scale accumulation along
logging) the wellbore. Previous well interventions using
» Downhole tension (HTU) was run electric line and slickline all failed to achieve the
in all the production logging runs job objectives.
to avoid slacking off and losing/
damaging tools downhole Another challenge was the requirement of a single

HAL123758
» Real-time data integration by the coiled-tubing unit for well intervention on an offshore
Halliburton Technical Support team
operation, with limited deck space for scale cleanout, Real-time coiled-tubing production
to assure data quality, while closely
collaborating with operator on reservoir surveillance, and perforating. logging tool.
decision making
SOLUTION

RESULT Halliburton proposed using e-SPECTRUMSM real-time


electric coiled-tubing service for the well intervention
» Successfully performed more than scale cleanout, surveillance, and perforating work.
30 well intervention runs, including
Through intensive operational planning, Halliburton ran
Reservoir Monitor Tool (RMT™)
and production logging tool (PLT) several modeling assessments to assure the proper
surveillance job planning for deployment, simulating the shock-
HAL123759

» Reduced operational cost by 34% wave effect on the coiled-tubing string, choosing
» Increased oil production by 30% of the proper tool selection and downhole tension, and
the original BOPD Coiled-tubing perforation with real-time
reaching the target depth safely. All production logs correlation.
would have downhole tension (HTU) run to prevent
slacking off and losing/damaging tools downhole.
To ensure data quality, real-time data integration would be handled by a Halliburton Technical
Support team to aid in swift decision making and collaboration with the customer.
CASE STUDY

RESULTS
More than 30 runs were successfully performed, including cleanouts, along with Reservoir Monitor
Tool (RMT™) and production logging tool (PLT) surveillance work deployed using a single coiled-
tubing reel on several wells. The total-added oil production value along the campaign was found to
add 30% to the GS327 field’s original produced oil per day (BOPD).
By optimizing the runs and deployment, the project was a commercial
success and completed for 34% less than the originally planned cost.
Rigless Well
Intervention
Increase Oil
Production
by 30%
of original
BOPD

HAL123802

www.halliburton.com
Sales of Halliburton products and services will be in
accord solely with the terms and conditions contained in
the contract between Halliburton and the customer that
is applicable to the sale.

H012916 07/18 © 2018 Halliburton. All Rights Reserved.