Beruflich Dokumente
Kultur Dokumente
Chandkheda, Ahmedabad.
Guided by: -
ASST. PROF. PARTH A PATEL
Semester – VII (B.E CIVIL ENGINEERING)
APOLLO INSTITUTE OF ENGINEERING
(ANASAN, AHMEDABAD)
2018-19
CERTIFICATE
Guides:-
ACKNOWLEDGEMENT .............................................................................................................. 8
ABSTRACT……………………………………………………………………………………….9
LIST OF FIGURE……………………………………………………………………….………10
LIST OF TABLE……………………………………………………...……………………...….12
In this particular regard we would firstly like to express our utmost gratitude
to our respected faculties for sharing their vast knowledge and intellect with us all
throughout, their indelible time alongside with their personal memoranda in each
and every step in the approach of the internship.
This project would never have been headed if it wasn’t for the straight
forward sight of our Head of Department and our respective Guide Dr. P V Patel
who has supported us in all ways possible to reach as far as we are today giving
every detailed input in every step we took towards our internship. Also the
continuous supported by Planning manager Mr. kuldeep brambhatt who has
encouraged and led us the way who has been a very big support in helping us get
exposed to the actual world of Civil Engineering and the insight of Metro projects.
Lastly I would like to thank all of our team members for their hard work and
their positive approach towards this particular course of Practical Training. This
innovative way of having us reluctant has made us realize the value of working
together as a team and the whole training brought us together to appreciate the value
of relations and also the mutual respect towards each other.
Site training provides a better exposure to the students & it proves to be much
effective as far as application of the theory is concerned. The practical training
provides a professional environment to the student to get ready for the Industry.
The training was undertaken at Ranjit Buildcon ltd.
The work consists of construction of elevated viaduct from Ranip to Motera. The
project was intended to provide a mass transport system in the city and to relieve
peoples from the Traffic & pollution problems. The report covers all the activities
starting from substructure to super structure. The work was quite different from
the normal construction work as it was a special project launched by Govt. by
forming a special purpose vehicle called MEGA.
Execution work not only needs technical knowledge but also requires
managing skills to manage material, time, labour & other resources. So, in this
report an emphasis has been given to Time cycle analysis as well as Productivity
of labour. Importance of safety & quality has been understood to a great extent.
10 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 6. 2 MOULD FOR PRAPET ............................................................. 56
FIGURE 6. 3 REINFORCEMENT DETAILING OF PRECAST STACKING PANEL ...... 59
FIGURE 6. 4 PRECAST STACKING DETAILS FOR STANDARD SPAN ...............60
FIGURE 7. 1 ELEVATION OF SPAN ............................................................ 63
FIGURE 7. 2 SHUTTERING DETAIL OF SEGMENT ......................................... 65
FIGURE 7. 3 REINFORCEMENT DETAIL OF SEGMENT ................................... 66
FIGURE 7. 4 DETAIL OF CABLE OF SUPER STRUCTURE ................................ 68
FIGURE 7. 5 LIFTING OF SEGMENT .......................................................... 70
FIGURE 7. 8 BAR BINDING SCHEDULE ...................................................... 73
FIGURE10.1 PPE MODEL .............................................................................. 94
11 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
List of Table
12 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
13 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.1 INTRODUCTION TO PROJECT
1.1 GENERAL:-
The historic city of Ahmedabad is amongst the major metropolitan cities in India.
With the increasing opportunities for trade &commerce & as a center for higher
education, the population of the city is already touching 6 million & this heavy
growth continues, so the need of strengthening the transport infrastructure has
increased.
The Gujarat Infrastructure Development Board carried out the study for urban
transport between Gandhinagar & Ahmedabad. The Special purpose vehicle called
Metro-Link Express for Gandhinagar& Ahmedabad (MEGA) Company Ltd, was
established by Government of Gujarat on 4 February 2010.
14 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
1.2 ROUTE LENGTH:
15 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
1.3 NUMBER OF STATION:
1.6 SPEED:
16 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
1.7 INTERCHANGE STATION:
CONTRACT CONTRACTOR
Apparel park Depot URC Constriction
Gyaspur Depot Gannon Deunkerly-PSPO JV
Vastral Gam-Apparel park (Viaduct 6km) J Kumar Infraprojects
Vastral Gam- Apparel park ( 6 station) DRA- CICO JV
East Ramp- Kalupur (Tunnels & 2 Station 2.45 km) Afcons Infrastructure.
Gyaspar-Shreyas (Viaduct & 4 stations 4.62km) IL & FS
Shreyas- Ranip (Viaduct & 6 station
Simplex Infrastructure
8.94km)
Motera-Ranip (viaduct- 4.85km)
Motera -Ranip ( 5 station Pratibha-Ranjit JV
Thaltej 9km to West Ramp. (viaduct,
Sabarmati Bridge & 7 stations 8.21 km) Tata- CCECC JV
17 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER. 2 SALIENT FEATURES
2.1 GENERAL:
This chapter describes detailinformation about the agencies involved & infrastructure
facilities provided.
RBL is a public incorporated company & has done many Infrastructure Projects.
18 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
Estimated cost of the work package 228 Cr
Time Frame of the Project 30 months
Date of commencement 12/1/2016
Date of completion as per current status 20/10/2020
2.4 LOCATION:
19 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.5 DETIALS OF THE AGENCIES INVOLVED:
20 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.7 ORGANIZATION CHART:
ELEMENT NUMBER
S.NO
1 Pile 747
3 Pier 173
5 Portal beam 23
7 Parapet 3060
8 Segment 1530
21 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.9 WORK BREAKDOWN STRUCTURE:
WATER SUPPLY:
There is under ground water tank at the casting yard and 1 bore. Also, there
is recycle water tank, where the recycled water at site is stored and later used
the same water for curing of the segments on the casting yard. On site, there
is a water tank of 3900litre, which is every filled up using the tanker water,
once in a day. The bore wells will be dug as per the requirement on site.
22 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
ELECTRICITY SUPPLY:
At casting yard, the electricity is generated using the GEB, and also have 1
Diesel Generator of 125KVA, whereas, on site they are using the Diesel
generator (3 nos.) and the power house of torrent for electricity is under
work.
LABOUR COLONY:
Labour Colony is situated at the casting behind the site office. Also, the
labour are provided transportation facilities to the site and back to the casting
yard.
LABOUR WELFARE:
At the casting yard, the canteen is provided for the staff and labours.
FIRST – AID:
The medical room is situated at the casting yard, where a doctor is available
24 hrs. Also, the provision of the ambulance is there for any emergency.
FIRE SAFETY:
The fire points are located at various locations on the site – At fabrication
yard, at the main store, near the project office, near the batching plant, at the
steel yard, near the transformer.
23 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.11 GRADE OF CONCRETE FOR VARIOUS ELEMENTS:
2.12.1 IN LABORTARY:
For various tests different lab equipment’s are used for performing various tests
on aggregates, on cement, on cubes etc., which are tabled below.
25 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.12.3 SHUTTER VIBRATOR
Vibrations:6000rpm
Centrifugal force max.: 14.23kN
Rated voltage 3.250V
LWH: 245150186mm
Standard centrifugal force: 8.22 kN
They are designed to easily transport to a site and use with different types of
load and cargo with little or no setup or assembly. It is used for handling and
placing shutter, barricading boards, etc. Other higher capacity crane is used for
lifting pile head and for other heavy lifting like pier cap reinforcement cage.
SPECIFICATIONS:
Fuel tank capacity: 45 liter
Boom: lifting angle- 2 deg. to 60 deg.
Telescoping: heavy duty, three-part box type hydraulically operated
Operating weight: 15315 kg
Overall dimension: 9725 mm length, 2450 mm width, 3215 mm height
Speed: maximum 40 kmph
Turning radius: 7.2 m
26 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 2. 7 MOBILE HYDRA
27 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
2.12.6 BAR BENDING MACHINE
Power: 3kW
Weight: 365kg
Electricity supply: 410Volts,50Hz
LWH: 810760860mm
Capacity:42mm
Power: 3kW
Weight: 510kg
Electricity supply: 410Volts,50Hz
Capacity:42Mm
29 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER. 3 PILE
3.1 GENERAL:
This chapter describes the important aspects & construction procedure of RCC
bored cast in-situ pile which includes layout work, Boring, Casing lowering,
Reinforcement Cage preparation and Cage lowering along with their IS Code
provision.
3.3 TERMINOLOGY:
BORED CAST IN-SITU PILE:
A pile is formed by boring a hole in the ground by percussion or rotary
method with the use of temporary or permanent casing or drilling mud &
subsequently filling the hole with the reinforced concrete.
CUT-OFF-LEVEL:
It is the level where a pile is cutoff to support the pile-cap or beams or any other
structural components at that level.
30 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
DIAMETER OF PILE:
Piles of 600mm or less in diameter are commonly known as small diameter
piles while piles greater than 600mm are called large diameter piles.
“Minimum pile diameter shall be 450mm” as per IS: 2911 (Part
1/Sec2:2010)
PILE SPACING:
The spacing of the piles means the center to center distance between the adjacent
piles.
MATERIAL SPECIFICATION
Cement PPC
Reinforcement (Fe 500D) 12,16,20,25,32mm TMT
Bars
Binding wire Galvanized iron
Polymer (POLYCOL 60 Eco-drill
LS)
Anti-corrosion agent Clean-flo
Sand Zone
Admixture BASF Glenium Sky
8583
Aggregate 10mm & 20mm
Grade of concrete M 35
TABLE 3. 2 MIX DESIGN
3.5 DESIGN:
31 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
3.6 EQUIPMENTS/MACHINERIES& TOOLS DETAILS:
32 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
3.6.2.2 SPIRAL AUGER:
Diameter:1.180m
One lift: 0.35m3 excavate
3.6.2.3 BUCKET AUGER:
3.6.2.4 HOPPER:
FIGURE 3. 3 HOPPER
33 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
3.6.2.5 CASING:
FIGURE 3. 4 CASING
1. Setting Out
3. Casing lowering
5. Tremie lowering
6. Concreteing
7. Removal of casing
34 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
3.8.1 PILE CONFIGURATION:
Center point of the piles are marked by the surveyor using total station with
the help of temporary benchmark.
Two points are marked by the surveyor at a distance of 2m from the center
of the pile (as shown in the figure 3.7 below) which serve as a reference to
check the accuracy of the pile after casing lowering.
35 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
BORING:
After 5m of boring is done M.S Liner is installed for the stability of soil.
Again a check is done from the marked reference point (as shown in figure
3.9).
Polymer is in the powder form & 5kg is mixed with 100lit of water.
The level of the polymer fluid in bore, shall be maintained 1.5m above the
bottom of the casing.
36 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
REINFORCEMENT CAGE LOWERING:
The cage is lapped with the other cage, welding is done & spirals are
provided in the lap region.
Similarly the whole cage is welded and lowered down as shown in figure
37 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 3. 7 CAGE LIFTING
38 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CONCRETING:
Tremie stand is placed for the installation of tremie pipe as shown in figure
3.13.
Number of tremie pipe are inserted as per the depth of bore and hopper is
kept at the top.
A sump is made nearby so that when concrete is poured into bore hole, the
polymer comes out and it can be recycled
39 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
3.10 BAR BENDING SCHEDULE:
Overhang of pile cap Clear overhang of the pile cap Provided overhang
beyond the outer most pile was 250mm.
0.250
shall be minimum of 150mm.
5.
41 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.4 PILE CAP
4.1 GENERAL:
This chapter describes the important aspects and construction of pile cap. The main
objective of constructing the pile cap is to distribute the load of pier to the
underlying piles. The entire process for the construction includes Excavation,
levelling & PCC, chipping of pile, straightening of pile reinforcement,
reinforcement cage preparation, shuttering work & concreting.
Pile Cap: It is a thick concrete mat that rest on the concrete or timber piles to provide a
suitable stable foundation.
Size: 6.6×6.6 m
Depth: 1.8 m
Grade: M35
42 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
4.4 GENERAL DETAIL OF PILE CAP:
1. Survey
2. Excavation
3. Levelling course
4. Chipping of piles
5. Reinforcement age
6. Shuttering
7. Concreting
8. Deshuttering
43 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
4.7 CONSTRUCTION METHODOLOGY:
SURVEY:
Before commencing the excavation, the pile cap layout shall be marked on the
ground with reference to the control points.
EXCAVATION:
The last 200mm excavation should be carried out manually levelling & course is to
be laid within 36 hours after completing excavation of last 200mm depth.
LEVELLING COURSE:
After levelling the bottom, the pit shall be watered to keep the soil moist.
PCC of M 20 mix shall be carried out of 100mm thickness.
Generally PCC was done 1m more than the size of pile cap to facilitate the erection
of formwork.
44 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHIPPPING OF PILES:
After the excavation the pile should be chipped to the cutoff level by using
Pneumatic jack hammer.
REINFORCEMENT CAGE:
Fabrication of the reinforcement shall be done as per the approved BBS in the Steel
Yard which includes cutting & bending of rebars.
Earthing bars of 25mm are provided throughout from pile cap to pier.
These bars are kept diagonally and are connected by earthing plate of 50×8mm.
45 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
SHUTTERING:
Shuttering oil shall be applies to ensure easy removal of formwork and for proper
finishing.
Steel plates are used as shutter plate, channels and U- Jack are also used to maintain
the shutter in its position.
46 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CONCRETING:
The concrete of approved design shall be transported from the batching plant to the
site by transit mixer.
Concrete slump should be checked before pouring & it should be 75mm to 100mm.
The concrete is placed directly by the chute from the transit mixer.
Concrete is vibrated using 60mm diameter needle vibrator.
Concrete cubes are casted for testing its compressive strength.
DESHUTTERING:
Hessian cloth shall be used for curing the sides of the pilecap which is kept wet by
sprinkling water.
47 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 4. 3 REINFORCEMENT DETAIL
48 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.5 PIER
5.1 GENERAL:
This chapter includes the construction aspect of Pier. The main objective of
constructing the pier is to support the elements above it. The entire process for the
construction reinforcement cage preparation, shuttering work & concreting.
49 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
5.3 PIER DETAIL:
50 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
5.5 WORK BREAK DOWN STRUCTURE:
1. Survey
2. Reinforcement
3. Casting of starter
4. Arrangement of mould
5. Concreting
6. Deshuttering
7. Curing
SURVEY:
The pier coordinates are transferred to the top of the footing using total station based
on the drawing provided.
The outer lines of the pier and the center shall be marked with the paint.
The placement of the main starter bars are checked properly, in terms of its quantity,
diameter, position and verticality.
REINFORCEMENT:
Vertical bars of the pier are already tied with the pile cap before concreting of the
pile cap and spacer bars areinserted.
51 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
After the construction of pile cap, temporary cup lock staging is provided for tying
the stirrups of pier.
The cutting and bending of the stirrups is done at the steel yard and then transported
to the site.
The stirrups are inserted from the top and tied from bottom to top according to the
spacing provided in the reinforcement schedule.
CASTING OF STARTER:
After, placing of the shutter, the alignment is checked, using the total station.
Then the verticality of the formwork is checked (should be in plumb, as it guides the
rest of the pier)
The starter height is up to 1000mm.
The surface shall be roughened, and then the surface shall be prepared as mentioned
above.
ARRANGEMENT OF MOULD:
52 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
First, one half of the bottom most form plate is lifted and placed above the marked
lineout.
Then the other half is placed and similarly above form plates are attached.
Then the staging tower on all four sides are placed and necessary bolting is provided.
CONCRETING:
Survey coordinates at the top of the pier are checked by the surveyor to confirm the
plumb.
Slump of the concrete should be 140 +/-20mm is checked using the slump cone and
12 cubes are filled for cube test.
Then the concreting is done from bottom to top and vibrating is done using needle
vibrators of 60mm from the top of the pier.
DE SHUTTERING:
First, the scaffolding is detached then the top most plates are removed using
a hydra crane and then the bottom plates are removed.
CURING:
After de shuttering, curing compound is sprinkled and jute bags are applied all over
the pier.
Water is sprinkled on the jute bags and curing is done for 14 days.
53 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 5. 1 REINFORCEMENT DETAIL OF PIER PILE
54 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.6 PARAPET
6.1 GENERAL:
According to the contract, precast parapets are provided above the span.
Parapets of 3 meter length are casted for the intermediate segments and that of
1.975 meter is casted for pier head segments, at the casting yard and then erected
on site using a launching girder.
Scope: 3060nos.
Type: type 1 & type 2
Grade: M30
Type II parapet is for pier segment whereas Type I is for Intermediate segment.
Grade of concrete M 30
w/c ratio 0.38
Cement 400kg
Water 152kg
20mm aggregate 683kg
10mm aggregate 455kg
Sand 823kg
Admixture (BASF Glenium Sky 3.2 kg
8583)
55 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
6.4 CONSTRUCTION METHODOLOGY:
REINFORCEMENT:
Cutting and Bending of bar is done simultaneously with the cage preparation.
56 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
ARRANGEMENT OF MOULD
The buffing of the mould is done and releasing agent is applied to it before laying
of reinforcement.
After the reinforcement cage is prepared the outer shutter is turned upwards and
locked.
The inner shutter plate is inserted with the help of hydra crane and necessary bolting
isdon
57 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
LIFTING OF CAGE
The prepared cage is staked nearby and is then lifted by using crane.
For lifting purpose one additional bar of 25mm diameter is tied with main bars.
CONCRETING:
Foam is applied at the corners to avoid the leakage of slurry.
Temperature is checked, slump test is done and total 5 nos. of cubes are filled for
cube test.
Concreting is done directly from the transit mixer into the mould with the help of
chute of transit mixer. Concreting is started and first concreting of the parapet
portion is done.
Then the concreting of the side connecting portion and the walk way is done.
DE SHUTTERING:
58 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FINISHING &CURING:
After the removal of mould proper finish is provided on the parapet wherever
required and if honeycombing has occurred at any place then that part is chipped
and finishing on it is done using repairing agent.
Curing of the parapets is done for 14 days from the date of casting.
Soon after the de shuttering, curing compound is applied on the surfaces.
STACKING
59 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 6. 4 PRECAST STACKING DETAILS FOR STANDARD SPAN
60 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.7 SEGMENT
7.1 GENERAL:
A Casting yard is a confined place where all concrete structure like segment,
parapets are casted, stacked cured for specific period and then shifted to working
site after they gain required strength.
Plot no: 44 casting yard near shree rang city, Chandkheda, Ahmedabad.
Area: 29725 m².
61 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
TABLE 7. 1 SEGMENT ID AND LENGTH
Span Segment I’ds
length S1U S2U S3U S4U S5U S6U S7C S6D S5D S4D S3D S2D S1D
37 m
34 m
31m
28 m
25 m
22 m
19 m
Here, ‘U’ denotes upward, ‘D’ denotes downward and ‘C’ denotes center
There are two batching plants at the casting yard, each of the capacity
30cu.m per hour, and 4 silos (2 silos for OPC and other 2 for PPC), for
storing of the cement.
The concrete produced using these batching plants, is only supplied for the
concreting of the other elements such as pile, pile-cap, pier, pier-cap, etc.
Permits reduction of construction time as the segment are casted in casting yard &
Superstructure work proceed simultaneously at the working site.
62 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
Better quality control is possible.
It contributes to aesthetically pleasing structure & good finishing.
The box girder superstructure for all the simply supported spans will be
constructed by precast prestressed segmental construction with bonded epoxy.
Other span comprises of 37,34,28,25 etc are made by adding or removing usual
segment of 3m from each span.
63 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
7.7 CONSTRUCTION METHODOLOGY:
MOULDS:
Each mould consist of major components like bulkhead, Outer shutter, Inner
shutter, Bottom carrier.
BUFFING:
Buffing is the operation used to remove the old and hardened concrete attached to
the formwork.
PUTTY:
After the buffing operation, putty is applied to fill the gap between the joints.
BOTTOM SHUTTERING:
Bottom shuttering is supported on steel table on the casting beds provided in the
transverse direction of casting.
Bottom shutters shall be fixed for all segments on longline casting bed except for
the pier segment which shall be cast on short bed.
64 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
SIDE SHUTTERING:
Side shuttering are mounted in the rail which are fixed during casting of the
segment by using jacks.
Each long line casting bed shall have two pairs of side shutters.
So that two intermediate segment can be casted simultaneously using matchcasting.
For pier segment along with the side shutter bulkhead are also required.
For intermediate segment having both the neighbouring segment casted, no
bulkhead ids required harden concrete itself act as a bulkhead.
For other segment having only one segment beside it, bulkhead is required on only
one side.
65 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
REINFORCEMENT CAGE:
When the buffing & oiling operation were going on cage fabrication work was also in
progress.
After putty application, the rebar cage was lifted by 10 ton gantry &coverblock are tied.
The cage is lifted & is transferred to the prepared formwork by rolling on the rails so
provided for the movement of gantry.
Before lowering the cage HDPE pipes are inserted if the segment is to be match casted.
Cutting and bending of TMT bar(Fe 500) is done in the steel yard, including the
application of inhibitor solution.
When the bars are ready, after bending, they are transported to the location of jig.
Firstly the web bars are placed on the jig as per the drawing & then soffit bars are placed.
Later on the deck bars & middle bars/ deviator block bars are placed.
All the bars are tied using binding wire of 18 gauge made from galvanized iron.
66 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
PROFILING:
Profiling is carried out, where the HDPE pipes are inserted with dummy inside it.
The dummy pipe is inserted in order to make sure that HDPE pipe inserted does not
deform from its original shape due to pressuere of concrete.
The coordinate so of these are marked using he measure tape, thread & chalk & then
10mm dia U shape bar is placed along with the tie bar then welding is done to fix in
position.
The profiling work is checked by GEC & after that inner trolley is inserted in all the
segments except S1.
All recesses will be covered with thermocol so that no slurry enter inside sheathin
67 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 7. 4 DETAIL OF CABLE OF SUPER STRUCTURE
68 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CONCRETING:
When the transit mixer (capacity 6m3) reaches the location, before unloading it to
the boom placer, the slump is again checked & 15 cubes are casted (5 cube for each
transit).
Then the concrete is pumped through the hose pipe to the soffit, followed by wed &
then deck.
DESHUTTERING:
Curing is done by sprinkling water through pipe on the side surface while for the
deck portion ponding is done & sprinkler system is provided.
LIFTING OF SEGMENT:
70 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
7.8 MIX DESIGN:
TABLE 7. 2 MIX DESIGN
COARSE COARSE
FINE WATE
CEMENT W/C AGGREGA AGGREGAT ADMIXTUR
AGGREGAT R
(kg/m3) RATIO TE 20mm E 10mm 3) E (kg/m3) 3)
E (kg/m (kg/m
(kg/m3) (kg/m3)
440 0.3 628 493 846 3.96 130
7.9 VOLUME OF CONCRETE IN SEGMENT:
71 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
7.11 BAR BENDING SCHEDULE:
72 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
FIGURE 7. 6 BAR BINDING SCHEDULE
73 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.8 QUALITY ASSURENCE AND CONTROL
8.1 GENERAL:
8.2 AGGREGATE:
APPARATUS:
Sieve (40mm, 20mm, 16mm, 12.5mm, 10mm, 4.75mm, 2.36mm,
1.18mm, 0.6mm, 0.3mm, 0.15mm and 0.075mm).
Balance (L.C. - 0.1 g) Sieve shaker
PROCEDURE:
Take the sieve & arrange them in decreasing order with the largest sieve on top.
If mechanical sieve shaker is used then put the ordered sieve in position & pour the
sample in the top sieve & close it with the lid.
Switch on the machine & shaking of sieve should be done for at least 5 minutes.
74 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
OBSERVATION TABLE AND CALCULATION:
SAND:
TABLE 8. 1 RESULT OF SAND
75 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
20mm AGGREGATE:
DISCUSSION:
The passing of 20 & 10 mm aggregate falls in limits of zone 2 that’s why they are
termed as Zone 2 aggregate.
For the coarse aggregate grading of aggregate are done for the determination of
particle size distribution of aggregate.
76 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.9 SAFETY PROGRAMME
9.1 PURPOSE:
The purpose of this EHS Plan is to ensure that all employees of RBL are
safeguarded, as far as is reasonably practicable, from potential hazards in the
performance of their duties and all practicable measures are taken to safeguard the
environment. RBL will undertake the project of Ahmedabad Metro and will be
dedicated to making improvements in safety, health and welfare standards as well
as being determined to maintain good environmental controls during every activity
and at all-time RBL requires employees, at all levels, to support and strictly
implement the EHS Policy to which end this plan is site-specific guidance to aid in
achieving the set objectives and targets.
9.2 OBJECTIVES:
The core objectives, from the RBL. EHS Policy, when completing any task are to:
Integrating EHS plan and procedure into every operation of the independent
company.
Achieving an incident free work places and offices through proactive capturing and
corrective of maximum number of UA/UB/UC, near miss and first-aid cases
subsequent reduction of severity rate, frequency & Fatality rates.
All people working for RBL will be provided with necessary personnel protective
equipment’s such as helmet, safety shoes, and fluorescent jacket for all workforces,
The supervisor, of the worker requiring it, must provide additional job specific PPE
like nose mask, hand gloves, goggles, face shield, ear plug, full body double lanyard
harness, etc. In turn the employee must maintain and use the correct PPE that is
provided to him. It is the responsibility of the site staff to ensure adequate supply of
PPE for the number of workers at site.
The Supervisors, with the assistance of the EHS section, must check that all
personnel are in compliance with Policies, Procedures, Plans and relevant
regulations during all work/operations and tasks.
78 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
9.4 HEALTH MANAGEMENT AND MEDICAL FACILITY:
RBL will medically examine all staff as well as workers before employment to get
base data line of employee’s physical fitness. RBL also periodically check medical
fitness of employees in special cases RBL can conduct medical camp as per
situation / demand / requirement. Project site and Labour Colony will be visited by
a qualified and experienced Doctor once a Month. Minimum required First Aid
Boxes will be provided at convenient location.
79 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )
CHAPTER.10 CONCULUSION
It was a profound fact that knowledge & experience both governs the ability of a
person to carry out a particular task. Some aspects of construction which are not
known at undergraduate level was learnt as a part of major project in semester.VII
Inspite of the activities are of repetitive nature but every time it has some different
problem to get solved. It was a profound fact that knowledge & experience both
governs the ability of a person to carry out a particular task. Some aspects of
construction it has some different problem to get solved.
80 | C A S E S T U D Y O F A H M E D A B A D M E T R O R A I L P R O J E C T ( M E G A )