Beruflich Dokumente
Kultur Dokumente
1. Transformer
3. Parts of Transformer
Windings) :-
A)Primary winding (H.T.)
a) Heat sink
b) Oil
c) Breather
Insulation:-
a) Bushes
b) Sleeves
c) Oil
d) Insulation tape
e) Cotton tape
f) Paper tape
g) Press board
h) Bakelite pipe
I) Drum
Connectors:
a)Thimble
b) Ferrule
Here:
VP - is the Primary Voltage
VS - is the Secondary Voltage
NP - is the Number of Primary Windings
NS - is the Number of Secondary Windings
Φ (phi) - is the Flux Linkage
Size of conductor: Thin wire (Because this winding carries high voltage as well as
smallcurrent,Hence due toeconomicfactor we use thin wire for HT winding.)
Connections: Delta connections (Because in a 3 Phase supply we do not require
neutral wire for transmission so we always connect primary side of transformer in
Delta connections.)
Connections: Star connections (Because our L.T. terminals are output terminals, so
for distribution we must require a Neutral wire, which is only possible when we have
connected our L.T. terminals in Star connections.)
Insulation of Windings: A paper tape is used for providing insulation to both H.T.
and L.T. windings.
2. Core of Transformer
Material of core: Silicon Steel is the best ever material for transformer core.
Practically we place layer of varnish over the silicon steel limb for providing
insulation between the limbs.
Oil Natural Air Natural (ONAN) cooling is the most commonly used way of
transformer cooling. There are two important parts of ONAN cooling
1. Heat sink: A heat sink is basically a heat absorber, it is placed over the body
of transformer in contact with natural air. Heat sink is a hollow or pipe type
structure through which oil flows and the natural air contact helps to cool the
transformer oil.
1. Bushes: It is insulator which is used at both the input and output terminal of
transformer.
H.T. bushes
L.T. bushes
NOTE: while making internal connection of H.T. winding we always place a layer
of paper tape and two layers of sleeves for providing proper insulation.
3.) Paper Insulator: It is basically a big role of paper which is wound over the core
of transformer before placing L.T. winding.
4.) Paper tape: It is a small role of paper which is wound over the terminals with the
help of fevicol for providing insulation.
6.) Cotton tape: It is a small role of cotton which is wound over the paper tape for
providing proper insulation.
7. Pressboard or Cardboard: It is one of the most important insulator of
transformer. It is a hard cardboard which provide insulation to core and H.T.
internal connections and act as drum.
Connectors:
Both Thimble and Ferrule are connected with die. There are different materials for
connectors like copper and aluminum.
1. Thimble: It is used for making end terminals of output connection to H.T. and
L.T. winding.
2. Ferrule: It is similar to thimble,but it is used for making internal
connections of H.T. and L.T. winding.
Disassembling Of transformer
Transformer assembling
1. Clean the core of transformer by dry cloth or brush
2. Place cotton tape over the core of transformer for providing support to core.
3. Place1 2 -3 layers of insulation paper over the core for providing insulation to
L.T. winding and removing air gap between core and L.T. winding.
4. Place the L.T. winding over insulation paper.
5. Now place a cardboard drum having two layers over the L.T. winding (
Cardboard drum is used for providing proper insulation between L.T. and H.T.
winding otherwise L.T .and H.T. windings will get short circuited)
6. Now place the H.T. winding over the Cardboard drum.
(Our H.T. winding carries a very large amount of voltage so if we place
L.T. winding over H.T. winding then we have to provide a very high
insulation over H.T. winding to protect L.T. winding but this process is very
costly.
So, we always place H.T. winding over L.T. winding which requires less cost
for insulation between both the windings.)
7. Now check the air gap between H.T. and L.T. winding and remove it by
placing cardboard stripsbetween them.
(If we do not remove this air gap between L.T. and H.T. windings, then our
transformer will produce a large sound called Humming while operation)
8. Now place the core roughly and make temporary connections and check the
turns ratio of transformer
9. After making a proper turn ratio remove the core and make Delta connections
of H.T. winding with ferrule and properly insulate it with sleeves.
10 . Now place the transformer core properly in proper spaceprovided called
steps.
Note:Always follow the standard that the neutral terminal must be at the right
end.
15 Now again insulate the star connections by cotton tape.
16. Now again check the turns ratio by T.T.R meter.
17. Now place the transformer core inside the oven for whole night to remove
moisture content.
18. Now place the transformer windings inside the transformer body and
properly tight the nut bolts of windings withtransformer body so that the
windings will not move from there proper place while transportation.
19. Now place a cardboard between H.T. connections and transformer body
for providing insulation to H.T. side.
20. Now make the L.T. connections through brushes.
21. Place a over main tank of transformer to prevent moisture and oil leakage.
22. Now place the transformer cover over the transformer body and make the
H.T. connections through bushes.
23. Now put mineral oil inside the transformer body and fill whole of the
main tank with mineral oil.
24. Now properly place the transformer cover over the main tank of
transformer and tightly connect the nut, bolts of the transformer cover
with transformer body.
Cause of major fault in transformer.
1. Lack of transformer oil: With the passage of time transformer oil decreases so
due to this lack of oil transformer will not cool properly, which results in
heating of windings and cause damage to transformer.
2. Due to heavy load on a phase of transformer, it may cause in heating of L.T.
winding which results in melting of L.T. winding.
3. Due to loose connections of transformer.
Testing of transformer.
DVDF (Double voltage and double frequency)test:In this test double the rated
voltage and double the rated frequency is applied to the Transformer under test and
observed for its withstand capability usually for 1 min. Double voltage is applied to
test the Transformer withstand capability for higher voltages which are sometimes
occur in the form of lightning surges and faults on the transformer. But, practically,
no transformer is subjected to double the rated frequency as the frequency variations
are not allowed beyond 0.5% by the power supply grid controlling authority. In such
a case, is it essential to test the transformer at 200% i.e. double the rated frequency
conditions?
Open circuit test or no load test on a transformer is performed to determine 'no load
loss (core loss)' and 'no load current I0'. The circuit diagram for open circuit test.
Usually high voltage (HV) winding is kept open and the low voltage (LV) winding
is connected to its normal supply. A wattmeter (W), ammeter (A) and voltmeter (V)
are connected to the LV winding. Now, applied voltage is slowly increased from
zero to normal rated value of the LV side with the help of a variac. When the applied
voltage reaches to the rated value of the LV winding, readings from all the three
instruments are taken.
The ammeter reading gives the no load current I0. As I0 itself is very small, the
voltage drops due to this current can be neglected.
The input power is indicated by the wattmeter (W). But, as the other side of
transformer is open circuited, there is no output power. Hence, this input power only
consists of core losses and copper losses. But as described above, short circuit
current is so small that these copper losses can be neglected. Hence, now the input
power is almost equal to the core losses. Thus, the wattmeter reading gives the core
losses of the transformer.
In this test the LV side of transformer is short circuited and wattmeter (W),
voltmere (V) and ammeter (A) are connected on the HV side of the transformer.
Voltage is applied to the HV side and increased from the zero until the ammeter
reading equals the rated current. All the readings are taken at this rated current.
The ammeter reading gives primary equivalent of full load current (Isc).
The voltage applied for full load current is very small as compared to rated voltage.
Hence, core loss due to small applied voltage can be neglected. Thus, the wattmeter
reading can be taken as copper loss in the transformer.
Therefore, W = Isc2Req....... (where Req is the equivalent resistance of transformer)
Zeq = Vsc/Isc.
Therefore, equivalent reactance of transformer can be calculated from the formula
Zeq2 = Req2 + Xeq2.
These, values are referred to the HV side of the transformer.
Hence, it is seen that the short circuit test gives copper losses of transformer and
approximate equivalent resistance and reactance of the transformer.
The difference in voltage between the primary and the secondary windings is
achieved by changing the number of coil turns in the primary winding ( NP )
compared to the number of coil turns on the secondary winding ( NS ).As the
transformer is basically a linear device, a ratio now exists between the number of
turns of the primary coil divided by the number of turns of the secondary coil. This
ratio, called the ratio of transformation, more commonly known as a transformers
“turns ratio”, ( TR ). This turns ratio value dictates the operation of the transformer
and the corresponding voltage available on the secondary winding.
It is necessary to know the ratio of the number of turns of wire on the primary
winding compared to the secondary winding. The turns ratio, which has no units,
compares the two windings in order and is written with a colon, such as 3:1 (3-to-1).
This means in this example, that if there are 3 volts on the primary winding there
will be 1 volt on the secondary winding, 3 volts-to-1 volt. Then we can see that if the
ratio between the number of turns changes the resulting voltages must also change
by the same ratio, and this is true. In other words for a transformer: “turns ratio =
voltage ratio”.
Phase test:
This test is performed during repair of transformer to check the short circuit and
continuity between LT and HT winding of transformer.
In this test we provide 230volt A.C. supply to H.T. winding of transformer. If the
bulb glow dim without any sparking in the winding then our windings are OK,
otherwise there is a short circuit.