Approved Revised Estimate Actual Work Done

SL No. Name of work


Estimate Amount Amount Estimate Amount

Estimate for shifting of HT/LT Line from Petrol


a 1079050 1025308 1025308
pump to Reliance tower for widening of NH-53
Estimate for shifting of HT/LT Line from Khairapali
b police Beat to Chilanti Nala due to widening of NH- 1178698 1177985 1177985
53
Shifting of HT/LT Line from Khindo Stone Kuanri to
c 957520 929359 929359
Dhiramunda Bus Stand for widening of road
1 Shifting of HT/LT Line from Haladia Khol to
d 437635 426469 426469
Chhatripita for widening of road
Shifting of HT/LT Line from Udayapur Forest Camp
e 847139 797170 797170
to Udayapur Club for widening of road
Shifting of HT/LT Line from Sankhajyoti to PGCIL
f 896004 908600 908600
Siva Mandir for widening of road
Shifting of HT/LT Line from Kushakhalia High
g School to Kushkhalia Play ground for widening of 917262 1108068 1108068
road
Estimate for shifting of HT/LT Line & Sub-station
a from Rengali Check post to Film Hall Chhak in 1168335 1372091 1372091
RHEP area of OHPC
Estimate for shifting of HT/LT Line & Sub-station
b from Film Hall Chhak to Irrigation guest house in 1917298 2328308 2328308
RHEP area of OHPC
2
Estimate for shifting of HT/LT Line & Sub-station at
c 1808402 1676954 1676954
Film Hall Chhak in RHEP area of OHPC
Estimate for shifting of HT/LT Line & Sub-station
d from Erectors Hostel to Rengali G.P office in RHEP 1655064 1578158 1578158
area of OHPC
Esti. For supply and erection of street light poles,
3 lights, cables and accessories, etc. from PGCIL 1385860 1612055 1612055
temple to PGCIL main gate
Estimate for shifting of Line & substation under
4 16559137 17474452 17474452
Rengali electrical section of TED, Chainpal
Kaniha medical to Godibandha Chawk (5nos
5 4353155 4353155 3042995
estimate )
Sub Total 35160559 36768132 35457972
PHD Utilities (Revised)
Estimate for repair & restorationof drinking water
utilities( laying of pipe line & installation of tube
1 240000 240000 240000
wells) from Khairpalli to Ahalya Chowk under
Reamal Block
Shifting of Civil Water supply structure of RHEP at
2 3078476 3078476 2885900
R.D Site
Sub Total 3318476 3318476 3125900
Total (A) 38479035 40086608 38583872
(B) Additional estimate :
(i) Electric Utility
Estimated Supervision Actual Work Done
SL No. Name of work Total Amount
Amount Charges Payable Estimate Amount
Estimate for shifting of LT Line & Sub-station at
a 2098644 125918
village Patharmunda 2224562 0
Estimate for shifting of LT Line & Sub-station from
b 2255092 135306
Tahasil to Gouda Sahi 2390398 0
Estimate for shifting of LT Line & Sub-station at
c 2031312 121879
village Kaniha 2153191 0
Estimate for shifting of LT Line & Sub-station at
d 3483100 208986
1 village Jharaberani 3692086 4919180
Estimate for shifting of LT Line & Sub-station at
e 4303689 258221
village Hanumanpur 4561910 6184803
Estimate for shifting of LT Line & Sub-station from
f 2673376 160402
Hanumanpur to Radharamanpur Petrol Pump
2833778 3224645
Estimate for shifting of LT Line & Sub-station from
g 2663592 159815
Kalandiprasad to Kandhal Mangal Mandir 2823407 3212843
Sub Total 19508805 1170527 20679332 17541471
Replacement of damaged M.S pipes with G.I pipe
2 12360821 741649 1563313
line in different places under Kaniha Block
13102470
Shifting of Civil Water supply structure of RHEP
3 from Km 263/560 to 264/500 under RHEP, Rengali 2380803 0 0
dam 2380803
Shifting of replacement of Civil Water pipelines
4 from Km. 263/560 to 264/339 at Rengali Dam site 1062635 63758 0
colony 1126393
Sub Total 15804259 805407 16609666 1563313
Total (B) 35313064 1975934 37288998 19104784
Grand Total ( A+B) 7,73,75,606 5,76,88,656