2. ABBREVIATIONS
3. ASSUMPTIONS
4. COMMISSIONING PREREQUISITES
7. REFERENCES
8. ATTACHMENTS
Yanbu Aramco Sinopec Export Refinery Page 2 of 13
SIGNATURES:
------------------------------------------
------------------------------------------ ------------------------------------------
------------------------------------------ ------------------------------------------
Yanbu Aramco Sinopec Export Refinery Page 3 of 13
The Purpose of this SOP is limited to the Commissioning of Phenolic Sour water Storage
Tank 142-D-0022 by Fire water which includes:-
B. MRT and Commissioning of Phenolic Sour water stripper feed pumps 142-G-
1022;142-G-0023;142-G-2022 :
1. Leak /Hold test of Phenolic sour water stripper feed pumps 142-G-022/2022/0023
Suction/Discharge line.
2. MRT of Pumps and followed by commissioning 142-G-1022; 142-G-0023; 142-G-
2022 will be done by circulation through SWS plant and receiving to tank 142-D-
0022.
The Circulation inside SWS will be done through 5 No. of loops. Loops are divided by
Loop-1: From Phenolic Sour water stripper feed pumps 143-G-1022 to Sour water stripper.
Loop-2: From Sour water stripper to Stripper bottom pump 142-G-1026A/B suction valve.
Loop-3: From Phenolic sour water Stripper bottom pump 142-G-1026A/B to De-
gassing drum startup line 8" isolation valve.
Loop-4: Phenolic Degassing drum to static mixer 142-IM-0021 at SWS B/L
Loop-5: Static mixer 142-IM-0021 in SWS to Phenolic tank inlet valve.
Note: Loop-1activity is under tank farm operations, while Loop-2/3/4/5 is under control of
SWS. Flushing to be done till get clear water at every loop end point.
2. ABBREVIATIONS:-
3. ASSUMPTIONS:-
4. COMMISSIONING PRE-REQUISITES:-
Safety Precautions: -
Outside Operators (OSO) and all other involved staff must use PPE’s as listed below:-
Basic PPE’s First Aid Emergency Equipment
Sr. No.
1. Helmet
2. Goggles First Aid Box
3. Safety Shoes
4. Hand Gloves
5. Uniform
6. Ear Muffs / Ear Plugs
7. Personalized H2S Monitor
Use caution when opening bleeders and vents.
No Mobile Phones are allowed in the Tank Dyke area.
No Vehicle Movement is allowed inside the Tank Dyke area.
The entire Phenolic Sour water Tank Receipt area is declared as NON-SMOKING Zone.
Ensure tank shell manhole closed tightly
Yanbu Aramco Sinopec Export Refinery Page 7 of 13
Environmental Precautions:-
Never drain hydrocarbon to the atmosphere.
Clear all hydrocarbons to a closed system to prevent exposure to toxics and to protect
the environment.
Prevent Soil contamination due to leak from valves/flanges/pipelines:
Contain the leak on priority basis.
In the meantime, drum/tray is to be placed below the leakage to collect liquid
hydrocarbon
Collect contaminated soil in drums & send to hazardous waste disposal site.
Spill Management (Oil Containment) Team is available with all the required
consumables.
Emergency Handling:-
During receipt if any abnormality observed then stop the receipt and transfer the tank
quantity to another tank using Phenolic sour water Feed pump.
8. COMMISSIONING PROCEDURE: -
Detailed procedure is given below:-
Action By :
Sr. No. Description Start
Name End Time Sign
Time
A. Commissioning of Phenolic Sour water Storage tank 142-D-0022
Commissioning Activities
Ensure clearance is received from production
planning department/Utilities & off sites for Fire
water receipt from Utilities to feed tank 142-D-
0022.
1
Initial tank to be filled up to 3.5 meter level.
Calculate the Quantity and approximate flow to
calculate no of days require filling the Tank at
desired level.
Yanbu Aramco Sinopec Export Refinery Page 8 of 13
Action By :
Sr. No. Description Start
Name End Time Sign
Time
Ensure commissioning check list for Fire water
receipt from Utilities to Phenolic sour water feed
2 tank 142-D-0022 is filled prior to start
commissioning activities.
Check list attached as Appendix-VI
Ensure Walk through to be done for entire system
including tank inlet line. Ensure no vent and drain
3 points are opened and it shall be properly
plugged, no short bolting, gasket missing at flange
joints, ensure proper pipeline support etc.
Tank should not be commissioned in inclement
4
Weather condition.
Ensure that all Instrument are inline and in
healthy condition for Tank 142-D-0022
Ensure tank level high and high-high alarms are
5 enabled to monitor tank level to avoid tank
Overflow.
Ensure all interlocks are healthy and no trip logic
is bypassed and if it require, it has to be approved.
Confirm the receipt plan for Fire water to fill the
pipeline. Ensure connection done at 6” sump
6
drain header for filling up fire water to Phenolic
sour water Tank 142-D-0022
Ensure that one operator is available near tank
7 Platform with “BRAVO” for effective
Communication and fast action response.
Note down Tank parameter like Level,
8
Pressure , Temperature etc.
Ensure tank inlet 10” valve, tank outlet 12” &
Floating skimmer line outlet 6” isolation valves are
closed condition.
Ensure R/D header connection with Suction of
9
142-G-1022, 142-G-0023, 142-G-2022 suction line
10” Valve located at outside dyke area should be
closed.
Action By :
Sr. No. Description Start
Name End Time Sign
Time
Calculate the time required to fill the system to
Phenolic sour water feed tank 142-D-0022 as per
Receipt flow rate.
12 Walk through the system to detect any
leakage from flanges, vents, drain, etc.
Monitor tank bottom area, nozzle flanges,
etc. for any leakage.
Monitor tank level, pressure and confirm PCV-
13
0532A & PCV-0532B functioning properly
Once level reach around 2 m stop receipt. Close
14 fire water supply line and then 6” sump drain
valve.
Monitor the tank condition at top and bottom
15
side by thorough round for any possible leak.
Manually gauge the tank and check for any
difference between manual dip and LT reading. If
16
difference is more ~ +/- 5 mm, it has to be
rectified.
A. MRT and Commissioning of Phenolic Sour water stripper feed pumps 142-G-1022;142-G-
0023;142-G-2022:
LOOP-1
Ensure that all Instrument are inline and in
healthy condition for Pumps 142-G-1022 / 2022
/0023
17
Ensure all interlocks are healthy and no trip logic
is bypassed and if it require, it has to be approved
Drop down Sour stripper feed pump discharge
18 header Spool piece near FIT-1000 to check water
and to clean header
Confirm the plan from production planning and
Sulphur for phenolic sour water to fill the pipeline.
19
Ensure line up from Phenolic sour water Tank 142-
D-0022
Ensure that one operator is available near tank
20 Platform with “BRAVO” for effective
Communication and fast action response.
Ensure Isolation valves of 6” header joining from
Non-phenolic water pumps 142-G-0002A/B to
21
discharge of 142-G-1022 discharge line are
closed/blinded
Yanbu Aramco Sinopec Export Refinery Page 10 of 13
Action By :
Sr. No. Description Start
Name End Time Sign
Time
Note: First Commissioning of Any one pump from
142-G-1022/2022/0023 to be carried out. We will
22 consider case of 142-G-1022 for commissioning.
For Rest pumps, procedure steps to be followed
are similar.
Before start filling header through gravity flow to
fill the system from Phenolic Sour Water storage
tank to Phenolic Sour water stripper feed pump
142-G-1022 ensure following valves are open for
142-G-1022
12” manual isolation at tank 142-D-0022
out let
10” suction manual isolation valve of 142-
23 G- 1022
Ensure the manual warm up bypass valve
1” for NRV on 142-G-1022
Pump casing vent valves discharge to
OWS.
Ensure following valves are close for 142-G-
1022/2022/0023
8” manual isolation at discharge line of
142-G-1022
Keep pumps casing vent valve open to ensure that
the air removed from the system and to monitor
24 receipt of the phenolic sour water from tank to
phenolic sour water stripper feed pumps 142-G-
1022.
Communicate with Stripper feed (Train 1 & 2) PO
about commissioning activity and gradually filling
the system by gravity before utilizing Phenolic
Sour water pump 142-G-1022
Ensure pumps 142-G-1022/2022/0023
25 auxiliaries are lined and healthy
Ensure that all pump permission to start
interlocks are healthy
Ensure tank level is sufficient to assure
minimum NPSH requirement of pumps.
Action By :
Sr. No. Description Start
Name End Time Sign
Time
Confirm receiving of Non-phenolic sour water,
27 close ¾” LPD and then gradually fill the system
then continue filling the system
Monitor the pressure differential indicator around
28 the pumps suction strainer to ensure that the
strainer is clean.
Once suction header of 142-G-1022 is filled,
29 discharge header to be filled and air to be
removed from the system.
Ensure from Sulphur operations that 142-FCV-
1000 upstream isolation valve removed and hose
connected to drain for flushing.
1” Vent valves of discharge header & ¾” LPD to be
30 keep open till air removal carried out from the
system.
Ensure 8” discharge manual isolation valve of 142-
31
G-1022 is open partially.
32 Start Phenolic sour water pumps 142-G-1022
Note :
After startup of pump, monitor pressure, Ampere,
DE/NDE side temperature and vibration for motor
and pumps etc. Check for any abnormalities like
seal leak, vibration, abnormal sound etc.
Ensure from Sulphur operations that flush water
33 coming out from 142-FCV-1000 upstream
isolation valve routed to open drain channel.
Continue the pump running till get clear water.
34
Water sample to be checked visually for clean.
If observed clear water from flushing point,Stop
35 the pump 142-G-1022.The lOOP-1 flushing activity
is completed.
LOOP-2-4 flushing
Action By :
Sr. No. Description Start
Name End Time Sign
Time
7. REFERENCES
Unit 142 – P&IDs
Phenolic Sour Water Storage Tank P&ID no. 142-SP1-PE-PID-0029.
Sour Water Stripper Degassing Drums & Tank PFD no.142-SP1-PE-PFD-0001.
Sour Water Storage Tank Stream Summaries PFD no.142-SP1-PE-PFD-0002
Sour Water Storage Tank Stream Summaries PFD no.142-SP1-PE-PFD-0003.
Simplified Process Flow Diagram – Degassing Drums and Storage Tank no. 142-YER-PE-
PDB-0001
Unit Operating Philosophy 142-YER-PE-DOP-001
Unit 143 – Operating Manual Volume 1 – 143-SP1-PE-OPM-0001
Unit 143 – Operating Manual Volume 2 – 143-SP1-PE-OPM-0002
Unit 148 – P&ID
Interconnecting Pipe ways SWS interconnecting II- 148-EP3-PE-PID-0267
Material Safety Data Sheet
Equipment Data Sheet
8. ATTACHMENTS:-