MANPOWER CAPABILITIES

1 man can excavate 0.72 cu. m. per day

1 man can backfill and compact 1.0 cu. m. per day

1 man can haul-out 2.0 cu. m. per day

1 man can spread and compact 1.0 cu. m. per day

2 men can accomplish 0.50 cu. m. per day

1 Mixing crew consist of 14 men: Mason = 2; Mixer Operator = 1; Carpenter = 1; Laborer = 10

1 Masonry crew (1 Mason & 1 Helper) can install 75 pcs of 4” CHB per day.

1 Masonry crew (1 Mason & 1 Helper) can install 50 pcs of 6” CHB per day.

1 Masonry crew can plaster 6.0 sq. m. per day.

1 Painter and 1 helper can consume and paint 1 gallon per day

1 Steel man and 1 helper can install 200 kgs. per day.

*For laying 8” x 8” tiles: 1 Crew (1 Mason and 1 helper) can accomplish 72 pcs per day

*For laying 12” x 12” tiles: 1 Crew (1 Mason and 1 helper) can accomplish 40 pcs per day

*For installation of longspan coloroof: 1 Crew (1 carpenter and 1 helper) can accomplish 32.7
LM per day.

*For Fabrication and installation of gutter, ridge roll, hip roll and valley roll: 1 Crew (1 carpenter
and 1 helper) can accomplish 2 sheets per day.

*For fabrication & installation of steel truss and purlins with round bar sag rod: 1 Crew (2
welders, 2 fitters & 2 helpers) can accomplish 335 kgs per day

*For installation of door jamb: 1 Carpenter can install 40 Bd. Ft. per day

*For installation of plywood ceiling: 1 Carpenter & 1 helper can accomplish 16 m2 per day

*For installation of ceiling joists: 1 Carpenter & 1 helper can accomplish 33 Bd. Ft. per day

*For installation of Water Closet: 1 Plumber & 1 helper can install 1 set per 2 days

*For installation of Lavatory: 1 Plumber & 1 helper can install 1 set per 1 ½” day
*For installation of Shower head and valve: 1 Plumber & 1 helper can install 1 set per ½” day

*For installation of sewer line of 1 T&B: 1 Plumber & 1 helper can finish in 2 days

*For installation of Kitchen Sink: 1 Plumber & 1 helper can install 1 set per ½” day

*For installation of PVC pipes and fittings leading to the septic tank and fitting in the septic: 1
Plumber & 1 helper can finish the installation of 1 unit in 1 day

*For installation of soap and toilet paper holder: 1 Mason & 1 helper can install 1 soap & toilet
paper holder in 1day

*For installation of Faucet: 1 Plumber & 1 helper can install 1 pc in 2 hours

*For installation of water line of 1 T&B: 1 Plumber & 1 helper can install the water line in 1 day

*For installation of ½” PVC Pipe & ¾” RSC Pipe w/ outlet boxes: 1 Electrician & 1 helper can
install 60 LM per day

*For installation of conduits with outlet boxes: 1 Electrician & 1 helper can install 81 LM per day

*For installation of service cap & conduit: 1 Electrician & 1 helper can install 1 pc per hour

*For installation of Electrical Wiring: 1 Electrician & 1 helper can install 100 LM per day

*For installation of Circuit Breaker: 1 Electrician & 1 helper can install 1 set of circuit breaker in
1 day.