Beruflich Dokumente
Kultur Dokumente
As on 31.08.2010
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
A. Projects as per 11th Plan Programme
Central Sector
37 Parbati-II H.P. Civil & HM works: awarded to M/s Patel SEW JV (Dam & part -Slow progress of excavation
NHPC NR HRT) on 11.09.2002, M/s Himachal JV (HRT) on 11.09.2002, of HRT due to poor
12.10.1999/11.09.2002 CS M/s Gammon (I) Ltd. (Power House, Pr. Shaft, Surge Shaft & geological strata especially in
4x200 = 800 MW Execution part HRT) and M/s BJ_Techno-HAS(JV) (Jiwah Nallah) on Face-4. For treatment of
Broad Features : 11.09.2002. strata ahead of face-4 of
Dam – 85m High, 2009-10 Dam- Excavation completed 146930 cum Dam & Inlet structure HRT, work has been awarded
concrete gravity 12th Plan concreting out of 195977 cum completed. to M/s Jager-Bau.
HRT- 6m x 31.52km Head Race Tunnel- 26503 m excavation out of 31525m Treatment of fault zone
S.Shaft-17m x 130m completed Total Overt lining: 13521 m excavation out of ahead of TBM face.
P.Shaft-2 x 3.5m x2133m 31525m completed HRT exc. Feeder Tunnels (Jiwa Nalah): Modification of TBM has
P.House- Surface 3270 m exc.out of 4560m done. been completed.
Turbine- Pelton (Manihar-Pancha) 2107 m excavation completed out of 2252m. - Rock busting phenomena in
Switchyard- 400 kV (Jigrai-Feeder) excavation completed . Face-III in HRT.
Cost: Pressure Shafts- Inclined pressure shaft (left) – Ferrule erection - Ban on use of aggregate by
Original: 3919.59 694 m out of 1546m completed. Ferrule erection in right H’ble High Court of H.P.
Latest: 4231.64 Pressure Shafts completed. -Slide in Power House area
Power House -Excavation completed and 8295 cum sub in April, 04 June, 06, &
structure and super structure conc. completed out of 60000 cum. Feb, 07.
progress hampered due to PH back slope failure on 20/21st Feb.,
2007. PH hill slope stabilization likely to be completed by
Jan’11
E&M works: Earth matting in service bay along with Drainage
Pit & vertical lift from Unit-1 to service bay completed.
Placement of anchor hooks for lower pit liner of Unit#1 at EL
1328.40 m and At EL 1329.45 m.Installation of two nos rotor
erection plates in service bay area completed. Further work of
power house suspended due to slide of backhill slope has been
resumed with the ongoing rehabilitation work of damaged
concrete structure in service bay area.
15 Chamera-III H.P. Civil Works: awarded to M/s HCC Ltd. on 21.09.2005. - Labor agitation and stoppage
NHPC NR Diversion Tunnel: Works completed & river diverted on 5.3.07. of works for 3-4 months in
10.10.2003/01.09.2005 CS Dam Area: June, 2006
3x77= 231 MW Execution River bed excavation: 70921 cum completed out of 71000 cum. - Washing away of coffer dam
Broad Features : Dam concreting118943 cum completed out of 155485 cum. in July, 2007.
Dam –68m High, concrete 2010-11 Head Race Tunnel- Excavation completed and 13240m overt HRT lining & Dam alongwith
gravity 2010-12 concreting completed out of 15900m. associated HM works are
HRT- 6.5m x 15.9km U-1:03/11 Surge Shaft: excavation completed . critical.
S.Shaft-24m x 110m U-2:04/11 Power House- Excavation completed & concreting nearing - Rockfall from right side of
P.House-Uunderground U-3:05/11 completion. hill at Dam site.
Turbine- V.Francis (Unit-1 E&M works:Erection of Draft tube, stay ring and Spiral casing
Switchyard- 220 kV likely to has been completed in all three units. Barrel concreting of
Cost: slip to U#1,Unit-2 & Unit-3 has been completed.. Erection of Generator
Original: 1405.63 2011-12) & Turbine for Unit#1 is in progress and Lowering of Rotor for
Latest: 1727.58 Unit-I has been achieved. Erection of generator of Unit-2 is in
progress.
HM works: Works awarded to M/s Om Metals-SPML(JV) on
26.07.07. Design and drawing under finization.Erection of
penstock liner completed.
16 Parbati-III H.P. Civil works: Awarded to M/s Patel – L&T Consortium & M/s -Construction of Sainj By-
NHPC NR Jager – Gammon JV respectively on 15.12.2005. pass road.
12.11.2003/09.11.2005 CS Diversion tunnel: River diverted on 14.03.07. -Poor geology in HRT
4x130 = 520 MW Execution Rockfill Dam- - Delay in award of E&M
Broad Features : Left bank excavation: Completed. works due to decision on
Dam – 43m High, Rockfill 2010-11 Right bank excavation: Completed participation of Chinese
HRT- 7.25m x 7.98km 2011-12 Rockfilling upto 1300 m: Completed. companies.
S.Shaft-20m x 114m U-1:07/11 Rockfilling above 1300 m: 214100 cum completed out of 353000
P.Shaft-2 x 4.5m x345m U-2:08/11 cum.
P.House- Underground U-3:09/11 Intake Structure: 10810 cum conc. completed out of
Turbine- V.Francis U-4:10/11 240000 cum.
Switchyard- 400 kV Head Race Tunnel: 7608m excavation out of 7869m completed.
1
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Cost: Surge Shaft- Slashing completed.
Original: 2304.56 Power House: Benching completed.
Latest: 2095.68 Tail Race Tunnel- 1576 m U/S Overt Conc. out of 1619m
completed.
E&M Design & Engg. works in progress by M/s BHEL. EOT
crane installed in service bay and extended to Unit-I for full
capacity. Draft tube liner erection completed in all Units. Scroll
casing erection in Unit-1 is in progress . Progress of E&M work
suffers badely due to delay in re-deployment of erection
component by M/s BHEL.
HM works: Works awarded to M/s Om metals-SPML (JV)
on 26.07.07. D&E works in progress .
32 Kol Dam H.P. Gravity Dam: Excavation in Dam area completed. Excavation in - Clay/earth filling of main
NTPC NR Spillway area 110.38 lac cum out of 125 lac cum has been dam.
30.6.2002/Oct.2002 CS completed. - Grouting of dam galleries.
4x200 = 800 MW Execution Coffer Dam Filling: 11.35 lac cum filling completed out of 12 lac - Concreting of spillway.
Broad Features : cum.
Dam – 163m High, Rock 2008-10 Main Dam: 78.28 lac cum filling completed out of 110 lac cum.
& Gravell fill 2011-12 Clay filling – 13.78 lac cum out of 21 lac cum completed.
Penstock Tunnel: 4nos. U-1:03/12 Other materials filling – 64.50 lac cum out of 89 lac cum
6.45m dia, 1600m long U-2:03/12 completed.
P.House- Surface U-3:03/12 Spillway concreting: 2.09 lac cum concreting completed out of
Turbine- V. Francis U-4:03/12 4.16 lac cum.
(With Power Intake Concreting: 48707 cum out of 63400 cum has
Cost: efforts) been completed.
Original: 4527.15 Power House-: 1.075 lac cum primary conc. out of 1.08 lac cum
Latest: 4527.15 and 20740 cum secondary conc. Out of 20754 cum have been
completed.
Unit-1: Boxed up on 22.10.2009.
Unit-2: Runner lowered. Stator lowered on 01.12.2009.
Unit-3: Runner shaft lowered on 7.4.10.
Unit-4: Generator barrel casted on 22.1.10.
Penstock : Erection of penstock liners completed.
36 Ram Pur (SJVNL) H.P. CCEA clearance obtained on 25.01.2007. Civil works awarded to Slow progress of HRT due to
SJVNL NR Patel Gammon JV on 01.02.2007. LOI for E&M works issued to poor geology.
16.12.2005/25.01.07 CS BHEL on 16.09.08
6x68.67= 412 Execution 9.5 km out of 15.144 km HRT excavation has been completed.
Broad Features: River cut & cover- River has been diverted to the original course.
HRT-10.5m x 15.08Km 2011-12 Main Surge Shaft (149 m): Pilot Hole excavation completed on
S.Shaft- 38m x 149m 2013-14 23.07.2008. Widening has been completed upto 136 m depth.
P.House- Surface (09/13) Service Bay #1 & #2: Beams at EL 895 m i.e. roof level
Turbine- Francis completed. Model test of turbine completed. EOT embedded parts
Switchyard – 400 kV received at site.
Cost:
Original: 2047.03
Latest: 2047.03
14 Uri-II J&K Civil Works: awarded to M/s HCC Ltd., on 21.09.2005. The - Earthquake on 08.10.2005
NHPC NR work has earlier been severely hampered due to devastation by - Flash flood in March, 2007
11.2.2004/1.9.2005 CS earthquake on 08.10.2005. and May, 10d washing away
4x60 = 240 MW Execution Diversion tunnel: River diverted in January, 2007. of coffer dams.
Broad Features : Dam- Concreting completed above RBL. -Massive slide on the right
Dam – 52m High, 2009-10 Open Channel & Desilting Chamber: side of Dam in January, 08.
concrete gravity 2010-12 37433cum concreting out of 56845 cum completed. -Widening of NH 1A by
HRT- 8.4m x 4.27km U-1:02/11 Head Race Tunnel: BRO.
S.Shaft-25m x 78m U-2:03/11 Benching excavation: 4219 m out of 4233 m completed. - Collapse of bridge being
P.House- under.ground U-3:07/11 Overt lining: from face-I, II & III is in progress. 4104 m constructed in river Jhelum in
Turbine- V. Francis U-4:08/11 completed out of 4233 m. Nov, 2008.
Switchyard – 400 kV (Unit-1 & Power House: 16160cum concreting out of 21878 cum - HM & E&M works are
Cost: 2 likely to completed. critical.
Original: 1724.79 slip to Surge Shaft excavation: Completed.
Latest: 1583.93 2011-12) TRT Excavation: 3599 m heading excavation completed out of
2
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
3615 m and 3502 m benching excavation completed out of
3615 m.
E&M works: Design & Engineering as well as fabrication works
is in progress. Erection of DT liner in Unit-1, 2, 3&4 completed.
Erection of Spiral casing and Pit liner in Unit-1and Unit-2 & 3 has
been completed and is in progress in U-4.
HM works: Ferrule erection is in progress . 1st stage & 2nd stage
embedded parts is in progress.
13 Chutak J&K Civil works: awarded to M/s HCC Ltd. on 23.09.2006. -Extreme cold climate.
NHPC NR River diverted on 22.11.2007. - Delay in award of E&M
23.04.2004/24.08.2006 CS Barrage: Excavation completed. Concreting upto crest level works due to poor
4x11 = 44 MW Execution completed. participation and re-tendering.
Broad Features: HRT: Excavation and overt lining completed. - HM works package award
Barrage- 5 bays, 47.5 long 2010-11 Power House: 4408 cum concreting completed out of 12000 cum. delayed due to abnormal high
HRT- 5.9m x 4.370m 2011-12 Pressure Shaft: Vertical excavation of PS-I completed. Vertical price bid.
S. Shaft- 19m x 59m U-1:05/11 excavation of PS-2 completed.
P Shaft-3.25m x 37m (2 U-2:06/11 E&M works: Design & Engineering is in progress. EOT Crane
no) U-3:07/11 erection in Service Bay completed. Earthmat work
P.House- Underground U-4:08/11 completed.Erection of DT liner in all units completed.Concreting
Turbine- V. Francis in P/H of unit-1 has been completed upto EL-2720 (Machine floor
Switchyard- 33 kV level) . Spiral case of Unit-2 has been erected and hydraulically
Cost: tested and matching and welding of spiral case segment of unit-3
Original: 621.26 is in progress.
Latest: 953.75 HM works: Awarded to M/s PES Engineers Private Limited on
28.07.08. 1st stage embedded parts of Dam arrived at site.
Penstock liner erection work in unit-1,2,3&4 completed. Further,
bifercation segments of unit-3&4 has been erected.
12 Nimoo Bazgo J&K Civil works: awarded to M/s HCC Ltd. on 23.09.2006. -Extreme cold climate.
NHPC NR River diverted on 22.11.2007. - Delay in award of E&M
16,03.2006/24.08.2006 CS Dam: works due to poor
3x15 = 45 MW Execution Concreting upto crest level: Completed and Power Dam participation and re-tendering.
Broad Features: concreting 32328cum completed out of 38280 cum. - HM works package award
Dam –57.5m High, 2010-11 Cellular Wall: Concreting completed. delayed due to abnormal high
concrete gravity 2011-12 Power House: Excavation completed. 8964cum concreting price bid.
Spillway- 5 x 65m U-1:05/11 completed out of 32000 cum.
Penstock- 3 x 63mx3.3m U-2:06/11 E&M works: Stay ring of unit-2 has been erected. Hydraulic
P.House- Surface U-3:07/11 testing of spiral casing of U-3 to be started. Stay ring in U-3 is
Turbine- V. Francis being lowered.
Switchyard- 33 kV HM works: 1st stage embedded parts installed in Dam. Penstock
Cost: liner erection in unit 1 & 2 completed.Further, erection of
Original: 611.01 transition segments for penstocks 2 & 3 completed. Transportation
Latest: 908.64 of material from Jammu to project site is in progress.
45 Lower Jurala AP Works for construction of weirs was awarded to M/s Patel Engg. - Delay in award of E&M
APGENCO, A.P. SR and the work commenced in November, 2008. 367572/416700 works.
TEC in July 2007 SS cum excavation and 59164/157000 cum concreting done. - Shifting of Power House
6x40=240 (120 MW likely Execution Excavation works for approach channel, intake pool, power house location.
to slip) pit, tail race pool and channel was awarded to M/s Ramakrishna - unprecedented floods on
Broad Features: 2011-12 Reddy, Hyderabad in November, 2007. 4211345/4507150 cum 01.10.200
Intake: 18 vents (3 vents 12th Plan excavation done,
for each unit) 4.7m width, Works for construction of power house civil works including
P.House- Surface, switchyard, gates etc was awarded on 04.07.2009.
Turbine- Bulb Erection of Earth mat in power house pit in progress.
Design Head- 20m LOA for E&M works earlier placed on M/s CMEC, China is
SWYD- 220 kV January, 2008 was cancelled and re-awarded to M/s Alsthom
Cost: Project India Ltd. on 09.06.2008..
Original: 908.34 Erection of 70/10 T EOT crane at unloading bay completed.
Latest: 908.34
21 Pulichintala A.P. Dam is under construction by Irrigation Department, Govt. of A.P. - Slow progress of Dam.
APGENCO SR The works for dam construction were awarded to M/s SCL- - E&M works need to be
120 MW (4x30 MW) SS CR18G JV. Dam concreting works are in progress and about 50% expedited.
25.04.2007 Execution concreting is completed. - unprecedented flood on
Broad Features: The excavation of power house completed. 02.10.2009.
Design Head: 24 M 2010-11 The E&M works have been awarded to M/s BHEL in May, 2007.
Power House: Surface 2010-12 Materials are being received progressively at site.
Turbine : V. Kaplan U-1:03/11 Erection of Draft tube of unit-2 is completed & released for
Annual Energy: 220 MU U-2:06/11 concreting. Erection of draft tube liner for Unit-1 is in progress.
Cost: U-3:09/11
Original: 380 Crs.(PL 06- U-4:12/11
07) (Unit-1
Latest: 380 Crs.(PL-06- likely to
07) slip to
2011-12)
11 Kuttiyadi Addl. Extn Kerala Unit-1 commissioned on 23.5.2010. - Late forest clearances
b KSEB SR Unit-2- Pre-commissioning tests are in progress. delayed penstock works.
15.7.97 SS - Slow progress of penstock
2x50 = 100 Execution erection due to bad weather
Broad Features: and steep slope.
HRT- 3m x 666m 2006-07
S. Shaft- 5m x 75m 2010-11
Penstock- 2x U-1:23.5.10
7
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
2.05mx2144m (Comnd)
P.House- Surface U-2:07/10
Turbine- Pelton
Swyd- 110 kV
Cost:
Original: 220.50
Latest: 168.28
44 Pallivasal Kerala Contract has been awarded for construction of the project on turn- - Works are getting affected
KSEB SR key basis to consortium of M/s ESSAR – DEC – CPPL. due to poor maintenance of
2x30= 60 MW SS Progress/Total Qty: machineries by contractor.
Broad Features: Execution Intake structure excavation – 28398/33492 cum. - Land acquisition problem for
HRT: 3.50m X 3396m HRT excavation –2669/3396 m. penstock.
Surge Shaft: 7.0m X 49m 2010-11 Surge Tank/Forebay excavation – 3260/3710 cum & concreting - Slow progress of civil
Pressure Shaft: 2.50m X 12th plan 226/768 cum. works.
1019.20m TRT/Channel Excavation – 6280/7384 cum. - Change in alignment of Adit
Penstock: Pressure Shaft excavation : 712/1062 m. to HRT.
2.00mX1161.20m Surface penstock excavation –74238/122600 cum.
Power House: Surface Concreting – 4700/11375 cum.
Turbine : Pelton Fabrication & supply –1968/2057 m.
S.Yard: 220kV – Single Erection & testing – 703/2057 m.
bus P.H. excavation : 53350/64408 cum.
Cost: Tail race Channel: 6280/7384 cum.
Original: 242.95 + US$ Switchyard excavation & leveling – 13240/16610 cum.
57M
22 Bhawani Kattalai Tamil Works divided in three packages. (Barrage works, PH civil works, - Barrage & associated HM
Barrage-II Nadu and E&M works). PH civil package and E&M works awarded in works.
11.6.99 SR February, 2006. LOI issued for barrage civil works on 12.04.2007. - Erection of unit is critical.
2x15 = 30 SS The excavation of barrage and Power House completed.
Broad Features: Execution Concreting of barrage 71661 cum (90%) completed.
Barrage –22 gates Concreting of P.H. 109326/119409 (92%) completed. In
P.House- Surface TRChannel, 3075 cum lining out of 3950 cum has been
Turbine- Bulb 2006-07 completed.
Cost: 2011-12 E&M Works:
Original: 99.15 U-1:05/11 Erection of stay ring for both the units completed.
Latest: 400.59 U-2:06/11 Further erection is in progress.
23 Bhawani Kattalai Tamil Power House –Works divided in three packages. (Barrage works, - Barrage & associated HM
Barrage-III Nadu PH civil works, and E&M works). PH civil package & barrage works.
27.03.02 SR civil works awarded in Feb & Oct. 2006 respectively. E&M - Erection of unit is critical.
2x15 = 30 SS works awarded in November, 2006.
Broad Features: Execution Dam & Dykes/Barrage: Excavation & Concreting completed.
Barrage –22 gates Head Race Channel: Excavation completed and 6835/7500 cum
P.House- Surface 2006-07 lining completd.
Turbine- Bulb 2011-12 Power House: Concreting 103890/121175 cum (86%) done.
Cost: U-1:08/11 Tail Race Channel: 2575/3950 cum concrete completed.
Original: 99.75 U-2:09/11 E&M Works:
Latest: 398.60 EOT crane commissioned.
Unit-1 & 2: Erection of stay ring in progress.
24 Myntdu, Meghalaya Flash flood on 20.5.10 caused damage to already erected electrical Flash flood occurred on
MeSEB NER equipment. 20.5.10. E&M works is at
20.09.99/ SS Main Dam: Excavation completed and 328983 out of 332311 standstill since 10.05.2010.
2x42+1x42 = 126 Execution cum concreting completed.
Broad Features: HRT & HPT: Completed.
Dam –63m High 2006-07 Surge Shaft: Works completed.
HRT- 3316.46mx3.4m dia 2010-11 Surface Penstock: Excavation completed. 25435 cum out of
Power House- Surface U-1:05/10 27385 cum concreting completed. Fabrication completed.
Turbine- V. Francis U-2:08/10 Erection 3000.52 m out of 3129m completed.
Cost: 2011-12 Power House: Excavation completed. 17770/20362 cum
Original: 363.08 U-3:05/11 substructure and 2585/4050 cum super structure concreting
Latest: 965.93 (slipping to completed.
2011-12) E&M: Rectification of damaged equipment is under progress.
HM works: Erection of Radial gates is underway and 3nos out of
7 gates erected.
Tail Race: Excavation completed. 10325/15000 cum lining
8
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
completed.
33 New Umtru Meghalay Civil works awarded to M/s ITD Cementation (India) Ltd. in Dec. Extremely slow progress of
MeSEB, a NER 2007. Work resumed 5th Dec. 2008. civil works.
2x20=40 Order for HM works has been placed to M/s SEW Texmaco in
Broad Features: 2011-12 January, 2009. E&M works awarded to VA Tech Hydro
Diversion Structur-Gated 2011-12 (ANDRITZ) in Feb. 2009.
structure (FRL-130.1m, U-1:11/11 Surge shaft: Open excavation completed and balance boring work
MDDL-123.3m) U-2:12/11 of surge shaft 6800 cum yet to be taken.
HRT- 5m dia, 750m long
P.House- Deep Set
SWYD- 132 kV
Cost: 194.3 Cr.
194.3 Cr.
Private
25 Allain Duhangan H.P. Financial closure : Achieved on 21.11.2005 Both the units rotated.
AD Hydro Power Ltd NR All civil works except Duhangan HRT is compeleted. Transmission works are
20.08.02/Nov. 2006 (FC) PS Both the units rotated. lagging behind the schedule.
2x96=192 Execution Transmission Lines: Erection, Tower erection 550/580, Stringing
Broad Features: 130 km out of 175 km completed.
Barrage- 2007-08
HRT- x 3.7 km 2010-11
x 4.6 km U-1:08/10
P.Shaft- 2.8m x 1750m U-2:08/10
P.House- underground
Turbine- Pelton
Cost:
Original: 922.35
Latest: 922.35
26 Karcham Wangtoo H.P. Financial closure achieved on 30.3.2006.
Jaypee Karcham Hydro NR Design, engineering, procurement & construction contract
Corporation Ltd. PS awarded to M/s JAL on 09.07.2003. LOI for E&M works issued
31.03.2003/30.3.2006 Execution on 30.10.2007 in favour of Voith-Siemens – Adritz VA Tech
(FC) Hydro Karcham Wangtoo Consortium.
4x250=1000 2008-09 River diversion completed on 11.04.2007.
Broad Features : 2011-12 Main Dam: 994299 cum out of 1081500 cum excavation and
Dam – 98m Height U-1:08/11 497627 cum concreting out of 502800 cum completed.
HRT- 10.48m x 17.2km U-2:09/11 Intake: Excavation and overt concreting of intake tunnel
P.Shaft-4x 4.7m x291m U-3:10/11 completed. 150m invert lining out of 1558m of intake tunnel
P.House- underground U-4:11/11 completed.
Turbine- Francis HRT: Heading excavation completed and 16875 m benching,
Cost: 13817 m overt lining & 4761 m invert lining out of 16925m HRT
Original: 5909.59 completed.
Latest: 5909.59 Power House: Both the EOT cranes are in operation and unit No.
1 stator erection is in progress.
TRT: Excavation completed and 802 m out of 1273 m lining has
been done.
27 Budhil H.P. Financial closure achieved in March, 2006. HRT lining & E&M works
Lanco Green Power Pvt NR All works awarded and are under progress are critical.
Ltd PS River diversion works completed.
1.06.2005/ Jan, 06 (FC) Execution Dam : Excavation completed and concreting of 36000 cum out of
2x35=70 MW 50000 cum also completed.
Broad Features: 2008-09 HRT: 6270 m excavation completed and 2600 m concreting has
Dam-58m High 2010-11 also been completed.
HRT-4m x U-1:03/11 Power House: Excavation completed. EOT crane is in operation.
6028m\.House- U-2:03/11 Stator & rotor formation is in progress.
underground E&M Works: Works awarded to M/s Dongfong Electric
Turbine- V. Francis Corporation Limited, China. 80% supply completed.
Cost:
Original: 418.80
Latest: 418.80
28 Malana-II H.P. Financial closure on 03.08.2006. HRT works slow due to poor
Everest Power Pvt. Ltd. NR Dam: Excavation of dam completed and 77236/86000 cum geology.
15.10.2004 by HP Govt./ PS concreting done.
9
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
2x50=100 MW Execution HRT: Out of 4987 m of excavation, 4951 m has been completed
Broad Features: and 2727 m lining has been done
Dam –45.5m High 2008-09 Power House: All major civil works for both the units is
HRT- 3m x 4.874 km 2010-11 complete.
S. Shaft- 6m x 90m U-1:01/11 Pressure Shaft: 155/198m Horizontal pressure shaft completed
P. Shaft- 2.5m x 666m U-2:02/11 and 540/566 m vertical Pressure Shaft ferrule erection completed.
P.House- underground E&M Works: Both the units are boxed up and dry test is in
Turbine- Pelton progress.
Cost:
Original: 598.00
Latest: 598.00
34 Sorang H.P. Financial closure achieved in June, 2007. Difficult area, accessibility
Himachal Sorang Power NR Civil & HM works awarded to NCC – Maytas – SSJV consortium and availability of working
corporation Ltd. PS in June, 2007. period.
June, 2006/ Execution E &M works awarded to M/s Voith Siemens in June, 2007.
2x50= 100 MW All infrastructure works including bridge completed.
2012-13 Excavation of Power house is completed.
2011-12 Boring of main access tunnel, Adit to HRT and excavation of PH
U-1:09/11 cavern has been completed. 86% excavation of transformer cavern
U-2:10/11 completed.
56% boring of HRT has been completed
Land – Forest & Pvt. Land acquisition is in progress.
35 Shrinagar Uttarakha - Order for civil works awarded to M/s NCC-GVKPL consortium - Concreting of dam is
GVK Industries Ltd. nd on 11.06.07. critical.
14/06/2000/ FC NR - LOA for E&M works issued to M/s BHEL in April,2007. - E&M equipment delievery
4x82.5=330 PS - HM works awarded to M/s Precision Infratech Limited. to be co-ordinated with
Broad Features: Execution - Financial closure achieved on 3.8.2007. BHEL.
Dam –66.5m High, Progress/Total Quantity of various Activities:
concrete gravity 2005-06 - Diversion tunnel and NH-54 Road realignment completed.
HRT- 13m x 889m 2011-12 - Construction of coffer dam near Power House completed.
Penstock-4x 5.6m x 114m U-1:12/11 - Dam excavation on Right Flank upto EL550 m (100%)
P.House- Surface U-2:01/12 completed. Left Flank excavation EL 550 completed. Conreting
Turbine- Francis U-3:02/12 21.5% done.
Cost: U-4:03/12 - HRT excavation completed and lining 3.5% completed.
Original: 1699.12 - Power Channel excavation 73% & concreting 24.5% completed.
Latest: 2069.00 - Power House excavation completed and concreting in progress..
Unit Erection:
Unit # 1; Erection of spiral casing is in progress.
Unit #2: Draft tube erected.
Unit #3: Draft tube erection in progress.
Unit #4: Pit liner erection in progress.,
35 Maheshwar, M. P. CIVIL WORKS: R&R issues.
SMHPCL WR Spillway: Out of total concreting of 4.88 L.Cum, 4.82 L.Cum
30 12 96/ 29.9.2006 (FC) PS (98.7%) completed. Work has been taken up in all 30 blocks. Supply of equipment by
10x40= 400 Execution Construction up to crest level completed for 27 blocks. BHEL in sequential manner.
Broad Features: Power Dam: Out of total concreting of 2.12 L.Cum, 2.11L.Cum
Dam-35m High, concrete 2001-02 (99.5%) completed. Work has been taken up in all 10 blocks. Commissioning may get pre-
gravity 2011-12 Concreting of all the blocks completed up to top level. poned if commercial issues
P.Shaft-10x7.82m x 52m U-1:06/11 Power House: Out of total concreting of 1.95 L.Cum, 1.58 L.Cum with BHEL are sorted out
P.House- Surface U-2:07/11 (81.1%) completed. and timely delivery of
Turbine- Kaplan U-3:08/11 Tail Race Channel: Out of total concreting of 8800 Cum, 8243 equipment by BHEL.
Cost: U-4:09/11 Cum (93.7%) completed.
Original: 1569.27 U-5:10/11 Earth Dam (Left + Right): Out of total concreting of 7065 Cum,
Latest: 2449.20 U-6:11/11 5684 Cum (80.4%) completed.
U-7:12/11
U-8:01/12 HM WORKS: M/s Om Metals have been assigned the job of
U-9:02/12 design engineering and fabrication and erection of the gates.
U-10:03/12 Erection and commissioning of 22 nos. spillway radial gates out
(U-6 to 10 of 27 nos. completed.
with E&M WORKS: Electro-mechanical contract with BHEL made
efforts) effective on 25.06.2007.
EOT Crane: 3nos. crane operational from Unit#10 to Unit# 7.
Unit Erection:
Unit# 10: Rotor lowered. Boxing up is in progress.
Unit# 9: Scroll case concreting in progress.
10
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Unit# 8: Scroll case erection is in progress.
Unit#7: Erection of draft tube cone completed.
Unit#6 to #2: Draft tube knee erection completed.
Unit#1: Embedments and draft tube knee erection in progress.
Switchyard: Civil works almost completed. Equipment
installation in progress.
30 Chujachen Sikkim Financial closure achieved on 14.03.2007 - Flash flood on 16.04.2009
Gati Infrastructure Ltd, ER Civil works: awarded to M/s SEW & PRASAD (JV) Hyderabad washing away Rangpo coffer
Secunderabad PS on 09.03.2006. dam.
30.11.2004 (State Govt.)/ Execution Rongli Dam: All excavation & concreting works completed. - HRT & HM works are
2x49.5= 99 MW Rongli Intake excavation and concreting completed. critical.
Broad Features: 2009-10
Dam – 2010-11 Rangpo Dam Excavation about 97574/100,000 cum completed
Rampo- 48.5m High U-1: 02/11 and concreting of 49473/76000 cum completed. Intake excavation
Rongli- 41m High U-2: 03/11 completed and concreting 3975/6000 cum completed.
HRT- Surge Tank: Excavation completed & concreting 527/2600 cum
Rampo-3.3m x 2578m completed.
Rongli-3.5m x 2256m HRT: 7456.5/7937 m excavation completed. Invert concreting
Common-5.2m x 3225m 485m completed. Overt concreting 446 m completed.
S. Shaft-12m x 104m BF Valve: Excavation completed and concreting 616.5/900 cum
P.House- Surface completed.
Turbine- V. Francis Pressure Shaft: Excavation almost completed. Fabrication of
Cost: steel liners completed (328m).Erection of steel liner in progress.
Original: 448.76 Concreting & Grouting are in progress.
Latest: 651.50 H&M works: awarded to M/s PES Engineers Pvt. Ltd on
11.12.07.
Erection works in various phases of completion.
TRT – Excavation 7050/7300 cum & lining 5158/5292 cum
completed.
EOT crane is in operation.
Units: Both units boxed up.
Switchyard 11/132 kV: Completed.
37 Teesta-III Sikkim State clearance to the project accorded on 18th July 2005. TEC As per contract, the
Teesta Urja Ltd. (TUL) ER from CEA accorded on 12.05.2006. Environment and Forest commissioning of three units
12.05.2006 PS clearance have been obtained. Private and Forest land acquisition is in 2011-12 and other three
6x200=1200MW Execution has been completed. LOA for turnkey execution of the project units in 2012-13.
Broad Features: placed on the EPC consortium led by M/s Navayuga Engineering
Dam-Concrete with chute 2011-12 Company, Hyderabad and AIPL on 18.04.2007 and contract Project authorities have
spillway 60m high. 2011-12 agreement signed on 12.09.2007. intimated that all the six units
HRT- 7.5m dia, U-1: 12/11 Flushing Tunnel heading excavation has been completed. would be commissioned
13.325Km long. U-2: 01/12 HRT: 9.7/13.816 km excavation completed. 1.07 km lining during 11th plan (from August,
Press. Shaft- 3nos. 3.8m U-3: 02/12 completed. 2011 to January, 2012.)
dia. U-4: 03/12 Excavation of all the access tunnels to the Machine Hall, GIS hall Considering the present pace
Power House- Under U-5: 03/12 & TRI completed. of civil works & mobilization
ground U-6: 03/12 TRT: 75% excavation completed. done at site, it is possible to
Turbine- Pelton (U-4 to 6 The electro-mechanical works have been awarded to consortium commission the units as per
Cost: with led by M/s VA tech Hydro and the contract has been signed on the revised schedule,
Original: 5705.55 Crs. efforts) 18.10.2007. indicated by the project
Latest: 5705.55 Crs. Diversion tunnel: Excavation completed. authorities provided no major
Adits: Inlet Adit to Diversion Tunnel, Intermediate Adit to geological surprises /
Diversion Tunnel, Zero Adit to Intake, Adit to flushing tunnel, bottlenecks are encountered
Adit to desilting basin, Adit to Power House top, Adit 2,3,4 & 5 to and completion of E&M
HRT completed. 2731 cum/14019m excavation completed’ works is done for all the units
Pressure shaft: Inclined portion PS-1 345/450 and PS-2 well in time..
269/450 m completed.
Power House: MAT completed.
B. Projects likely to give benefits beyond 11th Plan
Central
1 Kishanganga J&K Infrastructure works are under progress.
(NHPC), J&K NR Revised CCEA approval accorded in December, 2008.
20.07.07 CS Turnkey execution of the project awarded to M/s Kishanganga
3x110 Execution Consortium with HCC ld. As lead partner, M/s Halcow group ltd.,
330 2016-17 UK as partner and M/s SELI SJZA Italy, M/s BHEL, M/s DSD
Cost: 2016-17 NOELL Gmbll Germany & M/s PES engineers Pvt. Ltd. As sub-
11
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Original: 3642.04 contractor on 22.01.2009
Latest: 3642.00 Diversion Work: 558m excavation completed out of 569m.
HRT Face-2: 21m excavation completed out of 2880m.
2 Pare Ar. P Civil works awarded to M/s HCC ltd. on 12.10.2009.
M/s NEEPCO NER Infrastructure & Pre-construction activities are in progress.
2x55 = 110 MW CS
Execution
12th Plan
State
3 Baglihar-II J&K Some works already taken up with Baglihar-I.
JKPDC NR Works have been allotted but yet to start.
3x150= 450 MW SS
Execution
2014-15
2014-15
4 Kashang-I H.P. Civil & HM works awarded to M/s HCC Ltd. in February, 2009
H.P. Power Corpn. Ltd. NR and effective date for commencement of works is 09.04.2009.
31.07.08 SS E&M works awarded to M/s Andritz India on 29.04.2010.
65 MW Execution Excavation of Adits, TRT etc. are in progress.
12th Plan
12th Plan
5 Thottiyar Kerala Construction works started. Infrastructure & Pre-construction
KSEB SR activities are in progress.
40 MW SS
Execution
12th Plan
12th Plan
Private
6 Tidong-I H.P. Civil works awarded in November, 2008.
M/s Nuziveedu Seeds NR Infrastructure & Pre-construction activities are in progress.
100 MW PS
Execution
12th Plan
12th Plan
7 Phata Byung Uttarakhand Work awarded on 14.02.2008 as EPC contract to M/s Lanco
M/s Lanco NR Infratech Ltd. With a construction period of 36 months.
06.10.2008 PS Approach roads to Dam U/S, D/S , Adit-II, Adit-III, surge shaft
2x38 MW = 76 MW Execution Top,,Power House and Gabni Gad completed and approach road
Broad Features: to vertical pressure shaft is in progress.
12th Plan Diversion Tunnel Excavation and concreting completed.
Dam – 26m high
12th Plan Dam concreting are in progress.
HRT- 3.2 m dia & P.H.: Heading excavation in progress.
9.38 km length
Pressure Shaft: 2.5m
dia, 662.25 m length
Turbine – Frances
8 Singoli Bhatwari Uttarakhand Civil works awarded on 6.5.2008.
M/s L&T NR River diversion – Excavation of diversion channel 13000/16488 m
11.07.2008 PS completed & concreting 200/500 m done.
3x33 MW = 99 MW Execution HRT &HRC: Excavation 725/11255 m completed.
Broad Features: Pressure Shaft: Excavation 80/485 m completed.
2013-14
2013-14
9 Teesta-VI Sikkim Infrastructure works such as roads and bridges are in progress.
LANCO ER Land acquisition is in process. Excavation works of Adits
27.12.2006 PS (1+2+3+4+4A+HRT-2) 290138/2447447 completed.
4x125= 500 MW Execution Surge Tank Excavation 59082/278183 completed.
Cost: Pressure Shraft:5606/22000 cum. completed.
Original: 3283.08 2012-13 In power house complex Excavation of Main access Tunnel,
Latest : 3283.08 12th Plan ventilation Tunnel, Adit to Transformer cavern, cable tunnel and
Broad Features: Adit to BFV chamber completed.
Barrage: 34.27m high TRT: 14056/354714 cum completed.
HRT- 2nos,13.7km long
12
Sl. Name of Project State Broad Present Status Remarks/issues
No Executing Agency Region
Date ofCEA clearance / Sector
Approval Status
Capacity (MW) Commng.
Broad Features Schedule
Cost (original/latest) (original/
Now Ant.
Pressure shaft: 4nos. 5.4m
dia. 130m av length,
13.325Km long.
TRT: 4nos 250m av
length, 8.5m dia.
Power House- Under
ground
Turbine- Francis
2012-13
2012-13
13