U#1_SHUTDOWN_PLAN_BMD

ID Task Name Duration Start Finish % Material Status Apr '19 May '19
Complete 17 24 31 07 14 21 28
1 U#1_SD_BOILER_MAINTENANCE_DEPT. 14.99 days? 11-04-19 25-04-19 84%
2 Refractory repair 13.99 days 12-04-19 25-04-19 86%
3 Scaffolding at cyclone inlet #4 2.99 days 12-04-19 14-04-19 100% Completed
4 Cyclone inlet duct #4 bull nose refractory repair work & 7.99 days 13-04-19 20-04-19 100% Completed
bellow area ceramic wool filling
5 Scaffolding at combuster 1.99 days 14-04-19 15-04-19 100% Completed
6 Combustor rear and front refractory repair(SA Nozzle) 6.99 days 14-04-19 20-04-19 100% Completed
7 Scafolding removing at cyclone inlet & combustor 1.99 days 20-04-19 21-04-19 100% Completed
8 Close Inspection doors 3.99 days 20-04-19 23-04-19 95% U/p
9 Ignition for oil firing 1.99 days 23-04-19 24-04-19 0%
10 Hot curing/ Bed material filling 1.99 days 24-04-19 25-04-19 0%
11 Backpass Tube Replacement 9.99 days 11-04-19 20-04-19 100%
12 Tube spool replacement 6.99 days 11-04-19 17-04-19 100% Completed
13 Radiographic Test 0.99 days 15-04-19 15-04-19 100% Completed
14 Hydrostatic Test 4.99 days 16-04-19 20-04-19 100% Completed
15 Lignite Feeding System 13.99 days 11-04-19 24-04-19 92%
16 Bunker D cleaning & inspection 13.99 days 11-04-19 24-04-19 95% U/P
17 Bunker B cleaning & inspection 7.99 days 17-04-19 24-04-19 100% Completed
18 TF D cleaning & inspection 2.99 days 11-04-19 13-04-19 100% Completed
19 TF B cleaning & inspection 2.99 days 14-04-19 16-04-19 100% Completed
20 TF C cleaning & inspection 2.99 days 21-04-19 23-04-19 95% U/p
21 TF A cleaning & inspection 2.99 days 22-04-19 24-04-19 60% U/p
22 Trial 1.99 days 20-04-19 21-04-19 60% TF D, B, C trial done
23 Combustor Emergency drain line repair 12.99 days 11-04-19 23-04-19 100%
24 Rear side 3.99 days 11-04-19 14-04-19 100% Completed
25 Front side 3.99 days 14-04-19 17-04-19 100% Completed
26 Nozzle 1 replacement 2.99 days 17-04-19 19-04-19 100% Completed
27 PA Nozzle cleaning 6.99 days 17-04-19 23-04-19 100% Completed, DP test pass
28 Housekeeping in boiler 10.99 days 15-04-19 25-04-19 49%
29 Removing of ash bags, debris, scraps on platforms 7.99 days 15-04-19 22-04-19 65% At TF floor U/p
30 Removing of ash deposit on boiler roof 2.99 days 22-04-19 24-04-19 0% After TF floor comp.
31 house keeping in boiler top to bottom 1.99 days 24-04-19 25-04-19 0%
Page 1
U#1_SHUTDOWN_PLAN_BMD

ID Task Name Duration Start Finish % Material Status Apr '19 May '19
Complete 17 24 31 07 14 21 28
32 Housekeeping in ground floor(to continue) 10.99 days 15-04-19 25-04-19 60% u/p

Page 2