As per contract!

Checking and testing of equipment and construction


to confirm that the installation is in accordance with
Please remember! Definition drawings and specifications and ready for pre-
Can vary from client to client and plant to plant! commissioning OR commissioning in a safe manner
and in compliance with project requirements.

Visual inspection for complete and correct


installation

Verification of name plate details at tanks, vessels,


rotating equipment and other machines

Internal inspection of tanks and vessels


= Construction Completion Hydrostatic test of vessels and tanks
Planning Mechanical
= Ready for Pre-Commissioning Vendor representatives for large and/or complicated
1. MC - Mechanical Completion equipment
Construction & Commissioning Team
P&ID Checking Dimension control
Construction, Hydro Testing & Mechanical
Completion Testing done Pre-Commissioning Bolt tensioning
Commissioning Preservation
Start-Up Example 2 NDT done (nondestructive testing)
Initial Operation Pipe supports completed
Performance Test The 9 Key Elements Removal of all items subject to damage during
of flushing, cleaning and pressure testing
Post Commissioning
Successful Blowing
Plant Commissioning
Flushing

Element 2 Piping Chemical cleaning


- MECHANICAL COMPLETION - Drying

Preservation

Reinstatement
= Ready for Pre-Commissioning Planning
Bolt tensioning
Construction Team 1. Construction Completion
(Insulation)
Construction & Hydro Testing done P&ID Checking
(Flow coding)
Pre-Commissioning Typical Tasks
Structural Inspection of all supporting structure
= Ready for Commissioning Cable trays
Construction & Commissioning Team 2. MC - Mechanical Completion Cable tray supports
Example 1
Construction, Hydro Testing, Mechanical Completion Commissioning Cable tray fill
Testing & Pre-Commissioning done
Start-Up Cables
Inspection
Initial Operation Bend radius

Performance Test Wiring


Electrical
Post Commissioning Termination

Grounding

Megger testing Cable trays

Cable tray supports

Cable tray fill

Cables
Inspection
Bend radius

Wiring

Termination
As per contract!
Grounding
What is included? Instrumentation
Validation of instruments
Can vary from client to client and plant to plant!
Validation of valves

Loop checks

Flushing of tubing

Tightness test of tubing