Sie sind auf Seite 1von 10

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/3812196

Railway electrification systems and configurations

Conference Paper · August 1999


DOI: 10.1109/PESS.1999.784389 · Source: IEEE Xplore

CITATIONS READS
26 1,953

1 author:

Bharat Bhargava
Sunlight Power Consultants
30 PUBLICATIONS   627 CITATIONS   

SEE PROFILE

Some of the authors of this publication are also working on these related projects:

Please check the website - advancedpstinc.com View project

Power Quality View project

All content following this page was uploaded by Bharat Bhargava on 23 December 2015.

The user has requested enhancement of the downloaded file.


Benefits of a Low Frequency, Low Voltage
Railway Electrification System

Bharat Bhargava
Southern California Edison Company
Rosemead, California 91770

ABSTRACT have been the abundance of cheap diesel oil and the high
cost of railway electrification. However, because of
The benefits of a low frequency (15-20 HZ) railway environmental constraints, several major U.S. cities are
electrification system are presented in this paper. The low considering railway electrification. Also, several major
frequency railway electrification system has been used in cities and their Metropolitan areas are either building or
European countries for almost a century. The railway expanding their Metro rail system and building electrified
electrification load is one of the worst kinds of load to be railway traction systems. These environmental pressures
fed by an electrical utility. It requires over sized substation will continue and will force railway electrification on the
facilities and results in power quality deterioration. With heavily traveled freight routes. In view of this, this may be
the modern day power electronics technology available for an opportune time to select an appropriate railway
frequency conversion and the high power quality demanded electrification system which could provide superior
by the utility power customers, the low frequency systems performance at an economical price.
will provide an affordable and desirable railway
electrification system. RAILWAY INDUSTRY IN USA AND EUROPE

INTRODUCTION Railway usage in the U.S. differs greatly from the


railway industry in Europe and on other continents. They
The low frequency electrified railway system has been are primarily used for freight in the U.S. The freight trains
in operation for over a century in Sweden, Germany and in the U.S. are much larger and carry a much higher load as
other European countries. With the modern day power compared to those in Europe and in other parts of the
electronics technology available for frequency conversion, World. Since the railways are generally used for freight
and the high power quality demanded by the utility power movement in the U.S., they do not have to move as fast as
customers, the low frequency system is likely to make the in other European countries where the railway usage is for
railway electrification system more affordable and personal travel. The freight trains in the U.S. often carry
desirable. This paper will detail specifically how low double stacks, which require much higher electrical
frequency railway electrification may provide economic clearances. The railways are operated by private companies
and superior performance over the present railway and two or more companies operate in the same general
electrification system in America. area carrying freight from major ports to the main
The United States has the highest mileage of railway consumption areas in the country. For local transportation
tracks in the World, but is the least electrified when and the commute from work to home, the desired mode of
compared to other industrialized countries. Only one transportation has been the automobile. Because of the low
percent of the 244,000 miles of railway track is electrified cost, faster service and longer distances involved in the
in the U.S. The reasons for the low level of electrification United States, air travel has been the primary people
mover.
On the other hand, in Europe and even in most of the
rest of the World, the railways are the primary people
mover. Railway travel is not only used in the inner cities,
but also for the daily commute to work in the city from the
outskirts of the city. The railway trains move the people as
well as the freight. Air travel is used rarely and for longer
distances only. European countries provide railway
transportation at an affordable price. The train speeds have
steadily increased to reduce travel time, and TGV trains
travelling as fast as 330 MPH are in operation in France.
In view of these marked differences in public attitude,
railways have flourished steadily in Europe and other major
parts of the World, whereas they have been used to a RAILWAY ELECTRIFICATION SYSTEMS IN USA
limited extent in the United States and mostly for freight
transportation. Amtrak was set up by the U.S. Government Electrification System (Voltage, Frequency):
to encourage railway travel.
The railway electrification system in America has
FUTURE FOR RAILWAY ELECTRIFICATION : generally been electrified for commuter rails. There are
some widely traveled routes such as the Amtrak northeast
The extensive railway route length in the United States corridor railway between Boston, Massachusetts and New
will require large amounts of capital investment for railway Haven, Connecticut which were electrified recently. The
electrification maintenance and operation. Because of the electrification system is supplied by a single phase auto
large amounts of new capital and the low investment return, transformer +/- 25 KV catenary voltage[1]. The frequency
there is reluctance to electrify the railways on the part of the in this system is 60 HZ. This is the most commonly used
railway companies. Therefore, the electrification has still railway electrification alternative.
not been done except for heavily traveled routes. Reducing There are some exclusive freight trains electrified in
the cost of railway electrification will generate incentives the U.S. as well, particularly the Black Mesa-Lake Powell
for the railway companies and will help in expediting railroad, which carries coal for the Navajo steam plant[2].
railway electrification. The freight train for the Black Mesa-Lake Powell is a
The U.S. railways are under pressure due to the unique system built in the wilderness. Considerable
environment to electrify some routes which are either economy in the substations has been achieved by building
heavily traveled corridors or carry large quantities of the line on 50 KV catenary voltage and using series
freight. Since most of the tracks in America are already compensation. The entire railway line, which is about 80
built and in service, most of the civil work is already in miles long, is fed from a single substation. Since this
place. Electrification of these routes will require extensive railway line is in the wilderness and the railway line is for
civil modifications, like lowering the railway tracks or coal haulage, the economy has been achieved by partially
raising the overhead bridges, etc., which is in itself very compromising the reliability.
expensive. The completed civil engineering work limits the There are some railway electrification systems in the
choice of voltages as the higher voltage operating systems eastern U.S. operating at low voltage and low frequency.
may require extensive civil work modifications and turn out The New Jersey Coastline between Rahway and Matawan-
to be more expensive. Innovative methods of reducing the Longbranch operates at 12 KV, 25 HZ. The low frequency
operational voltages, which will eventually reduce civil used is 25 HZ. The frequency conversion is done using
work costs, are required. rotary converters and cyclo-converters[3]. Although this is
Railway electrification costs in the U.S. can be reduced a low frequency system, it appears that the full benefits of
and railway electrification/utility system performance can the lower frequency have not been exploited by this railway
be improved by suitable selection of the railway electrification.
electrification system. Modern day power electronics As indicated above, the trains in the U.S. are mostly
technology developments such as the high power thyristors used for freight. Passenger traffic is comparatively much
and the Gate Turn Off thyristors (GTO) can make it smaller and mostly confined to very heavily traveled routes.
economically attractive to select systems with frequencies Some of these heavily traveled routes are San Diego-Los
other than the utility system frequency. As a result of these Angeles, Washington-New York, and New Haven-
developments in power electronics, the principle of Connecticut, etc. The train travel is usually limited to
frequency conversion is being used extensively not only to distances less than 150 to 200 miles. The larger distances
improve the operational efficiency of the induction motor such as San Francisco-LA, LA-Phoenix or LA-Las Vegas,
application, but will provide superior speed control. The etc. which are in the range of 250-500 miles are mostly
same principles can be applied to railway electrification traveled by airplane.
system improvements and cost reduction.
The best fit for a U. S. railway electrification system Railway Electrification Substations:
could be to select a low frequency, low voltage system. The
low frequency (like 15 HZ or 20 HZ), of the traction power The railway electrification substations in U.S. typically feed
system will enable the U.S. to increase the distance between 20 miles of route length, 10 miles on each side of the
the system by increasing the distance between two railway electrification substation. The railway tracks are
successive substations. Also, lowering the frequency would generally double tracks and each substation feeds about 40
provide a margin to lower the voltage from the 25 KV miles of Single Track Mile (STM). Thus the distance
catenary voltage most commonly used to 15 KV - 16.5 KV, between each substation is about 20 miles. The distance
which could enable reducing the clearance requirements between each substation is usually limited because of the
thus reducing the civil modification costs. voltage drop in the catenary[4,5]. The railway
electrification load is a single phase load on the secondary
side of the transformer which feeds the catenary. This Number of Substations and other Major Railway
results in a highly unbalanced load on the electrical system. Electrification Costs :
The catenary can be serviced from either a 25 KV or 50 KV
voltage catenary to ground. The auto transformer system is The number of substations built to supply a railway
supplied with a voltage level of +/- 25 KV when large loads electrification system has a direct impact on the cost of the
have to be fed as in the case of northeast corridor railway electrification project. The other factors which will
electrification[5,6]. The primary side of the substation influence the cost are the size of the substation and the
transformer can be connected phase to ground or between voltage level required to feed the railway electrification
two phases. From the utility standpoint, it is desirable to load. The number of substations could be reduced if a
connect the primary of the transformer between two phases substation can provide power for greater track length. As
as the railway load is fed from two phases and the loading indicated above, this track length served from a substation
on a single phase and unbalanced load is reduced. A typical is usually limited by the catenary voltage drop. Higher
layout for a railway substation is shown in Figure 1. The conductor size, if used, would reduce losses, increase
two adjacent substations are thus fed from two different sets current capacity, but would not significantly reduce the
of phases. Substation A in Figure 1 may be fed from phases inductive voltage drop and thus not solve the voltage drop
AB, Substation B from BC and Substation C from phases problem.
CA. The catenaries between the substations are separated Innovative methods as in the case of the Black Mesa-
by Phase Breaks, which is a portion of the catenary with Lake Powell line have been used to reduce the number of
no power from either substation. substations and thus the cost of railway electrification. The
methods include going to higher voltage (50 KV), and using
harmonic filtering and series compensation at the middle of
Sub. A Sub. B Sub. C the line to reduce the voltage drop further[2]. Other
Phase A methods used to supply large loads are the auto-transformer
Phase B feeder method, etc.[6].
Phase C

Power Requirements and Other Needs of Railway


Electrification :

The freight trains in America are run by four to six


diesel locomotives. With each diesel locomotive providing
power of about 4.0 MW, the total train load can be between
Figure 1. Power Distribution System for Three Adjacent 18-24 MW. This load level is considerably higher than the
Railway Electrification Substations commuter loads in the U.S. or the freight and commuter
trains in other countries. With up to four trains within the
The train relies on its inertia to move through this substation jurisdiction, the substation peak load can be
phase break distance. When a train travels from Substation estimated to be between 60-100 MVA.
A to B and passes through the phase break, the train load on The train load depends on a multitude of factors, such
the system will be switched from Substation phases AB as the train load, train headway, train speed, load hauled,
(Substation A) to BC (Substation B) and when it travels the track profile, etc. The railway electrification load is
from Substation B to C the load will be switched from generally determined using Train Simulation Programs.
phases BC (Substation B) to phases CA (Substation C). The The programs can give a reasonably accurate load
sudden change in the train load or the load on the substation prediction. Generally when a system is designed, it must be
as the train moves out of the substation jurisdiction, will designed keeping in mind the future development or the
cause voltage flicker and is usually observable even at a ultimate needs the railway electrification system has to
very low percentage change. The perceptibility of this serve.
flicker is dependent on the voltage change and its The freight trains with loads above 18 to 24 MW could
frequency. If the change becomes too frequent or large then require substations at shorter distances or higher voltage or
it will cause annoyance to the people who may be supplied auto transformer service because of higher loads and power
power from this common substation bus. The irritability is requirements. The possible alternative arrangement to
dependent on the frequency of occurrence and the reduce the catenary voltage drop to maintain the distance
percentage of voltage change and is generally analyzed separation is to increase catenary service voltage with an
using a voltage flicker curve. A frequently traveled route auto transformer arrangement to +/- 25 KV. This system
may result in annoyed utility customers and result in more runs a parallel feeder circuit to maintain about 50 KV
frequent complaints. service voltage between the positive and the negative feeder
circuit but the railway catenary voltage to ground is at 25
KV. This system is being used in the Boston-New Haven Voltage Unbalance:
northeast corridor railway line.
Several studies conducted recently have shown that a The most restrictive criteria among voltage unbalance,
50 KV phase to ground system for railway electrification voltage flicker or harmonics is the voltage and current
could be less expensive, but would require extensive civil unbalance. Voltage unbalance in an electrical utility system
work modifications. The civil work would therefore is caused by unbalanced load or the untransposed
increase the cost of overall electrification considerably. transmission system. Railway electrification load is an
unbalanced load as it is fed from one or two phases only.
Design Basis for the Railway Electrification Loads : Voltage unbalance is dependent on the unbalanced load and
the power system source strength or the available short
When designing a railway electrification system, the circuit duty at the substation. The short circuit duty is
system is generally designed to operate with full efficiency dependent on the transmission system and the number of
even with the loss of a substation. Thus in Figure 1, the generators connected in the system. Current unbalance is
system must be able to withstand the loss of Substation B dependent on the load itself. At light load conditions, the
without any impact on train efficiency. Substations A and C number of generators is lower and so the short circuit duty
should be able to feed the power when the trains are in the is lower. The lesser number of generators results in each of
respective area. This basically puts a demand of almost 150 those generators sharing more unbalance current. Voltage
percent of the nominal substation load on each of the and current imbalance impacts both the utility and its
substations as each substation should be able to withstand customers. For the utility, the unbalance results in the
the loss of the adjacent substation. As such, Substation A negative phase sequence currents which flow into the utility
should be able to carry the load of Substation A and half of generators and result in heating the generator rotors. The
Substation B for the loss of Substation B, Substation B unbalance limit of a generator is dependent on the I 2T
should be able to carry Substation B and half of Substation withstand capability of the generators. Typically at
A for the loss of Substation A, and Substation C should be unbalanced voltage, the generators have to provide power
able to carry the load of Substation C and half of Substation and negative sequence currents which heat the generator
B, for the loss of Substation B, etc. These loads thus rotors and may result in tripping the generators. For utility
become the basis for the design of the system and for customers, unbalanced voltage causes negative phase
determining the voltage unbalance, harmonics, voltage sequence currents to flow into the motors and causes the
flicker, etc. motors to be heated up. This reduces the motors’ capacity
and the motors have to be derated[9].
POWER QUALITY CONSIDERATIONS FOR Electrical utilities in the U.S. try to limit the unbalance
RAILWAY ELECTRIFICATION LOADS: to about 2 percent maximum. There is also an inherent
system unbalance present in the utility system because of
The railway electrification load is one of the worst other sources. Typically these sources are the single phase
kinds of load for an electrical utility to supply. The only loads being fed from the distribution system, or the
load which gives more challenge to the utility is arc furnace untransposed high voltage transmission lines, etc. Typically
load. The railway electrification load is highly intermittent, an electrical utility can see up to 0.5 - 0.8 percent unbalance
irregular, low load factor and poor power factor. The inherently present in the system. Electrical utilities make
railway electrification load creates system voltage and efforts to balance these single phase loads on the
current unbalance, generates harmonics and results in distribution system, but it is extremely difficult to reduce
voltage flicker. Because of the above characteristics, the the unbalance because of the random nature of the load.
railway electrification load generally requires oversized Allowing for 1 percent ambient unbalance from other
substation facilities. It stresses the electrical utility sources, the voltage unbalance from the railway
equipment more and also causes interference with other electrification load will have to be limited to 1 percent.
customer loads and often complaints from the other utility Some utilities may allow higher ambient voltage unbalance.
customers, etc. The railway electrification load is fed on Also some utilities have reported consumer complaints
single or two phases of the electrical utility system. This when 2 percent imbalance was used[7,9]. While designing
load has always been a challenge to utility engineers and substations and the electrification system for railway
results in increased electrification cost to the railways. electrification, it is always desirable to measure the ambient
Some recently electrified railroads and the utilities are using voltage unbalance over a period of a couple of days. Also
extremely tight power quality standards to maintain the unbalance should be compared with the short circuit
acceptable power quality to other customers. They have duty available to actually calculate the load in the MW
also installed expensive Static Load Balancing devices to causing this ambient voltage unbalance.
reduce voltage unbalance and flicker problems[8]. Some of The typical load fed from a railway electrification
the common power quality characteristics of the loads are substation was estimated to be about 60 - 100 MVA. This
discussed below: would allow about four trains within the substation beat.
Assuming that a 100 MVA load has to be fed from two Load Factor:
phases of a substation in Figure 1, and also assuming that
the ambient unbalance is 1 percent, then the short circuit The railway electrification load factor is dependent on
duty must be more than 10,000 MVA to limit the voltage the train frequency and usage. The typical load factor for a
drop to less than 1 percent imbalance. substation is about 15-25 percent depending on the train
frequency. Compared to the other utility loads, this is a poor
Voltage Flicker: load factor and the energy sales are much lower compared
to the peak load demand. This type of load thus results in
The voltage flicker caused by the railway excessively high investment costs for the utility.
electrification load is also dependent on the system source
strength or the short circuit duty. If the source has a high SUBSTATION SHORT CIRCUIT DUTY, PRIMARY
short circuit duty (say 10,000 MVA), then a 25 MVA train VOLTAGE AND CAPACITY REQUIREMENTS:
load moving out of the substation will cause approximately
0.25 percent voltage change in the voltage. For a single Short Circuit Duty Requirements:
phase load, the short circuit duty for one phase (in this case
3333 MVA) and the flicker would be 0.75 percent. If the The voltage unbalance, flicker and harmonics are all
power is fed from two primary phases, then the load is dependent on the short circuit duty level at the substation. A
divided from two phases and the flicker will be about half high duty substation has more capability and can feed
or about 0.375 percent. Although unbalance is hard to higher unbalanced load and harmonics, or will have lower
uncover, the flicker is readily perceivable and can be flicker.
detected easily by the customers. In order to limit the unbalance to 1 percent and
allowing for the ambient unbalance of 1 percent, the
Harmonics from Railway Electrification Load: minimum short circuit duty required to meet a 60 to 100
MVA unbalanced load would be 6,000 to 10,000 MVA.
Most railway locomotives used today are thyristor This type of short circuit duty is only feasible on 230 KV
controlled power electronics based. This type of load substations with a strong network. Also, this short circuit
generates high levels of harmonics. Harmonic currents from duty would be required to limit the voltage flicker to 1
modern day locomotives have been shown to be as high as percent or below. Although the higher flicker levels can be
25 percent. The voltage THD is as high as 6 percent.[6] The tolerated, a high train frequency could result in customer
harmonics can, however, be controlled by appropriate complaints.
filtering whether on board or at the substation. The
allowable harmonic levels generally depend on the utility Substation Capacity and Primary Voltage:
but IEEE-519[10] defines some guidelines. The standard
just gives a guideline and each utility must establish its own The primary side substation voltage is a major concern.
standards. The allowable harmonics are dependent on Basically this will establish the voltage level from which
system characteristics. Systems with extensive shunt the railway electrification load will be fed by the utility and
capacitors have to be specially analyzed to avoid will have a major impact on the project cost. Both the
resonances with the utility or the customers capacitor substation cost and the transmission costs will increase with
installations. The French and English grid operators have substation capacity and the voltage level. A power level of
specified much lower harmonic limits for the Channel 120 MVA can easily be fed by a 69 KV or a 115 KV
Tunnel[8]. substation. The typical three phase short circuit duties on a
Although the levels given in IEEE-519 may not be a 69 KV or a 115 KV substation range from 1500 MVA to
major problem, the harmonics could interfere with 5000 MVA. Thus the single phase load that could be fed
sophisticated control systems and other loads. The voltage from these substations would be 15 MVA to 50 MVA only.
harmonics are also dependent on the short circuit duty at the Higher design basis loads require that the short circuit duty
substation. of the system be enough so that the voltage flicker,
unbalance and harmonics standards are satisfied. These are
Power Factor: dependent on the system strength at the substation. The
The railway traction load power factor can range only solution is to push for a higher voltage system.
between 0.5 to 0.8. Although power factor correction is A 230 KV or higher voltage substation would be
possible, the rapidly changing railway load and the power required to serve single phase loads with more than 60
factor still present a challenge for power factor correction. MVA power. Most of the substations built in France to
Power factor cannot be corrected as rapidly as the load is supply power to TGV high speed trains which feed power
changing and thus rapidly changing power factor and the to substations with 40-60 MVA capacity are built with
load will still result in fast changes in vars from the system primary voltages of 275 KV or 400 KV. A 230 KV voltage
and thus result in some flicker or voltage changes. substation if built to provide 60-100 MVA power will be
under utilized and costly. In the U.S., these substation A low frequency system decreases the cost of
voltages are typically used to provide 500-800 MVA electrification by increasing the distance between two
power. successive substations, and reducing civil engineering
modification costs by enabling lowering the catenary
Power Quality Problem Solutions in European voltage from the 25 KV voltage commonly used in the U.S.
Countries: to 16.5 KV at 15/20 HZ. Such a system would enable
paralleling the catenaries between two substations on the
Because of the above power quality and system secondary side, thus increasing the capabilities of the
problems, some European countries have totally isolated the catenaries and reducing the power quality and unbalance
railway electrification systems from other industrial and voltage problems. The various advantages that can be
residential loads. This of course increases their investment derived from low frequency operation are:
in power generation and transmission but eliminates other
problems and enables them to design the electrification BENEFITS OF A LOW FREQUENCY, LOW
system best suited for railway electrification. To solve the VOLTAGE ALTERNATIVE:
problems mentioned above they have designed single
phase railway electrification systems which provide several 1. Longer substation beat/less substation installations:
benefits in the utilization of the catenary system, keep the
power quality to the other customers clean, and eliminate A lower frequency system will reduce the inductive
the current unbalance problems, etc. The railways in voltage drop in the catenary. A 15 HZ system would have
Germany generate their own power, transmit and transform approximately one fourth the inductive voltage drop as
it. Generating electricity and transforming it at low compared to a 60 HZ system, thus it would enable the
frequency increases the size of the generating and substations to be located at 3 to 4 times the distance
transforming equipment and results in more expensive compared to a 60 HZ system based just on the voltage drop
equipment. In contrast, Sweden purchases power from the criterion. The number of substations required could be
electric grid, transforms it and then converts it into a lower reduced to 30-40 percent.
frequency. France and some other countries have gone to
higher substation primary voltages and very restrictive 2. Parallel operation of catenary from adjacent
power quality standards to feed the power system from the substation:
utility grid[11]. Going to higher voltage levels obviously is
an expensive alternative. The catenaries of the traction system can be all in
phase. They can be paralleled on the secondary side.
LOW FREQUENCY, LOW VOLTAGE SYSTEM FOR Paralleling the secondaries will enable the power to be
RAILWAY ELECTRIFICATION: drawn from two or more substations, thus decreasing the
voltage drop further in the catenary and also distributing the
Frequency conversion is not only possible, but is load on two or more substations. There will be a smoother
becoming an economically attractive alternative. The transition of load from one substation to the other as the
frequency conversion is being used for accurate speed train moves along. Paralleling the catenaries could further
control and energy and power savings in several industrial help in increasing the distance between substations and
processes. The cost of power frequency conversion is reduce power losses in the catenaries. This would also
dropping and the reliability is constantly improving. improve the effective utilization of the substations and
Modern day control systems are making the conversion reduce the peak load thereby increasing the substation load
very precise and efficient. Frequency conversion systems factor, and reducing substation size. With modern power
can be applied to the railway electrification systems to electronics and an advanced ASD control system, the
obtain the advantages of industrial frequency for power voltage at a substation can be controlled for optimum
generation and the low frequency system for power loading on the substation. This will also improve the
distribution on the catenary. The 60 HZ frequency can be utilization of the catenary system.
converted to 15 or 20 HZ for railway electrification. When
converting the frequency, the low frequency system can be
operated as a single phase system. The frequency 3. Reduced voltage operation at 15-16.5 KV:
conversion can be done using a cyclo-converter, or it can be
done using an AC/DC/AC system conversion. The Since the substation beat can be increased because of a
AC/DC/AC conversion is used extensively in Adjustable lower frequency and parallel operation of the catenary
Speed Drives(ASD). This would solve multitudes of system, lower catenary voltage could be used and
problems related to power quality, reduce the cost of substantial savings are achieved in civil engineering
electrification, etc. modifications by reducing the electrical clearance
requirements at the reduced voltage level. The lower
voltages have been used in Germany and Sweden with 7. Reduced harmonics into the system:
success. Reducing the voltage level; however, would
increase the current in the catenary and would increase With the low frequency system, harmonics would be
losses which may require a higher size catenary conductor generated in the conversion equipment. Appropriate
or an additional feeder circuit. filtering can be provided along with the conversion
equipment to limit the harmonics to acceptable levels. The
4. Lesser electrical clearances and civil engineering modern day electric locomotives have onboard power factor
requirements: correction and harmonic filtering. The frequency
conversion equipment filters on the system would further
Lower voltages will result in lower clearance reduce the harmonics generated from the locomotives and
requirements. This could be useful where bridges have to be reduce the harmonics entering into the utility system.
raised, tracks have to be lowered or when the tunnels do not
permit adequate clearances for the 25 KV system. In a 8. Lower voltage utility substations:
recent study conducted by the Los Angeles County
Transportation Commission, a 25 KV railway The unbalance voltage caused by the trains can become
electrification system was being selected even though the the single most important factor which will dictate the
electrification costs were lower for a 50 KV system selection of the substation primary voltage. Adequate short
primarily because of the higher electrical clearances circuit duty and voltage levels are required to limit the
required at 50 KV. voltage unbalance and the harmonics at the substation.
Additional substations had to be installed by British Rail to
5. Reduced substation voltage capacity or better reduce the voltage unbalance in their Eastern Corridor
utilization of substation and catenary capacity: Railway line. British Rail has developed extremely
conservative power quality (unbalance, harmonics)
With the 25 KV single-phase, 60 HZ system, each standards for the Channel electrification which would
substation has to be designed to provide full power for the require high voltage substations. SNIFF builds 275 or 400
trains within the substation beat and half the adjacent KV substations to provide the power for TGV (Ref. 11).
substation. By paralleling the traction system on the Since a low frequency, low voltage system would eliminate
secondary side and sharing the loads among the adjacent or reduce the power quality problems, a 40 to 60 MW load
substations, it is quite possible to reduce the substation could easily be served by a 69 KV or a 115 KV substation.
capacity or to provide larger train frequency. SCE’s typical 69 KV or 115 KV substations are designed to
serve up to 112 MW loads.
6. Reduced unbalance voltage problem:
9. Locomotive transformer and AC motor size:
The traction load, as explained earlier, is one of the
worst kinds of load as it is often supplied from one or two Lower traction frequency at the locomotive will require
phases of a power system. The single phase load creates a bigger transformer and motors in the electric locomotive.
voltage unbalance and other power quality problems. Very These low frequency locomotives have, however, been used
often the substation voltage level selection is based on or is extensively in Germany, Sweden and some other countries.
dictated by the acceptable unbalanced voltage levels which The lower frequency at the locomotive will increase the
have to be supplied by the utility. Because of large traction size and the weight of the locomotive slightly. The cost
loads (60 - 100 MVA), the US utility grid would have to would also increase slightly. Higher weight of the electric
supply the power from a short circuit duty source of about locomotive would improve the traction.
10,000 MVA. This short circuit duty source is only
available at 230 KV substations or above. The unbalanced CONCLUSIONS
load also generates negative sequence currents and the
substation will have to be separated adequately from the What America needs is an optimized system which will
generators. A balanced load would have to be supplied by a enable electrification at the lowest overall cost including the
high voltage system so that the traction load is separated railway electrification costs, the electrical utility costs and
from the other customers or the generators. the associated civil engineering costs. The electrical utility
With a low frequency traction system, the load will costs can become significant to meet the power quality
appear as a balanced load on the utility system. There requirements and needs to be included when considering
would be little unbalanced voltage or current problems. The the overall cost of railway electrification. This will reduce
frequency conversion system would also separate traction the overall investment required by the railway industry.
load from the rest of the customers. Learning from experience with low frequency, low voltage
electrification systems such as those utilized in Sweden
could enable the US to select an optimum, cost effective [9] ANSI C84.1 -1989, Appendix D, Polyphase Voltage
railway electrification system. Unbalance

NOTE [10] IEEE Standard 519-1992, “IEEE Recommended


This paper represents the views of its author and Practices and Requirements for Harmonic Control in
does not necessarily represent the views of Southern Electrical Power Systems.”
California Edison Co. or its parent organization SCE Corp.
[11] Bharat Bhargava, “What America Can Learn from
REFERENCES Railway Electrification Systems in Europe,” presented at
the 1994 Mass Transit Conference at Dallas, Texas,
[1] Ali F. Imece, Hubert Potard and John P. Daniel, October, 1994.
“Electromagnetic Impact of Railway Electrification”
presented at the 1994 Mass Transit Conference held in Bharat Bhargava
Dallas, Texas, in October, 1994.
Mr. Bharat Bhargava is a Senior Engineer in the
[2] J. J. Burke, A. P. Engle, S. R. Gilligan and N. A. Transmission / Substation Engineering Reliability Group
Mincer,“Increasing the Power System Capability of the 50 of the Southern California Edison Company in Rosemead,
KV Black Mesa and Lake Powell Railroad through California. He is actively involved in transient analysis and
Harmonic Filtering and Series Compensation”, IEEE paper power system studies such as SSR, System Dynamics,
No. F79284, presented at the IEEE Winter Power Meeting, Power System Stabilizers, Power Quality, Railway
New York, February 4-9, 1979. Electrification, capacitor switching studies, etc. Mr.
Bhargava has been involved in several research projects
[3] Tristan Kneshke, “Power Supply Systems for such as the NGH SSR protective device, and recently in the
Electrification of the New Jersey Coast Line,” IEEE Paper procurement, installation and testing of an Energy Source
No. CH2617-5/85/0000-0029 in IEEE Publication No. Power System Stabilizer for a 10 MW/40 MWH Battery
85CH2167-5 presented at the Joint IEEE/ASME Railroad Energy Storage System at Chino Substation. Mr. Bhargava
Conference in New York, New York, in April 1985. was a member of the team from SCE that visited four
European countries in December 1991 to study the various
[4] Tristan Kneshke,“ Simple Method for Determination of railway electrification systems in Europe. This paper is
Substation Spacings for AC and DC Electrification based on that visit.
Systems”, IEEE Paper No. CH2207-9/85/0000-0274 in Mr. Bhargava graduated from Delhi University in 1961
IEEE Publication No. 85CH2207-9 presented at the with a Masters from Rensselear Polytechnic Institute in
Industrial Application Society annual meeting held in 1976. He worked with UP State Electricity Board in India
Toronto, Canada, in October, 1985. from 1961 to 1975. Mr. Bhargava is a Senior Member of
IEEE PAS, IAS and Vehicular Societies, and a Member of
[5] Tristan Kneshke, “Substation Spacing for AC CIGRE.
Electrified Railroads - Some Influencing Factors,” IEEE
Paper No. 82-RT-4 in IEEE Publication No. 82-CH1778-0
presented at the Joint IEEE/ASME Railroad Conference in
Erie, Pennsylvania, in April 1982.

[6] P Stecuik, J. J.Burke, “The Impact of Railroad


Electrification on Utility System Power Quality”, presented
at the 1994 Mass Transit Conference held in Dallas , Texas
in October, 1994.

[7] Tristan Kneshke, “Control of Utility System Unbalance


Caused by Single Phase Electric Traction”, IEEE Paper No.
CH2060-2/84/0000-0259 in IEEE Publication No.
85CH2060-2 presented at the Industrial Application Society
annual meeting held at Chicago, Illinois in October, 1984.
[8] R. Bedrune , F. Gallon, A. Maher, J. S. Finn and J. M.
Lucas, “Load Balances for the Channel Tunnel”, CIGRE
1992, Paper No. 36-207.
View publication stats

Das könnte Ihnen auch gefallen