53-09 Trig Calculations

Although this is a fairly simple project, it is also a very typical example of calculating contour change points. The
objective of this project is to calculate all XY contour points on the part only, along the contour, back to the start
point. Program itself is not required, only the calculations.

ò To complete the project, follow these conditions:

1. Start at the lower left corner of the part = X0Y0

2. Calculate all points in the order required for climb milling (external machining)

3. Provide all calculations in the exact order of development

4. Provide the list of final coordinates to be used in the program


(include any auxiliary points, if applicable)

0.75

R1.125
28°

2.1
0.25

1.1

3.375

Peter Smid CNC Programming Handbook 53-09 [ 1 ]