Sie sind auf Seite 1von 9

Today we will see how to prepare rate analysis for Reinforced Concrete (RCC) work.

First step to rate analysis is the estimation of labour, materials, equipments and
miscellaneous items for particular quantity of reinforced concrete.

The second step is to determine the component of structure for which the RCC rate
analysis is required, as the quantity of reinforcement steel varies with slabs, beams,
columns, foundation, RCC Roads etc., though the quantity of other materials like
sand, coarse aggregate and cement remain the same with the same mix design (mix
proportion) of concrete.

Labour rates for reinforcement work changes with type of structural component as
the quantity of reinforcement steel changes. The Quantity of materials like sand,
cement and coarse aggregates vary with mix design such as M15 (1:2:4), M20
(1:1.5:3), M25, M30 etc..

Here we will see the rate analysis for 1m3 of reinforced concrete.
Data required for RCC Rate Analysis:
1. Estimation of materials:
Material estimation include sand, cement, coarse aggregate and steel for a particular
mix design. Let us consider a mix design of 1:1.5:3 for our estimation practice. The
dry volume of total materials required is considered as 1.54 times the wet volume of
concrete, due to voids present in sand and aggregates in dry stage. Therefore, for
our calculation, we will consider the total volume of materials required as 1.54 m 3
for 1 m3 of wet concrete.
a) Bags of cement required:
Volume of cement required for 1m3 of Concrete =

=0.28 m3
Then number of bags of cement (volume of one bag of cement = 0.0347 m 3)

= = 8.07 bags of cement.

b) Volume of Sand required:

Volume of sand required = = 0.42 m3 of sand.


c) Volume of Coarse Aggregate Required
Volume of Coarse Aggregate = = 0.84 m3 of coarse aggregates.
d) Estimation of Reinforced Steel:
Quantity of steel required depends on components of structure, i.e. slabs, beams,
columns, foundations, roads etc. To estimate the steel required, there are two
methods.

First method is, when we have the drawing available, we can calculate the total
weight of steel required divided by total volume of concrete for different
components. This will give us the weight of reinforcement steel per cubic meter of
concrete.

Second method is assuming the percentage of reinforcement for different


components. Following are the percentage of reinforcement steel generally required
per different components. Its values can vary from structure to structure, and can be
assumed from past experiences of similar structure.

 For slabs = 1.0 % of concrete volume.

 For Beam = 2 % concrete volume.

 For column = 2.5 % of concrete volume.

 For RCC Roads, 0.6% concrete volume.


Lets take example of RCC Column, where reinforcement required is 2.5% of concrete
volume, weight of steel required will be:

=196.25 kg.

2. Labour Requirement for 1m3 of RCC:


Labours required are presented in terms of days required by particular labour to
complete its work for the given quantity of concrete. Following are the various
labours required:

a) Mason: As per Standard Schedule of Rates and Analysis of Rates, One mason is
required for 0.37 days.

b) Labours: One Unskilled labours required for 3.5 days.

c) Water carrier: One water carrier required for 1.39 days.

d) Bar Bender: Bar bender requirement depends on weight of reinforcement. Lets


consider one bar bender required for 100 kg of steel as for 1 day.

e) Mixer Operator: One mixer operator required for 0.0714 days.

f) Vibrator Operator: One vibrator operator required for 0.0714 days.

3. Equipments and sundries:


Equipment and other charges, such as water charges, miscellaneous items, tools and
tackles etc can be assumed as some percentage of total cost of materials and
labours. Lets say it as 7.5%.

4. Contractor’s Profit:
Contractor’s profit depends on place to place, organization to organization and work
to work. It varies from 10 – 20%. For our case lets assume it as 15% of total cost of
materials, labours and equipments.

We have calculated the quantity of every item in above 1 – 3 steps. For rate analysis
of RCC, we need to multiply each quantity with their rates to get the amount for
every item of work. Rates vary from place to place and time to time. It is advisable to
assume local rates or standard rates of the place.
The sum total of all the four items above will give the rate or cost for 1m 3 of
concrete.

- Price per meter of reinforced concrete jacking pipes, reinforced concrete pipes & reinforced concrete
manhole (different diameters)

1000 MM ND NP4 Rs/ m 6500 to 9850 Jacking Pipe (2 m length with rings and gasket) Rs 20000

- Gross profit margins of the industry and of each type of reinforced concrete pipes 15 to 20%

- Utilization rate of a plant

Break even :33% Optimum average 50 to 55% Best scenario : 75-80%

- Main players in Qatar from a supply side & demand side (we will also need a view on the different
external factors that impacts the demand and a forward looking view on the demand)

- Cost structure of the industry

- A forward looking view on GRP (demand, supply)

Please note that they are mainly interested in the reinforced concrete pipes market in Qatar – in
terms in products, this should cover Reinforced Concrete Pipes (RCP), Reinforced Concrete
Jacking Pipes (RCJP), and Reinforced Concrete Manhole (RCM)

17.18 Providing at site, lowering & laying in trenches, aligning & jointing of RCC pipes NP4 class (with s/s
ends) IS: 458 - 2003 (amended up to date) marked and pipes from 300 mm and upto 1800 mm
manufactured through vertical casting process at all depths with Rubber gaskets (EPDM/SBR) for sewer
lines as per IS: 5382 (including cost of Rubber gaskets, lubricants) as per drawing, sectional hydro testing
of the sewer pipe line (including cost and conveyance of water to site for testing) etc., complete as per
specification and / or as directed by Engineer.

Note : E/w to be measured and paid separately


17.18.1 150 mm internal diameter metre 438.00
17.18.2 200 mm internal diameter metre 562.00
17.18.3 250 mm internal diameter metre 804.00
17.18.4 300 mm internal diameter metre 1060.00
17.18.5 350 mm internal diameter metre 1630.00
17.18.6 400 mm internal diameter metre 1860.00
17.18.7 450 mm internal diameter metre 2290.00
17.18.8 500 mm internal diameter metre 2630.00
17.18.9 600 mm internal diameter metre 3550.00
17.18.10 700 mm internal diameter metre 4430.00
17.18.11 800 mm internal diameter metre 4870.00
17.18.12 900 mm internal diameter metre 5900.00
17.18.13 1000 mm internal diameter metre 6680.00
17.18.14 1100 mm internal diameter metre 7920.00

RUIDP 66 SOR 2017

Code No
Description Unit Rate Rs.
17.18.15 1200 mm internal diameter metre 10700.00
17.18.16 1400 mm internal diameter metre 13400.00
17.18.17 1600 mm internal diameter metre 16800.00
17.18.18 1800 mm internal diameter metre 22000.00
17.18.19 2000 mm internal diameter metre 29200.00
17.19 Providing at site, lowering & laying in trenches, aligning & jointing of RCC pipes NP3 class (with s/s
ends) IS: 458 - 1988 (amended up to date) marked and pipes from 300 mm upto 2000 mm manufactured
through vertical casting process all levels with Rubber gaskets (EPDM/SBR) for sewer lines as per IS: 5382
(including cost of Rubber gaskets lubricants) as per drawing, sectional hydro testing of the sewer pipe line
(including cost and conveyance of water to site for testing) etc., complete as directed by Engineer.
Note : E/w to be measured and paid separately
17.19.1 150 mm internal diameter metre 417.00
17.19.2 200 mm internal diameter metre 521.00
17.19.3 250 mm internal diameter metre 732.00
17.19.4 300 mm internal diameter metre 1010.00
17.19.5 350 mm internal diameter metre 1510.00
17.19.6 400 mm internal diameter metre 1740.00
17.19.7 450 mm internal diameter metre 2120.00
17.19.8 500 mm internal diameter metre 2530.00
17.19.9 600 mm internal diameter metre 3230.00
17.19.10 700 mm internal diameter metre 3990.00
17.19.11 800 mm internal diameter metre 4550.00
17.19.12 900 mm internal diameter metre 5370.00
17.19.13 1000 mm internal diameter metre 6270.00
17.19.14 1100 mm internal diameter metre 7370.00
17.19.15 1200 mm internal diameter metre 9160.00
17.19.16 1400 mm internal diameter metre 11400.00
17.19.17 1600 mm internal diameter metre 14300.00
17.19.18 1800 mm internal diameter metre 18900.00
17.19.19 2000 mm internal diameter metre 24700.00
17.20 Providing at site, lowering & laying in trenches, aligning & jointing of RCC pipes NP2 class (with s/s
ends IS: 458 - 1988 (amended up to date) marked and manufactured through spun process at all levels
with Rubber gaskets (EPDM/SBR) for sewer lines as per IS: 5382 (including cost of Rubber gaskets
lubricants) as per drawing, sectional hydro testing of the sewer pipe line (including cost and conveyance
of water to site for testing) etc., complete as directed by Engineer.
Note : E/w to be measured and paid separately
RUIDP 67 SOR 2017

Code No
Description Unit Rate Rs.
17.20.1 150 mm internal diameter metre 394.00
17.20.2 200 mm internal diameter metre 503.00
17.20.3 250 mm internal diameter metre 584.00
17.20.4 300 mm internal diameter metre 713.00
17.20.5 350 mm internal diameter metre 859.00
17.20.6 400 mm internal diameter metre 1010.00
17.20.7 450 mm internal diameter metre 1160.00
17.20.8 500 mm internal diameter metre 1490.00
17.20.9 600 mm internal diameter metre 1870.00
17.20.10 700 mm internal diameter metre 2240.00
17.20.11 800 mm internal diameter metre 2680.00
17.20.12 900 mm internal diameter metre 3480.00
17.20.13 1000 mm internal diameter metre 4030.00
17.20.14 1100 mm internal diameter metre 5060.00
17.20.15 1200 mm internal diameter metre 5880.00
17.20.16 1400 mm internal diameter metre 6750.00
17.20.17 1600 mm internal diameter metre 8200.00
17.20.18 1800 mm internal diameter metre 10100.00
17.20.19 2000 mm internal diameter metre 11400.00
17.21 Add extra for manufacturing of RCC pipe with Sulphate Resistant Cement instead of OPC/PPC
cement
17.21.1 NP2 Pipes
17.21.1.1 150 mm internal diameter metre 7.50
17.21.1.2 200 mm internal diameter metre 9.50
17.21.1.3 250 mm internal diameter metre 12.00
17.21.1.4 300 mm internal diameter metre 17.00
17.21.1.5 350 mm internal diameter metre 21.00
17.21.1.6 400 mm internal diameter metre 23.50
17.21.1.7 450 mm internal diameter metre 29.00
17.21.1.8 500 mm internal diameter metre 32.00
17.21.1.9 600 mm internal diameter metre 49.50
17.21.1.10 700 mm internal diameter metre 64.00
17.21.1.11 800 mm internal diameter metre 72.50
17.21.1.12 900 mm internal diameter metre 90.00
17.21.1.13 1000 mm internal diameter metre 109.00
17.21.1.14 1100 mm internal diameter metre 129.00
17.21.1.15 1200 mm internal diameter metre 152.00
17.21.1.16 1400 mm internal diameter metre 189.00
RUIDP 68 SOR 2017

Code No
Description Unit Rate Rs.
17.21.1.17 1600 mm internal diameter metre 230.00
17.21.1.18 1800 mm internal diameter metre 291.00
17.21.1.19 2000 mm internal diameter metre 359.00
17.21.2 NP3 and NP4 Pipes
17.21.2.1 150 mm internal diameter metre 7.50
17.21.2.2 200 mm internal diameter metre 12.00
17.21.2.3 250 mm internal diameter metre 14.50
17.21.2.4 300 mm internal diameter metre 23.50
17.21.2.5 350 mm internal diameter metre 54.50
17.21.2.6 400 mm internal diameter metre 61.00
17.21.2.7 450 mm internal diameter metre 67.50
17.21.2.8 500 mm internal diameter metre 73.50
17.21.2.9 600 mm internal diameter metre 99.50
17.21.2.10 700 mm internal diameter metre 114.00
17.21.2.11 800 mm internal diameter metre 145.00
17.21.2.12 900 mm internal diameter metre 171.00
17.21.2.13 1000 mm internal diameter metre 219.00
17.21.2.14 1100 mm internal diameter metre 239.00
17.21.2.15 1200 mm internal diameter metre 271.00
17.21.2.16 1400 mm internal diameter metre 354.00
17.21.2.17 1600 mm internal diameter metre 416.00
17.21.2.18 1800 mm internal diameter metre 500.00
17.21.2.19 2000 mm internal diameter metre 631.00
17.22 Extra for providing 2.5mm thick HDPE Lining inside RCC pipe (while casting of pipe) as required.
17.22.1 600 mm internal diameter metre 680.00
17.22.2 700 mm internal diameter metre 794.00
17.22.3 800 mm internal diameter metre 795.00
17.22.4 900 mm internal diameter metre 1020.00
17.22.5 1000 mm internal diameter metre 1130.00
17.22.6 1100 mm internal diameter metre 1250.00
17.22.7 1200 mm internal diameter metre 1360.00
17.22.8 1400 mm internal diameter metre 1590.00
17.22.9 1600 mm internal diameter metre 1810.00
17.22.10 1800 mm internal diameter metre 2040.00
17.22.11 2000 mm internal diameter metre 2270.00

17.79 Providing, laying and jointing RCC NP4 pipe with cement mortar joints by trenchless method
adopting any suitable technology below ground at required depth under running traffic condition as per
the direction of NHAI including carrying out survey work at the job site for determining underground cable
trenches like telephone, power cable, water & sanitary lines and resistivity tests for finding the soil strata
using necessary equipments for completion of work, mobilizing of machineries and specialized crew at
the job site, etc. complete in all respects, including excavation of drive pit and exit pit (upto 3 metre
depth) with proper protection at the three sides, providing and casting of MS cutting edges for front shield
and constructing thrust bed at designed level as directed by the Engineer, necessary de-watering and
providing concrete foundations at the base of the Drive pit, crane for handling of pipes, and any other
machinery, tool & tackels required, construction of temporary works as per requirement and as approved
by NH authorities complete in all respect for the road crossing at necessary depth (all depths) with all lead
and lifts, as per specification and the direction of the Engineer.
17.79.1 In all type of soils
17.79.1.1 600 mm dia RCC pipe metre 18200.00
17.79.1.2 700 mm dia RCC pipe metre 19100.00
17.79.1.3 800 mm dia RCC pipe metre 22800.00

RUIDP 93 SOR 2017

Code No
Description Unit Rate Rs.
17.79.1.4 900 mm dia RCC pipe metre 23800.00
17.79.1.5 1000 mm dia RCC pipe metre 24600.00
17.79.1.6 1100 mm dia RCC pipe metre 27600.00
17.79.1.7 1200 mm dia RCC pipe metre 30400.00
17.79.1.8 1400 mm dia RCC pipe metre 36100.00
17.79.1.9 1600 mm dia RCC pipe metre 39600.00
17.79.1.10 1800 mm dia RCC pipe metre 48700.00
17.79.2 In Rock
17.79.2.1 600 mm dia RCC pipe metre 49200.00
17.79.2.2 700 mm dia RCC pipe metre 50100.00
17.79.2.3 800 mm dia RCC pipe metre 60000.00
17.79.2.4 900 mm dia RCC pipe metre 61000.00
17.79.2.5 1000 mm dia RCC pipe metre 61800.00
17.79.2.6 1100 mm dia RCC pipe metre 72300.00
17.79.2.7 1200 mm dia RCC pipe metre 75100.00
17.79.2.8 1400 mm dia RCC pipe metre 87700.00
17.79.2.9 1600 mm dia RCC pipe metre 91300.00
17.79.2.10 1800 mm dia RCC pipe metre 107600

N DIA PRESSURE PRICE MIN PRICE MAX PR CLASS PRICE MIN PRICE MAX
CLASS NP 4
150 330 350
200 416 450
250 585 650
300 810 850
350 1210 1300
400 1400 1490
450 1700 1830
500 2025 2100
600 2590 2840 7280
700 3200 3550 7610
800 3640 3900 9120
900 4300 4720 9520
1000 5016 5350 9840
1100 5900 8560 11040
1200 7328 10720 12160
1400 9120 17600 20000
1600 11440 23360 25000
1800 15120 31500 33000
2000 19760

Das könnte Ihnen auch gefallen