Sie sind auf Seite 1von 2

CLIENT

CONSULTANT
PROJECT
TITLE Data sheet for Heat Exchanger
DOC. NO.
A OPERATING CONDITIONS
FLUID 1 (HOT) FLUID 2 (COLD)
1 ITEM TRIM COOLER/HEAT EXCHANGER
2 TYPE SHELL AND TUBE HEAT EXCHANGER
3 QUANTITY NO. 1
4 TAG NO. xxxxxx
5 OPERATINON CONTINUOUS
6 LIQUID
7 FLOW RATE KG/HR
0
8 INLET TEMP C
0
9 OUTLET TEMP C
10 MAX PR DROP ALLOWED kg/cm2g
11 CALCULATED PR DROP kg/cm2g
12 DENSITY OF FLUID kg/m3
13 SPECIFIC HEAT CAPACITY KCAL/KG. DEG. C
14 THERMAL CONDUCTIVITY KCAL/M.HR.DEG.C
15 VISCOSITY @ INLET CP
16 VISCOSITY @ OUTLET CP
17 OPERATING PRESSURE (NORMAL/MAX) kg/cm2g
18 DESIGN PRESSURE kg/cm2g
0
19 DESIGN TEMPERATURE C
20 FOULING RESISTANCE HR M^2 0C/KCAL
21 VELOCITY m/sec

B CONSTRUCTIONAL FEATURES (CASE-I)


1 NO. OF PASSES ON FLUID 1 SIDE
2 NO. OF PASSES ON FLUID 2 SIDE
3 GA DRAWING NO
OVERALL HEAT TRANSFER COEFFICIENT @
4 KCAL/HR M 2 OC
CLEAN CONDITION
OVERALL HEAT TRANSFER COEFFICIENT @
5 KCAL/HR M 2 OC
SERVICE CONDITION
O
6 LMTD C
7 HEAT EXCHANGED MCAL/HR
HEAT TRANSFER AREA REQUIRED
8 m2
(CALCULATED)
9 PROVIDED HEAT TRANSFER AREA m2
10 PLATE SIZE (WIDTH X HEIGHT) mm
11 NO. OF PLATES Nos
12 PLATE THICKNESS mm

13 CHEVRON ANGLE OF CORRUGATED PLATES

14 NOZZLE SIZE FOR FLUID1/FLUID2 NB


FLANGE TYPE FLUID1/FLUID2 (As per ANSI
15 NB
B16.5 RF Class 150)
OVERALL SIZE
16 mm
(LENGTH X WIDTH X HEIGHT)
17 INSULATION THICKNESS mm

C MATERIAL OF CONSTRUCTION
1 PLATES
2 FRAME
3 PRESSURE PLATE
4 GASKET (NON-ASBESTOS)
5 TIE NUTS/BOLTS
6 UPPER GUIDE BAR
7 LOWER GUIDE BAR
8 GUIDE BAR SUPPORT
9 MOC OF FLANGE (AT FLUID 1 / FLUID 2)

D DESIGN STD. & INSPECTION


1 DESIGN CODE
2 INSPECTION AND TESTING
3 HYDROTEST PR #

E NOZZLE SCHEDULE
NOZZLE NO. SERVICE SIZE (NB) SCHEDULE END CONNECTION
1 HOT FLUID INLET
2 HOT FLUID OUTLET
3 COLD FLUID INLET

4 COLD FLUID OUTLET

5 HOT FLUID SIDE VENT


6 HOT FLUID SIDE DRAIN
7 COLD FLUID SIDE VENT
8 COLD FLUID SIDE DRAIN
9 INTERCONNECTING HOT FLUID SIDE
10 INTERCONNECTING COLD FLUID SIDE

F ACCESSORIES & SERVICES


1 FOUNDATION BOLTS Vendor scope of supply
2 SPANNER FOR TIGHTENNING BOLTS Vendor scope of supply
3 COMMISSIONING SPARES vendor to provide detail list
4 MANDATORY SPARES vendor to provide detail list
RECOMMENDED SPARES FOR TWO YEAR
5 vendor to provide detail list
OPERATION

Das könnte Ihnen auch gefallen