Duration Dec '18 06 Jan '19 13 Jan '19 20 Jan '19 27 Jan '19 03 Feb '19 10 Feb '19 17 Feb '19 24 Feb '19 03 Mar '19 10 Mar '19 17 Mar '19 24 Mar '19 31 Mar '19 07 Apr '19 14 Apr '19 21 Apr '19 28 Apr
MTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMTWT F S SMT
1 MAINTENANCE OUTAGE UNIT#2 84 days 77%
12 Penggantian pada PAF kassa seal pada side DE dan NDE 3 days 100%
13 Open /close manhole windbox PA dan SA, Legbox Cyclone & Air Preheater 2 days 100%
22 Perbaikan pada manual valve desuperheater inlet feed water DN 20 PN 100. 2 days 100%
40 Pengecekan dan Cleaning MCC Low dan High Voltage 1 day 100%
41 Pengecekan dan Cleaning Trafo ESP, Penggantian Silica gel Trafo ESP dan Motor-motor anoda dan katoda 1 day 100%
43 Pengecekan dan Cleanning Panel Control dan motor- motor Coal Feeder 1 day 100%
47 Penggantian dan Pengecekan Module Damper ID, PA dan SA & Motor Damper 1 day 100%
54 Support tim mekanik Perbaikan pada MOV Before MSV 1 day 100%
Project: maintenance outage #2 Critical Critical Progress Split Baseline Baseline Milestone Summary Progress Project Summary External Milestone
Date: Wed 10/04/19 Critical Split Task Task Progress Baseline Split Milestone Summary External Tasks Deadline