Sie sind auf Seite 1von 94

ESTIMATE MANUAL

TABLE OF CONTENTS

ACTIVITY LIST FOR HIGHWAYS & BUILDINGS


Group 100 - Roadside and related features ----------
Group 200 - Roadside features ----------
Group 300 - Traffic services ----------
Group 400 - Emergency works ----------
Group 500 - Supervision, support & overhead ----------

STANDARD SPECIFICATIONS FOR HIGHWAYS & BRIDGES


Part 1 - Earthwork ----------
Part 2 - Base course ----------
Part 3 - Surface course & pavements ----------
Part 4 - Structures ----------
Part 5 - Incidental construction ----------

ESTIMATING PROCEDURES FOR :


1. Batterboard ----------
2. Excavation ----------
3. Backfill ----------
4. Concrete ----------
5. Ratio of mixture ----------
6. Mortar mixture ----------
7. Curve & gutter ----------
8. Asphalt pavement ----------
9. Concrete pavement ----------
10. Base course ----------
11. Sub - grade ----------
12. Grouted riprap ----------
13. Adobe stone ----------
14. Adobe buttress ----------
15. Mortar for adobe stone ----------
16. Cement and sand factor per concrete pipe joint collar ----------
17. CHB concrete footing per meter ----------
18. Concrete hollow blocks ----------
19. Labor output per team ----------
20. Plastering ----------
21. Cement tiles ----------

1 of 47
ESTIMATE MANUAL

22. Grouting compound ----------


23. Scaffolding ----------
24. Form works ----------
25. Floor joist ----------
26. Wooden studs & sidings ----------
27. Wooden flooring ----------
28. Double walling ----------
29. Double wall partition ----------
30. Ceiling joist ----------
31. Baseboard ----------
32. Ceiling board ----------
33. Aluminum tee runner ----------
34. Facia board ----------
35. Wooden trusses & rafters ----------
36. Purlins ----------
37. Roofing ----------
37.c.1. Pitch fcator of truss & rafter ----------
37.g.1.a. Table of coverage ( G. I. sheet ) ----------
37.g.1.b. Table of coverage ----------
37.g.2. Table of fasteners ----------
37.g.3. Table of rivet per sheet of roofing ----------
37.g.4. Table of strap per plain G. I. sheet ----------

SPREADING RATES OF PAINTS


1. Oil paint ----------
2. Oil paint flat ----------
3. Enamel paint ----------
4. Exterior spur varnish ----------
5. Interior spur varnish ----------
6. Shellac ----------
7. Single satin finish ----------
8. Asphalt rough finish ----------
9. Water paint ----------

RATE OF APPLICATION ( TILES ) ----------


NAILS CONVERSION FACTORS ----------
STANDARD REINFORCEMENT OF WALLS ----------
DOOR JAMBS WITHOUT TRANSOM ----------

2 of 47
ESTIMATE MANUAL

DOOR JAMBS WITH TRANSOM ----------


FLUSH DOOR FRAME ----------
HOUR RATE PER ITEM OF WORK ----------
UNIT RATE PER ITEM OF WORK ----------
LABOR OUTPUT PER MAN-DAY ----------
LABOR CAPABILITY PER HOUR ----------
FLAT BAR IN KILOS ----------
WEIGHT OF BOLTS IN KILOS ----------
INCH TO MILLIMETER CONVERSION TABLE ----------
BOLTS REQUIRED FOR TRUSSES ----------
TABLE OF VALUES FOR STRENGTH OF CONCRETE ----------
REBAR CONVERSION TABLE ----------
TIEWIRE FORMULA ----------
DECORS ----------
CHANNELS ----------
ANGLES ----------
UNEQUAL ANGLES ----------
CARPENTRY WORKS ----------
CEILING PARTITION & FORMWORKS ----------
LIGHT & HEAVY EQUIPMENT CAPABILTY TABLE ----------

HEAVY & LIGHT EQUIPMENT FOR :


1. Clearing & grubbing ----------
2. Drainage ditche ----------
3. Excavation ----------
4. Embankment ----------
5. Base course construction ----------
6. Surface treatment ----------
7. Aggregate production ----------
8. Subgrade preparation ----------
9. Base course construction ----------
10. Capabilities of manual labor ----------

TABLE I - POL CONSUMPTION OF ORDINANCE EQUIP. ----------


TABLE II - POL CONSUMPTION OF ENGINEERING EQUIP. ----------

3 of 47
ESTIMATE MANUAL

ACTIVITY LIST FOR HIGHWAYS & BUILDINGS

GROUP 100 - ROAD & RELATED FEATURES

Unpaved Road Surfaces


101 Manual repair of unpaved road surfaces ----------
102 Manual patching of unpaved soad surfaces ----------
103 Machine patching of unpaved road surfaces ----------
104 Machine grading unpaved road surfaces ----------

Bituminou Pavements
111 Premix patching bituminous pavments ----------
112 Penetration patching bituminous pavements ----------
113 Sealing bituminous pavements ----------
114 Replacement of bituminous pavements ----------

Concrete Pavements
121 Patching concrete pavaments ----------
122 Crack & joint sealing of concrete pavements ----------
123 Replacement of concrete pavements ----------

Unpaved Shoulder
131 Manual repair of unpaved shoulder ----------
132 Manual patching unpaved shoulder ----------
133 Machine grading unpaved shoulder ----------

Drainage
141 Manual ditch cleaning ----------
142 Manual inlet/outlet cleaning ----------
143 Culvert line cleaning ----------
144 Repair / replacement of minor drainage structures ----------

Bridges
151 Cleaning bridges ----------
152 Patching concrete decks ----------
153 Repair to concrete bridges ----------
154 Repair to steel bridges ----------
155 Repair to bailey bridges ----------

4 of 47
ESTIMATE MANUAL

156 Repair to tomber bridges ----------


157 Cleaning bridge waterways ----------

Ferries
161 Ferry service ----------

Temporary Repairs
171 Temporary patching ----------

Other Maintenance and Repairs


181 Other maintenance to roadway & related feature ----------

GROUP 200 - ROADSIDE FEATURES

201 Vegetation control ----------


202 Erosion repair & control on roadside ----------
203 Repair to major roadside structures ----------
204 Other roadside maintenance ----------

GROUP 300 - TRAFFIC SERVICES

301 Sign maintenance ----------


302 Centerline & lane line repainting ----------
303 Guardrail maintenance ----------
304 Sight distnace mowing & clearing ----------
305 Other traffic services ----------

GROUP 400 - EMERGENCY WORKS

401 Initial response to emergency roadways ----------


402 Initial response to emergency bridges ----------
403 Emergency projects ----------

GROUP 500 - SUPERVISION, SUPPORT & OVERHEAD

501 Production of bituminous pavements ----------


502 Other material production & hnadling ----------

5 of 47
ESTIMATE MANUAL

503 Idirect cost of work or expenses ----------


504 Other work or expenses ----------
505 Foreman supervision ----------
506 Unproductive time ----------

STANDARD SPECIFICATIONS FOR HIGHWAYS & BRIDGES

CONSTRUCTION DETAILS

Part I - Earthwork Unit of M


100 Clearing & grubbing ----------
101 Selective removal of trees ----------
102 Stripping ----------
103 Removal of bridges,culverts & siphons ----------
104 Removal of miscellaneous structures ----------
105 Roadway & drainage excavation ----------
106 Excavation for structures ----------
107 Borrow ----------
108 Selected borrow (aggregate sub-base) ----------
109 Embankments ----------
110 Foundation fill ----------
111 Overhaul ----------
112 Borrow haul ----------
113 Subgrade
114 Rolling ----------
115 Watering ----------
116 Shoulders ----------
117 Finishing earth graded roads ----------
118 Preparation of previously constructed road ----------
119 Protection ditches
120 Spot subgrade reinforcement

Part 2 - Base Coarse


200 Selected borrow base course (agg. base course) ----------
201 Gravel, crushed gravel or crushed stone base course ----------
202 Sledged stone base course ----------
203 Bituminous macadam base base course ----------

6 of 47
ESTIMATE MANUAL

204 Bituminous plant mix base course ----------

Part 3 - Surface Coarse and Pavements


300 Field laboratory ----------
301 Asphaltic materials ----------
302 Bituminous prime coat ----------
303 Bituminous tack coat ----------
304 Bituminous surface treatment ( emulsified asphalt type ) ----------
305 Bituminous seal coat
306 Bituminous macadam pavement ( hot asph. type ) ----------
307 Bituminous macadam pavement ( emulsified asphalt type ) ----------
308 Dense graded plant - mix surface course ( emulsified asphalt type ) ----------
309 Open-graded plant - mix surface course ----------
310 Bituminous concrete surface course ----------
311 Bituminous preservative treatment ----------
312 Dense graded travel plant - mix surface course ----------
313 Rock asphalt ----------
314 Bituminous surface treatment ( H. A. T. ) ----------
315 Drag broom ----------
316 Portland cement concrete pavement ----------
317 Rock asphalt binder course ----------

Part 4 - Structures
400 Steel bridges ----------
401 Timber detour span ----------
402 Piling ----------
403 Concrete railing ---------- l.m. along C.L. '----------
404 Paints or painting
405 Concrete ----------
406 Reinforcing steel ----------
407 Structural steel ----------
408 Welding structural steel
409 Sheet files ----------
410 Treated & untreated timber ----------
411 Timber structures
412 Stone masonry ----------

Part 5 - Iincidental Construction

7 of 47
ESTIMATE MANUAL

500 Riprap & grouted riprap ----------


501 Hand - laid rock embankment ----------
502 Combination concrete curve & gutter ----------
503 Concrete sidewalk ----------
504 Bituminous sidewalk ----------
505 Reinforced concrete pipe culvert ----------
506 Catch basin, manholes & inlets ----------
507 Wood guardrail ----------
508 Traffic line lacquer ----------
509 Underdrains ----------

ESTIMATING PROCEDURE FOR :

1. BATTERBOARD
a. To estimate batterboard, first compute the area of the structure in sq.m. multiply the
4.85 bd.ft. for 2" x 2" lumber, 7.28 bd.ft. for 2" x 3" lumber. Then the total bd.ft. divi
2 will give you the bd.ft. of lumber to be used as batterboard.
b. The second procedure is to compute the lineal meter of the structure location giving an
wance or margin of 1.00 all around. Count also the no. of stake to be used. No. of stake
ply by 1.20 ( length of stake ) to get total lineal meter. Add all the ilneal meter & chang
neal foot. Compute the bd.ft. by using 2" x 2" or 2" x 3" lumber.
c. For nails : divide the total bd.ft. by 1,000 then multiply by 15 to get kilos required.
: divide the total bd.ft. by 2,500.
d. For # 12 guide wire to be used as guide in layout, divide the total bd.ft. by 4,000 to ob
roll of wire.

Batterboard
Stake

Guide

2. EXCAVATION
a. To estimate volume of excavation, compute the area to be excavated then multiply by

8 of 47
ESTIMATE MANUAL

depth
b. For cut and fill, use the Prismoidal Formula (A1 + A2)/2 x depth or length.

3. BACKFILL
a. For backfilling, use the same procedure as of the excavation no. 1, by multiply the len
width & depth. If the backfill will be compacted add 15% for compaction.

4. CONCRETE
a. To estimate volume or cu.m. of concrete, use the same procedure in computing excav
& backfilling.
b. To obtain bag of cement, sand and gravel, determine first the psi or class of mixture.

5. RATIO OF MIXTURES
Class AAA 1:1:2 4,5
Cement
Sand
Gravel
Class AA 1 : 1½ : 3 3,5
Cement
Sand
Gravel
Class A 1:2:4 3
Cement
Sand
Gravel
Class B 1 : 2½ : 5 2
Cement
Sand
Gravel
Class C 1:3:6 2
Cement
Sand
Gravel
Class D 1 : 3½ : 7 1
Cement
Sand
Gravel

9 of 47
ESTIMATE MANUAL

6. MORTAR MIXTURE
Class AA 1:1
Cement
Sand
Class A 1:2
Cement
Sand
Class B 1:3
Cement
Sand
Class C 1:4
Cement
Sand
Class D 1:5
Cement
Sand

7. CURVE & GUTTER


a. To estimate curve and gutter : lm x 0.74 cu.m. = total cu.m.
b. To obtain form lumber : lm x 8.50 bd.ft. = total bd. ft.
c. To obtain cement, sand , gravel : determine the mixture to be used & multiply the
by the corresponding factor of mixture.

8. ASPHALT PAVEMENT
a. To obtain asphalt for 2" thk. Asphalting : 1 metric ton of asphalt coverage of 8.75 s
for prime coating (liquid) : total sq.m. divided by 400 = no. of drums or 1 gal. Asp
coverage of 64.0 sq.ft. or 6.00 sq.m..

9. CONCRETE PAVEMENT
a. To obtain bag of cement for 8" thk. pavement : total cu.m. x 8.50 = bags, or total
x 1.90 = bags. for sand : total cu.m. x 0.47 = cu.m. of sand. for gravel : tota
x 0.94 = cu.m. of gravel. for water : cu.m. x 66.40 = gal. of water.

10. BASE COURSE


a. To obtain base coarse for 6.00 m. wide x 0.20 road : Compacted = for every km. u
1,200 cu.m. base course.
In-place-(Quarried) = for every km.use 1260 cu.m.
Loose (hauled) use 1400 cu.m.

10 of 47
ESTIMATE MANUAL

11. SUB GRADE


a. To obtain subgrade or road bed for 9.00 x 0.15 road using common borrow
Compacted = for every km. use 1350 cu.m.
In-place (Quarried) = for every km. use 1500 cu.m.
Loose (Hauled) = for every km. use 2010 cu.m.

12. GROUTED RIPRAP


a. To estimate riprap grouting : total volume of riprap x 0.15 or 0.30 = volume of co
To obtain cement : vol. x factor, same as to sand : area x 0.425 = cement, area
= sand in cu.m..
b. To obtain volume of riprap : area x depth = volume of riprap.

13. ADOBE STONE


a. To estimate adobe : 0.15 x 0.15 x 0.45 : total area x 15 pcs. for cross footing, ar
pcs for stairs, cu.m. x 90 pcs. for mortar of 1 cm. thk. Wall factor : 0.0009, f
footing factor : 0.000675, for stairs factor : 0.001575.
b. To obtain cement and sand, multiply the cu.m. by no. of pcs., then multiply by factor
moratr. To estimate cross footing : estimate it as continuous footing.

14. ADOBE BUTTRESS


Finish Cross Section Stone/Course Stone /
0.35 x 0.50 2
0.50 x 0.50 3
0.50 x 0.65 4
0.50 x 0.80 5
0.50 x 0.95 6

15. MORTAR FOR ADOBE STONE - 1 centimeter thick


Cross Footing 0.000675 cm.
Wall 0.0009 cm. one side
Stair - Buttress 0.001575 cm. two sides

16. CEMENT & SAND FACTOR PER CONCRETE PIPE JOINT COLLAR
Pipe Diameter Cement
4" dia. NRC 0.02
6" dia. NRC 0.03
8" dia. NRC 0.05

11 of 47
ESTIMATE MANUAL

12" dia. RCP 0.12


15" dia. RCP 0.15
18" dia. RCP 0.20
24" dia. RCP 0.35
30" dia. RCP 0.50
36" dia. RCP 0.70
42" dia. RCP 0.75
48" dia. RCP 1.20

Note : When wall is supported by buttress, estimate first the buttress stone for adobe.
estimate stone for adobe wall ( subtract width of buttress & openings ). To esti
cross footing, estimate it as continuous footing.

17. CHB CONCRETE FOOTING PER METER


CHB Ftg. thk. Ftg. Base Cement Sand Gravel
4" 0.10 0.30 0.27 0.01 0.02
0.15 0.30 0.45 0.02 0.04
0.15 0.45 0.63 0.03 0.06

18. CONCRETE HOLLOW BLOCKS ( C H B )


a. To estimate CHB Wall, compute the total area of coverage and less all openings such
dows & doors.
b. To obtain pieces of CHB : area x 12.15 or 12.50 .
c. To obtain cement : area x 0.27 for 4" CHB, 0.71 for 6" CHB, & 1.16 for 8" CHB
d. For sand : area x 0.022 for 4" CHB, 0.058 for 6" CHB, & 0.094 for 8" CHB.
e. For Rebars :
4" CHB using #3 @ 32" verical. & #3 @ 24" horizontal, area x 1.64 = kg.
using #3 @ 32" vertical & #4 @ 24" horizontal, area x 1.85 = kg.

6" CHB using #3 @ 32" verical . & #3 @ 24" horizontal, area x 1.64 = kg.
using #4 @ 32" vertical & #4 @ 24" horizontal, area x 2.90 = kg.

8" CHB using #3 @ 32" vertical & #3 @ 24" horizontal, area x 2.00 = kg.
using #4 @ 32" vertical & #4 @ 24" horizontal, area x 3.32 = kg.
f. For tie wire #16 : for 4" CHB = area x 0.005, for 6" CHB = area x 0.008, for
CHB = area x 0.009. All answer for this will be in roll of wire. Other procedure :
kgs. Divided by 0.300 = roll of wire.

12 of 47
ESTIMATE MANUAL

19. LABOR OUTPUT PER TEAM


a. 4" CHB : Crew - 1 mason & 2 helper will rate 12 sq.m./8 hrs. or 2.20 mh./sq.m.
b. 6" CHB : Crew - 1 mason & 2 helper will rate 10 sq.m./8 hrs. or 2.40 mh./sq.m.
c. 8" CHB : Crew - 1 mason & 2 helper will rate 8 sq.m./8 hrs. or 3.00 mh./sq.m.

20. PLASTERING
a. To estimate mortar for plastering, compute the area & multiply 0.025 or 0.0125 to ob
volume 1 Face = 0.0125, 2 Faces = 0.025.
b. To obtain bags of cement : vol. x 13, for sand : vol. x 1.06. Before obtaining ba
cement & cu.m. of sand, determine first the no. of face to be plastered & class of mixtu
c. To obtain cement : area x 0.33 = bags, for sand : area x 0.03 = cu.m. sand.

21. CEMENT TILES


a. To obtain pcs. of cement tiles of 4" x 4" : area in sq.m. x 100 pcs., for 6" x 6" :
x 45 pcs, for 8" x 8" : area x 25 pcs., for 12" x 12" : area x 12 pcs., for 16" x
area x 6.25 pcs.
b. For bedding : area x 0.33 = bags of cement, area x 0.03 = cu.m. of sand.

22. GROUTING COMPOUND


a. Horntop coating : 1 liter for every 1 sq.m.
b. Horntop floor topping : 1.20 for every 1 sq.m.
c. Applicaton : Part A and B should be mixed by machine at a rate of 250 to 300 rpm
4 min. minimum. During mixing period add 5 parts of sol. silica sand. Coating thickn
should be 2mm = 1/16 V for topping thickness 5mm = 1/4.
d. Using daraweld C : for bonding mixture use 1 part daraweld, 5 parts cement, 2.50
sand & 1 part water.
For topping : 1 part daraweld, 5 parts cement, 15 parts sand and 1 part water.
For non-skid surface : 1 part daraweld, 5 parts cement, 5 parts sand and 1.5 part
of water. For waterproofing : 1 part daraweld, 3 parts cement, 6 parts sand & 1 p
e. Using hornseal as hardener for floor : 1 liter for every 10 sq.m., using as curing
pound : 1 liter for every 5 sq.m., using as sealing : 1 liter for every 6.0 sq.m., if
& 1 liter for every 9 sq.m..
f. Hydratite : use 1 lb. for every 1 bag of cement.
g. Sahara : use I bag sahara for every 1 bag of cement.

23. SCAFFOLDING
a. Compute the floor area plus the area of the four elevations, then multiply by the no. of
for floor of the structure.

13 of 47
ESTIMATE MANUAL

b. To obtain bd.ft.of lumber : total area x 6.75 = total bd.ft. of 2" x 3" lumber.
c. To obtain nails : divide the total bd.ft. by 2500 = keg of nails, note that I keg of nail
equivalent to 45 kilos.
d. Other solution in obtaining nails : total bd.ft. divide by 1000 then multiply by 15
of nails.

24. FORMWORKS
a. To estimate formworks, compute the area of the item that need form work.
b. To obtain bd.ft. of lumber, multiply the area by the corresponding factor on the conve
table for formulas. After obtaining the total bd.ft. divide it to no. of uses.
c. To estimate ½" x 4' x 8' sht. board plywood, divide the total area by 2.88 then divide b
no. of uses.
d. For nails : total bd.ft. divide by 2500 = keg.
e. For tie wire : total bd.ft. divide by 4000 = roll.
f. For formoil : change the area of sq.m. to sq.ft. then divide by 200 = gals. of oil.

25. FLOOR JOIST


a. To estimate the floor joist board ft. per sq.m., compute the area then multiply by the c
ponding factor shown in the floor joist conversion.
b. For nails use the same procedure as of the formworks for keg of nails or divide the tot
by 1,000 then multiply by 11.44 for kilos of 4" CW nails.

26. WOODEN STUDS & SIDINGS


a. To estimate bd.ft. of studs at 0.60 o.c. for sidings using 2" x 3",multiply the area by 9
for 2" X 2" : area x 6.54, for 2" x 4" : area x 13.08, for 2" x 5" : area x 16.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 6.80 to obtain kilo
C.W. nails.
c. For stone cut sidings, compute the lineal meter of spread then multiply by 20 pcs / l.m
1" x 3", 13.16 pcs / lm.for 1" x 4", 7.87 pcs / lm. for 1" x 6" & 5.95 pcs / l.m. fo
8".
d. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 9.10 for kilos of 2½
shing nails.

27. WOODEN FLOORING


a. To estimate T&G flooring, compute the linlinear meter of spread then multiply by
l.m. for 1" x 3" T&G, 11.77 pcs / l.m. for 1" x 4", 7.87 pcs / l.m. for 1" x 6" T&
5.34 pcs / l.m. for 1" x 8" T&G.
b. To obtain nails : divide the total boardfeet by 1,000 then multiply by 13.60 for fini

14 of 47
ESTIMATE MANUAL

28. DOUBLE WALLING


a. To estimate plywood double walling of a siding, divide the total area by 2.88 = pcs
wood.
b. To obtain nails : pcs of plywood x 2 then divide by 1,000 then multiply by 9.10 for
shing nails.

29. DOUBLE WALL PARTITION


a. To estimate boardfoot of studs, use the same procedure as of wooden sidings.
b. For plywood, compute the area of the two (2) face walling then divide the total area b
c. For nails : use the same porcedure as of double wall sidings and studs.

30. CEILING JOISTS


a. Compute the area of the ceiling : area x 6.54 for 2" x 2" lumber, area x 9.84 for 2
lumber, area x 2.66 for 2" x 2" ceiling hanger.
b. For nails : use same procedure as of baseboard, then multiply by 9.10 for 3" C.W.

31. BASEBOARDS
a. To estimate the bd.ft. of baseboard : lm x 1.09 for 1" x 4" lumber, lm x 1.37 for
lumber, lm x 1.64 for 1" x 6" lumber.
b. To obtain nails : divide the total bd.ft. by 1,000 then multiply by 5.5 for 1½" finishi

32. CEILING BOARDS


a. To estimate the plywood uisng ¼" x 4' x 8' : divide the area by 2.88, for 0.60 x 1.2
nit or acoustic board : divide the area by 0.72.
b. For nails : use the same procedure of double walling.

33. ALUMINUM TEE RUNNER


a. Divide the length and width by 0.60 x 1.20 to obtain the no. of pcs of aluminum tee ru
Then multiply by the length of installation to obtain the total length of aluminum.
b. Note that the commercial length of aluminum tee runner is 20' or 6.0 meters. To obtai
divide the toatl length by 20' 0r 6.0 in linear meter.
c. For 12 guide wire : total area x 6.54 then divide by 4,000 = roll.

34. FASCIA BOARDS


a. Compute the total linear meter of the end roof all around to obtain total bd.ft. l.m. x 2
1" x 10", lm x 3.28 for 1" x 12", lm x 2.18 for 1" x 8" fascia boards.
b. For nails : divide the total boarddfeet by 1,000 then multiply by 5.5 for 2½" CWN

15 of 47
ESTIMATE MANUAL

35. WOODEN TRUSSES & RAFTERS


a. To obtain the total bd.ft. : take an actual counting of the number of the trusses or ra
then compute the bd.ft. of its members according to the size & length of the lumber to
b. After computing the bd.ft. of the lumber for one (1) truss or rafter multiply this by the
unit specified in the framing plan.
c. For nails : use the same procedure the multiply by 6.8 fo kilos of 3" - 4" C.W.N.

36. PURLINS
a. To estimate the total bd.ft. of purlins : make an actual counting of the purlins show
roof plans or truss and rafter details. Compute the bd.ft. according to size & length.
b. Or compute the area in sq.m., then multiply : area x 3.271 for 2" x 3" lumber, are
4.309 for 2" x 4" lumber, area x 5.321 for 2" x 5" lumber, area x 6.335 for 2" x 6
c. For cleats : area x 3.44 for 2" x 3", area x 4.571 for 2" x 4", area x 5.458 for 2"
area x 6.50 for 2" x 6".

37. ROOFING
a. To estimate roofing by area : solve the total area in flat then add the pitch factor ( s
1 & 2 percentage ), the total is the slotted area of the roof.
b. Divide the slotted area by factor from the table of G.I. sheet coverage.
c. Another procedure in estimating roofing : length of spread divided by 0.67 or 27"
multiply by the no. of lapping or row.

c.1. Pitch Factor of Truss and Rafter


NO. 1 SYMMETRICAL NO. 2 SYMMET
Pitch Inches Decimal % Pitch Inches
0.32 5.50 0.055 0.32 2.00
0.36 6.00 0.06 0.36 3.00
0.40 8.00 0.08 0.40 4.00
0.45 10.00 0.10 0.45 5.00
0.50 12.00 0.12 0.50 6.00
0.55 14.00 0.14 0.55 7.00
0.60 16.00 0.16 0.60 8.00
0.70 22.00 0.22 0.70 11.00
0.80 28.00 0.28 0.80 14.00
0.90 35.00 0.35 0.90 18.00
1.00 42.00 0.42 1.00 21.00
1.20 46.00 0.46 1.20 23.00

16 of 47
ESTIMATE MANUAL

1.50 54.00 0.54 1.50 27.00

d. To obtain metal rivet : pieces of G. I. Sheet x 0.073 = kilo of rivet, for washer
of G. I. sht x 0.146 = kilo of washer, for strap : pcs og G. I. sht x 12 or 9 = pcs o
To convert this to plain G. I. sheet, see table of strap.
e. To obtain gutter, ridge roll, valley roll, flashing : divide the total run or spread by
: 2.10 for ridge roll, valley roll & flashing, 2.25 for gutter & downspout, for cop
vet : no of pcs of joint multiply by 8 pcs then divide by 50 = no. of box, if in kilo
of pcs divided by 160 = kilo.
f. For nikolite : no. of joint x ¼ or 4 or length in foot divided by 24 = kilo
g. For muriatic acid : pcs of nikolite x 10 c.c. = total c.c. of muriatic.

g.1.a. G. I. Sheet coverage - 10" end lap with 2 sides coverlap


Size Effective Cov
32" x 6' 27" x 5' 2" 1.03
x 7' x 6' 2" 1.23
x 8' x 7' 2" 1.44
x 9' x 8' 2" 1.64
x 10' x 9' 2" 1.84
x 12' x 11' 2" 2.24
x 14' x 13' 2" 2.64

g.1.b. Table of Coverage - 12" end lap with 2 side corrugated lap
Size Effective Cov
32" x 6' 27" x 5' 1.01
x 7' x 6' 1.21
x 8' x 7' 1.40
x 9' x 8' 1.60
x 10' x 9' 1.79
x 12' x 11' 2.21
x 14' x 13' 1.61

g.2. Table of Fasteners


a. G. I. Nails 2½" 102.00
b. Lead Washer 86.00
c. G. I. Rivet ¼" x 3/8" 180.00
d. G. I. Rivet ¼" x ½" 157.00
e. Metal Washer 152.00

17 of 47
ESTIMATE MANUAL

g.3 Table of Rivet Per Sheet of Roofing


1. 6' - 0" 6.00
2. 7' - 0" 9.00
3. 8' - 9' 9.00
4. 10' - 12' 12.00

g.4. Table of Strap Per Plain G. I. Sheet


Purlin Size Strap Size Pc
2x3 1" x 9" 380.00
2x4 1" x 10" 340.00
2x5 1" x 11" 310.00
2x6 1" x 12" 285.00

h. For senepa flashing : total run divided by 7' or 2.135 to estimate flashing. The sa
of gutter flashing or no. of gutter = no. of flashing for gutter

SPREADING RATES OF PAINTS


Surface Gallon Coverage
1. Oil Paint smooth wood 1 coat 600 sq. ft. 55.74
2 coats 325 sq. ft. 30.19
3 coats 25 sq. ft. 21.91
rough 1 coat 350 sq. ft. 32.38
2 coats 200 sq. ft. 18.50
3 coats 135 sq. ft. 12.54
metal 1 coat 700 sq. ft. 65.03
2 coats 340 sq. ft. 31.59
3 coats 230 sq. ft. 21.37
plaster 1 coat 450 sq. ft. 41.81
2 coats 250 sq. ft. 23.23
3 coats 175 sq. ft. 16.25
hardbrick 1 coat 400 sq. ft. 37.16
2 coats 225 sq. ft. 20.90
3 coats 160 sq. ft. 14.86
softbrick 1 coat 350 sq. ft. 32.38
2 coats 200 sq. ft. 18.50
3 coats 150 sq. ft. 13.94
smooth cement 1 coat 350 sq. ft. 32.38

18 of 47
ESTIMATE MANUAL

2 coats 200 sq. ft. 18.50


3 coats 150 sq. ft. 13.94
rough cement 1 coat 200 sq. ft. 18.50
2 coats 100 sq. ft. 9.29
3 coats 50 sq. ft. 4.65
2. Oil Paint Flat smooth wall 1 coat 500 sq. ft. 46.25
2 coats 275 sq. ft. 25.55
3 coats 200 sq. ft. 18.50
plasters 1 coat 400 sq. ft. 37.00
2 coats 225 sq. ft. 20.81
3 coats 160 sq. ft. 14.86
stucco 1 coat 150 sq. ft. 13.94
2 coats 75 sq. ft. 6.97
3. Enamel Paint smooth with 1 coat 500 sq. ft. 46.25
undercoat 2 coats 250 sq. ft. 23.23
4. Exterior Spur smooth wood 1 coat 500 sq. ft. 46.25
Varnish 2 coats 275 sq. ft. 23.55
3 coats 200 sq. ft. 18.50
5. Interior Spur smooth wood 1 coat 450 sq. ft. 41.81
Varnish 2 coats 250 sq. ft. 23.23
3 coats 175 sq. ft. 16.25
6. Shellac smooth wood 1 coat 600 sq. ft. 31.50
2 coats 300 sq. ft. 22.87
rough wood 1 coat 125 sq. ft. 11.16
2 coats 75 sq. ft. 6.97
7. Shingles Satin smooth wood 1 coat 250 sq. ft. 23.23
Finish
8. Asphalt Rough rough 1 coat 150 sq. ft. 13.94
Paint smooth 1 coat 100 sq. ft. 9.29
9. Water Paint gold water paint - 5 lbs, powder
smooth 1 coat 300 sq. ft. 27.87
calsomine - 5 lbs, powder
plaster 1 coat 400 sq. ft. 37.10
wood 1 coat 250 sq. ft. 23.23
white wash - 4 to 5 lbs
brick 1 coat 200 sq. ft. 9.30
hydrated lime
plaster 1 coat 300 sq. ft. 27.87

19 of 47
ESTIMATE MANUAL

RATE OF APPLICATION ( TILES )


Granolithic tiles 0.250
Terrazo A cement tiles 0.250
Laying of Tiles
Rough plaster 0.250
Tile laying 0.080
Unglazed tiles 0.250
Grouted riprap 4.000
12" x 12" Vinyl Tiles 12.000
Holdtite adhesive 0.250
Color powder 1.000
¼" x 2" x 8" Red brick 12.000
¼" x 4½" x 4½" Vitrified tiles 86.000
Pebbles / synthetic 1.500
White cement tile filler 0.035
Hexagonal Tiles
4" x 4" 400.000
3 points hexagonal 2" size 20.000
4 points hexagonal 2" size 16.000
Cement
4" x 4" 100.000
6" x 6" 45.000
8" x 8" 25.000
12" x 12" 12.000
16" x 16" 6.250
Tool Finishing cement 0.150
sand 0.027
Cuirng compound 1.000
Curb and gutter 0.740
Cement 2.000
Sand 0.380
Gravel 0.640
Virified Tiles mortar bed
cement 0.350
sand 0.027

NAILS CONVERSION FACTORS

20 of 47
ESTIMATE MANUAL

Joist and sill 1,000 bd.ft. 11.4 kgs 4"


Studs 1,000 bd.ft. 6.80 kgs 3"
Sheating / sidings 1,000 bd.ft. 9.10 kgs 2½"
Rafters 1,000 bd.ft. 6.80 kgs 3"
Cornice 1,000 l.ft. 11.4 kgs 2½"
Shingling 1,000 pcs 1.80 kgs 1½"
Bevel sidings 1,000 bd.ft. 8.20 kgs 2"
Ceiling joist 1,000 bd.ft. 9.10 kgs 2"
Flooring 1,000 bd.ft. 13.6 kgs 2½"
Baseboard 1,000 bd.ft. 5.50 kgs 2½"
Window trim one (1) side per side 0.50 kgs 2½"
Don trim one (1) side per side 0.30 kgs 2½"
Lath 1,000 bd.ft. 3.60 kgs 1¼"
Lattice 1,000 sq. ft. 9.10 kgs 1¼"
Ballusters 1,000 l.ft. 8.20 kgs asso
Form for concrete 1,000 bd.ft. 15.0 kgs 2" & 4"

STANDARD REINFORCEMENT OF NAILS


Thk'ness Type Vertical Bars Horizontal bars Kgs/cu.m.
0.10 m 1.00 1 - #3/8 @ 0.30 1- #3 37.20
0.15 m 2.00 2 - #3 @ 0.30 2- #3 49.60
0.15 m 1.00 1 - #4 @ 0.30 1- #4 44.20
0.20 m 2.00 2 - #3 @ 0.30 2- #3 41.00
0.25 m 3.00 2 - #4 @ 0.30 2- #3 44.48
0.30 m 3.00 2 - #4 @ 0.30 2- #4 44.20
0.35 m 3.00 2 - #4 @ 0.30 2- #4 37.90
0.40 m 3.00 2 - #4 @ 0.30 2- #4 42.25
0.45 m 3.00 2 - #4 @ 0.30 2- #4 37.50
0.50 m 3.00 2 - #5 @ 0.30 2- #4 37.56
0.55 m 3.00 2 - #5 @ 0.30 2- #5 41.40

DOOR JAMBS WITHOUT TRANSOM


1. 0.60 x 2.10 Single panel type 1 pc - 2" x 6" x 16' 16.00
2. 0.65 to 0.90 x 2.10 Single panel type 1 pc - 2" x 6" x 18' 18.00
3. 1.20 x 2.10 Double panel type 1 pc - 2" x 6" x 18' 18.00
4. 1.20 to 1.60 x 2.10 Double panel type 1 pc - 2" x 6" x 20' 20.00
5. 1.80 x 2.10 Double panel type 1 pc - 2" x 6" x 20' 20.00

21 of 47
ESTIMATE MANUAL

DOOR JAMBS WITH TRANSOM


1. 0.90 x 2.10 with transom of 0.30 x 0.40 1 pc. - 2" x 6" x 24' 24.00
2. 1.20 x 2.10 with transom of 0.30 x 0.60 1 pc. - 2" x 6" x 8' 26.00
1 pc. - 2" x 6" x 18'
3. 1.40 to 1.60 x 2.10 with transom of
0.30 x 0.60 1 pc. - 2" x 6" x 18' 28.00
1 pc. - 2" x 6" x 10'
4. 1.80 x 2.10 with transom of 0.30 x 0.60 1 pc. - 2" x 6" x 18' 30.00
1 pc. - 2" x 6" x 12'

FLUSH DOOR FRAME


1. 0.90x2.10 using 2"x3" kiln dried tanguile 3 pcs - 2" x 3" x 8' 18.00
1 pc. - 2" x 3" x 12'
2. 0.60x2.10 using 2"x3" kiln dried tanguile 1 pc. - 2" x 3" x 22' 15.00
1 pc. - 2" x 3" x 8'
3. 0.70 to 0.85 x 2.10 using 2" x 3" kiln dried
tanguile 3 pcs - 2" x 3" x 8' 17.00
1 pc. - 2" x 3" x 10'

HOUR RATE PER ITEM OF WORK


Carpentry
Ceiling board on wood runner ( sq. m. ) 2-C
Frame installation 1.330
Board installation 1.000
Flush door ( 3' x 7' ) = 21 sq. ft.
Frame - 32.50 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication 12.000
Flush door ( 2' - 8" x 7' ) = 18.65 sq. ft.
Frame - 27 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication 14.000
Flush door ( 2' - 4" x 7' ) = 16.3 sq. ft.

22 of 47
ESTIMATE MANUAL

Frame - 27 bd.ft.
Board - 2 bd.ft.
Glue - 0.10 gal
Fabrication 12.000
Flush door ( 3' x 7' ) = 21 sq. ft.
Frame - 12 bd.ft. ( to be added to
flush door bd.ft. )
Fabrication 1.250
FRC or FSC with louvers
Louvers - 2 bd.ft.
Fabrication 5.000
Door Jamb
Material : 2" x 6" for 3' x 7' door 18 bd.ft.
Fabrication : 1 Carpenter 18 bd.ft. / 4 hr 4.500
Installation : 2 Carpenters 18 bd.ft. / 3 hr 3.000
Door Jamb with transom of 0.30 lm
Material : 2" x 6" for 3' x 7' door = 22 bd.ft.
Fabrication : 1 Carpenter 22 bd.ft. / 5 hr 4.400
Installation : 2 Carpenters 22 bd.ft. / 3 hr 3.600
Metal Door
Steel door with #16 cladding = size 3' x 7' 21 sq. ft.
Materials : #16 cladding = 42 sq. ft.
IGSC Frame #12 = 50 l.f.
Fabrication : 2 Steelmen / 12 hr 24.000
Equipment : 1 Welding machine 8.000
Steel door - 18" x 14" = 253 sq. ft. (2) leaf
Materials : #16 cladding = 504 sq. ft.
C - Frame #12 = 440 l.f.
Fabrication : 4 Steelmen / 56 hrs 224.000
Equipment : 1 Welding machine 40.000
Tinsmitting
Corrugated G. I. Sheet - 0.685 / sq.m.
Fastener : hook bolt - 4 pcs / 1.47 sq.m. 2.520
strap - pcs 1 sht / 792 (1/1.47) 0.015
G. I. rivets - 8 pcs. ( 1 kg /180 ) 0.030
( 1 kg /1.47 )
Lifting : 4 Tinsmith 0.270
Installation : 1.570

23 of 47
ESTIMATE MANUAL

Ridge roll #26 x 24"


Materials : 8' sht. ( 24/36 ), ( ½ . 33 ) 1… 0.285
Fastener : copper rivet : 8 pcs (1 kg /160), (½ . 33) 0.022
Nicolite : (24/36)(½ . 33) 1.300
Labor : bending 3 bend 8(½ . 33) 1.300
Installation : 2.430

UNIT RATE PER ITEM OF WORK


( man-hour x quantity ) = Total hour = duration
No. of Men
Excavation
1. Common excavation - manual 0.600
2. Common excavation - machine 0.500
3. Rock - manual & machine 8.000
4. Trenching - manual 6.000
5. Trenching - mechanical 0.020
Backfill
1. Structural backfill - manual 5.000
2. Structural backfill - mechanical 2.000
3. Hauling of soil 1.000
Formworks & concrete works
1. Grade member
- formworks 2.540
- concreting 8.540
- finishing 0.400
2. Suspended member
- formworks 3.280
- concreting 16.700
- finishing 0.800
Rebar work
1. ground floor 0.071
2. upper floor 0.080
Finishing
1. Plain cement plastering 1.330
2. Colored cement finish 1.400
3. Pebble washout 2.860
4. Granolithic tile finish 2.860
5. Marble tiles 2.860

24 of 47
ESTIMATE MANUAL

6. Vinyl tiles 1.670


7. Unglazed tiles 3.000
8. Glazed tile 0.170
9. Asphalt tiles 1.670
Carpentry works
1. Partition including framing
- ¼" thk plywood single wall 0.230
- ¼" thk plywood double wall 0.314
- wooden louver 314.000
- #10 cyclone wire 0.029
Doors ( excluding finish hardware )
1. FHC door 0.200
2. FSC door 0.286
3. Steel sliding door 0.860
4. Steel single door 0.715
5. Roll up aluminum door - manual 0.715
6. Cyclone wire sliding door 0.715
Windows
1. Fixed glass on steel frame 0.286
2. Fixed G. I. Louver 0.429
Fixed asbestos louver 0.429
4. Metal louver 0.286
Ceiling ( including framing )
1. 1/5" thk plywood 0.171
2. Acoustic tile with plywood backing 0.286
3. Concealed acoustic with aluminum T - runner 0.286
4. 3/16" thk asbestos cutting 0.171
Structural steel
1. Light structural steel framing 168.000
2. Heavy structural steel framing 164.000
Miscellaneous metal
1. Stair, stringer, handrail, tread & grating 102.000
Asbestos pipe
1. ½" ø 20
2. ¾" ø 20
3. 1" ø to 1¼" ø 22.5
4. 1½" ø to 2" ø 25
5. 2½" ø 30

25 of 47
ESTIMATE MANUAL

6. 3" ø 33
7. 3½" ø 35
8. 4" ø 40
Cast iron pipe
1. 2" ø 66
2. 4" ø 100
3. 6" ø 150
4. 8" ø 200
5. 10" ø 300
6. 12" ø 317
7. 14" ø 367
8. 16" ø 417
9. 18" ø 467
10. 20" ø 50
11. 24" ø 551
12. 30" ø 626
P V C pipes
1. ½" ø - ¾" ø 20
2. 1" ø - 1¼" ø 22
3. 1½" ø - 2" ø 25
4. 2½" ø 3
5. 3" ø 3
6. 3½" ø 3
7. 4" ø 4
8. 5" ø 5
9. 6" ø 7

LABOR OUTPUT PER MAN-DAY


Excavation 1.00 - 1.35
Backfill 3.870
Disposal of soil 4.700
Formwork 2.50 - 2.67
Rebar 10.000
Concreting 0.910
Planning concrete transit mixed 1.200
Setting anchor bolt 16.500
Setting anchor boxes 4.400
Demolition of slab, wall

26 of 47
ESTIMATE MANUAL

Excavation of cross & clampshell w/ 8 Laborers, 2 opertaors 4.400


CHB zoccalo wall 2.400
Gravel fill 3.870
Slab on fill concrete 1.000
Wood post 70.000
2nd floor wood post 75.000
T & G wood flooring 112.000
Plywood partition 80.000
Ceiling finishing 44.000
Ceiling plywood 60.000
Siding framing 60.000
L - cut sidings 112.000
roof wood framing 33.000
G. I. Gutter installation 58.000
G. I. Roofing 105.000
G. I. Gutter cut and shape 50 l.
Downspout cut and shape 27.000
Downspout installation 60.000
Vitrified floor tiles 1.500
Installation of base plate 45.000
Installation of steel roll up door 15.000
Installation of steel sliding door 10.000
Placing metal nosing 3.000
Installation of asbestos roofing 8.000
Installation of aluminum or G. I. Roofing 10.000
Roof deck copper cladding 52.000
K & O proofing 29.000
Fabrication of G. I. Gutter 2.300
Cross fabrication 46.000
Cross installation 40.000
Post 60 - 90
Girts 50 - 75
Plates 90 - 120
Fascia board 25 - 55
Tracing 30 - 60
Boarding 40 - 80
Plywood sheating 75 - 150
Cabinet door 40 - 80

27 of 47
ESTIMATE MANUAL

Doors & windows


Placing wooden door 30.000
Installation of sash glass 75.000
Placing steel windows 18.000
Placing wooden panel door 22.000
Placing wooden flush door 28.000
Installation of door lockset 5.000
Installation of flush bolt 2.000
Installation of astragal 80.000
Vitrified wall tiles 1.340
Painting 200 - 300
Floor hardener 45.000
Copper water stop - cut and shape 60.000
Copper water stop - cut installation 38.000
Installation of sliding door 10.000

LABOR CAPABILITIES PER HOUR


Clearing and grubbing - manual
Clearing undergrowth and trees 12" ø 20.000
Clearing undergrowth and shrubs 40.000
Excavation - manual
Coomon earth 0.130
Loam or sand 0.760
Clay or heavy soil 0.610
Rock 0.380
Trizzing depth and large common 0.150
Excavation - mechanical
Common earth 15.000
Rock with jack hammer 0.060
Backfilling
Common - mahual 1.220
Common backfill - manual 0.200
Compacted - crushed stone - mechanical 8.000
Compacted - common - manual 0.300
Compacted - common - mechanical 30.000
Spreading, tempering & grading 2.090
Trenching & backfill underground piping
Placing binders - gravel uncompacted 9.460

28 of 47
ESTIMATE MANUAL

Trenching & backfill underground piping


using excavated material - manual
from 0 - 2 m deep 0.060
2 - 3 m deep 0.040
3 - 4 m deep 0.030
4 - 5 m deep 0.020
Back trenching with jack hammer 0.070
Trenching & backfill underground piping
using excavated material - mechanical with backhoe
from 0 - 2 m deep 0.800
2 - 3 m deep 0.600
3 - 4 m deep 0.400
4 - 5 m deep 0.300
Placing concrete
Slab on fill 0.200
Slip form 0.040
Floor finish - unhardened 1.000
Concrete finish - hardened 0.700
Installation of pre - moulded expansion joint 1.000
Installation of water stop 1.500
Caulking of slab joint 5.000
Walls, beams, columns 1.300
Slab 1.700
Asphalting 1.250
Masonry work
4" CHB laying 1.250
6" CHB laying 1.250
8" CHB laying 1.250
Coating & tool finish plaster 0.600
Plain cement plastering finish - synthetic & pebbles 0.700
Marble slab installation 0.500
¼" x 2" x 8" red bricks 0.200
Ceramic glazed tiles 0.190
Unglazed tiles 0.230
Formwokrs installation
Nails on ground 1.000
Nails above 10' 0.850
Boxes 0.650

29 of 47
ESTIMATE MANUAL

Columns 0.850
Suspended slabs
4" - 18" 1.200
18" - 36" 0.800
36" - up 0.600
Formwork fabrication 1.860
Stripping of formwork
Nail on ground 8.000
Nails above 10' 1.550
Boxes 1.950
Columns 2.350
Suspended slabs
0 - 18" 3.600
18" - 36" 2.400
36" - up 1.850
General stripping 4.080
Reinforcing bars
Fabrication & installation 10.000
Metal work
Structural steel 10.000
Miscellaneous metal
Fabricstion of anchor bolt 10.000
Installation of anchor bolt 3.000
Fabrication of embedded item 7.000
Laying of RCP - 8 men one team
24" ø 16 pcs 2.000
36" ø 10 pcs 1.250
48" ø 6 pcs 0.750
Underground drainage piping laying
6" ø concrete pipe 0.400
12" ø concrete pipe 0.250
15" ø concrete pipe 0.230
18" ø concrete pipe 0.220
30" ø concrete pipe 0.120
Carpentry works
Plywood partition 0.930
Plywood ceiling 0.700
T&G flooring & siding 14.000

30 of 47
ESTIMATE MANUAL

Ceiling framing 5.500


Siding framing 7.500
Roof framing 4.130
Floor framing 9.380
Wood post 8.750
Truss fabrication 5.750
Truss erection 5.000
Girts 9.380
Plates 15.000
Purlins 7.500
Fascia board 4.380
Cabinets
Framing 7.500
boarding 10.000
Plywood sheeting 1.740
door 0.930
Painting works
Anay paint 3.480
Varnishing 2.320
Metal works
G. I. roofing 1.220
G. I. gutter cut & shape 6.250
G. I. gutter installation 2.250
Downspout cut & shape 3.380
Downspout installation 7.500
Backfilling & waterproofing 2.250
Painting structural steel framing 20.000

FLAT BAR IN KILOS


Thickness Width Length W
1/8" ( 3 mm ) 1" 20' 3.870
2" 7.730
3" 11.600
4" 15.460
5" 19.330
6" 23.200
¼" ( 6 mm ) 1" 20' 7.730
2" 15.460

31 of 47
ESTIMATE MANUAL

3" 23.200
4" 30.930
5" 38.600
6" 46.400
1/16" ( 2 mm ) 1" 20' 1.930
2" 3.860
3" 5.800
4" 7.730
5" 9.660
6" 11.600
3/16" ( 4 mm ) 1" 20' 5.800
2" 11.600
3" 17.400
4" 23.200
5" 29.000
6" 34.800
3/16" ( 9 mm ) 1" 20' 9.660
2" 19.330
3" 29.000
4" 38.000
5" 48.330
6" 58.000
7/16" ( mm ) 1" 20' 13.530
2" 27.060
3" 40.600
4" 54.130
5" 67.660
6" 81.200
9/16" ( 14 mm ) 1" 20' 17.400
2" 34.800
3" 52.200
4" 69.600
5" 87.000
6" 104.440
3/8" ( 10 mm ) 1" 20' 11.600
2" 23.200
3" 34.800
4" 46.400

32 of 47
ESTIMATE MANUAL

5" 58.000
6" 69.600
5/8" ( 15 mm ) 1" 20' 19.330
2" 38.660
3" 58.000
4" 77.330
5" 96.660
6" 116.000
7/8" ( 22 mm ) 1" 20' 27.060
2" 54.140
3" 81.200
4" 108.270
5" 135.330
6" 162.400
½" ( 12 mm ) 1" 20' 15.460
2" 30.930
3" 46.400
4" 61.860
5" 77.330
6" 92.800

FORMULA : to obtain kilo of flat bar, sample : ½" x 8" x 20'


'1 x 8 x 20 x 490
2 x 12 '12 = 123.73 kilos
'2.20

Note : 490 is a factor for pounds as to obtain kilo, divide then sum by 2.20 & the answ
kilo.

WEIGHT OF BOLTS IN KILOS


Lgth (in) Dinmension
1" ½" 3/8" ¾" 7/8" 1" 1 - 1/8"
2" 0.144 0.245 0.363 0.524 0.723 0.978
3" 0.169 0.285 0.421 0.601 0.824 1.106
6" 0.194 0.324 0.478 0.678 0.916 1.233
7" 0.219 0.364 0.535 0.755 1.027 1.361
8" 0.245 0.403 0.593 0.852 1.129 1.489
9" 0.270 0.443 0.649 0.509 1.250 1.617

33 of 47
ESTIMATE MANUAL

10" 0.295 0.482 0.706 0.986 1.351 1.744


11" 0.300 0.522 0.765 1.063 1.455 1.872
12" 0.346 0.561 0.820 1.140 1.534 2.000
13" 0.37 0.601 0.877 1.217 1.636 2.127
14" 0.40 0.640 0.934 1.294 1.737 2.255

INCHES TO MILLIMETER CONVERSION TABLE


1/16" = 2 mm 1/8" =
3/16" = 5 mm ¼" =
6/16" = 6 mm 3/8" =
7/16" = 11 mm ½" =
9/16" = 14 mm 5/8" =
11/16" = 17 mm ¾" =
13/16" = 21 mm 7/8" =
15/16" = 24 mm 1' =
2" = 50 mm 3" =
4" = 100 mm 5" =
6" = 150 mm 7" =
8" = 200 mm 9" =
10" = 250 mm 13" =
12" = 300 mm

BOLTS REQUIRED FOR TRUSSES


8 pcs ¼" ø bolts per splice
2 pcs ½" ø bolts per end joint
5 pcs ½" ø blots per ton joint
1 pc ½" ø blots per intermediate o. c.
2 pcs ½" ø blots per intermediate at top chord

TABLE OF VALUES FOR STRENGTH OF CONCRETE


( USING NORMAL PORTLAND CEMENT )
IN PERCENTAGE OF 28 DAYS STRENGTH
%'age of 28 %'age of 28
Days Day strength Days Day strength Days

1 17.1 30 100.9 59
2 34.3 31 101.6 60
3 44.4 32 102.4 61

34 of 47
ESTIMATE MANUAL

4 31.5 33 103.0 62
5 34.5 34 103.3 63
6 59.7 35 103.8 64
7 64.1 36 104.2 65
8 67.0 37 104.8 66
9 70.5 38 105.0 67
10 73.5 39 105.5 68
11 77.0 40 106.0 69
12 78.0 41 106.3 70
13 81.2 42 106.8 71
14 82.5 43 107.0 72
15 85.0 44 107.3 73
16 86.7 45 107.5 74
17 88.0 46 107.8 75
18 89.0 47 108.0 76
19 91.0 48 108.2 77
20 92.3 49 108.5 78
21 93.5 50 108.0 79
22 94.8 51 109.0 80
23 95.8 52 109.2 81
24 96.5 53 109.4 82
25 97.4 54 109.6 83
26 98.3 55 109.6 84
27 99.1 56 109.9 85
28 100.0 57 110.0 86
29 100.4 58 110.1 87

REBAR CONVERSION TABLE


6 mm ( # 2 ) ¼" ø 0
6.00 1.332 kgs
7.50 1.665 kgs
9.00 1.998 kgs
10.50 2.331 kgs
12.00 2.664 kgs
10 mm ( # 3 ) 3/8" ø 0
6.00 3.696 kgs
7.50 4.620 kgs
9.00 5.544 kgs

35 of 47
ESTIMATE MANUAL

10.50 6.468 kgs


12.00 7.392 kgs
12 mm ( # 4 ) ½" ø 0
6.00 5.328 kgs
7.50 6.660 kgs
9.00 7.992 kgs
10.50 9.324 kgs
12.00 10.656 kgs
16 mm ( # 5 ) 5/8" ø 1
6.00 9.474 kgs
7.50 11.843 kgs
9.00 14.211 kgs
10.50 16.580 kgs
12.00 18.948 kgs
20 mm ( # 6 ) ¾" ø 2
6.00 14.796 kgs
7.50 18.495 kgs
9.00 22.194 kgs
10.50 25.893 kgs
12.00 29.592 kgs
22 mm ( # 7 ) 7/8" ø 2
6.00 15.462 kgs
7.50 19.328 kgs
9.00 23.193 kgs
10.50 27.059 kgs
12.00 30.924 kgs
25 mm ( # 8 ) 1" ø 3
6.00 23.124 kgs
7.50 28.905 kgs
9.00 34.686 kgs
10.50 40.467 kgs
12.00 46.248 kgs
28 mm ( # 9 ) 1 - 1/8" ø 4
6.00 28.998 kgs
7.50 36.248 kgs
9.00 43.497 kgs
10.50 50.747 kgs
12.00 57.996 kgs

36 of 47
ESTIMATE MANUAL

32 mm ( # 10 ) 1 ¼" ø 6.313
6.00 37.878 kgs
7.50 47.348 kgs
9.00 56.817 kgs
10.50 66.287 kgs
12.00 75.756 kgs
36 mm ( # 11 ) 1 3/8" ø 7
6.00 47.946 kgs
7.50 59.933 kgs
9.00 71.919 kgs
10.50 83.906 kgs
12.00 95.892 kgs

THE WIRE FORMULA


For : # 16 tie wire
total rebar kgs. = Total wire ( roll ) x 45 = in kilo
'3,000
For : # 12 tie wire
total fromwork ( sq. m. ) = Total wire ( roll )
'2,000

DECORS
kgs. / ft.
150 x 50 x 2.30 mm 1.52
150 x 50 x 3.20 mm 2.06
100 x 75 x 3.20 mm 2.856

CHANNELS
kgs. / ft.
3/4.4 1.364
4/5.4 2.500
5/6.7 3.145
6/3.2 5.721
7/12.25 5.570
10/15.50 6.955

ANGLES
kgs. / ft.

37 of 47
ESTIMATE MANUAL

1" x 1" x 1/8" 0.364


1" x 1" x 3/16" 0.530
1" x 1" x ¼" 0.680
1¼" x 1¼" x ¼" 0.870
1¼" x 1¼" x 3/16" 0.670
1¼" x 1¼" x 1" 0.460
1½" x 1½" x ¼" 1.060
1½" x 1½" x 3/16" 0.820
1½" x 1½" x 1/8" 0.560
1¾" x 1¾" x ¼" 1.260
1¾" x 1¾" x 3/16" 0.960
1¾" x 1¾" x 1/8" 0.150
2" x 2" x 3/8" 2.140
2" x 2" x 5/16" 1.780
2" x 2" x ¼" 1.460
2" x 2" x 3/16" 1.110
2" x 2" x 1/8" 0.750
2½" x 2½" x ½" 3.500
2½" x 2½" x 3/8" 2.680
2½" x 2½" x 5/16" 2.270
2½" x 2½" x ¼" 1.865
2½" x 2½" x 3/16" 1.400

UNEQUAL ANGLES
kgs. / ft.
1¾" x 1¼" x ¼" 1.060
1¾" x 1¼" x 3/16" 0.820
1¾" x 1¼" x 1/8" 0.560
2" x 1¼" x ¼" 1.160
2" x 1¼" x 3/16" 0.890
2" x 1½" x ¼" 1.280
2" x 1½" x 3/16" 0.960
2" x 1½" x 1/8" 0.650
2" x 1½" x 5/16" 1.780
2" x 1½" x ¼" 1.450
2¼" x 1½" x 3/16" 1.110
2¼" x 2" x 3/8" 2.410
2¼" x 2" x 5/16" 2.050

38 of 47
ESTIMATE MANUAL

2¼" x 2" x ¼" 1.650


2¼" x 2" x 3/16" 1.250
3" x 2½" x ½" 3.860
3" x 2½" x 7/16" 3.850
3" x 2½" x 3/8" 3.000
3" x 2½" x 5/16" 2.550
3" x 2½" x ¼" 2.050
3½" x 2½" x ½" 4.270
3½" x 2½" x 7/16" 3.770
3½" x 2½" x 3/8" 3.220
3½" x 2½" x 5/16" 2.770
3½" x 2½" x ¼" 2.227
3" x 2" x 1/20" 3.500
3" x 2" x 7/16" 3.100
3" x 2" x 3/8" 2.680
3" x 2" x 5/16" 2.270
3" x 2" x ¼" 1.860

CARPENTRY WORKS
Type of work Material Cover
Columns form lumber 33 bd
Batterboard form lumber 6.50 bd
Pedestal form lumber 9.0 bd
Beam form lumber 34.0 bd
Concrete wall form lumber 19.0 bd
Slab form lumber 25.0 bd
Scaffolding form lumber 8.50 bd
Curb & gutter form lumber 36.0 bd
Coneslab form lumber 18.0 bd
Sill & lintel good lumber 1.0 bd
Baseboard good lumber 1.25 bd
Flooring 1" x 3" T&G 16.66
1" x 4" T&G 11.77
1" x 6" T&G 7.87
1" x 8" T&G 5.34
Sidings 1" x 3" S - cut 20.00
1" x 4" S - cut 13.16
1" x 6" S - cut 7.87

39 of 47
ESTIMATE MANUAL

1" x 8" S - cut 5.95

CEILING PARTITION & FORM WORK


Total area ( sq. m. ) = pcs of board 4' x 8'
2.88
Total area ( sq. m. ) = pcs of board 3' x 6'
1.87

LIGHT & HEAVY EQUIPMENTS CAPABILITY TABLE


Item Type of work Ca
Dozer clearing & grubbing 180.00
clearing 500.00
stripping 200.00
excavating 25.00
quarrying 50.00
pushing 3.00
Grader sub-grading 300.00
spreading 50.00
Payloader loading 50.00
Crane shovel loading 50.00
Shift roller static rolling (12 passes· 15 cm. lift) 45.00
vibratory rolling (4 passes·15 cm lift) 135.00
3W roller static rolling (6 passes· 20 cm. lift) 34.00
Tractor drwn roller (1-D ) vibratory rolling (6 passes·2 m lift) 240.00
Tanden roller static rolling (6 passes· 20 cm. lift) 24.00
vibratory rolling 72.00
(6 passes·60 cm. lift)
5-T dump truck hauling common borrow 3.50
hauling SBBC 3.00
hauling concrete batch class A 3.00
214 -T dump truck hauling common borrow 2.50
hauling SBBC 2.00
hauling concrete batch class A 2.00
Buggles hauling concrete mix 6.00
Wheel borrow hauling aggregates 2.50
hauling concrete mix 1.75
Water truck watering 1000.00
Asphalt dist spraying asphalt prime coat 300.00

40 of 47
ESTIMATE MANUAL

16-S concerete mixer mixing concrete 12.00


Buck crusher crushing MSG 30.00
Concrete vibrator vibrating concrete mix 40.00
Concrete floor finisher finishing concrete floor 40.00
Scraper towed ( 12 cu.yd hauling ( head capacity ) 11.00
capacity )
Scraper tournapul 45T hauling ( head capacity ) 22.00

1 hectare = 2.471 acre


1 acre = 0.4047 hectares
1 acre = 43.56 sq. ft.

HEAVY & LIGHT EQUIPMENTS FOR :


1. CLEARING & GRUBBING
Equipment Rate & unit/hour Unit Condit
Hand tool 125 mh acre
350 mh acre
1750 mh acre
Tractor 70 to 90 dump 0.25 acre
dozer
Tractor 30 to dump 0.50 acre
Mover with tractor 30 2.0 acre cutting
dump
Tractor 70 to 98 dump 1.0 acre
dozer

2. DRAINAGE DITCHES
Equipment Unit Condit
Ditching machine - wheel type 1.50 cu.yd.
1.25 cu.yd.
75.0 cu.yd. h
Ditching machine - ladder type 50 cu.yd.
45 cu.yd.
Shoe dragline 34 cu.yd. 45 cu.yd.
75 cu.yd.
Motorized grader 450 cu.yd.

300 cu.yd.

41 of 47
ESTIMATE MANUAL

Grader towed type 300 cu.yd.


Shovel at dragline 2 - cu.yd. 125 cu.yd.
200 cu.yd.

3. EXCAVATION
Equipment Unit Condit
Tractor 70 to 90 dbhp with single dozer 130.0 cu.yd. 50 ft. lev

80 cu.yd. 100 ft. lev

50 cu.yd. 200 ft. lev

Scraper Towed 8 cu.yd. With single dozer 95.0 cu.yd. 500 ft. lev

80 cu.yd. 600 ft. lev

60 cu.yd. 800 ft. lev

Motorized scraper 12 cu.yd. With tractor 87.93 cu.m.


70 to 90 dbhp 115 cu.yd. 80 ft. lev

Pusher 68.81 cu.m. 90 cu.yd. 1000 ft. lev

57.30 cu.m. 75 cu.yd. 2000 ft. lev


34.41 cu.m.
Shovel or dragline ¾ cu.m. 45 cu.yd.
57.35 cu.m. 75 cu.yd.
Shovel or dragline 2 cu.yd. 125 cu.yd. hard dig
152.92 cu.m. 200 cu.yd.

4. EMBANKMENT
Equipment Unit Condit
Tractor 70 to 90 dghp with single dozer 300 cu.yd. s
229.38 cu.m.
Rolller, sheepsfoot 2 drum 250 cu.yd.
191.15 cu.m.
In - line, towed by tractor 200 cu.yd.

42 of 47
ESTIMATE MANUAL

152.92 cu.m.
70 to 90 dbhp 150 cu.yd.
114.69 cu.m.
Pump, troiler, med., water distributor 350cpm mo

Towed type grader 400 sq.yd.


Motorized grader 400 sq.yd.
Roller, sheepsfoot 2 drum in-line towed 650 sq.yd. 60
by tractor
70 to 90 dbhp 540 sq.yd. 60
450 sq.yd. 60
Roller, road, tandem 5 to 8 tons 1,000 sq.yd.
Rubberized roller with tractor 30 dbhp 3,000 sq.yd.
Rotary tiller, tractor 30 dbhp 1,750 sq.yd. 6

Pump trailer, mounted water distributor 350 gpm mo

5. BASE COURSE CONSTRUCTION


Equipment Unit Condit
Tractor, 70 to 90 dbhp, with single 300 cu.yd.
dozer, 229.38 cu.m.
Motorized grader 152.92 cu.m. 200 cu.yd.
Motorized grader 344.07 cu.m. 450 cu.yd.
Roller road, tandem 5 to 8 tons 300 cu.yd. c
Rubber type tractor roller 30 dbhp 1500 cu.yd. co

Roller road, tandem 5 to 8 tons 75 cu.yd. com


Trailer mounted pump, water distributor 350 gpm moi

6. SURFACE TREATMENT
Equipment Unit Condit
Tractor sweeper 30 dbhp 2,500 sq. yd. sweepi
2,500 sq. yd. 0.10

Trailer mounted distributor 1,250 sq.yd. 0.10

43 of 47
ESTIMATE MANUAL

Concrete spreader 20 to 25 ft. 200 l.ft. capacity


Aggregate spreader, traction powered 5,000 sq.yd. spreading
Roller, road tnadem 5 to 8 tons 3,000 sq.yd. rolling

Rubber-tired tractor roller 30dbhp 3,000 sq.yd. rolling

Trailer mounted distributor 1,250 sq.yd. 0.20

Motorized grader 150 sq.yd. mix


bitu
Rotary tiller tractor 30dbhp 100 cu.yd. mixing
Travel -plant asphalt mixer 120 tons mixed

Roller, road tandem 6 to 8 tons 1,500 sq.yd. rolling p

Rubber-tired tractor roller 3,000 sq.yd. rolling p

Concrete mixer 14 cu.ft. 20 cu.yd 1 batch


10 cu.yd 1 batch
34 cu.ft. 40 cu.yd 1 batc
Asphalt finisher 12 ft. 100 ton ft. finishin
Concrete finisher 20 to 25 ft. 200 l.ft. capacity

7. AGGREGATE PRODUCTION
Equipment Rate & unit/hour Unit Condit
Crusher 2 units 25 tons / hr 15 tons 1" sc
20 tons 1½" sc
30 tons 1½" sc
crusher 9 units 150 tons / hr 60 tons 1" ag

100 tons 1½" ag

240 tons 3" ag

Compressor 105 cfm 105 cfm


90 cfm 5,000 f
Drill, rock 350 lbs. class 20 l.ft. 1¾" ho
require

44 of 47
ESTIMATE MANUAL

45 lbs. class 30 l.ft. 1¾" ho


require

Bucket type leader type 150 cu.yd.

Roller sheepsfoot 250 cu.yd. / hr 9" loo


( 2 drums in line ) 200 cu.yd. / hr 9" loose
150 cu.yd. / hr 9" loose

8. SUBGRADE PREPARATION
Equipment Rate & unit/hour Unit Condit
Grader - scarify & shape 334.40 sq.m. / hr 2.60 days
3.20 days
Road roller 5 - 8 tons 83.16 sq.m. / hr 100 sq.yd. 7-9 surf
1.10 days

9. BASE COURSE CONSTRUCTION ( 10 cm thick )


Equipment Rate & unit/hour Unit Condit
Grader - spreading of 153 cu.m. / hr ½ day
materials
Grader - shoving of 376 sq.m. / hr 2.0 days
surface
Raod roller 5 - 8 tons
connecting gravel 250 sq.m. / hr 3.0 days
connecting ma- 57.0 cu.m. / hr 1.0 days
cadam (0.60 thk)

cu.ft. x 0.02832 = cu.m.


cu.yd. x 0.7646 = cu.m.

10. CAPABILITIES OF MANUAL LABOR


Unit Type of work Cap
1 man excavating loam or sand 0.76
exacavating clay or heavy soil 0.61
excavating rock 0.38
backfilling 1.22
spreading, tamping & grading 2.09

45 of 47
ESTIMATE MANUAL

Placing ascombre fill 4.78


placing binders 9.46
clearing undergrowth & tree 12" ø 20.00
clearing undergrowth & small bush 40.00
team ( 8 men ) laying of 24" ø rcp
laying of 36" ø rcp
laying of 48" ø rcp

TABLE - I : POL - CONSUMPTION OF ORDINANCE


EQUIPMENTS
Fuel OE30 GO90
Item type of fuel ( 9 liters ) ( gal ) ( gal )
Utility truck ¼ T, 4' x 4' gasoline 0.14 0.0012 -
Truck, ¾ T, 4' x 4' gasoline 0.28 0.0012 -
Truck, 11/T, 4' x 4' gasoline 0.33 0.0025 -
Truck, 11/T, 6' x 6' gasoline 0.33 0.0025 -
Truck, 22/T, 6' x 6' gasoline 0.43 0.0025 -
Trk, wrecker, 4 T, 6' x 6' gasoline 0.80 0.0037 -
Dump truck , 5 T gasoline 0.95 0.0162 0.0100
Truck, 5 T, 6' x 6' gasoline 0.80 0.0050 -
Truck, medium wrecker, gasoline 0.90 0.0050 -
5 T, 6' x 6'
Primemover truck, 6 T gasoline 1.08 0.0062 -
Primemover truck, 7 T gasoline 0.95 0.0062 -
Tractor truck, 5 - 6 T gasoline 0.80 0.0150 -
( 10 ) semi trailer
Truck crane gasoline 1.61 0.0030 -
Tractor truck, 12 T gasoline 2.37 0.0112 0.0037

TABLE - II : POL - CONSUMPTION OF ENGINEERING


EQUIPMENTS
Fuel OE30 GO90
Item type of fuel ( 9 liters ) ( gal ) ( gal )
Earthe auger gasoline 10.00 0.03 0.03
Air compressor, 15 cfm gasoline 2.30 0.02 -
Air compressor, 210 cfm gasoline 20.00 0.04 0.03
Air compressor, 312 cfm diesel 15.00 0.01 -
Crane, ¾ cu.yd. gasoline 15.00 0.06 0.03

46 of 47
ESTIMATE MANUAL

Crushing plant, 3 units, gasoline 7.50 0.53 0.35


50 T / hr diesel 20.00 - -
Ladder type ditching gasoline 20.00 0.06 0.09
machine
Bituminous distributor, gasoline 15.50 0.04 0.03

Water distributor, 1000 gasoline 15.50 0.04 0.03


gal. capacity
Percussion drill gasoline 10.00 0.03 -
Electric gen, sets-5 KW gasoline 13.00 - 0.03
Electric gen, sets-15 KW gasoline 11.00 0.05 -
Electric welder gasoline 5.00 - -
Road motorized grader diesel 15.00 0.05 0.03
Asphalt heater gasoline 22.00 1.00 -
diesel 10.00 0.02 -
Asphalt kettle, 185 gal. diesel 75.00 0.02 -
Bucket loader diesel 20.00 0.04 0.03
Fabricator gasoline 38.00 0.02 -
Concrete mixer, 16 S gasoline 76.00 0.03 -
Pump centrifugal, 340 gasoline 3.00 0.03 0.03
GPU
Raod roller, 3 W lot gasoline 15.00 0.03 0.03
Road tandem roller gasoline 13.00 0.03 0.03
Pneumatic roller, 50 T gasoline - - -
Pneumatic roller, 13 W gasoline - - -
Sheepfoot towed roller, gasoline - - -
Roates, 3 tooth, H - 5 gasoline - - -
Scraper, towed, cu.yd. gasoline - - -
Scraper, towed, 18 cu.yd. gasoline - - -
Shop equipment, trzd. gasoline 6.00 0.02 0.03
Tool set Nr 3 sher shop gasoline 23.00 0.02 -
11 KW gen.
Tractor dozer L- 7, diesel 2.50 0.01 0.07
D - 8, D - 6

47 of 47
ESTIMATE MANUAL

Page
4-6
4-5
5
5
5
5-6

6-8
6
6-7
7
7
8

8 - 18
8
9
9
9
9 - 10
10
10
10
10
10 - 11
11
11
11
11
11
11 - 12
12
12 - 13
13
13
13

48 of 47
ESTIMATE MANUAL

13
13 - 14
14
14
14
14 - 15
15
15
15
15
15
15
15 - 16
16
16
16
16 - 17
17
17
17 - 18
18
18

18 - 20
18 - 19
19
19
19
19
19
19
19
19 - 20

20
21
21
21 - 22

49 of 47
ESTIMATE MANUAL

22
22
22 - 24
24 - 26
26 - 28
28 - 31
31 - 33
33 - 34
34
34
34 - 35
35 - 37
37
37
37
37 - 38
38 - 39
39
40
40 - 41

41 - 46
41
41 - 42
42
42 - 43
43
43 - 44
44 - 45
45
45
45 - 46

46
46 - 47

50 of 47
ESTIMATE MANUAL

cu.m.
cu.m.
cu.m.
sq.m.

cu.m.
cu.m.
li.
sq.m.

cu.m.
li.
sq.m.

m.
cu.m.
k.m.

m.
no.
no.
no.

m.
sq.m.
no.
no.
no.

51 of 47
ESTIMATE MANUAL

no.
no.

hrs.

m.

md

m.
cu.m.
no.
md

no.
k.m.
m.
m.
md

md
md
proj.

cu.m.
md

52 of 47
ESTIMATE MANUAL

md
md
cd
cd

Measurement
hectare
no.
cu.m.
l.s.
l.s.
cu.m.
cu.m.
cu.m.
cu.m.
l.s.
cu.m.
cu.m.
cu.m.

per hr.
1,000 li. / unit
l.s.
k.m.
k.m.

cu.m.
cu.m.
sq.m.
m or cu.m.

53 of 47
ESTIMATE MANUAL

net direct pay't


m.
m.
m.
m or cu.m.
m.
m or cu.m.
m or cu.m.
m or cu.m.
m or cu.m.
m.
m.
m or cu.m.
m.
m or cu.m.
n.d.p.
sq.m.
cu.m.

qty of struc. stl


as unit
l.m. of piles
l.m. along C.L.

cu.m.
kg.
kg.

l.m.
bd.ft.

cu.m.

54 of 47
ESTIMATE MANUAL

cu.m.
cu.m.
l.m.
sq.m.
sq.m.
l.m. or l.f.
no.
l.m.
l.m.
l.m.

area by
ided by

n allo-
e multi-
ge to li-

If keg

btain

Wire

the

55 of 47
ESTIMATE MANUAL

ngth,

vation

500-5,000 psi
13.50 bags
0.51 cu.m.
1.02 cu.m.
500-4,000 psi
11.35 bags
0.41 cu.m.
0.82 cu.m.
3,000 psi
9.50 bags
0.42 cu.m.
0.84 cu.m.
2,500 psi
8.50 bags
0.44 cu.m.
0.87 cu.m.
2,000 psi
7.50 bags
0.44 cu.m.
0.89 cu.m.
1,600 psi
6.50 bags
0.45 cu.m.
0.91 cu.m.

56 of 47
ESTIMATE MANUAL

21.0 bags
0.85 cu.m.

18.85 bags
1.0 cu.m.

13.0 bags
1.06 cu.m.

10.0 bags
1.08 cu.m.

8.0 bags
1.10 cu.m.

cu.m.

sq.m.,
phalt

sq.m.
al cu.m.

use

57 of 47
ESTIMATE MANUAL

oncrete.
a x 0.03

rea x 6
for cross

of

/ Mt. Bt.
12
18
24
30
36

one side
e, one end
, one end

Sand
0.13
0.19
0.26

58 of 47
ESTIMATE MANUAL

0.39
0.49
0.59
0.79
0.99
1.19
1.38
1.58

.
imate

Vol. / m.
0.03
0.05
0.07

as win-

r 8"
total

59 of 47
ESTIMATE MANUAL

btain

ags of
ures.

area
x 16" :

=
ness

0 parts

part water.
g com-
f rough

f storey

60 of 47
ESTIMATE MANUAL

ls is

= kls.

ersion

by the

corres-

tal bd.ft.

9.84,
38.
os of 3"

m. for
or 1" x

½" fini-

G,

. nails.

61 of 47
ESTIMATE MANUAL

of ply-

1" fini-

by 2.88.

2" x 3"

1" x 5"

ing nails.

0 lawa-

unners.

in pcs :

2.73 for

62 of 47
ESTIMATE MANUAL

afters
be used.
no. of

wn in the

ea x
6" lumber.
" x 5",

sum of

" then

TRICAL
Decimal %
0.02
0.03
0.04
0.05
0.06
0.07
0.08
0.11
0.14
0.18
0.21
0.23

63 of 47
ESTIMATE MANUAL

0.27

: pcs
of atrap,

y factor
pper ri-
: no.

verage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

verage
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo
pcs / kilo

64 of 47
ESTIMATE MANUAL

pcs / sht
pcs / sht
pcs / sht
pcs / sht

cs / sht
pcs
pcs
pcs
pcs

ame as

e
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

65 of 47
ESTIMATE MANUAL

sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.
sq.m.

sq.m.
sq.m.

sq.m.

sq.m.
sq.m.

sq.m.

sq.m.

66 of 47
ESTIMATE MANUAL

bag / sq.m.
bag / sq.m.

bag / sq.m.
bag / sq.m.
bag / sq.m.
bags/cu.m.
pcs / sq.m.
gal. / sq.m.
kg / sq.m.
pcs / sq.m.
pcs / sq.m.
cans/sq.m.
pcs / sq.m.

pcs / sq.m.
pcs / sq.m.
pcs / sq.m.

pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
pcs / sq.m.
bag /sq.m. .
cu. m./sq.m.
gal/sq.m.of 7
cu m.
bags/cu.m.
cu.m.
cu.m.

bag /cu.m.
cu.m./sq.m.

67 of 47
ESTIMATE MANUAL

CW
CW
CW
CW
finishing
CW
CW
CW
CW
finishing
finishing
finishing
CW
CW
orted nails
CW

Kgs/sq.m.
3.72
7.44
6.63
8.22
11.12
13.25
13.25
16.90
16.90
18.78
20.70

bd.ft.
bd.ft.
bd.ft.
bd.ft.
bd.ft.

68 of 47
ESTIMATE MANUAL

bd.ft.
bd.ft.

bd.ft.

bd.ft.

bd.ft.

bd.ft.

bd.ft.

Carpenters
mh / sq.m.
mh / sq.m.

mh / pc

mh / pc

69 of 47
ESTIMATE MANUAL

mh / pc

mh / pc

mh / pc

bd.ft./ mh
bd.ft./ mh

bd.ft./ mh
bd.ft./ mh

mh / pc.
hrs / pc

mh / pc.
hrs / pc

sets /sq.m.
sht /sq.m.
kg / sq.m.

mh /sq.m.
mh /sq.m.

70 of 47
ESTIMATE MANUAL

sht /sq.m.
kg. / l.m.
bend /l.m.
bend /l.m.
cu.m./ lm

mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.
mh /cu.m.

mh /cu.m.
mh /cu.m.
mh /cu.m.

mh /sq.m
mh /sq.m
mh /sq.m

mh /sq.m
mh /sq.m
mh /sq.m

mh / kg
mh / kg

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

71 of 47
ESTIMATE MANUAL

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

mh /sq.m
mh /sq.m
mh /sq.m
mh /sq.m

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

mh /sq.ft
mh /sq.ft
mh /sq.ft
mh /sq.ft

mh / m
mh / m

mh / m

mh / l. ft. of 100
mh / l. ft. of 100
mh / l. ft. of 100
mh / l. ft. of 100
mh / l. ft. of 100

72 of 47
ESTIMATE MANUAL

mh / l. ft. of 100
mh / l. ft. of 100
mh / l. ft. of 100

6.80 mh / 100 l. ft.


0.20 mh / 100 l. ft.
0.30 mh / 100 l. ft.
0.40 mh / 100 l. ft.
0.40 mh / 100 l. ft.
7.30 mh / 100 l. ft.
7.40 mh / 100 l. ft.
7.50 mh / 100 l. ft.
7.60 mh / 100 l. ft.
01.0 mh / 100 l. ft.
1.20 mh / 100 l. ft.
6.30 mh / 100 l. ft.

0.22 mh / 100 l. ft.


2.50 mh / 100 l. ft.
5.00 mh / 100 l. ft.
30.0 mh / 100 l. ft.
33.0 mh / 100 l. ft.
35.0 mh / 100 l. ft.
40.0 mh / 100 l. ft.
50.0 mh / 100 l. ft.
75.0 mh / 100 l. ft.

cu.m./ md
cu.m./ md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md
cu.m./ md
kgs / md
cu.m./ md

73 of 47
ESTIMATE MANUAL

cu.m./ md
kgs / md
cu.m./ md
cu.m./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
sq.ft. / md
bd.ft./ md
bd.ft./ md
bd.ft./ md
l.ft. / md
sq.ft. / md
l.ft. / md
l.ft. / md
l.ft. / md
sq.m./ md
l.ft. / md
sq.ft. / md
sq.ft. / md
steps / md
sheets/md
sheets/md
l.ft. / md
sq.m./ md
sheets/md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
bd.ft./ md
sq.ft. / md
sq.ft. / md

74 of 47
ESTIMATE MANUAL

sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sq.ft. / md
sets / md
pairs / md
l.ft. / md
sq.m./ md
sq.ft. / md
sq.m./ md
l.ft. / md
l.ft. / md
sq.ft. / md

sq.m./ mh
sq.m./ mh

cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh

cu.m./ mh
cu.m./ mh

cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
cu.m./ mh
sq.m./ mh

sq.m./ mh

75 of 47
ESTIMATE MANUAL

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
cu.m./ mh

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
l.m. / mh
l.m. / mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

sq.m./ mh
sq.m./ mh
sq.m./ mh

76 of 47
ESTIMATE MANUAL

sq.m./ mh

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

sq.m./ mh
sq.m./ mh
sq.m./ mh
sq.m./ mh

kgs / mh

kgs / mh

kgs / mh
kgs / mh
kgs / mh

l.m. / mh
l.m. / mh
l.m. / mh

l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh

sq.m./ mh
sq.m./ mh
bd.ft. / mh

77 of 47
ESTIMATE MANUAL

bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh

bd.ft. / mh
bd.ft. / mh
bd.ft. / mh
bd.ft. / mh

sq.m./ mh
sq.m./ mh

sq.m./ mh
l.m. / mh
l.m. / mh
l.m. / mh
l.m. / mh
sq.m./ mh
mh/m ton

Weight
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

78 of 47
ESTIMATE MANUAL

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

79 of 47
ESTIMATE MANUAL

kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs
kgs

wer is in

1 - ¼"
1.260
1.448
1.576
1.735
1.893
2.051

80 of 47
ESTIMATE MANUAL

2.209
2.367
2.526
2.684
2.042

3 mm
6 mm
10 mm
12-13 mm
16 mm
19-20 mm
22 mm
25 mm
75 mm
125 mm
175 mm
225 mm
325 mm

%age of 28
Day strgth

110.20
110.30
110.40

81 of 47
ESTIMATE MANUAL

110.50
110.60
110.70
110.80
110.90
110.90
111.00
111.00
111.10
111.10
111.10
111.20
111.30
111.40
111.60
111.70
111.80
111.90
112.00
112.00
112.20
112.30
112.40
112.50
112.50
112.60

.222 kgs. / m

.616 kgs. / m

82 of 47
ESTIMATE MANUAL

.888 kgs. / m

.579 kgs. / m

.466 kgs. / m

.577 kgs. / m

.854 kgs. / m

.833 kgs. / m

83 of 47
ESTIMATE MANUAL

kgs. / m

.991 kgs. / m

kgs / 20'
31.24
41.20
56.52

kgs / 20'
37.28
50.00
60.90
74.54
111.40
139.10

kgs / 20'

84 of 47
ESTIMATE MANUAL

1.20
10.60
13.60
17.40
13.40
9.20
21.20
16.40
11.20
25.20
19.20
3.90
42.80
35.60
29.20
22.20
15.00
70.00
53.60
45.40
37.30
28.00

kgs / 20'
21.20
16.40
11.20
23.20
17.80
25.20
19.20
13.00
35.60
29.00
22.20
48.20
47.00

85 of 47
ESTIMATE MANUAL

33.00
23.00
77.20
69.00
60.00
51.00
41.00
85.40
75.40
65.40
55.40
44.54
70.00
62.00
53.60
45.40
37.20

rage
d.ft /.sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
d.ft. / sq.m.
pcs. / l.m.
pcs. / l.m.
pcs. / l.m.
pcs. / l.m.
pcs. / l.m.
pcs. / l.m.
pcs. / l.m.

86 of 47
ESTIMATE MANUAL

pcs. / l.m.

apability
180 sq.m./ hr.
180 sq.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
180 sq.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.
cu.m./ hr.

cu.m./trip
cu.m./trip
batch/trip
cu.m./trip
cu.m./trip
batch/trip
cu.ft./trip
cu.ft./trip
cu.ft./trip
180 sq.m./ hr.
180 sq.m./ hr.

87 of 47
ESTIMATE MANUAL

180 sq.m./ hr.


180 sq.m./ hr.
180 sq.m./ hr.
180 sq.m./ hr.
cu.m./trip

cu.m./trip

tion
light clearing
medium clearing
heavy clearing
medium clearing

pulling disk
g weeds & grasses

light stripping

tion
sandy soil
common earth
hard / frozen earth
sandy soil
common earth
hard digging
basing digging
"V" ditches
sandy soil
"V" ditches

88 of 47
ESTIMATE MANUAL

common earth
common earth
hard digging
easy digging

tion
vel haul, common
earth
vel haul, common
earth
vel haul, common
earth
vel haul, common
earth
vel haul, common
earth
vel haul, common
earth

vel haul, common


earth
vel haul, common
earth
vel haul, common
earth
hard digging
easy digging
gging 95.58 cu.m.
easy digging

tion
spreading material

9" loose layers


8 passes
9" loose layers

89 of 47
ESTIMATE MANUAL

10 passes
9" loose layers
12 passes
oisture varies with
materials
scarify & shape
scarify & shape
0" layer, 8 passes

0" layer, 10 passes


0" layer, 12 passes
3 mph, 5 passes
3 mph, 5 passes
6" depth, 3 mph,
6 passes
oisture varies with
materials

tion
spread materials

spread materials
sharing materials
compacting gravel
ompacting grade,
10 passes
mpacting macadam
isture varies with
materials

tion
ing, compact base
0gal / sq.yd. 24 ft.
spray
0 gal / sq.yd. 24 ft.
spray

90 of 47
ESTIMATE MANUAL

y depnds on payer
coned aggregates
aggregate 3 mph
3 passes
aggregate 5 mph
5 passes
0 gal / sq.yd. 24 ft.
spray
xed in place, 2 in
uminous materials
g bituminous mat'l
in place by travel
plant
pavement, 3 mph
6 passes
pavement, 5 mph
5 passes
h every 3 minutes
h every 3 minutes
ch every 1.75 min
ng plant mix mat'l
depends on payer

tion
creened aggregate
creened aggregate
creened aggregate
ggregate screened
mashed
ggregate screened
mashed
ggregate screened
mashed
at sea level
ft. above sea level
ole mix 16 ft. deep
es 40 to 60 cfm of

91 of 47
ESTIMATE MANUAL

air
ole mix 16 ft. deep
es 70 to 90 cfm of
air
from stock pile

se layer, 8 passes
e layer, 10 passes
e layer, 12 passes

tion
7.0 surface / k.m.
9.0 surface / k.m.
face / k.m, 3 mph
6 passes

tion
1.0 day

3.0 days

3.70 days

pability
cu.m. / hr
cu.m. / hr
cu.m. / hr
cu.m. / hr
sq.m. / hr

92 of 47
ESTIMATE MANUAL

cu.m. / hr
cu.m. / hr
sq.m. / hr
sq.m. / hr
16 pipes / 8 hrs
10 pipes / 8 hrs
6 pipes / 8 hrs

GAA
( lb )
0.0025
0.0037
0.0061
0.0050
0.0075
0.0120
0.0166
0.0132
0.0062

0.0012
0.0112
0.0075

0.0087
0.0162

GAA
( lb )
0.06
-
0.05
0.04
0.05

93 of 47
ESTIMATE MANUAL

0.25
-
0.01

0.05

0.05

0.06
-
-
-
0.06
-
0.02
0.03
0.06
0.01
0.03
0.04

0.03
0.01
0.03
0.03
0.03
0.03
0.05
0.06
0.05
-

0.05

94 of 47

Das könnte Ihnen auch gefallen